SlideShare una empresa de Scribd logo
1 de 33
Descargar para leer sin conexión
PROPOSED PILOT PROGRAM FOR IMPROVING
PROVINCIAL ROAD MAINTENANCE (PRIM)
Program Design



08 November 2012
Background
• Roads are the predominant mode of transport in Indonesia
• Sub-national roads comprise 91% of the primary road network
  in Indonesia
• Provincial road 10.2% and Kabupaten/Kota road 80.7%
• Investment and maintenance have not kept up with demand
  – Typically only 51% of sub-national network is in stable condition
• Priority tends to be given to new construction/rehabilitation,
  not (more cost-effective) to maintenance
  – But more effective asset management is one of 5 key DGH objectives
    for 2010-2014
• Road Traffic and Transport Law 2009 provides for:
  – Road Preservation Units/Funds
  – Road Traffic & Transport Forums (RTTFs)
  – Clarification of asset management responsibilities

                                                                        2
Lessons Learned from International
Experience
• Maintenance problem is not unique to Indonesia
• Trend to improve accountability and ensure sound road
  management
• Move from force account to maintenance by contract
• Move towards results based arrangements for
  implementation
  – Output based-will be implemented by PRIM
  – Performance based
• Introduce incentives into funding mechanisms




                                                          3
Lessons Learned from National Experience
1. EIRTP-2 (World Bank Project 2006-2011)
       13 Provinces and 35 Kabupaten using contestibility
       20% Routine maintenance per year doesn’t succeed
       Low Fiscal Capacity grant/matching fund (90/10); Medium (60/40); High
        (30/70)
       Reimbursement by contract/MC
       Reduce financial gap but not sustainable
       13 Indicators and 8 indicators have failed to achieved
2. Local Government Decentralized Project /LGDP (WB Project
   2011-2013)
       6 Provinces and 66 Kabupaten/Kota
       Road, Irrigation and water
       Verification of Output
       Contract and swakelola
       RUC too generic
3. EINRIP (AusAID 2008-2013)
       Only National Roads
       Technical and Financial Audit


                                                                           4
Proposed Pilot Program Objectives
• Develop and test a pilot grant program using results
  based disbursements to improve the condition and
  connectivity of provincial roads
• Sustain and improve the condition and connectivity of
  provincial roads, with emphasis on better value for
  money;
• Strengthen the existing governance arrangements to
  promote the adoption of more sustainable and efficient
  maintenance practices;
• Build demand for better governance; and
• Demonstrate replicability and sustainability of the
  proposed approach


                                                           5
Program Design Document
• Provide additional funding for maintenance
• Focus on results and greater accountability
• Outside oversight by the Donor will be reduced,
• Establish a program safeguards and clear criteria for
  success, fostering trust and efficiency.
• Financial incentives for good performance
• Coordination between agencies and consultation with
  the public will be improved through the RTTF, under
  Road Traffic and Transport Law 22/2009 and PP 37/2011.
• Application of recent regulations relating to road
  maintenance, road design and procurement.


                                                      6
Why Pilot Provincial Roads? Why NTB?
• Key connectivity links between national roads and district
  roads
  – 10% of network length and 19% of vehicle-km
• Provinces have better institutional capacity than districts
  – Stronger likelihood of successful implementation
• NTB has demonstrated strong support and commitment
  –   Budget support
  –   Adoption of Multi years contract
  –   Institutional support and the role of the RTTF
  –   Demonstrated understanding of output-based concepts
• Subsequent program extension:
  – Extend to other provinces when lessons are learned and
    mechanism is demonstrated to be effective in the pilot program
  – Consider possible involvement of additional selected LG


                                                                     7
Justification for NTB
1 - Weak (major deficiencies and outcomes likely)
2 - Moderate (some qualifications)
3 - Strong (few or no qualifications)

   Kupang


     NTT


  Tabanan
                                                        Overall
      Bali                                              Execution
                                                        Preparation
      KLT                                               Planning


      KLB


     NTB


             0           1               2          3

                                                                      8
Program Description
• Component 1a: Payment of an incentive (approximately
  A$ 52 million) after verified maintenance of provincial
  roads.
• Routine maintenance (through swakelola- force account
  and contracts)
• Periodic maintenance by overlays or regravelling
• Rehabilitation of pavements and structures
• All programs to include repair or reconstruction of
  shoulders, roadside and drainage systems
• Costs are preliminary and are presently being revised by
  interim support consultants



                                                         9
Program Description(cont’d)
• Component 1b: Payment of an Institutional
  development incentive (approximately A$ 2.6 million) for
  adopting PPBP and improvement RTTF
• Component 2: Institutional strengthening, program
  management support, monitoring and evaluation, and
  verification of results ($12 million).
• Institutional Strengthening
  ₋ Training of personnel in provincial government road offices
  ₋ Capacity to plan, program, budget and implement
    maintenance works;
  ₋ Improvements to the swakelola system and mentoring of
    personnel;
  ₋ Other Training based on Training Need Analyses Study will be
    carryout by Implementation Consultant

                                                               10
Program Description(cont’d)
• Implementation support (assisted by IndII consultant)
  ₋ Technical team to be created by DGH
  ₋ Project Implementation Unit (PIU) to be created in pilot
    province
• Technical verification of maintenance works as a
  condition for disbursement
• Incentive for adopting and implementing adequate
  PPBP and effective RTTF
• Monitoring and evaluation of the pilot program during
  implementation and for 3 years afterwards
• Note: design and supervision is to be the responsibility
  of the Province, after improvement of skills (design)
  and remuneration (supervision)

                                                               11
COST OF PILOT PROGRAM IN NTB
• Maintenance Works-5 years program: $143 million: $52
  million incentive from AusAID.
• Maintenance Works – 2 years (May 2013 to June 2015):
  $36.96 million: $13.44 million incentive from AusAID
  and $23.52 million Prov. contribution
• Technical Assistance: $12 million from AusAID (five
  years) of which $5 million will be incurred 2013 up to
  June 2015
• Cost of Design and Supervision estimated $ 4 million is
  assumed to be met by NTB
• Total Cost: $159 million; AusAID: $64 million
• Incentive for PPBP/RTTF: 5% of works: $2.6 million
• Total Potential Contribution from AusAID: $66.6 million
                                                      12
Estimated Program and Flow of Grant
disbursements under Component 1a
              Total Program and Grant Disbursements
                            (A$)million                           Net Grant           Net Province
Fiscal Year                                                      Contribution         Contribution
                                Program        Implemen.
                 APBD                                            (A$) million         (A$) million
                                  Disb.          Disb.

  2013/2               11.25            1.23              0.40                 1.63            11.65
   2014                19.28            2.15              4.97                 7.51            11.77
  2015/1                6.04            0.66              4.04                 4.70             1.34
  Sum 1                36.96            4.03              9.41                13.44            23.52
  2015/2               17.67            1.93              0.00                 1.93            15.75
   2016                35.35            3.86              9.00                12.85            22.49
   2017                35.35            3.86              9.00                12.85            22.49
  2018/1               17.67            1.93              9.00                10.93             6.75
  Sum 2               106.04           11.57             26.99                38.56            67.48
  Works               130.00           15.60             36.40                52.00            78.00
   + VAT               13.00               0                 0                   0             13.00
   Total              143.00           15.60             36.40                52.00            91.00
    Notes: 2015/1 means Semester 1 (January – June) of 2015, the completion
    date of Phase 1 of the Grant

                                                                                               13
Budget allocation & grant disbursement
• Program value
     • 2013- June 2015
     • July 2015-2018
• Grant contribution
     • 40% contribution to total program
     • 60% APBD value
• Cash flow
     • Budget provision (APBD) -Prefinancing 100% until
       verification and reimbursement is approved
     • Reimbursement
        o Advance payment on annual work program value – 30%
        o Approved work to Verification point (less advance)




                                                               14
Additional notes
1. Assumes 30% advance on total agreed annual program
2. Advance deducted in proportion to the amount of
   annual work program approved.
3. Two disbursement dates per year, in May and October
4. For programming purposes base year of 2012 and
   allowance for 5% physical contingency and 5% per
   annum price contingency, and a 5% provision for
   mobilisation etc.




                                                    15
Program composition 2013- June 2015
• Routine Maintenance contracts
   Length 387 Km and Cost A$ 2.73 million
• Routine Maintenance Swakelola
   Length 696 Km and Cost A$ 16.31 million
• Periodic Maintenance
   Length 42 Km and Cost A$ 3.13 million
• Rehabilitation
   Length 43 Km and Cost A$ 14.79 million


• TOTAL PROGRAM A$ 36.96 million




                                              16
Program of 7 Contracts for 2013-June 2015
                      Routine Maintenance   Periodic Maintenance      Rehabilitation
             No.of
Package Name            Road        Cost      Work                   Work         Cost
             links                                     Cost (A$m)
                       length      (A$m)     length                 length       (A$m)
Rembiga -
                 3      80         0.57       14         0.87         -          0.49
Bayan
Lb Lombok -
                 2      53         0.22        1         0.15         1          0.55
Biluk

Praya - Kruak    1      21         0.17       12         0.79         -          0.08


Sb Pengatap -
                 2      59         0.54        -         0.15        12          4.46
Kuta -Penunjak

Sumbawa
                 3      71         0.46        5         0.38         -          0.49
Besar
Sb Kempo - Sp
                 1      18         0.16        5         0.31         8          1.81
Kore
Tawali -
                 2      84         0.60        5         0.47        22          6.91
Karumbu
    Totals       14     387        2.73       42         3.13        43         14.79

                                                                                         17
Swakelola Program for 2013- June 2015
                              Routine Maintenance
  PPK Group
                       Road length            Cost (A$m)

  Lombok Utara                        5 km                  0.08

  Lombok Barat                       95 km                  2.14

  Lombok Tengah                      37 km                  0.95

  Lombok Timur                   105 km                     1.91

  Sumbawa Barat                       3 km                  0.04

  Sumbawa Timur                  111 km                     2.16

  Bima/Dompu                     340 km                     9.04

              Totals             696 km                    16.31


                                                                   18
Program composition July 2015-June 2018
• Routine Maintenance contracts
   Length 771 Km and Cost A$ 8.31 million
• Routine Maintenance Swakelola
   Length 489 Km and Cost A$ 4.81 million
• Periodic Maintenance
   Length 273 Km and Cost A$ 14.95 million
• Rehabilitation
   Length 173 Km and Cost A$ 77.96 million


• TOTAL PROGRAM FOR 2015-2018 A$ 106.04 million




                                                  19
Combined Works Programs, 2015 – 2018
                   Routine Maintenance       Periodic Maintenance         Rehabilitation
No.of links         Road                                                 Work        Cost
                             Cost (A$m)     Work length   Cost (A$m)
                   length                                               length      (A$m)
    31             771 km       8.31          273 km        14.95       173 km       77.96




         Routine Maintenance, 2015 – 2018
              Contracts and Swakelola
                                                Routine Maintenance
      No.of links
                                         Road length                   Cost (A$m)


              23                           489 km                         4.81




                                                                                             20
Identification of the PRIM Network In NTB




                                            21
Recommended Treatments 2013 – 2015




                                     22
Recommended Treatments 2015 – 2018




                                     23
Verification of Results and Disbursement
• Output eligibility criteria
   ₋   Compliance with Program Verification
   ₋   Compliance with national procurement law and regulations
   ₋   Compliance with technical specifications
   ₋   Compliance with environmental and social safeguards
• Reference Unit Cost/prices-calculated by specific link, condition,
  treatment (initial and annual) and length (RUC vs contract price)
• Technical Team DGH, Ministry of Public Works undertakes
  Technical Verification supported by a Verification Consultant
• Disbursement:
   Advance Payment Disbursement (30% of annual Program)
   Implementation Disbursement




                                                                       24
Compliance With Program Verification
• Proposed works are entered into the provincial Budget
  or have a formal Cost Analysis (RAB); the date of
  approval of all budget documents is noted;
• The maintenance budget is announced on a website,
  including location of works;
• The procurement documents for Supervision
  Consultants specify remuneration at INKINDO rates, as
  well as the personnel’s minimum salary component.




                                                          25
Compliance With National Procurement Law
and Regulations
•   Presence of Integrity Pact
•   Availability of Minutes of Pre Bid Meeting
•   Availability of Bid Evaluation Report
•   Name of the Winner in an official announcement
•   Any objections are resolved




                                                     26
Compliance With Technical Specifications
•   Quality of Routine Maintenance Plan
•   Visual Assessment
•   assessment of Routine Maintenance Works
•   Road pavement thickness, length and width is consistent
    with contracts
•   Quality of surface condition and presence defects at
    visual assessment
•   Quality and quantity of asphalt and aggregate base/sub
    base; soil; road shoulders
•   Bridge repair works consistent with contracts
•   Physical progress after 25% and 50% of contract time has
    elapsed
•   How about non compliance works??

                                                         27
Compliance With Environmental and Social
Safeguards
• Acceptance of Environmental and Social Safeguard
  Framework
• Fulfilment of environmental monitoring procedure
• Implementation of disability provisions in the designs, if
  applicable




                                                           28
Risks
• Timely availability of annual budget in agreed amounts, where
  Province has to pre-finance maintenance works
• Weak capacity of provincial works department and ineffective
  coordination
• Election year 2013 for Governor
• Verification of results
• Excess ‘Swakelola’ staff
• Capacity of local contractors and consultants
• Corruption
• Other Risks
     ₋   Number of Pilot Provinces
     ₋   Size of Grant
     ₋   Uncertainity regarding extension of current funding authorisation for IndII
         and AIIG beyond June 30, 2015
     ₋   Availability of additional sources of funding for scaling program
     ₋   Appointment and funding of design and supervision consultants

                                                                                       29
Organisation Chart for Provincial Road Improvement Maintenance/PRIM
Australian-Indonesia Infrastructure Initiative/IndII




                                                                  30
Implementation Schedule for PRIM until June
                                                               2015
                                                                               2012                                                                                       2013                                                                                       2014                                                                      2015
                                             Jan - Apr   May   Jun   Jul       Aug Sept     Oct           Nov       Dec    Jan   Feb   March    April    May    June    July August   Sept    Oct      Nov     Dec    Jan     Feb      March    April       May       June   July August Sept      Oct     Nov     Dec Jan   Feb     March    April    May      June

                                                                                                                                   DFA
                                                                                                   PMM                                                  NPPH

                                                                                                                                         SPPH
                                                                                                                                                                              1st Output     MoF 1st                                                       MoF 2nd                3rd Output     MoF 3rd                           4th Output         MoF 4th
                                                                                                                                                                                                                              2nd Output Verification
                                                                                                                                                                                             Payment                                                       Payment                Verification   Payment                           Verification       Payment
  Grant




                                                                                                                                                                              Verification
                                            Subsidiary                       Grant Preparation incl. LG
                                                                                                                APBN +
                                            Agreement                                 Proposal
                                                                                                                  DIPA
                                            (AusAID &                      (IndII, Bappenas, MoF, Tech.
                                                                                                                 (MoF)
                                              MoF)                                 Ministry & LG)

                                                                                                                                                                                                       RKUD                                                          RKUD                                  RKUD                                                 RKUD
                                                                                                                                                                                                        (LG)                                                          (LG)                                  (LG)                                                 (LG)
                                                                                                  Plan APBD 2013
                                                                                                        (LG)


                                                                                                    Perda for Road Maintenance
                                                                                                       Program 2013 - 2018
                                                                                                            (incl. PRIM)


                                                                                       Establish Tech. Team in
                                                                                                 DGH
                                                                                                                                                                                                                            DGH Technical Team Support


                                                         ADD/TOR
                                                         & Procure         Interim Support Consultant


                                                                                           Establish PIU                                                                                                             DPU Program Implementation Unit (PIU)


                                                                                                                                                                                                                               PRIM Swakelola (Force Account) Routine Maintenance
                                               Concept Note
                                                                                                                                           Detailed
                                                                                                                                         Design & Bid
Technical Assistance (TA) & LG Activities




                                                                                                                                          Document
                                                                                                                                          for Multi-
                                                                                                                                            years


                                                                                                                                                           Procure
                                                                                                                                                          Contractor
                                                                                                                                                                                                                                                            PRIM Construction


                                                                                                                                                            Procure
                                                                                                                                                          Supervision                                                                                   PRIM Supervision Consultant
                                                                                                                                                          Consultant



                                                                                                                                                                                                               Road Traffic & Transport Forum (RTTF)



                                                                                                                                                                                                                                               PIU Consultant


                                                                                                                                                                                                                                                    Monitoring & Evaluation

                                                                                            ADD / TOR                    Procure
                                                                                                                                                                                                                                       Technical and Financial Assessment Consultant (TFAC)



                                                                                                                                                                                                                                    Training & Institutional Strenghtening




                                                                                                                                                                                                                                                                                                                                                                31
Critical Path
                  Activity                                     By               Deadline

Grant Preparation including LG Proposal     IndII, Bappenas, MoF, DGH & LG   15 Nov 2012

DIPA for APBN                               MoF                              31 Dec 2012
DPA for APBD 2013                           LG                               31 Dec 2012

Activity Design Document /ToR               IndII & AusAID                   30 Nov 2012

Procurement and mobilisation of IndII
                                            IndII                            28 Feb 2013
Consultant

Survey, Prepare Design and Bid Documents
                                            IndII Consultant                 30 April 2013
for Multi-year Contracts 2013-2015

Procure Contractors                         LG                               30 June 2013
Program Management Manual                   DGH MPW                          30 Nov 2012
Direct Funding Agreement                    AusAID & DGDM MoF                31 March 2013
Prepare and Issue SPPH (Surat Penetapan
                                            DGFB MoF                         31 March 2013
Penerusan Hibah)
Prepare and Sign PPH (PerjanjianPenerusan
                                            DGFB MoF and LG                  31 May 2013
Hibah)
                                                                                             32
Next Steps
•   Socialization to NTB for on grant condition 14 Nov 2012
•   Establish TT in DGH and PIU in DPU NTB: November 2012
•   Program Management Manual Nov 2012
•   Statement Letter from Governor of NTB concerning 100%
    Prefinancing prior reimbursement, PERDA Accelleration 2/PRIM,
    APBD Budget 2013: Nov 2012
•   PERDA Accelleration 2/PRIM: Nov 2012-April 2013
•   Procure Preparation and Implementation Project Consultant:
    December 2012-February 2013
•   Prepare project implementation: March-June 2013
•   Start Improved Swakelola: May 2013
•   Procurement 7 Packages A$ 20.65 million May-June 2013
•   Finalize direct funding agreement, grant channeling decree/SPPH:
    Jan - March 2013
•   On Granting Agreement /PPH: April-May 2013
                                                                  33

Más contenido relacionado

Similar a Ind ii program design document-pilot program prim pp presentation 08112012 (formatted)

ThinkTank Cities - Assignment 4 - Toronto Baseline Case
ThinkTank Cities - Assignment 4  - Toronto Baseline CaseThinkTank Cities - Assignment 4  - Toronto Baseline Case
ThinkTank Cities - Assignment 4 - Toronto Baseline Case
Leuphana Digital School
 
Aiesec vietnam national award
Aiesec vietnam national awardAiesec vietnam national award
Aiesec vietnam national award
samsoonkum
 
Session Harmonization 3c - Minta kampala seminar 2010
Session Harmonization 3c - Minta kampala seminar 2010Session Harmonization 3c - Minta kampala seminar 2010
Session Harmonization 3c - Minta kampala seminar 2010
IRC
 
2nd interim financial report
2nd interim financial report2nd interim financial report
2nd interim financial report
dvodicka
 

Similar a Ind ii program design document-pilot program prim pp presentation 08112012 (formatted) (20)

Full Eecs Report Draft 11 05 2009
Full Eecs Report Draft 11 05 2009Full Eecs Report Draft 11 05 2009
Full Eecs Report Draft 11 05 2009
 
Amrut ppt
Amrut pptAmrut ppt
Amrut ppt
 
Leading change
Leading changeLeading change
Leading change
 
LECTURE-1 Introduction to Project Concept, Lifecycle .pptx
LECTURE-1 Introduction to Project Concept, Lifecycle .pptxLECTURE-1 Introduction to Project Concept, Lifecycle .pptx
LECTURE-1 Introduction to Project Concept, Lifecycle .pptx
 
Corporate presentation 4 q 14 sa
Corporate presentation 4 q 14 saCorporate presentation 4 q 14 sa
Corporate presentation 4 q 14 sa
 
Overview of GWP 3 Year Work Programme
Overview of GWP 3 Year Work ProgrammeOverview of GWP 3 Year Work Programme
Overview of GWP 3 Year Work Programme
 
RPN Manila 2022: Session 5.1 Slamet Rona Ircham MoF.pdf
RPN Manila 2022: Session 5.1 Slamet Rona Ircham MoF.pdfRPN Manila 2022: Session 5.1 Slamet Rona Ircham MoF.pdf
RPN Manila 2022: Session 5.1 Slamet Rona Ircham MoF.pdf
 
APR Workshop 2010-APR Performance-Maria Donnat
APR Workshop 2010-APR Performance-Maria DonnatAPR Workshop 2010-APR Performance-Maria Donnat
APR Workshop 2010-APR Performance-Maria Donnat
 
Pair public final
Pair public finalPair public final
Pair public final
 
GEF Adaptation Program Accessing Financing from the Least Developed Countries...
GEF Adaptation ProgramAccessing Financing from the Least Developed Countries...GEF Adaptation ProgramAccessing Financing from the Least Developed Countries...
GEF Adaptation Program Accessing Financing from the Least Developed Countries...
 
Getting started on the PBB reform agenda in Indonesia – a practical outline o...
Getting started on the PBB reform agenda in Indonesia – a practical outline o...Getting started on the PBB reform agenda in Indonesia – a practical outline o...
Getting started on the PBB reform agenda in Indonesia – a practical outline o...
 
ThinkTank Cities - Assignment 4 - Toronto Baseline Case
ThinkTank Cities - Assignment 4  - Toronto Baseline CaseThinkTank Cities - Assignment 4  - Toronto Baseline Case
ThinkTank Cities - Assignment 4 - Toronto Baseline Case
 
Q2 2015 16
Q2 2015 16Q2 2015 16
Q2 2015 16
 
Aiesec vietnam national award
Aiesec vietnam national awardAiesec vietnam national award
Aiesec vietnam national award
 
Briefing on MIG Expenditure for Select Committee on Appropriations 12 May 2015
Briefing on MIG Expenditure for Select Committee on Appropriations 12 May 2015Briefing on MIG Expenditure for Select Committee on Appropriations 12 May 2015
Briefing on MIG Expenditure for Select Committee on Appropriations 12 May 2015
 
Session Harmonization 3c - Minta kampala seminar 2010
Session Harmonization 3c - Minta kampala seminar 2010Session Harmonization 3c - Minta kampala seminar 2010
Session Harmonization 3c - Minta kampala seminar 2010
 
2nd interim financial report
2nd interim financial report2nd interim financial report
2nd interim financial report
 
BNTF 7 RMF_MIS
BNTF 7 RMF_MISBNTF 7 RMF_MIS
BNTF 7 RMF_MIS
 
EXT PPT.pptx
EXT PPT.pptxEXT PPT.pptx
EXT PPT.pptx
 
3Q earnings presentation geb vf1
3Q earnings presentation geb vf13Q earnings presentation geb vf1
3Q earnings presentation geb vf1
 

Más de Indonesia Infrastructure Initiative

Más de Indonesia Infrastructure Initiative (20)

Presentasi Sanitasi INDII
Presentasi Sanitasi INDIIPresentasi Sanitasi INDII
Presentasi Sanitasi INDII
 
Balikpapan Public Diplomacy 25 May 2015
Balikpapan  Public Diplomacy 25 May 2015Balikpapan  Public Diplomacy 25 May 2015
Balikpapan Public Diplomacy 25 May 2015
 
World experience-in-railway-restructuring
World experience-in-railway-restructuringWorld experience-in-railway-restructuring
World experience-in-railway-restructuring
 
Indonesian railways revitalisation bambang susantono, vice minister for tra...
Indonesian railways revitalisation   bambang susantono, vice minister for tra...Indonesian railways revitalisation   bambang susantono, vice minister for tra...
Indonesian railways revitalisation bambang susantono, vice minister for tra...
 
WS2 Infrastructure Issues
WS2 Infrastructure IssuesWS2 Infrastructure Issues
WS2 Infrastructure Issues
 
Development of multimodal transport in north java corridor
Development of multimodal transport in north java corridorDevelopment of multimodal transport in north java corridor
Development of multimodal transport in north java corridor
 
Railway function in developing multimodal transportation in java
Railway function in developing multimodal transportation in javaRailway function in developing multimodal transportation in java
Railway function in developing multimodal transportation in java
 
The role of ipc in developing multimodal transportation in java
The role of ipc in developing multimodal transportation in javaThe role of ipc in developing multimodal transportation in java
The role of ipc in developing multimodal transportation in java
 
Government strategy in developing multimodal transportation
Government strategy in developing multimodal transportationGovernment strategy in developing multimodal transportation
Government strategy in developing multimodal transportation
 
The role of ferry in developing multimodal transportation
The role of ferry in developing multimodal transportationThe role of ferry in developing multimodal transportation
The role of ferry in developing multimodal transportation
 
Development of multimodal transportation and inter regional connectivitiy
Development of multimodal transportation and inter regional connectivitiyDevelopment of multimodal transportation and inter regional connectivitiy
Development of multimodal transportation and inter regional connectivitiy
 
Ws3 safe system approach (bahasa version)
Ws3 safe system approach (bahasa version)Ws3 safe system approach (bahasa version)
Ws3 safe system approach (bahasa version)
 
Ws3 safe system supporting vru (english version)
Ws3 safe system supporting vru (english version)Ws3 safe system supporting vru (english version)
Ws3 safe system supporting vru (english version)
 
Ws3 safe system supporting vru (bahasa version)
Ws3 safe system supporting vru (bahasa version)Ws3 safe system supporting vru (bahasa version)
Ws3 safe system supporting vru (bahasa version)
 
Ws3 presentation
Ws3 presentationWs3 presentation
Ws3 presentation
 
Ws3 me
Ws3 meWs3 me
Ws3 me
 
Ws3 infrastructure related to pedestrian safety
Ws3 infrastructure related to pedestrian safetyWs3 infrastructure related to pedestrian safety
Ws3 infrastructure related to pedestrian safety
 
Ws3 gender and disability presentation
Ws3 gender and disability presentationWs3 gender and disability presentation
Ws3 gender and disability presentation
 
Ws2 introduction
Ws2 introductionWs2 introduction
Ws2 introduction
 
Workshop #2 safe system approach
Workshop #2 safe system approachWorkshop #2 safe system approach
Workshop #2 safe system approach
 

Último

₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
Diya Sharma
 
Israel Palestine Conflict, The issue and historical context!
Israel Palestine Conflict, The issue and historical context!Israel Palestine Conflict, The issue and historical context!
Israel Palestine Conflict, The issue and historical context!
Krish109503
 

Último (20)

2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
 
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
 
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
 
Julius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the TableJulius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the Table
 
Lorenzo D'Emidio_Lavoro sullaNorth Korea .pptx
Lorenzo D'Emidio_Lavoro sullaNorth Korea .pptxLorenzo D'Emidio_Lavoro sullaNorth Korea .pptx
Lorenzo D'Emidio_Lavoro sullaNorth Korea .pptx
 
Kishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdf
 
30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdf30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdf
 
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's DevelopmentNara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
 
Enjoy Night⚡Call Girls Rajokri Delhi >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Rajokri Delhi >༒8448380779 Escort ServiceEnjoy Night⚡Call Girls Rajokri Delhi >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Rajokri Delhi >༒8448380779 Escort Service
 
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
 
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
 
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
 
How Europe Underdeveloped Africa_walter.pdf
How Europe Underdeveloped Africa_walter.pdfHow Europe Underdeveloped Africa_walter.pdf
How Europe Underdeveloped Africa_walter.pdf
 
Israel Palestine Conflict, The issue and historical context!
Israel Palestine Conflict, The issue and historical context!Israel Palestine Conflict, The issue and historical context!
Israel Palestine Conflict, The issue and historical context!
 
28042024_First India Newspaper Jaipur.pdf
28042024_First India Newspaper Jaipur.pdf28042024_First India Newspaper Jaipur.pdf
28042024_First India Newspaper Jaipur.pdf
 
1971 war india pakistan bangladesh liberation.ppt
1971 war india pakistan bangladesh liberation.ppt1971 war india pakistan bangladesh liberation.ppt
1971 war india pakistan bangladesh liberation.ppt
 
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptxKAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
 
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhEmbed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
 
Enjoy Night⚡Call Girls Iffco Chowk Gurgaon >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Iffco Chowk Gurgaon >༒8448380779 Escort ServiceEnjoy Night⚡Call Girls Iffco Chowk Gurgaon >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Iffco Chowk Gurgaon >༒8448380779 Escort Service
 
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
 

Ind ii program design document-pilot program prim pp presentation 08112012 (formatted)

  • 1. PROPOSED PILOT PROGRAM FOR IMPROVING PROVINCIAL ROAD MAINTENANCE (PRIM) Program Design 08 November 2012
  • 2. Background • Roads are the predominant mode of transport in Indonesia • Sub-national roads comprise 91% of the primary road network in Indonesia • Provincial road 10.2% and Kabupaten/Kota road 80.7% • Investment and maintenance have not kept up with demand – Typically only 51% of sub-national network is in stable condition • Priority tends to be given to new construction/rehabilitation, not (more cost-effective) to maintenance – But more effective asset management is one of 5 key DGH objectives for 2010-2014 • Road Traffic and Transport Law 2009 provides for: – Road Preservation Units/Funds – Road Traffic & Transport Forums (RTTFs) – Clarification of asset management responsibilities 2
  • 3. Lessons Learned from International Experience • Maintenance problem is not unique to Indonesia • Trend to improve accountability and ensure sound road management • Move from force account to maintenance by contract • Move towards results based arrangements for implementation – Output based-will be implemented by PRIM – Performance based • Introduce incentives into funding mechanisms 3
  • 4. Lessons Learned from National Experience 1. EIRTP-2 (World Bank Project 2006-2011)  13 Provinces and 35 Kabupaten using contestibility  20% Routine maintenance per year doesn’t succeed  Low Fiscal Capacity grant/matching fund (90/10); Medium (60/40); High (30/70)  Reimbursement by contract/MC  Reduce financial gap but not sustainable  13 Indicators and 8 indicators have failed to achieved 2. Local Government Decentralized Project /LGDP (WB Project 2011-2013)  6 Provinces and 66 Kabupaten/Kota  Road, Irrigation and water  Verification of Output  Contract and swakelola  RUC too generic 3. EINRIP (AusAID 2008-2013)  Only National Roads  Technical and Financial Audit 4
  • 5. Proposed Pilot Program Objectives • Develop and test a pilot grant program using results based disbursements to improve the condition and connectivity of provincial roads • Sustain and improve the condition and connectivity of provincial roads, with emphasis on better value for money; • Strengthen the existing governance arrangements to promote the adoption of more sustainable and efficient maintenance practices; • Build demand for better governance; and • Demonstrate replicability and sustainability of the proposed approach 5
  • 6. Program Design Document • Provide additional funding for maintenance • Focus on results and greater accountability • Outside oversight by the Donor will be reduced, • Establish a program safeguards and clear criteria for success, fostering trust and efficiency. • Financial incentives for good performance • Coordination between agencies and consultation with the public will be improved through the RTTF, under Road Traffic and Transport Law 22/2009 and PP 37/2011. • Application of recent regulations relating to road maintenance, road design and procurement. 6
  • 7. Why Pilot Provincial Roads? Why NTB? • Key connectivity links between national roads and district roads – 10% of network length and 19% of vehicle-km • Provinces have better institutional capacity than districts – Stronger likelihood of successful implementation • NTB has demonstrated strong support and commitment – Budget support – Adoption of Multi years contract – Institutional support and the role of the RTTF – Demonstrated understanding of output-based concepts • Subsequent program extension: – Extend to other provinces when lessons are learned and mechanism is demonstrated to be effective in the pilot program – Consider possible involvement of additional selected LG 7
  • 8. Justification for NTB 1 - Weak (major deficiencies and outcomes likely) 2 - Moderate (some qualifications) 3 - Strong (few or no qualifications) Kupang NTT Tabanan Overall Bali Execution Preparation KLT Planning KLB NTB 0 1 2 3 8
  • 9. Program Description • Component 1a: Payment of an incentive (approximately A$ 52 million) after verified maintenance of provincial roads. • Routine maintenance (through swakelola- force account and contracts) • Periodic maintenance by overlays or regravelling • Rehabilitation of pavements and structures • All programs to include repair or reconstruction of shoulders, roadside and drainage systems • Costs are preliminary and are presently being revised by interim support consultants 9
  • 10. Program Description(cont’d) • Component 1b: Payment of an Institutional development incentive (approximately A$ 2.6 million) for adopting PPBP and improvement RTTF • Component 2: Institutional strengthening, program management support, monitoring and evaluation, and verification of results ($12 million). • Institutional Strengthening ₋ Training of personnel in provincial government road offices ₋ Capacity to plan, program, budget and implement maintenance works; ₋ Improvements to the swakelola system and mentoring of personnel; ₋ Other Training based on Training Need Analyses Study will be carryout by Implementation Consultant 10
  • 11. Program Description(cont’d) • Implementation support (assisted by IndII consultant) ₋ Technical team to be created by DGH ₋ Project Implementation Unit (PIU) to be created in pilot province • Technical verification of maintenance works as a condition for disbursement • Incentive for adopting and implementing adequate PPBP and effective RTTF • Monitoring and evaluation of the pilot program during implementation and for 3 years afterwards • Note: design and supervision is to be the responsibility of the Province, after improvement of skills (design) and remuneration (supervision) 11
  • 12. COST OF PILOT PROGRAM IN NTB • Maintenance Works-5 years program: $143 million: $52 million incentive from AusAID. • Maintenance Works – 2 years (May 2013 to June 2015): $36.96 million: $13.44 million incentive from AusAID and $23.52 million Prov. contribution • Technical Assistance: $12 million from AusAID (five years) of which $5 million will be incurred 2013 up to June 2015 • Cost of Design and Supervision estimated $ 4 million is assumed to be met by NTB • Total Cost: $159 million; AusAID: $64 million • Incentive for PPBP/RTTF: 5% of works: $2.6 million • Total Potential Contribution from AusAID: $66.6 million 12
  • 13. Estimated Program and Flow of Grant disbursements under Component 1a Total Program and Grant Disbursements (A$)million Net Grant Net Province Fiscal Year Contribution Contribution Program Implemen. APBD (A$) million (A$) million Disb. Disb. 2013/2 11.25 1.23 0.40 1.63 11.65 2014 19.28 2.15 4.97 7.51 11.77 2015/1 6.04 0.66 4.04 4.70 1.34 Sum 1 36.96 4.03 9.41 13.44 23.52 2015/2 17.67 1.93 0.00 1.93 15.75 2016 35.35 3.86 9.00 12.85 22.49 2017 35.35 3.86 9.00 12.85 22.49 2018/1 17.67 1.93 9.00 10.93 6.75 Sum 2 106.04 11.57 26.99 38.56 67.48 Works 130.00 15.60 36.40 52.00 78.00 + VAT 13.00 0 0 0 13.00 Total 143.00 15.60 36.40 52.00 91.00 Notes: 2015/1 means Semester 1 (January – June) of 2015, the completion date of Phase 1 of the Grant 13
  • 14. Budget allocation & grant disbursement • Program value • 2013- June 2015 • July 2015-2018 • Grant contribution • 40% contribution to total program • 60% APBD value • Cash flow • Budget provision (APBD) -Prefinancing 100% until verification and reimbursement is approved • Reimbursement o Advance payment on annual work program value – 30% o Approved work to Verification point (less advance) 14
  • 15. Additional notes 1. Assumes 30% advance on total agreed annual program 2. Advance deducted in proportion to the amount of annual work program approved. 3. Two disbursement dates per year, in May and October 4. For programming purposes base year of 2012 and allowance for 5% physical contingency and 5% per annum price contingency, and a 5% provision for mobilisation etc. 15
  • 16. Program composition 2013- June 2015 • Routine Maintenance contracts  Length 387 Km and Cost A$ 2.73 million • Routine Maintenance Swakelola  Length 696 Km and Cost A$ 16.31 million • Periodic Maintenance  Length 42 Km and Cost A$ 3.13 million • Rehabilitation  Length 43 Km and Cost A$ 14.79 million • TOTAL PROGRAM A$ 36.96 million 16
  • 17. Program of 7 Contracts for 2013-June 2015 Routine Maintenance Periodic Maintenance Rehabilitation No.of Package Name Road Cost Work Work Cost links Cost (A$m) length (A$m) length length (A$m) Rembiga - 3 80 0.57 14 0.87 - 0.49 Bayan Lb Lombok - 2 53 0.22 1 0.15 1 0.55 Biluk Praya - Kruak 1 21 0.17 12 0.79 - 0.08 Sb Pengatap - 2 59 0.54 - 0.15 12 4.46 Kuta -Penunjak Sumbawa 3 71 0.46 5 0.38 - 0.49 Besar Sb Kempo - Sp 1 18 0.16 5 0.31 8 1.81 Kore Tawali - 2 84 0.60 5 0.47 22 6.91 Karumbu Totals 14 387 2.73 42 3.13 43 14.79 17
  • 18. Swakelola Program for 2013- June 2015 Routine Maintenance PPK Group Road length Cost (A$m) Lombok Utara 5 km 0.08 Lombok Barat 95 km 2.14 Lombok Tengah 37 km 0.95 Lombok Timur 105 km 1.91 Sumbawa Barat 3 km 0.04 Sumbawa Timur 111 km 2.16 Bima/Dompu 340 km 9.04 Totals 696 km 16.31 18
  • 19. Program composition July 2015-June 2018 • Routine Maintenance contracts  Length 771 Km and Cost A$ 8.31 million • Routine Maintenance Swakelola  Length 489 Km and Cost A$ 4.81 million • Periodic Maintenance  Length 273 Km and Cost A$ 14.95 million • Rehabilitation  Length 173 Km and Cost A$ 77.96 million • TOTAL PROGRAM FOR 2015-2018 A$ 106.04 million 19
  • 20. Combined Works Programs, 2015 – 2018 Routine Maintenance Periodic Maintenance Rehabilitation No.of links Road Work Cost Cost (A$m) Work length Cost (A$m) length length (A$m) 31 771 km 8.31 273 km 14.95 173 km 77.96 Routine Maintenance, 2015 – 2018 Contracts and Swakelola Routine Maintenance No.of links Road length Cost (A$m) 23 489 km 4.81 20
  • 21. Identification of the PRIM Network In NTB 21
  • 24. Verification of Results and Disbursement • Output eligibility criteria ₋ Compliance with Program Verification ₋ Compliance with national procurement law and regulations ₋ Compliance with technical specifications ₋ Compliance with environmental and social safeguards • Reference Unit Cost/prices-calculated by specific link, condition, treatment (initial and annual) and length (RUC vs contract price) • Technical Team DGH, Ministry of Public Works undertakes Technical Verification supported by a Verification Consultant • Disbursement:  Advance Payment Disbursement (30% of annual Program)  Implementation Disbursement 24
  • 25. Compliance With Program Verification • Proposed works are entered into the provincial Budget or have a formal Cost Analysis (RAB); the date of approval of all budget documents is noted; • The maintenance budget is announced on a website, including location of works; • The procurement documents for Supervision Consultants specify remuneration at INKINDO rates, as well as the personnel’s minimum salary component. 25
  • 26. Compliance With National Procurement Law and Regulations • Presence of Integrity Pact • Availability of Minutes of Pre Bid Meeting • Availability of Bid Evaluation Report • Name of the Winner in an official announcement • Any objections are resolved 26
  • 27. Compliance With Technical Specifications • Quality of Routine Maintenance Plan • Visual Assessment • assessment of Routine Maintenance Works • Road pavement thickness, length and width is consistent with contracts • Quality of surface condition and presence defects at visual assessment • Quality and quantity of asphalt and aggregate base/sub base; soil; road shoulders • Bridge repair works consistent with contracts • Physical progress after 25% and 50% of contract time has elapsed • How about non compliance works?? 27
  • 28. Compliance With Environmental and Social Safeguards • Acceptance of Environmental and Social Safeguard Framework • Fulfilment of environmental monitoring procedure • Implementation of disability provisions in the designs, if applicable 28
  • 29. Risks • Timely availability of annual budget in agreed amounts, where Province has to pre-finance maintenance works • Weak capacity of provincial works department and ineffective coordination • Election year 2013 for Governor • Verification of results • Excess ‘Swakelola’ staff • Capacity of local contractors and consultants • Corruption • Other Risks ₋ Number of Pilot Provinces ₋ Size of Grant ₋ Uncertainity regarding extension of current funding authorisation for IndII and AIIG beyond June 30, 2015 ₋ Availability of additional sources of funding for scaling program ₋ Appointment and funding of design and supervision consultants 29
  • 30. Organisation Chart for Provincial Road Improvement Maintenance/PRIM Australian-Indonesia Infrastructure Initiative/IndII 30
  • 31. Implementation Schedule for PRIM until June 2015 2012 2013 2014 2015 Jan - Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb March April May June July August Sept Oct Nov Dec Jan Feb March April May June July August Sept Oct Nov Dec Jan Feb March April May June DFA PMM NPPH SPPH 1st Output MoF 1st MoF 2nd 3rd Output MoF 3rd 4th Output MoF 4th 2nd Output Verification Payment Payment Verification Payment Verification Payment Grant Verification Subsidiary Grant Preparation incl. LG APBN + Agreement Proposal DIPA (AusAID & (IndII, Bappenas, MoF, Tech. (MoF) MoF) Ministry & LG) RKUD RKUD RKUD RKUD (LG) (LG) (LG) (LG) Plan APBD 2013 (LG) Perda for Road Maintenance Program 2013 - 2018 (incl. PRIM) Establish Tech. Team in DGH DGH Technical Team Support ADD/TOR & Procure Interim Support Consultant Establish PIU DPU Program Implementation Unit (PIU) PRIM Swakelola (Force Account) Routine Maintenance Concept Note Detailed Design & Bid Technical Assistance (TA) & LG Activities Document for Multi- years Procure Contractor PRIM Construction Procure Supervision PRIM Supervision Consultant Consultant Road Traffic & Transport Forum (RTTF) PIU Consultant Monitoring & Evaluation ADD / TOR Procure Technical and Financial Assessment Consultant (TFAC) Training & Institutional Strenghtening 31
  • 32. Critical Path Activity By Deadline Grant Preparation including LG Proposal IndII, Bappenas, MoF, DGH & LG 15 Nov 2012 DIPA for APBN MoF 31 Dec 2012 DPA for APBD 2013 LG 31 Dec 2012 Activity Design Document /ToR IndII & AusAID 30 Nov 2012 Procurement and mobilisation of IndII IndII 28 Feb 2013 Consultant Survey, Prepare Design and Bid Documents IndII Consultant 30 April 2013 for Multi-year Contracts 2013-2015 Procure Contractors LG 30 June 2013 Program Management Manual DGH MPW 30 Nov 2012 Direct Funding Agreement AusAID & DGDM MoF 31 March 2013 Prepare and Issue SPPH (Surat Penetapan DGFB MoF 31 March 2013 Penerusan Hibah) Prepare and Sign PPH (PerjanjianPenerusan DGFB MoF and LG 31 May 2013 Hibah) 32
  • 33. Next Steps • Socialization to NTB for on grant condition 14 Nov 2012 • Establish TT in DGH and PIU in DPU NTB: November 2012 • Program Management Manual Nov 2012 • Statement Letter from Governor of NTB concerning 100% Prefinancing prior reimbursement, PERDA Accelleration 2/PRIM, APBD Budget 2013: Nov 2012 • PERDA Accelleration 2/PRIM: Nov 2012-April 2013 • Procure Preparation and Implementation Project Consultant: December 2012-February 2013 • Prepare project implementation: March-June 2013 • Start Improved Swakelola: May 2013 • Procurement 7 Packages A$ 20.65 million May-June 2013 • Finalize direct funding agreement, grant channeling decree/SPPH: Jan - March 2013 • On Granting Agreement /PPH: April-May 2013 33