Item Descripción Und. Metrado Precio (S/.) Parcial (S/.)
01 INSTALACION DEL SISTEMA DE AGUA POTABLE 636,367.27
01.01 OBRAS PROVISIONALES 42,570.40
01.01.01 CONSTRUCCION DE ALMACENES Y GUARDIANÍA M2 120.00 107.50 12,900.00
01.01.02 CARTEL DE OBRA UND 1.00 1,266.70 1,266.70
01.01.03 SALUD Y SEGURIDAD 28,403.70
01.01.03.01 EQUIPOS DE PROTECCIÓN INDIVIDUAL GLB 1.00 9,210.00 9,210.00
01.01.03.02 SEÑALIZACION TEMPORAL DE SEGURIDAD MES 5.00 360.46 1,802.30
01.01.03.03 CAPACITACION EN SALUD Y SEGURIDAD GLB 1.00 16,631.40 16,631.40
01.01.03.04 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJOGLB 1.00 760.00 760.00
01.02 CONSTRUCCION DE CAPTACIONES 11,789.76
01.02.01 CAPT. DE LADERA L.C.=2" (01 UNID.) 11,789.76
01.02.01.01 TRAZO Y REPLANTEO PRELIMINAR M2 6.29 0.84 5.28
01.02.01.02 EXCAV. MANUAL EN TERRENO SUELTO M3 23.37 40.05 935.97
01.02.01.03 ELIMINACION DE MATERIAL EXCEDENTE (D<500m)) M3 30.38 33.37 1,013.78
01.02.01.04 RELLENO DE GRAVA DE 1 1/2'' SELECCIONADA M3 6.00 181.31 1,087.86
01.02.01.05 CONCRETO CICLOPEO 1:10 + 50% de P.G. M3 1.15 330.20 379.73
01.02.01.06 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 5.38 576.26 3,100.28
01.02.01.07 ACERO DE REFUERZO FY=4200 KG/CM2 KG 28.20 5.70 160.74
01.02.01.08 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 41.50 53.96 2,239.34
01.02.01.09 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 20.58 39.17 806.12
01.02.01.10 TARRAJEO INTERIOR CON IMPERMEABILIZANTE e=1.50 cm - MEZCLA 1:2 M2 6.16 51.05 314.47
01.02.01.11 PINTURA ESMALTE EN MUROS M2 5.10 12.93 65.94
01.02.01.12 PINTURA ANTICORROSIVA EN TAPAS METALICAS M2 50.06 15.34 767.92
01.02.01.13 SUMINISTRO Y COLOCACION DE ACCES./CAPTACION DE LADERA (L.C.=Ø2") UND 1.00 912.33 912.33
01.03 LINEA DE CONDUCCION 491,564.07
01.03.01 RED PRIMARIA 452,717.85
01.03.01.01 LIMPIEZA MANUAL DE TERRENO CON PRESENCIA DE PIEDRA M2 5,043.00 3.34 16,843.62
01.03.01.02 TRAZO Y REPLANTEO DE ZANJAS (ML) ML 3,362.00 2.17 7,295.54
01.03.01.03 EXCAVACION MANUAL EN ZANJAS (TERRENO NATURAL) (ZANJA DE 0.40 x 0.60) ML 1,782.21 10.01 17,839.92
01.03.01.04 EXCAVACION DE ZANJA EN ROCA SUELTA ML 400.00 85.77 34,308.00
01.03.01.05 EXCAVACION DE ZANJA EN ROCA DURA ML 1,180.00 144.53 170,545.40
01.03.01.06 REFINE Y NIVELACION DE ZANJAS (b=0.40m) ML 3,362.00 2.00 6,724.00
01.03.01.07 CAMA DE APOYO PARA TUB. C/MAT. ZARANDEADO (h=0.10m) ML 3,362.00 3.34 11,229.08
01.03.01.08 SUMINISTRO E INSTALACION DE TUBERIA PVC-SAP C=7.5, D=2" ML 2,681.21 9.74 26,114.99
01.03.01.09 SUMINISTRO E INSTALACION DE TUBERIA PVC-SAP C=7.5, D=1 1/2" ML 42.00 8.10 340.20
01.03.01.10 SUMINISTRO E INSTALACION DE TUBERIA PVC-SAP C=10, D=1" ML 639.00 6.62 4,230.18
01.03.01.11 PRUEBA HIDRAULICA LIMPIEZA Y DESINFECCIÓN ML 3,362.00 1.52 5,110.24
01.03.01.12 RELLENO Y COMPACTACION MANUAL DE ZANJAS ML 3,362.00 2.40 8,068.80
01.03.01.13 PROVISION DE MATERIAL DE PRESTAMO PUESTO A PIE DE OBRA GLB 1.00 144,067.88 144,067.88
01.03.02 PASE AEREO (D=2", L=15 M) (02 UNID) 7,006.02
01.03.02.01 TRAZO Y REPLANTEO PRELIMINAR M2 23.40 0.84 19.66
01.03.02.02 EXCAV. MANUAL EN TERRENO SUELTO M3 4.91 40.05 196.65
01.03.02.03 ELIMINACION DE MATERIAL EXCEDENTE M3 6.38 33.37 212.90
01.03.02.04 SOLADO DE 2" MEZCLA 1:12 C:H M2 0.29 21.78 6.32
01.03.02.05 CONCRETO CICLOPEO 1:10 + 50% de P.G. M3 3.38 330.20 1,116.08
01.03.02.06 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 0.26 576.26 149.83
01.03.02.07 CONCRETO f'c=210 kg/cm2 (SIN MEZCLADORA) M3 0.53 612.26 324.50
01.03.02.08 ACERO DE REFUERZO FY=4200 KG/CM2 KG 70.34 5.70 400.94
01.03.02.09 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 11.06 53.96 596.80
01.03.02.10 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/PASE AEREO (D=2", L=15 M) UND 2.00 1,824.45 3,648.90
01.03.02.11 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 6.40 39.17 250.69
01.03.02.12 PINTURA ESMALTE EN COLUMNAS M2 6.40 12.93 82.75
01.03.03 PASE AEREO (D=1", L=35 M) (01 UNID) 8,655.01
01.03.03.01 TRAZO Y REPLANTEO PRELIMINAR M2 46.80 0.84 39.31
01.03.03.02 EXCAV. MANUAL EN TERRENO SUELTO M3 9.82 40.05 393.29
01.03.03.03 ELIMINACION DE MATERIAL EXCEDENTE M3 12.77 33.37 426.13
01.03.03.04 SOLADO DE 2" MEZCLA 1:12 C:H M2 0.58 21.78 12.63
01.03.03.05 CONCRETO CICLOPEO 1:10 + 50% de P.G. M3 6.75 330.20 2,228.85
01.03.03.06 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 0.51 576.26 293.89
01.03.03.07 CONCRETO f'c=210 kg/cm2 (SIN MEZCLADORA) M3 0.80 612.26 489.81
01.03.03.08 ACERO DE REFUERZO FY=4200 KG/CM2 KG 119.82 5.70 682.97
01.03.03.09 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 17.31 53.96 934.05
01.03.03.10 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/PASE AEREO (D=1", L=35 M) UND 1.00 2,737.28 2,737.28
01.03.03.11 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 8.00 39.17 313.36
01.03.03.12 PINTURA ESMALTE EN COLUMNAS M2 8.00 12.93 103.44
01.03.04 VALVULAS DE CONTROL (03 UNID) 1,354.53
01.03.04.01 TRAZO Y REPLANTEO PRELIMINAR M2 1.92 0.84 1.61
01.03.04.02 EXCAV. MANUAL EN TERRENO SUELTO M3 0.86 40.05 34.44
01.03.04.03 SOLADO DE 2" MEZCLA 1:12 C:H M2 0.10 21.78 2.18
01.03.04.04 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 0.47 576.26 270.84
01.03.04.05 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 3.60 53.96 194.26
01.03.04.06 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 2.16 39.17 84.61
01.03.04.07 PINTURA ESMALTE EN MUROS M2 2.16 12.93 27.93
01.03.04.08 PINTURA ANTICORROSIVA EN TAPAS METALICAS M2 0.96 15.34 14.73
01.03.04.09 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/CAMARA DE VALVULA DE CONTROL (L.C.=2")UND 2.00 252.06 504.12
01.03.04.10 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/CAMARA DE VALVULA DE CONTROL (L.C.=1")UND 1.00 219.81 219.81
01.03.05 VALVULA DE PURGA (10 UNID.) 5,131.57
01.03.05.01 TRAZO Y REPLANTEO PRELIMINAR M2 6.40 0.84 5.38
01.03.05.02 EXCAV. MANUAL EN TERRENO SUELTO M3 2.88 40.05 115.34
01.03.05.03 SOLADO DE 2" MEZCLA 1:12 C:H M2 0.32 21.78 6.97
01.03.05.04 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 1.92 576.26 1,106.42
01.03.05.05 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 16.80 53.96 906.53
01.03.05.06 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 12.00 39.17 470.04
01.03.05.07 PINTURA ESMALTE EN MUROS M2 7.20 12.93 93.10
01.03.05.08 PINTURA ANTICORROSIVA EN TAPAS METALICAS M2 3.20 15.34 49.09
01.03.05.09 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/CAMARA DE VALVULA DE PURGA (L.C.=1")UND 3.00 256.21 768.63
01.03.05.10 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/CAMARA DE VALVULA DE PURGA (L.D.=3/4")UND 7.00 230.01 1,610.07
01.03.06 CAMARAS DE CARGA (02 UNID) 8,393.25
01.03.06.01 TRAZO Y REPLANTEO PRELIMINAR M2 4.51 0.84 3.79
01.03.06.02 EXCAV. MANUAL EN TERRENO SUELTO M3 4.51 40.05 180.63
01.03.06.03 ELIMINACION DE MATERIAL EXCEDENTE M3 5.86 33.37 195.55
01.03.06.04 SOLADO DE 2" MEZCLA 1:12 C:H M2 4.51 21.78 98.23
01.03.06.05 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 3.19 576.26 1,838.27
01.03.06.06 ACERO DE REFUERZO FY=4200 KG/CM2 KG 201.71 5.70 1,149.75
01.03.06.07 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 32.67 53.96 1,762.87
01.03.06.08 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 20.42 39.17 799.85
01.03.06.09 TARRAJEO INTERIOR CON IMPERMEABILIZANTE e=1.50 cm - MEZCLA 1:2 M2 14.08 51.05 718.78
01.03.06.10 PINTURA ESMALTE EN MUROS M2 20.42 12.93 264.03
01.03.06.11 PINTURA ANTICORROSIVA EN TAPAS METALICAS M2 1.28 15.34 19.64
01.03.06.12 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/CAMARA DE CARGA TIPO 01 (LC=2" , S1=1 1/2" y S2=1")UND 1.00 688.93 688.93
01.03.06.13 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/CAMARA DE CARGA TIPO 02 (LC=1" , S1=1")UND 1.00 672.93 672.93
01.03.07 CAMARAS ROMPEPRESIONES (05 UNID.) 8,305.84
01.03.07.01 TRAZO Y REPLANTEO PRELIMINAR M2 6.05 0.84 5.08
01.03.07.02 EXCAV. MANUAL EN TERRENO SUELTO M3 6.66 40.05 266.73
01.03.07.03 ELIMINACION DE MATERIAL EXCEDENTE M3 8.65 33.37 288.65
01.03.07.04 SOLADO DE 2" MEZCLA 1:12 C:H M2 6.05 21.78 131.77
01.03.07.05 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 2.50 576.26 1,440.65
01.03.07.06 ACERO DE REFUERZO FY=4200 KG/CM2 KG 81.66 5.70 465.46
01.03.07.07 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 37.60 53.96 2,028.90
01.03.07.08 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 21.15 39.17 828.45
01.03.07.09 TARRAJEO INTERIOR CON IMPERMEABILIZANTE e=1.50 cm - MEZCLA 1:2 M2 16.45 51.05 839.77
01.03.07.10 PINTURA ESMALTE EN MUROS M2 19.80 12.93 256.01
01.03.07.11 PINTURA ANTICORROSIVA EN TAPAS METALICAS M2 3.60 15.34 55.22
01.03.07.12 SUMINISTRO Y COLOCACION DE ACCESORIOS P/C.R.P. TIPO VI EN L.C. DE 2" UND 5.00 339.83 1,699.15
01.04 CONSTRUCCION DE RESERVORIOS DE ALMACENAMIENTO 19,856.97
01.04.01 RESERV. DE 2.50 M3 (E=1", S=1")(INC. CAMARA DE VALVULAS) (01 UNID.) 7,259.12
01.04.01.01 TRAZO Y REPLANTEO PRELIMINAR M2 7.59 0.84 6.38
01.04.01.02 EXCAV. MANUAL EN TERRENO SUELTO M3 6.11 40.05 244.71
01.04.01.03 ELIMINACION DE MATERIAL EXCEDENTE M3 7.94 33.37 264.96
01.04.01.04 SOLADO DE 2" MEZCLA 1:12 C:H M2 6.53 21.78 142.22
01.04.01.05 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 3.23 576.26 1,861.32
01.04.01.06 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 27.93 53.96 1,507.10
01.04.01.07 ACERO DE REFUERZO FY=4200 KG/CM2 KG 122.25 5.70 696.83
01.04.01.08 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 13.18 39.17 516.26
01.04.01.09 TARRAJEO INTERIOR CON IMPERMEABILIZANTE e=1.50 cm - MEZCLA 1:2 M2 10.24 51.05 522.75
01.04.01.10 PINTURA ESMALTE EN MUROS M2 10.24 12.93 132.40
01.04.01.11 PINTURA ANTICORROSIVA EN TAPAS METALICAS M2 1.44 15.34 22.09
01.04.01.12 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/RESERVORIO DE 2.00 M3 (L.C.=1") UND 1.00 1,342.10 1,342.10
01.04.02 RESERV. DE 5.00 M3 (E=1 1/2", S=1 1/2")(INC. CAMARA DE VALVULAS) (01 UNID.) 12,597.85
01.04.02.01 TRAZO Y REPLANTEO PRELIMINAR M2 12.56 0.84 10.55
01.04.02.02 EXCAV. MANUAL EN TERRENO SUELTO M3 9.99 40.05 400.10
01.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE M3 12.99 33.37 433.48
01.04.02.04 SOLADO DE 2" MEZCLA 1:12 C:H M2 11.11 21.78 241.98
01.04.02.05 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 5.56 576.26 3,204.01
01.04.02.06 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 45.38 53.96 2,448.70
01.04.02.07 ACERO DE REFUERZO FY=4200 KG/CM2 KG 356.80 5.70 2,033.76
01.04.02.08 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 23.40 39.17 916.58
01.04.02.09 TARRAJEO INTERIOR CON IMPERMEABILIZANTE e=1.50 cm - MEZCLA 1:2 M2 19.68 51.05 1,004.66
01.04.02.10 PINTURA ESMALTE EN MUROS M2 22.95 12.93 296.74
01.04.02.11 PINTURA ANTICORROSIVA EN TAPAS METALICAS M2 1.44 15.34 22.09
01.04.02.12 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/RESERVORIO DE 5.00 M3 (L.C.=1 1/2") UND 1.00 1,585.20 1,585.20
01.05 LINEA DE DISTRIBUCION 32,605.76
01.05.01 LIMPIEZA MANUAL DE TERRENO CON PRESENCIA DE PIEDRA M2 1,505.00 3.34 5,026.70
01.05.02 TRAZO Y REPLANTEO DE ZANJAS (ML) ML 1,003.00 2.17 2,176.51
01.05.03 EXCAVACION MANUAL EN ZANJAS (TERRENO NATURAL) (ZANJA DE 0.40 x 0.60) ML 1,003.00 10.01 10,040.03
01.05.04 REFINE Y NIVELACION DE ZANJAS (b=0.40m) ML 1,003.00 2.00 2,006.00
01.05.05 CAMA DE APOYO PARA TUB. C/MAT. ZARANDEADO (h=0.10m) ML 1,003.00 3.34 3,350.02
01.05.06 SUMINISTRO E INSTALACION DE TUBERIA PVC-SAP C=7.5, D=1 1/2" ML 119.00 8.10 963.90
01.05.07 SUMINISTRO E INSTALACION DE TUBERIA PVC-SAP C=10, D=1" ML 333.00 6.62 2,204.46
01.05.08 SUMINISTRO E INSTALACION DE TUBERIA PVC-SAP C=10, D=3/4" ML 551.00 4.76 2,622.76
01.05.09 PRUEBA HIDRAULICA LIMPIEZA Y DESINFECCIÓN ML 1,003.00 1.52 1,524.56
01.05.10 RELLENO Y COMPACTACION MANUAL DE ZANJAS ML 1,003.00 2.40 2,407.20
01.05.11 TEE SP PVC-SAP 1 1/2" (INCLUYE SUMIN. E INSTALAC.) UND 3.00 24.66 73.98
01.05.12 TEE SP PVC-SAP 1" (INCLUYE SUMIN. E INSTALAC.) UND 2.00 19.07 38.14
01.05.13 TEE SP PVC-SAP 3/4" (INCLUYE SUMIN. E INSTALAC.) UND 2.00 17.37 34.74
01.05.14 REDUCCION SP PVC-SAP DE 1 1/2" A 1" (INCLUYE SUMIN. E INSTALAC.) UND 2.00 19.07 38.14
01.05.15 REDUCCION SP PVC-SAP DE 1 1/2" A 3/4" (INCLUYE SUMIN. E INSTALAC.) UND 2.00 18.07 36.14
01.05.16 REDUCCION SP PVC-SAP DE 1" A 3/4" (INCLUYE SUMIN. E INSTALAC.) UND 3.00 15.57 46.71
01.05.17 CODO SP PVC-SAP 1"x90 (INCLUYE SUMIN. E INSTALAC.) UND 1.00 15.77 15.77
01.06 CONEXIONES DOMICILIARIAS PARA AGUA POTABLE (32 UNID.) 7,779.86
01.06.01 TRAZO Y REPLANTEO PRELIMINAR M2 192.00 0.84 161.28
01.06.02 EXCAV. MANUAL EN TERRENO SUELTO M3 76.80 40.05 3,075.84
01.06.03 SUMINISTRO Y COLOCACION DE ACCESORIOS P/CONEX. DOMICIL. (MATRIZ 1") UND 23.00 142.72 3,282.56
01.06.04 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/CONEX. DOMICIL. (MATRIZ 3/4'') UND 9.00 140.02 1,260.18
01.07 PILETAS DOMICILIARIAS (32 UNID.) 30,200.45
01.07.01 TRAZO Y REPLANTEO PRELIMINAR M2 26.08 0.84 21.91
01.07.02 EXCAV. MANUAL EN TERRENO SUELTO M3 1.73 40.05 69.29
01.07.03 ELIMINACION DE MATERIAL EXCEDENTE M3 2.25 33.37 75.08
01.07.04 CONCRETO CICLOPEO 1:10 + 50% de P.G. M3 1.73 330.20 571.25
01.07.05 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 8.16 576.26 4,702.28
01.07.06 ACERO DE REFUERZO FY=4200 KG/CM2 KG 158.19 5.78 914.34
01.07.07 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 184.00 53.96 9,928.64
01.07.08 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 137.12 39.17 5,370.99
01.07.09 ACABADO COLOREADO CON OCRE (1:3) M2 137.12 21.17 2,902.83
01.07.10 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/PILETA DOMICILIARIA UND 32.00 176.37 5,643.84
02 FLETE TERRESTRE 349,217.97
02.01 TRANSPORTE DE MATERIALES TN 150.00 489.22 73,383.00
02.02 TRASLADO DE CEMENTO A MANO - A PIE DE OBRA BLS 1,079.00 24.30 26,219.70
02.03 TRASLADO DE MADERA A MANO - A PIE DE OBRA KG 10,362.00 0.61 6,320.82
02.04 TRASLADO DE FIERROS, MATERIALES DE FERRETERIAY OTROS A MANO - A PIE DE OBRA KG 46,713.00 0.61 28,494.93
02.05 TRASLADO DE AGREGADOS A MANO - A PIE DE OBRA KG 740,688.00 0.29 214,799.52
03 VARIOS 4,258.85
03.01 PLACA INAUGURACION UND 1.00 970.77 970.77
03.02 CERCO PERIMETRICO CON ALAMBRE DE PUAS - CAPTACIONES M 40.00 35.45 1,418.00
03.03 CERCO PERIMETRICO CON ALAMBRE DE PUAS - RESERVORIOS M 36.00 38.44 1,383.84
03.04 PUERTA DE INGRESO PARA CERCOS CON ALAMBRE DE PUAS UND 3.00 162.08 486.24
01 OBRAS PROVISIONALES Y PRELIMINARES 222.57
01.01 TRAZO Y REPLANTEO PRELIMINAR M2 264.96 0.84 222.57
02 MOVIMIENTO DE TIERRAS 3,013.93
02.01 EXCAV. MANUAL EN TERRENO SUELTO M3 36.86 40.05 1,476.24
02.02 ELIMINACION DE MATERIAL EXCEDENTE (D<500m)) M3 46.08 33.37 1,537.69
03 OBRAS DE CONCRETO CICLOPEO 10,390.83
03.01 CONCRETO CICLOPEO f'c=140 Kg/cm2 + 70% PM. M3 36.86 281.90 10,390.83
04 OBRAS DE CONCRETO SIMPLE 15,115.79
04.01 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTO M2 143.42 55.09 7,901.01
04.02 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 12.52 576.26 7,214.78
05 ALBAÑILERIA 73,795.06
05.01 MURO DE LADRILLO MECANIZADO 24x12x9 SOGA M2 399.62 79.96 31,953.62
05.02 TARRAJEO EN INTERIORES Y EXTERIORES (MORTERO 1:5) M2 854.43 29.83 25,487.65
05.03 PINTURA ESMALTE EN MUROS EXTERIORES M2 854.43 19.14 16,353.79
06 PISOS Y PAVIMENTOS 28,488.64
06.01 APISONADO DE PISO M2 80.64 3.34 269.34
06.02 EMPEDRADO DE PISO M2 80.64 16.88 1,361.20
06.03 CONCRETO f"c=140 Kg/cm2 (SIN MEZCLADORA) M3 8.06 476.24 3,838.49
06.04 PISO DE LOSETA M2 80.64 59.93 4,832.76
06.05 VEREDA DE CONCRETO f'c=140 Kg/cm2 E=4" M2 149.76 121.44 18,186.85
07 COBERTURAS 10,952.10
07.01 COBERTURA CON CALAMINA GALVANIZADA M2 149.76 38.74 5,801.70
07.02 LISTONES Y/O CORREAS DE MADERA MOD 32.00 160.95 5,150.40
08 CARPINTERIA DE MADERA 14,127.68
08.01 CONFECCION Y COLOCACION DE PUERTAS DE MADERA UND 32.00 315.31 10,089.92
08.02 CONFECCION Y COLOCACION DE VENTANA DE MADERA CON MALLA UND 32.00 126.18 4,037.76
09 APARATOS Y ACCESORIOS SANITARIOS 9,538.88
09.01 INODORO TANQUE BAJO BLANCO PZA 32.00 298.09 9,538.88
10 INSTALACIONES SANITARIAS 15,612.80
10.01 SUMINISTRO E INSTALACION DE ACCESORIOS PARA AGUA Ø1/2" MOD 32.00 279.50 8,944.00
10.02 SUMINISTRO E INSTALACION DE ACCESORIOS PARA ELIMINACION DE AGUAS SERVIDAS MOD 32.00 208.40 6,668.80
11 INSTALACION DE BIODIGESTOR 73,599.28
11.01 TRAZO Y REPLANTEO PRELIMINAR M2 118.08 0.84 99.19
11.02 EXCAV. MANUAL EN TERRENO SUELTO M3 145.14 40.05 5,812.86
11.03 ELIMINACION DE MATERIAL EXCEDENTE (D<500m)) M3 80.63 33.37 2,690.62
11.04 REFINE Y NIVELACION DE ZANJAS (b=0.40m) ML 40.00 2.00 80.00
11.05 CAMA DE APOYO PARA TUBERIAS M3 13.44 33.37 448.49
11.06 CAJA DE REGISTRO 12" x 24" TAPA DE CONCRETO UND 32.00 120.54 3,857.28
11.07 CAJA DE REGISTRO DE LODOS UND 32.00 275.08 8,802.56
11.08 SUMINISTRO E INSTALACION DE BIODIGESTOR PREFABRICADO DE CAP. 600L UND 32.00 1,363.88 43,644.16
11.09 RELLENO CON MATERIAL PROPIO M3 80.64 16.69 1,345.88
11.10 SUMINISTRO EN INSTALCION DE TUBERIA Y ACCESORIOS GLB 32.00 213.07 6,818.24
12 PERCOLACION 12,747.96
12.01 TRAZO Y REPLANTEO PRELIMINAR M2 155.90 0.84 130.96
12.02 EXCAV. MANUAL EN TERRENO SUELTO M3 94.54 40.05 3,786.33
12.03 ELIMINACION DE MATERIAL EXCEDENTE (D<500m)) M3 116.93 33.37 3,901.95
12.04 FILTRO DE GRAVA CLASIFICADA 1 1/2" A 1//4" M3 92.16 53.48 4,928.72
13 MITIGACION DE IMPACTOS AMBIENTALES 41,007.40
13.01 MANEJO DE RESIDUOS SOLIDOS 15,584.41
13.01.01 RECOLECCION DE DESECHOS DE OBRA GLB 1.00 256.82 256.82
13.01.02 EXCAVACION DE HOYOS PARA RELLENO PROVISIONAL UND 9.00 82.51 742.59
13.01.03 CLAUSURA DE RELLENO PROVISIONAL UND 9.00 49.26 443.34
13.01.04 SUMINISTRO E INST. PROVISIONAL DE BAÑOS MOVILES UND 2.00 3,937.01 7,874.02
13.01.05 OPERACION Y MANT. PROVISIONAL DE BAÑOS MOVILES UND 4.00 1,566.91 6,267.64
13.02 REHABILITACION DE AREAS DEGRADAS 20,398.96
13.02.01 REHABILITACION DE AREA DE CAMPAMENTO M2 120.00 91.84 11,020.80
13.02.02 REHABILITACION DE AREA DE PREPARADO DE MATERIAL DE CONCRETO M2 90.00 91.84 8,265.60
13.02.03 ADECUACION DE VIAS DE ACCESO GLB 1.00 1,112.56 1,112.56
13.03 REFORESTACION 4,787.18
13.03.01 PLANTAS ARBOREAS UND 150.00 2.51 376.50
13.03.02 PLANTAS FRUTALES UND 100.00 2.52 252.00
13.03.03 PLANTAS ARBUSTIVAS UND 150.00 0.51 76.50
13.03.04 AGUA PARA RIEGO M3 2.00 180.29 360.58
13.03.05 TRANSPORTE DE PLANTONES VJE 2.00 900.80 1,801.60
13.03.06 PLANTACION DE ESPECIES VEGETALES UND 400.00 4.80 1,920.00
13.04 CONTROL DE CALIDAD DEL AIRE 236.85
13.04.01 LONA PARA PROTECCION DE TRANSPORTE EN VOLQUETE M 15.00 15.79 236.85
01 CAPACITACION EN EDUCACION SANITARIA 46,810.00
01.01 CAPACITACION EN EDUCACION SANITARIA GLB 1.00 46,810.00 46,810.00

Más contenido relacionado

Destacado

Letter of Recommendation from Kendall Point CB
Letter of Recommendation from Kendall Point CBLetter of Recommendation from Kendall Point CB
Letter of Recommendation from Kendall Point CB
Krystyna Gehl
 
2014 2015-update-on-ebola-virus-dr-bryna-warshawsky (1)
2014 2015-update-on-ebola-virus-dr-bryna-warshawsky  (1)2014 2015-update-on-ebola-virus-dr-bryna-warshawsky  (1)
2014 2015-update-on-ebola-virus-dr-bryna-warshawsky (1)
Elyas Mohammed
 
Providers Agreement Coordination Treatment (PACT)
Providers Agreement Coordination Treatment (PACT)Providers Agreement Coordination Treatment (PACT)
Providers Agreement Coordination Treatment (PACT)
motleycoolin
 
Turnaround management
Turnaround managementTurnaround management
Turnaround management
Amit Fogla
 

Destacado (20)

마니커 (027740) 알고리즘 기업분석 보고서
마니커 (027740) 알고리즘 기업분석 보고서마니커 (027740) 알고리즘 기업분석 보고서
마니커 (027740) 알고리즘 기업분석 보고서
 
5 reporte
5 reporte5 reporte
5 reporte
 
Descripcion de autobiografia
Descripcion de autobiografiaDescripcion de autobiografia
Descripcion de autobiografia
 
Li fi
Li fiLi fi
Li fi
 
Ada 1
Ada 1Ada 1
Ada 1
 
Glosario
GlosarioGlosario
Glosario
 
Infographic: Mobile Retail Execution & Quality Assurance
Infographic: Mobile Retail Execution & Quality AssuranceInfographic: Mobile Retail Execution & Quality Assurance
Infographic: Mobile Retail Execution & Quality Assurance
 
Letter of Recommendation from Kendall Point CB
Letter of Recommendation from Kendall Point CBLetter of Recommendation from Kendall Point CB
Letter of Recommendation from Kendall Point CB
 
2014 2015-update-on-ebola-virus-dr-bryna-warshawsky (1)
2014 2015-update-on-ebola-virus-dr-bryna-warshawsky  (1)2014 2015-update-on-ebola-virus-dr-bryna-warshawsky  (1)
2014 2015-update-on-ebola-virus-dr-bryna-warshawsky (1)
 
Triptico
TripticoTriptico
Triptico
 
Second evaltuation q1
Second evaltuation q1Second evaltuation q1
Second evaltuation q1
 
Introductory discussion to 13 C NMR
Introductory discussion to 13 C NMRIntroductory discussion to 13 C NMR
Introductory discussion to 13 C NMR
 
Sexual Assult
Sexual AssultSexual Assult
Sexual Assult
 
Providers Agreement Coordination Treatment (PACT)
Providers Agreement Coordination Treatment (PACT)Providers Agreement Coordination Treatment (PACT)
Providers Agreement Coordination Treatment (PACT)
 
Practicas de aprendizaje_n_5 (1) (1)
Practicas de aprendizaje_n_5 (1) (1)Practicas de aprendizaje_n_5 (1) (1)
Practicas de aprendizaje_n_5 (1) (1)
 
Using technology & innovation to tackle the effects of climate change
Using technology & innovation to tackle the effects of climate changeUsing technology & innovation to tackle the effects of climate change
Using technology & innovation to tackle the effects of climate change
 
Inteligencias multiples
Inteligencias multiplesInteligencias multiples
Inteligencias multiples
 
Dell boomi interview questions
Dell boomi interview questionsDell boomi interview questions
Dell boomi interview questions
 
Turnaround management
Turnaround managementTurnaround management
Turnaround management
 
Radiología del tórax
Radiología del tóraxRadiología del tórax
Radiología del tórax
 

Saneamiento amsat

  • 1. Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) 01 INSTALACION DEL SISTEMA DE AGUA POTABLE 636,367.27 01.01 OBRAS PROVISIONALES 42,570.40 01.01.01 CONSTRUCCION DE ALMACENES Y GUARDIANÍA M2 120.00 107.50 12,900.00 01.01.02 CARTEL DE OBRA UND 1.00 1,266.70 1,266.70 01.01.03 SALUD Y SEGURIDAD 28,403.70 01.01.03.01 EQUIPOS DE PROTECCIÓN INDIVIDUAL GLB 1.00 9,210.00 9,210.00 01.01.03.02 SEÑALIZACION TEMPORAL DE SEGURIDAD MES 5.00 360.46 1,802.30 01.01.03.03 CAPACITACION EN SALUD Y SEGURIDAD GLB 1.00 16,631.40 16,631.40 01.01.03.04 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJOGLB 1.00 760.00 760.00 01.02 CONSTRUCCION DE CAPTACIONES 11,789.76 01.02.01 CAPT. DE LADERA L.C.=2" (01 UNID.) 11,789.76 01.02.01.01 TRAZO Y REPLANTEO PRELIMINAR M2 6.29 0.84 5.28 01.02.01.02 EXCAV. MANUAL EN TERRENO SUELTO M3 23.37 40.05 935.97 01.02.01.03 ELIMINACION DE MATERIAL EXCEDENTE (D<500m)) M3 30.38 33.37 1,013.78 01.02.01.04 RELLENO DE GRAVA DE 1 1/2'' SELECCIONADA M3 6.00 181.31 1,087.86 01.02.01.05 CONCRETO CICLOPEO 1:10 + 50% de P.G. M3 1.15 330.20 379.73 01.02.01.06 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 5.38 576.26 3,100.28 01.02.01.07 ACERO DE REFUERZO FY=4200 KG/CM2 KG 28.20 5.70 160.74 01.02.01.08 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 41.50 53.96 2,239.34 01.02.01.09 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 20.58 39.17 806.12 01.02.01.10 TARRAJEO INTERIOR CON IMPERMEABILIZANTE e=1.50 cm - MEZCLA 1:2 M2 6.16 51.05 314.47 01.02.01.11 PINTURA ESMALTE EN MUROS M2 5.10 12.93 65.94 01.02.01.12 PINTURA ANTICORROSIVA EN TAPAS METALICAS M2 50.06 15.34 767.92 01.02.01.13 SUMINISTRO Y COLOCACION DE ACCES./CAPTACION DE LADERA (L.C.=Ø2") UND 1.00 912.33 912.33 01.03 LINEA DE CONDUCCION 491,564.07 01.03.01 RED PRIMARIA 452,717.85 01.03.01.01 LIMPIEZA MANUAL DE TERRENO CON PRESENCIA DE PIEDRA M2 5,043.00 3.34 16,843.62 01.03.01.02 TRAZO Y REPLANTEO DE ZANJAS (ML) ML 3,362.00 2.17 7,295.54 01.03.01.03 EXCAVACION MANUAL EN ZANJAS (TERRENO NATURAL) (ZANJA DE 0.40 x 0.60) ML 1,782.21 10.01 17,839.92 01.03.01.04 EXCAVACION DE ZANJA EN ROCA SUELTA ML 400.00 85.77 34,308.00 01.03.01.05 EXCAVACION DE ZANJA EN ROCA DURA ML 1,180.00 144.53 170,545.40 01.03.01.06 REFINE Y NIVELACION DE ZANJAS (b=0.40m) ML 3,362.00 2.00 6,724.00 01.03.01.07 CAMA DE APOYO PARA TUB. C/MAT. ZARANDEADO (h=0.10m) ML 3,362.00 3.34 11,229.08 01.03.01.08 SUMINISTRO E INSTALACION DE TUBERIA PVC-SAP C=7.5, D=2" ML 2,681.21 9.74 26,114.99 01.03.01.09 SUMINISTRO E INSTALACION DE TUBERIA PVC-SAP C=7.5, D=1 1/2" ML 42.00 8.10 340.20 01.03.01.10 SUMINISTRO E INSTALACION DE TUBERIA PVC-SAP C=10, D=1" ML 639.00 6.62 4,230.18 01.03.01.11 PRUEBA HIDRAULICA LIMPIEZA Y DESINFECCIÓN ML 3,362.00 1.52 5,110.24 01.03.01.12 RELLENO Y COMPACTACION MANUAL DE ZANJAS ML 3,362.00 2.40 8,068.80 01.03.01.13 PROVISION DE MATERIAL DE PRESTAMO PUESTO A PIE DE OBRA GLB 1.00 144,067.88 144,067.88 01.03.02 PASE AEREO (D=2", L=15 M) (02 UNID) 7,006.02 01.03.02.01 TRAZO Y REPLANTEO PRELIMINAR M2 23.40 0.84 19.66 01.03.02.02 EXCAV. MANUAL EN TERRENO SUELTO M3 4.91 40.05 196.65 01.03.02.03 ELIMINACION DE MATERIAL EXCEDENTE M3 6.38 33.37 212.90 01.03.02.04 SOLADO DE 2" MEZCLA 1:12 C:H M2 0.29 21.78 6.32 01.03.02.05 CONCRETO CICLOPEO 1:10 + 50% de P.G. M3 3.38 330.20 1,116.08 01.03.02.06 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 0.26 576.26 149.83 01.03.02.07 CONCRETO f'c=210 kg/cm2 (SIN MEZCLADORA) M3 0.53 612.26 324.50 01.03.02.08 ACERO DE REFUERZO FY=4200 KG/CM2 KG 70.34 5.70 400.94 01.03.02.09 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 11.06 53.96 596.80 01.03.02.10 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/PASE AEREO (D=2", L=15 M) UND 2.00 1,824.45 3,648.90 01.03.02.11 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 6.40 39.17 250.69 01.03.02.12 PINTURA ESMALTE EN COLUMNAS M2 6.40 12.93 82.75 01.03.03 PASE AEREO (D=1", L=35 M) (01 UNID) 8,655.01 01.03.03.01 TRAZO Y REPLANTEO PRELIMINAR M2 46.80 0.84 39.31 01.03.03.02 EXCAV. MANUAL EN TERRENO SUELTO M3 9.82 40.05 393.29 01.03.03.03 ELIMINACION DE MATERIAL EXCEDENTE M3 12.77 33.37 426.13 01.03.03.04 SOLADO DE 2" MEZCLA 1:12 C:H M2 0.58 21.78 12.63 01.03.03.05 CONCRETO CICLOPEO 1:10 + 50% de P.G. M3 6.75 330.20 2,228.85 01.03.03.06 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 0.51 576.26 293.89 01.03.03.07 CONCRETO f'c=210 kg/cm2 (SIN MEZCLADORA) M3 0.80 612.26 489.81 01.03.03.08 ACERO DE REFUERZO FY=4200 KG/CM2 KG 119.82 5.70 682.97 01.03.03.09 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 17.31 53.96 934.05 01.03.03.10 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/PASE AEREO (D=1", L=35 M) UND 1.00 2,737.28 2,737.28 01.03.03.11 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 8.00 39.17 313.36 01.03.03.12 PINTURA ESMALTE EN COLUMNAS M2 8.00 12.93 103.44 01.03.04 VALVULAS DE CONTROL (03 UNID) 1,354.53 01.03.04.01 TRAZO Y REPLANTEO PRELIMINAR M2 1.92 0.84 1.61 01.03.04.02 EXCAV. MANUAL EN TERRENO SUELTO M3 0.86 40.05 34.44 01.03.04.03 SOLADO DE 2" MEZCLA 1:12 C:H M2 0.10 21.78 2.18 01.03.04.04 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 0.47 576.26 270.84 01.03.04.05 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 3.60 53.96 194.26 01.03.04.06 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 2.16 39.17 84.61 01.03.04.07 PINTURA ESMALTE EN MUROS M2 2.16 12.93 27.93 01.03.04.08 PINTURA ANTICORROSIVA EN TAPAS METALICAS M2 0.96 15.34 14.73 01.03.04.09 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/CAMARA DE VALVULA DE CONTROL (L.C.=2")UND 2.00 252.06 504.12 01.03.04.10 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/CAMARA DE VALVULA DE CONTROL (L.C.=1")UND 1.00 219.81 219.81
  • 2. 01.03.05 VALVULA DE PURGA (10 UNID.) 5,131.57 01.03.05.01 TRAZO Y REPLANTEO PRELIMINAR M2 6.40 0.84 5.38 01.03.05.02 EXCAV. MANUAL EN TERRENO SUELTO M3 2.88 40.05 115.34 01.03.05.03 SOLADO DE 2" MEZCLA 1:12 C:H M2 0.32 21.78 6.97 01.03.05.04 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 1.92 576.26 1,106.42 01.03.05.05 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 16.80 53.96 906.53 01.03.05.06 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 12.00 39.17 470.04 01.03.05.07 PINTURA ESMALTE EN MUROS M2 7.20 12.93 93.10 01.03.05.08 PINTURA ANTICORROSIVA EN TAPAS METALICAS M2 3.20 15.34 49.09 01.03.05.09 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/CAMARA DE VALVULA DE PURGA (L.C.=1")UND 3.00 256.21 768.63 01.03.05.10 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/CAMARA DE VALVULA DE PURGA (L.D.=3/4")UND 7.00 230.01 1,610.07 01.03.06 CAMARAS DE CARGA (02 UNID) 8,393.25 01.03.06.01 TRAZO Y REPLANTEO PRELIMINAR M2 4.51 0.84 3.79 01.03.06.02 EXCAV. MANUAL EN TERRENO SUELTO M3 4.51 40.05 180.63 01.03.06.03 ELIMINACION DE MATERIAL EXCEDENTE M3 5.86 33.37 195.55 01.03.06.04 SOLADO DE 2" MEZCLA 1:12 C:H M2 4.51 21.78 98.23 01.03.06.05 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 3.19 576.26 1,838.27 01.03.06.06 ACERO DE REFUERZO FY=4200 KG/CM2 KG 201.71 5.70 1,149.75 01.03.06.07 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 32.67 53.96 1,762.87 01.03.06.08 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 20.42 39.17 799.85 01.03.06.09 TARRAJEO INTERIOR CON IMPERMEABILIZANTE e=1.50 cm - MEZCLA 1:2 M2 14.08 51.05 718.78 01.03.06.10 PINTURA ESMALTE EN MUROS M2 20.42 12.93 264.03 01.03.06.11 PINTURA ANTICORROSIVA EN TAPAS METALICAS M2 1.28 15.34 19.64 01.03.06.12 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/CAMARA DE CARGA TIPO 01 (LC=2" , S1=1 1/2" y S2=1")UND 1.00 688.93 688.93 01.03.06.13 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/CAMARA DE CARGA TIPO 02 (LC=1" , S1=1")UND 1.00 672.93 672.93 01.03.07 CAMARAS ROMPEPRESIONES (05 UNID.) 8,305.84 01.03.07.01 TRAZO Y REPLANTEO PRELIMINAR M2 6.05 0.84 5.08 01.03.07.02 EXCAV. MANUAL EN TERRENO SUELTO M3 6.66 40.05 266.73 01.03.07.03 ELIMINACION DE MATERIAL EXCEDENTE M3 8.65 33.37 288.65 01.03.07.04 SOLADO DE 2" MEZCLA 1:12 C:H M2 6.05 21.78 131.77 01.03.07.05 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 2.50 576.26 1,440.65 01.03.07.06 ACERO DE REFUERZO FY=4200 KG/CM2 KG 81.66 5.70 465.46 01.03.07.07 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 37.60 53.96 2,028.90 01.03.07.08 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 21.15 39.17 828.45 01.03.07.09 TARRAJEO INTERIOR CON IMPERMEABILIZANTE e=1.50 cm - MEZCLA 1:2 M2 16.45 51.05 839.77 01.03.07.10 PINTURA ESMALTE EN MUROS M2 19.80 12.93 256.01 01.03.07.11 PINTURA ANTICORROSIVA EN TAPAS METALICAS M2 3.60 15.34 55.22 01.03.07.12 SUMINISTRO Y COLOCACION DE ACCESORIOS P/C.R.P. TIPO VI EN L.C. DE 2" UND 5.00 339.83 1,699.15 01.04 CONSTRUCCION DE RESERVORIOS DE ALMACENAMIENTO 19,856.97 01.04.01 RESERV. DE 2.50 M3 (E=1", S=1")(INC. CAMARA DE VALVULAS) (01 UNID.) 7,259.12 01.04.01.01 TRAZO Y REPLANTEO PRELIMINAR M2 7.59 0.84 6.38 01.04.01.02 EXCAV. MANUAL EN TERRENO SUELTO M3 6.11 40.05 244.71 01.04.01.03 ELIMINACION DE MATERIAL EXCEDENTE M3 7.94 33.37 264.96 01.04.01.04 SOLADO DE 2" MEZCLA 1:12 C:H M2 6.53 21.78 142.22 01.04.01.05 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 3.23 576.26 1,861.32 01.04.01.06 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 27.93 53.96 1,507.10 01.04.01.07 ACERO DE REFUERZO FY=4200 KG/CM2 KG 122.25 5.70 696.83 01.04.01.08 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 13.18 39.17 516.26 01.04.01.09 TARRAJEO INTERIOR CON IMPERMEABILIZANTE e=1.50 cm - MEZCLA 1:2 M2 10.24 51.05 522.75 01.04.01.10 PINTURA ESMALTE EN MUROS M2 10.24 12.93 132.40 01.04.01.11 PINTURA ANTICORROSIVA EN TAPAS METALICAS M2 1.44 15.34 22.09 01.04.01.12 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/RESERVORIO DE 2.00 M3 (L.C.=1") UND 1.00 1,342.10 1,342.10 01.04.02 RESERV. DE 5.00 M3 (E=1 1/2", S=1 1/2")(INC. CAMARA DE VALVULAS) (01 UNID.) 12,597.85 01.04.02.01 TRAZO Y REPLANTEO PRELIMINAR M2 12.56 0.84 10.55 01.04.02.02 EXCAV. MANUAL EN TERRENO SUELTO M3 9.99 40.05 400.10 01.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE M3 12.99 33.37 433.48 01.04.02.04 SOLADO DE 2" MEZCLA 1:12 C:H M2 11.11 21.78 241.98 01.04.02.05 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 5.56 576.26 3,204.01 01.04.02.06 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 45.38 53.96 2,448.70 01.04.02.07 ACERO DE REFUERZO FY=4200 KG/CM2 KG 356.80 5.70 2,033.76 01.04.02.08 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 23.40 39.17 916.58 01.04.02.09 TARRAJEO INTERIOR CON IMPERMEABILIZANTE e=1.50 cm - MEZCLA 1:2 M2 19.68 51.05 1,004.66 01.04.02.10 PINTURA ESMALTE EN MUROS M2 22.95 12.93 296.74 01.04.02.11 PINTURA ANTICORROSIVA EN TAPAS METALICAS M2 1.44 15.34 22.09 01.04.02.12 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/RESERVORIO DE 5.00 M3 (L.C.=1 1/2") UND 1.00 1,585.20 1,585.20 01.05 LINEA DE DISTRIBUCION 32,605.76 01.05.01 LIMPIEZA MANUAL DE TERRENO CON PRESENCIA DE PIEDRA M2 1,505.00 3.34 5,026.70 01.05.02 TRAZO Y REPLANTEO DE ZANJAS (ML) ML 1,003.00 2.17 2,176.51 01.05.03 EXCAVACION MANUAL EN ZANJAS (TERRENO NATURAL) (ZANJA DE 0.40 x 0.60) ML 1,003.00 10.01 10,040.03 01.05.04 REFINE Y NIVELACION DE ZANJAS (b=0.40m) ML 1,003.00 2.00 2,006.00 01.05.05 CAMA DE APOYO PARA TUB. C/MAT. ZARANDEADO (h=0.10m) ML 1,003.00 3.34 3,350.02 01.05.06 SUMINISTRO E INSTALACION DE TUBERIA PVC-SAP C=7.5, D=1 1/2" ML 119.00 8.10 963.90 01.05.07 SUMINISTRO E INSTALACION DE TUBERIA PVC-SAP C=10, D=1" ML 333.00 6.62 2,204.46 01.05.08 SUMINISTRO E INSTALACION DE TUBERIA PVC-SAP C=10, D=3/4" ML 551.00 4.76 2,622.76 01.05.09 PRUEBA HIDRAULICA LIMPIEZA Y DESINFECCIÓN ML 1,003.00 1.52 1,524.56 01.05.10 RELLENO Y COMPACTACION MANUAL DE ZANJAS ML 1,003.00 2.40 2,407.20 01.05.11 TEE SP PVC-SAP 1 1/2" (INCLUYE SUMIN. E INSTALAC.) UND 3.00 24.66 73.98 01.05.12 TEE SP PVC-SAP 1" (INCLUYE SUMIN. E INSTALAC.) UND 2.00 19.07 38.14 01.05.13 TEE SP PVC-SAP 3/4" (INCLUYE SUMIN. E INSTALAC.) UND 2.00 17.37 34.74 01.05.14 REDUCCION SP PVC-SAP DE 1 1/2" A 1" (INCLUYE SUMIN. E INSTALAC.) UND 2.00 19.07 38.14 01.05.15 REDUCCION SP PVC-SAP DE 1 1/2" A 3/4" (INCLUYE SUMIN. E INSTALAC.) UND 2.00 18.07 36.14 01.05.16 REDUCCION SP PVC-SAP DE 1" A 3/4" (INCLUYE SUMIN. E INSTALAC.) UND 3.00 15.57 46.71 01.05.17 CODO SP PVC-SAP 1"x90 (INCLUYE SUMIN. E INSTALAC.) UND 1.00 15.77 15.77
  • 3. 01.06 CONEXIONES DOMICILIARIAS PARA AGUA POTABLE (32 UNID.) 7,779.86 01.06.01 TRAZO Y REPLANTEO PRELIMINAR M2 192.00 0.84 161.28 01.06.02 EXCAV. MANUAL EN TERRENO SUELTO M3 76.80 40.05 3,075.84 01.06.03 SUMINISTRO Y COLOCACION DE ACCESORIOS P/CONEX. DOMICIL. (MATRIZ 1") UND 23.00 142.72 3,282.56 01.06.04 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/CONEX. DOMICIL. (MATRIZ 3/4'') UND 9.00 140.02 1,260.18 01.07 PILETAS DOMICILIARIAS (32 UNID.) 30,200.45 01.07.01 TRAZO Y REPLANTEO PRELIMINAR M2 26.08 0.84 21.91 01.07.02 EXCAV. MANUAL EN TERRENO SUELTO M3 1.73 40.05 69.29 01.07.03 ELIMINACION DE MATERIAL EXCEDENTE M3 2.25 33.37 75.08 01.07.04 CONCRETO CICLOPEO 1:10 + 50% de P.G. M3 1.73 330.20 571.25 01.07.05 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 8.16 576.26 4,702.28 01.07.06 ACERO DE REFUERZO FY=4200 KG/CM2 KG 158.19 5.78 914.34 01.07.07 ENCOFRADO Y DESENCOFRADO NORMAL EN OBRAS DE ARTE M2 184.00 53.96 9,928.64 01.07.08 TARRAJEO EXTERIOR e=1.50 cm - MEZCLA 1:4 M2 137.12 39.17 5,370.99 01.07.09 ACABADO COLOREADO CON OCRE (1:3) M2 137.12 21.17 2,902.83 01.07.10 SUMINISTRO Y COLOCACIÓN DE ACCESORIOS P/PILETA DOMICILIARIA UND 32.00 176.37 5,643.84 02 FLETE TERRESTRE 349,217.97 02.01 TRANSPORTE DE MATERIALES TN 150.00 489.22 73,383.00 02.02 TRASLADO DE CEMENTO A MANO - A PIE DE OBRA BLS 1,079.00 24.30 26,219.70 02.03 TRASLADO DE MADERA A MANO - A PIE DE OBRA KG 10,362.00 0.61 6,320.82 02.04 TRASLADO DE FIERROS, MATERIALES DE FERRETERIAY OTROS A MANO - A PIE DE OBRA KG 46,713.00 0.61 28,494.93 02.05 TRASLADO DE AGREGADOS A MANO - A PIE DE OBRA KG 740,688.00 0.29 214,799.52 03 VARIOS 4,258.85 03.01 PLACA INAUGURACION UND 1.00 970.77 970.77 03.02 CERCO PERIMETRICO CON ALAMBRE DE PUAS - CAPTACIONES M 40.00 35.45 1,418.00 03.03 CERCO PERIMETRICO CON ALAMBRE DE PUAS - RESERVORIOS M 36.00 38.44 1,383.84 03.04 PUERTA DE INGRESO PARA CERCOS CON ALAMBRE DE PUAS UND 3.00 162.08 486.24 01 OBRAS PROVISIONALES Y PRELIMINARES 222.57 01.01 TRAZO Y REPLANTEO PRELIMINAR M2 264.96 0.84 222.57 02 MOVIMIENTO DE TIERRAS 3,013.93 02.01 EXCAV. MANUAL EN TERRENO SUELTO M3 36.86 40.05 1,476.24 02.02 ELIMINACION DE MATERIAL EXCEDENTE (D<500m)) M3 46.08 33.37 1,537.69 03 OBRAS DE CONCRETO CICLOPEO 10,390.83 03.01 CONCRETO CICLOPEO f'c=140 Kg/cm2 + 70% PM. M3 36.86 281.90 10,390.83 04 OBRAS DE CONCRETO SIMPLE 15,115.79 04.01 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTO M2 143.42 55.09 7,901.01 04.02 CONCRETO f'c=175 kg/cm2 (SIN MEZCLADORA) M3 12.52 576.26 7,214.78 05 ALBAÑILERIA 73,795.06 05.01 MURO DE LADRILLO MECANIZADO 24x12x9 SOGA M2 399.62 79.96 31,953.62 05.02 TARRAJEO EN INTERIORES Y EXTERIORES (MORTERO 1:5) M2 854.43 29.83 25,487.65 05.03 PINTURA ESMALTE EN MUROS EXTERIORES M2 854.43 19.14 16,353.79 06 PISOS Y PAVIMENTOS 28,488.64 06.01 APISONADO DE PISO M2 80.64 3.34 269.34 06.02 EMPEDRADO DE PISO M2 80.64 16.88 1,361.20 06.03 CONCRETO f"c=140 Kg/cm2 (SIN MEZCLADORA) M3 8.06 476.24 3,838.49 06.04 PISO DE LOSETA M2 80.64 59.93 4,832.76 06.05 VEREDA DE CONCRETO f'c=140 Kg/cm2 E=4" M2 149.76 121.44 18,186.85 07 COBERTURAS 10,952.10 07.01 COBERTURA CON CALAMINA GALVANIZADA M2 149.76 38.74 5,801.70 07.02 LISTONES Y/O CORREAS DE MADERA MOD 32.00 160.95 5,150.40 08 CARPINTERIA DE MADERA 14,127.68 08.01 CONFECCION Y COLOCACION DE PUERTAS DE MADERA UND 32.00 315.31 10,089.92 08.02 CONFECCION Y COLOCACION DE VENTANA DE MADERA CON MALLA UND 32.00 126.18 4,037.76 09 APARATOS Y ACCESORIOS SANITARIOS 9,538.88 09.01 INODORO TANQUE BAJO BLANCO PZA 32.00 298.09 9,538.88 10 INSTALACIONES SANITARIAS 15,612.80 10.01 SUMINISTRO E INSTALACION DE ACCESORIOS PARA AGUA Ø1/2" MOD 32.00 279.50 8,944.00 10.02 SUMINISTRO E INSTALACION DE ACCESORIOS PARA ELIMINACION DE AGUAS SERVIDAS MOD 32.00 208.40 6,668.80 11 INSTALACION DE BIODIGESTOR 73,599.28 11.01 TRAZO Y REPLANTEO PRELIMINAR M2 118.08 0.84 99.19 11.02 EXCAV. MANUAL EN TERRENO SUELTO M3 145.14 40.05 5,812.86 11.03 ELIMINACION DE MATERIAL EXCEDENTE (D<500m)) M3 80.63 33.37 2,690.62 11.04 REFINE Y NIVELACION DE ZANJAS (b=0.40m) ML 40.00 2.00 80.00 11.05 CAMA DE APOYO PARA TUBERIAS M3 13.44 33.37 448.49 11.06 CAJA DE REGISTRO 12" x 24" TAPA DE CONCRETO UND 32.00 120.54 3,857.28 11.07 CAJA DE REGISTRO DE LODOS UND 32.00 275.08 8,802.56 11.08 SUMINISTRO E INSTALACION DE BIODIGESTOR PREFABRICADO DE CAP. 600L UND 32.00 1,363.88 43,644.16 11.09 RELLENO CON MATERIAL PROPIO M3 80.64 16.69 1,345.88 11.10 SUMINISTRO EN INSTALCION DE TUBERIA Y ACCESORIOS GLB 32.00 213.07 6,818.24 12 PERCOLACION 12,747.96 12.01 TRAZO Y REPLANTEO PRELIMINAR M2 155.90 0.84 130.96 12.02 EXCAV. MANUAL EN TERRENO SUELTO M3 94.54 40.05 3,786.33 12.03 ELIMINACION DE MATERIAL EXCEDENTE (D<500m)) M3 116.93 33.37 3,901.95 12.04 FILTRO DE GRAVA CLASIFICADA 1 1/2" A 1//4" M3 92.16 53.48 4,928.72
  • 4. 13 MITIGACION DE IMPACTOS AMBIENTALES 41,007.40 13.01 MANEJO DE RESIDUOS SOLIDOS 15,584.41 13.01.01 RECOLECCION DE DESECHOS DE OBRA GLB 1.00 256.82 256.82 13.01.02 EXCAVACION DE HOYOS PARA RELLENO PROVISIONAL UND 9.00 82.51 742.59 13.01.03 CLAUSURA DE RELLENO PROVISIONAL UND 9.00 49.26 443.34 13.01.04 SUMINISTRO E INST. PROVISIONAL DE BAÑOS MOVILES UND 2.00 3,937.01 7,874.02 13.01.05 OPERACION Y MANT. PROVISIONAL DE BAÑOS MOVILES UND 4.00 1,566.91 6,267.64 13.02 REHABILITACION DE AREAS DEGRADAS 20,398.96 13.02.01 REHABILITACION DE AREA DE CAMPAMENTO M2 120.00 91.84 11,020.80 13.02.02 REHABILITACION DE AREA DE PREPARADO DE MATERIAL DE CONCRETO M2 90.00 91.84 8,265.60 13.02.03 ADECUACION DE VIAS DE ACCESO GLB 1.00 1,112.56 1,112.56 13.03 REFORESTACION 4,787.18 13.03.01 PLANTAS ARBOREAS UND 150.00 2.51 376.50 13.03.02 PLANTAS FRUTALES UND 100.00 2.52 252.00 13.03.03 PLANTAS ARBUSTIVAS UND 150.00 0.51 76.50 13.03.04 AGUA PARA RIEGO M3 2.00 180.29 360.58 13.03.05 TRANSPORTE DE PLANTONES VJE 2.00 900.80 1,801.60 13.03.06 PLANTACION DE ESPECIES VEGETALES UND 400.00 4.80 1,920.00 13.04 CONTROL DE CALIDAD DEL AIRE 236.85 13.04.01 LONA PARA PROTECCION DE TRANSPORTE EN VOLQUETE M 15.00 15.79 236.85 01 CAPACITACION EN EDUCACION SANITARIA 46,810.00 01.01 CAPACITACION EN EDUCACION SANITARIA GLB 1.00 46,810.00 46,810.00