RD CONSTRUCTION MANAGEMENT

                                                                       GENERAL DESIGNER
                                                                       GENERAL CONTRACTOR
                                                                       TECHNICAL SUPERVISOR
                                                                       C O N S U LTA N T




125009, 6 Bol. Kislovsky Lane   www.rdcm.com   tel.:+7(495)937 77 48                       fax:+7(495)937 77 49
Contents
  About us
  Functions
  Company Structure
  Management
  Personnel
  Fit out
  Data-Centres




125009, 6 Bol. Kislovsky Lane   www.rdcm.com   tel.:+7(495)937 77 48   fax:+7(495)937 77 49
ABOUT US     INTRODUCTION
                                                                                                                                                                               RD Construction
                                                                                                                                                                               Management




                                                             RD Construction Management today - is a company           working environment that contributes to creation of
                                                             with a solid reputation, won over a long-term, working    corporate success.
                                                             towards the creation of high class o ces.
                                                                                                                      We support the friendship and cooperation with our
                                                             Over the past few years, «RD Construction counterparts and clients whom we know for many
                                                             Management has signi cantly strengthened its years.
                                                             position, having mastered a new market segment for
                                                             itself - the construction of technically complex o ces I want to thank all those who chose us and our
                                                             for major international and Russian companies.           team, and who trusted us - our partners, and most
                                                                                                                      importantly, our customers.
                                Oleg Zhukov                  The desire to break into new paths of development,
                                                             not afraid of di culties, is a critical component of our
                                                             corporate philosophy, which encourages us to never
                                                             rest, but to move foward.

                                                             Our company is client oriented. Understanding
                                                             the requirements and wishes of customers - is our
                                                             professional duty. It is this high quality and standard
                                                             of work that has helped us earn recognition and
                                                             respect of our clients and to take a leading position
                                                             in the market.

                                                             If you are holding our brochure, then you have found
                                                             an excellent company with which the chances of
                                                             successful implementation of your project has
                                                             increased to 100%!
                                                             I'm sure that the investment made into your new
                                                             o ce build by our team will be one of the most best
                                                             investments you can make. Do not hesitate in choosing
                                                             our team - we will save your time and money.

                                                             We guarantee the quality and standards of our
                                                             projects. We rmly believe that projects constructed
                                                             with our team's heart and soul results in high quality




125009, 6 Bol. Kislovsky Lane                 www.rdcm.com                                   tel.:+7(495)937 77 48                                      fax:+7(495)937 77 49
ABOUT US     FUNCTIONS
                                                                                                                               RD Construction
                                                                                                                               Management




                                               We can undertake the following functions

                                               Consultant
                                               RDCM can recommend the correct solutions that
                                               will completely meet your requirements


                                               Design Manager
                                               Linking all project disciplines together


                                               General Planner
                                               Attracting the best designer and architectural bureau,
                                               along with the most experienced engineering
                                               companies to design the future o ce of your
                                               company


                                               General Contractor
                                               We construct everything planned by you from the
                                               concept of the architect and match this to your
                                               quality standards.


                                               Construction Manager
                                               Managing contractors to the most binding controls
                                               and requirements




125009, 6 Bol. Kislovsky Lane   www.rdcm.com                                   tel.:+7(495)937 77 48    fax:+7(495)937 77 49
ABOUT US                                      COMPANY STRUCTURE
                                                                                                                                                                                                                                                                                                                                                                                                                      RD Construction
                                                                                                                                                                                                                                                                                                                                                                                                                      Management



                                                                                                                    General Director of RD Construction Management
                                                                                                                    Zhukov Oleg




                                                                                                                                                                                               Technical Director

                                                                                                                      General
                                                                                                                      Director‘s                                                               Margulis Alexander
                                                                                                                      assistant


                                                                                                                    Samorodova Eugenia




  Marketing                               Contract                                Cost accounting                     Accounting                            Administrative                        Projects performance                                                                                     Engineering                                                                        Quality control and safety
  department                              department                              department                          department                            department                            department                                                                                               department                                                                         department



 Business Development Director            Head of department                                       CFO                Chief accountant                                                           Deputy of General Director                                                                                 Chief Project Engineer                                                           Head of department
                                                                                                                                                                                                 Project Manager


Baybus Ilya                              Somova Olga                                              Avakyan Shogik    Rednikina Marina                      Fotesku Valentina                    Silov Eugine                                                                                              Prokofiev Valeriy                                                                  Babayan Esai
                                                                                                                                                                                                                                                                                                                                                                                            Karavaev Maxim



                                                                                                                                                                                                                Senior                                           Approvals                                 Lead HVAC engineer                      Chief                   Chief
                                                                                                                                                                                                                Project Manager                                  manager                                                                           Electrical              Weak Current
                                                                                                                                                                                                                                                                                                                                                   Engineer                Engineer

                                                                                                                                                                                                              Mikheev Sergey                                   Bakanova Lubove                           Merzliakov Dmitriy                       Chernichenko Dmitriy   Malinkin Oleg




 Engineer              Marketing          Cost                  Cost             Contract          Economist         Accountant           Accountant                                             Project                Project             Project              Project                Purchases and
 Estimator             Specialists        Control               Control          manager                                                                                                         manager                manager             manager              manager                Logistic
                                          Engineer              Engineer                                                                                                                                                                                                                Specialist

Kompanichenko Gala   Barashenko Andrey   Kostuchkova Marina    Shemyakova Anna   Maseykin Peter   Kochergina Liza   Kycher Sveta         Kadeykina Vera                                        Karavaev Maxim          Zvantsov Anton     Pokrovsky Nickolay   Denisov Sergey         vacancy
                     James Byrne                                                                  Sverchkova Anna
                     Alexander Semenov

                                                                                                                                                            Secretary           Courier          Site managers          Site managers       Site manager         Site manager           Purchases         Mechanical             Mechanical        Deputy of Chief        Security           SCS and TV/AV         IT
                                                                                                                                                                                /Drivers                                                                                                managers          Engineer               Engineer          Electrical             Systems            Systems               Engineer
                                                                                                                                                                                                                                                                                                                                                   Engineer               Engineer           Engineer

                                                                                                                                                          Tichanova Alla      Suntsov Yuriy    Kudimov Igor           Telminov Nickolay   Ilatovsky Sergey     Petrachkov Alexander   Kasimova Lilya     Pavlovsky Yurek        Dvornikov Juriy   Mauricio Nino          Bredikhin Leonid   vacancy               Chaycowskiy Ilya
                                                                                                                                                          Usarova Dasha       Sajnev Dmitriy   Zvyagin Ivan           Mikheev Alexander                                               Kurilo Alexander                                            Balikin Nickolay




125009, 6 Bol. Kislovsky Lane                                                                         www.rdcm.com                                                                                                             tel.:+7(495)937 77 48                                                                                                 fax:+7(495)937 77 49
ABOUT US                   MANAGEMENT
                                                                                                                                                                                                                 RD Construction
                                                                                                                                                                                                                 Management




 Oleg Zhukov                                              Alexander Margulis                                        Eugene Silov                                          Ilya Baybus
 General Director                                         Technical Director                                        Deputy General Director                               Business Development Director


 Graduated from Moscow Road Construction                  Graduated from Moscow Engineering and                     Graduated from Moscow Road Construction Institute Graduated from Moscow State University of Foreign
 institute (MMRI), faculty of Construction of roads and   Construction Institute (MECI, Hons). The second           (MMCI).                                           A airs (MGIMO) (U) of the Ministry of Foreign
 airdromes. After graduation from MMRI relocated to       highest educational award attained in the Moscow          1996-2003 – Engineering Manager at Hines          A airs of Russia, “International business and
 Italy entered postgraduate course in Vicenza (Italy).    Management Institute (MMI). 1992 Director of              International.                                    business administration” faculty. After conferral
                                                          Engineering services at Hines International. A very                                                         of a Management and Marketing Master’s degree
                                                          experienced specialist with up to 30 years in the                                                           he worked as a Head of the Ventilation and
                                                          construction business.                                                                                      Conditioning for a large Engineering company from
                                                                                                                                                                      2002.




                                                                                                                                                                           ''The goal of our company is to create a unique
                                                                                                                                                                          product of high-class quality o ces. Our team
                                                                                                                                                                          has the ability to solve tasks of di cult complexity.
                                                                                                                                                                          Our Specialists reply to all the questions: the
''RD Construction Management is a company                   ''Our long-term aim is the build cooperation and        '' The main purpose of our RDCM’s activity is to      more complex and more di cult the project is
 oriented to provide the Customer with the desired        partnership relationships with our Customers, based        provide a nished project with maximal comfort        the more attractive and challenging it is to RDCM.
 coordinated result and within the approved budget.       on trust and open communications. We o er a                and safe conditions for the business activities of   We strive for experience and knowledge, strive
 Our close-knit team of quali ed specialists can solve    high-quality service at all stages of construction of A    the Customer and his clients. Our specialists are    to create a quality product and at the same time
 tasks of technical complexity. This accumulated          class real estate construction from development to         prepared to render quali ed assistance to solve a    develop partnership relations with our Customers
 experience and knowledge permits RDCM to work            concept to its commercial realization”                     client’s problems and complete the given tasks.      which is the recipe of success of RD Construction
 in di erent areas, such as capital construction,                                                                                                                         Management.''
 designing and nishing works''


125009, 6 Bol. Kislovsky Lane                        www.rdcm.com                                                      tel.:+7(495)937 77 48                                     fax:+7(495)937 77 49
ABOUT US                     PROJECT STRUCTURE
                                                                                                                                                                                                                                              RD Construction
                                                                                                                                                                                                                                              Management




                                                                                                                                  GENERAL DIRECTOR




                CLIENTS                                                   PROJECT LEADER                                                                                   TECHNICAL DIRECTOR
                REPRESENTATIVE


              • Cooperation with the client's                         •   Coperation with all project participants                                                     •   Technical concept design
                representative. One point                             •   Holding meetings draw up actional minutes                                                    •   Supervision of the technical aspects of the project
                of contact principle.                                 •   Prepare and present progress reports                                                         •   Formulate technical tasks
                                                                      •   Manage the ongoing project                                                                   •   Technical Project audit
                                                                      •   Cordination of the ongoing works




 SITE MANAGER                  OCCUPATIONAL                TECHNICAL AND CON                APPROVALS AND                   PURCHASE AND                   MECHANICAL                         ELECTRICAL                         LOW VOLTAGE
                               HEALTH AND SAFETY           STRUCTION                        COMPLIANCE SPE                  LOGISTICS                      SYSTEMS                            ENGINEER                           SYSTEMS
                               ENGINEER                    SUPERVISORY ENGI                 CIALIST                         SPECIALIST                     ENGINEER                                                              ENGINEER
                                                           NEER
 • Cordination on site.        • H&S instructions          •   Site Supervision             • Contracts and                 • Purchase and delivery        •   Ventilation                    • Power Supply                     •   Structured cabling systems
 • Operational management      • Monitor and adherance     •   Hidden Works                   document approvals              of materials to site         •   Air conditioning               • Lighting systems                 •   IT
   of the site                   to work regulations       •   Quality Control              • Work with local authorities   • Liase with suppliers         •   Plumbing systems                                                  •   Fire alarm systems
 • Cooperation with              and safety on site.       •   Acceptance works                                                                            •   Fire supression systems                                           •   Security systems , CCTV
   local authorities
 • Keep and update local
   authorities work log.




                                                                                                                                      • Quality control of materials and equipment
                                                                          QUALITY CONTROL ENGINEER                                    • Quality control and inspection of works
                                                                                                                                      • Maintain quality log and snag lists




125009, 6 Bol. Kislovsky Lane                            www.rdcm.com                                                          tel.:+7(495)937 77 48                                                   fax:+7(495)937 77 49
ABOUT US                    REALISED PROJECTS
                                                                                                                                                                                                            RD Construction
                                                                                                                                                                                                            Management




 Romanov Dvor Business Centre                         Troika Dialog                                         Mannheimer Swartling                                    Media Park Aif

 Address 4 Romanov Lane                               Address     4 Romanov Lane, Romanov Dvor BC           Address     4 Romanov Lane Romanov Dvor BC              Address     27 Electrozavodskaya St, LeFort BC
 Size     65 000 m2                                   Size        3 000 m2                                  Size        800 m2                                      Size        10 500 m2
   Romanov Dvor, 1 stage — 15 000 m2                  Timeline    02.2007-05.2007                           Timeline    04.2008-04.2008                             Timeline    07.2008-01.2009
   Romanov Dvor, 2 stage — 35 000 m2                  Functions   General Contractor                        Functions   General Contractor                          Functions   General Contractor
   Romanov Dvor, 3 stage — 15 000 m2
 Time Line
   Romanov Dvor, 1 stage — 1998-2001                  Rectors House Romanov Dvor                            Total System Services – RUS (TSYS)                      Troika Dialog
   Romanov Dvor, 2 stage — 2001-2003
   Romanov Dvor, 3 stage — 2009-ongoing               Address   11 Mohovaya St. bld.6                       Address     18/20 Zvenigorodskoe Ave, BC «NPO Rodina»   Address     Kislovsky lane 6, BC «Lucine»
 Functions General Planner, General Contractor        Size       3 500 m2                                   Size        1 200 m2                                    Size        3 000 m2
                                                      Timeline   2003-2006                                  Timeline    10.2008-12.2008                             Timeline    10.2007-12.2007
                                                      Functions General Contractor                          Functions   General Contractor                          Functions   General Contractor
 Val Des Roses, Luxemburg
 Address      Strassen, Grand-Duche de Luxemburg,     East Capital International AB                         Aeroclub / BCD Travel
              Val Des Roses                                                                                                                                         L’Oreal
 Size         2 600 m2                                Address     4 Romanov Lane, Romanov Dvor              Address     12 Ribinskaya St, Burevestnik BC
 Time Line    10.2008-08.2009                         Size        1 400 m2                                  Size        2 200 m2                                    Address 1st Golutvinskiy lane, BC «Golutvinskaya
 Functions    Consultant and advisor                  Timeline    08.2007-12.2007 / 05.2007-08.2007         Timeline    11.2008-01.2009                               Sloboda»
                                                      Functions   General Constractor                       Functions    General Contractor                         Size       7 000 m2
 Kellogg Brown & Root                                                                                                                                               Timeline 2.2007-04.2008
                                                                                                                                                                    Functions General Contractor
 Address     8 Arbat, Midland Plaza                   Carcade Leasing                                       Kraft Foods                                                        Design & Build
 Size        1 300 m2
 Timeline    02.2007-05.2007                          Address     21 Stanislavskogo St. Stanislavskogo BC   Address     7 Dolgorukovskaya str. Sadovaya Plaza BC    Baker&McKenzie
 Functions   General Contractor                       Size        2 400 m2                                  Size        4 300 m2
                                                      Timeline    01.2008-04.2008                           Timeline    09.2008-08.2009                             Address     Dolgorukovskaya str. 7, BC «Sadovaya Plaza»
                                                      Functions   General Contractor                        Functions   General Contractor                          Size        3 700 m2
                                                                                                                                                                    Timeline    09.2008-02.2009
 Wrigley                                                                                                                                                            Functions   General Contractor
                                                                                                            Johnson&Johnson
 Address Rublevo-uspenskoe Avenue, Moscow BC
   «Residence on Rublevka»                                                                                  Address     27 Pirogovskaya St, Luch BC
 Size      4 000 m2                                                                                         Size        940 m2
 Timeline  08.2007-12.2007                                                                                  Timeline    05.2009-08.2009
 Functions General Contractor                                                                               Functions   General Contractor



125009, 6 Bol. Kislovsky Lane                       www.rdcm.com                                               tel.:+7(495)937 77 48                                      fax:+7(495)937 77 49
ABOUT US                     REALISED PROJECTS
                                                                                                                                                                                                  RD Construction
                                                                                                                                                                                                  Management



Novatek                                              Nycomed                                       Honeywell                                            Troika Dialog

Address     2 Udalcova Street                        Address       2-1 Usacheva St                 Address      8 Kievskaya, Legion III BC              Address     18/20 Zvenigorodskoe , NPO Rodina BC
Size        12 730 m2                                Size          4 200 m2                        Size         2 800 m2                                SIze        1 200 m2
Functions   General Contractor                       Functions     General Contractor              Functions    General Contractor                      Functions   General Contractor        Data Centre



BC «Rector’s house»                                  TSYS                                          KBR                                                  Linxtelecom
                                                                   Zvenigorodkoe ave 18/20                                                              Address 8th of March St 14
            11 Mohovaya St                           Address
Address                                                                                            Address      8 Arbat St                              Size      2 500 m2
Size        3 500 m2                                 Size          1 200 m2                        Size         1 200 m2
                                                                   General Contractor                                                                   Functions General Contractor
Timeline    2003-2006                                Functions                                     Functions    General Contractor                                                             Data Centre
Functions   General Contractor


Baker&McKenzie                                      East Capital International AB                  Hemofarm                                             Nokia Siemens Networks

                                                                                                   Address 27 Electrozavodskaya St, Lefort BC           Address     21 stanislavkogo Street
Address     7 Dolgorukovskaya , Sadovaya Plaza BC   Address      4 Romanov Lane, Romanov Dvor BC                                                        Size        5 000 m2
Size        3 700 m2                                                                               Size      1 000 m2
                                                    Size         1 400 m2                                                                               Functions   General Contractor
Functions   General Contrator                                                                      Functions General Contractor
                                                    Functions    General Contractor
                                                                                                                                                                                               Data Centre


L’Oreal                                             Credit Suisse                                  Troika Dialog                                        Otkritie
Address Golutvinskiy Ln, Golutvinskaya Sloboda BC                                                                                                       Address 12/1Yakovoapostalskiy lane
                                                    Address   Romanov lane 4, Romanov Dvor BC      Address      Kislovsky lane 6, BC «Lucine»
SIze      7 000 m2                                                                                                                                      Size      1100 m2
                                                    Size      1 700 m2                             Size         3 000 m2
Functions General Contractor                                                                                                                            Functions General Contractor
                                                    Functions General Contractor                   Functions    General Contractor
                                                                                                                                                                                               Data Centre

Correa’s                                            AirClub / BCD Travel                            Etihad Airways                                      Alcatel-Lucent
Address 4 Romanov Lane, Romanov Dvor BC             Address      12 Ribinskaya, Burivestnik BC     Address     27 Serebrianicheskaya , Silver City BC   Address     27 Electrozavodskaya St. LeFort BC
Size      700 m2                                    Size          2 200 m2                         Size        250 m2                                   Size        3800 m2
Functions Design & Build                            Functions     General Contractor               Function    General Contractor                       Timeline    07.2009-09.2009
                                                                                                                                                        Functions   General Contractor
                                                                                                                                                                                              Data Centre



125009, 6 Bol. Kislovsky Lane                       www.rdcm.com                                         tel.:+7(495)937 77 48                                      fax:+7(495)937 77 49
DELIVERED PROJECTS    JOHNSON&JOHNSON TVCI
                                                                                                              RD Construction
                                                                                                              Management




    Address:
            27/4 Bolshoya Pirogvskaya
            Luch Business Centre

    Size:
            940 m2

    Timeline:
            06-2009 - 09-2009

    Functions:
            General Contractor




125009, 6 Bol. Kislovsky Lane            www.rdcm.com          tel.:+7(495)937 77 48   fax:+7(495)937 77 49
DELIVERED PROJECTS    HONEYWELL
                                                                                                                  RD Construction
                                                                                                                  Management




    Address:
            Legion 3 business centre
            7 Kieveskaya Street

    Size:
            2800 m2

    Timeline:
            03-2010 - 07-2010

    Functions:
            General Contractor




125009, 6 Bol. Kislovsky Lane                 www.rdcm.com         tel.:+7(495)937 77 48   fax:+7(495)937 77 49
DELIVERED PROJECTS    NYCOMED
                                                                                                                 RD Construction
                                                                                                                 Management




         Address:
                 2/1 Usacheva Street

         Size:
                 4 200 m2

         Timeline:
                 09-2010 - 12-2010

         Functions:
                 General Contractor




125009, 6 Bol. Kislovsky Lane                www.rdcm.com         tel.:+7(495)937 77 48   fax:+7(495)937 77 49
DELIVERED PROJECTS   CORREAS
                                                                                                          RD Construction
                                                                                                          Management




   Address:
        4 Romanov Lane

   Size:
           700 m2

   Timeline:
        10-2010 - 11-2010

   Functions:
        General Contractor




125009, 6 Bol. Kislovsky Lane         www.rdcm.com         tel.:+7(495)937 77 48   fax:+7(495)937 77 49
DELIVERED PROJECTS         ETIHAD AIRWAYS
                                                                                                                 RD Construction
                                                                                                                 Management




                         Address:
                              27 Serebyanicheskaya

                         Size:
                                 250 m2

                         Timeline:
                              08-2010 - 10-2010

                         Functions:
                              General Contractor




125009, 6 Bol. Kislovsky Lane               www.rdcm.com          tel.:+7(495)937 77 48   fax:+7(495)937 77 49
DELIVERED PROJECTS           EAST CAPITAL
                                                                                                                    RD Construction
                                                                                                                    Management




                            Address:
                                  Romanov Dvor BC

                            Size:
                                    1000 m2

                            Timeline:
                                   55 days
                                   04-2008 - 07-2008

                            Functions:
                                  General Contractor




125009, 6 Bol. Kislovsky Lane                 www.rdcm.com           tel.:+7(495)937 77 48   fax:+7(495)937 77 49
DELIVERED PROJECTS   MANNHEIMER SWARTLING
                                                                                                            RD Construction
                                                                                                            Management




      Address:
            4 Romanov Lane

      Size:
              600 m2

      Timeline:
             55 days
             04-2008 - 07-2008

      Functions:
            General Contractor




125009, 6 Bol. Kislovsky Lane          www.rdcm.com          tel.:+7(495)937 77 48   fax:+7(495)937 77 49
DELIVERED PROJECTS      AIF
                                                                                                                 RD Construction
                                                                                                                 Management




        Address:
               27 Elecktrozovodkaya Street
        Size:
               10 500 m2

        Timeline:
               07-2008 - 04-2009

        Functions:
               General Contractor




125009, 6 Bol. Kislovsky Lane                www.rdcm.com         tel.:+7(495)937 77 48   fax:+7(495)937 77 49
DELIVERED PROJECTS      BAKER & MCKENZIE
                                                                                                                RD Construction
                                                                                                                Management




     Address:
          7 Dolgorukovskaya Street
          Sadovaya Plaza Business Centre

     Size:
             3 600 m2

     Timeline:
         12-2008 - 03-2009

     Functions:
         General Contractor




125009, 6 Bol. Kislovsky Lane              www.rdcm.com          tel.:+7(495)937 77 48   fax:+7(495)937 77 49
DELIVERED PROJECTS    AIRCLUB /BCD TRAVEL
                                                                                                              RD Construction
                                                                                                              Management




     Address:
          12 Ribinskaya
          Burevestnik Business Centre

     Size:
             2 400 m2

     Timeline:
           11-2008 - 01-2009

     Functions:
          General Contractor




125009, 6 Bol. Kislovsky Lane           www.rdcm.com           tel.:+7(495)937 77 48   fax:+7(495)937 77 49
DELIVERED PROJECTS   KRAFT FOODS
                                                                                                              RD Construction
                                                                                                              Management




        Address:
             7 Dolgorukovskaya St
             Sadovaya Business Centre

        Size:
                3 800 m2

        Timeline:
               01-2009 - 05-2009

        Functions:
              General Contractor




125009, 6 Bol. Kislovsky Lane            www.rdcm.com          tel.:+7(495)937 77 48   fax:+7(495)937 77 49
DELIVERED PROJECTS      TSYS CARD TECH
                                                                                                              RD Construction
                                                                                                              Management




       Address:
            18-20 Zvenigorodskoe Shosee

       Size:
               1 200 m2

       Timeline:
            10-2008 - 11-2008

       Functions:
           General Contractor




125009, 6 Bol. Kislovsky Lane             www.rdcm.com         tel.:+7(495)937 77 48   fax:+7(495)937 77 49
DELIVERED PROJECTS   WRIGLEY
                                                                                                             RD Construction
                                                                                                             Management




       Address:
            100 Rubleveke shosse
             Residenziya BC

       Size:
               4 000 m2

       Timeline:
              11-2007 - 12-2007

       Functions:
             General Contractor




125009, 6 Bol. Kislovsky Lane            www.rdcm.com         tel.:+7(495)937 77 48   fax:+7(495)937 77 49
DELIVERED PROJECTS                        TROIKA DIALOG
                                                     Data Centre                                                                 RD Construction
                                                                                                                                 Management




                                 Address: 2 Romanov Lane
                                 Size: Total Area               2500 m2
                                       Data Center (260 kVA) 210 m2
                                      Trading Floor             980 m2
                                       Back O ce               1320 m2
                                 Description: Tier 4 Data Centre
                                 Timeline: Design Stage 42 Weeks
                                            Execution        9 Weeks
                                            Fine Tuning      5 weeks
                                   75 C-days (01.03.2007-14.05.2007)
                                    including dealing center and back
                                    o ce
                                 Functions: General Contractor
                                              Design and Build
                                              Equipment Supplier
                                 Major engineering systems installed:
                                   - active & cross-connect equipment
                                    UPS, RC-units APC (Ireland)
                                   - chillers – HITACHI (Spain)
                                   - dry coolers Gunter (Germany)
                                   - diesel-generators VOLVO
                                    (Sweden)
                                   - building management systems
                                    (BMS) – Computrols (USA)




125009, 6 Bol. Kislovsky Lane                 www.rdcm.com                        tel.:+7(495)937 77 48   fax:+7(495)937 77 49
DELIVERED PROJECTS       TROIKA DIALOG
                                                                                                                RD Construction
                                           Data Centre                                                          Management




125009, 6 Bol. Kislovsky Lane          www.rdcm.com              tel.:+7(495)937 77 48   fax:+7(495)937 77 49
DELIVERED PROJECTS                           LINXTELECOM
                                                                                                                                   RD Construction
                                                     Data Centre                                                                   Management




                                 Address: Ul. The 8th of March, «Kulon»
                                 industrial estate
                                 Size: 2 500 m2 (critical power 800 kVA)
                                 Description: Tier 3 Data Centre
                                 Timeline: 140 C-days (13.05.09-
                                 30.09.09)
                                 Functions: General Contractor
                                             Design and Build
                                             Equipment Supplier
                                 Major engineering systems installed:
                                   - close control AC – STULZ (Germany)
                                   - dry coolers – Gunter (Germany)
                                   - PDU – ABB (Russia)
                                   - RC-units – APC (France)
                                   - diesel-generators – Wilson (England
                                    GB)
                                   - building management systems
                                    (BMS) – Computrols (USA)
                                 Challenges and solutions:
                                      The project special feature was a
                                    complicated and multistage process
                                    of balancing, commissioning, and
                                    start-up under the terms of electrical
                                    power de cit. We also met the tough
                                    requirements of the potential data-
                                    center tenant – one of the biggest
                                    international IT providing company.




125009, 6 Bol. Kislovsky Lane                 www.rdcm.com                          tel.:+7(495)937 77 48   fax:+7(495)937 77 49
DELIVERED PROJECTS       LINXTELECOM
                                           Data Centre                                                         RD Construction
                                                                                                               Management




125009, 6 Bol. Kislovsky Lane          www.rdcm.com             tel.:+7(495)937 77 48   fax:+7(495)937 77 49
DELIVERED PROJECTS                           NOKIA SIEMENS NETWORKS
                                                                                                                                   RD Construction
                                                     Data Centre                                                                   Management




                                 Address: 26 Ul. Stanislavskogo, bl. 13,
                                 Business Center « Stanislavskii»
                                 Size: 145 m2 (critical power 225 kVA)
                                 Description: Test Bed Laboratory
                                 Timeline: 02-2010 - 04-2010
                                 Functions: General Contractor
                                              Design and build
                                 Major engineering systems installed:
                                     - active equipment, communication
                                    equipment and UPS Eaton Power
                                    Ware (USA)
                                   - precision air conditioner – Uni air
                                    (Italy)
                                   - dry coolers – Uni air (Italy)
                                   - PDU – ABB (Russia)
                                   - automated gas re- ghting system
                                    Eusebi Impianti (Italy)
                                 Challenges and solutions:
                                     A special metal structure was
                                    installed around the racks for the
                                    electrical and data cabling traces.
                                    We will utilise this universal method
                                    when we are in situations where it’s
                                    impossible to stack cable trays to the
                                    ceiling.




125009, 6 Bol. Kislovsky Lane                 www.rdcm.com                          tel.:+7(495)937 77 48   fax:+7(495)937 77 49
DELIVERED PROJECTS                         ALCATEL LUCENT
                                                                                                                                 RD Construction
                                                   Data Centre                                                                   Management




                                  Address: 27 Electrozavodskaya Street
                                            LeFort Business Centre
                                  Size: 136 m2 (critical power 90 kVA)
                                  Description: Test bed labratory
                                  Timeline: 91 C-days from start to nish
                                  (07.07.09-08.10.09)
                                  Functions: General Contractor
                                  Major engineering systems installed:
                                    - Close control AC units with remote
                                     condenser – TRANE (GB)
                                    - PDU – ABB (Russia)
                                    - UPS – APC
                                    - gas suppression «Automatic re-
                                      ghting equipment and service»
                                     (Russia)
                                  Challenges and solutions:
                                       The test bed cooling system was
                                     operating in conditions where air
                                     temperature in the summer of 2010
                                     was extreme. This bears witness
                                     of the proper choice of the cooling
                                     system equipment.




125009, 6 Bol. Kislovsky Lane                www.rdcm.com                         tel.:+7(495)937 77 48   fax:+7(495)937 77 49
ONGOING PROJECTS                           ROMANOV DVOR DATA CENTRE
                                                                                                                                  RD Construction
                                                   Data Centre                                                                    Management




                                Address: 2-4 Romanov Lane
                                Size:
                                Timeline: in progress
                                Functions: General Planner
                                       General Contractor
                                       Technical supervisor
                                  Major engineering systems installed:
                                  Power range 1210 kVa
                                  on active Equipment 720 kVa
                                  on accessory equipment 490 kVa
                                  Parameter PUE 1,68
                                  DPC Provides:
                                  1. Two independent inputs from TP
                                     25345
                                  2. TP is powered by PS 834
                                  Zubovskaya (CHP 12) and PS 655
                                  Nikita (GES 1)
                                  3.Reservation inputs provided from
                                  diesel power plant consisting of three
                                  DSU capacity of 700 kVA each.DSU
                                  backup scheme N+1
                                  4. Active and auxiliary equipment is
                                  connected through three UPS 660
                                  kVA, Reserved for N+1
                                  5. Means the connection counters on
                                  two boards PDU, N+1 redundancy
                                  scheme
                                  Working Time UPS – seven Minutes
                                Challenges and solutions:
                                  Time to start the diesel generator set
                                  rated capacity 50 seconds. All active
                                  and auxiliary equipment connected to
                                  UPS.
                                  Repair work on any element of the
                                  power supply system can be carried
                                  out at any time without disconnecting
                                  the load.



125009, 6 Bol. Kislovsky Lane               www.rdcm.com                           tel.:+7(495)937 77 48   fax:+7(495)937 77 49
CAPITAL CONSTRUCTION                              ROMANOV DVOR BUSINESS STAGE 3
                                                                                                                              RD Construction
                                                       Capital Const                                                          Management




                                Address:
                                        4 Romanov Lane

                                Size:
                                        15 000 m2

                                Timeline:
                                            2005 - to date

                                Functions:
                                        General Planner
                                        General Contractor
                                        Technical supervisor




125009, 6 Bol. Kislovsky Lane                    www.rdcm.com                  tel.:+7(495)937 77 48   fax:+7(495)937 77 49
CAPITAL CONSTRUCTION          ROMANOV DVOR BUSINESS STAGE 3
                                                                                                          RD Construction
                                   Capital Const                                                          Management




125009, 6 Bol. Kislovsky Lane   www.rdcm.com               tel.:+7(495)937 77 48   fax:+7(495)937 77 49
CAPITAL CONSTRUCTION                                  VAL DES ROSES, LUXEMBURG
                                                                                                                                 RD Construction
                                                     Capital Const                                                               Management




                                Address:
                                         70, Grand Rue L-1660 Luxembourg

                                Size:
                                         2600 m2
                                         22 apartments

                                Timeline:
                                        04-2007 - 10-2009

                                Functions:
                                    General Planner
                                    Consultant




125009, 6 Bol. Kislovsky Lane                   www.rdcm.com                      tel.:+7(495)937 77 48   fax:+7(495)937 77 49
CAPITAL CONSTRUCTION          VAL DES ROSES, LUXEMBURG
                                                                                                         RD Construction
                                   Capital Const                                                         Management




125009, 6 Bol. Kislovsky Lane   www.rdcm.com              tel.:+7(495)937 77 48   fax:+7(495)937 77 49
REFERENCES
                                                                                                                                                                                                                                                              RD Construction
                                                                                                                                                                                                                                                              Management


                                                                                                CURRENT AND REALIZED PROJECTS
                                                                                                           1. Current projects

                                                                    Project       Area          Address           Timing                       Functions                Contact name                    Contact details

                                                               BC “ Romanov
                                                               Dvor “                                              2006-now                General Contractor,          RD Group own
                                                               Romanov Dvor,                4 Romanov Lane
                                               Capital Const   3 stage
                                                                                  15 000                                                   Engineering design              project

                                                                                                                                                                           Valentin                     kolchin@novatek.ru
                                                               NOVATEK            12 000    2 Udalzova Str.      06.2010-04.2011           General Contractor                                            +7 985 762 7119
                                                                                                                                                                            Kolchin
                                                                                                                                                                             Petr                  petr.adamiants@philips.com
                                                                                                                                                                          Adamyanz                       +7 985 769 02 71
                                                                                            13 Sergeya                                                                      Senior
                                                               Philips            5 050                          11.2010-03.2011           General Contractor
                                                                                            Makeeva                                                                       manager of
                                                                                                                                                                         procurement
                                                                                                                                                                          department
                                                                                                                                                                                                   dkmoon21@samsung.com
                                                                                                                                                                          Duck Kyu                    7 (985) 764 6376
                                                               Samsung            5 100     10 Vozdvizhenka      03.2011-06.2011           General Contractor
                                                                                                                                                                           Moon
                                                                                                                                                                            Irina                  stepanovaster@gmail.com
                                                                                                                                                                         Stepanova,                    +7 (495) 760-4278
                                                               Sotheby’s           200      4 Romanov Lane       01.2011-04.2011           General Contractor
                                                                                                                                                                          General
                                                                                                                                                                          Director
                                                                                                                                                                                                       alt@belovskaya.ru
                                                                                            4/7 bld 2                                                                     Aleksey                      +7 916 546 27 20
                                                               Karakan-Invest     1 150                          04.2011-07.2011           General Contractor
                                                                                            Vozdvizhenka                                                                  Tokanov




                                                                                                          2. Realized projects

                                                                    Project          Area           Address             Timing                      Functions                     Contact name                    Contact details

                                                               BC “Romanov
                                               Capital Const   Dvor”
                                                                                  65 000
                                                               Romanov Dvor,                                                                     General Contractor,
                                                                                  15 000     4 Romanov Lane                                                                 RD Group own project
                                                               1 stage                                                  1998-2001                Engineering design
                                                               Romanov Dvor,
                                                                                  35 000
                                                               2 stage                                                  2001-2003
                                               Capital Const   BC “Rektorskiy
                                                                                   3 500     11/6 Mohovaya Str.         2003-2006                General Contractor         RD Group own project
                                                               Domik “
                                                                                                                                                                                                       sergey.¿limonov@credit-suisse.com
                                                               Credit Suisse       1 700     4 Romanov Lane             10.2010-02.2011          General Contractor           Sergey Fillimonov                  +7 495 967 8200
                                                                                                                                                 General Contractor,                                   Ekaterina.grebenikowa@nycomed.
                                                                                                                                                 Engineering project            Grebennikova                           com
                                                               Nycomed             4 200     2/1 Usacheva Str.          09.2010-12.2010
                                                                                                                                                 adaptation, working              Ekaterina                      +7 915 136 75 74
                                                                                                                                                 Architectural design
                                                                                                                                                 General Contractor,         Alexand r Pelenev                 pelenev@open.ru
                                                                                             12/1 Yakovoapostolskiy
                                                               FC OTKRITIE         5 050                                10.2010-12.2010            Architectural &               Deputy of                     +7 903 752 42 42
                                                                                             Lane
                                                                                                                                                 Engineering design         Administrative director
                                                                                                                                                 General Contractor,                                     Vitaly_Koulmanakov@avica.pro
                                                               Cafetera             700      4 Romanov Lane             08.2010-10.2010            Architectural &            Kulmanakov Vitaliy                +7 495 287 18 18
                                                                                                                                                 Engineering design
                                                                                                                                                                                                            NGoryunova@etihad.ae
                                                               Etihad Airways       250      27 Serebryanicheskaya      08.2010-10.2010           General Contractor         Nataliya Gorunova                +7 905 710 0812
                                                                                             “Val Des Roses”                                                                                                 seva99@yandex.ru
                                                               “Val Des Roses”,                                                                                             Vsevolod Yampolskiy
                                                                                   2 600     Strassen, Grand-Duche      10.2008-08.2010           General Contractor                                          +352-621-168969
                                                               Luxemburg                                                                                                      General Director
                                                                                             de Luxemburg
                                                                                                                                                                                                            elena.sopova@nsn.com
                                               Data Centre     Nokia Siemens                                                                  General planner, General
                                                                                   5 000     21 Stanislavskogo Str.     02.2010-04.2010                                         Elena Sopova                   +7 925 507 70 17
                                                               Networks                                                                             Contractor
                                                                                                                                                                                                         igor.zolotaryev@honeywell.com
                                                                                             Legion III                                          General Contractor,                                             +7 495 796 9817
                                                               Honeywell           3 600                                03.2010-06.2010                                         Igor Zolotarev
                                                                                             7 Kievskaya Str.                                    Development project

                                                                                                                                                                              Kvasnikov Igor                igor_kvasnikov@troika.ru
                                                                                             4 Romanov Lane                                                                                                    +7 (495) 258-0500
                                               Data Centre     Troika Dialog       3 500
                                                                                             4th Àoor
                                                                                                                        11.2009-01.2010          General Contractor             Deputy of
                                                                                                                                                                           Administrative Director
                                                                                                                                                                                                        Milos.Davidovic@hemofarm.com
                                                                                             BC “LeFort” 27                                                                  Milosh Davydovich
                                                               Hemofarm            1 000                                11.2009-01.2010          General Contractor
                                                                                             Electrozavodskaya Str.                                                           General Director

                                                                                                                                                                               Shmel’kov Andrej         Andrey.Shmelkov@alcatel-lucent.
                                                                                             BC “LeFort” 27                                                                                                            com
                                                               Alcatel-Lucent      4500                                 07.2009- 12.2009         General Contractor         Director Administrative
                                                                                             Electrozavodskaya Str.                                                                                             +7 (915) 278 0488
                                                                                                                                                                                 Department
                                                                                                                                                                                                         alexandr.maslov@linxtelecom.com
                                               Data Centre                                   Ul. The 8th of March
                                                               Linxtelecom        2 500                                 05.2009- 09.2009         General Contractor           Alexand r Maslov                    +79857278608




125009, 6 Bol. Kislovsky Lane   www.rdcm.com                                                                     tel.:+7(495)937 77 48                                                                                                 fax:+7(495)937 77 49
REFERENCES
                                                                                                                                                                                                                                         RD Construction
                                                                                                                                                                                                                                         Management




                                                                                                                                                              Vagin Konstantin,              vagin@aif.ru
                                                                                         BC “LeFort” 27                               General Contractor,                                 +7 (903) 974-0669
                                                             Mediapark “AiF”    10 500                              07.2008-01.2009                           Deputy of General
                                                                                         Electrozavodskaya Str.                       Engineering design
                                                                                                                                                                  Director
                                                                                                                                                                                    Laird.Cenotto@BAKERNET.com
                                                                                                                                      General Contractor,
                                                                                                                                                                                           +7 (495) 787-2700
                                                                                         BC “Sadovaya Plaza” 7                        Engineering project       Laird Senotto,
                                                             Baker&McKenzie     3 700                               09.2008-02.2009
                                                                                         Dolgorukovskaya Str.                         adaptation, working      Project Manager
                                                                                                                                      Architectural design
                                                                                         BC “NPO “Rodina”,                              Architectural &                                Andrei.Povarov@ctl.com
                                                                                                                                                               Povarov Andrej,           +7 (903) 743-2612
                                                             TSYS               1 200    18/20 Zvenigorodskoe       10.2008-12.2008   Engineering design,
                                                                                                                                                               General Director
                                                                                         highway                                      General Contractor
                                                                                                                                                              Lobynceva Marina,        lobyntseva@aeroclub.ru
                                                             Aeroclub/BCD                BC “Burevestnik”                             General Contractor,                                 +7 (917) 586-6974
                                                                                2 200                               11.2008-01.2009                             Administrative
                                                             Travel                      12 the 3rd Ribinskaya                        Engineering design
                                                                                                                                                                   Director
                                                                                                                                      General Contractor,      Gupaisov Sergej,      SGupaisov@krafteurope.com
                                                                                         BC “Sadovaya Plaza” 7                                                                           +7 (495) 960-2480
                                                             Kraft Foods        4 300                               09.2008-08.2009   Engineering design         Director IS
                                                                                         Dolgorukovskaya Str.
                                                                                                                                          adaptation             Department
                                                                                         BC “Luch”                                                                                      ababadja@its.jnj.com
                                                             Johnson &                                                                                         Anna Babadjan,
                                                                                1000     27/4 Bolshaya              05.2009-08.2009   General Contractor                                 +7 (916) 640-6838
                                               Data Centre   Johnson
                                                                                         Pirogovskaya
                                                                                                                                                              Project coordinator
                                                                                                                                                                                             toj@msa.se
                                                             Mannheimer                  BC “ Romanov Dvor”                           General Contractor,     Tomas Johannson,            +7 (495) 380-3280
                                                                                 800                                04.2008-07.2008
                                                             Swartling                   4/2 Romanov Lane                             Engineering design        Partner, layer
                                                                                                                                                               Kvasnikov Igor’         igor_kvasnikov@troika.ru
                                                                                         BC “Lucine”                                    Architectural &
                                                                                                                                                                  Deputy of               +7 (495) 258-0500
                                                             Troika Dialog      3 600    6 Bolsoy Kislovskiy        10.2007-12.2007   Engineering design,
                                                                                                                                                                Administrative
                                                                                         lane                                         General Contractor
                                                                                                                                                                   Director
                                                                                                                                        Architectural &       Aleksejuk Natal’ja,     nalekseyuk@carcade.com
                                                                                         BC “Stanislavskogo”                                                                              +7 (495) 933-8816
                                                             Carcade Leasing    2 400                               01.2008-04.2008   Engineering design,       Administrative
                                                                                         , 21 Stanislavskogo Str.
                                                                                                                                      General Contractor           Director
                                                                                                                                                               Anna Zhukova,        anna.zukova@eastcapital.com
                                                             East Capital                BC “ Romanov Dvor”         05.2007-08.2007   General Contractor,                                +7 (495) 380-1505
                                                                                1 400                                                                           Administrative
                                                             International AB            4/2 Romanov Lane           04.2008-07.2008   Engineering design
                                                                                                                                                                  Manager
                                                                                         BC “ Romanov Dvor”                                                    Sergei Slobodin,       Sergei_Slobodin@troika.ru
                                                                                                                                      General Contractor,                                 +7 (495) 258-0500
                                               Data Centre   Troika Dialog      2 500    4 Romanov Lane             02.2007-05.2007
                                                                                                                                      Engineering design
                                                                                                                                                                Administrative
                                                                                         Dealing                                                             Management Director
                                                                                         BC “Residenziya na                                                                         Alexandr.Sakoyan@Wrigley.com
                                                                                                                                                                  Alexandr
                                                                                         Rublevke”                                      Architectural &                                   +7 (906) 773-03-44
                                                                                                                                                                  Sakoyan,
                                                             Wrigley            4 000    Usovo,                     08.2007-12.2007   Engineering design,
                                                                                                                                                                Administrative
                                                                                         100 Rublevo-                                 General Contractor
                                                                                                                                                                   Director
                                                                                         Uspenskoe Highway
                                                                                                                                        Architectural &       Garbuzov Nikolay,        ngarbuzov@airunion.ru
                                                                                         BC “Midland Plaza”                                                                              +7 (495) 411-6260
                                                             AirUnion           1 300                               05.2007-07.2007   Engineering design,      Administrative
                                                                                         8 Arbat Str.
                                                                                                                                      General Contractor,         Director
                                                                                                                                        Architectural &                             oscar.karash@halliburton.com
                                                             Kellogg Brown               BC “Midland Plaza”                                                     Oscar Karash,             +7 (495) 775-7530;
                                                                                1 300                               02.2007-05.2007   Engineering design,
                                                             & Root                      8 Arbat Str.                                                          General Director           +1 (713)471-3014
                                                                                                                                      General Contractor
                                                                                                                                                                                      stepanovaster@gmail.com
                                                                                         BC “ Romanov Dvor”                           General Contractor,      Irina Stepanova,           +7 (495) 760-4278
                                                             Sotheby’s           200                                02.2007-04.2007
                                                                                         4 Romanov Lane                               Engineering design       General Director

                                                                                         BC “Golutvinskaya                                                                           VFAVORINE@ru.loreal.com
                                                                                                                                      Engineering design,       Favorin Victor,         +7 (495) 725-6376
                                                             L’Oreal            7 000    Sloboda”                   12.2007-04.2008
                                                                                                                                                                   Director
                                                                                         1st Golutvinskiy Lane




125009, 6 Bol. Kislovsky Lane   www.rdcm.com                                                               tel.:+7(495)937 77 48                                                                                  fax:+7(495)937 77 49
LICENCES (SRO)
                                                                                                      RD Construction
                                                                                                      Management




125009, 6 Bol. Kislovsky Lane   www.rdcm.com           tel.:+7(495)937 77 48   fax:+7(495)937 77 49
CERTIFICATES ISO 9001:2000
                                                                                                      RD Construction
                                                                                                      Management




125009, 6 Bol. Kislovsky Lane   www.rdcm.com           tel.:+7(495)937 77 48   fax:+7(495)937 77 49
Head of department                                                                          Project managers:                                                                                        Head of department                                                                 Head of department- Ivanova Anna                                                                      - Petrov Ivan                                                                               - Ivanov Ivan                                                                                            - Sidorov Petr                                                                     - Smirnov Nikolay- Petrova Svetlana                                                                  Accountants:                                                                              - Sidorova Anna                                                                                          Engineers:                                                                         Safety engineers:                                                                                      - Sidorova Maria                                                                            - Petrov Petr                                                                                            - Ivanova Maria                                                                    - Petrov Dmitry                                                                                     - Ivanov Dmitry                                                                            - Smirnova Svetlana                                                                                      - Sidorov Dmitry                                                                   - Smirnova Anna                                                                                                                                                                                                                                                                                                                                                         - Ivanov Pet

Más contenido relacionado

La actualidad más candente

Microsoft Power Point China Mining Nov 2008 [Compatibility Mode]
Microsoft Power Point   China Mining Nov 2008 [Compatibility Mode]Microsoft Power Point   China Mining Nov 2008 [Compatibility Mode]
Microsoft Power Point China Mining Nov 2008 [Compatibility Mode]guest9c8069
 
Specialty Information Sheets
Specialty Information SheetsSpecialty Information Sheets
Specialty Information SheetsTim Fernandez
 
Cullen Master Builder Portfolio
Cullen Master Builder PortfolioCullen Master Builder Portfolio
Cullen Master Builder Portfoliokrhino2000
 
Doug Personal
Doug PersonalDoug Personal
Doug PersonalDougPM
 
Repack Pg 18 19
Repack Pg 18 19Repack Pg 18 19
Repack Pg 18 19camelevy
 
Andrew Stevenson CV
Andrew Stevenson CVAndrew Stevenson CV
Andrew Stevenson CVAndystevo
 
Entrepart in English
Entrepart in EnglishEntrepart in English
Entrepart in EnglishEntrepart
 
Profile Spacewell Interiors
Profile Spacewell InteriorsProfile Spacewell Interiors
Profile Spacewell Interiorsmichaeloleary1
 
John R. Gustafson P.E.'s Resume
John R. Gustafson P.E.'s ResumeJohn R. Gustafson P.E.'s Resume
John R. Gustafson P.E.'s ResumeJohn Gustafson
 
China Mining Nov 2008
China Mining Nov 2008China Mining Nov 2008
China Mining Nov 2008PaulPittman
 
ACS healthcare presentation for ipad
ACS healthcare presentation for ipad ACS healthcare presentation for ipad
ACS healthcare presentation for ipad In Out Creatives
 
Cr capabilities high res
Cr capabilities high resCr capabilities high res
Cr capabilities high resbrookemcconnell
 

La actualidad más candente (17)

Microsoft Power Point China Mining Nov 2008 [Compatibility Mode]
Microsoft Power Point   China Mining Nov 2008 [Compatibility Mode]Microsoft Power Point   China Mining Nov 2008 [Compatibility Mode]
Microsoft Power Point China Mining Nov 2008 [Compatibility Mode]
 
SEC Prequalification
SEC PrequalificationSEC Prequalification
SEC Prequalification
 
Jarob, Inc.
Jarob, Inc.Jarob, Inc.
Jarob, Inc.
 
Specialty Information Sheets
Specialty Information SheetsSpecialty Information Sheets
Specialty Information Sheets
 
Cullen Master Builder Portfolio
Cullen Master Builder PortfolioCullen Master Builder Portfolio
Cullen Master Builder Portfolio
 
SKV Company Profile
SKV Company ProfileSKV Company Profile
SKV Company Profile
 
Doug Personal
Doug PersonalDoug Personal
Doug Personal
 
Ay Consultants Ltd
Ay Consultants LtdAy Consultants Ltd
Ay Consultants Ltd
 
Repack Pg 18 19
Repack Pg 18 19Repack Pg 18 19
Repack Pg 18 19
 
Andrew Stevenson CV
Andrew Stevenson CVAndrew Stevenson CV
Andrew Stevenson CV
 
Entrepart in English
Entrepart in EnglishEntrepart in English
Entrepart in English
 
Profile Spacewell Interiors
Profile Spacewell InteriorsProfile Spacewell Interiors
Profile Spacewell Interiors
 
John R. Gustafson P.E.'s Resume
John R. Gustafson P.E.'s ResumeJohn R. Gustafson P.E.'s Resume
John R. Gustafson P.E.'s Resume
 
China Mining Nov 2008
China Mining Nov 2008China Mining Nov 2008
China Mining Nov 2008
 
ACS healthcare presentation for ipad
ACS healthcare presentation for ipad ACS healthcare presentation for ipad
ACS healthcare presentation for ipad
 
Cr capabilities high res
Cr capabilities high resCr capabilities high res
Cr capabilities high res
 
CR Capabilities
CR CapabilitiesCR Capabilities
CR Capabilities
 

Similar a Head of department Project managers: Head of department Head of department- Ivanova Anna - Petrov Ivan - Ivanov Ivan - Sidorov Petr - Smirnov Nikolay- Petrova Svetlana Accountants: - Sidorova Anna Engineers: Safety engineers: - Sidorova Maria - Petrov Petr - Ivanova Maria - Petrov Dmitry - Ivanov Dmitry - Smirnova Svetlana - Sidorov Dmitry - Smirnova Anna - Ivanov Pet

Damden Infra Brochure
Damden Infra Brochure Damden Infra Brochure
Damden Infra Brochure Damla Mathew
 
BBR Design
BBR DesignBBR Design
BBR DesignmikY9451
 
businesszone profile
businesszone profilebusinesszone profile
businesszone profileSanthan Reddy
 
Redwood Credentials Digital Version (1)
Redwood Credentials Digital Version (1)Redwood Credentials Digital Version (1)
Redwood Credentials Digital Version (1)Sam Graiche
 
Rainbow Developers Profile
Rainbow Developers ProfileRainbow Developers Profile
Rainbow Developers ProfileMansoor Chandio
 
DNB Interiors Company Profile (1) (1)
DNB Interiors Company Profile (1) (1)DNB Interiors Company Profile (1) (1)
DNB Interiors Company Profile (1) (1)DNB Interiors LLC
 
Why Interior Talent..
Why Interior Talent..Why Interior Talent..
Why Interior Talent..kgroberts
 
Rainbow Developers With Blue Background
Rainbow  Developers With  Blue  BackgroundRainbow  Developers With  Blue  Background
Rainbow Developers With Blue Backgroundguest470ea8
 
Rainbow Developers With Blue Background
Rainbow  Developers With  Blue  BackgroundRainbow  Developers With  Blue  Background
Rainbow Developers With Blue BackgroundMansoor Chandio
 
SEI brochure
SEI brochureSEI brochure
SEI brochurekdubesena
 
Dicedge limited. Building and construction company.
Dicedge limited. Building and construction company. Dicedge limited. Building and construction company.
Dicedge limited. Building and construction company. gichukianthony07
 

Similar a Head of department Project managers: Head of department Head of department- Ivanova Anna - Petrov Ivan - Ivanov Ivan - Sidorov Petr - Smirnov Nikolay- Petrova Svetlana Accountants: - Sidorova Anna Engineers: Safety engineers: - Sidorova Maria - Petrov Petr - Ivanova Maria - Petrov Dmitry - Ivanov Dmitry - Smirnova Svetlana - Sidorov Dmitry - Smirnova Anna - Ivanov Pet (20)

Damden Infra Brochure
Damden Infra Brochure Damden Infra Brochure
Damden Infra Brochure
 
BBR Design
BBR DesignBBR Design
BBR Design
 
Our Portfolio
Our PortfolioOur Portfolio
Our Portfolio
 
businesszone profile
businesszone profilebusinesszone profile
businesszone profile
 
Design tracks
Design tracksDesign tracks
Design tracks
 
Redwood Credentials Digital Version (1)
Redwood Credentials Digital Version (1)Redwood Credentials Digital Version (1)
Redwood Credentials Digital Version (1)
 
Rainbow Developers Profile
Rainbow Developers ProfileRainbow Developers Profile
Rainbow Developers Profile
 
Rainbow Developers
Rainbow  DevelopersRainbow  Developers
Rainbow Developers
 
Digital profile
Digital profileDigital profile
Digital profile
 
DNB Interiors Company Profile (1) (1)
DNB Interiors Company Profile (1) (1)DNB Interiors Company Profile (1) (1)
DNB Interiors Company Profile (1) (1)
 
Why Interior Talent..
Why Interior Talent..Why Interior Talent..
Why Interior Talent..
 
Rainbow Developers With Blue Background
Rainbow  Developers With  Blue  BackgroundRainbow  Developers With  Blue  Background
Rainbow Developers With Blue Background
 
Rainbow Developers With Blue Background
Rainbow  Developers With  Blue  BackgroundRainbow  Developers With  Blue  Background
Rainbow Developers With Blue Background
 
SEI Overview
SEI OverviewSEI Overview
SEI Overview
 
Sei Brochure
Sei BrochureSei Brochure
Sei Brochure
 
SEI brochure
SEI brochureSEI brochure
SEI brochure
 
SEI Overview
SEI OverviewSEI Overview
SEI Overview
 
Sei Brochure
Sei BrochureSei Brochure
Sei Brochure
 
Kiewit Recommendation 09
Kiewit Recommendation 09Kiewit Recommendation 09
Kiewit Recommendation 09
 
Dicedge limited. Building and construction company.
Dicedge limited. Building and construction company. Dicedge limited. Building and construction company.
Dicedge limited. Building and construction company.
 

Head of department Project managers: Head of department Head of department- Ivanova Anna - Petrov Ivan - Ivanov Ivan - Sidorov Petr - Smirnov Nikolay- Petrova Svetlana Accountants: - Sidorova Anna Engineers: Safety engineers: - Sidorova Maria - Petrov Petr - Ivanova Maria - Petrov Dmitry - Ivanov Dmitry - Smirnova Svetlana - Sidorov Dmitry - Smirnova Anna - Ivanov Pet

  • 1. RD CONSTRUCTION MANAGEMENT GENERAL DESIGNER GENERAL CONTRACTOR TECHNICAL SUPERVISOR C O N S U LTA N T 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 2. Contents About us Functions Company Structure Management Personnel Fit out Data-Centres 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 3. ABOUT US INTRODUCTION RD Construction Management RD Construction Management today - is a company working environment that contributes to creation of with a solid reputation, won over a long-term, working corporate success. towards the creation of high class o ces. We support the friendship and cooperation with our Over the past few years, «RD Construction counterparts and clients whom we know for many Management has signi cantly strengthened its years. position, having mastered a new market segment for itself - the construction of technically complex o ces I want to thank all those who chose us and our for major international and Russian companies. team, and who trusted us - our partners, and most importantly, our customers. Oleg Zhukov The desire to break into new paths of development, not afraid of di culties, is a critical component of our corporate philosophy, which encourages us to never rest, but to move foward. Our company is client oriented. Understanding the requirements and wishes of customers - is our professional duty. It is this high quality and standard of work that has helped us earn recognition and respect of our clients and to take a leading position in the market. If you are holding our brochure, then you have found an excellent company with which the chances of successful implementation of your project has increased to 100%! I'm sure that the investment made into your new o ce build by our team will be one of the most best investments you can make. Do not hesitate in choosing our team - we will save your time and money. We guarantee the quality and standards of our projects. We rmly believe that projects constructed with our team's heart and soul results in high quality 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 4. ABOUT US FUNCTIONS RD Construction Management We can undertake the following functions Consultant RDCM can recommend the correct solutions that will completely meet your requirements Design Manager Linking all project disciplines together General Planner Attracting the best designer and architectural bureau, along with the most experienced engineering companies to design the future o ce of your company General Contractor We construct everything planned by you from the concept of the architect and match this to your quality standards. Construction Manager Managing contractors to the most binding controls and requirements 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 5. ABOUT US COMPANY STRUCTURE RD Construction Management General Director of RD Construction Management Zhukov Oleg Technical Director General Director‘s Margulis Alexander assistant Samorodova Eugenia Marketing Contract Cost accounting Accounting Administrative Projects performance Engineering Quality control and safety department department department department department department department department Business Development Director Head of department CFO Chief accountant Deputy of General Director Chief Project Engineer Head of department Project Manager Baybus Ilya Somova Olga Avakyan Shogik Rednikina Marina Fotesku Valentina Silov Eugine Prokofiev Valeriy Babayan Esai Karavaev Maxim Senior Approvals Lead HVAC engineer Chief Chief Project Manager manager Electrical Weak Current Engineer Engineer Mikheev Sergey Bakanova Lubove Merzliakov Dmitriy Chernichenko Dmitriy Malinkin Oleg Engineer Marketing Cost Cost Contract Economist Accountant Accountant Project Project Project Project Purchases and Estimator Specialists Control Control manager manager manager manager manager Logistic Engineer Engineer Specialist Kompanichenko Gala Barashenko Andrey Kostuchkova Marina Shemyakova Anna Maseykin Peter Kochergina Liza Kycher Sveta Kadeykina Vera Karavaev Maxim Zvantsov Anton Pokrovsky Nickolay Denisov Sergey vacancy James Byrne Sverchkova Anna Alexander Semenov Secretary Courier Site managers Site managers Site manager Site manager Purchases Mechanical Mechanical Deputy of Chief Security SCS and TV/AV IT /Drivers managers Engineer Engineer Electrical Systems Systems Engineer Engineer Engineer Engineer Tichanova Alla Suntsov Yuriy Kudimov Igor Telminov Nickolay Ilatovsky Sergey Petrachkov Alexander Kasimova Lilya Pavlovsky Yurek Dvornikov Juriy Mauricio Nino Bredikhin Leonid vacancy Chaycowskiy Ilya Usarova Dasha Sajnev Dmitriy Zvyagin Ivan Mikheev Alexander Kurilo Alexander Balikin Nickolay 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 6. ABOUT US MANAGEMENT RD Construction Management Oleg Zhukov Alexander Margulis Eugene Silov Ilya Baybus General Director Technical Director Deputy General Director Business Development Director Graduated from Moscow Road Construction Graduated from Moscow Engineering and Graduated from Moscow Road Construction Institute Graduated from Moscow State University of Foreign institute (MMRI), faculty of Construction of roads and Construction Institute (MECI, Hons). The second (MMCI). A airs (MGIMO) (U) of the Ministry of Foreign airdromes. After graduation from MMRI relocated to highest educational award attained in the Moscow 1996-2003 – Engineering Manager at Hines A airs of Russia, “International business and Italy entered postgraduate course in Vicenza (Italy). Management Institute (MMI). 1992 Director of International. business administration” faculty. After conferral Engineering services at Hines International. A very of a Management and Marketing Master’s degree experienced specialist with up to 30 years in the he worked as a Head of the Ventilation and construction business. Conditioning for a large Engineering company from 2002. ''The goal of our company is to create a unique product of high-class quality o ces. Our team has the ability to solve tasks of di cult complexity. Our Specialists reply to all the questions: the ''RD Construction Management is a company ''Our long-term aim is the build cooperation and '' The main purpose of our RDCM’s activity is to more complex and more di cult the project is oriented to provide the Customer with the desired partnership relationships with our Customers, based provide a nished project with maximal comfort the more attractive and challenging it is to RDCM. coordinated result and within the approved budget. on trust and open communications. We o er a and safe conditions for the business activities of We strive for experience and knowledge, strive Our close-knit team of quali ed specialists can solve high-quality service at all stages of construction of A the Customer and his clients. Our specialists are to create a quality product and at the same time tasks of technical complexity. This accumulated class real estate construction from development to prepared to render quali ed assistance to solve a develop partnership relations with our Customers experience and knowledge permits RDCM to work concept to its commercial realization” client’s problems and complete the given tasks. which is the recipe of success of RD Construction in di erent areas, such as capital construction, Management.'' designing and nishing works'' 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 7. ABOUT US PROJECT STRUCTURE RD Construction Management GENERAL DIRECTOR CLIENTS PROJECT LEADER TECHNICAL DIRECTOR REPRESENTATIVE • Cooperation with the client's • Coperation with all project participants • Technical concept design representative. One point • Holding meetings draw up actional minutes • Supervision of the technical aspects of the project of contact principle. • Prepare and present progress reports • Formulate technical tasks • Manage the ongoing project • Technical Project audit • Cordination of the ongoing works SITE MANAGER OCCUPATIONAL TECHNICAL AND CON APPROVALS AND PURCHASE AND MECHANICAL ELECTRICAL LOW VOLTAGE HEALTH AND SAFETY STRUCTION COMPLIANCE SPE LOGISTICS SYSTEMS ENGINEER SYSTEMS ENGINEER SUPERVISORY ENGI CIALIST SPECIALIST ENGINEER ENGINEER NEER • Cordination on site. • H&S instructions • Site Supervision • Contracts and • Purchase and delivery • Ventilation • Power Supply • Structured cabling systems • Operational management • Monitor and adherance • Hidden Works document approvals of materials to site • Air conditioning • Lighting systems • IT of the site to work regulations • Quality Control • Work with local authorities • Liase with suppliers • Plumbing systems • Fire alarm systems • Cooperation with and safety on site. • Acceptance works • Fire supression systems • Security systems , CCTV local authorities • Keep and update local authorities work log. • Quality control of materials and equipment QUALITY CONTROL ENGINEER • Quality control and inspection of works • Maintain quality log and snag lists 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 8. ABOUT US REALISED PROJECTS RD Construction Management Romanov Dvor Business Centre Troika Dialog Mannheimer Swartling Media Park Aif Address 4 Romanov Lane Address 4 Romanov Lane, Romanov Dvor BC Address 4 Romanov Lane Romanov Dvor BC Address 27 Electrozavodskaya St, LeFort BC Size 65 000 m2 Size 3 000 m2 Size 800 m2 Size 10 500 m2 Romanov Dvor, 1 stage — 15 000 m2 Timeline 02.2007-05.2007 Timeline 04.2008-04.2008 Timeline 07.2008-01.2009 Romanov Dvor, 2 stage — 35 000 m2 Functions General Contractor Functions General Contractor Functions General Contractor Romanov Dvor, 3 stage — 15 000 m2 Time Line Romanov Dvor, 1 stage — 1998-2001 Rectors House Romanov Dvor Total System Services – RUS (TSYS) Troika Dialog Romanov Dvor, 2 stage — 2001-2003 Romanov Dvor, 3 stage — 2009-ongoing Address 11 Mohovaya St. bld.6 Address 18/20 Zvenigorodskoe Ave, BC «NPO Rodina» Address Kislovsky lane 6, BC «Lucine» Functions General Planner, General Contractor Size 3 500 m2 Size 1 200 m2 Size 3 000 m2 Timeline 2003-2006 Timeline 10.2008-12.2008 Timeline 10.2007-12.2007 Functions General Contractor Functions General Contractor Functions General Contractor Val Des Roses, Luxemburg Address Strassen, Grand-Duche de Luxemburg, East Capital International AB Aeroclub / BCD Travel Val Des Roses L’Oreal Size 2 600 m2 Address 4 Romanov Lane, Romanov Dvor Address 12 Ribinskaya St, Burevestnik BC Time Line 10.2008-08.2009 Size 1 400 m2 Size 2 200 m2 Address 1st Golutvinskiy lane, BC «Golutvinskaya Functions Consultant and advisor Timeline 08.2007-12.2007 / 05.2007-08.2007 Timeline 11.2008-01.2009 Sloboda» Functions General Constractor Functions General Contractor Size 7 000 m2 Kellogg Brown & Root Timeline 2.2007-04.2008 Functions General Contractor Address 8 Arbat, Midland Plaza Carcade Leasing Kraft Foods Design & Build Size 1 300 m2 Timeline 02.2007-05.2007 Address 21 Stanislavskogo St. Stanislavskogo BC Address 7 Dolgorukovskaya str. Sadovaya Plaza BC Baker&McKenzie Functions General Contractor Size 2 400 m2 Size 4 300 m2 Timeline 01.2008-04.2008 Timeline 09.2008-08.2009 Address Dolgorukovskaya str. 7, BC «Sadovaya Plaza» Functions General Contractor Functions General Contractor Size 3 700 m2 Timeline 09.2008-02.2009 Wrigley Functions General Contractor Johnson&Johnson Address Rublevo-uspenskoe Avenue, Moscow BC «Residence on Rublevka» Address 27 Pirogovskaya St, Luch BC Size 4 000 m2 Size 940 m2 Timeline 08.2007-12.2007 Timeline 05.2009-08.2009 Functions General Contractor Functions General Contractor 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 9. ABOUT US REALISED PROJECTS RD Construction Management Novatek Nycomed Honeywell Troika Dialog Address 2 Udalcova Street Address 2-1 Usacheva St Address 8 Kievskaya, Legion III BC Address 18/20 Zvenigorodskoe , NPO Rodina BC Size 12 730 m2 Size 4 200 m2 Size 2 800 m2 SIze 1 200 m2 Functions General Contractor Functions General Contractor Functions General Contractor Functions General Contractor Data Centre BC «Rector’s house» TSYS KBR Linxtelecom Zvenigorodkoe ave 18/20 Address 8th of March St 14 11 Mohovaya St Address Address Address 8 Arbat St Size 2 500 m2 Size 3 500 m2 Size 1 200 m2 Size 1 200 m2 General Contractor Functions General Contractor Timeline 2003-2006 Functions Functions General Contractor Data Centre Functions General Contractor Baker&McKenzie East Capital International AB Hemofarm Nokia Siemens Networks Address 27 Electrozavodskaya St, Lefort BC Address 21 stanislavkogo Street Address 7 Dolgorukovskaya , Sadovaya Plaza BC Address 4 Romanov Lane, Romanov Dvor BC Size 5 000 m2 Size 3 700 m2 Size 1 000 m2 Size 1 400 m2 Functions General Contractor Functions General Contrator Functions General Contractor Functions General Contractor Data Centre L’Oreal Credit Suisse Troika Dialog Otkritie Address Golutvinskiy Ln, Golutvinskaya Sloboda BC Address 12/1Yakovoapostalskiy lane Address Romanov lane 4, Romanov Dvor BC Address Kislovsky lane 6, BC «Lucine» SIze 7 000 m2 Size 1100 m2 Size 1 700 m2 Size 3 000 m2 Functions General Contractor Functions General Contractor Functions General Contractor Functions General Contractor Data Centre Correa’s AirClub / BCD Travel Etihad Airways Alcatel-Lucent Address 4 Romanov Lane, Romanov Dvor BC Address 12 Ribinskaya, Burivestnik BC Address 27 Serebrianicheskaya , Silver City BC Address 27 Electrozavodskaya St. LeFort BC Size 700 m2 Size 2 200 m2 Size 250 m2 Size 3800 m2 Functions Design & Build Functions General Contractor Function General Contractor Timeline 07.2009-09.2009 Functions General Contractor Data Centre 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 10. DELIVERED PROJECTS JOHNSON&JOHNSON TVCI RD Construction Management Address: 27/4 Bolshoya Pirogvskaya Luch Business Centre Size: 940 m2 Timeline: 06-2009 - 09-2009 Functions: General Contractor 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 11. DELIVERED PROJECTS HONEYWELL RD Construction Management Address: Legion 3 business centre 7 Kieveskaya Street Size: 2800 m2 Timeline: 03-2010 - 07-2010 Functions: General Contractor 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 12. DELIVERED PROJECTS NYCOMED RD Construction Management Address: 2/1 Usacheva Street Size: 4 200 m2 Timeline: 09-2010 - 12-2010 Functions: General Contractor 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 13. DELIVERED PROJECTS CORREAS RD Construction Management Address: 4 Romanov Lane Size: 700 m2 Timeline: 10-2010 - 11-2010 Functions: General Contractor 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 14. DELIVERED PROJECTS ETIHAD AIRWAYS RD Construction Management Address: 27 Serebyanicheskaya Size: 250 m2 Timeline: 08-2010 - 10-2010 Functions: General Contractor 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 15. DELIVERED PROJECTS EAST CAPITAL RD Construction Management Address: Romanov Dvor BC Size: 1000 m2 Timeline: 55 days 04-2008 - 07-2008 Functions: General Contractor 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 16. DELIVERED PROJECTS MANNHEIMER SWARTLING RD Construction Management Address: 4 Romanov Lane Size: 600 m2 Timeline: 55 days 04-2008 - 07-2008 Functions: General Contractor 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 17. DELIVERED PROJECTS AIF RD Construction Management Address: 27 Elecktrozovodkaya Street Size: 10 500 m2 Timeline: 07-2008 - 04-2009 Functions: General Contractor 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 18. DELIVERED PROJECTS BAKER & MCKENZIE RD Construction Management Address: 7 Dolgorukovskaya Street Sadovaya Plaza Business Centre Size: 3 600 m2 Timeline: 12-2008 - 03-2009 Functions: General Contractor 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 19. DELIVERED PROJECTS AIRCLUB /BCD TRAVEL RD Construction Management Address: 12 Ribinskaya Burevestnik Business Centre Size: 2 400 m2 Timeline: 11-2008 - 01-2009 Functions: General Contractor 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 20. DELIVERED PROJECTS KRAFT FOODS RD Construction Management Address: 7 Dolgorukovskaya St Sadovaya Business Centre Size: 3 800 m2 Timeline: 01-2009 - 05-2009 Functions: General Contractor 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 21. DELIVERED PROJECTS TSYS CARD TECH RD Construction Management Address: 18-20 Zvenigorodskoe Shosee Size: 1 200 m2 Timeline: 10-2008 - 11-2008 Functions: General Contractor 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 22. DELIVERED PROJECTS WRIGLEY RD Construction Management Address: 100 Rubleveke shosse Residenziya BC Size: 4 000 m2 Timeline: 11-2007 - 12-2007 Functions: General Contractor 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 23. DELIVERED PROJECTS TROIKA DIALOG Data Centre RD Construction Management Address: 2 Romanov Lane Size: Total Area 2500 m2 Data Center (260 kVA) 210 m2 Trading Floor 980 m2 Back O ce 1320 m2 Description: Tier 4 Data Centre Timeline: Design Stage 42 Weeks Execution 9 Weeks Fine Tuning 5 weeks 75 C-days (01.03.2007-14.05.2007) including dealing center and back o ce Functions: General Contractor Design and Build Equipment Supplier Major engineering systems installed: - active & cross-connect equipment UPS, RC-units APC (Ireland) - chillers – HITACHI (Spain) - dry coolers Gunter (Germany) - diesel-generators VOLVO (Sweden) - building management systems (BMS) – Computrols (USA) 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 24. DELIVERED PROJECTS TROIKA DIALOG RD Construction Data Centre Management 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 25. DELIVERED PROJECTS LINXTELECOM RD Construction Data Centre Management Address: Ul. The 8th of March, «Kulon» industrial estate Size: 2 500 m2 (critical power 800 kVA) Description: Tier 3 Data Centre Timeline: 140 C-days (13.05.09- 30.09.09) Functions: General Contractor Design and Build Equipment Supplier Major engineering systems installed: - close control AC – STULZ (Germany) - dry coolers – Gunter (Germany) - PDU – ABB (Russia) - RC-units – APC (France) - diesel-generators – Wilson (England GB) - building management systems (BMS) – Computrols (USA) Challenges and solutions: The project special feature was a complicated and multistage process of balancing, commissioning, and start-up under the terms of electrical power de cit. We also met the tough requirements of the potential data- center tenant – one of the biggest international IT providing company. 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 26. DELIVERED PROJECTS LINXTELECOM Data Centre RD Construction Management 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 27. DELIVERED PROJECTS NOKIA SIEMENS NETWORKS RD Construction Data Centre Management Address: 26 Ul. Stanislavskogo, bl. 13, Business Center « Stanislavskii» Size: 145 m2 (critical power 225 kVA) Description: Test Bed Laboratory Timeline: 02-2010 - 04-2010 Functions: General Contractor Design and build Major engineering systems installed: - active equipment, communication equipment and UPS Eaton Power Ware (USA) - precision air conditioner – Uni air (Italy) - dry coolers – Uni air (Italy) - PDU – ABB (Russia) - automated gas re- ghting system Eusebi Impianti (Italy) Challenges and solutions: A special metal structure was installed around the racks for the electrical and data cabling traces. We will utilise this universal method when we are in situations where it’s impossible to stack cable trays to the ceiling. 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 28. DELIVERED PROJECTS ALCATEL LUCENT RD Construction Data Centre Management Address: 27 Electrozavodskaya Street LeFort Business Centre Size: 136 m2 (critical power 90 kVA) Description: Test bed labratory Timeline: 91 C-days from start to nish (07.07.09-08.10.09) Functions: General Contractor Major engineering systems installed: - Close control AC units with remote condenser – TRANE (GB) - PDU – ABB (Russia) - UPS – APC - gas suppression «Automatic re- ghting equipment and service» (Russia) Challenges and solutions: The test bed cooling system was operating in conditions where air temperature in the summer of 2010 was extreme. This bears witness of the proper choice of the cooling system equipment. 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 29. ONGOING PROJECTS ROMANOV DVOR DATA CENTRE RD Construction Data Centre Management Address: 2-4 Romanov Lane Size: Timeline: in progress Functions: General Planner General Contractor Technical supervisor Major engineering systems installed: Power range 1210 kVa on active Equipment 720 kVa on accessory equipment 490 kVa Parameter PUE 1,68 DPC Provides: 1. Two independent inputs from TP 25345 2. TP is powered by PS 834 Zubovskaya (CHP 12) and PS 655 Nikita (GES 1) 3.Reservation inputs provided from diesel power plant consisting of three DSU capacity of 700 kVA each.DSU backup scheme N+1 4. Active and auxiliary equipment is connected through three UPS 660 kVA, Reserved for N+1 5. Means the connection counters on two boards PDU, N+1 redundancy scheme Working Time UPS – seven Minutes Challenges and solutions: Time to start the diesel generator set rated capacity 50 seconds. All active and auxiliary equipment connected to UPS. Repair work on any element of the power supply system can be carried out at any time without disconnecting the load. 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 30. CAPITAL CONSTRUCTION ROMANOV DVOR BUSINESS STAGE 3 RD Construction Capital Const Management Address: 4 Romanov Lane Size: 15 000 m2 Timeline: 2005 - to date Functions: General Planner General Contractor Technical supervisor 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 31. CAPITAL CONSTRUCTION ROMANOV DVOR BUSINESS STAGE 3 RD Construction Capital Const Management 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 32. CAPITAL CONSTRUCTION VAL DES ROSES, LUXEMBURG RD Construction Capital Const Management Address: 70, Grand Rue L-1660 Luxembourg Size: 2600 m2 22 apartments Timeline: 04-2007 - 10-2009 Functions: General Planner Consultant 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 33. CAPITAL CONSTRUCTION VAL DES ROSES, LUXEMBURG RD Construction Capital Const Management 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 34. REFERENCES RD Construction Management CURRENT AND REALIZED PROJECTS 1. Current projects Project Area Address Timing Functions Contact name Contact details BC “ Romanov Dvor “ 2006-now General Contractor, RD Group own Romanov Dvor, 4 Romanov Lane Capital Const 3 stage 15 000 Engineering design project Valentin kolchin@novatek.ru NOVATEK 12 000 2 Udalzova Str. 06.2010-04.2011 General Contractor +7 985 762 7119 Kolchin Petr petr.adamiants@philips.com Adamyanz +7 985 769 02 71 13 Sergeya Senior Philips 5 050 11.2010-03.2011 General Contractor Makeeva manager of procurement department dkmoon21@samsung.com Duck Kyu 7 (985) 764 6376 Samsung 5 100 10 Vozdvizhenka 03.2011-06.2011 General Contractor Moon Irina stepanovaster@gmail.com Stepanova, +7 (495) 760-4278 Sotheby’s 200 4 Romanov Lane 01.2011-04.2011 General Contractor General Director alt@belovskaya.ru 4/7 bld 2 Aleksey +7 916 546 27 20 Karakan-Invest 1 150 04.2011-07.2011 General Contractor Vozdvizhenka Tokanov 2. Realized projects Project Area Address Timing Functions Contact name Contact details BC “Romanov Capital Const Dvor” 65 000 Romanov Dvor, General Contractor, 15 000 4 Romanov Lane RD Group own project 1 stage 1998-2001 Engineering design Romanov Dvor, 35 000 2 stage 2001-2003 Capital Const BC “Rektorskiy 3 500 11/6 Mohovaya Str. 2003-2006 General Contractor RD Group own project Domik “ sergey.¿limonov@credit-suisse.com Credit Suisse 1 700 4 Romanov Lane 10.2010-02.2011 General Contractor Sergey Fillimonov +7 495 967 8200 General Contractor, Ekaterina.grebenikowa@nycomed. Engineering project Grebennikova com Nycomed 4 200 2/1 Usacheva Str. 09.2010-12.2010 adaptation, working Ekaterina +7 915 136 75 74 Architectural design General Contractor, Alexand r Pelenev pelenev@open.ru 12/1 Yakovoapostolskiy FC OTKRITIE 5 050 10.2010-12.2010 Architectural & Deputy of +7 903 752 42 42 Lane Engineering design Administrative director General Contractor, Vitaly_Koulmanakov@avica.pro Cafetera 700 4 Romanov Lane 08.2010-10.2010 Architectural & Kulmanakov Vitaliy +7 495 287 18 18 Engineering design NGoryunova@etihad.ae Etihad Airways 250 27 Serebryanicheskaya 08.2010-10.2010 General Contractor Nataliya Gorunova +7 905 710 0812 “Val Des Roses” seva99@yandex.ru “Val Des Roses”, Vsevolod Yampolskiy 2 600 Strassen, Grand-Duche 10.2008-08.2010 General Contractor +352-621-168969 Luxemburg General Director de Luxemburg elena.sopova@nsn.com Data Centre Nokia Siemens General planner, General 5 000 21 Stanislavskogo Str. 02.2010-04.2010 Elena Sopova +7 925 507 70 17 Networks Contractor igor.zolotaryev@honeywell.com Legion III General Contractor, +7 495 796 9817 Honeywell 3 600 03.2010-06.2010 Igor Zolotarev 7 Kievskaya Str. Development project Kvasnikov Igor igor_kvasnikov@troika.ru 4 Romanov Lane +7 (495) 258-0500 Data Centre Troika Dialog 3 500 4th Àoor 11.2009-01.2010 General Contractor Deputy of Administrative Director Milos.Davidovic@hemofarm.com BC “LeFort” 27 Milosh Davydovich Hemofarm 1 000 11.2009-01.2010 General Contractor Electrozavodskaya Str. General Director Shmel’kov Andrej Andrey.Shmelkov@alcatel-lucent. BC “LeFort” 27 com Alcatel-Lucent 4500 07.2009- 12.2009 General Contractor Director Administrative Electrozavodskaya Str. +7 (915) 278 0488 Department alexandr.maslov@linxtelecom.com Data Centre Ul. The 8th of March Linxtelecom 2 500 05.2009- 09.2009 General Contractor Alexand r Maslov +79857278608 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 35. REFERENCES RD Construction Management Vagin Konstantin, vagin@aif.ru BC “LeFort” 27 General Contractor, +7 (903) 974-0669 Mediapark “AiF” 10 500 07.2008-01.2009 Deputy of General Electrozavodskaya Str. Engineering design Director Laird.Cenotto@BAKERNET.com General Contractor, +7 (495) 787-2700 BC “Sadovaya Plaza” 7 Engineering project Laird Senotto, Baker&McKenzie 3 700 09.2008-02.2009 Dolgorukovskaya Str. adaptation, working Project Manager Architectural design BC “NPO “Rodina”, Architectural & Andrei.Povarov@ctl.com Povarov Andrej, +7 (903) 743-2612 TSYS 1 200 18/20 Zvenigorodskoe 10.2008-12.2008 Engineering design, General Director highway General Contractor Lobynceva Marina, lobyntseva@aeroclub.ru Aeroclub/BCD BC “Burevestnik” General Contractor, +7 (917) 586-6974 2 200 11.2008-01.2009 Administrative Travel 12 the 3rd Ribinskaya Engineering design Director General Contractor, Gupaisov Sergej, SGupaisov@krafteurope.com BC “Sadovaya Plaza” 7 +7 (495) 960-2480 Kraft Foods 4 300 09.2008-08.2009 Engineering design Director IS Dolgorukovskaya Str. adaptation Department BC “Luch” ababadja@its.jnj.com Johnson & Anna Babadjan, 1000 27/4 Bolshaya 05.2009-08.2009 General Contractor +7 (916) 640-6838 Data Centre Johnson Pirogovskaya Project coordinator toj@msa.se Mannheimer BC “ Romanov Dvor” General Contractor, Tomas Johannson, +7 (495) 380-3280 800 04.2008-07.2008 Swartling 4/2 Romanov Lane Engineering design Partner, layer Kvasnikov Igor’ igor_kvasnikov@troika.ru BC “Lucine” Architectural & Deputy of +7 (495) 258-0500 Troika Dialog 3 600 6 Bolsoy Kislovskiy 10.2007-12.2007 Engineering design, Administrative lane General Contractor Director Architectural & Aleksejuk Natal’ja, nalekseyuk@carcade.com BC “Stanislavskogo” +7 (495) 933-8816 Carcade Leasing 2 400 01.2008-04.2008 Engineering design, Administrative , 21 Stanislavskogo Str. General Contractor Director Anna Zhukova, anna.zukova@eastcapital.com East Capital BC “ Romanov Dvor” 05.2007-08.2007 General Contractor, +7 (495) 380-1505 1 400 Administrative International AB 4/2 Romanov Lane 04.2008-07.2008 Engineering design Manager BC “ Romanov Dvor” Sergei Slobodin, Sergei_Slobodin@troika.ru General Contractor, +7 (495) 258-0500 Data Centre Troika Dialog 2 500 4 Romanov Lane 02.2007-05.2007 Engineering design Administrative Dealing Management Director BC “Residenziya na Alexandr.Sakoyan@Wrigley.com Alexandr Rublevke” Architectural & +7 (906) 773-03-44 Sakoyan, Wrigley 4 000 Usovo, 08.2007-12.2007 Engineering design, Administrative 100 Rublevo- General Contractor Director Uspenskoe Highway Architectural & Garbuzov Nikolay, ngarbuzov@airunion.ru BC “Midland Plaza” +7 (495) 411-6260 AirUnion 1 300 05.2007-07.2007 Engineering design, Administrative 8 Arbat Str. General Contractor, Director Architectural & oscar.karash@halliburton.com Kellogg Brown BC “Midland Plaza” Oscar Karash, +7 (495) 775-7530; 1 300 02.2007-05.2007 Engineering design, & Root 8 Arbat Str. General Director +1 (713)471-3014 General Contractor stepanovaster@gmail.com BC “ Romanov Dvor” General Contractor, Irina Stepanova, +7 (495) 760-4278 Sotheby’s 200 02.2007-04.2007 4 Romanov Lane Engineering design General Director BC “Golutvinskaya VFAVORINE@ru.loreal.com Engineering design, Favorin Victor, +7 (495) 725-6376 L’Oreal 7 000 Sloboda” 12.2007-04.2008 Director 1st Golutvinskiy Lane 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 36. LICENCES (SRO) RD Construction Management 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49
  • 37. CERTIFICATES ISO 9001:2000 RD Construction Management 125009, 6 Bol. Kislovsky Lane www.rdcm.com tel.:+7(495)937 77 48 fax:+7(495)937 77 49