SlideShare una empresa de Scribd logo
1 de 3
Descargar para leer sin conexión
Offshore Wind Turbine Foundations
and Commercial Project Experience
www.foundations-offshore.com
Foundations for offshore wind turbines
are one of the key areas of development
for the growth of the wind industry into
deeper waters. There has been a sustained
research effort over recent years to design
and implement new foundation technologies
and to build on already successful designs,
such as monopiles.
Amrumbank West Offshore Wind Farm
The Amrumbank West Offshore Wind Farm is
being constructed by E.ON in the North Sea
off the coast of Germany. It is approximately
37km North-West of the German Island of
Helgoland, which will be used as an operations
and maintenance base.
In total the wind farm will cover an area of 2km2
,
with 80 turbines installed at a depth of 20-25
metres. The 80 turbines, which will give the
wind farm a capacity of 288MW, will be Siemens
SWT-3.6-120 Turbines, rated at 3.6MW each.
The foundations used for the project are
monopile foundations, the first of which was
installed in January 2014. The wind farm is
scheduled to be completed and enter service
in autumn 2015.
Three different ports are being used during the
construction phase, with Esbjerg, Denmark
as an installation base for turbines, Hoboken,
Belgium as a base for the substation, and
Cuxhaven, Germany as the installation base for
foundations.
The grid connection point for the wind farm is
the Helwin2 (beta) converter station (offshore),
and the Buttel onshore substation. The cable
landing point is at the German coastal town of
Busum.
The design, construction and installation of the
foundations were collaborative processes, with
a number of firms involved in the supply chain.
The initial detailed design and certification
process was carried out by Danish company,
Ramboll, and they were also responsible for the
development of the turbine foundation structure
for BSH standards application, the work taking
place between 2010 and 2011.
MPI Adventure installs the first turbine at the Amrumbank West
Offshore Wind Farm. Source: MPI Offshore
Offshore Wind Turbine Foundations and Commercial Project Experience
www.foundations-offshore.com
The manufacture of the monopile foundation
and transition pieces was undertaken by SIF
Group of the Netherlands, and Smulders
group of Belgium, Euskal Forging of Spain was
contracted to fabricate and supply 160 transition
piece flanges and 80 monopile flanges for the
new double hull monopile design.
MPI Offshore Ltd was originally contracted
to install the foundations, at the same time
as carrying out installation work at Humber
Gateway. Ballast Nedam was also contracted
to aid installation work while the contracted
vessel, MPI Discovery, continued work at
Humber Gateway. MPI Offshore has also
been contracted to install the turbines atop the
foundations, and carried out the first installation
early in 2015, with the MPI Adventure vessel set
to continue installation work until the autumn
and completion.
Sandbank Offshore Wind Farm
Source: Vattenfall
The Sandbank wind farm is another North Sea
construction, which is located around 90km
off the coast of the island of Sylt. The project
is being financed by a joint investment from
Vattenfall and StadtWerke Miinchen (SWM),
with a total investment value of 1.2 billion Euros.
Aspecial project company has been established
for the purpose of managing the construction,
with Vattenfall owning 51% and SWM 49% of
the shares.
The Wind farm will cover an area of 66km2,
with 72 turbines, in water depths between 25
and 37 metres, giving a capacity of 288MW.
Construction is planned to start in summer 2015,
with completion set for 2017. The wind farm
has been downsized from initial plans, it seems
likely that this was due to the limited remaining
connection capacity in the SylWin1 converter
station, but it has the potential to be extended in
the future to approximately 500MW. The project
area has room for a further 64 wind turbines, 24
of which have already received approval.
Siemens SWT-4.0-130 win turbines will be
installed at the site, supported by monopile
foundations. MPI Offshore have been
contracted to install the turbines, and Siemens
Wind Power will be responsible for operations
and maintenance for the first five years. The
monopile foundations and transition pieces
are being fabricated by EEW Special Pipe
Constructions GmbH, and they will be installed
by Bilfinger Construction GmbH.
Offshore Wind Turbine Foundations and Commercial Project Experience
www.foundations-offshore.com
Vattenfall and SWM also worked together on the
nearby DanTysk Offshore Wind Farm, which began
construction in 2013 and will be commissioned on
the 30th of April 2015. The wind farm also has
a capacity of 288MW and Siemens Wind Power
will also be responsible for O&M for the first five
years. A new service concept will be tested at the
two wind farms, with one service vessel servicing
both wind farms. The vessel will house workshops
and accommodation for 30 technicians, and will
be positioned permanently between the two wind
farms, with personnel transferred to and from the
vessel via helicopter.
Eneco Luchterduinen Offshore Wind Farm
The Eneco Luchterduinen Offshore Wind Farm is
a Dutch project currently under construction, which
will see 43 wind turbines providing a capacity of
129MW, 23km off the Dutch coast near Noordwijk
and Zandvoort. The wind farm is jointly-owned by
Eneco and Mitsubishi, who acquired a 50% stake
as part of a long-term cooperation agreement with
Eneco.
The 43 turbines will be V112-3.0 MW models
supplied by Vestas, and will be installed by main
contractor, Van Oord, which has an EPCI contract
to carry out full construction of the wind farm. This
may be slightly unusual in the industry, as the
owners of the wind farm are usually responsible for
development, but in this case all responsibility has
been handed over to Van Oord. The company has
used its new transport and installation vessel, the
Aeolus, to install the foundations on the site since
August 2014, and the Aeolus also completed the
first turbine installation in early April 2015.
One of the most interesting aspects of this
development is the foundations that were used,
which consisted of a monopile foundation and	
Foundation installation at Luchterduinen Offshore Wind Farm. 		
Source: Eneco				
transition piece manufactured together,
rather than as two separate components.
SIF Group were contracted to fabricate the
foundations, which the turbines will be
attached to directly, using an innovative
technique that has previously only been applied
in a few smaller cases.
One of the biggest challenges of this design is
the flange at the top of the foundation pile where
the turbine is connected. The impact of the pile
driver had potential to cause issues, so a flange
was designed with a horizontal outer edge for
driving purposes, and a slight downward slant
towards the inside. This ensured that the surface
to which the bolts will be attached to connect the
turbine remained intact during the driving
process. Euskal Forging of Spain was contracted
to manufacture and supply the flanges for this
purpose.
Construction will continue in the coming months,
and the wind farm is expected to be operational
by August 2015.

Más contenido relacionado

Más de Torben Haagh

SOTIF Conference 2019 - APTIV, Toyota, Delphi Tech, Texas Instruments
SOTIF Conference 2019 - APTIV, Toyota, Delphi Tech, Texas InstrumentsSOTIF Conference 2019 - APTIV, Toyota, Delphi Tech, Texas Instruments
SOTIF Conference 2019 - APTIV, Toyota, Delphi Tech, Texas InstrumentsTorben Haagh
 
Daimler, Audi, and Volvo, at Advanced E-Motor - Advanced E-Motor Technology C...
Daimler, Audi, and Volvo, at Advanced E-Motor - Advanced E-Motor Technology C...Daimler, Audi, and Volvo, at Advanced E-Motor - Advanced E-Motor Technology C...
Daimler, Audi, and Volvo, at Advanced E-Motor - Advanced E-Motor Technology C...Torben Haagh
 
Volkswagen, Ford, and PSA Group - Intelligent Automotive Lighting Agenda 2019
Volkswagen, Ford, and PSA Group - Intelligent Automotive Lighting Agenda 2019Volkswagen, Ford, and PSA Group - Intelligent Automotive Lighting Agenda 2019
Volkswagen, Ford, and PSA Group - Intelligent Automotive Lighting Agenda 2019Torben Haagh
 
14th International Conference Innovative Seating 2019
14th International Conference Innovative Seating 201914th International Conference Innovative Seating 2019
14th International Conference Innovative Seating 2019Torben Haagh
 
Agenda - Airport Operational Excellence and Automation 2019, Frankfurt Am Ma...
Agenda  - Airport Operational Excellence and Automation 2019, Frankfurt Am Ma...Agenda  - Airport Operational Excellence and Automation 2019, Frankfurt Am Ma...
Agenda - Airport Operational Excellence and Automation 2019, Frankfurt Am Ma...Torben Haagh
 
Agenda: Interior Cabin Innovation for Automated Vehicles 2019
Agenda: Interior Cabin Innovation for Automated Vehicles 2019Agenda: Interior Cabin Innovation for Automated Vehicles 2019
Agenda: Interior Cabin Innovation for Automated Vehicles 2019Torben Haagh
 
Cognitive Automation 2019, Berlin, Germany
Cognitive Automation 2019, Berlin, GermanyCognitive Automation 2019, Berlin, Germany
Cognitive Automation 2019, Berlin, GermanyTorben Haagh
 
Präsentation zu Roll-Out Messsysteme Infrastruktur bei EnBW
Präsentation zu Roll-Out Messsysteme Infrastruktur bei EnBWPräsentation zu Roll-Out Messsysteme Infrastruktur bei EnBW
Präsentation zu Roll-Out Messsysteme Infrastruktur bei EnBWTorben Haagh
 
Is there potential for robotics in finance and accounting?
Is there potential for robotics in finance and accounting?Is there potential for robotics in finance and accounting?
Is there potential for robotics in finance and accounting?Torben Haagh
 
Mythos und Realität des ERF
Mythos und Realität des ERFMythos und Realität des ERF
Mythos und Realität des ERFTorben Haagh
 
Expert interview with Nexans - the 66kV cabling technology
Expert interview with Nexans - the 66kV cabling technologyExpert interview with Nexans - the 66kV cabling technology
Expert interview with Nexans - the 66kV cabling technologyTorben Haagh
 
ENERCON - Energy System Change: Era of Feed-in Tariffs is coming to an end
ENERCON - Energy System Change: Era of Feed-in Tariffs is coming to an endENERCON - Energy System Change: Era of Feed-in Tariffs is coming to an end
ENERCON - Energy System Change: Era of Feed-in Tariffs is coming to an endTorben Haagh
 
Innovative Ansätze im Mahn- und Inkassoprozess - Kundenorientiertes Mahnen in...
Innovative Ansätze im Mahn- und Inkassoprozess - Kundenorientiertes Mahnen in...Innovative Ansätze im Mahn- und Inkassoprozess - Kundenorientiertes Mahnen in...
Innovative Ansätze im Mahn- und Inkassoprozess - Kundenorientiertes Mahnen in...Torben Haagh
 
Letzte Chance auf Ihr Konferenzticket
Letzte Chance auf Ihr KonferenzticketLetzte Chance auf Ihr Konferenzticket
Letzte Chance auf Ihr KonferenzticketTorben Haagh
 
Effizienter mit Kooperationen bei Integra-Partnern
Effizienter mit Kooperationen bei Integra-PartnernEffizienter mit Kooperationen bei Integra-Partnern
Effizienter mit Kooperationen bei Integra-PartnernTorben Haagh
 
Digitalisierte bAV
Digitalisierte bAV Digitalisierte bAV
Digitalisierte bAV Torben Haagh
 
Die Bank von morgen
Die Bank von morgenDie Bank von morgen
Die Bank von morgenTorben Haagh
 
"Die Zeit-Zielscheibe" von Zach Davis
"Die Zeit-Zielscheibe" von Zach Davis"Die Zeit-Zielscheibe" von Zach Davis
"Die Zeit-Zielscheibe" von Zach DavisTorben Haagh
 
Onshore Wind 2017
Onshore Wind 2017 Onshore Wind 2017
Onshore Wind 2017 Torben Haagh
 
ITSiG für KRITIS-Betreiber
ITSiG für KRITIS-BetreiberITSiG für KRITIS-Betreiber
ITSiG für KRITIS-BetreiberTorben Haagh
 

Más de Torben Haagh (20)

SOTIF Conference 2019 - APTIV, Toyota, Delphi Tech, Texas Instruments
SOTIF Conference 2019 - APTIV, Toyota, Delphi Tech, Texas InstrumentsSOTIF Conference 2019 - APTIV, Toyota, Delphi Tech, Texas Instruments
SOTIF Conference 2019 - APTIV, Toyota, Delphi Tech, Texas Instruments
 
Daimler, Audi, and Volvo, at Advanced E-Motor - Advanced E-Motor Technology C...
Daimler, Audi, and Volvo, at Advanced E-Motor - Advanced E-Motor Technology C...Daimler, Audi, and Volvo, at Advanced E-Motor - Advanced E-Motor Technology C...
Daimler, Audi, and Volvo, at Advanced E-Motor - Advanced E-Motor Technology C...
 
Volkswagen, Ford, and PSA Group - Intelligent Automotive Lighting Agenda 2019
Volkswagen, Ford, and PSA Group - Intelligent Automotive Lighting Agenda 2019Volkswagen, Ford, and PSA Group - Intelligent Automotive Lighting Agenda 2019
Volkswagen, Ford, and PSA Group - Intelligent Automotive Lighting Agenda 2019
 
14th International Conference Innovative Seating 2019
14th International Conference Innovative Seating 201914th International Conference Innovative Seating 2019
14th International Conference Innovative Seating 2019
 
Agenda - Airport Operational Excellence and Automation 2019, Frankfurt Am Ma...
Agenda  - Airport Operational Excellence and Automation 2019, Frankfurt Am Ma...Agenda  - Airport Operational Excellence and Automation 2019, Frankfurt Am Ma...
Agenda - Airport Operational Excellence and Automation 2019, Frankfurt Am Ma...
 
Agenda: Interior Cabin Innovation for Automated Vehicles 2019
Agenda: Interior Cabin Innovation for Automated Vehicles 2019Agenda: Interior Cabin Innovation for Automated Vehicles 2019
Agenda: Interior Cabin Innovation for Automated Vehicles 2019
 
Cognitive Automation 2019, Berlin, Germany
Cognitive Automation 2019, Berlin, GermanyCognitive Automation 2019, Berlin, Germany
Cognitive Automation 2019, Berlin, Germany
 
Präsentation zu Roll-Out Messsysteme Infrastruktur bei EnBW
Präsentation zu Roll-Out Messsysteme Infrastruktur bei EnBWPräsentation zu Roll-Out Messsysteme Infrastruktur bei EnBW
Präsentation zu Roll-Out Messsysteme Infrastruktur bei EnBW
 
Is there potential for robotics in finance and accounting?
Is there potential for robotics in finance and accounting?Is there potential for robotics in finance and accounting?
Is there potential for robotics in finance and accounting?
 
Mythos und Realität des ERF
Mythos und Realität des ERFMythos und Realität des ERF
Mythos und Realität des ERF
 
Expert interview with Nexans - the 66kV cabling technology
Expert interview with Nexans - the 66kV cabling technologyExpert interview with Nexans - the 66kV cabling technology
Expert interview with Nexans - the 66kV cabling technology
 
ENERCON - Energy System Change: Era of Feed-in Tariffs is coming to an end
ENERCON - Energy System Change: Era of Feed-in Tariffs is coming to an endENERCON - Energy System Change: Era of Feed-in Tariffs is coming to an end
ENERCON - Energy System Change: Era of Feed-in Tariffs is coming to an end
 
Innovative Ansätze im Mahn- und Inkassoprozess - Kundenorientiertes Mahnen in...
Innovative Ansätze im Mahn- und Inkassoprozess - Kundenorientiertes Mahnen in...Innovative Ansätze im Mahn- und Inkassoprozess - Kundenorientiertes Mahnen in...
Innovative Ansätze im Mahn- und Inkassoprozess - Kundenorientiertes Mahnen in...
 
Letzte Chance auf Ihr Konferenzticket
Letzte Chance auf Ihr KonferenzticketLetzte Chance auf Ihr Konferenzticket
Letzte Chance auf Ihr Konferenzticket
 
Effizienter mit Kooperationen bei Integra-Partnern
Effizienter mit Kooperationen bei Integra-PartnernEffizienter mit Kooperationen bei Integra-Partnern
Effizienter mit Kooperationen bei Integra-Partnern
 
Digitalisierte bAV
Digitalisierte bAV Digitalisierte bAV
Digitalisierte bAV
 
Die Bank von morgen
Die Bank von morgenDie Bank von morgen
Die Bank von morgen
 
"Die Zeit-Zielscheibe" von Zach Davis
"Die Zeit-Zielscheibe" von Zach Davis"Die Zeit-Zielscheibe" von Zach Davis
"Die Zeit-Zielscheibe" von Zach Davis
 
Onshore Wind 2017
Onshore Wind 2017 Onshore Wind 2017
Onshore Wind 2017
 
ITSiG für KRITIS-Betreiber
ITSiG für KRITIS-BetreiberITSiG für KRITIS-Betreiber
ITSiG für KRITIS-Betreiber
 

Último

Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...Amil Baba Dawood bangali
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Steel Structures - Building technology.pptx
Steel Structures - Building technology.pptxSteel Structures - Building technology.pptx
Steel Structures - Building technology.pptxNikhil Raut
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdfCaalaaAbdulkerim
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfRajuKanojiya4
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptNarmatha D
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 

Último (20)

Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Steel Structures - Building technology.pptx
Steel Structures - Building technology.pptxSteel Structures - Building technology.pptx
Steel Structures - Building technology.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdf
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdf
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.ppt
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 

Commercial project experience at the Amrumbank West, Sandbank, Eneco Luchterduinen and WindFloat Atlantic offshore wind farms

  • 1. Offshore Wind Turbine Foundations and Commercial Project Experience www.foundations-offshore.com Foundations for offshore wind turbines are one of the key areas of development for the growth of the wind industry into deeper waters. There has been a sustained research effort over recent years to design and implement new foundation technologies and to build on already successful designs, such as monopiles. Amrumbank West Offshore Wind Farm The Amrumbank West Offshore Wind Farm is being constructed by E.ON in the North Sea off the coast of Germany. It is approximately 37km North-West of the German Island of Helgoland, which will be used as an operations and maintenance base. In total the wind farm will cover an area of 2km2 , with 80 turbines installed at a depth of 20-25 metres. The 80 turbines, which will give the wind farm a capacity of 288MW, will be Siemens SWT-3.6-120 Turbines, rated at 3.6MW each. The foundations used for the project are monopile foundations, the first of which was installed in January 2014. The wind farm is scheduled to be completed and enter service in autumn 2015. Three different ports are being used during the construction phase, with Esbjerg, Denmark as an installation base for turbines, Hoboken, Belgium as a base for the substation, and Cuxhaven, Germany as the installation base for foundations. The grid connection point for the wind farm is the Helwin2 (beta) converter station (offshore), and the Buttel onshore substation. The cable landing point is at the German coastal town of Busum. The design, construction and installation of the foundations were collaborative processes, with a number of firms involved in the supply chain. The initial detailed design and certification process was carried out by Danish company, Ramboll, and they were also responsible for the development of the turbine foundation structure for BSH standards application, the work taking place between 2010 and 2011. MPI Adventure installs the first turbine at the Amrumbank West Offshore Wind Farm. Source: MPI Offshore
  • 2. Offshore Wind Turbine Foundations and Commercial Project Experience www.foundations-offshore.com The manufacture of the monopile foundation and transition pieces was undertaken by SIF Group of the Netherlands, and Smulders group of Belgium, Euskal Forging of Spain was contracted to fabricate and supply 160 transition piece flanges and 80 monopile flanges for the new double hull monopile design. MPI Offshore Ltd was originally contracted to install the foundations, at the same time as carrying out installation work at Humber Gateway. Ballast Nedam was also contracted to aid installation work while the contracted vessel, MPI Discovery, continued work at Humber Gateway. MPI Offshore has also been contracted to install the turbines atop the foundations, and carried out the first installation early in 2015, with the MPI Adventure vessel set to continue installation work until the autumn and completion. Sandbank Offshore Wind Farm Source: Vattenfall The Sandbank wind farm is another North Sea construction, which is located around 90km off the coast of the island of Sylt. The project is being financed by a joint investment from Vattenfall and StadtWerke Miinchen (SWM), with a total investment value of 1.2 billion Euros. Aspecial project company has been established for the purpose of managing the construction, with Vattenfall owning 51% and SWM 49% of the shares. The Wind farm will cover an area of 66km2, with 72 turbines, in water depths between 25 and 37 metres, giving a capacity of 288MW. Construction is planned to start in summer 2015, with completion set for 2017. The wind farm has been downsized from initial plans, it seems likely that this was due to the limited remaining connection capacity in the SylWin1 converter station, but it has the potential to be extended in the future to approximately 500MW. The project area has room for a further 64 wind turbines, 24 of which have already received approval. Siemens SWT-4.0-130 win turbines will be installed at the site, supported by monopile foundations. MPI Offshore have been contracted to install the turbines, and Siemens Wind Power will be responsible for operations and maintenance for the first five years. The monopile foundations and transition pieces are being fabricated by EEW Special Pipe Constructions GmbH, and they will be installed by Bilfinger Construction GmbH.
  • 3. Offshore Wind Turbine Foundations and Commercial Project Experience www.foundations-offshore.com Vattenfall and SWM also worked together on the nearby DanTysk Offshore Wind Farm, which began construction in 2013 and will be commissioned on the 30th of April 2015. The wind farm also has a capacity of 288MW and Siemens Wind Power will also be responsible for O&M for the first five years. A new service concept will be tested at the two wind farms, with one service vessel servicing both wind farms. The vessel will house workshops and accommodation for 30 technicians, and will be positioned permanently between the two wind farms, with personnel transferred to and from the vessel via helicopter. Eneco Luchterduinen Offshore Wind Farm The Eneco Luchterduinen Offshore Wind Farm is a Dutch project currently under construction, which will see 43 wind turbines providing a capacity of 129MW, 23km off the Dutch coast near Noordwijk and Zandvoort. The wind farm is jointly-owned by Eneco and Mitsubishi, who acquired a 50% stake as part of a long-term cooperation agreement with Eneco. The 43 turbines will be V112-3.0 MW models supplied by Vestas, and will be installed by main contractor, Van Oord, which has an EPCI contract to carry out full construction of the wind farm. This may be slightly unusual in the industry, as the owners of the wind farm are usually responsible for development, but in this case all responsibility has been handed over to Van Oord. The company has used its new transport and installation vessel, the Aeolus, to install the foundations on the site since August 2014, and the Aeolus also completed the first turbine installation in early April 2015. One of the most interesting aspects of this development is the foundations that were used, which consisted of a monopile foundation and Foundation installation at Luchterduinen Offshore Wind Farm. Source: Eneco transition piece manufactured together, rather than as two separate components. SIF Group were contracted to fabricate the foundations, which the turbines will be attached to directly, using an innovative technique that has previously only been applied in a few smaller cases. One of the biggest challenges of this design is the flange at the top of the foundation pile where the turbine is connected. The impact of the pile driver had potential to cause issues, so a flange was designed with a horizontal outer edge for driving purposes, and a slight downward slant towards the inside. This ensured that the surface to which the bolts will be attached to connect the turbine remained intact during the driving process. Euskal Forging of Spain was contracted to manufacture and supply the flanges for this purpose. Construction will continue in the coming months, and the wind farm is expected to be operational by August 2015.