1. ID Task Name Duration Start Finish PredecesResource Names Notes
1 Carolinas Core Lab Implementation
Project ‐ Beckman Coulter Schedule
5040 Airport Center Parkway
Charlotte, NC
2
3
4 Pre‐Installation Activities 1 day? Mon 10/6/14 Mon 10/6/14
12
13
14 REMISOL and IT
15 Remisol Middleware System 127 days? Mon 10/6/14 Fri 3/27/15
16 Customer Acceptance of support docs 1 day? Mon 10/6/14 Mon 10/6/14
17 Bomgar Ann Sheehe,Chris Gray
18 ProService Ann Sheehe,Chris Gray
19 Networking review and discussions Ann Sheehe,Chris Gray
20 Hardware review Ann Sheehe,Chris Gray
21 Hardware Delivery 35 days Mon 11/3/14 Fri 12/19/14
22 Inventory check (servers only) 1 day Mon 11/3/14 Mon 11/3/14 Alvera Stevens,Bin Kallan Need Dongle IDs
23 Centralized Server PMFs 4 days Tue 11/4/14 Fri 11/7/14 22 Toby Reimers
24 Hardware Installation 5 days Mon 12/15/14 Fri 12/19/14 22 Paul Reischmann
25 C.O.N. Ready 0 days Tue 12/16/14 Tue 12/16/14 Paul Reischmann
26 Applications Testing through GoLive 40 days Mon 2/2/15 Wed 3/25/15 Steve Johnson,Cindy Friedman GoLive and Post‐GoLive
27 Command Central Install and Test 30 days Mon 2/2/15 Fri 3/13/15 Steve Johnson,Cindy Friedman
28 New Analyzers and Equipment Testing 30 days Mon 2/2/15 Fri 3/13/15
29 AU5822 (x2) 30 days Mon 2/2/15 Fri 3/13/15 Steve Johnson,Cindy Friedman work with instrument Apps to test
30 DxI800 (x2) 30 days Mon 2/2/15 Fri 3/13/15 Steve Johnson,Cindy Friedman work with instrument Apps to test
31 DxH (new analyzer) 30 days Mon 2/2/15 Fri 3/13/15 Steve Johnson,Cindy Friedman work with instrument Apps to test
32 Cennexus Track Computer 30 days Mon 2/2/15 Fri 3/13/15 Steve Johnson,Cindy Friedman work with instrument Apps to test
33 Existing Equipment Testing 2 days Sat 3/14/15 Sun 3/15/15
34 DxH800 (from Main Lab) 2 days Sat 3/14/15 Sun 3/15/15 CMC LIS? Apps needed over this weekend?
35 SMS (from Main Lab) 2 days Sat 3/14/15 Sun 3/15/15 CMC LIS? Apps needed over this weekend?
36 Customer Offsite Training for Remisol 5 days Mon 1/19/15 Fri 1/23/15 CMC need to check with Leadership
37 Customer onsite Training 10 days Mon 2/23/15 Fri 3/6/15 Steve Johnson,Cindy Friedman need names of Key Ops and if they
went to school
38 Integration Testing 15 days Mon 2/23/15 Fri 3/13/15 Steve Johnson,Cindy Friedman Work with CMC LIS team on testing
plan
39 GoLive 0 days Mon 3/16/15 Mon 3/16/15 Steve Johnson,Cindy Friedman
40 Post GoLive support 5 days Mon 3/23/15 Fri 3/27/15 Steve Johnson,Cindy Friedman
41
42
43 AUTOMATION
44 Power Express Track System 172 days Mon 8/4/14 Fri 3/27/15
45 Pre‐installation Utilities 75 days Mon 8/4/14 Fri 11/14/14
46 Power 75 days Mon 8/4/14 Fri 11/14/14 B&G Contractors,Bin Kallan
S M
Aug 3
Page 1
2. ID Task Name Duration Start Finish PredecesResource Names Notes
47 Air 75 days Mon 8/4/14 Fri 11/14/14 B&G Contractors,Bin Kallan
48 Data 75 days Mon 8/4/14 Fri 11/14/14 B&G Contractors,Bin Kallan
49 Hardware Delivery 13 days Thu 11/13/14 Mon 12/1/14
50 Delivery of Track System 1 day Thu 11/13/14 Thu 11/13/14 Bin Kallan,Labor Team 8am delivery, 8 man team, tractor
trailers, impact drills with 10mm
socket adapters
51 Inventory check 1 day Fri 11/14/14 Fri 11/14/14 Bin Kallan,Labor Team
52 Cennexus delivery from IT 1 day Mon 12/1/14 Mon 12/1/14 Alvera Stevens,Justin Deardorff
53 Hardware Installation ‐ Phase 1 25 days Mon 11/17/14 Fri 12/19/14 Randy Prella,Phil Cantrell,Local Service
54 Hardware Installation ‐ Phase 2 ‐ continued 30 days Mon 2/2/15 Fri 3/13/15 Randy Prella,Phil Cantrell,Local Service
55 Applications Testing ‐ Phase 1 15 days Mon 12/1/14 Fri 12/19/14 Angela Briones,Justin Deardorff Angela starts 12/8 week through
week of 2/16
56 Applications Testing ‐ Phase 2 ‐ continued 62 days Mon 1/5/15 Fri 3/27/15 Justin Deardorff,Angela Briones Angela as needed ‐ GoLive
57 C.O.N. Ready 0 days Mon 12/15/14 Mon 12/15/14 Randy Prella,Phil Cantrell
58 Onsite Staff Training 5 days Mon 3/2/15 Fri 3/6/15 Onsite Brea Staff Need Key Ops from all 3 shifts. Line
is technically ready for GoLive at this
point.
59 Integration Testing 30 days Mon 2/2/15 Fri 3/13/15 Angela Briones,Alvera Stevens,Justin
Deardorff
Angela only until week of 2/16. Then
returns for GoLive.
60 GoLive 0 days Mon 3/16/15 Mon 3/16/15 Randy Prella,Phil Cantrell,Angela Brione
61
62
63 Automate 2500 (x2) 66 days Mon 9/1/14 Mon 12/1/14
64 Pre‐site activities 60 days Mon 9/1/14 Fri 11/21/14 Bin Kallan,B&G,CMC
65 Baseframes 41 days Mon 10/6/14 Mon 12/1/14 Matt Gates,CMC
66 IT discussions 41 days Mon 10/6/14 Mon 12/1/14 Alvera Stevens,Ann Sheehe
67 Hardware delivery 1 day Tue 12/2/14 Tue 12/2/14 KJ Masseke‐Harvey,David Kester 9am delivery, forklift, Impact drills,
size20 Torx Bits, Adjustable wrenches
68 Hardware Installation 9 days Tue 12/2/14 Fri 12/12/14 KJ Masseke‐Harvey,David Kester
69 Hardware installation continued 10 days Mon 2/9/15 Fri 2/20/15 KJ Masseke‐Harvey,Mike Wagner
70 Applications Testing 10 days Mon 12/8/14 Fri 12/19/14 Matt Gates
71 Applications Testing continued 10 days Mon 3/2/15 Fri 3/13/15 Matt Gates Work with Remisol and PE teams to
test EVERYTHING
72 C.O.N. Ready 0 days Mon 12/15/14 Mon 12/15/14
73 Customer Training 3 days Mon 2/2/15 Wed 2/4/15 ???
74 Integration Testing 10 days Mon 3/2/15 Fri 3/13/15 Matt Gates
75 GoLive 0 days Mon 3/16/15 Mon 3/16/15 Matt Gates
76
77
78 CHEMISTRY ANALYZERS
79 AU5822 (x2) 102 days Mon 11/10/14 Fri 3/27/15
80 Utilities Ready 1 day Mon 11/10/14 Mon 11/10/14 B&G,CMC
81 Hardware Delivery 1 day Wed 11/12/14 Wed 11/12/14 Bin Kallan,Labor Team
S M
Aug 3
Page 2
3. ID Task Name Duration Start Finish PredecesResource Names Notes
82 Hardware Installation 10 days Mon 11/17/14 Fri 11/28/14 David Kester,National Specialist
83 Applications Testing 50 days Mon 1/5/15 Fri 3/13/15 Mitzi Cassell Need permanent refrigerators ready
84 C.O.N. Ready 0 days Mon 12/15/14 Mon 12/15/14
85 Staff OFFSITE training 5 days Mon 2/23/15 Fri 2/27/15 CMC need to send staff in Dec, Jan or Feb?
86 Staff onsite training 10 days Mon 2/23/15 Fri 3/6/15 Mitzi Cassell,CMC
87 Integration Testing 20 days Mon 2/16/15 Fri 3/13/15 Mitzi Cassell
88 GoLive 0 days Mon 3/16/15 Mon 3/16/15 Mitzi Cassell
89 Post GoLive support 5 days Mon 3/23/15 Fri 3/27/15 Mitzi Cassell
90
91 DxI800 (x2) 92 days Mon 11/10/14 Mon 3/16/15
92 Utilities Ready 1 day Mon 11/10/14 Mon 11/10/14 B & G,CMC
93 Hardware Delivery 1 day Wed 11/12/14 Wed 11/12/14 Bin Kallan,Labor Team
94 Hardware Installation 15 days Mon 11/17/14 Fri 12/5/14 Local Service (outside)
95 Applications Testing 25 days Mon 1/5/15 Fri 2/6/15 Barbara Jones need permanent refrigerators ready
96 C.O.N. Ready 0 days Mon 11/10/14 Mon 11/10/14
97 Staff OFFSITE training 1 day Thu 1/1/15 Thu 1/1/15 CMC
98 Staff onsite training 5 days Mon 2/9/15 Fri 2/13/15
99 Integration Testing 20 days Mon 2/16/15 Fri 3/13/15 Remisol Team
100 GoLive 0 days Mon 3/16/15 Mon 3/16/15
101
102
103 HEMATOLOGY ANALYZERS
104 DxH800 (NEW Analyzer) 92 days Mon 11/10/14 Mon 3/16/15
105 Utilities Ready 1 day Mon 11/10/14 Mon 11/10/14 B & G,CMC
106 Hardware Delivery 1 day Wed 11/12/14 Wed 11/12/14 Bin Kallan,Labor Team
107 Hardware Installation 10 days Mon 11/17/14 Fri 11/28/14 Local Service
108 Applications Testing 5 days Mon 1/5/15 Fri 1/9/15 Teri Nevel need permanent refrigerators ready
109 C.O.N. Ready 0 days Mon 12/15/14 Mon 12/15/14
110 Staff OFFSITE training 5 days Thu 1/1/15 Wed 1/7/15
111 Staff onsite training 0 days Mon 2/9/15 Mon 2/9/15
112 Integration Testing 20 days Mon 2/16/15 Fri 3/13/15
113 GoLive 0 days Mon 3/16/15 Mon 3/16/15
114
115 DxH800+SMS (from Main Lab) 93 days Mon 11/10/14 Mon 3/16/15
116 Utilities Ready 1 day Mon 11/10/14 Mon 11/10/14 B & G,CMC
117 Hardware Delivery 1 day Sat 3/14/15 Sat 3/14/15 Local Service,CMC Labor Team CMC will transport, Local FSE to
supervise
118 Hardware Installation 2 days Sat 3/14/15 Sun 3/15/15 Local Service Local FSE to receive and reinstall
119 Applications Testing 1 day Sun 3/15/15 Sun 3/15/15 CMC LIS,CMC Full validation or just QC?
120 Integration Testing 2 days Sun 3/15/15 Mon 3/16/15 CMC LIS CMC LIS team or our team?
121 GoLive 0 days Mon 3/16/15 Mon 3/16/15
122
S M
Aug 3
Page 3
4. ID Task Name Duration Start Finish PredecesResource Names Notes
123 Cellavision (from NE Lab) 87 days Mon 11/17/14 Mon 3/16/15
124 Utilities Ready 1 day Mon 11/17/14 Mon 11/17/14 B&G,CMC
125 Hardware Delivery 1 day Mon 2/9/15 Mon 2/9/15 CMC CMC will transport
126 Hardware Installation 5 days Mon 2/16/15 Fri 2/20/15 Local Service Local FSE to receive and reinstall
127 Applications Testing 5 days Mon 2/23/15 Fri 2/27/15 Full validation or just QC?
128 Integration Testing 15 days Mon 2/23/15 Fri 3/13/15 CMC LIS team may need help
mounting onto network for remote
129 GoLive 0 days Mon 3/16/15 Mon 3/16/15
130
131
132 COAGULATION ANALYZERS
133 IRIScell (NEW Analyzer) 90 days Wed 11/12/14 Mon 3/16/15
134 Utilities Ready 1 day Mon 11/17/14 Mon 11/17/14
135 Hardware Delivery 1 day Wed 11/12/14 Wed 11/12/14 Bin Kallan,Labor Team
136 Hardware Installation 10 days Mon 12/8/14 Fri 12/19/14 Local Service (outside)
137 Applications Testing 5 days Mon 2/2/15 Fri 2/6/15 Terry Lyons need permanent refrigerators ready
138 C.O.N. Ready 0 days Mon 12/15/14 Mon 12/15/14
139 Staff OFFSITE training 1 day Thu 1/1/15 Thu 1/1/15
140 Staff onsite training 5 days Mon 2/9/15 Fri 2/13/15
141 Integration Testing 15 days Mon 2/23/15 Fri 3/13/15
142 GoLive 0 days Mon 3/16/15 Mon 3/16/15
143
144 IRIScell (from CMC Main Lab) 88 days Mon 11/17/14 Mon 3/16/15
145 Utilities Ready 1 day Mon 11/17/14 Mon 11/17/14 B&G Contractors
146 Hardware Delivery 1 day Sat 3/14/15 Sat 3/14/15 CMC
147 Hardware Installation 1 day Sat 3/14/15 Sat 3/14/15 CMC
148 Applications Testing 1 day Sun 3/15/15 Sun 3/15/15 CMC
149 Integration Testing 1 day Sun 3/15/15 Sun 3/15/15 CMC
150 GoLive 1 day Mon 3/16/15 Mon 3/16/15
S M
Aug 3
Page 4