• The new EU Public Procurement Directives
Carina Risvig Hamer
Ph.d. Assistant Professor, University of Southern Denmark
Carh@sam.sdu.dk
www.udbudslov.dk
Agenda
• Main changes in the EU Procurement Directive
• Implementation in Denmark
Modernisation of the EU Procurement
Directives
• January – April 2011: Commission’s Green Paper
hearing
• April 2011: Single Market Act points out the
procurement directives as a key initiative
• December 2011: Commission Proposals
• December 2012: Council general position
• January 2013: Parliament proposal
• June 2013 – Political agreement
• Published March 2014 (Directive 2014/24/EU)
Public Procurement Directive
2014/24/EU
• Cluster 1: Flexible Procedures
• Cluster 2: Strategic use of Procurement
• Cluster 3: Reduction of documentation costs
• Cluster 4: E-procurement
• Cluster 5: SMV access
• Cluster 6: Aggregation of demands
• Cluster 7: Other procedural requirements
• Cluster 8: Sound procedures
• Cluster 9: Governance
• Cluster 10: Scope
Cluster 1. Flexible procedures
1. Increased access to the procedures ”Competitive procedure
with negotiation” and ”competitive dialogue”
– Article 26(1)(C) Contracting authorities may apply a
competitive procedure with negotiation or a competitive
dialogue when
– ”i) (i) the needs of the contracting authority cannot be
met without adaptation of readily available solutions;
1. Innovation partnership, (Article 31)
1. Reduction of the minimum time limits
Cluster 2. Strategic use of procurement
1. Life-cycle costing Article 68
2. Use of labels: specific environmental, social labels, Article 43
3. New terminology regarding award criteria
4. Possibility to use tenderers experience in the award phase when
– (b) organisation, qualification and experience of staff assigned
to performing the contract, where the quality of the staff
assigned can have a significant impact on the level of
performance of the contract;
5. Abolishing the A/B Services and introduction of a new “light
regime”
New terminology regarding award criteria
• Art. 67(1), the award of public contracts shall
be based on the most economically
advantageous tender (MEAT)
• Art. 67(2) MEAT shall be identified based on
– Price
– Cost, using a cost-effectiveness approach, such as
life-cycle costing in accordance with Article 68,
– The best price-quality ratio,
”Light regime”
• Social and other specific services (Annex XVI
)
• Fx hotel og restaurant services, certain legal
services, firefighting services and prison
services
• Thresholds 750.000 euro
Light regime
• Art. 74-76. Contracting authorities shall make known their
intention by
– Light Contract Notice or
– Light PIN
• Contract award Notice
• Member States shall put in place national rules for the award
of contracts subject to this Chapter in order to ensure
contracting authorities comply with the principles of trans
parency and equal treatment
Cluster 3 Reducing documentation
requirements
1. Possibility for contracting authorities to request the
economic operators concerned to submit,
supplement, clarify or complete information or
documentation which appears to be incomplete or
missing
2. (updated) Exclusion grounds
1. European Single Procurement document
2. Self-cleaning
Exclusion grounds
• Art. 57 (3) b)
• Possibility to exclude an economic operator in case he has
shown significant or persistent deficiencies in the
performance of a substantive requirement under a prior
public contract which led to early termination of that prior
contract, damages or other comparable sanctions;
Cluster 4: E-procurement
1. Mandatory availability of procurement
documents
2. Mandatory electronic communication and
tender submission within 2 ½ years after
transposition deadline
3. E-auctions and E-catalogues, dynamic
purchasing systems
Cluster 5: SME Access
1. The minimum yearly turnover that economic
operators are required to have shall not
exceed two times the estimated contract
value,
1. Contracting authorities must provide an
indication of the main reasons for their
decision not to subdivide into lots,
Cluster 6: Aggregation of demand
1. Dynamic purchasing systems
2. Clarification of use of framework agreements
(mini-competition and ”direct award”)
3. Clarification of responsibility between CPB
and its users
Clarification of use of framework
agreements
• Art. 33(4) b
• The choice of whether specific works, supplies or services
shall be acquired following a reopening of competition or
directly on the terms set out in the framework agreement
shall be made pursuant to objective criteria,
• Recital 61
• Such criteria could for instance relate to the quantity, value or
characteristics of the works, supplies or services concerned,
including the need for a higher degree of service or an
increased security level, or to developments in price levels
compared to a predetermined price index.
Responsibility
• Art. 37(3) A contracting authority fulfils its obligations
pursuant to this Directive when it acquires supplies or
services from a CPB
• Art. 37(3) The contracting authority shall be responsible for
(a) awarding a contract under a dynamic purchasing system,
(b) conducting a reopening of competition
• (c) pursuant to points (a) or (b) of Article 33(4), determining
which of the economic operators, party to the framework
agreement, shall perform a given task under a framework
agreement that has been concluded by a central purchasing
body.
Cluster 8 Sound Procedures
1. New provision on conflict of interest
– Member States shall ensure that contracting authorities
take appropriate measures to effectively prevent, identify
and remedy conflicts of interest arising in the conduct of
procurement procedures so as to avoid any distortion of
competition and to ensure equal treatment of all economic
operators.
– Directly or indirectly, a financial, economic or other personal
interest which might be perceived to compromise their
impartiality and independence in the context of the
procurement procedure.
Cluster 8 Sound Procedures
1. Termination of contracts
1. Substantial modification of the contract
2. The contractor should have been excluded because of an
exclusion ground
3. The contract should not have been awarded to the
contractor in view of a serious infringement of the
obligations under the Treaties and this Directive that has
been declared by the Court of Justice of the European
Union in a procedure pursuant to Article 258 TFEU.
Cluster 8 Sound Procedures
• Substantial modification of the contract
– …where it renders the contract or the framework agreement
materially different in character from the one initially concluded.
[Pressetext pr 34] (….)
• Substantial in any event:
– a) introduces conditions which, had they been part of the initial
procurement procedure, would have allowed for the admission of
other candidates/tenderers [Pressetext, pr. 35]
– B) changes the economic balance of the contract or the framework
agreement in favour of the contractor in a manner [Pressetext pr. 37]
– c) extends the scope of the contract or framework agreement
considerably; [Pressetext pr. 36]
– d) where a new contractor replaces the one to which the contracting
authority had initially awarded the contract in other cases than those
provided for under point (d) of paragraph 1.
Replacing a contractor
• (d) replacing a contractor
– (i) an unequivocal review clause or option
– (ii) universal or partial succession into the position of the
initial contractor, following corporate restructuring, including
takeover, merger, acquisition or insolvency, of another
economic operator that fulfils the criteria for qualitative
selection initially established provided that this does not entail
other substantial modifications to the contract and is not
aimed at circumventing the application of this Directive; or
De minimis rule
• Never substantial
– where the value of the modification is below both
of the following values:
– (i) the thresholds set out in Article 4; and
– (ii) 10 % of the initial contract value for service
and supply contracts and below 15 % of the initial
contract value for works contracts.
• The modification may not alter the overall
nature of the contract or framework
agreement.
Governance
1. Member States shall ensure
– application of public procurement rules is monitored.
– information and guidance on the interpretation and appli
cation of the Union public procurement law is available
free of charge to assist contracting authorities and
economic operators, in particular SMEs
• Contracting authorities shall, at least for the duration of the
contract, keep copies of all concluded contracts with a value equal
to or greater than:
– (a) 1 000 000 EUR in the case of public supply contracts or public
service contracts;
– (b) 10 000 000 EUR in the case of public works contracts.
Cluster 10: Scope
1. Definition and thresholds
1. Exceptions
– Legal services, political campaign, public passenger
transport services by rail or metro, loans,
3. In-house (art. 12)
In-house (art. 12)
• A contract can be awarded without following the Directive if
a) the contracting authority exercises over the legal person concerned
a control which is similar to that which it exercises over its own
departments; (Control criterion)
b) more than 80 % of the activities of the controlled legal person are
carried out in the performance of tasks entrusted to it by the
controlling contracting authority (…) (the activity criterion)
c) There is no direct private capital participation in the controlled legal
person with the exception of non- controlling and non-blocking
forms of private capital participation required by national legislative
provisions, in conformity with the Treaties, which do not exert a
decisive influence on the controlled legal person.
.
In-house (art. 12) Horisontal
• A contracting authority can award a contract to another
contracting authority
a. the contract establishes or implements a cooperation
between the participating contracting authorities with the
aim of ensuring that public services they have to perform are
provided with a view to achieving objectives they have in
common;
b. the implementation of that cooperation is governed solely
by considerations relating to the public interest; and
c. the participating contracting authorities perform on the
open market less than 20 % of the activities concerned by
the cooperation.
• Danish implementation of the EU
Procurement Directives
Danish ”set-up”
• How Denmark implemented the 2004-Directives
– A general act empowers the minister to implement new procurement
rules
– Can be done on the administrative level on basis of a governmental order
– The governmental order deals with the rights and obligations of the
contracting authorities
– The actual text of the directive is annexed
– This means that text of the Directive constitutes the current legislation
(“telles quelles”)
Danish ”set-up”
• The public sector in Denmark is very decentralised
– 2 619 Tenders in TED (2011)
– Total expenditure in regard to public procurement is estimated at 294
billion Danish kroner (39,4 billion €)
• National law for works below the EU thresholds
• National law on advertising goods and services of a value above DKK
500,000 (app. € 67,000) but under the EU threshold values (only A-
services)
• No rules for B-services
• 1 Complaints board for Public Procurement
Implementation
(Public Procurement Directive)
• Public Procurement law committee
• President: Director of Competition Authority
• Members:
– Advokatsamfundet/Danske Advokater, LO, FTF, Dansk
Byggeri, Dansk Erhverv, Danske Regioner, DI, Erhvervs- og
Vækstministeriet, Finansministeriet, Foreningen af
offentlige indkøbere, Foreningen af Rådgivende Ingeniører,
Kommunernes Landsforening, Håndværksrådet, Statens og
Kommunernes Indkøbsservice, Økonomi- og
Indenrigsministeriet
Subcommittee’s
• Subcommittee regarding the procedures for goods
and services below the EU tresholds and the light
regime
• Subcommittee regarding E-Procurement
• Subcommittee regarding award criterira and
transparency
The outcome?
• One (big?) Act
• Wording close to the Directive?
• Preparatory acts…
• Last meeting end of September 2014
• Proposal beginning of 2015
• New Government…..
Thank you for your attention
Carina Risvig Hamer
Ph.D. Assistant Professor
University of Southern
Denmark
Legal Department
Tlf. 0045-23717973
E-mail: carh@sam.sdu.dk
www.udbudslov.dk

Más contenido relacionado

La actualidad más candente

Ppp w.a. janssen - ippc6 -dublin 2014
Ppp   w.a. janssen - ippc6 -dublin 2014Ppp   w.a. janssen - ippc6 -dublin 2014
Ppp w.a. janssen - ippc6 -dublin 2014
Dr. Paul Davis
 
20150610 febelmar privacy matters eu regulation
20150610 febelmar privacy matters eu regulation20150610 febelmar privacy matters eu regulation
20150610 febelmar privacy matters eu regulation
Febelmar
 
Recent eu data_initiatives_in_context_infographic
Recent eu data_initiatives_in_context_infographicRecent eu data_initiatives_in_context_infographic
Recent eu data_initiatives_in_context_infographic
marino54
 
Heico Kerkmeester - Soft Law and the Margin of Appreciation of the National J...
Heico Kerkmeester - Soft Law and the Margin of Appreciation of the National J...Heico Kerkmeester - Soft Law and the Margin of Appreciation of the National J...
Heico Kerkmeester - Soft Law and the Margin of Appreciation of the National J...
FSR Communications and Media
 
S panagopoulos public_public_partnerships (ippc_bud_161102011)
S panagopoulos public_public_partnerships (ippc_bud_161102011)S panagopoulos public_public_partnerships (ippc_bud_161102011)
S panagopoulos public_public_partnerships (ippc_bud_161102011)
Spyros Panagopoulos
 

La actualidad más candente (18)

Plymouth & INCIC Launch Event 30th November 2017 Dynamic Purchasing System (D...
Plymouth & INCIC Launch Event 30th November 2017 Dynamic Purchasing System (D...Plymouth & INCIC Launch Event 30th November 2017 Dynamic Purchasing System (D...
Plymouth & INCIC Launch Event 30th November 2017 Dynamic Purchasing System (D...
 
East of England Local Government Association: The Changing Face of Public Pro...
East of England Local Government Association: The Changing Face of Public Pro...East of England Local Government Association: The Changing Face of Public Pro...
East of England Local Government Association: The Changing Face of Public Pro...
 
Analysis of recent procurement reforms from perspective of flexibility
Analysis of recent procurement reforms from perspective of flexibilityAnalysis of recent procurement reforms from perspective of flexibility
Analysis of recent procurement reforms from perspective of flexibility
 
Recent ECJ public procurement case law on selected topics
Recent ECJ public procurement case law on selected topicsRecent ECJ public procurement case law on selected topics
Recent ECJ public procurement case law on selected topics
 
Presentation, Niels Schuster, 7th Regional Public Procurement Conference, Vlo...
Presentation, Niels Schuster, 7th Regional Public Procurement Conference, Vlo...Presentation, Niels Schuster, 7th Regional Public Procurement Conference, Vlo...
Presentation, Niels Schuster, 7th Regional Public Procurement Conference, Vlo...
 
Procurement and labour objectives: some thoughts on regulatory substitution a...
Procurement and labour objectives: some thoughts on regulatory substitution a...Procurement and labour objectives: some thoughts on regulatory substitution a...
Procurement and labour objectives: some thoughts on regulatory substitution a...
 
Ppp w.a. janssen - ippc6 -dublin 2014
Ppp   w.a. janssen - ippc6 -dublin 2014Ppp   w.a. janssen - ippc6 -dublin 2014
Ppp w.a. janssen - ippc6 -dublin 2014
 
20150610 febelmar privacy matters eu regulation
20150610 febelmar privacy matters eu regulation20150610 febelmar privacy matters eu regulation
20150610 febelmar privacy matters eu regulation
 
Public sector breakfast club, April 2018, Exeter
Public sector breakfast club, April 2018, ExeterPublic sector breakfast club, April 2018, Exeter
Public sector breakfast club, April 2018, Exeter
 
LAW ON PUBLIC PROCUREMENT CONTRACTS
LAW ON PUBLIC PROCUREMENT CONTRACTSLAW ON PUBLIC PROCUREMENT CONTRACTS
LAW ON PUBLIC PROCUREMENT CONTRACTS
 
Some suggestions to the EFTA Surveillance Authority
Some suggestions to the EFTA Surveillance AuthoritySome suggestions to the EFTA Surveillance Authority
Some suggestions to the EFTA Surveillance Authority
 
ERA annual public procurement conference 2016
ERA annual public procurement conference 2016ERA annual public procurement conference 2016
ERA annual public procurement conference 2016
 
Recent eu data_initiatives_in_context_infographic
Recent eu data_initiatives_in_context_infographicRecent eu data_initiatives_in_context_infographic
Recent eu data_initiatives_in_context_infographic
 
2 Modernisation of EU Public Procurement Policy - Association Agreements_English
2 Modernisation of EU Public Procurement Policy - Association Agreements_English2 Modernisation of EU Public Procurement Policy - Association Agreements_English
2 Modernisation of EU Public Procurement Policy - Association Agreements_English
 
Competition and state aid implications of minimum wage in procurement
Competition and state aid implications of minimum wage in procurementCompetition and state aid implications of minimum wage in procurement
Competition and state aid implications of minimum wage in procurement
 
Heico Kerkmeester - Soft Law and the Margin of Appreciation of the National J...
Heico Kerkmeester - Soft Law and the Margin of Appreciation of the National J...Heico Kerkmeester - Soft Law and the Margin of Appreciation of the National J...
Heico Kerkmeester - Soft Law and the Margin of Appreciation of the National J...
 
S panagopoulos public_public_partnerships (ippc_bud_161102011)
S panagopoulos public_public_partnerships (ippc_bud_161102011)S panagopoulos public_public_partnerships (ippc_bud_161102011)
S panagopoulos public_public_partnerships (ippc_bud_161102011)
 
Adam Scott - UK Scope of Judicial Review of NRA's decisions
Adam Scott - UK Scope of Judicial Review of NRA's decisionsAdam Scott - UK Scope of Judicial Review of NRA's decisions
Adam Scott - UK Scope of Judicial Review of NRA's decisions
 

Destacado

National public procurement policy framework
National public procurement policy frameworkNational public procurement policy framework
National public procurement policy framework
Dr Lendy Spires
 
Gestão de vendas primeiros conceitos
Gestão de vendas   primeiros conceitosGestão de vendas   primeiros conceitos
Gestão de vendas primeiros conceitos
Lucinea Lima Lacerda
 
Product and service design
Product and service designProduct and service design
Product and service design
Grace Falcis
 

Destacado (13)

Vesna Gojkovic Milin, SIGMA Public procurement review bodies conference, Ohri...
Vesna Gojkovic Milin, SIGMA Public procurement review bodies conference, Ohri...Vesna Gojkovic Milin, SIGMA Public procurement review bodies conference, Ohri...
Vesna Gojkovic Milin, SIGMA Public procurement review bodies conference, Ohri...
 
National public procurement policy framework
National public procurement policy frameworkNational public procurement policy framework
National public procurement policy framework
 
Kenya’s public procurement policy: A women’s perspective
Kenya’s public procurement policy: A women’s perspectiveKenya’s public procurement policy: A women’s perspective
Kenya’s public procurement policy: A women’s perspective
 
Implementing the procurement legislation
Implementing the procurement legislationImplementing the procurement legislation
Implementing the procurement legislation
 
Doing Business With Coal India
Doing Business With Coal IndiaDoing Business With Coal India
Doing Business With Coal India
 
Bid evaluation shopping
Bid evaluation   shoppingBid evaluation   shopping
Bid evaluation shopping
 
Gestão de vendas primeiros conceitos
Gestão de vendas   primeiros conceitosGestão de vendas   primeiros conceitos
Gestão de vendas primeiros conceitos
 
Public Procurement and Contract - Theory and practice in Nepal_2013
Public Procurement and Contract - Theory and practice in Nepal_2013Public Procurement and Contract - Theory and practice in Nepal_2013
Public Procurement and Contract - Theory and practice in Nepal_2013
 
MBA663 Philippine Business Environment PPT presentation
MBA663 Philippine Business Environment PPT presentationMBA663 Philippine Business Environment PPT presentation
MBA663 Philippine Business Environment PPT presentation
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 
A view of procurement best practice
A view of procurement best practiceA view of procurement best practice
A view of procurement best practice
 
Product and service design
Product and service designProduct and service design
Product and service design
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement Guide
 

Similar a Major changes in the new Public Procurement Directives, June 2014, Universidade Catolica Portugesa

TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTSTUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
Prof Handley Mpoki Mafwenga
 
Introduction To EU Procurement Rules October 2011
Introduction To EU Procurement Rules October 2011Introduction To EU Procurement Rules October 2011
Introduction To EU Procurement Rules October 2011
EuanPirie
 
Ogc guidance on_framework_agreements_sept_08
Ogc guidance on_framework_agreements_sept_08Ogc guidance on_framework_agreements_sept_08
Ogc guidance on_framework_agreements_sept_08
Martin Ellis
 

Similar a Major changes in the new Public Procurement Directives, June 2014, Universidade Catolica Portugesa (20)

Presentation by Aleksandra Melesko, public procurement reality and challenges...
Presentation by Aleksandra Melesko, public procurement reality and challenges...Presentation by Aleksandra Melesko, public procurement reality and challenges...
Presentation by Aleksandra Melesko, public procurement reality and challenges...
 
The impact of Public Contracts Regulations 2015 on public procurement exercis...
The impact of Public Contracts Regulations 2015 on public procurement exercis...The impact of Public Contracts Regulations 2015 on public procurement exercis...
The impact of Public Contracts Regulations 2015 on public procurement exercis...
 
Catherine Barnard
Catherine Barnard Catherine Barnard
Catherine Barnard
 
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTSTUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
 
How to make the most of framework agreements - Andrew Millross
How to make the most of framework agreements - Andrew MillrossHow to make the most of framework agreements - Andrew Millross
How to make the most of framework agreements - Andrew Millross
 
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
 
Framework Days
Framework DaysFramework Days
Framework Days
 
Plymouth City Council & INCIC Launch Event 30th November Dynamic Purchasing S...
Plymouth City Council & INCIC Launch Event 30th November Dynamic Purchasing S...Plymouth City Council & INCIC Launch Event 30th November Dynamic Purchasing S...
Plymouth City Council & INCIC Launch Event 30th November Dynamic Purchasing S...
 
Introduction To EU Procurement Rules October 2011
Introduction To EU Procurement Rules October 2011Introduction To EU Procurement Rules October 2011
Introduction To EU Procurement Rules October 2011
 
PPT, B Garcia Porras, EC, Third ENP East public procurement conference, Tbili...
PPT, B Garcia Porras, EC, Third ENP East public procurement conference, Tbili...PPT, B Garcia Porras, EC, Third ENP East public procurement conference, Tbili...
PPT, B Garcia Porras, EC, Third ENP East public procurement conference, Tbili...
 
Montenegro Presentation, Sandra Skataric, PPA, Legislative framework, 7th Reg...
Montenegro Presentation, Sandra Skataric, PPA, Legislative framework, 7th Reg...Montenegro Presentation, Sandra Skataric, PPA, Legislative framework, 7th Reg...
Montenegro Presentation, Sandra Skataric, PPA, Legislative framework, 7th Reg...
 
QA-new-public-sector-regs-FINAL
QA-new-public-sector-regs-FINALQA-new-public-sector-regs-FINAL
QA-new-public-sector-regs-FINAL
 
Presentation, SIGMA Workshop on PPP characteristics, models & sectors, Turkey...
Presentation, SIGMA Workshop on PPP characteristics, models & sectors, Turkey...Presentation, SIGMA Workshop on PPP characteristics, models & sectors, Turkey...
Presentation, SIGMA Workshop on PPP characteristics, models & sectors, Turkey...
 
Horizon 2020 ga
Horizon 2020 gaHorizon 2020 ga
Horizon 2020 ga
 
EU spends 5 MIO EUR for media campaign in Turkey
EU spends 5 MIO EUR for media campaign in Turkey EU spends 5 MIO EUR for media campaign in Turkey
EU spends 5 MIO EUR for media campaign in Turkey
 
Presentation_Public Procurement in International Construction and Infrastruct...
Presentation_Public Procurement in International Construction and Infrastruct...Presentation_Public Procurement in International Construction and Infrastruct...
Presentation_Public Procurement in International Construction and Infrastruct...
 
Vietnam - The World Bank is asking Duane Morris about Doing Business and Gove...
Vietnam - The World Bank is asking Duane Morris about Doing Business and Gove...Vietnam - The World Bank is asking Duane Morris about Doing Business and Gove...
Vietnam - The World Bank is asking Duane Morris about Doing Business and Gove...
 
EMT MUTAHIR for CTBCM 60 SMC.pptx
EMT MUTAHIR for CTBCM 60 SMC.pptxEMT MUTAHIR for CTBCM 60 SMC.pptx
EMT MUTAHIR for CTBCM 60 SMC.pptx
 
Polish CIT in 2019 - CIT and TP revolution marches on
Polish CIT in 2019 - CIT and TP revolution marches onPolish CIT in 2019 - CIT and TP revolution marches on
Polish CIT in 2019 - CIT and TP revolution marches on
 
Ogc guidance on_framework_agreements_sept_08
Ogc guidance on_framework_agreements_sept_08Ogc guidance on_framework_agreements_sept_08
Ogc guidance on_framework_agreements_sept_08
 

Más de Carina Risvig Hamer (12)

Light regime
Light regime Light regime
Light regime
 
Ny udbudslov
Ny udbudslovNy udbudslov
Ny udbudslov
 
Udbud under tærskelværdierne
Udbud under tærskelværdierne Udbud under tærskelværdierne
Udbud under tærskelværdierne
 
Ineffectiveness of contracts in Denmark
Ineffectiveness of contracts in Denmark Ineffectiveness of contracts in Denmark
Ineffectiveness of contracts in Denmark
 
Udbudslovens regler i light regimet
Udbudslovens regler i light regimetUdbudslovens regler i light regimet
Udbudslovens regler i light regimet
 
Lov om håndhævelse af udbudsreglerne, Horten 3. juni 2016
Lov om håndhævelse af udbudsreglerne, Horten 3. juni 2016Lov om håndhævelse af udbudsreglerne, Horten 3. juni 2016
Lov om håndhævelse af udbudsreglerne, Horten 3. juni 2016
 
Light regime -
Light regime - Light regime -
Light regime -
 
Væsentlige ændringer af kontrakten
Væsentlige ændringer af kontraktenVæsentlige ændringer af kontrakten
Væsentlige ændringer af kontrakten
 
Udbudsmedia
Udbudsmedia Udbudsmedia
Udbudsmedia
 
Væsentlige ændringer af kontrakt - Nohr-Con, maj 2014
Væsentlige ændringer af kontrakt - Nohr-Con, maj 2014Væsentlige ændringer af kontrakt - Nohr-Con, maj 2014
Væsentlige ændringer af kontrakt - Nohr-Con, maj 2014
 
Nyt udbudsdirektiv (ika) 18. juni 2014
Nyt udbudsdirektiv (ika) 18. juni 2014Nyt udbudsdirektiv (ika) 18. juni 2014
Nyt udbudsdirektiv (ika) 18. juni 2014
 
Nyt udbudsdirektiv netværk (un)
Nyt udbudsdirektiv   netværk (un)Nyt udbudsdirektiv   netværk (un)
Nyt udbudsdirektiv netværk (un)
 

Último

PowerPoint - Legal Citation Form 1 - Case Law.pptx
PowerPoint - Legal Citation Form 1 - Case Law.pptxPowerPoint - Legal Citation Form 1 - Case Law.pptx
PowerPoint - Legal Citation Form 1 - Case Law.pptx
ca2or2tx
 
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
Airst S
 
一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理
Airst S
 
Contract law. Indemnity
Contract law.                     IndemnityContract law.                     Indemnity
Contract law. Indemnity
mahikaanand16
 
一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理
Airst S
 
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
Airst S
 
Appeal and Revision in Income Tax Act.pdf
Appeal and Revision in Income Tax Act.pdfAppeal and Revision in Income Tax Act.pdf
Appeal and Revision in Income Tax Act.pdf
PoojaGadiya1
 
一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理
Airst S
 
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
Airst S
 

Último (20)

Clarifying Land Donation Issues Memo for
Clarifying Land Donation Issues Memo forClarifying Land Donation Issues Memo for
Clarifying Land Donation Issues Memo for
 
PowerPoint - Legal Citation Form 1 - Case Law.pptx
PowerPoint - Legal Citation Form 1 - Case Law.pptxPowerPoint - Legal Citation Form 1 - Case Law.pptx
PowerPoint - Legal Citation Form 1 - Case Law.pptx
 
IBC (Insolvency and Bankruptcy Code 2016)-IOD - PPT.pptx
IBC (Insolvency and Bankruptcy Code 2016)-IOD - PPT.pptxIBC (Insolvency and Bankruptcy Code 2016)-IOD - PPT.pptx
IBC (Insolvency and Bankruptcy Code 2016)-IOD - PPT.pptx
 
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
 
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
 
BPA GROUP 7 - DARIO VS. MISON REPORTING.pdf
BPA GROUP 7 - DARIO VS. MISON REPORTING.pdfBPA GROUP 7 - DARIO VS. MISON REPORTING.pdf
BPA GROUP 7 - DARIO VS. MISON REPORTING.pdf
 
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
 
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYA SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
 
ARTICLE 370 PDF about the indian constitution.
ARTICLE 370 PDF about the  indian constitution.ARTICLE 370 PDF about the  indian constitution.
ARTICLE 370 PDF about the indian constitution.
 
一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理
 
589308994-interpretation-of-statutes-notes-law-college.pdf
589308994-interpretation-of-statutes-notes-law-college.pdf589308994-interpretation-of-statutes-notes-law-college.pdf
589308994-interpretation-of-statutes-notes-law-college.pdf
 
8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx
8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx
8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx
 
Contract law. Indemnity
Contract law.                     IndemnityContract law.                     Indemnity
Contract law. Indemnity
 
一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理
 
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
 
Appeal and Revision in Income Tax Act.pdf
Appeal and Revision in Income Tax Act.pdfAppeal and Revision in Income Tax Act.pdf
Appeal and Revision in Income Tax Act.pdf
 
The doctrine of harmonious construction under Interpretation of statute
The doctrine of harmonious construction under Interpretation of statuteThe doctrine of harmonious construction under Interpretation of statute
The doctrine of harmonious construction under Interpretation of statute
 
一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理
 
CAFC Chronicles: Costly Tales of Claim Construction Fails
CAFC Chronicles: Costly Tales of Claim Construction FailsCAFC Chronicles: Costly Tales of Claim Construction Fails
CAFC Chronicles: Costly Tales of Claim Construction Fails
 
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
 

Major changes in the new Public Procurement Directives, June 2014, Universidade Catolica Portugesa

  • 1. • The new EU Public Procurement Directives Carina Risvig Hamer Ph.d. Assistant Professor, University of Southern Denmark Carh@sam.sdu.dk www.udbudslov.dk
  • 2. Agenda • Main changes in the EU Procurement Directive • Implementation in Denmark
  • 3. Modernisation of the EU Procurement Directives • January – April 2011: Commission’s Green Paper hearing • April 2011: Single Market Act points out the procurement directives as a key initiative • December 2011: Commission Proposals • December 2012: Council general position • January 2013: Parliament proposal • June 2013 – Political agreement • Published March 2014 (Directive 2014/24/EU)
  • 4. Public Procurement Directive 2014/24/EU • Cluster 1: Flexible Procedures • Cluster 2: Strategic use of Procurement • Cluster 3: Reduction of documentation costs • Cluster 4: E-procurement • Cluster 5: SMV access • Cluster 6: Aggregation of demands • Cluster 7: Other procedural requirements • Cluster 8: Sound procedures • Cluster 9: Governance • Cluster 10: Scope
  • 5. Cluster 1. Flexible procedures 1. Increased access to the procedures ”Competitive procedure with negotiation” and ”competitive dialogue” – Article 26(1)(C) Contracting authorities may apply a competitive procedure with negotiation or a competitive dialogue when – ”i) (i) the needs of the contracting authority cannot be met without adaptation of readily available solutions; 1. Innovation partnership, (Article 31) 1. Reduction of the minimum time limits
  • 6. Cluster 2. Strategic use of procurement 1. Life-cycle costing Article 68 2. Use of labels: specific environmental, social labels, Article 43 3. New terminology regarding award criteria 4. Possibility to use tenderers experience in the award phase when – (b) organisation, qualification and experience of staff assigned to performing the contract, where the quality of the staff assigned can have a significant impact on the level of performance of the contract; 5. Abolishing the A/B Services and introduction of a new “light regime”
  • 7. New terminology regarding award criteria • Art. 67(1), the award of public contracts shall be based on the most economically advantageous tender (MEAT) • Art. 67(2) MEAT shall be identified based on – Price – Cost, using a cost-effectiveness approach, such as life-cycle costing in accordance with Article 68, – The best price-quality ratio,
  • 8. ”Light regime” • Social and other specific services (Annex XVI ) • Fx hotel og restaurant services, certain legal services, firefighting services and prison services • Thresholds 750.000 euro
  • 9. Light regime • Art. 74-76. Contracting authorities shall make known their intention by – Light Contract Notice or – Light PIN • Contract award Notice • Member States shall put in place national rules for the award of contracts subject to this Chapter in order to ensure contracting authorities comply with the principles of trans parency and equal treatment
  • 10. Cluster 3 Reducing documentation requirements 1. Possibility for contracting authorities to request the economic operators concerned to submit, supplement, clarify or complete information or documentation which appears to be incomplete or missing 2. (updated) Exclusion grounds 1. European Single Procurement document 2. Self-cleaning
  • 11. Exclusion grounds • Art. 57 (3) b) • Possibility to exclude an economic operator in case he has shown significant or persistent deficiencies in the performance of a substantive requirement under a prior public contract which led to early termination of that prior contract, damages or other comparable sanctions;
  • 12. Cluster 4: E-procurement 1. Mandatory availability of procurement documents 2. Mandatory electronic communication and tender submission within 2 ½ years after transposition deadline 3. E-auctions and E-catalogues, dynamic purchasing systems
  • 13. Cluster 5: SME Access 1. The minimum yearly turnover that economic operators are required to have shall not exceed two times the estimated contract value, 1. Contracting authorities must provide an indication of the main reasons for their decision not to subdivide into lots,
  • 14. Cluster 6: Aggregation of demand 1. Dynamic purchasing systems 2. Clarification of use of framework agreements (mini-competition and ”direct award”) 3. Clarification of responsibility between CPB and its users
  • 15. Clarification of use of framework agreements • Art. 33(4) b • The choice of whether specific works, supplies or services shall be acquired following a reopening of competition or directly on the terms set out in the framework agreement shall be made pursuant to objective criteria, • Recital 61 • Such criteria could for instance relate to the quantity, value or characteristics of the works, supplies or services concerned, including the need for a higher degree of service or an increased security level, or to developments in price levels compared to a predetermined price index.
  • 16. Responsibility • Art. 37(3) A contracting authority fulfils its obligations pursuant to this Directive when it acquires supplies or services from a CPB • Art. 37(3) The contracting authority shall be responsible for (a) awarding a contract under a dynamic purchasing system, (b) conducting a reopening of competition • (c) pursuant to points (a) or (b) of Article 33(4), determining which of the economic operators, party to the framework agreement, shall perform a given task under a framework agreement that has been concluded by a central purchasing body.
  • 17. Cluster 8 Sound Procedures 1. New provision on conflict of interest – Member States shall ensure that contracting authorities take appropriate measures to effectively prevent, identify and remedy conflicts of interest arising in the conduct of procurement procedures so as to avoid any distortion of competition and to ensure equal treatment of all economic operators. – Directly or indirectly, a financial, economic or other personal interest which might be perceived to compromise their impartiality and independence in the context of the procurement procedure.
  • 18. Cluster 8 Sound Procedures 1. Termination of contracts 1. Substantial modification of the contract 2. The contractor should have been excluded because of an exclusion ground 3. The contract should not have been awarded to the contractor in view of a serious infringement of the obligations under the Treaties and this Directive that has been declared by the Court of Justice of the European Union in a procedure pursuant to Article 258 TFEU.
  • 19. Cluster 8 Sound Procedures • Substantial modification of the contract – …where it renders the contract or the framework agreement materially different in character from the one initially concluded. [Pressetext pr 34] (….) • Substantial in any event: – a) introduces conditions which, had they been part of the initial procurement procedure, would have allowed for the admission of other candidates/tenderers [Pressetext, pr. 35] – B) changes the economic balance of the contract or the framework agreement in favour of the contractor in a manner [Pressetext pr. 37] – c) extends the scope of the contract or framework agreement considerably; [Pressetext pr. 36] – d) where a new contractor replaces the one to which the contracting authority had initially awarded the contract in other cases than those provided for under point (d) of paragraph 1.
  • 20. Replacing a contractor • (d) replacing a contractor – (i) an unequivocal review clause or option – (ii) universal or partial succession into the position of the initial contractor, following corporate restructuring, including takeover, merger, acquisition or insolvency, of another economic operator that fulfils the criteria for qualitative selection initially established provided that this does not entail other substantial modifications to the contract and is not aimed at circumventing the application of this Directive; or
  • 21. De minimis rule • Never substantial – where the value of the modification is below both of the following values: – (i) the thresholds set out in Article 4; and – (ii) 10 % of the initial contract value for service and supply contracts and below 15 % of the initial contract value for works contracts. • The modification may not alter the overall nature of the contract or framework agreement.
  • 22. Governance 1. Member States shall ensure – application of public procurement rules is monitored. – information and guidance on the interpretation and appli cation of the Union public procurement law is available free of charge to assist contracting authorities and economic operators, in particular SMEs • Contracting authorities shall, at least for the duration of the contract, keep copies of all concluded contracts with a value equal to or greater than: – (a) 1 000 000 EUR in the case of public supply contracts or public service contracts; – (b) 10 000 000 EUR in the case of public works contracts.
  • 23. Cluster 10: Scope 1. Definition and thresholds 1. Exceptions – Legal services, political campaign, public passenger transport services by rail or metro, loans, 3. In-house (art. 12)
  • 24. In-house (art. 12) • A contract can be awarded without following the Directive if a) the contracting authority exercises over the legal person concerned a control which is similar to that which it exercises over its own departments; (Control criterion) b) more than 80 % of the activities of the controlled legal person are carried out in the performance of tasks entrusted to it by the controlling contracting authority (…) (the activity criterion) c) There is no direct private capital participation in the controlled legal person with the exception of non- controlling and non-blocking forms of private capital participation required by national legislative provisions, in conformity with the Treaties, which do not exert a decisive influence on the controlled legal person. .
  • 25. In-house (art. 12) Horisontal • A contracting authority can award a contract to another contracting authority a. the contract establishes or implements a cooperation between the participating contracting authorities with the aim of ensuring that public services they have to perform are provided with a view to achieving objectives they have in common; b. the implementation of that cooperation is governed solely by considerations relating to the public interest; and c. the participating contracting authorities perform on the open market less than 20 % of the activities concerned by the cooperation.
  • 26. • Danish implementation of the EU Procurement Directives
  • 27. Danish ”set-up” • How Denmark implemented the 2004-Directives – A general act empowers the minister to implement new procurement rules – Can be done on the administrative level on basis of a governmental order – The governmental order deals with the rights and obligations of the contracting authorities – The actual text of the directive is annexed – This means that text of the Directive constitutes the current legislation (“telles quelles”)
  • 28. Danish ”set-up” • The public sector in Denmark is very decentralised – 2 619 Tenders in TED (2011) – Total expenditure in regard to public procurement is estimated at 294 billion Danish kroner (39,4 billion €) • National law for works below the EU thresholds • National law on advertising goods and services of a value above DKK 500,000 (app. € 67,000) but under the EU threshold values (only A- services) • No rules for B-services • 1 Complaints board for Public Procurement
  • 29. Implementation (Public Procurement Directive) • Public Procurement law committee • President: Director of Competition Authority • Members: – Advokatsamfundet/Danske Advokater, LO, FTF, Dansk Byggeri, Dansk Erhverv, Danske Regioner, DI, Erhvervs- og Vækstministeriet, Finansministeriet, Foreningen af offentlige indkøbere, Foreningen af Rådgivende Ingeniører, Kommunernes Landsforening, Håndværksrådet, Statens og Kommunernes Indkøbsservice, Økonomi- og Indenrigsministeriet
  • 30. Subcommittee’s • Subcommittee regarding the procedures for goods and services below the EU tresholds and the light regime • Subcommittee regarding E-Procurement • Subcommittee regarding award criterira and transparency
  • 31. The outcome? • One (big?) Act • Wording close to the Directive? • Preparatory acts… • Last meeting end of September 2014 • Proposal beginning of 2015 • New Government…..
  • 32. Thank you for your attention Carina Risvig Hamer Ph.D. Assistant Professor University of Southern Denmark Legal Department Tlf. 0045-23717973 E-mail: carh@sam.sdu.dk www.udbudslov.dk