SlideShare una empresa de Scribd logo
1 de 73
GUJARAT TECHNOLOGICAL
       UNIVERSITY



 SIR BHAVSINHJI POLYTECHNIC INSTITUTE
             BHAVNAGAR


DEPARTMENT OF FABRICATION TECHNOLOGY

                         L&T MHI TURBINE GENERATORS
PREPARED BY:
1. MILAN J. VISANI     (096490355031)
2.CHIRAG P. GOHIL      (096490355057)
3. BHUPENDRA SOLANKI   (096490355201)
4. CHHATRAPAL RANA     (096490355038)




                       L&T MHI TURBINE GENERATORS
MAJOR REPORT ON
GENERATOR STATOR FRAME
PROJECT NAME:           MAHAGENCO-3.
PART NAME:              STATOR FRAME.
DROWING NO:             A11M430
STAGE FOR PRODUCTION:   FABRICATION
MANUFACTURE:            L&T HAZIRA, SURAT
MATERIAL:               SS 400 JIS
                        IS 2062 gr A/B




                        L&T MHI TURBINE GENERATORS
L&T MHI TURBINE GENERATORS
Introduction
     To
Steam Turbine

          L&T MHI TURBINE GENERATORS
INDEX
  •Steam Turbine Basics
  • Main component/assemblies/ systems of steam turbine
  •Major Sources of Producing Electricity
  • Principles of Electricity generation
  •Working principal of steam turbine
  •Supercritical technology
  •Turbine by-pass system
  •Major Components used In Turbine
  •Shop weld plan
  •Test plan
  •Quality control plan
  •Bill of material
  •Stator frame model fabrication sequence procedure
  •Box plot plan of generator stator frame
  •Process planning sheet
  •Some specific terms used in WPS
  •WPS
  •Functions of generator stator frame



                                                          L&T MHI TURBINE GENERATORS
STEAM              TURBINE

            LP TURBINE




GENERATOR


                              HIP
                            TURBINE




                             L&T MHI TURBINE GENERATORS
STEAM         TURBINE
                               HP PEDESTAL
 CROSS OVER
    PIPE




                            RSV&ICV
                       (Reheat Stop Valve)
                       (Interceptor Valve)

       MSV&GV
   (Main Stop Valve)
   (Governing Valve)



                       L&T MHI TURBINE GENERATORS
HIP TURBINE
HIP OUTER CASING            HIP ROTOR
     (UPPER)




                     HIP OUTER CASING
                          (LOWER)



                   L&T MHI TURBINE GENERATORS
HIP TURBINE

GO TO LP TURBINE




                      MAIN STEAM INLET
                   REHEAT STEAM INLET
                             L&T MHI TURBINE GENERATORS
Generator Stator Assembly




               L&T MHI TURBINE GENERATORS
Electricity is the
key ingredient for the
development of a nation




    L&T MHI TURBINE GENERATORS
Hydro Power Plant                 Thermal Power Plant




Prime mover is Hydro Turbine
                                Prime mover is Steam Turbine
 Rotated by energy of flowing
                                Rotated by steam produced in
  Water supplied from Dam
                                 boiler by burning fossil fuels
         / reservoir


                                    L&T MHI TURBINE GENERATORS
Nuclear Power Station                   Gas based Power Station




Prime-mover is Steam Turbine rotated   Prime- mover is Gas Turbine run by
by steam produced in Steam Generator   air gas mixture ignited in combustion
by Nuclear fission in the reactor.     chamber
                                               L&T MHI TURBINE GENERATORS
World Power generation scenario

Thermal Power Plant are most popular way for producing
electricity on large scale and will remain major source of
power generation in foreseeable future due to relatively

          •Low capital cost
          •Shorter gestation time
          •Easy availability of fuel
          •Competitive generating cost
          •Reasonable high level of operating
          availability




                                        L&T MHI TURBINE GENERATORS
Power generation scenario in India


                 11
          3
                                                             Thermal
                                                             Hydro
                                                             Nuclear
    27                                           58          Gas
.




    Major share in installed capacity and planned in future is thermal




                                                 L&T MHI TURBINE GENERATORS
L&T MHI TURBINE GENERATORS
Thermal Power Plant




               L&T MHI TURBINE GENERATORS
Working Principal Of Steam Turbine




Nozzle           Plate



                         Force
                          ‘F’



                                                     F

CHANGE IN MOMENTUM = m x v – m x 0
                         =mxv
                                     L&T MHI TURBINE GENERATORS
Working Principal Of Steam Turbine




               V


                                                         Force ‘F’
                     -V




CHANGE IN MOMENTUM = (m x v) – (- m x v)
                          = 2 x (m x v)
              Force ‘F’ α 2 x (m x v)


                                           L&T MHI TURBINE GENERATORS
Working Principal Of Steam Turbine


                                 v       v sinθ
                                θ
                              v cosθ



                                                  F




-v cosθ             CHANGE IN MOMENTUM = (mvcosθ) – (- mvcos θ)
 θ -v
                                                  = 2 x (mvcos θ)
          -v sinθ

                                       Force ‘F’ α 2 (mvcos θ)
                                            L&T MHI TURBINE GENERATORS
WORKING PRINCIPLE OF STEAM TURBINE

                ROTATING    •Steam at high pressure & temperature is made to pass
                BLADE ROW   through a set of fixed blade mounted on stationary
                            body in Casing.

                            •There will be drop in pressure of the steam across the
                            fixed blade resulting to very high steam velocity at the
 FIXED
                            exit of fixed blade
 BLADE
 ROW                        •The high velocity steam then passes through another
                 DRIVING    row of blades mounted on the rotor shaft
STATIONARY       FORCE
BODY/CASING
                            •The impingement of high velocity steam generates
                            driving force on these rotating blades which rotate the
                            rotor.

                            • A set of fixed blades and rotating blades mounted on
                             rotor is called stage of turbine. Depending on steam
                             condition and power output, number of stages in
                             steam turbine is decided
                                                        L&T MHI TURBINE GENERATORS
              ROTOR
Main Components of Steam Turbine
                                      1   2   3             4   5   6      7




                             1
                                                        1




                                              8



1. Fixed/Guide Blades   5. Gland seals                          9. Governing System
2. Moving Blades        6. Bearing & bearing Pedestal           10.Lub. System
3. Casing               7. Coupling                             11.Drain system
4. Rotor                8. Stop & Control Valves                12. C&I System
                                                   L&T MHI TURBINE GENERATORS
Rotor is vital element involved in
conversion of kinetic energy of
steam into mechanical energy of
rotation.

Run at high speed depending upon
grid frequency (50Hz,60 Hz).

Subjected to sever stresses i.e.
Centrifugal forces, thermal




    L&T MHI TURBINE GENERATORS
Turbine By-Pass System




                 L&T MHI TURBINE GENERATORS
Generator stator
     frame



             L&T MHI TURBINE GENERATORS
SHOP WELD PLAN
   Welding engineering department issues shop weld plan to Planning,
    Shop floor where actual job is going on.

   The name self indicate that it is a welding plan of actual job – vessel and
    it guides to shop floor supervisor and welder that which WPS/PQR shall
    use for particular seam.

   Shop welding plan is related to the welding of the job. It provided all the
    information regarding weld seam to the welder, as he must well aware of
    all required conditions of the welding each seam.

   If company is working under ISO-9000. It has to keep all the activities to
    be documented Hence the required documents are made.


                                                L&T MHI TURBINE GENERATORS
   SWP gives the following information regarding the job as related they all seem
    to be welded.
    ◦ Seam numbers
    ◦ Base metal / P-Number
    ◦ Joint Detail
    ◦ Weld process
    ◦ Layer
    ◦ WPS No.
    ◦ PQR No.
    ◦ F - Number
    ◦ Pre heat temperature
    ◦ Inter pass temperature
    ◦ Position
    ◦ Customer
    ◦ Inspection agency
    ◦ Mfg. Code
    ◦ Post weld heat treatment
    ◦ Special notes.
                                                    L&T MHI TURBINE GENERATORS
TEST PLAN
   Welding engineering department issues test plan to planning, NDT, and
    shop floor for a particular job which is under production.

   In testing plan list of test for particular seam number is given with
    reference of ASME and customer specification and also given detail of
    production weld test coupon such as type of testing (destructive & Non-
    destructive), quantity thickness, For which seam no. required the PTC that
    is also described.

   After completion of welding of all seams particular test is carried out as per
    testing plan.

   With reference of Test plan the shop supervisor is offered the seam for
    testing to NDT department.

                                                  L&T MHI TURBINE GENERATORS
   The following manners are given in the test plan:
    • Seam wise stage no. and stage description. For testing.
    • Extent
    • Specification
    • Acceptance standard
    • Production Test Coupon
      o Seam No,
      o Thickness
      o NDT
      o Chem. Analysis.
      o Transverse tensile’
      o All weld tensile
      o Impact test
      o Micro/Macro test
    • Hardness
    • Inspection agencies
   Hydraulic/pneumatic/leak test and other tests TURBINE GENERATORS
                                              L&T MHI
QUALITY CONTROL PLAN
                                                         QUALITY CONTROL PLAN
Order: MODEL                              Drawing No.:                                                     Control No.: RJ/GEN/QAP-043
Part No: As per drawing                   Part Name: GENERATOR STATOR FRAME                                Dt. 10.06.211
QC Flow Chart           Type : Project Items              Project Name : Generator Stator Frame            Ref. Doc.: Nil
        Manufacturing                           Relevant
 Sr.                                                                                     L&T MHI
        and Inspection      Control Item     Document And     Frequency       Supplier           QC Sign    Quality Record         Remarks
 No.                                                                                       TG
           Process                             Procedure
                                                         T-Side Block Assy (A42B327)
1      Receiving         Mill Sheet Visual   Purchase         100%        W              R/W               Mill TC Material   All plates shall be
       inspection and    & Dimension         Specification As                                              identification     UT tested as
       material                              per drawing JV                                                record             mentioned in JV
       conformation                          Standard                                                                         std. &
                                                                                                                              identification (P.
                                                                                                                              No etc. must be
                                                                                                                              there)**
2      Fit-up &          Groove shape,       As per drawing   100%        W              W                 Fit Up Report      All line items as
       marking           Angle,                                                                                               per drawing no.
       inspection        Misalignment,                                                                                        A42B327 shall be
                         Cleaning (Groove                                                                                     inspected at this
                         Surface)                                                                                             stage.
3      Welding           Welder, Welding     ASME Sec. IX     100%        W              …                 …                  Welding spatters,
                         electrode,          A35G107 A-                                                                       under cut etc.
                         Preheating,         KOSHI-R04702                                                                     must not be there.
                         Current/voltage

4      PT test of        Flaw detection    A-SIKI-            100%        W              W                 PT Report          For PT, Solvent
       completed weld    method,           ROWB007                                                                            removal method
                         Situation of flaw                                                                                    shall be applied
                         detection surface

5      Dimensional &          Visual,        As per drawing   100%        W              W                 Dimensional
       visual               Dimension,                                                                     Report
       inspection             Surface
                            roughness                                                          L&T MHI TURBINE GENERATORS
E-Side Block Assy (A42B326)
6    Receiving        Mill Sheet Visual   Purchase        100%   W           R/W           Mill TC Material   All plates shall be
     inspection and   & Dimension         Specification                                    identification     UT tested as
     material                             As per                                           record             mentioned in JV
     conformation                         drawing JV                                                          std. &
                                          Standard                                                            identification (P.
                                                                                                              No etc. must be
                                                                                                              there)**


7    Fit-up &         Groove shape,       As per          100%   W           W             Fit Up Report      All line items as
     marking          Angle,              drawing                                                             per drawing no.
     inspection       Misalignment,                                                                           A42B327 shall be
                      Cleaning (Groove                                                                        inspected at this
                      Surface)                                                                                stage.


8    Welding          Welder, Welding     ASME Sec. IX    100%   W           …             …                  Welding spatters,
                      electrode,          A35G107 A-                                                          under cut etc.
                      Preheating,         KOSHI-                                                              must not be
                      Current/voltage     R04702                                                              there.


9    PT test of       Flaw detection      A-SIKI-         100%   W           W             PT Report          For PT, Solvent
     completed        method, Situation   ROWB007                                                             removal method
     weld             of flaw detection                                                                       shall be applied
                      surface



10   Dimensional &    Visual,             As per          100%   W           W             Dimensional
     visual           Dimension,          drawing                                          Report
     inspection       Surface
                      roughness



                                                                                 L&T MHI TURBINE GENERATORS
Centre Block Assy (A35F896)
11   Receiving        Mill Sheet Visual   Purchase        100%   W           R/W           Mill TC Material   All plates shall be
     inspection and   & Dimension         Specification                                    identification     UT tested as
     material                             As per                                           record             mentioned in JV
     conformation                         drawing JV                                                          std. &
                                          Standard                                                            identification (P.
                                                                                                              No etc. must be
                                                                                                              there)**


12   Fit-up &         Groove shape,       As per          100%   W           W             Fit Up Report      All line items as
     marking          Angle,              drawing                                                             per drawing no.
     inspection       Misalignment,                                                                           A42B327 shall be
                      Cleaning (Groove                                                                        inspected at this
                      Surface)                                                                                stage.

13   Welding          Welder, Welding     ASME Sec. IX    100%   W           …             …                  Welding spatters,
                      electrode,          A35G107 A-                                                          under cut etc.
                      Preheating,         KOSHI-                                                              must not be
                      Current/voltage     R04702                                                              there.

14   PT test of       Flaw detection      A-SIKI-         100%   W           W             PT Report          For PT, Solvent
     completed        method, Situation   ROWB007                                                             removal method
     weld             of flaw detection                                                                       shall be applied
                      surface

15   Dimensional &    Visual,             As per          100%   W           W             Dimensional
     visual           Dimension,          drawing                                          Report
     inspection       Surface
                      roughness




                                                                                 L&T MHI TURBINE GENERATORS
Frame Block Docking Assy (A35G121)
16   Receiving         Mill Sheet Visual &   Purchase         100%     W                R/W                Mill TC Material   All plates shall be
     inspection and    Dimension             Specification As                                              identification     UT tested as
     material                                per drawing JV                                                record             mentioned in JV
     conformation                            Standard                                                                         std. &
                                                                                                                              identification (P.
                                                                                                                              No etc. must be
                                                                                                                              there)**

17   Fit-up &          Groove shape,         As per drawing   100%     W                W                  Fit Up Report      All line items as
     marking           Angle,                                                                                                 per drawing no.
     inspection        Misalignment,                                                                                          A42B327 shall be
                       Cleaning (Groove                                                                                       inspected at this
                       Surface)                                                                                               stage.
18   Welding           Welder, Welding       ASME Sec. IX     100%     W                …                  …                  Welding spatters,
                       electrode,            A35G107 A-                                                                       under cut etc.
                       Preheating,           KOSHI-R04702                                                                     must not be there.
                       Current/voltage
19   PT test of        Flaw detection        A-SIKI-          100%     W                W                  PT Report          For PT, Solvent
     completed weld    method, Situation     ROWB007                                                                          removal method
                       of flaw detection                                                                                      shall be applied
                       surface
20   Final             Visual, Dimension,    As per drawing   100%     W                W                  Dimensional
     Dimensional &     Surface roughness                                                                   Report
     visual
     inspection
21   Surface coating   Type of coat,         As per drawing   100%     W                R                  Painting Report
     & painting        coating thickness     and
                                             Specification
                                                     Abbreviation :- W- Witness R- Review
                                  This quality control flow chart & QCL shall be revised as an when required.
               Prepared By                                       Checked By                                        Approved By

                                                                                            L&T MHI TURBINE GENERATORS
BILL OF MATERIAL
                                         BILL OF MATERIAL
                                 PROJECT NAME:- GENERATOR STATOR FRAME
                                                                          Unit     Total
Sr     Part                               THK in                Qty
                       Description                  Material             Weight    Weight   Remarks
No.    No.                                 mm                   unit
                                                                          (Kg)      (Kg)
1     001      Shell Plate               5         SS400P      4       11.50      46.00
2     002      Cooler Adapter            10        SS400P      2       4.8        9.50
3     003      Lead box                  10        SS400P      1       5.40       5.40
4     004      Frame Foot                10        SS400P      4       1.25       5.00
5     005      Frame Foot Support 1      8         SS400P      8       0.075      0.06
6     006      Frame Foot Support 2      8         SS400P      12      0.042      0.50
7     007      End Plate                 10        SS400P      2       2.5        5.00
8     008      Rib Plate                 10        SS400P      2       1.75       3.50
9     009      Flange                    10        SS400P      6       0..67      0.40
10    010      Trunion                   10        SS400P      4       0.25       1.00
11    011      Man hole                  10        SS400P      4       1.25       5.00
12    012      support                   10        SS400P      4       2.5        10.00
13    013      Bore Ring                 8         SS400P      6       0.083      2.50
14    014      Boring Support            10        SS400P      4       0.025      0.10
15    015      Lifting Lug               10        SS400P      4       0.0375     0.15
Total Weight                                                                      97.24


                                                                    L&T MHI TURBINE GENERATORS
STATOR FRAME MODELFABRICATION SEQUENCE
                 PROCEDURE

                        Stator Frame Model fabrication Sequence Procedure
 Sr.
                          Description                   Planned Date    Actual Date   Remarks
 No.
1      Material Selection                              5/3/2012        6/3/2012
2      Marking Of Shell                                6/3/2012        8/3/2012
3      Long Seam Marking                               7/3/2012        10/3/2012
4      Long Seam Welding On Shell                      7/3/2012        10/3/2012
5      Circ. Seam Marking                              8/3/2012        10/3/2012
6      Circ. Seam Welding On Shell                     8/3/2012        11/3/2012
7      Gas Cutting Of T-Side And E-Side                9/3/2012        12/3/2012
8      Grinding Of Cutting Parts                       10/3/2012       13/3/2012
9      Cnc Cutting Of E-Side And T-Side Parts          12/3/2012       153/2012
10     Grinding Of E-Side And T-Side Parts             13/3/2012       15/3/2012
11     Cnc Cutting Of Flanges, Manhole, Trunnion       14/3/2012       16/3/2012
12     Grinding Of Flanges, Manhole, Trunnion          14/3/2012       18/3/2012
13     Marking Of Bore Ring And Rib Plates             15/3/2012       19/3/2012
14     Cnc Cutting Of Bore Ring And Rib Plates         16/3/2012       20/3/2012
15     Grinding Of Bore Ring And Rib Plates            19/3/2012       21/3/2012

                                                            L&T MHI TURBINE GENERATORS
16   Set-Up And Assembly Of E-Block Parts     20/3/2012   22/3/2012
17   Welding Of E-Block Parts                 21/3/2012   23/3/2012
18   Set-Up And Assembly Of T-Block Parts     22/3/2012   24/3/2012
19   Welding Of T-Block Parts                 23/3/2012   24/3/2012
20   Full Welding Of E-Block With Shell       24/3/2012   24/3/2012
21   Full Welding Of T-Block With Shell       24/3/2012   27/3/2012
22   Marking Of outer Components On Shell     26/3/2012   27/3/2012
23   Gas Cutting Of Components                27/3/2012   28/3/2012
24   Assembly Of Bore Ring And Rib Plates     28/3/2012   28/3/2012
25   Horizontal Docking Of Structure          29/3/2012   29/3/2012
26   Tack Weld Of Structure                   29/3/2012   29/3/2012
27   Full Welding Of Structure With Shell     29/3/2012   30/3/2012
28   Fit-Up Of Outer Components               30/3/2012   30/3/2012
29   Welding Of Components                    31/3/2012   2/4/2012
30   Marking Of Frame Foot And Its Supports   31/3/2012   2/4/2012
31   Welding Of Frame Foot And Its Supports   31/3/2012   3/4/2012
32   End Plate Fit-Up                         2/4/2012    3/4/2012



                                                   L&T MHI TURBINE GENERATORS
33   End Plate Welding                  2/4/2012     4/4/2012
34   Visual Inspection                  2/4/2012     4/4/2012
35   Distortion Removal                 3/4/2012     4/4/2012
36   Dimension Checking                 4/4/2012     4/4/2012
37   Cleaning And Surface Preparation   4/4/2012     4/4/2012
38   Marking Of Supports                5/4/2012     5/4/2012
39   Leveling Of Stator Frame           5/4/2012     5/4/2012
40   Welding Of Supports                5/4/2012     5/4/2012
41   Visual Inspection                  5/4/2012     6/4/2012
42   Cleaning And Surface Preparation   5/4/2012     7/4/2012
43   Blasting                           6/4/2012     9/4/2012
44   Painting                           6/4/2012     10/4/2012
45   Final Inspection                   7/4/2012     11/4/2012
46   Packing                            9/4/2012     11/4/2012
47   Dispatch                           10/4/2012    12/4/2012




                                            L&T MHI TURBINE GENERATORS
BOX PLOT PLAN OF GENERATOR STATOR FRAME
                    Drawing        Material     CNC cutting of       Fit-up
   E-BLOCK
  Fabrication       7/3/2012      Selection      parts and         assembly
                                  8/3/2012        grinding         16/3/2012
                                                  14/3/2012
                                                                                                                         BOX PLOT PLAN OF
                                                                                                                           GENERATOR
   T-BLOCK                                                         Fit-up                                              STATOR FRAME MODEL
  Fabrication       Drawing        Material     CNC cutting
                                  Selection                      assembly
                    7/3/2012                    of parts and
                                  8/3/2012
                                                                 17/3/2012
                                                  grinding
                                                  14/3/2012
                                                                                                                      Full Welding of
                                                                 Gas cutting          Final Fit-up                     Outer Parts
   C-BLOCK                         Material                       of Shell,          of E and T-       Full Welding      28/3/2012          Support
  Fabrication        Drawing      Selection     Marking of                                              24/3/2012                          cutting and
                                                                 Grinding on             block
                     7/3/2012     8/3/2012       E and T         cutting part                                                               welding
                                                                                       18/3/2012
                                                block side        17/3/2012                                                                 7/4/2012
                                                12/3/2012


     Inner side                    Marking of                      Vertical
    Fabrication        Drawing      Borering     CNC cutting     Assembly of         Final Fit Of
  of Borering and      7/3/2012     and Rib      of Borering     Borering and           Parts
      Rib plate                       plate          and           Rib plate          18/3/2012                                           Blasting
                                    8/3/2012      Rib plate                                                                               9/4/2012
                                                  16/3/2012




Flanges/ manhole/                                    CNC
                                    Material                      Marking on
    trunnion          Drawing                     cutting of         shell            Fit-up on                                            Painting
                                   Selection
   Fabrication        7/3/2012                     external                                                                                9/4/2012
                                   8/3/2012                        21/3/2012             shell
                                                    items                             22/3/2012
                                                  16/3/2012



 Frame foot/End                     Material
                      Drawing      Selection      CNC cutting          Marking,          Fit-up                                             Packing
     plate
                      7/3/2012     8/3/2012       of external           Set-up          24/3/2012                                           10/4/2012
   Fabrication
                                                     items             22/3/2012
                                                   19/3/2012




                                                                                   FABRICATION HRS: 34 DAYS                             Dispatch
                                                                                    TOTAL WEIGHT: 97.24 KGS                             10/4/2012




                                                                                                     L&T MHI TURBINE GENERATORS
PROCESS PLANNING SHEET
         Process Planning Sheet                            PPS. No.      Methods Eng. ref.   Rev. No.     Page No.
                                                                         No.
                                                           FAB           0                   0            Total:
Client   Part Name                                         Rev. NO.      Drawing No.         Material     Facility

Projec Stator frame model                                  0                                 SS400        Nil
t
Order Process Description                                  Process No.   MHI/MELCO           Date         Estimated Time
No.                                                                      Reference No.
1       Fabrication.                                       01#           0                   24-Feb-10          34 days

Opn.     Process                                           IMAGES                            Target day   Remarks
No.
1        Documentation
         Fabrication Drawings                                                                        5    REF.OF ACTUAL
                                                                                                          DRG.
         Inspection record formats
2        Technical standards & work procedures

         WPS                                                                                         1
         QCL AND QAP                                                                                 1
3        MARKING OF SHELL
         Marking of Centre line of shell by using the                                                1
         divider and punch mark. LONG SEAM
         MARKING and CIRC. SEAM MARKING
4        Cutting & edge preparation
         Gas cut the of shell as per e-block and t-block                                             1
         dimensions
5        CNC CUTTING OF E-SIDE AND T-SIDE
         PARTS
         Cutting as per design requirement and grinding                                              2
         of all cut-out of parts after cutting.
                                                                                 L&T MHI TURBINE GENERATORS
6    CNC CUTTING OF FLANGES, MANHOLE, TRUNNION

     Cutting as per design requirement and grinding of all cut-out of parts after   2
     cutting.
7    MARKING OF BORE RING AND RIB PLATES
     Marking of the rib plate as per the design and cut-out the plate in CNC        2
     machine then grinding the all parts.

8    SET-UP AND ASSEMBLY OF E-BLOCK PARTS

     all cut-out parts are set-up properly and assemble the structure of E-block    2

9    WELDING OF E-BLOCK PARTS
     All parts in joint by the GTAW process as per the welding design

10   SET-UP AND ASSEMBLY OF T-BLOCK PARTS                                           3

     All cut-out parts are set-up properly and assemble the structure of T-block

11   WELDING OF E-BLOCK PARTS
     All parts is joint by the GTAW process as per the welding design               1

12   FULL WELDING OF E-BLOCK WITH SHELL
     The E-block structure is welded with shell by using GMAW process.              1

13   FULL WELDING OF T-BLOCK WITH SHELL
     The T-block structure is welded with shell by using GMAW process.              1

14   FIT-UP OF OUTER COMPONENTS
     Fit-Up THE FLANGES, MANHOLE, TRUNNIONS IN THE OUTER SIDE OF                   1
     SHELL
15   WELDING OF COMPONENTS
     Full welding of components by using GTAW process.                             1
                                                                 L&T MHI TURBINE GENERATORS
16   MARKING OF FRAME FOOT AND ITS
     SUPPORTS
     MARKING OF FRAME FOOT AND ITS SUPPORTS                           1
     ON THE SHELL
17   WELDING OF FRAME FOOT AND ITS
     SUPPORTS
     All cut-out parts of frame foot and supports                     1
     welded by GMAW welding process.
18   END PLATE FIT-UP AND WELDING
     Leveling of shell and end plate with respect of                  1
     design and full welded
19   VISUAL INSPECTION
     After all welding complete visual check                          1
     inspection
20   DISTORTION REMOVAL
     Remove all NDT points by grinding and chipping                   1
     hammer.
21   MARKING OF SUPPORTS
     LEVELLING OF STATOR FRAME
     Marking and leveling of supports then full
     welding
22   CLEANING AND SURFACE PREPARATION
     CLEANING AND SURFACE PREPARATION OF ALL                          1
     WELDED PARTS AND COMPLETE SHELL.
23   BLASTING
     BLASTING USING SMALL PRESSURE APPLIED                            1
24   PAINTING
     PAINTING OUTER AND INNER SIDE                                    1
     BYMANUALLY.
25   DISPATCH                                                         1
26   PACKING                                                          1
                                                       L&T MHI TURBINE GENERATORS
SOME SPECIFIC TERMS USED IN WPS
Welding Variables
  ◦ Essential variables.
  ◦ Supplementary essential variable.
  ◦ Non-essential variables.

P – Numbers:
  ◦ To reduce the number of welding procedure qualification required, base
    metals have been assigned P – Numbers.

F – Numbers:
  ◦ F Numbers are used for filler metal designation and grouping of electrodes &
    welding rods.
  ◦ It is based essentially on their usability characteristics.

A – Numbers:
  ◦ A – Numbers are used to identify the weld metal chemical composition of
    ferrous metals.
                                                    L&T MHI TURBINE GENERATORS
CONT…

  Joints
    • The WPS describe some variable like groove design ,backing etc.,

  Base Metals
    • It is essential variables for all welding processes.
    • A change in a base metal thickness beyond the range qualified in
      table (As per qw-4541) requires the requalification of WPS.

  Filler Metal
     • Filler metal should be selected which is compatible to base metal
       chemical composition (Sec.II_A/B). They must have same/similar
       chemical composition.
     • For filler metal chemical composition, we have the refer ASME SEC-II
       C.


                                             L&T MHI TURBINE GENERATORS
CONT…

 Position
   • Position is supplementary essential variable.
   • 1G, 2G, 3G, etc., are different types of welding positions (as per QW-461
      Sec IX)

 Preheat
   • It can be determine from ASME SEC VIII, Division – 1, Appendix – R.

 PWHT
   • ASME SEC – VIII, DIV- I, Per. UCS-56 describes PWHT temperature and
     time range for specific material with respect to P – Number.




                                              L&T MHI TURBINE GENERATORS
CONT…

  Gases
    • Three types of gases are described in WPS.
      o Shielding gas.
      o Backing gas.
    • Trailing gas

  Electrical Characteristics
     • ELECTRICAL CHARACTERISTICS (QW – 409)
     • We have to write Current, Polarity, and Voltage as electrical
       characteristics.

  Technique
    • It is determined manually with respect to joint design, material type
      material thickness etc
                                               L&T MHI TURBINE GENERATORS
WPS
                      QW-482 WELDING PROCEDURE QUALIFICATION (WPS)

                                                          Supporting
WPS NO: 1                              DATE: 12-3-2012                       -
                                                          PQR No(s)

                                                          Welding
Revision:                              RO                                    SMAW
                                                          Process
Date:                                  12-3-2012          Type               MANUAL
JOINTS (QW-402)
Groove Design                                             As per Drg.
Backing: (Yes/No)                                         Yes
Backing Material (type)                                   Base metal/Weld metal
Other                                                     -
BASE METALS (QW-403)
                                       MATERIAL 1                            MATERIAL 2

P. No.                                 1               P. No.                1

Group No.                              1               Group No.             1


Specification/Grade                    -               Specification/Grade   -


Thickness Range: (mm):5 to 200 mm

Base Metal: ss-400                     Groove: all                     Fillet ANY


Deposited weld thickness: 200 mm MAX   SMAW               6            Fillet ANY

Other:                                 13 mm maximum weld deposition in single pass
                                                                 L&T MHI TURBINE GENERATORS
FILLER METALS(QW-404)
Process                      SMAW
F. No.                       4
A. No.                       1
                             SFA
Spec No.
                             5.1

AWS No. (class)              E 7018

                             Φ 2.5,
Size of filler metals (mm)   3.15,
                             4,
Electrode Flux (class)       NA
Flux Trade name              NA
Consumable Insert            NA
Chemical composition         NA
Other                        NA
POSITIONS (QW-405)
Process(es):                 SMAW
Position of Groove:          ALL              F-Flat
Welding Progression:         uphill
Position of Fillet:          ALL              H-Horizontal

                                              V-Vertical
Other                        None
                                              O-Overhead


PREHEAT (QW-406)
Preheat Temp. (Min):ºC       150 ºC
Interpass Temp. (Max):ºC     350 ºC
Preheat Maintenance:         During Welding
                                                  L&T MHI TURBINE GENERATORS
Other                        NA
POST WELD HEAT TREATMENT (QW-407)   ELECTRICAL CHARACTERISTICS(QW-409)
Type of PWHT                        Current(AC or Dc)                     DC
TEMP. Range: ºC                     Polarity (EN or EP)                   EP
                                    Amps (Range)                          70-155 A
Soaking/Holding Time
                                    Voltage (Range)                       20-30 V

Rate of Heating                     Tungsten Type & Size                  NA


Rate of Cooling                     Mode of Metal Transfer                NA

                                                                          NA
Others:                             Electrode wire feed
GASES (QW-408)
                                                                          Flow
                                    % Composition
                                                                          Rate(LPM)
Shielding Gas                       NA                                    NA
Backing/Purging Gas                 NA                                    NA
Trailing Gas                        NA                                    NA
Other                               NA                                    NA
TECHNIQUE (QW-410)
String/Weave Bead                   Gas Cup Size                          NA
Travel Speed (range)                Cont. Tube Work Dist.                 NA

Multiple/Single Electrode           Multi/Single Pass (per side)          Multi Pass
Oscillation                         NA
Closed to out chamber               NA
Cleaning                            By wire brush
Method of Gouging/Back chip         By grinding
Other                               NA
                                                            L&T MHI TURBINE GENERATORS
Filler Metal           Current
                                                                                          Max     Min
                                      Flux                                 Travel Speed
Weld                            Dia                                Volt                   heat    Bead
             Process                  Trade                                Range
                                              Type &     Amp.      Range                  input
Layer                  Class    (mm Name                                                          Length
                                              Polarity   Range             (mm/min)
                                )                                                         (KJ/mm) (mm)


                                2.5   NA      DCEP       70-90     20-30   -              -       -
  ALL PASS




                       E-7018 3.15    NA      DCEP       100-140   20-30   -              -       -
             SMAW
                                4     NA      DCEP       155-190   20-30   -              -       -




                                                                   L&T MHI TURBINE GENERATORS
QW-482 WELDING PROCEDURE SPECIFICATION (WPS)
                                              Supporting PQR
WPS NO: 3                  DATE: 12-3-2012                          -
                                              No(s)



Revision:                  RO                 Welding Process       GMAW

Date:                      12/3/2012          Type                  Machine
JOINTS (QW-402)
Groove Design                                 As per Drg.
Backing: (Yes/No)                             with and without
Backing Material (type)                       Base metal/Weld metal
Other                                         -
BASE METALS (QW-403)
                           MATERIAL 1                                         MATERIAL 2
P. No.                     1                  P. No.                          1

Group No.                  1                  Group No.                       1



Specification/Grade        SS-400             Specification/Grade             SS-400


Thickness Range: (mm)
                                5mm to 200
Base Metal:                Groove                Fillet                        ANY
                                mm
                                5 mm to 200
Deposited weld thickness   GMAW                  Fillet                        ANY
                                mm
Other:                     None

                                                          L&T MHI TURBINE GENERATORS
FILLER METALS(QW-404)
Process                      GMAW

F. No.                       6

A. No.                       1

Spec No.                     5.28

AWS No. (class)              ER 70S 6

Size of filler metals (mm)   Φ 1.6

Electrode Flux (class)       Na

Flux Trade name              NA
Consumable Insert            NA
Chemical composition         NA
Other                        NA
POSITIONS (QW-405)
Process(es):                 GMAW
Position of Groove:          all
                                                           F-Flat
Welding Progression:         NA
Position of Fillet:          F,H,V,O                       H-Horizontal

                                                           V-Vertical
Other                        None
                                                           O-Overhead
PREHEAT (QW-406)
Preheat Temp. (Min):ºC       150*
Interpass Temp. (Max):ºC     350*
Preheat Maintenance:         During welding
Other                        NA
                                              L&T MHI TURBINE GENERATORS
Prepared By                  Reviewed By                   Approved By
WPS No:

POST WELD HEAT TREATMENT (QW-407)        ELECTRICAL CHARACTERISTICS(QW-409)

Type of PWHT         -                   Current(AC or Dc)                        DC
TEMP. Range: ºC      -                   Polarity (EN or EP)                      EP
                     -                   Amps (Range)                             -
Soaking/Holding Time
                     -                   Voltage (Range)                          -
Rate of Heating      -                   Tungsten Type & Size                     NA
Rate of Cooling      -                   Mode of Metal Transfer                   SPRAY
                     -                                                            NA
Others:                                  Electrode wire feed
                     -
GASES (QW-408)

                                    Gas            % Composition     Flow Rate(LPM)

Shielding Gas                       Ar-Co2         80% to 20%        14 to 24
Backing/Purging Gas                 NA             NA                NA
Trailing Gas                        NA             NA                NA
Other                               NA             NA                NA
TECHNIQUE (QW-410)
String/Weave Bead                   String         Gas Cup Size      NA

                                    30-200         Cont. Tube Work
Travel Speed (range)                                               15-22mm
                                    mm/min         Dist.

                                                   Multi/Single
Multiple/Single Electrode           Single                           Multi pass
                                                   Pass (per side)

Oscillation                         None
Closed to out chamber               None
Cleaning                            With wire brush
Method of Gouging/Back chip         -
Other                               -                          L&T MHI TURBINE GENERATORS
V
                  Filler Metal             Current               o                                 Min
                                   Flux                          lt    Travel Speed   Max
Weld                                                             R                                 Bead
        Process                    Trade                               Range          heat input
Layer                       Dia                                  a                                 Length
                                   Name    Type &     Amp.             (mm/min)
                  Class                                          n                    (KJ/mm)
                            (mm)           Polarity   Range
                                                                 g                                 (mm)
                                                                 e
                                                                 1
                                                                 8
                  ER 70S                                               30-
-       GMAW                1.6    -       DCEP       180-280    -                    -
                  6                                                    200mm/min
                                                                 3
                                                                 0

Prepared by                        Reviewed by                        Approved by




                                                              L&T MHI TURBINE GENERATORS
QW-482 WELDING PROCEDURE SPECIFICATION (WPS)111
                                         DATE: 12-3-      Supporting PQR
WPS NO: 5                                                                   -
                                         2012             No(s)
Revision                                 RO               Welding Process   GTAW
Date                                     12-3-2012        Type              Manual
JOINTS (QW-402)
Groove Design                            As per Drg.
Backing: (Yes/No)                        No
Backing Material (type)                  NA
Other                                    -
BASE METALS (QW-403)

                                     MATERIAL 1                             MATERIAL 2

P. No.                               4                  P. No.              4


Group No.                            1,2                Group No.           1,2



Specification/Grade                  -                  Specification/Grade -


Thickness Range: (mm)

Base Metal:                 Groove              (5-200mm) Fillet            ANY


Deposited weld thickness    GTAW                (5-200mm) Fillet            ANY

Other:                      None
                                                       L&T MHI TURBINE GENERATORS
FILLER METALS(QW-404)
Process                      GTAW
F. No.                       6
A. No.                       1
Spec No.                     5.18
AWS No. (class)              ER 70S-2
Size of filler metals (mm)   Φ 1.6, 2.4
Electrode Flux (class)       NA
Flux Trade name              NA
Consumable Insert            NA
Chemical composition         NA
Other                        NA
POSITIONS (QW-405)
Process(es):                 GTAW
                                               F-Flat
Position of Groove:          ALL
Welding Progression:         Uphill            H-Horizontal
Position of Fillet:          ALL
                                               V-Vertical

Other                        None              O-Overhead




                                      L&T MHI TURBINE GENERATORS
PREHEAT (QW-406)
Preheat Temp. (Min):ºC               -
Interpass Temp. (Max):ºC             -
Preheat Maintenance:                 -
Other                                -
WPS No:
POST WELD HEAT TREATMENT (QW-407)    ELECTRICAL CHARACTERISTICS(QW-409)
Type of PWHT                 -       Current(AC or Dc)                     DC

TEMP. Range: ºC              -       Polarity (EN or EP)                   EN

                             -       Amps (Range)                          -
Soaking/Holding Time
                             -       Voltage (Range)                       -

Rate of Heating              -       Tungsten Type & Size                  EWTh-2

Rate of Cooling              -       Mode of Metal Transfer                NA

Other                        -       Electrode wire feed                   NA

GASES (QW-408)-

                             Gas         % Composition                         Flow Rate(LPM)

Shielding Gas                Argon       99.995%                               8-12
Backing/Purging Gas          NA          NA                                    NA
Trailing Gas                 NA          NA                                    NA
Other                        NA          NA                                    NA

                                                              L&T MHI TURBINE GENERATORS
TECHNIQUE (QW-410)
String/Weave Bead                  String                  Gas Cup Size             Φ 6.0-10.0mm dia
Travel Speed (range)               NA                      Cont. Tube Work Dist.    NA
                                                           Multi/Single Pass (per
Multiple/Single Electrode          Single                                           Multi Pass
                                                           side)
Oscillation                     None
Closed to out chamber           None
Cleaning                        With wire brush
Method of Gouging/Back chip     By grinding
Other                           -
                    Filler Metal            Current
                                      Flux                                      Travel   Max     Min
                                      Trad                                      Speed    heat
Weld                                                                    Volt                     Bead
         Process              Dia     e     Type &           Amp.               Range    input
Layer                Class                                              Range                 Length
                              (mm)          Nam Polarity     Range              (mm/mi (KJ/mm
                                            e                                   n)     )      (mm)



Root     GTAW        ER 80S-G 2.4,2.5 NA         DCEN        80-120     10-18 -          -       -



Rest     GTAW        ER 80S-G 2.4,2.5 NA         DCEN        110-180    10-18 -          -       -


All      SMAW        -        -             NA -             -          -       -        -       -
All      SMAW        -        -             NA -             -          -       -        -       -
Prepared by                                 Reviewed by                         Approved by

                                                                     L&T MHI TURBINE GENERATORS
FUNCTION OF GENERATOR STATOR FRAME




                      L&T MHI TURBINE GENERATORS
PARTS OF GENERATOR STATOR FRAME




                    L&T MHI TURBINE GENERATORS
PARTS OF GENERATOR STATOR FRAME




                    L&T MHI TURBINE GENERATORS
BORE RING
  • bore ring is mainly use for the supporting the core bolt and
    balancing the rotor All fabrication process complete after send to
    assembly shop.

     Clamping
    arrangement


                                                               Outer ring

                              Inner ring




                                           L&T MHI TURBINE GENERATORS
After Leveling & centering of bore ring do tack weld elastic plate to bottom Frame plate.

Then place new Frame Plate Above it. Do leveling & centering of same frame plate. Do tack weld
it with elastic plate below it. Additional temporary support can also be utilize.

Then place next `Bore ring + Elastic Plate` and repeat the above process.

And so on complete the Centre block assembly fit-up.          L&T MHI TURBINE GENERATORS
FRAME FOOT
  • Frame foot is use for the foundation of the generator.




                                           L&T MHI TURBINE GENERATORS
LEAD BOX
  • Lead box mainly use the Supply the lead outside inside




                                          L&T MHI TURBINE GENERATORS
PROCESS
   Marking frame plate
   Setting end plate (T side)
   Mounting ribs of T side block (1st set)
   Mounting frame plate of T side block
   Mounting ribs of T side block (2nd set)
   Mounting 1st frame plate of center block
   Partial welding ribs of T side block (1st set)
   Mounting shell plate of T side block
   Gas cutting hole for lead box adapter
   Mounting of 1st bore ring




                                                L&T MHI TURBINE GENERATORS
CONT…

     Mounting of 2nd frame plate of center block
     Welding inside frame
     Cleaning welding portion, Painting of angle, pipe and flexible beam
      support
     Mounting shell plate of center block
     Welding shell plate center block
     Mounting lead box adapter
     Welding lead box adapter




                                               L&T MHI TURBINE GENERATORS
TRUNNION
  • Lifting the generator




                            L&T MHI TURBINE GENERATORS
COOLER ADAPTER
  • Cooler adapter is mainly use to cooling the steam.




                                         L&T MHI TURBINE GENERATORS
PROCESS
   Marking frame plate
   Setting end plate (E side)
   Mounting ribs of E side block (1st set)
   Mounting frame plate of E side block
   Mounting shell plate of E side block
   Mounting ribs of E side block (1st set)
   Gas cutting hole for cooler adapter
   Welding inside frame in flat position
   Turnover
   Welding inside frame in flat position




                                              L&T MHI TURBINE GENERATORS
L&T MHI TURBINE GENERATORS
L&T MHI TURBINE GENERATORS

Más contenido relacionado

La actualidad más candente (20)

Steam turbine power plant
Steam turbine power plantSteam turbine power plant
Steam turbine power plant
 
Steam Turbine modelling
Steam Turbine modellingSteam Turbine modelling
Steam Turbine modelling
 
Steam turbine and its types
Steam turbine and its typesSteam turbine and its types
Steam turbine and its types
 
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSESSTUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
 
Steamturbines part1
Steamturbines part1Steamturbines part1
Steamturbines part1
 
STEAM TURBINES AND ITS GOVERNINGS
STEAM TURBINES AND ITS GOVERNINGSSTEAM TURBINES AND ITS GOVERNINGS
STEAM TURBINES AND ITS GOVERNINGS
 
Steam turbine ntpc seepat bilaspur chhattisgarh
Steam turbine ntpc seepat bilaspur chhattisgarhSteam turbine ntpc seepat bilaspur chhattisgarh
Steam turbine ntpc seepat bilaspur chhattisgarh
 
Steam turbines
Steam turbinesSteam turbines
Steam turbines
 
A Report on Steam Turbine
A Report on Steam TurbineA Report on Steam Turbine
A Report on Steam Turbine
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
BASIC PARTS OF STEAM TURBINE
BASIC PARTS OF STEAM TURBINEBASIC PARTS OF STEAM TURBINE
BASIC PARTS OF STEAM TURBINE
 
Turbo generator & its auxiliaries
Turbo generator & its auxiliariesTurbo generator & its auxiliaries
Turbo generator & its auxiliaries
 
P2 Steam Turbine Evolution
P2 Steam Turbine EvolutionP2 Steam Turbine Evolution
P2 Steam Turbine Evolution
 
Steam turbine & it's classification
Steam turbine & it's classificationSteam turbine & it's classification
Steam turbine & it's classification
 
Steam Turbine
Steam TurbineSteam Turbine
Steam Turbine
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
Steam turbines
Steam turbinesSteam turbines
Steam turbines
 
ME 6404 THERMAL ENGINEERING UNIT III
ME 6404 THERMAL ENGINEERING UNIT IIIME 6404 THERMAL ENGINEERING UNIT III
ME 6404 THERMAL ENGINEERING UNIT III
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 

Destacado

Process Planning
Process PlanningProcess Planning
Process PlanningGuhan M
 
Bureau Veritas Construction
Bureau Veritas ConstructionBureau Veritas Construction
Bureau Veritas Constructionajaikartik
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality ManagementSerdar Temiz
 
Duplex welding guidelines
Duplex welding guidelinesDuplex welding guidelines
Duplex welding guidelinesLalu Rajendran
 
E2M - Full 3D Black Box Navigation Application for Android
E2M - Full 3D Black Box Navigation Application for AndroidE2M - Full 3D Black Box Navigation Application for Android
E2M - Full 3D Black Box Navigation Application for AndroidTerry Kim
 
Formato hv foto sena copia2 sammymar
Formato hv foto sena   copia2 sammymarFormato hv foto sena   copia2 sammymar
Formato hv foto sena copia2 sammymarAndreita Gomez
 
50 Highlights der 37. Auktion am 18. April 2015 - 50 Highlights of Scripophil...
50 Highlights der 37. Auktion am 18. April 2015 - 50 Highlights of Scripophil...50 Highlights der 37. Auktion am 18. April 2015 - 50 Highlights of Scripophil...
50 Highlights der 37. Auktion am 18. April 2015 - 50 Highlights of Scripophil...Matthias Schmitt
 
Haris Hamza- Resume
Haris Hamza- ResumeHaris Hamza- Resume
Haris Hamza- ResumeHaris Hamza
 
InstantFiler oct 2010
InstantFiler oct 2010InstantFiler oct 2010
InstantFiler oct 2010Uniport Ltd.
 
A Gremlin ate my graph
A Gremlin ate my graphA Gremlin ate my graph
A Gremlin ate my graphDamien Seguy
 
Ort business breakfast mailer deloitte final
Ort business breakfast mailer deloitte finalOrt business breakfast mailer deloitte final
Ort business breakfast mailer deloitte finalekagan
 
REGIONE VENETO - Turismo flash - Febbraio 2011
REGIONE VENETO - Turismo flash - Febbraio 2011REGIONE VENETO - Turismo flash - Febbraio 2011
REGIONE VENETO - Turismo flash - Febbraio 2011BTO Educational
 
CLASE 5 Gruposde google
CLASE 5 Gruposde googleCLASE 5 Gruposde google
CLASE 5 Gruposde googlejemalaga
 

Destacado (20)

Process Planning
Process PlanningProcess Planning
Process Planning
 
Bureau Veritas Construction
Bureau Veritas ConstructionBureau Veritas Construction
Bureau Veritas Construction
 
ALTERNATOR DESIGN
ALTERNATOR DESIGNALTERNATOR DESIGN
ALTERNATOR DESIGN
 
BHEL Trainning Report
BHEL Trainning ReportBHEL Trainning Report
BHEL Trainning Report
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality Management
 
Design of Quality Plan
Design of Quality PlanDesign of Quality Plan
Design of Quality Plan
 
Duplex welding guidelines
Duplex welding guidelinesDuplex welding guidelines
Duplex welding guidelines
 
E2M - Full 3D Black Box Navigation Application for Android
E2M - Full 3D Black Box Navigation Application for AndroidE2M - Full 3D Black Box Navigation Application for Android
E2M - Full 3D Black Box Navigation Application for Android
 
Gbpa porcina
Gbpa porcinaGbpa porcina
Gbpa porcina
 
Formato hv foto sena copia2 sammymar
Formato hv foto sena   copia2 sammymarFormato hv foto sena   copia2 sammymar
Formato hv foto sena copia2 sammymar
 
50 Highlights der 37. Auktion am 18. April 2015 - 50 Highlights of Scripophil...
50 Highlights der 37. Auktion am 18. April 2015 - 50 Highlights of Scripophil...50 Highlights der 37. Auktion am 18. April 2015 - 50 Highlights of Scripophil...
50 Highlights der 37. Auktion am 18. April 2015 - 50 Highlights of Scripophil...
 
Cumple de luis
Cumple de luisCumple de luis
Cumple de luis
 
Haris Hamza- Resume
Haris Hamza- ResumeHaris Hamza- Resume
Haris Hamza- Resume
 
5 cuento fran
5 cuento fran5 cuento fran
5 cuento fran
 
InstantFiler oct 2010
InstantFiler oct 2010InstantFiler oct 2010
InstantFiler oct 2010
 
A Gremlin ate my graph
A Gremlin ate my graphA Gremlin ate my graph
A Gremlin ate my graph
 
Cuidadores Clase Lorena Javet
Cuidadores Clase Lorena JavetCuidadores Clase Lorena Javet
Cuidadores Clase Lorena Javet
 
Ort business breakfast mailer deloitte final
Ort business breakfast mailer deloitte finalOrt business breakfast mailer deloitte final
Ort business breakfast mailer deloitte final
 
REGIONE VENETO - Turismo flash - Febbraio 2011
REGIONE VENETO - Turismo flash - Febbraio 2011REGIONE VENETO - Turismo flash - Febbraio 2011
REGIONE VENETO - Turismo flash - Febbraio 2011
 
CLASE 5 Gruposde google
CLASE 5 Gruposde googleCLASE 5 Gruposde google
CLASE 5 Gruposde google
 

Similar a foram

ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESHppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESHAKHILESH KUMAR
 
Kota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathurKota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathurAbhishek Mathur
 
bhel haridwr training ppt k-10655
bhel haridwr training ppt k-10655bhel haridwr training ppt k-10655
bhel haridwr training ppt k-10655Hariom Rathore
 
THERMAL POWER PLANT PARALI
THERMAL POWER PLANT PARALITHERMAL POWER PLANT PARALI
THERMAL POWER PLANT PARALIMahendra Magre
 
NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportAditya Shekhar
 
NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportAditya Shekhar
 
kstps summer training 36 slides
 kstps summer training 36 slides kstps summer training 36 slides
kstps summer training 36 slidesDanveer Singh
 
Ntpc kahalgaon project by bhanu kishan
Ntpc kahalgaon project by bhanu kishanNtpc kahalgaon project by bhanu kishan
Ntpc kahalgaon project by bhanu kishanBHANUKISHAN1
 
Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Abhijeet Thakur
 
Industrial training ppt bhel bhopal
Industrial training ppt bhel bhopalIndustrial training ppt bhel bhopal
Industrial training ppt bhel bhopalPRAVEENKUMARSINGH87
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC KantiTarun Kumar
 
Ntpc badarpur summer training
Ntpc badarpur summer trainingNtpc badarpur summer training
Ntpc badarpur summer trainingAnubhav Ghosh
 
Mini project presentation
Mini project presentation   Mini project presentation
Mini project presentation CHharsha
 
Ranjan NTPC KAHALGAON ppt
Ranjan  NTPC KAHALGAON pptRanjan  NTPC KAHALGAON ppt
Ranjan NTPC KAHALGAON pptRanjan kumar
 

Similar a foram (20)

Pintu raj
Pintu rajPintu raj
Pintu raj
 
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESHppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
 
Kota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathurKota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathur
 
A Project Report
A Project ReportA Project Report
A Project Report
 
bhel haridwr training ppt k-10655
bhel haridwr training ppt k-10655bhel haridwr training ppt k-10655
bhel haridwr training ppt k-10655
 
Hydal power plant
Hydal power plantHydal power plant
Hydal power plant
 
THERMAL POWER PLANT PARALI
THERMAL POWER PLANT PARALITHERMAL POWER PLANT PARALI
THERMAL POWER PLANT PARALI
 
NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training Report
 
NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training Report
 
Saba Power Plant
Saba Power Plant Saba Power Plant
Saba Power Plant
 
kstps summer training 36 slides
 kstps summer training 36 slides kstps summer training 36 slides
kstps summer training 36 slides
 
Ntpc kahalgaon project by bhanu kishan
Ntpc kahalgaon project by bhanu kishanNtpc kahalgaon project by bhanu kishan
Ntpc kahalgaon project by bhanu kishan
 
Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT
 
Industrial training ppt bhel bhopal
Industrial training ppt bhel bhopalIndustrial training ppt bhel bhopal
Industrial training ppt bhel bhopal
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC Kanti
 
V.T ppt
V.T pptV.T ppt
V.T ppt
 
Lovely Amit
Lovely AmitLovely Amit
Lovely Amit
 
Ntpc badarpur summer training
Ntpc badarpur summer trainingNtpc badarpur summer training
Ntpc badarpur summer training
 
Mini project presentation
Mini project presentation   Mini project presentation
Mini project presentation
 
Ranjan NTPC KAHALGAON ppt
Ranjan  NTPC KAHALGAON pptRanjan  NTPC KAHALGAON ppt
Ranjan NTPC KAHALGAON ppt
 

Último

08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century educationjfdjdjcjdnsjd
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoffsammart93
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdflior mazor
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUK Journal
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsJoaquim Jorge
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)wesley chun
 

Último (20)

08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 

foram

  • 1. GUJARAT TECHNOLOGICAL UNIVERSITY SIR BHAVSINHJI POLYTECHNIC INSTITUTE BHAVNAGAR DEPARTMENT OF FABRICATION TECHNOLOGY L&T MHI TURBINE GENERATORS
  • 2. PREPARED BY: 1. MILAN J. VISANI (096490355031) 2.CHIRAG P. GOHIL (096490355057) 3. BHUPENDRA SOLANKI (096490355201) 4. CHHATRAPAL RANA (096490355038) L&T MHI TURBINE GENERATORS
  • 4. PROJECT NAME: MAHAGENCO-3. PART NAME: STATOR FRAME. DROWING NO: A11M430 STAGE FOR PRODUCTION: FABRICATION MANUFACTURE: L&T HAZIRA, SURAT MATERIAL: SS 400 JIS IS 2062 gr A/B L&T MHI TURBINE GENERATORS
  • 5. L&T MHI TURBINE GENERATORS
  • 6. Introduction To Steam Turbine L&T MHI TURBINE GENERATORS
  • 7. INDEX •Steam Turbine Basics • Main component/assemblies/ systems of steam turbine •Major Sources of Producing Electricity • Principles of Electricity generation •Working principal of steam turbine •Supercritical technology •Turbine by-pass system •Major Components used In Turbine •Shop weld plan •Test plan •Quality control plan •Bill of material •Stator frame model fabrication sequence procedure •Box plot plan of generator stator frame •Process planning sheet •Some specific terms used in WPS •WPS •Functions of generator stator frame L&T MHI TURBINE GENERATORS
  • 8. STEAM TURBINE LP TURBINE GENERATOR HIP TURBINE L&T MHI TURBINE GENERATORS
  • 9. STEAM TURBINE HP PEDESTAL CROSS OVER PIPE RSV&ICV (Reheat Stop Valve) (Interceptor Valve) MSV&GV (Main Stop Valve) (Governing Valve) L&T MHI TURBINE GENERATORS
  • 10. HIP TURBINE HIP OUTER CASING HIP ROTOR (UPPER) HIP OUTER CASING (LOWER) L&T MHI TURBINE GENERATORS
  • 11. HIP TURBINE GO TO LP TURBINE MAIN STEAM INLET REHEAT STEAM INLET L&T MHI TURBINE GENERATORS
  • 12. Generator Stator Assembly L&T MHI TURBINE GENERATORS
  • 13. Electricity is the key ingredient for the development of a nation L&T MHI TURBINE GENERATORS
  • 14. Hydro Power Plant Thermal Power Plant Prime mover is Hydro Turbine Prime mover is Steam Turbine Rotated by energy of flowing Rotated by steam produced in Water supplied from Dam boiler by burning fossil fuels / reservoir L&T MHI TURBINE GENERATORS
  • 15. Nuclear Power Station Gas based Power Station Prime-mover is Steam Turbine rotated Prime- mover is Gas Turbine run by by steam produced in Steam Generator air gas mixture ignited in combustion by Nuclear fission in the reactor. chamber L&T MHI TURBINE GENERATORS
  • 16. World Power generation scenario Thermal Power Plant are most popular way for producing electricity on large scale and will remain major source of power generation in foreseeable future due to relatively •Low capital cost •Shorter gestation time •Easy availability of fuel •Competitive generating cost •Reasonable high level of operating availability L&T MHI TURBINE GENERATORS
  • 17. Power generation scenario in India 11 3 Thermal Hydro Nuclear 27 58 Gas . Major share in installed capacity and planned in future is thermal L&T MHI TURBINE GENERATORS
  • 18. L&T MHI TURBINE GENERATORS
  • 19. Thermal Power Plant L&T MHI TURBINE GENERATORS
  • 20. Working Principal Of Steam Turbine Nozzle Plate Force ‘F’ F CHANGE IN MOMENTUM = m x v – m x 0 =mxv L&T MHI TURBINE GENERATORS
  • 21. Working Principal Of Steam Turbine V Force ‘F’ -V CHANGE IN MOMENTUM = (m x v) – (- m x v) = 2 x (m x v) Force ‘F’ α 2 x (m x v) L&T MHI TURBINE GENERATORS
  • 22. Working Principal Of Steam Turbine v v sinθ θ v cosθ F -v cosθ CHANGE IN MOMENTUM = (mvcosθ) – (- mvcos θ) θ -v = 2 x (mvcos θ) -v sinθ Force ‘F’ α 2 (mvcos θ) L&T MHI TURBINE GENERATORS
  • 23. WORKING PRINCIPLE OF STEAM TURBINE ROTATING •Steam at high pressure & temperature is made to pass BLADE ROW through a set of fixed blade mounted on stationary body in Casing. •There will be drop in pressure of the steam across the fixed blade resulting to very high steam velocity at the FIXED exit of fixed blade BLADE ROW •The high velocity steam then passes through another DRIVING row of blades mounted on the rotor shaft STATIONARY FORCE BODY/CASING •The impingement of high velocity steam generates driving force on these rotating blades which rotate the rotor. • A set of fixed blades and rotating blades mounted on rotor is called stage of turbine. Depending on steam condition and power output, number of stages in steam turbine is decided L&T MHI TURBINE GENERATORS ROTOR
  • 24. Main Components of Steam Turbine 1 2 3 4 5 6 7 1 1 8 1. Fixed/Guide Blades 5. Gland seals 9. Governing System 2. Moving Blades 6. Bearing & bearing Pedestal 10.Lub. System 3. Casing 7. Coupling 11.Drain system 4. Rotor 8. Stop & Control Valves 12. C&I System L&T MHI TURBINE GENERATORS
  • 25. Rotor is vital element involved in conversion of kinetic energy of steam into mechanical energy of rotation. Run at high speed depending upon grid frequency (50Hz,60 Hz). Subjected to sever stresses i.e. Centrifugal forces, thermal L&T MHI TURBINE GENERATORS
  • 26. Turbine By-Pass System L&T MHI TURBINE GENERATORS
  • 27. Generator stator frame L&T MHI TURBINE GENERATORS
  • 28. SHOP WELD PLAN  Welding engineering department issues shop weld plan to Planning, Shop floor where actual job is going on.  The name self indicate that it is a welding plan of actual job – vessel and it guides to shop floor supervisor and welder that which WPS/PQR shall use for particular seam.  Shop welding plan is related to the welding of the job. It provided all the information regarding weld seam to the welder, as he must well aware of all required conditions of the welding each seam.  If company is working under ISO-9000. It has to keep all the activities to be documented Hence the required documents are made. L&T MHI TURBINE GENERATORS
  • 29. SWP gives the following information regarding the job as related they all seem to be welded. ◦ Seam numbers ◦ Base metal / P-Number ◦ Joint Detail ◦ Weld process ◦ Layer ◦ WPS No. ◦ PQR No. ◦ F - Number ◦ Pre heat temperature ◦ Inter pass temperature ◦ Position ◦ Customer ◦ Inspection agency ◦ Mfg. Code ◦ Post weld heat treatment ◦ Special notes. L&T MHI TURBINE GENERATORS
  • 30. TEST PLAN  Welding engineering department issues test plan to planning, NDT, and shop floor for a particular job which is under production.  In testing plan list of test for particular seam number is given with reference of ASME and customer specification and also given detail of production weld test coupon such as type of testing (destructive & Non- destructive), quantity thickness, For which seam no. required the PTC that is also described.  After completion of welding of all seams particular test is carried out as per testing plan.  With reference of Test plan the shop supervisor is offered the seam for testing to NDT department. L&T MHI TURBINE GENERATORS
  • 31. The following manners are given in the test plan: • Seam wise stage no. and stage description. For testing. • Extent • Specification • Acceptance standard • Production Test Coupon o Seam No, o Thickness o NDT o Chem. Analysis. o Transverse tensile’ o All weld tensile o Impact test o Micro/Macro test • Hardness • Inspection agencies  Hydraulic/pneumatic/leak test and other tests TURBINE GENERATORS L&T MHI
  • 32. QUALITY CONTROL PLAN QUALITY CONTROL PLAN Order: MODEL Drawing No.: Control No.: RJ/GEN/QAP-043 Part No: As per drawing Part Name: GENERATOR STATOR FRAME Dt. 10.06.211 QC Flow Chart Type : Project Items Project Name : Generator Stator Frame Ref. Doc.: Nil Manufacturing Relevant Sr. L&T MHI and Inspection Control Item Document And Frequency Supplier QC Sign Quality Record Remarks No. TG Process Procedure T-Side Block Assy (A42B327) 1 Receiving Mill Sheet Visual Purchase 100% W R/W Mill TC Material All plates shall be inspection and & Dimension Specification As identification UT tested as material per drawing JV record mentioned in JV conformation Standard std. & identification (P. No etc. must be there)** 2 Fit-up & Groove shape, As per drawing 100% W W Fit Up Report All line items as marking Angle, per drawing no. inspection Misalignment, A42B327 shall be Cleaning (Groove inspected at this Surface) stage. 3 Welding Welder, Welding ASME Sec. IX 100% W … … Welding spatters, electrode, A35G107 A- under cut etc. Preheating, KOSHI-R04702 must not be there. Current/voltage 4 PT test of Flaw detection A-SIKI- 100% W W PT Report For PT, Solvent completed weld method, ROWB007 removal method Situation of flaw shall be applied detection surface 5 Dimensional & Visual, As per drawing 100% W W Dimensional visual Dimension, Report inspection Surface roughness L&T MHI TURBINE GENERATORS
  • 33. E-Side Block Assy (A42B326) 6 Receiving Mill Sheet Visual Purchase 100% W R/W Mill TC Material All plates shall be inspection and & Dimension Specification identification UT tested as material As per record mentioned in JV conformation drawing JV std. & Standard identification (P. No etc. must be there)** 7 Fit-up & Groove shape, As per 100% W W Fit Up Report All line items as marking Angle, drawing per drawing no. inspection Misalignment, A42B327 shall be Cleaning (Groove inspected at this Surface) stage. 8 Welding Welder, Welding ASME Sec. IX 100% W … … Welding spatters, electrode, A35G107 A- under cut etc. Preheating, KOSHI- must not be Current/voltage R04702 there. 9 PT test of Flaw detection A-SIKI- 100% W W PT Report For PT, Solvent completed method, Situation ROWB007 removal method weld of flaw detection shall be applied surface 10 Dimensional & Visual, As per 100% W W Dimensional visual Dimension, drawing Report inspection Surface roughness L&T MHI TURBINE GENERATORS
  • 34. Centre Block Assy (A35F896) 11 Receiving Mill Sheet Visual Purchase 100% W R/W Mill TC Material All plates shall be inspection and & Dimension Specification identification UT tested as material As per record mentioned in JV conformation drawing JV std. & Standard identification (P. No etc. must be there)** 12 Fit-up & Groove shape, As per 100% W W Fit Up Report All line items as marking Angle, drawing per drawing no. inspection Misalignment, A42B327 shall be Cleaning (Groove inspected at this Surface) stage. 13 Welding Welder, Welding ASME Sec. IX 100% W … … Welding spatters, electrode, A35G107 A- under cut etc. Preheating, KOSHI- must not be Current/voltage R04702 there. 14 PT test of Flaw detection A-SIKI- 100% W W PT Report For PT, Solvent completed method, Situation ROWB007 removal method weld of flaw detection shall be applied surface 15 Dimensional & Visual, As per 100% W W Dimensional visual Dimension, drawing Report inspection Surface roughness L&T MHI TURBINE GENERATORS
  • 35. Frame Block Docking Assy (A35G121) 16 Receiving Mill Sheet Visual & Purchase 100% W R/W Mill TC Material All plates shall be inspection and Dimension Specification As identification UT tested as material per drawing JV record mentioned in JV conformation Standard std. & identification (P. No etc. must be there)** 17 Fit-up & Groove shape, As per drawing 100% W W Fit Up Report All line items as marking Angle, per drawing no. inspection Misalignment, A42B327 shall be Cleaning (Groove inspected at this Surface) stage. 18 Welding Welder, Welding ASME Sec. IX 100% W … … Welding spatters, electrode, A35G107 A- under cut etc. Preheating, KOSHI-R04702 must not be there. Current/voltage 19 PT test of Flaw detection A-SIKI- 100% W W PT Report For PT, Solvent completed weld method, Situation ROWB007 removal method of flaw detection shall be applied surface 20 Final Visual, Dimension, As per drawing 100% W W Dimensional Dimensional & Surface roughness Report visual inspection 21 Surface coating Type of coat, As per drawing 100% W R Painting Report & painting coating thickness and Specification Abbreviation :- W- Witness R- Review This quality control flow chart & QCL shall be revised as an when required. Prepared By Checked By Approved By L&T MHI TURBINE GENERATORS
  • 36. BILL OF MATERIAL BILL OF MATERIAL PROJECT NAME:- GENERATOR STATOR FRAME Unit Total Sr Part THK in Qty Description Material Weight Weight Remarks No. No. mm unit (Kg) (Kg) 1 001 Shell Plate 5 SS400P 4 11.50 46.00 2 002 Cooler Adapter 10 SS400P 2 4.8 9.50 3 003 Lead box 10 SS400P 1 5.40 5.40 4 004 Frame Foot 10 SS400P 4 1.25 5.00 5 005 Frame Foot Support 1 8 SS400P 8 0.075 0.06 6 006 Frame Foot Support 2 8 SS400P 12 0.042 0.50 7 007 End Plate 10 SS400P 2 2.5 5.00 8 008 Rib Plate 10 SS400P 2 1.75 3.50 9 009 Flange 10 SS400P 6 0..67 0.40 10 010 Trunion 10 SS400P 4 0.25 1.00 11 011 Man hole 10 SS400P 4 1.25 5.00 12 012 support 10 SS400P 4 2.5 10.00 13 013 Bore Ring 8 SS400P 6 0.083 2.50 14 014 Boring Support 10 SS400P 4 0.025 0.10 15 015 Lifting Lug 10 SS400P 4 0.0375 0.15 Total Weight 97.24 L&T MHI TURBINE GENERATORS
  • 37. STATOR FRAME MODELFABRICATION SEQUENCE PROCEDURE Stator Frame Model fabrication Sequence Procedure Sr. Description Planned Date Actual Date Remarks No. 1 Material Selection 5/3/2012 6/3/2012 2 Marking Of Shell 6/3/2012 8/3/2012 3 Long Seam Marking 7/3/2012 10/3/2012 4 Long Seam Welding On Shell 7/3/2012 10/3/2012 5 Circ. Seam Marking 8/3/2012 10/3/2012 6 Circ. Seam Welding On Shell 8/3/2012 11/3/2012 7 Gas Cutting Of T-Side And E-Side 9/3/2012 12/3/2012 8 Grinding Of Cutting Parts 10/3/2012 13/3/2012 9 Cnc Cutting Of E-Side And T-Side Parts 12/3/2012 153/2012 10 Grinding Of E-Side And T-Side Parts 13/3/2012 15/3/2012 11 Cnc Cutting Of Flanges, Manhole, Trunnion 14/3/2012 16/3/2012 12 Grinding Of Flanges, Manhole, Trunnion 14/3/2012 18/3/2012 13 Marking Of Bore Ring And Rib Plates 15/3/2012 19/3/2012 14 Cnc Cutting Of Bore Ring And Rib Plates 16/3/2012 20/3/2012 15 Grinding Of Bore Ring And Rib Plates 19/3/2012 21/3/2012 L&T MHI TURBINE GENERATORS
  • 38. 16 Set-Up And Assembly Of E-Block Parts 20/3/2012 22/3/2012 17 Welding Of E-Block Parts 21/3/2012 23/3/2012 18 Set-Up And Assembly Of T-Block Parts 22/3/2012 24/3/2012 19 Welding Of T-Block Parts 23/3/2012 24/3/2012 20 Full Welding Of E-Block With Shell 24/3/2012 24/3/2012 21 Full Welding Of T-Block With Shell 24/3/2012 27/3/2012 22 Marking Of outer Components On Shell 26/3/2012 27/3/2012 23 Gas Cutting Of Components 27/3/2012 28/3/2012 24 Assembly Of Bore Ring And Rib Plates 28/3/2012 28/3/2012 25 Horizontal Docking Of Structure 29/3/2012 29/3/2012 26 Tack Weld Of Structure 29/3/2012 29/3/2012 27 Full Welding Of Structure With Shell 29/3/2012 30/3/2012 28 Fit-Up Of Outer Components 30/3/2012 30/3/2012 29 Welding Of Components 31/3/2012 2/4/2012 30 Marking Of Frame Foot And Its Supports 31/3/2012 2/4/2012 31 Welding Of Frame Foot And Its Supports 31/3/2012 3/4/2012 32 End Plate Fit-Up 2/4/2012 3/4/2012 L&T MHI TURBINE GENERATORS
  • 39. 33 End Plate Welding 2/4/2012 4/4/2012 34 Visual Inspection 2/4/2012 4/4/2012 35 Distortion Removal 3/4/2012 4/4/2012 36 Dimension Checking 4/4/2012 4/4/2012 37 Cleaning And Surface Preparation 4/4/2012 4/4/2012 38 Marking Of Supports 5/4/2012 5/4/2012 39 Leveling Of Stator Frame 5/4/2012 5/4/2012 40 Welding Of Supports 5/4/2012 5/4/2012 41 Visual Inspection 5/4/2012 6/4/2012 42 Cleaning And Surface Preparation 5/4/2012 7/4/2012 43 Blasting 6/4/2012 9/4/2012 44 Painting 6/4/2012 10/4/2012 45 Final Inspection 7/4/2012 11/4/2012 46 Packing 9/4/2012 11/4/2012 47 Dispatch 10/4/2012 12/4/2012 L&T MHI TURBINE GENERATORS
  • 40. BOX PLOT PLAN OF GENERATOR STATOR FRAME Drawing Material CNC cutting of Fit-up E-BLOCK Fabrication 7/3/2012 Selection parts and assembly 8/3/2012 grinding 16/3/2012 14/3/2012 BOX PLOT PLAN OF GENERATOR T-BLOCK Fit-up STATOR FRAME MODEL Fabrication Drawing Material CNC cutting Selection assembly 7/3/2012 of parts and 8/3/2012 17/3/2012 grinding 14/3/2012 Full Welding of Gas cutting Final Fit-up Outer Parts C-BLOCK Material of Shell, of E and T- Full Welding 28/3/2012 Support Fabrication Drawing Selection Marking of 24/3/2012 cutting and Grinding on block 7/3/2012 8/3/2012 E and T cutting part welding 18/3/2012 block side 17/3/2012 7/4/2012 12/3/2012 Inner side Marking of Vertical Fabrication Drawing Borering CNC cutting Assembly of Final Fit Of of Borering and 7/3/2012 and Rib of Borering Borering and Parts Rib plate plate and Rib plate 18/3/2012 Blasting 8/3/2012 Rib plate 9/4/2012 16/3/2012 Flanges/ manhole/ CNC Material Marking on trunnion Drawing cutting of shell Fit-up on Painting Selection Fabrication 7/3/2012 external 9/4/2012 8/3/2012 21/3/2012 shell items 22/3/2012 16/3/2012 Frame foot/End Material Drawing Selection CNC cutting Marking, Fit-up Packing plate 7/3/2012 8/3/2012 of external Set-up 24/3/2012 10/4/2012 Fabrication items 22/3/2012 19/3/2012 FABRICATION HRS: 34 DAYS Dispatch TOTAL WEIGHT: 97.24 KGS 10/4/2012 L&T MHI TURBINE GENERATORS
  • 41. PROCESS PLANNING SHEET Process Planning Sheet PPS. No. Methods Eng. ref. Rev. No. Page No. No. FAB 0 0 Total: Client Part Name Rev. NO. Drawing No. Material Facility Projec Stator frame model 0 SS400 Nil t Order Process Description Process No. MHI/MELCO Date Estimated Time No. Reference No. 1 Fabrication. 01# 0 24-Feb-10 34 days Opn. Process IMAGES Target day Remarks No. 1 Documentation Fabrication Drawings 5 REF.OF ACTUAL DRG. Inspection record formats 2 Technical standards & work procedures WPS 1 QCL AND QAP 1 3 MARKING OF SHELL Marking of Centre line of shell by using the 1 divider and punch mark. LONG SEAM MARKING and CIRC. SEAM MARKING 4 Cutting & edge preparation Gas cut the of shell as per e-block and t-block 1 dimensions 5 CNC CUTTING OF E-SIDE AND T-SIDE PARTS Cutting as per design requirement and grinding 2 of all cut-out of parts after cutting. L&T MHI TURBINE GENERATORS
  • 42. 6 CNC CUTTING OF FLANGES, MANHOLE, TRUNNION Cutting as per design requirement and grinding of all cut-out of parts after 2 cutting. 7 MARKING OF BORE RING AND RIB PLATES Marking of the rib plate as per the design and cut-out the plate in CNC 2 machine then grinding the all parts. 8 SET-UP AND ASSEMBLY OF E-BLOCK PARTS all cut-out parts are set-up properly and assemble the structure of E-block 2 9 WELDING OF E-BLOCK PARTS All parts in joint by the GTAW process as per the welding design 10 SET-UP AND ASSEMBLY OF T-BLOCK PARTS 3 All cut-out parts are set-up properly and assemble the structure of T-block 11 WELDING OF E-BLOCK PARTS All parts is joint by the GTAW process as per the welding design 1 12 FULL WELDING OF E-BLOCK WITH SHELL The E-block structure is welded with shell by using GMAW process. 1 13 FULL WELDING OF T-BLOCK WITH SHELL The T-block structure is welded with shell by using GMAW process. 1 14 FIT-UP OF OUTER COMPONENTS Fit-Up THE FLANGES, MANHOLE, TRUNNIONS IN THE OUTER SIDE OF 1 SHELL 15 WELDING OF COMPONENTS Full welding of components by using GTAW process. 1 L&T MHI TURBINE GENERATORS
  • 43. 16 MARKING OF FRAME FOOT AND ITS SUPPORTS MARKING OF FRAME FOOT AND ITS SUPPORTS 1 ON THE SHELL 17 WELDING OF FRAME FOOT AND ITS SUPPORTS All cut-out parts of frame foot and supports 1 welded by GMAW welding process. 18 END PLATE FIT-UP AND WELDING Leveling of shell and end plate with respect of 1 design and full welded 19 VISUAL INSPECTION After all welding complete visual check 1 inspection 20 DISTORTION REMOVAL Remove all NDT points by grinding and chipping 1 hammer. 21 MARKING OF SUPPORTS LEVELLING OF STATOR FRAME Marking and leveling of supports then full welding 22 CLEANING AND SURFACE PREPARATION CLEANING AND SURFACE PREPARATION OF ALL 1 WELDED PARTS AND COMPLETE SHELL. 23 BLASTING BLASTING USING SMALL PRESSURE APPLIED 1 24 PAINTING PAINTING OUTER AND INNER SIDE 1 BYMANUALLY. 25 DISPATCH 1 26 PACKING 1 L&T MHI TURBINE GENERATORS
  • 44. SOME SPECIFIC TERMS USED IN WPS Welding Variables ◦ Essential variables. ◦ Supplementary essential variable. ◦ Non-essential variables. P – Numbers: ◦ To reduce the number of welding procedure qualification required, base metals have been assigned P – Numbers. F – Numbers: ◦ F Numbers are used for filler metal designation and grouping of electrodes & welding rods. ◦ It is based essentially on their usability characteristics. A – Numbers: ◦ A – Numbers are used to identify the weld metal chemical composition of ferrous metals. L&T MHI TURBINE GENERATORS
  • 45. CONT… Joints • The WPS describe some variable like groove design ,backing etc., Base Metals • It is essential variables for all welding processes. • A change in a base metal thickness beyond the range qualified in table (As per qw-4541) requires the requalification of WPS. Filler Metal • Filler metal should be selected which is compatible to base metal chemical composition (Sec.II_A/B). They must have same/similar chemical composition. • For filler metal chemical composition, we have the refer ASME SEC-II C. L&T MHI TURBINE GENERATORS
  • 46. CONT… Position • Position is supplementary essential variable. • 1G, 2G, 3G, etc., are different types of welding positions (as per QW-461 Sec IX) Preheat • It can be determine from ASME SEC VIII, Division – 1, Appendix – R. PWHT • ASME SEC – VIII, DIV- I, Per. UCS-56 describes PWHT temperature and time range for specific material with respect to P – Number. L&T MHI TURBINE GENERATORS
  • 47. CONT… Gases • Three types of gases are described in WPS. o Shielding gas. o Backing gas. • Trailing gas Electrical Characteristics • ELECTRICAL CHARACTERISTICS (QW – 409) • We have to write Current, Polarity, and Voltage as electrical characteristics. Technique • It is determined manually with respect to joint design, material type material thickness etc L&T MHI TURBINE GENERATORS
  • 48. WPS QW-482 WELDING PROCEDURE QUALIFICATION (WPS) Supporting WPS NO: 1 DATE: 12-3-2012 - PQR No(s) Welding Revision: RO SMAW Process Date: 12-3-2012 Type MANUAL JOINTS (QW-402) Groove Design As per Drg. Backing: (Yes/No) Yes Backing Material (type) Base metal/Weld metal Other - BASE METALS (QW-403) MATERIAL 1 MATERIAL 2 P. No. 1 P. No. 1 Group No. 1 Group No. 1 Specification/Grade - Specification/Grade - Thickness Range: (mm):5 to 200 mm Base Metal: ss-400 Groove: all Fillet ANY Deposited weld thickness: 200 mm MAX SMAW 6 Fillet ANY Other: 13 mm maximum weld deposition in single pass L&T MHI TURBINE GENERATORS
  • 49. FILLER METALS(QW-404) Process SMAW F. No. 4 A. No. 1 SFA Spec No. 5.1 AWS No. (class) E 7018 Φ 2.5, Size of filler metals (mm) 3.15, 4, Electrode Flux (class) NA Flux Trade name NA Consumable Insert NA Chemical composition NA Other NA POSITIONS (QW-405) Process(es): SMAW Position of Groove: ALL F-Flat Welding Progression: uphill Position of Fillet: ALL H-Horizontal V-Vertical Other None O-Overhead PREHEAT (QW-406) Preheat Temp. (Min):ºC 150 ºC Interpass Temp. (Max):ºC 350 ºC Preheat Maintenance: During Welding L&T MHI TURBINE GENERATORS Other NA
  • 50. POST WELD HEAT TREATMENT (QW-407) ELECTRICAL CHARACTERISTICS(QW-409) Type of PWHT Current(AC or Dc) DC TEMP. Range: ºC Polarity (EN or EP) EP Amps (Range) 70-155 A Soaking/Holding Time Voltage (Range) 20-30 V Rate of Heating Tungsten Type & Size NA Rate of Cooling Mode of Metal Transfer NA NA Others: Electrode wire feed GASES (QW-408) Flow % Composition Rate(LPM) Shielding Gas NA NA Backing/Purging Gas NA NA Trailing Gas NA NA Other NA NA TECHNIQUE (QW-410) String/Weave Bead Gas Cup Size NA Travel Speed (range) Cont. Tube Work Dist. NA Multiple/Single Electrode Multi/Single Pass (per side) Multi Pass Oscillation NA Closed to out chamber NA Cleaning By wire brush Method of Gouging/Back chip By grinding Other NA L&T MHI TURBINE GENERATORS
  • 51. Filler Metal Current Max Min Flux Travel Speed Weld Dia Volt heat Bead Process Trade Range Type & Amp. Range input Layer Class (mm Name Length Polarity Range (mm/min) ) (KJ/mm) (mm) 2.5 NA DCEP 70-90 20-30 - - - ALL PASS E-7018 3.15 NA DCEP 100-140 20-30 - - - SMAW 4 NA DCEP 155-190 20-30 - - - L&T MHI TURBINE GENERATORS
  • 52. QW-482 WELDING PROCEDURE SPECIFICATION (WPS) Supporting PQR WPS NO: 3 DATE: 12-3-2012 - No(s) Revision: RO Welding Process GMAW Date: 12/3/2012 Type Machine JOINTS (QW-402) Groove Design As per Drg. Backing: (Yes/No) with and without Backing Material (type) Base metal/Weld metal Other - BASE METALS (QW-403) MATERIAL 1 MATERIAL 2 P. No. 1 P. No. 1 Group No. 1 Group No. 1 Specification/Grade SS-400 Specification/Grade SS-400 Thickness Range: (mm) 5mm to 200 Base Metal: Groove Fillet ANY mm 5 mm to 200 Deposited weld thickness GMAW Fillet ANY mm Other: None L&T MHI TURBINE GENERATORS
  • 53. FILLER METALS(QW-404) Process GMAW F. No. 6 A. No. 1 Spec No. 5.28 AWS No. (class) ER 70S 6 Size of filler metals (mm) Φ 1.6 Electrode Flux (class) Na Flux Trade name NA Consumable Insert NA Chemical composition NA Other NA POSITIONS (QW-405) Process(es): GMAW Position of Groove: all F-Flat Welding Progression: NA Position of Fillet: F,H,V,O H-Horizontal V-Vertical Other None O-Overhead PREHEAT (QW-406) Preheat Temp. (Min):ºC 150* Interpass Temp. (Max):ºC 350* Preheat Maintenance: During welding Other NA L&T MHI TURBINE GENERATORS Prepared By Reviewed By Approved By
  • 54. WPS No: POST WELD HEAT TREATMENT (QW-407) ELECTRICAL CHARACTERISTICS(QW-409) Type of PWHT - Current(AC or Dc) DC TEMP. Range: ºC - Polarity (EN or EP) EP - Amps (Range) - Soaking/Holding Time - Voltage (Range) - Rate of Heating - Tungsten Type & Size NA Rate of Cooling - Mode of Metal Transfer SPRAY - NA Others: Electrode wire feed - GASES (QW-408) Gas % Composition Flow Rate(LPM) Shielding Gas Ar-Co2 80% to 20% 14 to 24 Backing/Purging Gas NA NA NA Trailing Gas NA NA NA Other NA NA NA TECHNIQUE (QW-410) String/Weave Bead String Gas Cup Size NA 30-200 Cont. Tube Work Travel Speed (range) 15-22mm mm/min Dist. Multi/Single Multiple/Single Electrode Single Multi pass Pass (per side) Oscillation None Closed to out chamber None Cleaning With wire brush Method of Gouging/Back chip - Other - L&T MHI TURBINE GENERATORS
  • 55. V Filler Metal Current o Min Flux lt Travel Speed Max Weld R Bead Process Trade Range heat input Layer Dia a Length Name Type & Amp. (mm/min) Class n (KJ/mm) (mm) Polarity Range g (mm) e 1 8 ER 70S 30- - GMAW 1.6 - DCEP 180-280 - - 6 200mm/min 3 0 Prepared by Reviewed by Approved by L&T MHI TURBINE GENERATORS
  • 56. QW-482 WELDING PROCEDURE SPECIFICATION (WPS)111 DATE: 12-3- Supporting PQR WPS NO: 5 - 2012 No(s) Revision RO Welding Process GTAW Date 12-3-2012 Type Manual JOINTS (QW-402) Groove Design As per Drg. Backing: (Yes/No) No Backing Material (type) NA Other - BASE METALS (QW-403) MATERIAL 1 MATERIAL 2 P. No. 4 P. No. 4 Group No. 1,2 Group No. 1,2 Specification/Grade - Specification/Grade - Thickness Range: (mm) Base Metal: Groove (5-200mm) Fillet ANY Deposited weld thickness GTAW (5-200mm) Fillet ANY Other: None L&T MHI TURBINE GENERATORS
  • 57. FILLER METALS(QW-404) Process GTAW F. No. 6 A. No. 1 Spec No. 5.18 AWS No. (class) ER 70S-2 Size of filler metals (mm) Φ 1.6, 2.4 Electrode Flux (class) NA Flux Trade name NA Consumable Insert NA Chemical composition NA Other NA POSITIONS (QW-405) Process(es): GTAW F-Flat Position of Groove: ALL Welding Progression: Uphill H-Horizontal Position of Fillet: ALL V-Vertical Other None O-Overhead L&T MHI TURBINE GENERATORS
  • 58. PREHEAT (QW-406) Preheat Temp. (Min):ºC - Interpass Temp. (Max):ºC - Preheat Maintenance: - Other - WPS No: POST WELD HEAT TREATMENT (QW-407) ELECTRICAL CHARACTERISTICS(QW-409) Type of PWHT - Current(AC or Dc) DC TEMP. Range: ºC - Polarity (EN or EP) EN - Amps (Range) - Soaking/Holding Time - Voltage (Range) - Rate of Heating - Tungsten Type & Size EWTh-2 Rate of Cooling - Mode of Metal Transfer NA Other - Electrode wire feed NA GASES (QW-408)- Gas % Composition Flow Rate(LPM) Shielding Gas Argon 99.995% 8-12 Backing/Purging Gas NA NA NA Trailing Gas NA NA NA Other NA NA NA L&T MHI TURBINE GENERATORS
  • 59. TECHNIQUE (QW-410) String/Weave Bead String Gas Cup Size Φ 6.0-10.0mm dia Travel Speed (range) NA Cont. Tube Work Dist. NA Multi/Single Pass (per Multiple/Single Electrode Single Multi Pass side) Oscillation None Closed to out chamber None Cleaning With wire brush Method of Gouging/Back chip By grinding Other - Filler Metal Current Flux Travel Max Min Trad Speed heat Weld Volt Bead Process Dia e Type & Amp. Range input Layer Class Range Length (mm) Nam Polarity Range (mm/mi (KJ/mm e n) ) (mm) Root GTAW ER 80S-G 2.4,2.5 NA DCEN 80-120 10-18 - - - Rest GTAW ER 80S-G 2.4,2.5 NA DCEN 110-180 10-18 - - - All SMAW - - NA - - - - - - All SMAW - - NA - - - - - - Prepared by Reviewed by Approved by L&T MHI TURBINE GENERATORS
  • 60. FUNCTION OF GENERATOR STATOR FRAME L&T MHI TURBINE GENERATORS
  • 61. PARTS OF GENERATOR STATOR FRAME L&T MHI TURBINE GENERATORS
  • 62. PARTS OF GENERATOR STATOR FRAME L&T MHI TURBINE GENERATORS
  • 63. BORE RING • bore ring is mainly use for the supporting the core bolt and balancing the rotor All fabrication process complete after send to assembly shop. Clamping arrangement Outer ring Inner ring L&T MHI TURBINE GENERATORS
  • 64. After Leveling & centering of bore ring do tack weld elastic plate to bottom Frame plate. Then place new Frame Plate Above it. Do leveling & centering of same frame plate. Do tack weld it with elastic plate below it. Additional temporary support can also be utilize. Then place next `Bore ring + Elastic Plate` and repeat the above process. And so on complete the Centre block assembly fit-up. L&T MHI TURBINE GENERATORS
  • 65. FRAME FOOT • Frame foot is use for the foundation of the generator. L&T MHI TURBINE GENERATORS
  • 66. LEAD BOX • Lead box mainly use the Supply the lead outside inside L&T MHI TURBINE GENERATORS
  • 67. PROCESS  Marking frame plate  Setting end plate (T side)  Mounting ribs of T side block (1st set)  Mounting frame plate of T side block  Mounting ribs of T side block (2nd set)  Mounting 1st frame plate of center block  Partial welding ribs of T side block (1st set)  Mounting shell plate of T side block  Gas cutting hole for lead box adapter  Mounting of 1st bore ring L&T MHI TURBINE GENERATORS
  • 68. CONT…  Mounting of 2nd frame plate of center block  Welding inside frame  Cleaning welding portion, Painting of angle, pipe and flexible beam support  Mounting shell plate of center block  Welding shell plate center block  Mounting lead box adapter  Welding lead box adapter L&T MHI TURBINE GENERATORS
  • 69. TRUNNION • Lifting the generator L&T MHI TURBINE GENERATORS
  • 70. COOLER ADAPTER • Cooler adapter is mainly use to cooling the steam. L&T MHI TURBINE GENERATORS
  • 71. PROCESS  Marking frame plate  Setting end plate (E side)  Mounting ribs of E side block (1st set)  Mounting frame plate of E side block  Mounting shell plate of E side block  Mounting ribs of E side block (1st set)  Gas cutting hole for cooler adapter  Welding inside frame in flat position  Turnover  Welding inside frame in flat position L&T MHI TURBINE GENERATORS
  • 72. L&T MHI TURBINE GENERATORS
  • 73. L&T MHI TURBINE GENERATORS