Construction Update 3-17-2010
1. From: Brandon Valdez To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Office: Kansas City Lee Turner – OnGoal
Date: 3/17/2010 Andy Heitmann – Turner
Dave Dudzik - Turner
Re: Wizards Stadium Project
Update – Week of
3/15/2010
Current Activities this Week:
Mass Excavation:
Mass Excavation Activities in the Main Bowl continues
In Areas 1, 2 and 3. Clarkson is excavating and hauling
Sandstone and Rock to Area C.
Area 4 Mezzanine Level – Rough grading of the Slab on
Grade Seating has begun.
A shot from Mid-Field Looking South
Site Utilities:
BPU has removed the power from switchgear to
manhole.
Foundations:
Area 1 Field Level – D-Line wall have been placed to
Column Line 30.5.
Area 1 Field Level – A Line wall placement has begun
at Column Line 32.
Area 1 Field Level – A-Line footing placement has Area 2 – Shotcrete Installation on 2nd Lift
begun south of Player Field Entrance.
Area 1 Concourse Level - D-Line Wall Placement is
currently placed to Column Line 29.5.
Area 2 Concourse Level – D-Line Wall Placement
is completed to Column Line 14, along with associated
waterproofing.
Soil Nail Wall:
Area 1 – Soil Nail installation has started on the 3rd lift.
Concourse Level Area 1 – Pumping Concrete
for D-Line Walls (near Column Line 24)
Building the Future
2. Area 2 – Working platform for soil nail installation is
currently being removed so soil nail drilling can begin.
Projected Activities occurring next Week:
Mass Excavation:
Area 1 and 2 Field Level - As the soil nail wall progresses,
the working platform (sandstone bench) will continue Area 3 – Sandstone Excavation behind A-
to be removed. Line
Site Utilities:
Installation of the new electrical ductback will begin.
Boring under the Field Level D-Line Wall
for the Sanitary Lateral Line D will begin.
Foundations:
Area 1 Concourse Level – Waterproofing of D-Line
wall will begin.
Area 1 Field Level – A-Line wall placement will continue. Area 1 – E-Line Grade Beam Reinforcing off
of D-Line Wall
Soil Nail Wall:
Area 1 – Shotcrete installation on 3rd lift will begin.
Area 2 – Drilling for the soil nails on the 2nd lift will begin.
Area 1 – Field Level D-Line Wall with forms
stripped
Building the Future
3. Additional Photos:
Area 1 – Pump truck setting up for A-Line Area 1 Field Level – Setting wall dowels for
Footing Pour A-Line Footing
Area 2 – Concourse Level D-Line Walls Area 1 – Rock Excavation, Footing
getting backfilled Excavation and Hauling Operations
Area 2 – Concourse Level Waterproofing Area 4 – View of the Future Cauldron Club
installation on D-Line Walls Area