Process Groups and Knowledge Areas

                                  Loren Karl Schwappach
                               Colorado Technical University
                                      30 August 2011


                           Process Groups and Knowledge Areas
Introduction
                Hello, my name is Loren Karl Schwappach. I am the new project manager for
the 2011 Billing System Upgrade Project (BSUP). I have been asked to create this briefing to
enlighten the customer service and billing departments about project management process
groups and the knowledge areas of project management. I hope this briefing is informative
and helps to open eyes to the upcoming challenges ahead. It is my goal to see this project to
success and as base line users you will play a large role in determining the quality and
performance of the final project.




                                                                                                1
Overview
                  Today I will talk to you about the five project management process groups to
include: initiating, planning, executing, monitor and controlling and closing. I will also
introduce the nine knowledge areas of project management to include: integration
management, scope management, time management, cost management, quality management,
human Resources management, communications management, risk management, and
procurement management. I will end the briefing with a project management case study. If
you have any questions as I proceed during this briefing please feel free to speak them during
the briefing.




                                                                                                 2
Project Management Process Groups
                 Before the customer service and billing department’s legacy billing system
web-based upgrade project can be initiated, it is imperative for the project manager, project
team, and project stakeholders to recognize what is to pass once the project is started and the
undertakings they will be required to participate in. This briefing was designed to provide an
understanding of project management process groups and the nine knowledge areas of project
management so that IRTC employees can observe how to properly work with and structure the
project to ensure this projects success. Although, there is no way to completely anticipate and
prevent all problems, having a clear understanding of the processes will help increase the
effectiveness in managing this large upgrade project.
Group #1: Initiating
                 The initial phase of project management involves obtaining the necessary
permissions and approvals required to begin the project. Usually, a document outlining the
necessity for the project is created in order to reason to the project’s sponsor how the needs of
the organization will be met, and approximately how much the project will cost and how long
the project is expected to take (Babou, 2008).
                 The initiating process group contains the processes designed to describe the
project, subproject, or phase of an existing project and obtain authorization to begin each
project phase. The main processes of the initiating group as defined by the PMBOK are to
develop the project charter and identify stakeholders (Global Standard, 2008).




                                                                                                    3
Group #2: Planning
                  This project group is about planning out the project and defining project goals.
Large portions of the project need to be stripped down and deadlines will be scheduled.
Stakeholders will play a large role in authorizing and planning out resources (Babou, 2008).
This is also the phase in which the project team is put together and begins to identify tasks and
roles. Project costs are estimated to provide the groundwork for a project budget. The IRTC
project team will utilize MS Project to aid in the scheduling of costs and resources and will
utilize your departments in streamlining these plans.
                  The planning process group contains processes needed to establish the
projects scope, smooth and refine objectives and identify courses of action necessary to
complete project objectives. This group contains the following processes: develop project
management plan, collect requirements, define scope, create WBS, define activities, sequence
activities, estimate activity resources, estimate activity durations, develop schedule, estimate
costs, determine budget, plan quality, develop human resource plan, plan communications,
plan risk management, identify risks, perform quantitative risk analysis, plan risk responses,
and plan procurements (Global Standard, 2008).
Group #3: Executing
                  Now that the project team has everything in place and goals well-defined, it is
time to begin developing the end product results. Contracts are administered as needed, and
the project’s team members make periodic reports on their status. Everything that goes into
making the plan a reality takes place during the project’s execution group (Babou, 2008).
                  This process group contains the processes used to perform and complete work
as outlined by the project management plan and needed to satisfy project specifications. This
group contains the following processes: direct and manage project execution, perform quality
assurance, acquire project team, develop project team, manage project team, distribute
information, manage stakeholder expectations, and conduct procurements (Global Standard,
2008).
                                                                                                     4
Group #4: Monitoring and controlling
                 After the execution stage is under way the project team should begin
monitoring to ensure everything goes according to the project plan. As products and stages are
completed, each is submitted to the project sponsor (IRTC CIO) for approval. If adjustments
are required they are made during this stage. The project team and stakeholders should keep
an ongoing list of valuable lessons learned during the project to help in evaluating the projects
performance (Babou, 2008).
                 This process group contains the processes utilized in tracking, reviewing, and
regulating the performance and progress of the project, identifying areas for change, and
initiating changes. The group contains the following processes: monitor and control project
work, perform integrated change control, verify scope, control scope, control schedule, control
costs, perform quality control, report performance, monitor and control risks, and administer
procurements (Global Standard, 2008).
Group #5: Closing
                 The last project management group marks the end of the project. The project
manager arranges for the final acceptance of the product, and the sponsor accepts. Everything
is carefully documented in writing, and records of contracts, transactions, and other
agreements are completed. Project debriefing and plans for necessary follow up are made at
this time (Babou, 2008).
                 The closing process group contains the processes for finalizing activities
across all process groups. This group contains the following processes: close project or phase,
and close procurements (Global Standard, 2008).




                                                                                                    5
Project Management Knowledge Areas
                  Managing projects involves applying knowledge, skills, tools, and techniques
to project activities in order to meet project objectives. IRTC’s project team will accomplish
this by performing processes at various stages of the project, as I discussed in the project phase
slides. Each aspect of a project is managed by using the corresponding knowledge area.
                  Each process belongs to one of the nine knowledge areas: scope management,
time management, cost management, human resource management, procurement management,
risk management, quality management, integration management, and communication
management (Kerzner, 2003).
Project Integration Management
                  The project is initiated, planned, and executed in pieces, and all those need to
fit together. That is where project integration management is utilized. Project integration
management includes developing the project charter (the document that authorizes the project
and identifies initial project requirements), developing the project management plan (defines
how the project is executed, monitored, and controlled), directing and managing project
execution (creating deliverables, training staff and team members, obtaining resources,
performing risk management, managing sellers and suppliers, issuing change requests),
monitoring and controlling project work (tracking, reviewing, and regulating the progress to
meet performance objectives), performing integrated change control (reviewing, approving,
and managing project changes), and closing the project or a phase of a project (review and
finalizing all activities) (Global Standard, 2008).




                                                                                                     6
Project Scope Management
                  Project scope management includes collecting requirements (defining and
documenting stakeholder’s needs, customer service will play a large part here), defining the
scope (develop detailed description of the project), creating a Work Breakdown Structure
(WBS) (subdivides deliverables into smaller manageable components), verifying the scope
(formalizing acceptance of deliverables), and controlling the scope (monitoring the status of
the project and scope and managing changes). Initially our project team will collect the
requirements for the project based on the stakeholders’ needs, which will determine the project
scope. Next our project team will develop the description for the project and its products,
which is the basis for the project scope. Customer service and billing departments will play a
large role in identifying the features need for this project and thus will play a large part in
defining the projects scope and deliverables. Our project team will then create the project’s
work breakdown structure (WBS). Next our project team will verify the scope and plan how
the completed deliverables of the project will be accepted. Finally in order to control the
scope, only the approved changes to the scope should be implemented. Obviously, these
components are performed by using the corresponding processes (Global Standard, 2008).




                                                                                                  7
Project Time Management
                  Project time management is accomplished by defining activities, sequencing
activities, estimating activity resources, estimating activity durations, developing a schedule,
and controlling the schedule. Define activities includes identifying all the work activities that
need to be scheduled to produce the project deliverables. Sequencing activities involves
identifying the dependencies among the activities that need to be scheduled so that they can be
scheduled in the correct order. Estimating activity resources includes estimate the types of
resources needed and the quantity for each type for each schedule activity. Estimating activity
durations involves estimating the time needed to complete each schedule activity. Developing
the schedule includes analyzing the data created in the previous steps to develop the schedule.
Control of the schedule involves controlling the changes to the project schedule (Global
Standard, 2008).
Project Cost Management
                  Cost management includes estimating the cost, determining the project
budget, and controlling the cost. Estimate cost involves developing the cost of the resources
needed to complete the project, which includes schedule activities and outsourced/procured
work. Determining the budget requires aggregating the costs of individual activities to
establish a cost baseline that includes timing. Control the cost involves monitoring and
controlling the cost variance in the project execution (Global Standard, 2008).




                                                                                                    8
Project Quality Management
                 Project quality management includes planning the quality, performing quality
assurance, and performing quality control. Planning quality involves determining the quality
requirements and standards that are relevant to the project at hand and how to apply them.
Performing quality assurance involves ensuring the planned quality requirements and
standards are applied. Performing quality control involves monitoring the quality activities
and recording the results of these activities in order to assess performance and make necessary
recommendations for corrective actions and changes (Global Standard, 2008).
Project Human Resource Management
                 Project human resource management includes developing a human resource
plan, acquiring the project team, developing the project team, and managing the project team.
Developing a human resources plan involves identifying project roles, responsibilities for each
role, and reporting relationships among the roles. The staff management plan describes when
and how the resource requirements will be met. Acquiring the project team involves obtaining
the human resources needed to work on the project. Developing the project team involves
improving the competencies of the team members and the interaction among members to
optimize the team performance. Managing the project team involves tracking the performance
of team members, provide team members with feedback, and resolve issues and conflicts
(Global Standard, 2008).




                                                                                                  9
Project Communication Management
                 Communication management includes identifying project stakeholders,
planning communication, distributing information, managing stake holder expectations, and
reporting performance. Stakeholder identification involves identifying all individuals, groups,
and organizations that will potentially be impacted by the project and find relevant information
about them (this includes customer service and billing department staff). Planning
communications involves determining the information and communication needs of the project
at hand and the communication approach to be used. Distributing information involves
making the needed information available to the project stakeholders in a timely fashion.
Managing stakeholder expectations involves communicating and working with the
stakeholders in order to understand and meet their needs, address the issues, and manage the
expectations within the project scope and the project management plan. This maybe the most
essential process and will require a lot of brain storming between the project team and
customer service and billing departments. Finally, reporting performance involves collecting
and distributing performance information to the stakeholders to stay on the same page (Global
Standard, 2008).




                                                                                                   10
Project Risk Management
                  Project risk management includes risk management planning, identification of
risks, performing qualitative risk analysis, planning risk responses, and monitor and control of
risks. Planning risk management involves deciding how to determine and execute the risk
management tasks. Identifying risks included identifying the potential risks relevant to the
project at hand and determine the characteristics of those risks. Performing qualitative risk
analysis involves assessing the probability of occurrence and the impact for each risk in order
to prioritize risks for an action or for further analysis. Performing quantitative risk analysis
involves estimating the effects of identified risks on project objectives. Planning risk
responses involves developing action options for risks to maximize opportunities for and
minimize threats to satisfying project objectives. Monitor and control of risks involves
tracking identified risks, implement risk response plans, identify new risks, and evaluate the
effectiveness of risk management processes throughout the project (Global Standard, 2008).
Project Procurement Management
                  Procurement management includes planning procurements, conducting
procurements, administering procurements, and closing procurements. To plan procurements
the project team needs to identify purchasing needs (what hardware / software is needed,
materials, personnel outsourcing, etc.), specify the procurement approach, and identify
potential venders. Conducting procurements involves obtaining vender responses, selecting
venders, and issuing contracts. Administering procurements involves managing procurement
relationships, monitoring the procurement performance, and monitoring and controlling
changes in procurement. Closing procurements involves completing procurements with proper
closure, such as accepting products and closing contracts (Global Standard, 2008).




                                                                                                   11
Case Study
                [WHY] Project management training offers advantages and clear
benefits to include reduced delivery costs, increased project efficiency, focus
advantages, prediction increases, and problem identification (Egeland, 2010). As an
example a case study of [WHO] a major investment company was completed
[WHERE] by Rosenhead (2010) of Project Agency a project management online
training agency [WHEN] in 2006 (Rosenhead, 2010). [WHAT] The investment
company studied was facing a problem where projects were not being delivered
effectively (on time or on budget). Very few staff had been involved with project
management courses and they had no overall project management approach. [HOW]
The company developed a non-standard project methodology and asked Project
Agency to benchmark their practices, and the preliminary results were poor. Project
Agency provided essential project management training to the company and projects
began being completed in record time, without breaking budget constraints, and
increased quality. The investment companies’ staff was more aware of the way to
approach change management thorough the use of and application of project
management skills. IRTC customer service employees will play a tremendous role on
the success of this project which is why an understanding of the standard processes
involved is so essential.




                                                                                      12
Summary
                  Today I talked to you about the five project management process groups to
include: initiating, planning, executing, monitor and controlling and closing. I also introduced
the nine knowledge areas of project management to include: integration management, scope
management, time management, cost management, quality management, human Resources
management, communications management, risk management, and procurement management.
I concluded the briefing with a project management case study and explained some of the
benefits of project management. I would now like to open the floor to any additional
questions. Thank you.




                                                                                                   13
References

Babou, S.(2008). Project Management Processes & Process Groups. Leadership Champions,
       Retrieved August 30, 2011, from
       http://leadershipchamps.wordpress.com/2008/03/03/project-management-process-
       groups/

Egeland, B. (2010). “Strategic Organizational Benefits of Project Management”. Project
       Management Tips, Retrieved August 30, 2011, from http://pmtips.net/strategic-
       organizational-benefits-project-management/

Global Standard. (2008). A Guide to the Project Management Body of Knowledge (4th ed.).
        Newtown Square, PA: Project Management Institute, Inc.

Kerzner, H. (2003). Project management: A systems approach to planning, scheduling, and
        controlling (8th ed.). Hoboken, New Jersey: John Wiley & Sons, Inc.

Rosenhead, R. (2010). Case Studies. Retrieved August 30, 2011, from Project Agency
       Website: http://pmtips.net/strategic-organizational-benefits-project-management/




                                                                                          14
[Illustration of PMBOK Processes]. (n.d.). Retrieved August 30, 2011, from:
          http://www.projectmanagement-ema.com/imageprocessor.php?src=images/pmbok-
          processes.jpg&w=200

[Illustration of PMBOK Processes]. (n.d.). Retrieved August 30, 2011, from:
          http://www.projectmanagement-ema.com/imageprocessor.php?src=images/pmbok-
          processes.jpg&w=200

[Illustration of PMBOK Processes]. (n.d.). Retrieved August 30, 2011, from:
          http://www.projectmanagement-ema.com/imageprocessor.php?src=images/pmbok-
          processes.jpg&w=200

[Illustration of Man Juggling PM Constraints]. (n.d.). Retrieved August 30, 2011, from:
          http://www.theposselist.com/wp-content/uploads/2009/09/project-management-
          1mod-a.jpg

[Illustration of Human Resource Networks]. (n.d.). Retrieved August 30, 2011, from:
          http://www.whizlabs.com/blog/wp-content/uploads/2011/06/PMP1.jpg




                                                                                          15
[Illustration of Men Fitting Together Gears]. (n.d.). Retrieved August 30, 2011, from:
          http://heartwooddigital.com/images/integration_m.jpg

[Illustration of a Scope]. (n.d.). Retrieved August 30, 2011, from:
          http://amtruni.com/Amtruni_files/Scope%20Management.jpg

[Illustration of a Stakeholders]. (n.d.). Retrieved August 30, 2011, from:
          http://pmtips.net/wp-content/uploads/2011/01/stakeholders_cartoon1.jpg

[Illustration of a Project Management Puzzle]. (n.d.). Retrieved August 30, 2011, from:
          http://www.google.com/imgres?q=project+management&hl=en&safe=active&biw=1
          068&bih=707&tbm=isch&tbnid=17lRVVuJd2SrAM:&imgrefurl=http://pmtips.net/act
          ual-
          project/&docid=ltHjOBhfLTlBjM&w=1331&h=1030&ei=ftdfTtv5K8Le0QHJ2bUb&zoo
          m=1

[Illustration of a Man Holding PM World]. (n.d.). Retrieved August 30, 2011, from:
          http://pmtips.net/wp-content/uploads/2010/05/ProjectManager.jpg




                                                                                          16

Más contenido relacionado

La actualidad más candente

Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as OpportunityGlen Alleman
 
PMP - Risk Management plan & template
PMP - Risk Management plan & templatePMP - Risk Management plan & template
PMP - Risk Management plan & templateAllie Gentry
 
Theory of Project Management
Theory of Project ManagementTheory of Project Management
Theory of Project ManagementGlen Alleman
 
What Does Done Look Like?
What Does Done Look Like?What Does Done Look Like?
What Does Done Look Like?Glen Alleman
 
Capabilities based planning essay
Capabilities based planning essayCapabilities based planning essay
Capabilities based planning essayGlen Alleman
 
Srae2014 - Construction Projects Risks from the Perspective of Project Manage...
Srae2014 - Construction Projects Risks from the Perspective of Project Manage...Srae2014 - Construction Projects Risks from the Perspective of Project Manage...
Srae2014 - Construction Projects Risks from the Perspective of Project Manage...Safak EBESEK
 
Step by step guide on project risk management
Step by step guide on project risk managementStep by step guide on project risk management
Step by step guide on project risk managementPMC Mentor
 
PMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep PresentationPMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep Presentationscottdreynolds
 
5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them TooSHAZEBALIKHAN1
 
Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...Glen Alleman
 

La actualidad más candente (20)

043 Integrating Risk Management
043 Integrating Risk Management043 Integrating Risk Management
043 Integrating Risk Management
 
Pmp risk management
Pmp risk managementPmp risk management
Pmp risk management
 
Software Engineering
Software EngineeringSoftware Engineering
Software Engineering
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as Opportunity
 
PMP - Risk Management plan & template
PMP - Risk Management plan & templatePMP - Risk Management plan & template
PMP - Risk Management plan & template
 
Theory of Project Management
Theory of Project ManagementTheory of Project Management
Theory of Project Management
 
What is risk?
What is risk?What is risk?
What is risk?
 
PMP_Project Risk Management
PMP_Project Risk ManagementPMP_Project Risk Management
PMP_Project Risk Management
 
What Does Done Look Like?
What Does Done Look Like?What Does Done Look Like?
What Does Done Look Like?
 
Project Risk management
Project Risk managementProject Risk management
Project Risk management
 
11 project risk management
11 project risk management11 project risk management
11 project risk management
 
Capabilities based planning essay
Capabilities based planning essayCapabilities based planning essay
Capabilities based planning essay
 
Handling risk
Handling riskHandling risk
Handling risk
 
Srae2014 - Construction Projects Risks from the Perspective of Project Manage...
Srae2014 - Construction Projects Risks from the Perspective of Project Manage...Srae2014 - Construction Projects Risks from the Perspective of Project Manage...
Srae2014 - Construction Projects Risks from the Perspective of Project Manage...
 
Step by step guide on project risk management
Step by step guide on project risk managementStep by step guide on project risk management
Step by step guide on project risk management
 
1_PMI-RMP_Project Risk Management Plan
1_PMI-RMP_Project Risk Management Plan1_PMI-RMP_Project Risk Management Plan
1_PMI-RMP_Project Risk Management Plan
 
GAFM Academy HOW TO START A PROJECT
GAFM Academy HOW TO START A PROJECTGAFM Academy HOW TO START A PROJECT
GAFM Academy HOW TO START A PROJECT
 
PMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep PresentationPMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep Presentation
 
5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too
 
Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...
 

Similar a Pm610 1103 b-02-schwappach-loren-p1-ip1

Pm600 1103 a-02-schwappach-loren-p1-t3
Pm600 1103 a-02-schwappach-loren-p1-t3Pm600 1103 a-02-schwappach-loren-p1-t3
Pm600 1103 a-02-schwappach-loren-p1-t3Loren Schwappach
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time ManagementSabrinaScott22
 
PMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OnePMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OneHossam Maghrabi
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Amr Miqdadi
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life CycleReema
 
Project management.docx
Project management.docxProject management.docx
Project management.docxHumaRazi1
 
Project management
Project managementProject management
Project managementArnab Ghosh
 
PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxSabrinaScott22
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docxShiraPrater50
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...write31
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...write4
 
PMBOK(Project Management Body of Knowledge)
PMBOK(Project Management Body of Knowledge)PMBOK(Project Management Body of Knowledge)
PMBOK(Project Management Body of Knowledge)Mohammad Mohammadi
 
Project management professional
Project management professionalProject management professional
Project management professionalReema
 
Project management slide show
Project management slide showProject management slide show
Project management slide showTanvir Anwar
 

Similar a Pm610 1103 b-02-schwappach-loren-p1-ip1 (20)

Pm600 1103 a-02-schwappach-loren-p1-t3
Pm600 1103 a-02-schwappach-loren-p1-t3Pm600 1103 a-02-schwappach-loren-p1-t3
Pm600 1103 a-02-schwappach-loren-p1-t3
 
Entra lecture6 PM1.pdf
Entra lecture6 PM1.pdfEntra lecture6 PM1.pdf
Entra lecture6 PM1.pdf
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time Management
 
PMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OnePMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part One
 
2) PMT & PIM.pptx
2) PMT & PIM.pptx2) PMT & PIM.pptx
2) PMT & PIM.pptx
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life Cycle
 
Project management.docx
Project management.docxProject management.docx
Project management.docx
 
Project management
Project managementProject management
Project management
 
PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptx
 
Pm training 1 18
Pm training 1 18Pm training 1 18
Pm training 1 18
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...
 
Day 1 framework
Day 1 frameworkDay 1 framework
Day 1 framework
 
PMBOK(Project Management Body of Knowledge)
PMBOK(Project Management Body of Knowledge)PMBOK(Project Management Body of Knowledge)
PMBOK(Project Management Body of Knowledge)
 
Project management professional
Project management professionalProject management professional
Project management professional
 
Project management
Project managementProject management
Project management
 
Project management slide show
Project management slide showProject management slide show
Project management slide show
 
Project Management
Project ManagementProject Management
Project Management
 

Más de Loren Schwappach

EE312 Embedded Microcontrollers Lab
EE312 Embedded Microcontrollers LabEE312 Embedded Microcontrollers Lab
EE312 Embedded Microcontrollers LabLoren Schwappach
 
Ee325 cmos design lab 7 report - loren k schwappach
Ee325 cmos design   lab 7 report - loren k schwappachEe325 cmos design   lab 7 report - loren k schwappach
Ee325 cmos design lab 7 report - loren k schwappachLoren Schwappach
 
Ee325 cmos design lab 6 report - loren k schwappach
Ee325 cmos design   lab 6 report - loren k schwappachEe325 cmos design   lab 6 report - loren k schwappach
Ee325 cmos design lab 6 report - loren k schwappachLoren Schwappach
 
Ee325 cmos design lab 5 report - loren k schwappach
Ee325 cmos design   lab 5 report - loren k schwappachEe325 cmos design   lab 5 report - loren k schwappach
Ee325 cmos design lab 5 report - loren k schwappachLoren Schwappach
 
Ee325 cmos design lab 4 report - loren k schwappach
Ee325 cmos design   lab 4 report - loren k schwappachEe325 cmos design   lab 4 report - loren k schwappach
Ee325 cmos design lab 4 report - loren k schwappachLoren Schwappach
 
Ee325 cmos design lab 3 report - loren k schwappach
Ee325 cmos design   lab 3 report - loren k schwappachEe325 cmos design   lab 3 report - loren k schwappach
Ee325 cmos design lab 3 report - loren k schwappachLoren Schwappach
 
Loren k. schwappach ee331 - lab 4
Loren k. schwappach   ee331 - lab 4Loren k. schwappach   ee331 - lab 4
Loren k. schwappach ee331 - lab 4Loren Schwappach
 
Loren k. schwappach ee331 - lab 3
Loren k. schwappach   ee331 - lab 3Loren k. schwappach   ee331 - lab 3
Loren k. schwappach ee331 - lab 3Loren Schwappach
 
Ee343 signals and systems - lab 2 - loren schwappach
Ee343   signals and systems - lab 2 - loren schwappachEe343   signals and systems - lab 2 - loren schwappach
Ee343 signals and systems - lab 2 - loren schwappachLoren Schwappach
 
Ee343 signals and systems - lab 1 - loren schwappach
Ee343   signals and systems - lab 1 - loren schwappachEe343   signals and systems - lab 1 - loren schwappach
Ee343 signals and systems - lab 1 - loren schwappachLoren Schwappach
 
Ee 352 lab 1 (tutorial) - schwappach - 15 oct 09
Ee 352   lab 1 (tutorial) - schwappach - 15 oct 09Ee 352   lab 1 (tutorial) - schwappach - 15 oct 09
Ee 352 lab 1 (tutorial) - schwappach - 15 oct 09Loren Schwappach
 
EE375 Electronics 1: lab 3
EE375   Electronics 1: lab 3EE375   Electronics 1: lab 3
EE375 Electronics 1: lab 3Loren Schwappach
 
EE375 Electronics 1: lab 1
EE375   Electronics 1: lab 1EE375   Electronics 1: lab 1
EE375 Electronics 1: lab 1Loren Schwappach
 
Ee395 lab 2 - loren - victor - taylor
Ee395   lab 2 - loren - victor - taylorEe395   lab 2 - loren - victor - taylor
Ee395 lab 2 - loren - victor - taylorLoren Schwappach
 
Ee395 lab 1 - bjt - loren - victor - taylor
Ee395   lab 1 - bjt - loren - victor - taylorEe395   lab 1 - bjt - loren - victor - taylor
Ee395 lab 1 - bjt - loren - victor - taylorLoren Schwappach
 
5 ee415 - adv electronics - presentation - schwappach
5   ee415 - adv electronics - presentation - schwappach5   ee415 - adv electronics - presentation - schwappach
5 ee415 - adv electronics - presentation - schwappachLoren Schwappach
 
4 ee414 - adv electroncs - lab 3 - loren schwappach
4   ee414 - adv electroncs - lab 3 - loren schwappach4   ee414 - adv electroncs - lab 3 - loren schwappach
4 ee414 - adv electroncs - lab 3 - loren schwappachLoren Schwappach
 
3 ee414 - adv electroncs - lab 2 - loren schwappach
3   ee414 - adv electroncs - lab 2 - loren schwappach3   ee414 - adv electroncs - lab 2 - loren schwappach
3 ee414 - adv electroncs - lab 2 - loren schwappachLoren Schwappach
 
2 ee414 - adv electroncs - lab 1 - loren schwappach
2   ee414 - adv electroncs - lab 1 - loren schwappach2   ee414 - adv electroncs - lab 1 - loren schwappach
2 ee414 - adv electroncs - lab 1 - loren schwappachLoren Schwappach
 

Más de Loren Schwappach (20)

Ubuntu OS Presentation
Ubuntu OS PresentationUbuntu OS Presentation
Ubuntu OS Presentation
 
EE312 Embedded Microcontrollers Lab
EE312 Embedded Microcontrollers LabEE312 Embedded Microcontrollers Lab
EE312 Embedded Microcontrollers Lab
 
Ee325 cmos design lab 7 report - loren k schwappach
Ee325 cmos design   lab 7 report - loren k schwappachEe325 cmos design   lab 7 report - loren k schwappach
Ee325 cmos design lab 7 report - loren k schwappach
 
Ee325 cmos design lab 6 report - loren k schwappach
Ee325 cmos design   lab 6 report - loren k schwappachEe325 cmos design   lab 6 report - loren k schwappach
Ee325 cmos design lab 6 report - loren k schwappach
 
Ee325 cmos design lab 5 report - loren k schwappach
Ee325 cmos design   lab 5 report - loren k schwappachEe325 cmos design   lab 5 report - loren k schwappach
Ee325 cmos design lab 5 report - loren k schwappach
 
Ee325 cmos design lab 4 report - loren k schwappach
Ee325 cmos design   lab 4 report - loren k schwappachEe325 cmos design   lab 4 report - loren k schwappach
Ee325 cmos design lab 4 report - loren k schwappach
 
Ee325 cmos design lab 3 report - loren k schwappach
Ee325 cmos design   lab 3 report - loren k schwappachEe325 cmos design   lab 3 report - loren k schwappach
Ee325 cmos design lab 3 report - loren k schwappach
 
Loren k. schwappach ee331 - lab 4
Loren k. schwappach   ee331 - lab 4Loren k. schwappach   ee331 - lab 4
Loren k. schwappach ee331 - lab 4
 
Loren k. schwappach ee331 - lab 3
Loren k. schwappach   ee331 - lab 3Loren k. schwappach   ee331 - lab 3
Loren k. schwappach ee331 - lab 3
 
Ee343 signals and systems - lab 2 - loren schwappach
Ee343   signals and systems - lab 2 - loren schwappachEe343   signals and systems - lab 2 - loren schwappach
Ee343 signals and systems - lab 2 - loren schwappach
 
Ee343 signals and systems - lab 1 - loren schwappach
Ee343   signals and systems - lab 1 - loren schwappachEe343   signals and systems - lab 1 - loren schwappach
Ee343 signals and systems - lab 1 - loren schwappach
 
Ee 352 lab 1 (tutorial) - schwappach - 15 oct 09
Ee 352   lab 1 (tutorial) - schwappach - 15 oct 09Ee 352   lab 1 (tutorial) - schwappach - 15 oct 09
Ee 352 lab 1 (tutorial) - schwappach - 15 oct 09
 
EE375 Electronics 1: lab 3
EE375   Electronics 1: lab 3EE375   Electronics 1: lab 3
EE375 Electronics 1: lab 3
 
EE375 Electronics 1: lab 1
EE375   Electronics 1: lab 1EE375   Electronics 1: lab 1
EE375 Electronics 1: lab 1
 
Ee395 lab 2 - loren - victor - taylor
Ee395   lab 2 - loren - victor - taylorEe395   lab 2 - loren - victor - taylor
Ee395 lab 2 - loren - victor - taylor
 
Ee395 lab 1 - bjt - loren - victor - taylor
Ee395   lab 1 - bjt - loren - victor - taylorEe395   lab 1 - bjt - loren - victor - taylor
Ee395 lab 1 - bjt - loren - victor - taylor
 
5 ee415 - adv electronics - presentation - schwappach
5   ee415 - adv electronics - presentation - schwappach5   ee415 - adv electronics - presentation - schwappach
5 ee415 - adv electronics - presentation - schwappach
 
4 ee414 - adv electroncs - lab 3 - loren schwappach
4   ee414 - adv electroncs - lab 3 - loren schwappach4   ee414 - adv electroncs - lab 3 - loren schwappach
4 ee414 - adv electroncs - lab 3 - loren schwappach
 
3 ee414 - adv electroncs - lab 2 - loren schwappach
3   ee414 - adv electroncs - lab 2 - loren schwappach3   ee414 - adv electroncs - lab 2 - loren schwappach
3 ee414 - adv electroncs - lab 2 - loren schwappach
 
2 ee414 - adv electroncs - lab 1 - loren schwappach
2   ee414 - adv electroncs - lab 1 - loren schwappach2   ee414 - adv electroncs - lab 1 - loren schwappach
2 ee414 - adv electroncs - lab 1 - loren schwappach
 

Último

Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insightsseri bangash
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...lizamodels9
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 

Último (20)

Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insights
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 

Pm610 1103 b-02-schwappach-loren-p1-ip1

  • 1. Process Groups and Knowledge Areas Loren Karl Schwappach Colorado Technical University 30 August 2011 Process Groups and Knowledge Areas Introduction Hello, my name is Loren Karl Schwappach. I am the new project manager for the 2011 Billing System Upgrade Project (BSUP). I have been asked to create this briefing to enlighten the customer service and billing departments about project management process groups and the knowledge areas of project management. I hope this briefing is informative and helps to open eyes to the upcoming challenges ahead. It is my goal to see this project to success and as base line users you will play a large role in determining the quality and performance of the final project. 1
  • 2. Overview Today I will talk to you about the five project management process groups to include: initiating, planning, executing, monitor and controlling and closing. I will also introduce the nine knowledge areas of project management to include: integration management, scope management, time management, cost management, quality management, human Resources management, communications management, risk management, and procurement management. I will end the briefing with a project management case study. If you have any questions as I proceed during this briefing please feel free to speak them during the briefing. 2
  • 3. Project Management Process Groups Before the customer service and billing department’s legacy billing system web-based upgrade project can be initiated, it is imperative for the project manager, project team, and project stakeholders to recognize what is to pass once the project is started and the undertakings they will be required to participate in. This briefing was designed to provide an understanding of project management process groups and the nine knowledge areas of project management so that IRTC employees can observe how to properly work with and structure the project to ensure this projects success. Although, there is no way to completely anticipate and prevent all problems, having a clear understanding of the processes will help increase the effectiveness in managing this large upgrade project. Group #1: Initiating The initial phase of project management involves obtaining the necessary permissions and approvals required to begin the project. Usually, a document outlining the necessity for the project is created in order to reason to the project’s sponsor how the needs of the organization will be met, and approximately how much the project will cost and how long the project is expected to take (Babou, 2008). The initiating process group contains the processes designed to describe the project, subproject, or phase of an existing project and obtain authorization to begin each project phase. The main processes of the initiating group as defined by the PMBOK are to develop the project charter and identify stakeholders (Global Standard, 2008). 3
  • 4. Group #2: Planning This project group is about planning out the project and defining project goals. Large portions of the project need to be stripped down and deadlines will be scheduled. Stakeholders will play a large role in authorizing and planning out resources (Babou, 2008). This is also the phase in which the project team is put together and begins to identify tasks and roles. Project costs are estimated to provide the groundwork for a project budget. The IRTC project team will utilize MS Project to aid in the scheduling of costs and resources and will utilize your departments in streamlining these plans. The planning process group contains processes needed to establish the projects scope, smooth and refine objectives and identify courses of action necessary to complete project objectives. This group contains the following processes: develop project management plan, collect requirements, define scope, create WBS, define activities, sequence activities, estimate activity resources, estimate activity durations, develop schedule, estimate costs, determine budget, plan quality, develop human resource plan, plan communications, plan risk management, identify risks, perform quantitative risk analysis, plan risk responses, and plan procurements (Global Standard, 2008). Group #3: Executing Now that the project team has everything in place and goals well-defined, it is time to begin developing the end product results. Contracts are administered as needed, and the project’s team members make periodic reports on their status. Everything that goes into making the plan a reality takes place during the project’s execution group (Babou, 2008). This process group contains the processes used to perform and complete work as outlined by the project management plan and needed to satisfy project specifications. This group contains the following processes: direct and manage project execution, perform quality assurance, acquire project team, develop project team, manage project team, distribute information, manage stakeholder expectations, and conduct procurements (Global Standard, 2008). 4
  • 5. Group #4: Monitoring and controlling After the execution stage is under way the project team should begin monitoring to ensure everything goes according to the project plan. As products and stages are completed, each is submitted to the project sponsor (IRTC CIO) for approval. If adjustments are required they are made during this stage. The project team and stakeholders should keep an ongoing list of valuable lessons learned during the project to help in evaluating the projects performance (Babou, 2008). This process group contains the processes utilized in tracking, reviewing, and regulating the performance and progress of the project, identifying areas for change, and initiating changes. The group contains the following processes: monitor and control project work, perform integrated change control, verify scope, control scope, control schedule, control costs, perform quality control, report performance, monitor and control risks, and administer procurements (Global Standard, 2008). Group #5: Closing The last project management group marks the end of the project. The project manager arranges for the final acceptance of the product, and the sponsor accepts. Everything is carefully documented in writing, and records of contracts, transactions, and other agreements are completed. Project debriefing and plans for necessary follow up are made at this time (Babou, 2008). The closing process group contains the processes for finalizing activities across all process groups. This group contains the following processes: close project or phase, and close procurements (Global Standard, 2008). 5
  • 6. Project Management Knowledge Areas Managing projects involves applying knowledge, skills, tools, and techniques to project activities in order to meet project objectives. IRTC’s project team will accomplish this by performing processes at various stages of the project, as I discussed in the project phase slides. Each aspect of a project is managed by using the corresponding knowledge area. Each process belongs to one of the nine knowledge areas: scope management, time management, cost management, human resource management, procurement management, risk management, quality management, integration management, and communication management (Kerzner, 2003). Project Integration Management The project is initiated, planned, and executed in pieces, and all those need to fit together. That is where project integration management is utilized. Project integration management includes developing the project charter (the document that authorizes the project and identifies initial project requirements), developing the project management plan (defines how the project is executed, monitored, and controlled), directing and managing project execution (creating deliverables, training staff and team members, obtaining resources, performing risk management, managing sellers and suppliers, issuing change requests), monitoring and controlling project work (tracking, reviewing, and regulating the progress to meet performance objectives), performing integrated change control (reviewing, approving, and managing project changes), and closing the project or a phase of a project (review and finalizing all activities) (Global Standard, 2008). 6
  • 7. Project Scope Management Project scope management includes collecting requirements (defining and documenting stakeholder’s needs, customer service will play a large part here), defining the scope (develop detailed description of the project), creating a Work Breakdown Structure (WBS) (subdivides deliverables into smaller manageable components), verifying the scope (formalizing acceptance of deliverables), and controlling the scope (monitoring the status of the project and scope and managing changes). Initially our project team will collect the requirements for the project based on the stakeholders’ needs, which will determine the project scope. Next our project team will develop the description for the project and its products, which is the basis for the project scope. Customer service and billing departments will play a large role in identifying the features need for this project and thus will play a large part in defining the projects scope and deliverables. Our project team will then create the project’s work breakdown structure (WBS). Next our project team will verify the scope and plan how the completed deliverables of the project will be accepted. Finally in order to control the scope, only the approved changes to the scope should be implemented. Obviously, these components are performed by using the corresponding processes (Global Standard, 2008). 7
  • 8. Project Time Management Project time management is accomplished by defining activities, sequencing activities, estimating activity resources, estimating activity durations, developing a schedule, and controlling the schedule. Define activities includes identifying all the work activities that need to be scheduled to produce the project deliverables. Sequencing activities involves identifying the dependencies among the activities that need to be scheduled so that they can be scheduled in the correct order. Estimating activity resources includes estimate the types of resources needed and the quantity for each type for each schedule activity. Estimating activity durations involves estimating the time needed to complete each schedule activity. Developing the schedule includes analyzing the data created in the previous steps to develop the schedule. Control of the schedule involves controlling the changes to the project schedule (Global Standard, 2008). Project Cost Management Cost management includes estimating the cost, determining the project budget, and controlling the cost. Estimate cost involves developing the cost of the resources needed to complete the project, which includes schedule activities and outsourced/procured work. Determining the budget requires aggregating the costs of individual activities to establish a cost baseline that includes timing. Control the cost involves monitoring and controlling the cost variance in the project execution (Global Standard, 2008). 8
  • 9. Project Quality Management Project quality management includes planning the quality, performing quality assurance, and performing quality control. Planning quality involves determining the quality requirements and standards that are relevant to the project at hand and how to apply them. Performing quality assurance involves ensuring the planned quality requirements and standards are applied. Performing quality control involves monitoring the quality activities and recording the results of these activities in order to assess performance and make necessary recommendations for corrective actions and changes (Global Standard, 2008). Project Human Resource Management Project human resource management includes developing a human resource plan, acquiring the project team, developing the project team, and managing the project team. Developing a human resources plan involves identifying project roles, responsibilities for each role, and reporting relationships among the roles. The staff management plan describes when and how the resource requirements will be met. Acquiring the project team involves obtaining the human resources needed to work on the project. Developing the project team involves improving the competencies of the team members and the interaction among members to optimize the team performance. Managing the project team involves tracking the performance of team members, provide team members with feedback, and resolve issues and conflicts (Global Standard, 2008). 9
  • 10. Project Communication Management Communication management includes identifying project stakeholders, planning communication, distributing information, managing stake holder expectations, and reporting performance. Stakeholder identification involves identifying all individuals, groups, and organizations that will potentially be impacted by the project and find relevant information about them (this includes customer service and billing department staff). Planning communications involves determining the information and communication needs of the project at hand and the communication approach to be used. Distributing information involves making the needed information available to the project stakeholders in a timely fashion. Managing stakeholder expectations involves communicating and working with the stakeholders in order to understand and meet their needs, address the issues, and manage the expectations within the project scope and the project management plan. This maybe the most essential process and will require a lot of brain storming between the project team and customer service and billing departments. Finally, reporting performance involves collecting and distributing performance information to the stakeholders to stay on the same page (Global Standard, 2008). 10
  • 11. Project Risk Management Project risk management includes risk management planning, identification of risks, performing qualitative risk analysis, planning risk responses, and monitor and control of risks. Planning risk management involves deciding how to determine and execute the risk management tasks. Identifying risks included identifying the potential risks relevant to the project at hand and determine the characteristics of those risks. Performing qualitative risk analysis involves assessing the probability of occurrence and the impact for each risk in order to prioritize risks for an action or for further analysis. Performing quantitative risk analysis involves estimating the effects of identified risks on project objectives. Planning risk responses involves developing action options for risks to maximize opportunities for and minimize threats to satisfying project objectives. Monitor and control of risks involves tracking identified risks, implement risk response plans, identify new risks, and evaluate the effectiveness of risk management processes throughout the project (Global Standard, 2008). Project Procurement Management Procurement management includes planning procurements, conducting procurements, administering procurements, and closing procurements. To plan procurements the project team needs to identify purchasing needs (what hardware / software is needed, materials, personnel outsourcing, etc.), specify the procurement approach, and identify potential venders. Conducting procurements involves obtaining vender responses, selecting venders, and issuing contracts. Administering procurements involves managing procurement relationships, monitoring the procurement performance, and monitoring and controlling changes in procurement. Closing procurements involves completing procurements with proper closure, such as accepting products and closing contracts (Global Standard, 2008). 11
  • 12. Case Study [WHY] Project management training offers advantages and clear benefits to include reduced delivery costs, increased project efficiency, focus advantages, prediction increases, and problem identification (Egeland, 2010). As an example a case study of [WHO] a major investment company was completed [WHERE] by Rosenhead (2010) of Project Agency a project management online training agency [WHEN] in 2006 (Rosenhead, 2010). [WHAT] The investment company studied was facing a problem where projects were not being delivered effectively (on time or on budget). Very few staff had been involved with project management courses and they had no overall project management approach. [HOW] The company developed a non-standard project methodology and asked Project Agency to benchmark their practices, and the preliminary results were poor. Project Agency provided essential project management training to the company and projects began being completed in record time, without breaking budget constraints, and increased quality. The investment companies’ staff was more aware of the way to approach change management thorough the use of and application of project management skills. IRTC customer service employees will play a tremendous role on the success of this project which is why an understanding of the standard processes involved is so essential. 12
  • 13. Summary Today I talked to you about the five project management process groups to include: initiating, planning, executing, monitor and controlling and closing. I also introduced the nine knowledge areas of project management to include: integration management, scope management, time management, cost management, quality management, human Resources management, communications management, risk management, and procurement management. I concluded the briefing with a project management case study and explained some of the benefits of project management. I would now like to open the floor to any additional questions. Thank you. 13
  • 14. References Babou, S.(2008). Project Management Processes & Process Groups. Leadership Champions, Retrieved August 30, 2011, from http://leadershipchamps.wordpress.com/2008/03/03/project-management-process- groups/ Egeland, B. (2010). “Strategic Organizational Benefits of Project Management”. Project Management Tips, Retrieved August 30, 2011, from http://pmtips.net/strategic- organizational-benefits-project-management/ Global Standard. (2008). A Guide to the Project Management Body of Knowledge (4th ed.). Newtown Square, PA: Project Management Institute, Inc. Kerzner, H. (2003). Project management: A systems approach to planning, scheduling, and controlling (8th ed.). Hoboken, New Jersey: John Wiley & Sons, Inc. Rosenhead, R. (2010). Case Studies. Retrieved August 30, 2011, from Project Agency Website: http://pmtips.net/strategic-organizational-benefits-project-management/ 14
  • 15. [Illustration of PMBOK Processes]. (n.d.). Retrieved August 30, 2011, from: http://www.projectmanagement-ema.com/imageprocessor.php?src=images/pmbok- processes.jpg&w=200 [Illustration of PMBOK Processes]. (n.d.). Retrieved August 30, 2011, from: http://www.projectmanagement-ema.com/imageprocessor.php?src=images/pmbok- processes.jpg&w=200 [Illustration of PMBOK Processes]. (n.d.). Retrieved August 30, 2011, from: http://www.projectmanagement-ema.com/imageprocessor.php?src=images/pmbok- processes.jpg&w=200 [Illustration of Man Juggling PM Constraints]. (n.d.). Retrieved August 30, 2011, from: http://www.theposselist.com/wp-content/uploads/2009/09/project-management- 1mod-a.jpg [Illustration of Human Resource Networks]. (n.d.). Retrieved August 30, 2011, from: http://www.whizlabs.com/blog/wp-content/uploads/2011/06/PMP1.jpg 15
  • 16. [Illustration of Men Fitting Together Gears]. (n.d.). Retrieved August 30, 2011, from: http://heartwooddigital.com/images/integration_m.jpg [Illustration of a Scope]. (n.d.). Retrieved August 30, 2011, from: http://amtruni.com/Amtruni_files/Scope%20Management.jpg [Illustration of a Stakeholders]. (n.d.). Retrieved August 30, 2011, from: http://pmtips.net/wp-content/uploads/2011/01/stakeholders_cartoon1.jpg [Illustration of a Project Management Puzzle]. (n.d.). Retrieved August 30, 2011, from: http://www.google.com/imgres?q=project+management&hl=en&safe=active&biw=1 068&bih=707&tbm=isch&tbnid=17lRVVuJd2SrAM:&imgrefurl=http://pmtips.net/act ual- project/&docid=ltHjOBhfLTlBjM&w=1331&h=1030&ei=ftdfTtv5K8Le0QHJ2bUb&zoo m=1 [Illustration of a Man Holding PM World]. (n.d.). Retrieved August 30, 2011, from: http://pmtips.net/wp-content/uploads/2010/05/ProjectManager.jpg 16