Developing Country Studies
ISSN 2224-607X (Paper) ISSN 2225-0565 (Online)
Vol.3, No.12, 2013

www.iiste.org

Management of Government Funded Construction Projects in
Ghana: Stakeholders’ Perspective of Causes of Delays in
Construction of Public Buildings.
Adwoa Difie Ampadu-Asiamah¹ ⃰

Obed Kofi Ampadu-Asiamah²

1. School of Engineering, Accra Polytechnic, PO Box GP 561 Accra, Ghana
2. Barclays Bank Ghana PO Box A N 5487 Accra, Ghana
⃰ E-mail of corresponding author: nana.dife@gmail.com
Abstract
Construction projects funded by the government of Ghana are plagued by time delays. This has resulted in
disruptions to the development plans of the government. This research identifies and assesses the factors that
cause time delays in government funded construction projects by focusing on the activities of stakeholders
(Clients and professionals) in the public sector of the construction industry. Factors identified from literature
review were incorporated into questionnaires to be answered by clients and professionals in the public sector of
the construction industry in Ghana. Responses from 36 stakeholders were analysed to identify causes of time
delays. Results from the analysis suggests that major factors that cause time delays are long bureaucratic process
of honouring certificates, variation orders, cash flow problems, lackadaisical attitudes attitude to decision
making, plant/ equipment efficiency and shortage of liquidity. Based on the factors identified it was deduced that
the client is most of the time responsible for the time delays.
Keywords: Time delays, Government funded, Construction projects, Public sector.

1.

Introduction

One of the principal ways in which modern societies generate new value is through projects which create
physical assets that can then be used to facilitate the achievement of social and economic ends. (Winch, 2002)
The creation of such assets which include schools, hospitals, roads, etc., is most of the time undertaken by
governments to be able to attain targets set towards the improvement of conditions in various sections of their
countries.
The construction industry in every country is responsible for the creation of around half of all the physical assets
which make up about 10% of national wealth. (Winch, 2002)
The success of a project requires that the project is completed on time, within budget and meets the expectations
of stakeholders. (Chatfield and Johnson, 2002)
Project failures are however common and can be attributed to many causes.
According to Armah, (1999), construction is considered unique in Ghana as it is in every country in the world,
because it stimulates the growth of other sectors of the economy and contributes greatly to the overall growth of
gross domestic product.
Construction has been a major part of government’s expenditure since Ghana gained its independence in 1957.
The government spends a lot of money in the provision of infrastructure in various sectors of the country, the
most prominent being roads. The government’s development plan, vision 2020, spells out plans of making
Ghana a middle income country by the year 2020. Provision of infrastructure in the public sectors is prominent
in the government’s plans towards achieving this aim. This is particularly manifest in the education sector where
the government through the Ghana Education Trust Fund (GETFUND) provides funding to improve education
and infrastructure for educational institutions.
Government funded construction projects in Ghana are mostly beset with problems like delay, cost overruns,
lack of funds in the middle of the project implementation and mismanagement of funds at various stages of the
project’s implementation. These, according to Armah (1999), can be attributed to economic difficulties within
Ghana, the nature of the construction industry in Ghana and the manner in which construction projects are
managed. There is however the need to identify causes of these problems in order to reduce or curtail the
reoccurrence. It is in this vein that this research is being conducted on the causes of time delays that occur during
the implementation of construction projects funded by the government in Ghana.
1.1

Time in Construction Projects

Time in construction projects can be regarded as the elapsed period from the inception of a construction project
to the completion and handover of a building to the client. (Choudhury et al. 2004). ‘Time is normally scheduled
149
Developing Country Studies
ISSN 2224-607X (Paper) ISSN 2225-0565 (Online)
Vol.3, No.12, 2013

www.iiste.org

to enable the building to be used by a date determined by the client’s future plans. (Hatush and Skitmore in Chan,
2001)’ Limited time is one constraint of any construction project. It is considered as one of the most important
and in some cases, the most difficult constraint to manage.
The duration of construction projects from inception to completion is assuming great importance in the
construction industry especially among Clients and consumers due to increasing interest rates, inflation and other
commercial pressures, development plan targets, among other factors. They are no longer content merely with
minimal cost and adequate functional performance for their projects. This means that it is in many instances
most cost-effective to complete a project within the shortest possible time.
1.2

Delays in construction projects

A delay as defined by Thefreedictionary.com (2006) is ‘to cause to be later or slower than expected or desired.’
Delays in construction projects are defined by Annan (2003) as extension or prolonging of project time. Delays
also referred to as time overruns have been one of the major and most common problems affecting construction
industries worldwide. They are costly to all parties involved in construction projects and often result in litigation,
increase in cost of construction, abandonment of projects, disruption of development programmes, and
destruction of contractors’ and consultants’ reputations among other things (Annan, 2003). It is therefore
important for each member of the project team to be responsible for devising means to combat delays in the
execution of their assigned responsibilities.
There has been a lot of research on delays in the construction industry; the types of delays, their causes, and
effects. Even though most of the literature reviewed are not directly related to Ghana they are researches
conducted in countries sharing similar characteristics with Ghana.
Preliminary research data conducted on delays in construction projects collected through literature review reveal
that the causes of delays are common to almost all construction industries. The intensity or the gravity of the
causes however differs with each industry.
Aibinu and Odeyinka, (2006) observed that ‘delays in construction projects are caused generally by actions and
inactions of project participants, which cause ripple effects on the roles played by others on the project team.’
The impact of delays on construction projects can be direct or indirect. The direct impact can be measured by
calculating the exact time units of the project operation that has been directly affected. Annan (2003)
The indirect impact is the resulting ripple effect on the whole project a delay. This is usually difficult to measure.
Annan (2003)
It has been pointed out, however, that when delays occur the client stand to lose in terms of disruption of
programmes and sometimes having to spend more on the project than budgeted for. (Lock, 2003)
Such delays affect the reputation of both the consultant in charge and the contractor as well.
For the consultant and contractor, completing the current project and winning the next one is a very important
priority (Winch, 2002) thus having delays in projects can cost them more.
In view of the above, it is therefore important for a project is carefully managed and monitored in order for it to
proceed without unnecessary disruptions.
2.

Methodology

In order to identify the factors that cause delays in government funded construction projects in Ghana, a review
of literature was conducted on construction time and delays. Information from literature review was used to
formulate questionnaires to be answered by stakeholders in the construction industry in Ghana, specifically in
the public sector.
Forty one (41) factors were identified from the literature review as potential causes of delays in construction
industries in many countries.
The aim of the questionnaire was to gather information about the level of occurrence of delays in the public
sector of the construction industry in Ghana, and the factors that lead to their occurrence.
Basically the questions consisted of open and closed questions. They included questions that sought to know the
name, profession, contact number and email address of respondents. They also had questions which sought to
know how rampant delays are in the public sector of the construction industry. There was also the rating of
hypothetical factors (which were put in a likert scale format) that cause delay according to how common they
150
Developing Country Studies
ISSN 2224-607X (Paper) ISSN 2225-0565 (Online)
Vol.3, No.12, 2013

www.iiste.org

occur; thus they rated ‘Very Common’, ‘Common’ to ‘Not Common’. The factors causing delay were
categorized into seven major groups namely contractor related, client related, consultant related, labour/
equipment related, material related, contract related and external factors.
2.1

Distribution of Questionnaire

The questionnaires were distributed to heads of projects divisions of public institutions like public universities,
municipal assemblies, and other firms. Some of the questionnaires were distributed to professionals in the
construction industry. The professionals chosen to answer the questions were architects, quantity surveyors,
project managers, structural engineers and contractors. Sixty six questionaires were distributed among the
professionals and the firms. Thirty six responses were received.
Table1: Questionnaire distribution and response rates
Respondents

Number
distributed

Number returned

Percentage
of
number distributed

Percentage
of
number returned

Clients

10

4

15

11

Architects

15

13

23

36

Contractors

11

7

17

19

Quantity Surveyors

10

5

15

14

Structural Engineers

10

4

15

11

Project Managers

10

3

15

8

Total

66

36

100

55

3.

Analyses and Evaluation of Data

On how rampant delays are in the public sector of the construction industry., it was discovered from the
respondents that they have been or are involved in a total of two hundred and forty nine projects (249); meaning
that each person has been or is involved in an average of seven(7) projects over the past five years. Out of the
249 projects, sixty seven (67) (27%) were/are within the proposed time scheduled, and one hundred and sixty
two (182) (73%) had/ have been delayed. This means that five out of every seven projects have been/ are delayed.
Table 2. below show the breakdown of the number of projects according to stake holders and the difference
between projects finished within time and those that were or are being delayed.
Table 2: Breakdown of number of projects per stakeholders and their status in terms of Time
Status of
Projects

Clients

Architects

Structural
engineers

Quantity
surveyors

Contractors

Project
managers

Total

Over
time

42

33

29

43

23

12

182

Within
time

3

10

6

28

16

4

67

The next section of the questionnaire was to help identify the factors that cause delays in government funded
construction projects in Ghana. In all 41 possible factors were identified from the literature review listed in a
likert scale form with ranking ‘Very Common’, ‘Common’, ‘Not Common’ and ‘Do Not Know’ as the choices to
be made by respondents. ‘Very Common’ means that the factor is recognised as a cause of delay in government
funded construction projects and occur very frequently. ‘Common’ means the factor is recognised and occurs
frequently. ‘Not Common’ means that the factor is recognised but hardly occurs. ‘Do Not Know’ means that
factor is not known to be a cause of delay in government funded construction projects in Ghana. The rankings
were later rated from 1 to four where 1=Very Common, 2= Common, 3=Not Common and 4=Do Not Know.
a. Delay Factors –selection of actors that are “COMMON” based on Majority selection.
151
Developing Country Studies
ISSN 2224-607X (Paper) ISSN 2225-0565 (Online)
Vol.3, No.12, 2013

www.iiste.org

A look through the results revealed that most of the factors are known to respondents to be factors of delay.
Some of the factors were chosen as ‘Not Known’ by a few of the respondents. Factors that are selected as not
known by the respondents are as follows:
Inadequate contractor experience; Improper control of site resource allocation; Complexity of project; Using the
same staff for other projects; Inadequate managerial skills; Shortage of liquidity; Method of construction;
Inadequate flow of information between team members;
Inadequate design team experience;
Inadequate quality assurance and control; Preparation and approval of drawings; Inadequate quality assurance
and control; Preparation and approval of drawings; Low motivation
Shortage in materials; Mistakes and discrepancies in contract documents; Weather Conditions; Problems with
neighbours.
The following factors were identified as ‘Common’ causes of delays in government funded construction projects.
They are listed according to the frequency of occurrence.
Cash flow problems; Long bureaucratic process of honouring certificates; Variation orders; Shortage of liquidity ;
Low motivation; Inadequate managerial skills; Equipment availability and failure ; Long waiting time for
approval of drawings; Improper control of site resource allocation ; Plant/equipment efficiency; Using the same
staff for other projects; Low labour productivity; Poor Site Management; Shortage in materials; Inadequate
contractor experience; Lackadaisical attitude to decision making; Ambiguity in requirement/scope of project;
Poor contract management; Inadequate flow of information between team members; Inadequate skilled labour;
Non-adherence to contract conditions; No proper in house team; Unrealistic proposed contract duration;
Importation of materials; Land ownership disputes.
In all Twenty five (25) factors had majority of the factors saying they are common, with minority saying
otherwise for the same factors. Fifteen (15) of the factors recorded majority of them saying they are not common,
with minority saying otherwise. There was one tie.
3.1

Statistical Analysis

Further analysis of the data was conducted in order to be able to statistically select the factors that are recognised
as frequent causes of delays in government funded construction projects in Ghana, based on the level of
agreement among all the respondents (stakeholders). The statistical measure used was the Kendall’s coefficient
of concordance (Kothari, 2005) a non-parametric statistical method, to investigate the level of agreement
between respondents. (Howell, 2002), (Kothari, 2005), (Vogt, 2005)
Table 3 below shows the ordered ranking of the factors that cause delays based on level of agreement between
respondents.

152
Developing Country Studies
ISSN 2224-607X (Paper) ISSN 2225-0565 (Online)
Vol.3, No.12, 2013

www.iiste.org

Table 3: Ordered Rankings of factors of delay
No. Factors
1
Method of construction
2
Long bureaucratic process of honouring certificates
3
Variation orders
4
Cash flow problems
5
Lackadaisical attitude to decision making
6
Inspection and testing of completed portions of Work
7
Mistakes and discrepancies in contract documents
8
Plant/equipment efficiency
9
Shortage of liquidity
10
Inadequate contractor experience
11
Poor contract management
12
Non-adherence to contract conditions
13
Time used in drawing up contracts
14
Importation of materials
15
Mistakes and discrepancies in design
16
Weather Conditions
17
Regulatory changes and building Codes
18
Problems with neighbours
19
Long waiting time for approval of drawings
20
Low motivation
21
Unforeseen ground conditions
22
Major disputes and negotiations
23
Preparation and approval of drawings
24
Equipment availability and failure
25
Unrealistic proposed contract duration
26
Low labour productivity
27
No proper in house team
28
Inadequate managerial skills
29
Improper control of site resource allocation
30
Poor Site Management
31
Labour supply
32
Inadequate design team experience
33
Undefined organisational structure
34
Ambiguity in requirement/scope of project
35
Shortage in materials
36
Inadequate skilled labour
37
Inadequate flow of information between team members
38
Land ownership disputes
39
Using the same staff for other projects
40
Complexity of project
41
Inadequate quality assurance and control
Factors That Are Agreed On As Common causes of delay.

W
0.84
0.84
0.83
0.78
0.77
0.76
0.74
0.74
0.71
0.68
0.68
0.67
0.65
0.64
0.63
0.63
0.63
0.61
0.61
0.60
0.59
0.58
0.58
0.57
0.56
0.53
0.52
0.50
0.49
0.49
0.48
0.48
0.45
0.43
0.41
0.39
0.37
0.34
0.29
0.27
0.17

Rankings
1
1
2
3
4
5
6
6
7
8
8
9
10
11
12
12
12
13
13
14
15
16
16
17
18
19
20
21
22
22
23
23
24
25
26
27
28
29
30
31
32

From Table 3, it can be seen that 27 out of the 41 factors are agreed upon by all the respondents (stakeholders) as
known to be COMMON factors that cause delay. Out of these factors, the respondents show weak agreement on
eight (8) and agreed or strongly agree on nineteen (19).
3.1.1

Selection of Factors.

The analysis so far has identified two sets of lists of factors of delay. The first list is made up of factors that have
153
Developing Country Studies
ISSN 2224-607X (Paper) ISSN 2225-0565 (Online)
Vol.3, No.12, 2013

www.iiste.org

been selected as ‘Common’ by cumulative effect of individual independent responses. The second list comprises
of the factors that have been selected as ‘Common’ based on agreement among respondents.
In order to identify the factors that cause delays in government funded construction projects, another selection
was made consisting of factors which fell within both categories of ‘Common’ by majority selection, and
‘Common’ by level of agreement among the respondents (stakeholders).
Table 4 below, shows the various factors that are potential causes of delays and their positions within the two
categories. Common = Common by majority selection, Agreed= Common by level of agreement among
respondents. N= No, Y=Yes
Table 4: position of factors that cause delay within the categories of ‘Common’ by majority selection and
‘Common’ by level of agreement
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41

Factors
Method of construction
Long bureaucratic process of honouring certificates
Variation orders
Cash flow problems
Lackadaisical attitude to decision making
Inspection and testing of completed portions of Work
Mistakes and discrepancies in contract documents
Plant/equipment efficiency
Shortage of liquidity
Inadequate contractor experience
Poor contract management
Non-adherence to contract conditions
Time used in drawing up contracts
Importation of materials
Mistakes and discrepancies in design
Weather Conditions
Regulatory changes and building Codes
Problems with neighbours
Long waiting time for approval of drawings
Low motivation
Unforeseen ground conditions
Major disputes and negotiations
Preparation and approval of drawings
Equipment availability and failure
Unrealistic proposed contract duration
Low labour productivity
No proper in house team
Inadequate managerial skills
Improper control of site resource allocation
Poor Site Management
Labour supply
Inadequate design team experience
Undefined organisational structure
Ambiguity in requirement/scope of project
Shortage in materials
Inadequate skilled labour
Inadequate
flow
of
information
Members
Land ownership disputes
Using the same staff for other projects
Complexity of project
Inadequate quality assurance and control

154

between

team

Common
N
Y
Y
Y
Y
N
N
Y
Y
Y
Y
Y
N
Y
Y
N
N
N
Y
Y
N
N
N
Y
Y
Y
Y
Y
Y
Y
N
N
N
Y
Y
Y
N

Agreed
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
N
N
N
N
N
N
N
N
N
N

Y
Y
N
N

N
N
N
N
Developing Country Studies
ISSN 2224-607X (Paper) ISSN 2225-0565 (Online)
Vol.3, No.12, 2013

www.iiste.org

From Table 4 the following was found out:
i.

Delay factors that are ‘Agreed upon as Common’ and ‘Common’

The factors listed below were selected in the two categories as both ‘Common’ and ‘Agreed upon as Common’
and were thus selected as the main ones that cause delays in government funded construction projects in Ghana.
Long bureaucratic process of honouring certificates; Variation orders; Cash flow problems; Lackadaisical
attitude to decision making; Plant/equipment efficiency; Shortage of liquidity; Inadequate contractor experience;
Poor contract management; Non-adherence to contract conditions; Importation of materials; Mistakes and
discrepancies in design; Long waiting time for approval of drawings; Low motivation; Equipment availability
and failure; Unrealistic proposed contract duration; Low labour productivity; No proper in house team.
ii.

Delay factors that are ‘Agreed upon as Common’ but ‘Not Common’

The factors listed below are those which were selected as common by agreement but not selected in the other
category:
Method of construction; Inspection and testing of completed portions of work; Mistakes and discrepancies in
contract documents; Time used in drawing up contracts; Weather Conditions; Regulatory changes and building
Codes; Problems with neighbours; Unforeseen ground conditions; Major disputes and negotiation;Preparation
and approval of drawings.
This means that respondents had experienced one time or the other and therefore agreed on as a cause of delay
on a project. However, they do not represent a common cause in the view of the majority. They are not common
in the sense that they do not often occur, or they are not frequent causes.
iii. Delay factors that are ‘Common’ but ‘Not Agreed upon as Common’
The factors listed below were selected as common by majority selection but not by agreement:
Inadequate managerial skills; Improper control of site resource allocation; Poor Site Management; Ambiguity in
requirement/scope of project; Shortage in materials; Inadequate skilled labour; Land ownership disputes; Using
the same staff for other projects;
This means that they are known to majority of the respondents (not all) as common causes of delay on
construction projects, but respondents generally have divergent view on them. The respondents do not agree that
they cause delay even though they know of it as a factor that is common.
iv. Delay factors that are both ‘Not Common’ and ‘Not Agreed upon as Common’
The factors listed below were selected as common by majority selection but not by agreement:
Labour supply; Inadequate design team experience; Undefined organisational structure; Inadequate flow of
information between team members; Complexity of project; Inadequate quality assurance and control
This means that they are known to majority of the respondents (not all) as common causes of delay on
construction projects, but respondents generally have divergent view on them. The respondents do not agree that
they cause delay even though they know of it as a factor that is common.
Conclusion
In accordance with the aim of this research, 17 factors were identified as causes of time delays in government
funded construction projects in Ghana. The major factors identified were long bureaucratic process of honouring
certificates, variation orders, client’s cash flow problems (which sometimes lead to abandonment of project),
consultants’ lackadaisical attitude to decision making and plant/ equipment efficiency. Other factors identified
are shortage of liquidity, inadequate contractor experience, poor contract management, non-adherence to contract
conditions, importation of materials, mistakes and discrepancies in design, long waiting time for approval of
drawings, low motivation of staff, availability and failure of equipment, unrealistic proposed contract duration,
low labour productivity and finally lack of proper in house team.The first three factors that were identified as
causes of delays fall into the category of client related factors. This means that the most common causes of
delays are the fault of the client.
One of the features of this research is that the perspectives of all the relevant stakeholders in the construction
industry were considered. This certainly had influence on the results. For what the client will see as a common
155
Developing Country Studies
ISSN 2224-607X (Paper) ISSN 2225-0565 (Online)
Vol.3, No.12, 2013

www.iiste.org

factor may not be common to the Architect or the Structural engineer etc. It was in this light that in addition to
selecting the factors that are ‘Common’ by selection of majority, a test of their level of agreement was conducted
in their selection.
Therefore those factors that were not selected by the analysis do not necessarily represent a “rejected list” in the
real sense. They could well be key factors should the research be conducted only with consultants, or only with
clients etc. The selected list represents the stakeholders view.
References
Aibinu, A. A., and Odeyinka, H. A. (2006) Construction delays and their causative factors in Nigeria. Journal of
Construction Engineering and Management. 132, (7), pp 667-677
Annan, E., (2003) Causes of construction delays in Ghana; case study: District Assembly Common funded
projects in Ashanti Region. Kwame Nkrumah University of Science and Technology. (Unpublished)
Armah, E. ( 1999) The changing face of the construction industry in developing countries under International
Monetary Fund(IMF) and World Bank policies. (A study of the Republic of Ghana). University of Greenwich.
(Unpublished)
Chan, A. P. C., (2001) Time-cost relationship of public sector projects in Malaysia. International Journal of
Project
Management.
19,
(4)
pp.
223-229
(online)
assessed
10.01.2007
at
www.ingentaconnect.com/content/els/02637863/2001/00000019/00000004/art00072 Chatfield, C., and Johnson, T., (2002) Step by step Microsoft Project version 2002. Microsoft Press.
Choudhury, I. and Phatak, O. (2004) Correlates of time overrun in commercial construction. American Schools
of Construction Proceedings of the 40th Annual conference. Brigham Young University Provo Utah. (online)
accessed on 03.08.2006 at www. Peresearch.pe.ttu.edu/ASEE/Abstract/ASEE-GSW2004-049.doc
Dictionary.com (2006) ‘Top web results for delay’ (online) accessed on 05.01.2007 at
http://dictionary.reference.com/browse/delay.
Kothari, C. K. (2005). Research Methodology: Methods and Techniques. 2nd Ed. New International Age
Publishers.
Lock, D., (2003) Project Management. Eighth edition. Gower Publishing limited
Winch, G. (2002) Managing construction projects. Blackwell Publishing

156
This academic article was published by The International Institute for Science,
Technology and Education (IISTE). The IISTE is a pioneer in the Open Access
Publishing service based in the U.S. and Europe. The aim of the institute is
Accelerating Global Knowledge Sharing.
More information about the publisher can be found in the IISTE’s homepage:
http://www.iiste.org
CALL FOR JOURNAL PAPERS
The IISTE is currently hosting more than 30 peer-reviewed academic journals and
collaborating with academic institutions around the world. There’s no deadline for
submission. Prospective authors of IISTE journals can find the submission
instruction on the following page: http://www.iiste.org/journals/
The IISTE
editorial team promises to the review and publish all the qualified submissions in a
fast manner. All the journals articles are available online to the readers all over the
world without financial, legal, or technical barriers other than those inseparable from
gaining access to the internet itself. Printed version of the journals is also available
upon request of readers and authors.
MORE RESOURCES
Book publication information: http://www.iiste.org/book/
Recent conferences: http://www.iiste.org/conference/
IISTE Knowledge Sharing Partners
EBSCO, Index Copernicus, Ulrich's Periodicals Directory, JournalTOCS, PKP Open
Archives Harvester, Bielefeld Academic Search Engine, Elektronische
Zeitschriftenbibliothek EZB, Open J-Gate, OCLC WorldCat, Universe Digtial
Library , NewJour, Google Scholar

Más contenido relacionado

La actualidad más candente

Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...IJERA Editor
 
Final paper rizky citra islami
Final paper  rizky citra islamiFinal paper  rizky citra islami
Final paper rizky citra islamiRizky Islami
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...IAEME Publication
 
Prospects of building information modeling (bim) in malaysian construction in...
Prospects of building information modeling (bim) in malaysian construction in...Prospects of building information modeling (bim) in malaysian construction in...
Prospects of building information modeling (bim) in malaysian construction in...Alexander Decker
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET Journal
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...IRJET Journal
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...IRJET Journal
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSIAEME Publication
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Managementijsrd.com
 
FACTORS PROMOTING STAKEHOLDER MANAGEMENT OF BUILDING PROJECTS
FACTORS PROMOTING STAKEHOLDER MANAGEMENT OF BUILDING PROJECTSFACTORS PROMOTING STAKEHOLDER MANAGEMENT OF BUILDING PROJECTS
FACTORS PROMOTING STAKEHOLDER MANAGEMENT OF BUILDING PROJECTSIAEME Publication
 
Causes and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitCauses and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitIJERA Editor
 
IRJET- Impacts of Significant Risk Factors on Forecasted Construction Cash Fl...
IRJET- Impacts of Significant Risk Factors on Forecasted Construction Cash Fl...IRJET- Impacts of Significant Risk Factors on Forecasted Construction Cash Fl...
IRJET- Impacts of Significant Risk Factors on Forecasted Construction Cash Fl...IRJET Journal
 
Causes of Variation Orders 1268
Causes of Variation Orders 1268Causes of Variation Orders 1268
Causes of Variation Orders 1268HASHIM HANIF
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsDr. Amarjeet Singh
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libreUTHM
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodIRJET Journal
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsTwana Ahmad
 

La actualidad más candente (20)

Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
Final paper rizky citra islami
Final paper  rizky citra islamiFinal paper  rizky citra islami
Final paper rizky citra islami
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
 
Prospects of building information modeling (bim) in malaysian construction in...
Prospects of building information modeling (bim) in malaysian construction in...Prospects of building information modeling (bim) in malaysian construction in...
Prospects of building information modeling (bim) in malaysian construction in...
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
FACTORS PROMOTING STAKEHOLDER MANAGEMENT OF BUILDING PROJECTS
FACTORS PROMOTING STAKEHOLDER MANAGEMENT OF BUILDING PROJECTSFACTORS PROMOTING STAKEHOLDER MANAGEMENT OF BUILDING PROJECTS
FACTORS PROMOTING STAKEHOLDER MANAGEMENT OF BUILDING PROJECTS
 
20320140503023
2032014050302320320140503023
20320140503023
 
Causes and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitCauses and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in Kuwait
 
IRJET- Impacts of Significant Risk Factors on Forecasted Construction Cash Fl...
IRJET- Impacts of Significant Risk Factors on Forecasted Construction Cash Fl...IRJET- Impacts of Significant Risk Factors on Forecasted Construction Cash Fl...
IRJET- Impacts of Significant Risk Factors on Forecasted Construction Cash Fl...
 
Causes of Variation Orders 1268
Causes of Variation Orders 1268Causes of Variation Orders 1268
Causes of Variation Orders 1268
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
Risk management
Risk managementRisk management
Risk management
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index Method
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 

Destacado

Expanding residential real estate in ghana and uganda with audio
Expanding residential real estate in ghana and uganda with audioExpanding residential real estate in ghana and uganda with audio
Expanding residential real estate in ghana and uganda with audiodelmount
 
Exploring the challenges and barriers in accessing financial facilities by sm...
Exploring the challenges and barriers in accessing financial facilities by sm...Exploring the challenges and barriers in accessing financial facilities by sm...
Exploring the challenges and barriers in accessing financial facilities by sm...Alexander Decker
 
Business in Africa Pays: The Changing Real Estate Landscape in Ghana - Silk ...
 Business in Africa Pays: The Changing Real Estate Landscape in Ghana - Silk ... Business in Africa Pays: The Changing Real Estate Landscape in Ghana - Silk ...
Business in Africa Pays: The Changing Real Estate Landscape in Ghana - Silk ...BusinessInAfricaPays.com
 
A model for reactivating abandoned public housing projects in ghana
A model for reactivating abandoned public housing projects in ghanaA model for reactivating abandoned public housing projects in ghana
A model for reactivating abandoned public housing projects in ghanaAlexander Decker
 
African real estate outlook
African real estate outlookAfrican real estate outlook
African real estate outlookEmmanuel Obike
 
Assessment of the acceptability of personal guarantees and life assurance pol...
Assessment of the acceptability of personal guarantees and life assurance pol...Assessment of the acceptability of personal guarantees and life assurance pol...
Assessment of the acceptability of personal guarantees and life assurance pol...Alexander Decker
 
DISSERTATION ON THE NATURE, CONSTRAINTS AND IMPLICATIONS OF MORTGAGE REPAYMEN...
DISSERTATION ON THE NATURE, CONSTRAINTS AND IMPLICATIONS OF MORTGAGE REPAYMEN...DISSERTATION ON THE NATURE, CONSTRAINTS AND IMPLICATIONS OF MORTGAGE REPAYMEN...
DISSERTATION ON THE NATURE, CONSTRAINTS AND IMPLICATIONS OF MORTGAGE REPAYMEN...AMPOFO AGYEI JUSTICE
 
11.[1 6]the relationship between employee voice and organizational performanc...
11.[1 6]the relationship between employee voice and organizational performanc...11.[1 6]the relationship between employee voice and organizational performanc...
11.[1 6]the relationship between employee voice and organizational performanc...Alexander Decker
 
Real Estate Leadership Issues 2011 - Henley Business School
Real Estate Leadership Issues 2011 - Henley Business SchoolReal Estate Leadership Issues 2011 - Henley Business School
Real Estate Leadership Issues 2011 - Henley Business SchoolAna Silva O'Reilly
 
Evaluation of the factors influencing time and cost overruns in telecom tower...
Evaluation of the factors influencing time and cost overruns in telecom tower...Evaluation of the factors influencing time and cost overruns in telecom tower...
Evaluation of the factors influencing time and cost overruns in telecom tower...Alexander Decker
 
India real estate research
India real estate researchIndia real estate research
India real estate researchSharad Jhingan
 
1.1 introduction to real estate project management
1.1 introduction to real estate project management1.1 introduction to real estate project management
1.1 introduction to real estate project managementIrefuser1
 
Real estate & Construction Industry Market Research in India
Real estate & Construction Industry Market Research in IndiaReal estate & Construction Industry Market Research in India
Real estate & Construction Industry Market Research in IndiaRumanshu Katiyar
 
introduction to commercial real estate development
introduction to commercial real estate developmentintroduction to commercial real estate development
introduction to commercial real estate developmentPMILebanonChapter
 
State of the Word 2011
State of the Word 2011State of the Word 2011
State of the Word 2011photomatt
 

Destacado (16)

Expanding residential real estate in ghana and uganda with audio
Expanding residential real estate in ghana and uganda with audioExpanding residential real estate in ghana and uganda with audio
Expanding residential real estate in ghana and uganda with audio
 
Exploring the challenges and barriers in accessing financial facilities by sm...
Exploring the challenges and barriers in accessing financial facilities by sm...Exploring the challenges and barriers in accessing financial facilities by sm...
Exploring the challenges and barriers in accessing financial facilities by sm...
 
PRISCILLA OSEI ASIBEY - CITI
PRISCILLA OSEI ASIBEY - CITIPRISCILLA OSEI ASIBEY - CITI
PRISCILLA OSEI ASIBEY - CITI
 
Business in Africa Pays: The Changing Real Estate Landscape in Ghana - Silk ...
 Business in Africa Pays: The Changing Real Estate Landscape in Ghana - Silk ... Business in Africa Pays: The Changing Real Estate Landscape in Ghana - Silk ...
Business in Africa Pays: The Changing Real Estate Landscape in Ghana - Silk ...
 
A model for reactivating abandoned public housing projects in ghana
A model for reactivating abandoned public housing projects in ghanaA model for reactivating abandoned public housing projects in ghana
A model for reactivating abandoned public housing projects in ghana
 
African real estate outlook
African real estate outlookAfrican real estate outlook
African real estate outlook
 
Assessment of the acceptability of personal guarantees and life assurance pol...
Assessment of the acceptability of personal guarantees and life assurance pol...Assessment of the acceptability of personal guarantees and life assurance pol...
Assessment of the acceptability of personal guarantees and life assurance pol...
 
DISSERTATION ON THE NATURE, CONSTRAINTS AND IMPLICATIONS OF MORTGAGE REPAYMEN...
DISSERTATION ON THE NATURE, CONSTRAINTS AND IMPLICATIONS OF MORTGAGE REPAYMEN...DISSERTATION ON THE NATURE, CONSTRAINTS AND IMPLICATIONS OF MORTGAGE REPAYMEN...
DISSERTATION ON THE NATURE, CONSTRAINTS AND IMPLICATIONS OF MORTGAGE REPAYMEN...
 
11.[1 6]the relationship between employee voice and organizational performanc...
11.[1 6]the relationship between employee voice and organizational performanc...11.[1 6]the relationship between employee voice and organizational performanc...
11.[1 6]the relationship between employee voice and organizational performanc...
 
Real Estate Leadership Issues 2011 - Henley Business School
Real Estate Leadership Issues 2011 - Henley Business SchoolReal Estate Leadership Issues 2011 - Henley Business School
Real Estate Leadership Issues 2011 - Henley Business School
 
Evaluation of the factors influencing time and cost overruns in telecom tower...
Evaluation of the factors influencing time and cost overruns in telecom tower...Evaluation of the factors influencing time and cost overruns in telecom tower...
Evaluation of the factors influencing time and cost overruns in telecom tower...
 
India real estate research
India real estate researchIndia real estate research
India real estate research
 
1.1 introduction to real estate project management
1.1 introduction to real estate project management1.1 introduction to real estate project management
1.1 introduction to real estate project management
 
Real estate & Construction Industry Market Research in India
Real estate & Construction Industry Market Research in IndiaReal estate & Construction Industry Market Research in India
Real estate & Construction Industry Market Research in India
 
introduction to commercial real estate development
introduction to commercial real estate developmentintroduction to commercial real estate development
introduction to commercial real estate development
 
State of the Word 2011
State of the Word 2011State of the Word 2011
State of the Word 2011
 

Similar a Management of government funded construction projects in ghana

Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Associate Professor in VSB Coimbatore
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET Journal
 
10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docxEbrahimJemal4
 
PAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxPAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxsaeedahmed433704
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...iosrjce
 
IRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction ProjectsIRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction ProjectsIRJET Journal
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...
Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...
Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...Adeoye Charles
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewIRJET Journal
 
Factors Affecting Cost Escalation in Construction Projects in Gaza Strip
Factors Affecting Cost Escalation in Construction Projects in Gaza StripFactors Affecting Cost Escalation in Construction Projects in Gaza Strip
Factors Affecting Cost Escalation in Construction Projects in Gaza StripDr. Amarjeet Singh
 
To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...Harish Rajmane
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delayEst
 
Literature Review - Final
Literature Review - FinalLiterature Review - Final
Literature Review - FinalRifan Fhazi
 
Effective Project Preparation Process: A Key Factor to a Successful PPP Infra...
Effective Project Preparation Process: A Key Factor to a Successful PPP Infra...Effective Project Preparation Process: A Key Factor to a Successful PPP Infra...
Effective Project Preparation Process: A Key Factor to a Successful PPP Infra...inventionjournals
 
Building information-modeling-and-construction-projects-performance-the-effec...
Building information-modeling-and-construction-projects-performance-the-effec...Building information-modeling-and-construction-projects-performance-the-effec...
Building information-modeling-and-construction-projects-performance-the-effec...oircjournals
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET Journal
 
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...IRJET Journal
 

Similar a Management of government funded construction projects in ghana (20)

Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
 
10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx
 
PAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxPAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptx
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
IRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction ProjectsIRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction Projects
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...
Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...
Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
Factors Affecting Cost Escalation in Construction Projects in Gaza Strip
Factors Affecting Cost Escalation in Construction Projects in Gaza StripFactors Affecting Cost Escalation in Construction Projects in Gaza Strip
Factors Affecting Cost Escalation in Construction Projects in Gaza Strip
 
To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delay
 
Literature Review - Final
Literature Review - FinalLiterature Review - Final
Literature Review - Final
 
Ijciet 08 02_005
Ijciet 08 02_005Ijciet 08 02_005
Ijciet 08 02_005
 
Effective Project Preparation Process: A Key Factor to a Successful PPP Infra...
Effective Project Preparation Process: A Key Factor to a Successful PPP Infra...Effective Project Preparation Process: A Key Factor to a Successful PPP Infra...
Effective Project Preparation Process: A Key Factor to a Successful PPP Infra...
 
Building information-modeling-and-construction-projects-performance-the-effec...
Building information-modeling-and-construction-projects-performance-the-effec...Building information-modeling-and-construction-projects-performance-the-effec...
Building information-modeling-and-construction-projects-performance-the-effec...
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
 

Más de Alexander Decker

Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Alexander Decker
 
A validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inA validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inAlexander Decker
 
A usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesA usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesAlexander Decker
 
A universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksA universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksAlexander Decker
 
A unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dA unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dAlexander Decker
 
A trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceA trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceAlexander Decker
 
A transformational generative approach towards understanding al-istifham
A transformational  generative approach towards understanding al-istifhamA transformational  generative approach towards understanding al-istifham
A transformational generative approach towards understanding al-istifhamAlexander Decker
 
A time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaA time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaAlexander Decker
 
A therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenA therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenAlexander Decker
 
A theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksA theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksAlexander Decker
 
A systematic evaluation of link budget for
A systematic evaluation of link budget forA systematic evaluation of link budget for
A systematic evaluation of link budget forAlexander Decker
 
A synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabA synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabAlexander Decker
 
A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...Alexander Decker
 
A survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalA survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalAlexander Decker
 
A survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesA survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesAlexander Decker
 
A survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbA survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbAlexander Decker
 
A survey on challenges to the media cloud
A survey on challenges to the media cloudA survey on challenges to the media cloud
A survey on challenges to the media cloudAlexander Decker
 
A survey of provenance leveraged
A survey of provenance leveragedA survey of provenance leveraged
A survey of provenance leveragedAlexander Decker
 
A survey of private equity investments in kenya
A survey of private equity investments in kenyaA survey of private equity investments in kenya
A survey of private equity investments in kenyaAlexander Decker
 
A study to measures the financial health of
A study to measures the financial health ofA study to measures the financial health of
A study to measures the financial health ofAlexander Decker
 

Más de Alexander Decker (20)

Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...
 
A validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inA validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale in
 
A usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesA usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websites
 
A universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksA universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banks
 
A unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dA unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized d
 
A trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceA trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistance
 
A transformational generative approach towards understanding al-istifham
A transformational  generative approach towards understanding al-istifhamA transformational  generative approach towards understanding al-istifham
A transformational generative approach towards understanding al-istifham
 
A time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaA time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibia
 
A therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenA therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school children
 
A theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksA theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banks
 
A systematic evaluation of link budget for
A systematic evaluation of link budget forA systematic evaluation of link budget for
A systematic evaluation of link budget for
 
A synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabA synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjab
 
A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...
 
A survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalA survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incremental
 
A survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesA survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniques
 
A survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbA survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo db
 
A survey on challenges to the media cloud
A survey on challenges to the media cloudA survey on challenges to the media cloud
A survey on challenges to the media cloud
 
A survey of provenance leveraged
A survey of provenance leveragedA survey of provenance leveraged
A survey of provenance leveraged
 
A survey of private equity investments in kenya
A survey of private equity investments in kenyaA survey of private equity investments in kenya
A survey of private equity investments in kenya
 
A study to measures the financial health of
A study to measures the financial health ofA study to measures the financial health of
A study to measures the financial health of
 

Último

8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadAyesha Khan
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionMintel Group
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncrdollysharma2066
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 

Último (20)

8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted Version
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 

Management of government funded construction projects in ghana

  • 1. Developing Country Studies ISSN 2224-607X (Paper) ISSN 2225-0565 (Online) Vol.3, No.12, 2013 www.iiste.org Management of Government Funded Construction Projects in Ghana: Stakeholders’ Perspective of Causes of Delays in Construction of Public Buildings. Adwoa Difie Ampadu-Asiamah¹ ⃰ Obed Kofi Ampadu-Asiamah² 1. School of Engineering, Accra Polytechnic, PO Box GP 561 Accra, Ghana 2. Barclays Bank Ghana PO Box A N 5487 Accra, Ghana ⃰ E-mail of corresponding author: nana.dife@gmail.com Abstract Construction projects funded by the government of Ghana are plagued by time delays. This has resulted in disruptions to the development plans of the government. This research identifies and assesses the factors that cause time delays in government funded construction projects by focusing on the activities of stakeholders (Clients and professionals) in the public sector of the construction industry. Factors identified from literature review were incorporated into questionnaires to be answered by clients and professionals in the public sector of the construction industry in Ghana. Responses from 36 stakeholders were analysed to identify causes of time delays. Results from the analysis suggests that major factors that cause time delays are long bureaucratic process of honouring certificates, variation orders, cash flow problems, lackadaisical attitudes attitude to decision making, plant/ equipment efficiency and shortage of liquidity. Based on the factors identified it was deduced that the client is most of the time responsible for the time delays. Keywords: Time delays, Government funded, Construction projects, Public sector. 1. Introduction One of the principal ways in which modern societies generate new value is through projects which create physical assets that can then be used to facilitate the achievement of social and economic ends. (Winch, 2002) The creation of such assets which include schools, hospitals, roads, etc., is most of the time undertaken by governments to be able to attain targets set towards the improvement of conditions in various sections of their countries. The construction industry in every country is responsible for the creation of around half of all the physical assets which make up about 10% of national wealth. (Winch, 2002) The success of a project requires that the project is completed on time, within budget and meets the expectations of stakeholders. (Chatfield and Johnson, 2002) Project failures are however common and can be attributed to many causes. According to Armah, (1999), construction is considered unique in Ghana as it is in every country in the world, because it stimulates the growth of other sectors of the economy and contributes greatly to the overall growth of gross domestic product. Construction has been a major part of government’s expenditure since Ghana gained its independence in 1957. The government spends a lot of money in the provision of infrastructure in various sectors of the country, the most prominent being roads. The government’s development plan, vision 2020, spells out plans of making Ghana a middle income country by the year 2020. Provision of infrastructure in the public sectors is prominent in the government’s plans towards achieving this aim. This is particularly manifest in the education sector where the government through the Ghana Education Trust Fund (GETFUND) provides funding to improve education and infrastructure for educational institutions. Government funded construction projects in Ghana are mostly beset with problems like delay, cost overruns, lack of funds in the middle of the project implementation and mismanagement of funds at various stages of the project’s implementation. These, according to Armah (1999), can be attributed to economic difficulties within Ghana, the nature of the construction industry in Ghana and the manner in which construction projects are managed. There is however the need to identify causes of these problems in order to reduce or curtail the reoccurrence. It is in this vein that this research is being conducted on the causes of time delays that occur during the implementation of construction projects funded by the government in Ghana. 1.1 Time in Construction Projects Time in construction projects can be regarded as the elapsed period from the inception of a construction project to the completion and handover of a building to the client. (Choudhury et al. 2004). ‘Time is normally scheduled 149
  • 2. Developing Country Studies ISSN 2224-607X (Paper) ISSN 2225-0565 (Online) Vol.3, No.12, 2013 www.iiste.org to enable the building to be used by a date determined by the client’s future plans. (Hatush and Skitmore in Chan, 2001)’ Limited time is one constraint of any construction project. It is considered as one of the most important and in some cases, the most difficult constraint to manage. The duration of construction projects from inception to completion is assuming great importance in the construction industry especially among Clients and consumers due to increasing interest rates, inflation and other commercial pressures, development plan targets, among other factors. They are no longer content merely with minimal cost and adequate functional performance for their projects. This means that it is in many instances most cost-effective to complete a project within the shortest possible time. 1.2 Delays in construction projects A delay as defined by Thefreedictionary.com (2006) is ‘to cause to be later or slower than expected or desired.’ Delays in construction projects are defined by Annan (2003) as extension or prolonging of project time. Delays also referred to as time overruns have been one of the major and most common problems affecting construction industries worldwide. They are costly to all parties involved in construction projects and often result in litigation, increase in cost of construction, abandonment of projects, disruption of development programmes, and destruction of contractors’ and consultants’ reputations among other things (Annan, 2003). It is therefore important for each member of the project team to be responsible for devising means to combat delays in the execution of their assigned responsibilities. There has been a lot of research on delays in the construction industry; the types of delays, their causes, and effects. Even though most of the literature reviewed are not directly related to Ghana they are researches conducted in countries sharing similar characteristics with Ghana. Preliminary research data conducted on delays in construction projects collected through literature review reveal that the causes of delays are common to almost all construction industries. The intensity or the gravity of the causes however differs with each industry. Aibinu and Odeyinka, (2006) observed that ‘delays in construction projects are caused generally by actions and inactions of project participants, which cause ripple effects on the roles played by others on the project team.’ The impact of delays on construction projects can be direct or indirect. The direct impact can be measured by calculating the exact time units of the project operation that has been directly affected. Annan (2003) The indirect impact is the resulting ripple effect on the whole project a delay. This is usually difficult to measure. Annan (2003) It has been pointed out, however, that when delays occur the client stand to lose in terms of disruption of programmes and sometimes having to spend more on the project than budgeted for. (Lock, 2003) Such delays affect the reputation of both the consultant in charge and the contractor as well. For the consultant and contractor, completing the current project and winning the next one is a very important priority (Winch, 2002) thus having delays in projects can cost them more. In view of the above, it is therefore important for a project is carefully managed and monitored in order for it to proceed without unnecessary disruptions. 2. Methodology In order to identify the factors that cause delays in government funded construction projects in Ghana, a review of literature was conducted on construction time and delays. Information from literature review was used to formulate questionnaires to be answered by stakeholders in the construction industry in Ghana, specifically in the public sector. Forty one (41) factors were identified from the literature review as potential causes of delays in construction industries in many countries. The aim of the questionnaire was to gather information about the level of occurrence of delays in the public sector of the construction industry in Ghana, and the factors that lead to their occurrence. Basically the questions consisted of open and closed questions. They included questions that sought to know the name, profession, contact number and email address of respondents. They also had questions which sought to know how rampant delays are in the public sector of the construction industry. There was also the rating of hypothetical factors (which were put in a likert scale format) that cause delay according to how common they 150
  • 3. Developing Country Studies ISSN 2224-607X (Paper) ISSN 2225-0565 (Online) Vol.3, No.12, 2013 www.iiste.org occur; thus they rated ‘Very Common’, ‘Common’ to ‘Not Common’. The factors causing delay were categorized into seven major groups namely contractor related, client related, consultant related, labour/ equipment related, material related, contract related and external factors. 2.1 Distribution of Questionnaire The questionnaires were distributed to heads of projects divisions of public institutions like public universities, municipal assemblies, and other firms. Some of the questionnaires were distributed to professionals in the construction industry. The professionals chosen to answer the questions were architects, quantity surveyors, project managers, structural engineers and contractors. Sixty six questionaires were distributed among the professionals and the firms. Thirty six responses were received. Table1: Questionnaire distribution and response rates Respondents Number distributed Number returned Percentage of number distributed Percentage of number returned Clients 10 4 15 11 Architects 15 13 23 36 Contractors 11 7 17 19 Quantity Surveyors 10 5 15 14 Structural Engineers 10 4 15 11 Project Managers 10 3 15 8 Total 66 36 100 55 3. Analyses and Evaluation of Data On how rampant delays are in the public sector of the construction industry., it was discovered from the respondents that they have been or are involved in a total of two hundred and forty nine projects (249); meaning that each person has been or is involved in an average of seven(7) projects over the past five years. Out of the 249 projects, sixty seven (67) (27%) were/are within the proposed time scheduled, and one hundred and sixty two (182) (73%) had/ have been delayed. This means that five out of every seven projects have been/ are delayed. Table 2. below show the breakdown of the number of projects according to stake holders and the difference between projects finished within time and those that were or are being delayed. Table 2: Breakdown of number of projects per stakeholders and their status in terms of Time Status of Projects Clients Architects Structural engineers Quantity surveyors Contractors Project managers Total Over time 42 33 29 43 23 12 182 Within time 3 10 6 28 16 4 67 The next section of the questionnaire was to help identify the factors that cause delays in government funded construction projects in Ghana. In all 41 possible factors were identified from the literature review listed in a likert scale form with ranking ‘Very Common’, ‘Common’, ‘Not Common’ and ‘Do Not Know’ as the choices to be made by respondents. ‘Very Common’ means that the factor is recognised as a cause of delay in government funded construction projects and occur very frequently. ‘Common’ means the factor is recognised and occurs frequently. ‘Not Common’ means that the factor is recognised but hardly occurs. ‘Do Not Know’ means that factor is not known to be a cause of delay in government funded construction projects in Ghana. The rankings were later rated from 1 to four where 1=Very Common, 2= Common, 3=Not Common and 4=Do Not Know. a. Delay Factors –selection of actors that are “COMMON” based on Majority selection. 151
  • 4. Developing Country Studies ISSN 2224-607X (Paper) ISSN 2225-0565 (Online) Vol.3, No.12, 2013 www.iiste.org A look through the results revealed that most of the factors are known to respondents to be factors of delay. Some of the factors were chosen as ‘Not Known’ by a few of the respondents. Factors that are selected as not known by the respondents are as follows: Inadequate contractor experience; Improper control of site resource allocation; Complexity of project; Using the same staff for other projects; Inadequate managerial skills; Shortage of liquidity; Method of construction; Inadequate flow of information between team members; Inadequate design team experience; Inadequate quality assurance and control; Preparation and approval of drawings; Inadequate quality assurance and control; Preparation and approval of drawings; Low motivation Shortage in materials; Mistakes and discrepancies in contract documents; Weather Conditions; Problems with neighbours. The following factors were identified as ‘Common’ causes of delays in government funded construction projects. They are listed according to the frequency of occurrence. Cash flow problems; Long bureaucratic process of honouring certificates; Variation orders; Shortage of liquidity ; Low motivation; Inadequate managerial skills; Equipment availability and failure ; Long waiting time for approval of drawings; Improper control of site resource allocation ; Plant/equipment efficiency; Using the same staff for other projects; Low labour productivity; Poor Site Management; Shortage in materials; Inadequate contractor experience; Lackadaisical attitude to decision making; Ambiguity in requirement/scope of project; Poor contract management; Inadequate flow of information between team members; Inadequate skilled labour; Non-adherence to contract conditions; No proper in house team; Unrealistic proposed contract duration; Importation of materials; Land ownership disputes. In all Twenty five (25) factors had majority of the factors saying they are common, with minority saying otherwise for the same factors. Fifteen (15) of the factors recorded majority of them saying they are not common, with minority saying otherwise. There was one tie. 3.1 Statistical Analysis Further analysis of the data was conducted in order to be able to statistically select the factors that are recognised as frequent causes of delays in government funded construction projects in Ghana, based on the level of agreement among all the respondents (stakeholders). The statistical measure used was the Kendall’s coefficient of concordance (Kothari, 2005) a non-parametric statistical method, to investigate the level of agreement between respondents. (Howell, 2002), (Kothari, 2005), (Vogt, 2005) Table 3 below shows the ordered ranking of the factors that cause delays based on level of agreement between respondents. 152
  • 5. Developing Country Studies ISSN 2224-607X (Paper) ISSN 2225-0565 (Online) Vol.3, No.12, 2013 www.iiste.org Table 3: Ordered Rankings of factors of delay No. Factors 1 Method of construction 2 Long bureaucratic process of honouring certificates 3 Variation orders 4 Cash flow problems 5 Lackadaisical attitude to decision making 6 Inspection and testing of completed portions of Work 7 Mistakes and discrepancies in contract documents 8 Plant/equipment efficiency 9 Shortage of liquidity 10 Inadequate contractor experience 11 Poor contract management 12 Non-adherence to contract conditions 13 Time used in drawing up contracts 14 Importation of materials 15 Mistakes and discrepancies in design 16 Weather Conditions 17 Regulatory changes and building Codes 18 Problems with neighbours 19 Long waiting time for approval of drawings 20 Low motivation 21 Unforeseen ground conditions 22 Major disputes and negotiations 23 Preparation and approval of drawings 24 Equipment availability and failure 25 Unrealistic proposed contract duration 26 Low labour productivity 27 No proper in house team 28 Inadequate managerial skills 29 Improper control of site resource allocation 30 Poor Site Management 31 Labour supply 32 Inadequate design team experience 33 Undefined organisational structure 34 Ambiguity in requirement/scope of project 35 Shortage in materials 36 Inadequate skilled labour 37 Inadequate flow of information between team members 38 Land ownership disputes 39 Using the same staff for other projects 40 Complexity of project 41 Inadequate quality assurance and control Factors That Are Agreed On As Common causes of delay. W 0.84 0.84 0.83 0.78 0.77 0.76 0.74 0.74 0.71 0.68 0.68 0.67 0.65 0.64 0.63 0.63 0.63 0.61 0.61 0.60 0.59 0.58 0.58 0.57 0.56 0.53 0.52 0.50 0.49 0.49 0.48 0.48 0.45 0.43 0.41 0.39 0.37 0.34 0.29 0.27 0.17 Rankings 1 1 2 3 4 5 6 6 7 8 8 9 10 11 12 12 12 13 13 14 15 16 16 17 18 19 20 21 22 22 23 23 24 25 26 27 28 29 30 31 32 From Table 3, it can be seen that 27 out of the 41 factors are agreed upon by all the respondents (stakeholders) as known to be COMMON factors that cause delay. Out of these factors, the respondents show weak agreement on eight (8) and agreed or strongly agree on nineteen (19). 3.1.1 Selection of Factors. The analysis so far has identified two sets of lists of factors of delay. The first list is made up of factors that have 153
  • 6. Developing Country Studies ISSN 2224-607X (Paper) ISSN 2225-0565 (Online) Vol.3, No.12, 2013 www.iiste.org been selected as ‘Common’ by cumulative effect of individual independent responses. The second list comprises of the factors that have been selected as ‘Common’ based on agreement among respondents. In order to identify the factors that cause delays in government funded construction projects, another selection was made consisting of factors which fell within both categories of ‘Common’ by majority selection, and ‘Common’ by level of agreement among the respondents (stakeholders). Table 4 below, shows the various factors that are potential causes of delays and their positions within the two categories. Common = Common by majority selection, Agreed= Common by level of agreement among respondents. N= No, Y=Yes Table 4: position of factors that cause delay within the categories of ‘Common’ by majority selection and ‘Common’ by level of agreement No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 Factors Method of construction Long bureaucratic process of honouring certificates Variation orders Cash flow problems Lackadaisical attitude to decision making Inspection and testing of completed portions of Work Mistakes and discrepancies in contract documents Plant/equipment efficiency Shortage of liquidity Inadequate contractor experience Poor contract management Non-adherence to contract conditions Time used in drawing up contracts Importation of materials Mistakes and discrepancies in design Weather Conditions Regulatory changes and building Codes Problems with neighbours Long waiting time for approval of drawings Low motivation Unforeseen ground conditions Major disputes and negotiations Preparation and approval of drawings Equipment availability and failure Unrealistic proposed contract duration Low labour productivity No proper in house team Inadequate managerial skills Improper control of site resource allocation Poor Site Management Labour supply Inadequate design team experience Undefined organisational structure Ambiguity in requirement/scope of project Shortage in materials Inadequate skilled labour Inadequate flow of information Members Land ownership disputes Using the same staff for other projects Complexity of project Inadequate quality assurance and control 154 between team Common N Y Y Y Y N N Y Y Y Y Y N Y Y N N N Y Y N N N Y Y Y Y Y Y Y N N N Y Y Y N Agreed Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y N N N N N N N N N N Y Y N N N N N N
  • 7. Developing Country Studies ISSN 2224-607X (Paper) ISSN 2225-0565 (Online) Vol.3, No.12, 2013 www.iiste.org From Table 4 the following was found out: i. Delay factors that are ‘Agreed upon as Common’ and ‘Common’ The factors listed below were selected in the two categories as both ‘Common’ and ‘Agreed upon as Common’ and were thus selected as the main ones that cause delays in government funded construction projects in Ghana. Long bureaucratic process of honouring certificates; Variation orders; Cash flow problems; Lackadaisical attitude to decision making; Plant/equipment efficiency; Shortage of liquidity; Inadequate contractor experience; Poor contract management; Non-adherence to contract conditions; Importation of materials; Mistakes and discrepancies in design; Long waiting time for approval of drawings; Low motivation; Equipment availability and failure; Unrealistic proposed contract duration; Low labour productivity; No proper in house team. ii. Delay factors that are ‘Agreed upon as Common’ but ‘Not Common’ The factors listed below are those which were selected as common by agreement but not selected in the other category: Method of construction; Inspection and testing of completed portions of work; Mistakes and discrepancies in contract documents; Time used in drawing up contracts; Weather Conditions; Regulatory changes and building Codes; Problems with neighbours; Unforeseen ground conditions; Major disputes and negotiation;Preparation and approval of drawings. This means that respondents had experienced one time or the other and therefore agreed on as a cause of delay on a project. However, they do not represent a common cause in the view of the majority. They are not common in the sense that they do not often occur, or they are not frequent causes. iii. Delay factors that are ‘Common’ but ‘Not Agreed upon as Common’ The factors listed below were selected as common by majority selection but not by agreement: Inadequate managerial skills; Improper control of site resource allocation; Poor Site Management; Ambiguity in requirement/scope of project; Shortage in materials; Inadequate skilled labour; Land ownership disputes; Using the same staff for other projects; This means that they are known to majority of the respondents (not all) as common causes of delay on construction projects, but respondents generally have divergent view on them. The respondents do not agree that they cause delay even though they know of it as a factor that is common. iv. Delay factors that are both ‘Not Common’ and ‘Not Agreed upon as Common’ The factors listed below were selected as common by majority selection but not by agreement: Labour supply; Inadequate design team experience; Undefined organisational structure; Inadequate flow of information between team members; Complexity of project; Inadequate quality assurance and control This means that they are known to majority of the respondents (not all) as common causes of delay on construction projects, but respondents generally have divergent view on them. The respondents do not agree that they cause delay even though they know of it as a factor that is common. Conclusion In accordance with the aim of this research, 17 factors were identified as causes of time delays in government funded construction projects in Ghana. The major factors identified were long bureaucratic process of honouring certificates, variation orders, client’s cash flow problems (which sometimes lead to abandonment of project), consultants’ lackadaisical attitude to decision making and plant/ equipment efficiency. Other factors identified are shortage of liquidity, inadequate contractor experience, poor contract management, non-adherence to contract conditions, importation of materials, mistakes and discrepancies in design, long waiting time for approval of drawings, low motivation of staff, availability and failure of equipment, unrealistic proposed contract duration, low labour productivity and finally lack of proper in house team.The first three factors that were identified as causes of delays fall into the category of client related factors. This means that the most common causes of delays are the fault of the client. One of the features of this research is that the perspectives of all the relevant stakeholders in the construction industry were considered. This certainly had influence on the results. For what the client will see as a common 155
  • 8. Developing Country Studies ISSN 2224-607X (Paper) ISSN 2225-0565 (Online) Vol.3, No.12, 2013 www.iiste.org factor may not be common to the Architect or the Structural engineer etc. It was in this light that in addition to selecting the factors that are ‘Common’ by selection of majority, a test of their level of agreement was conducted in their selection. Therefore those factors that were not selected by the analysis do not necessarily represent a “rejected list” in the real sense. They could well be key factors should the research be conducted only with consultants, or only with clients etc. The selected list represents the stakeholders view. References Aibinu, A. A., and Odeyinka, H. A. (2006) Construction delays and their causative factors in Nigeria. Journal of Construction Engineering and Management. 132, (7), pp 667-677 Annan, E., (2003) Causes of construction delays in Ghana; case study: District Assembly Common funded projects in Ashanti Region. Kwame Nkrumah University of Science and Technology. (Unpublished) Armah, E. ( 1999) The changing face of the construction industry in developing countries under International Monetary Fund(IMF) and World Bank policies. (A study of the Republic of Ghana). University of Greenwich. (Unpublished) Chan, A. P. C., (2001) Time-cost relationship of public sector projects in Malaysia. International Journal of Project Management. 19, (4) pp. 223-229 (online) assessed 10.01.2007 at www.ingentaconnect.com/content/els/02637863/2001/00000019/00000004/art00072 Chatfield, C., and Johnson, T., (2002) Step by step Microsoft Project version 2002. Microsoft Press. Choudhury, I. and Phatak, O. (2004) Correlates of time overrun in commercial construction. American Schools of Construction Proceedings of the 40th Annual conference. Brigham Young University Provo Utah. (online) accessed on 03.08.2006 at www. Peresearch.pe.ttu.edu/ASEE/Abstract/ASEE-GSW2004-049.doc Dictionary.com (2006) ‘Top web results for delay’ (online) accessed on 05.01.2007 at http://dictionary.reference.com/browse/delay. Kothari, C. K. (2005). Research Methodology: Methods and Techniques. 2nd Ed. New International Age Publishers. Lock, D., (2003) Project Management. Eighth edition. Gower Publishing limited Winch, G. (2002) Managing construction projects. Blackwell Publishing 156
  • 9. This academic article was published by The International Institute for Science, Technology and Education (IISTE). The IISTE is a pioneer in the Open Access Publishing service based in the U.S. and Europe. The aim of the institute is Accelerating Global Knowledge Sharing. More information about the publisher can be found in the IISTE’s homepage: http://www.iiste.org CALL FOR JOURNAL PAPERS The IISTE is currently hosting more than 30 peer-reviewed academic journals and collaborating with academic institutions around the world. There’s no deadline for submission. Prospective authors of IISTE journals can find the submission instruction on the following page: http://www.iiste.org/journals/ The IISTE editorial team promises to the review and publish all the qualified submissions in a fast manner. All the journals articles are available online to the readers all over the world without financial, legal, or technical barriers other than those inseparable from gaining access to the internet itself. Printed version of the journals is also available upon request of readers and authors. MORE RESOURCES Book publication information: http://www.iiste.org/book/ Recent conferences: http://www.iiste.org/conference/ IISTE Knowledge Sharing Partners EBSCO, Index Copernicus, Ulrich's Periodicals Directory, JournalTOCS, PKP Open Archives Harvester, Bielefeld Academic Search Engine, Elektronische Zeitschriftenbibliothek EZB, Open J-Gate, OCLC WorldCat, Universe Digtial Library , NewJour, Google Scholar