NG BB 45 Quick Change Over
1. UNCLASSIFIED / FOUO
National Guard
Black Belt Training
Module 45
Quick Changeover
UNCLASSIFIED / FOUO
2. UNCLASSIFIED / FOUO
CPI Roadmap – Improve
8-STEP PROCESS
6. See
1.Validate 2. Identify 3. Set 4. Determine 5. Develop 7. Confirm 8. Standardize
Counter-
the Performance Improvement Root Counter- Results Successful
Measures
Problem Gaps Targets Cause Measures & Process Processes
Through
Define Measure Analyze Improve Control
TOOLS
ACTIVITIES
•Brainstorming
• Develop Potential Solutions
•Replenishment Pull/Kanban
• Develop Evaluation Criteria
•Stocking Strategy
• Select Best Solutions
•Process Flow Improvement
• Develop Future State Process Map(s)
•Process Balancing
• Develop Pilot Plan
•Standard Work
• Pilot Solution
•Quick Change Over
• Develop Full Scale Action/
•Design of Experiments (DOE)
Implementation Plan
•Solution Selection Matrix
• Complete Improve Gate
•‘To-Be’ Process Mapping
•Poka-Yoke
•6S Visual Mgt
•RIE
Note: Activities and tools vary by project. Lists provided here are not necessarily all-inclusive. UNCLASSIFIED / FOUO 2
3. UNCLASSIFIED / FOUO
Changeover Definition
The amount of time taken to change
equipment from the Last Good Part of a
process to the First Good Part of the
next process
Clock Time, not Labor Time!
UNCLASSIFIED / FOUO 3
4. UNCLASSIFIED / FOUO
Traditional vs. CPI Thinking
Traditional Thinking
Changeovers cause downtime
Changeovers cause poor utilization, defects & scrap
Big Batch Size desirable - “The Bigger, the Better”
(less changeovers)
CPI Thinking
Quick changeovers decrease downtime
Well designed changeovers decrease waste
Quick changeovers (with small batches) Increases
Flexibility
UNCLASSIFIED / FOUO 4
5. UNCLASSIFIED / FOUO
Why Quick Changeover?
Shorter Changeover Times
More Frequent Changeovers
Smaller Batch Sizes
Shorter Lead Times
Increased Combat Capability!
UNCLASSIFIED / FOUO 5
6. UNCLASSIFIED / FOUO
Internal vs. External
The first task is to recognize that there
are two essentially different components
of any changeover, Internal Activities
and External Activities.
UNCLASSIFIED / FOUO 6
7. UNCLASSIFIED / FOUO
Changeover Activities
Internal Activities
An activity that must be performed while the machine
or process is turned off (no product)
Example – Refuel plane on the ground
External Activities
An activity that can be performed while the machine or
process is turned on (producing product)
Example – Refuel plane in the air
UNCLASSIFIED / FOUO 7
8. UNCLASSIFIED / FOUO
Improvement Steps
1. Identify changeover activities and document the
process (time each step).
2. Separate Internal activity from External activity
External Internal External
UNCLASSIFIED / FOUO 8
9. UNCLASSIFIED / FOUO
Internal vs. External Quiz
Possible CT Scan Changeover Steps: Which are
1. Machine is turned off as scan ends Internal &
2. IV is removed from the patient
3. Patient is moved off of scan bed
Which should
4. Patient is removed from CT scan room be External?
5. New Patient is identified off of CT scan schedule
6. New Patient is brought into CT scan room
7. Patient identification is verified
8. CT Scan procedure is explained to patient
9. Type of Scan is verified from Physician Orders
10. IV is started on new Patient
11. Patient is placed on CT scan bed
12. CT Scan machine is turned on and scan begins
Adapted from “A Lean Guide to
Transforming Healthcare”, Zidel, 2006
UNCLASSIFIED / FOUO 9
10. UNCLASSIFIED / FOUO
Internal vs. External Quiz
Possible CT Scan Changeover Steps: Internal
1. Machine is turned off as scan ends External
2. IV is removed from the patient
3. Patient is moved off of scan bed
4. Patient is removed from CT scan room
5. New Patient is identified off of CT scan schedule
6. New Patient is brought into CT scan room
7. Patient identification is verified
8. CT Scan procedure is explained to patient
9. Type of Scan is verified from Physician Orders
10. IV is started on new Patient
11. Patient is placed on CT scan bed
12. CT Scan machine is turned on and scan begins
Adapted from “A Lean Guide to
Transforming Healthcare”, Zidel, 2006
UNCLASSIFIED / FOUO 10
11. UNCLASSIFIED / FOUO
Improvement Steps
1. Identify activities and document the process.
2. Separate Internal from External activity
3. Convert Internal to External
UNCLASSIFIED / FOUO 11
12. UNCLASSIFIED / FOUO
Converting Internal to External
Prepare operating conditions prior to changeover
Preheat molds or dies
Prepare Patient or Care-givers
Prepare service materials or providers
Pre-adjust parts
Use intermediary sets
Preset tools
Position dies
Standardize necessary functions
Change the fewest parts possible
Minimize or eliminate adjustments
UNCLASSIFIED / FOUO 12
13. UNCLASSIFIED / FOUO
Improvement Steps
1. Identify activities and document the process.
2. Separate Internal from External activity
3. Convert Internal to External
4. Reduce all remaining activities.
UNCLASSIFIED / FOUO 13
14. UNCLASSIFIED / FOUO
Reduce All Remaining Activities
Perform Parallel Operations
Improve Clamping Mechanisms
One turn clamps
One motion methods
Eliminate all adjustments
Numerical Settings vs. “Feel”
Automate activities where appropriate
UNCLASSIFIED / FOUO 14
15. UNCLASSIFIED / FOUO
Pit Stop Photo
Team with Pre-assigned Tasks Placement Clearly
Defined
Quick Connect & Tools Properly Positioned Prior
Disconnect Devices to Arrival
UNCLASSIFIED / FOUO 15
16. UNCLASSIFIED / FOUO
Takeaways
Remember Safety at all times!!!
Change internal to external then reduce all
activities
Standards are standards, they are not flexible
Standardize all changeover operations
UNCLASSIFIED / FOUO 16
17. UNCLASSIFIED / FOUO
What other comments or questions
do you have?
UNCLASSIFIED / FOUO 17