Construction Update 10-13-2010
1. From: Mike McKeen To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Office: Kansas City Lee Turner – OnGoal
Date: 10.13.2010 Andy Heitmann – Turner
Dave Dudzik – Turner
Re: Wizards Stadium Project
Update – Week of
10.11.2010
Area 3 – Loading dock SOG.
Current Activities this Week:
Foundations:
Area 4 Field Level – Foundations for “infill” area
between Column Lines 39-1 are complete.
Concrete Flatwork:
Field Level - Cauldron club should pour Thursday 10/14
Bowl – Intermediate stairs should be complete this week.
Masonry:
Area 1 – Field level masonry installation is ongoing in
Field 3 – Masonry – Concrete slab-on grade
Area Level Area 3 walls on east side.
Area F, E, D and C.
prep is ongoing to column line 4.
Area 2/3 – Concourse building masonry installation
is ongoing. Masonry pilasters will begin 10/13
on the east side.
Steel Erection:
Area 4 – decking and stud install for “infill” area is
ongoing (Sequence 3-3). Truss installation is complete,
and now installing purlins.
Area 2/3 – Steel joist and metal decking installation for
concourse buildings is ongoing. Canopy decking
installation is ongoing. Canopy gutter enclosure framing
installation is ongoing. Field Level Area 3 – Masonry in Section D is
ongoing.
Roofing and Sheetmetal:
Area 1 – Permanent roofing installation at West
Building should be complete by end of wk.
Area 2/3 – Canopy gutter installation will be complete
by the end of wk.
Building the Future Area 4 – All the large trusses are set.
2. Metal Stud Framing:
Area 1 – Metal stud framing and sheetrock install
for Field, Concourse, Suite and Press Levels are ongoing.
Exterior metal stud framing and sheathing installation
is ongoing at Field, Suite, and Press Levels.
Area 2 –Metal studs at south corridor ongoing.
Metal studs at concessions will begin 10/14 – 10/15.
Glass:
Area 1 - Curtainwall framing and glass installation is
ongoing at West Building on west, south, east and north
elevations. South “wing” framing is complete. Curtainwall Area 1 – RTU’s and roofing on west building.
framing on Suite and Press Level balconies is complete.
Curtainwall framing at Field Side of Main Concourse
is also complete.
MEP Rough-in:
Area 1 -Ductwork installation on Field, Main, Suite
and Press Levels are ongoing. Plumbing rough-in is
ongoing on Field, Mezz, Main, Suite and Press Levels.
Fire Protection rough-in is ongoing at Field Level.
Electrical rough-in is ongoing on Field, Mezz, Concourse,
Suite and Press Levels. The main electrical gear is onsite,
and the RTU units will be will set this week.
Area 3 – Underground MEP rough-in is ongoing. Rough-in
at Main Concourse CMU walls is ongoing.
Area 3 – Canopy decking on east side.
Elevators:
S1 elevator is onsite and install is ongoing.
F1 elevator to arrive onsite 10/13.
Projected Activities occurring next Week:
Concrete Flatwork:
Area 3 – Mezzanine concrete will be poured from grid
33 – 40. Area 3 and 4 Field Level – Installation of on-grade
seating risers and intermediate stairs will continue.
Building the Future Area 1 – Install of playing field storm loop.
3. Masonry:
Area 1 – Field level masonry installation will continue inArea F, E, D and C.
Area 2/3 – Concourse building masonry, Field Level walls
Area 2 – South Corridor Framing
and east exterior pilasters will continue.
Structural Steel Erection:
Area 4 – Decking of “infill” area should be complete and
ready for MEP rough-in.
Area 2 – Steel joist and metal decking
installation for concourse buildings will continue.
Canopy decking and canopy gutter enclosure framing
installation will continue.
Roofing and Sheetmetal:
Prepping and field measuring for metal panels at suites.
Metal Stud Framing:
Area 1 – Metal stud framing and sheetrock install
for Field, Concourse, Suite and Press Levels will continue.
Exterior Framing and sheathing installation will continue.
Area 2 – Field Level and Concession framing will continue.
Glass:
Area 1 – Curtain Framing and Glass installation around West
Building will continue. Glass install will begin at Press Level
balcony, Suite Level balcony, and Main Concourse west side
elevation. North wing wall framing will begin next week as Area 1 – Metal stud framing in the home
well. locker room.
MEP Rough-in:
MEP rough-in at Concourse, Suite and Press Levels will
continue. Ductwork installation on Concourse, Suite, and
Press Levels will continue. Fire Sprinkler installation will
continue on the Field Level. Storm system plumbing
install will continue at all levels.
Elevators:
Install of F1 and S1 will continue.
Building the Future
4. Additional Photos:
Area 3– On-grade seating installation is
ongoing at north elevation.
Building the Future