SlideShare una empresa de Scribd logo
1 de 2
Descargar para leer sin conexión
NEW ELEVETOR®
TANK SYSTEM
Example for an elevation of 2 meters:
Requires: Base NEW ELEVETOR® + PVC tube dia. 125 mm 182.5 cm lenght + NEW ELEVETOR® H 15
Concrete consumption = (0.037 x 1.85) + 0.030 = 0.098 m³/m²
Concrete consumption calculation:
*Supply of the tubes ø 125 mm can be discussed at the time of order.
The quantity of concrete to fill the pillars is equal to 0.037 m³/m² per meter height.
NEW ELEVETOR®
H=15 cm DATA
DIMENSION
cm
58 X 58
HEIGHT
H
15
CONCRETE QUANTITY to fill
the formwork - m3/m2
PALLET HEIGHT
m
No. OF UNITS/
PALLET
QUANTITY
m²
752252.50.030
**Place ø 8 mm reinforcement bars within the tubes that are part of the NEW ELEVETOR® system. These inserts must be joined to the rebar mesh
used to reinforce the slab, and should be long enough to reach the base of the tube.
1
2
3
4
5
6
7
8
QUANTITY
NEW ELEVETOR® formwork
ø 125 mm tube*
BASE NEW ELEVATOR® footing grid
Installation of NEW ELEVETOR® system
Rebar mesh ø 6 20x20
(cost of material and labour)
Concrete class Rck 250 to fill the tubes
(cost of material and labour)
Concrete class Rck 250 to fill the formwork
(material and labour)
Concrete class Rck 250 for the floor slab thickness
(material and labour)
BILL OF MATERIAL UNIT/MEASURE PRICE TOTALAMOUNT
Total cost €/m2
m2
No./m2
No./m2
hours/m2
kg/m2
m3/m2
m3/m2
m3/m2
2.328
0.05
3
3
1
No.
[0,037 X (NEW ELEVETOR®
system height in meters - 0,15)] + = [m³/m²]concrete
consumption
The concrete consumption for each square meter of ELEVETOR®
is:
REV.004
www.geoplast.it
The formwork for ventilated foundations from 70 cm to 250 cm
ST.11/2011
Disclaimer: the values shown in this brochure are for guidance only. They are not meant to be used for design criteria.
Their use and reliance thereon for any purpose by anyone is entirely voluntary and at the sole risk of the user. GEOPLAST is not responsible for any loss, claim, or damage resulting from their use.
NEW ELEVETOR® / PROJECT COST ANALYSISNEW ELEVETOR® / TYPICAL CALCULATION
Stormwater management systems for both residential and industrial use can be made using NEW ELEVETOR®
. Tanks can
be built for temporary stormwater storage and attenuation, or permanent storage and reuse. The NEW ELEVETOR®
system
allows to build tanks of any shape and up to 2 meters depth without using cranes or heavy-lifting equipment.
inite-element modelling for a plot of land 16.82 meters long and 7 meters deep, of which 6.30 m are soft clay
and 0.70 m of compacted pozzolana and lapillo.
The simulated structure was assumed to be made by a layer of lean mix 12 cm thickness, NEW ELEVETOR®
system
95 cm height and a slab 5 cm thickness.
F
Fig 1) Maximum vertical tension in the clay layer with two concentrated loads of 3,500 kg at centres 2.32 m.
Fig 2) Effect of four 3,500 kg loads in axis to the plate axis
Plate Disp: DZ (cm)
0.0038 [Pt: 31443, Nd: 38983]
-0.0043
-0.0205
-0.0366
-0.0528
-0.0690
-0.0852
-0.1014
-0.1175
-0.1337
-0.1499
-0.1580 [Pt: 31480, Nd:39019]
Plate Stress: MC (kg/cm²)
-0.0484 [Pt: 2106, Nd: 2447]
-0.0613
-0.0869
-0.1125
-0.1382
-0.1638
-0.1895
-0.2151
-0.2408
-0.2664
-0.2921
-0.3049 [Pt: 730, Nd:1422]
LOAD TABLE for NEW ELEVETOR®
H=120 cm
0.8710,000 10 15 4.30 30 8 20 x 20INDUSTRIAL
Lean mix
cm
TYPE OF
LOAD
Screed
thickness
cm
Rebar
diameter
mm
Overload
kg/m²
Pressure on
the soil
kg/cm²
Min. slab
thickness
cm
Pressure on
the scree
kg/cm²
Rebar
mesh
cm x cm
1,800 5
1.49
0.52
0.82
2.45
1.36
5.68
1,000
10
5 2.45 10 0.86
5
10
5
0
5
1.49
0
0
10
0
0
0
6
6
20 x 20
20 x 20
RESIDENTIAL
4
20 x 200.675,000 7 10 3.48 25 6
3.440 0
NEW ELEVETOR®
formwork
Concrete slab Lightweight screed Screed
Wooden support
panelist
PVC tube ø 125 mm
Base NEW ELEVETOR®
Gravel
Existing soil
Lean-mix
Foundation wall
Polystyrene panelist
Flooring
5
NEW ELEVETOR® / USE AND CHARACTERISTICS NEW ELEVETOR® / USE AND CHARACTERISTICS
Create ventilated foundations of any height
The formwork is treadable before pouring
High load-bearing capacity
It can be laid on the subgrade without lean mix
QUICK AND EASY SYSTEM
BASE NEW ELEVETOR® / ADVANTAGES AND CHARACTERISTICS
BASE NEW ELEVETOR®
IS AN ELEMENT IN RECYCLED POLYPROPYLENE (*) THAT GUARANTEES AN EASY
AND QUICK INSTALLATION OF THE PVC TUBES SUPPORTING THE ELEVETOR SYSTEM. INSTALLATION
IS PRECISE AND TUBES REMAIN PERFECTLY VERTICAL.
NEW ELEVETOR® FORMWORK / ADVANTAGES AND CHARACTERISTICS
58 cm
15 cm
58 cm
47 cm
8 cm
NEW ELEVETOR®
IS AN INNOVATIVE SYSTEM WITH DIMENSIONS 58X58 H15 CM THAT CREATES A
CRAWL SPACE AND ALLOW INSTALLATIONS UNDERNEATH REDUCING CONSIDERABLY CONCRETE
CONSUMPTION AND INSTALLATION TIME. THE CONCRETE CONSUMPTION FLUSH WITH THE TOP LAYER
IS 0.030 m³/m², WHILE THE AMOUNT OF CONCRETE NECESSARY TO FILL THE PILLARS IS 0.037 m³/m² PER
LINEAR METER OF HEIGHT.
NEW ELEVETOR® / HOW TO INSTALL
• Installation surface: cover the subgrade with lean mix to create an even surface for NEW ELEVETOR®.
Lean mix thickness to spec;
• Installation: place the NEW ELEVETOR® system made by GEOPLAST S.p.A., made by polypropylene
formwork size 58 x 58 x h15 cm, joined with tubes Ø 125 mm of length as by project specification, with
BASE NEW ELEVETOR® footing grid, assembled before the concrete pour:
1. Lay the BASE NEW ELEVETOR® footing grid (58 x 58 x h2.5 cm): it is recommended to place the parts from right
to left and from top to bottom.
2. Fit tubes into each cup of the footing grid. The tubes are cut to the length suitable to achieve the specified height of
NEW ELEVETOR® (from 70 to 200 cm).
3. Place the NEW ELEVETOR® FORMWORK (58 x 58 x h15): the operation is performed attaching the parts to the tubes
from the right-hand side to the left, and from top to bottom, always keeping the printed arrow upwards.
4. The Grid + Tube + Formwork assembly guarantees a perfect perpendicularity of the pillars within the foundation.
5. Place the specified rebar mesh over the surface of the NEW ELEVETOR® system (ref. to load table).
6. Place ø 8 mm reinforcement bars within the tubes that are part of the NEW ELEVETOR® system. These inserts must
be joined to the rebar mesh used to reinforce the slab, and should be long enough to reach the base of the tube.
7. Slab pour: use a Rck 250 kg/cm² concrete to fill the tubes and the formwork, cover the rebar mesh and reach the
designed slab thickness.
2sd
row
1st
row
2
1st
row
2sd
row
58 cm
58 cm
2.5 cm
3
(*)Recycled Polypropylene: Flexural modulus 1,100 N/mm2
- Tensile strength 35 N/mm2
- Coefficient of thermal expansion 0.15 mm/m/°C
2 3
4 5 6
7
1
4

Más contenido relacionado

La actualidad más candente

EP- August 2015.PDF
EP- August 2015.PDFEP- August 2015.PDF
EP- August 2015.PDFMoises Nava
 
IRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET Journal
 
Well abandonment process procedures
Well abandonment process proceduresWell abandonment process procedures
Well abandonment process proceduresDrilling Manual
 
D wall construction
D wall constructionD wall construction
D wall constructionanuragrikku
 
10 Well Abandonment Presentation Jan 29
10 Well Abandonment Presentation Jan 2910 Well Abandonment Presentation Jan 29
10 Well Abandonment Presentation Jan 29Will Butler, P.Eng
 
Norstar U Shaped Drains
Norstar U Shaped DrainsNorstar U Shaped Drains
Norstar U Shaped Drainsnorslides
 
Creation of low cost Housing
Creation of low cost HousingCreation of low cost Housing
Creation of low cost HousingNilanjana Pal
 
Speed Floor Melbourne Engineers Presentation & Techinicial Data
Speed Floor Melbourne Engineers Presentation & Techinicial DataSpeed Floor Melbourne Engineers Presentation & Techinicial Data
Speed Floor Melbourne Engineers Presentation & Techinicial Datadrk357111
 
Prefabricated panels
Prefabricated panelsPrefabricated panels
Prefabricated panelsMoldtech SL
 
MEKA K SERIES CONCRETE BATCHING PLANTS
MEKA K SERIES CONCRETE BATCHING PLANTSMEKA K SERIES CONCRETE BATCHING PLANTS
MEKA K SERIES CONCRETE BATCHING PLANTSMehmet Kaybal 🌿
 

La actualidad más candente (18)

EP- August 2015.PDF
EP- August 2015.PDFEP- August 2015.PDF
EP- August 2015.PDF
 
BUILDING PROJECT REPORT PPT.
BUILDING PROJECT REPORT PPT.BUILDING PROJECT REPORT PPT.
BUILDING PROJECT REPORT PPT.
 
Bena Brochure
Bena BrochureBena Brochure
Bena Brochure
 
IRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing Technique
 
Well abandonment process procedures
Well abandonment process proceduresWell abandonment process procedures
Well abandonment process procedures
 
D wall construction
D wall constructionD wall construction
D wall construction
 
Concrete Batching Plant
Concrete Batching PlantConcrete Batching Plant
Concrete Batching Plant
 
10 Well Abandonment Presentation Jan 29
10 Well Abandonment Presentation Jan 2910 Well Abandonment Presentation Jan 29
10 Well Abandonment Presentation Jan 29
 
Apc versawall
Apc versawallApc versawall
Apc versawall
 
Norstar U Shaped Drains
Norstar U Shaped DrainsNorstar U Shaped Drains
Norstar U Shaped Drains
 
Creation of low cost Housing
Creation of low cost HousingCreation of low cost Housing
Creation of low cost Housing
 
TPES OF CEMENTS
TPES OF CEMENTSTPES OF CEMENTS
TPES OF CEMENTS
 
Speed Floor Melbourne Engineers Presentation & Techinicial Data
Speed Floor Melbourne Engineers Presentation & Techinicial DataSpeed Floor Melbourne Engineers Presentation & Techinicial Data
Speed Floor Melbourne Engineers Presentation & Techinicial Data
 
Prefabricated panels
Prefabricated panelsPrefabricated panels
Prefabricated panels
 
Dishant ppt
Dishant pptDishant ppt
Dishant ppt
 
Specifications of concrete
Specifications of concreteSpecifications of concrete
Specifications of concrete
 
Install guttering
Install gutteringInstall guttering
Install guttering
 
MEKA K SERIES CONCRETE BATCHING PLANTS
MEKA K SERIES CONCRETE BATCHING PLANTSMEKA K SERIES CONCRETE BATCHING PLANTS
MEKA K SERIES CONCRETE BATCHING PLANTS
 

Similar a Elevetor COFRAJ PIERDUT PENTRU PARDOSELI SUSPENDATE

011 - Proposed Ground Floor plan
011 - Proposed Ground Floor plan011 - Proposed Ground Floor plan
011 - Proposed Ground Floor planDanny Chiverton
 
REINFORCED CONCRETE PRECAST TWIN WALLS
REINFORCED CONCRETE PRECAST TWIN WALLSREINFORCED CONCRETE PRECAST TWIN WALLS
REINFORCED CONCRETE PRECAST TWIN WALLSGuy Pomphrey
 
Water proofing in islamabad
Water proofing in islamabadWater proofing in islamabad
Water proofing in islamabadtayyab94
 
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURESUNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURESVenkateswaran S
 
EMSEAL BEJS durability statement- Lester Hensley
EMSEAL BEJS durability statement- Lester HensleyEMSEAL BEJS durability statement- Lester Hensley
EMSEAL BEJS durability statement- Lester HensleySeal EM
 
Base UFH Brochure 2016
Base UFH Brochure 2016Base UFH Brochure 2016
Base UFH Brochure 2016James Canny
 
Isokern Celsius stove system installation instructions
Isokern Celsius stove system installation instructionsIsokern Celsius stove system installation instructions
Isokern Celsius stove system installation instructionsSchiedel UK
 
Water supply, sanitation and rainwater harvesting
Water supply, sanitation and rainwater harvestingWater supply, sanitation and rainwater harvesting
Water supply, sanitation and rainwater harvestingAyushi Agrawal
 
Unitile Adjustable Pedestal .pdf
Unitile  Adjustable Pedestal .pdfUnitile  Adjustable Pedestal .pdf
Unitile Adjustable Pedestal .pdfHakimuddinGheewala
 
Unitile Adjustable Pedestal .pdf
Unitile  Adjustable Pedestal .pdfUnitile  Adjustable Pedestal .pdf
Unitile Adjustable Pedestal .pdfHakimuddinGheewala
 
Installation Instructions for CULTEC Stormwater Management Systems
Installation Instructions for CULTEC Stormwater Management SystemsInstallation Instructions for CULTEC Stormwater Management Systems
Installation Instructions for CULTEC Stormwater Management SystemsGina Carolan
 

Similar a Elevetor COFRAJ PIERDUT PENTRU PARDOSELI SUSPENDATE (20)

011 - Proposed Ground Floor plan
011 - Proposed Ground Floor plan011 - Proposed Ground Floor plan
011 - Proposed Ground Floor plan
 
Ertf
ErtfErtf
Ertf
 
REINFORCED CONCRETE PRECAST TWIN WALLS
REINFORCED CONCRETE PRECAST TWIN WALLSREINFORCED CONCRETE PRECAST TWIN WALLS
REINFORCED CONCRETE PRECAST TWIN WALLS
 
Permable paving
Permable pavingPermable paving
Permable paving
 
Water proofing in islamabad
Water proofing in islamabadWater proofing in islamabad
Water proofing in islamabad
 
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURESUNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
 
Aerocon bricks
Aerocon bricksAerocon bricks
Aerocon bricks
 
EMSEAL BEJS durability statement- Lester Hensley
EMSEAL BEJS durability statement- Lester HensleyEMSEAL BEJS durability statement- Lester Hensley
EMSEAL BEJS durability statement- Lester Hensley
 
Base UFH Brochure 2016
Base UFH Brochure 2016Base UFH Brochure 2016
Base UFH Brochure 2016
 
Isokern Celsius stove system installation instructions
Isokern Celsius stove system installation instructionsIsokern Celsius stove system installation instructions
Isokern Celsius stove system installation instructions
 
Water supply, sanitation and rainwater harvesting
Water supply, sanitation and rainwater harvestingWater supply, sanitation and rainwater harvesting
Water supply, sanitation and rainwater harvesting
 
Water proofing in buildings
Water proofing in buildingsWater proofing in buildings
Water proofing in buildings
 
Unitile Adjustable Pedestal .pdf
Unitile  Adjustable Pedestal .pdfUnitile  Adjustable Pedestal .pdf
Unitile Adjustable Pedestal .pdf
 
Unitile Adjustable Pedestal .pdf
Unitile  Adjustable Pedestal .pdfUnitile  Adjustable Pedestal .pdf
Unitile Adjustable Pedestal .pdf
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
 
Roof Waterproofing Karachi
Roof Waterproofing KarachiRoof Waterproofing Karachi
Roof Waterproofing Karachi
 
Installation Instructions for CULTEC Stormwater Management Systems
Installation Instructions for CULTEC Stormwater Management SystemsInstallation Instructions for CULTEC Stormwater Management Systems
Installation Instructions for CULTEC Stormwater Management Systems
 
Trulift presentation
Trulift presentationTrulift presentation
Trulift presentation
 
ALL WEATHER PEDESTAL
ALL WEATHER PEDESTALALL WEATHER PEDESTAL
ALL WEATHER PEDESTAL
 
DECK PEDESTAL
DECK PEDESTALDECK PEDESTAL
DECK PEDESTAL
 

Elevetor COFRAJ PIERDUT PENTRU PARDOSELI SUSPENDATE

  • 1. NEW ELEVETOR® TANK SYSTEM Example for an elevation of 2 meters: Requires: Base NEW ELEVETOR® + PVC tube dia. 125 mm 182.5 cm lenght + NEW ELEVETOR® H 15 Concrete consumption = (0.037 x 1.85) + 0.030 = 0.098 m³/m² Concrete consumption calculation: *Supply of the tubes ø 125 mm can be discussed at the time of order. The quantity of concrete to fill the pillars is equal to 0.037 m³/m² per meter height. NEW ELEVETOR® H=15 cm DATA DIMENSION cm 58 X 58 HEIGHT H 15 CONCRETE QUANTITY to fill the formwork - m3/m2 PALLET HEIGHT m No. OF UNITS/ PALLET QUANTITY m² 752252.50.030 **Place ø 8 mm reinforcement bars within the tubes that are part of the NEW ELEVETOR® system. These inserts must be joined to the rebar mesh used to reinforce the slab, and should be long enough to reach the base of the tube. 1 2 3 4 5 6 7 8 QUANTITY NEW ELEVETOR® formwork ø 125 mm tube* BASE NEW ELEVATOR® footing grid Installation of NEW ELEVETOR® system Rebar mesh ø 6 20x20 (cost of material and labour) Concrete class Rck 250 to fill the tubes (cost of material and labour) Concrete class Rck 250 to fill the formwork (material and labour) Concrete class Rck 250 for the floor slab thickness (material and labour) BILL OF MATERIAL UNIT/MEASURE PRICE TOTALAMOUNT Total cost €/m2 m2 No./m2 No./m2 hours/m2 kg/m2 m3/m2 m3/m2 m3/m2 2.328 0.05 3 3 1 No. [0,037 X (NEW ELEVETOR® system height in meters - 0,15)] + = [m³/m²]concrete consumption The concrete consumption for each square meter of ELEVETOR® is: REV.004 www.geoplast.it The formwork for ventilated foundations from 70 cm to 250 cm ST.11/2011 Disclaimer: the values shown in this brochure are for guidance only. They are not meant to be used for design criteria. Their use and reliance thereon for any purpose by anyone is entirely voluntary and at the sole risk of the user. GEOPLAST is not responsible for any loss, claim, or damage resulting from their use. NEW ELEVETOR® / PROJECT COST ANALYSISNEW ELEVETOR® / TYPICAL CALCULATION Stormwater management systems for both residential and industrial use can be made using NEW ELEVETOR® . Tanks can be built for temporary stormwater storage and attenuation, or permanent storage and reuse. The NEW ELEVETOR® system allows to build tanks of any shape and up to 2 meters depth without using cranes or heavy-lifting equipment. inite-element modelling for a plot of land 16.82 meters long and 7 meters deep, of which 6.30 m are soft clay and 0.70 m of compacted pozzolana and lapillo. The simulated structure was assumed to be made by a layer of lean mix 12 cm thickness, NEW ELEVETOR® system 95 cm height and a slab 5 cm thickness. F Fig 1) Maximum vertical tension in the clay layer with two concentrated loads of 3,500 kg at centres 2.32 m. Fig 2) Effect of four 3,500 kg loads in axis to the plate axis Plate Disp: DZ (cm) 0.0038 [Pt: 31443, Nd: 38983] -0.0043 -0.0205 -0.0366 -0.0528 -0.0690 -0.0852 -0.1014 -0.1175 -0.1337 -0.1499 -0.1580 [Pt: 31480, Nd:39019] Plate Stress: MC (kg/cm²) -0.0484 [Pt: 2106, Nd: 2447] -0.0613 -0.0869 -0.1125 -0.1382 -0.1638 -0.1895 -0.2151 -0.2408 -0.2664 -0.2921 -0.3049 [Pt: 730, Nd:1422] LOAD TABLE for NEW ELEVETOR® H=120 cm 0.8710,000 10 15 4.30 30 8 20 x 20INDUSTRIAL Lean mix cm TYPE OF LOAD Screed thickness cm Rebar diameter mm Overload kg/m² Pressure on the soil kg/cm² Min. slab thickness cm Pressure on the scree kg/cm² Rebar mesh cm x cm 1,800 5 1.49 0.52 0.82 2.45 1.36 5.68 1,000 10 5 2.45 10 0.86 5 10 5 0 5 1.49 0 0 10 0 0 0 6 6 20 x 20 20 x 20 RESIDENTIAL 4 20 x 200.675,000 7 10 3.48 25 6 3.440 0 NEW ELEVETOR® formwork Concrete slab Lightweight screed Screed Wooden support panelist PVC tube ø 125 mm Base NEW ELEVETOR® Gravel Existing soil Lean-mix Foundation wall Polystyrene panelist Flooring 5
  • 2. NEW ELEVETOR® / USE AND CHARACTERISTICS NEW ELEVETOR® / USE AND CHARACTERISTICS Create ventilated foundations of any height The formwork is treadable before pouring High load-bearing capacity It can be laid on the subgrade without lean mix QUICK AND EASY SYSTEM BASE NEW ELEVETOR® / ADVANTAGES AND CHARACTERISTICS BASE NEW ELEVETOR® IS AN ELEMENT IN RECYCLED POLYPROPYLENE (*) THAT GUARANTEES AN EASY AND QUICK INSTALLATION OF THE PVC TUBES SUPPORTING THE ELEVETOR SYSTEM. INSTALLATION IS PRECISE AND TUBES REMAIN PERFECTLY VERTICAL. NEW ELEVETOR® FORMWORK / ADVANTAGES AND CHARACTERISTICS 58 cm 15 cm 58 cm 47 cm 8 cm NEW ELEVETOR® IS AN INNOVATIVE SYSTEM WITH DIMENSIONS 58X58 H15 CM THAT CREATES A CRAWL SPACE AND ALLOW INSTALLATIONS UNDERNEATH REDUCING CONSIDERABLY CONCRETE CONSUMPTION AND INSTALLATION TIME. THE CONCRETE CONSUMPTION FLUSH WITH THE TOP LAYER IS 0.030 m³/m², WHILE THE AMOUNT OF CONCRETE NECESSARY TO FILL THE PILLARS IS 0.037 m³/m² PER LINEAR METER OF HEIGHT. NEW ELEVETOR® / HOW TO INSTALL • Installation surface: cover the subgrade with lean mix to create an even surface for NEW ELEVETOR®. Lean mix thickness to spec; • Installation: place the NEW ELEVETOR® system made by GEOPLAST S.p.A., made by polypropylene formwork size 58 x 58 x h15 cm, joined with tubes Ø 125 mm of length as by project specification, with BASE NEW ELEVETOR® footing grid, assembled before the concrete pour: 1. Lay the BASE NEW ELEVETOR® footing grid (58 x 58 x h2.5 cm): it is recommended to place the parts from right to left and from top to bottom. 2. Fit tubes into each cup of the footing grid. The tubes are cut to the length suitable to achieve the specified height of NEW ELEVETOR® (from 70 to 200 cm). 3. Place the NEW ELEVETOR® FORMWORK (58 x 58 x h15): the operation is performed attaching the parts to the tubes from the right-hand side to the left, and from top to bottom, always keeping the printed arrow upwards. 4. The Grid + Tube + Formwork assembly guarantees a perfect perpendicularity of the pillars within the foundation. 5. Place the specified rebar mesh over the surface of the NEW ELEVETOR® system (ref. to load table). 6. Place ø 8 mm reinforcement bars within the tubes that are part of the NEW ELEVETOR® system. These inserts must be joined to the rebar mesh used to reinforce the slab, and should be long enough to reach the base of the tube. 7. Slab pour: use a Rck 250 kg/cm² concrete to fill the tubes and the formwork, cover the rebar mesh and reach the designed slab thickness. 2sd row 1st row 2 1st row 2sd row 58 cm 58 cm 2.5 cm 3 (*)Recycled Polypropylene: Flexural modulus 1,100 N/mm2 - Tensile strength 35 N/mm2 - Coefficient of thermal expansion 0.15 mm/m/°C 2 3 4 5 6 7 1 4