What is Hydroelectric Power?
 Hydroelectricity is a term referring to the electricity
generated by hydro power
 A hydropower development is essentially to utilize the
hydraulic power possessed by the water flowing in a
stream and to develop from it electric power through
hydraulic turbines coupled to electric generators
 The total amount of hydroelectric power that would be
made available from a stream depends on continuous
flow rate of the stream and the head possessed by the
flowing water
Lay out of typical hydroelectric power scheme
Comparison of Hydroelectric and Thermal Power Plants
Criterion Hydroelectric Power Plant Thermal Power Plant
1. Initial cost and life
expectancy
Higher initial cost due to costly
infrastructure such as dam,
spillway, et., and its location at
a place far off from the
consumer or load centre
Lower initial cost due to its
proximity to consumer or load
centre
Higher life expectancy, may be
about 50 years
Lower life expectancy
2. operation, maintenance and
repair (OMR) cost
Low OMR cost due to no fuel
cost
High OMR cost due to costly
fuel and the cost of fuel
transport
Less maintenance and repair
cost and staff needed for
operation is less
High maintenance and repair
cost and staff needed for
operation is more
Water is replenished every year
an put to non-consumable use.
However, supply of water may
be erratic year after year
Non-replenishable source
Low taxes due to its location in
remote areas
High taxes due to its location
near cities
Criterion Hydroelectric power plant Thermal power plant
3. Transmission losses
More due to long transmission
lines
Less due to short transmission
lines
4. Pollution
No problem of pollution or
ecological unbalance later
Causes air pollution as well as
stream pollution resulting in
ecological imbalance unless
cooling towers or cooling ponds
are provided
No waste product and hence no
problem of its disposal
Problem of haulage and disposal
of waste product viz., smoke,
ash etc.
5. Actuating time
A few seconds to 3 to 4 minutes
depending on the length of
conduit
About 30 minutes
Quite suitable to take up peak
load
Not suitable for use as peak
load plants
Selection of Suitable Types of Turbines
S.No Head in meters Type of turbine Specific speed
1 300 or more
Pelton wheel,
single or
multiple jet
8.5 to 47
2 150 to 300
Pelton or
Francis
30 to 85
3 60 to 150
Francis or
Deriaz
85 to 188
4 Less than 60
Kaplan or
Deriaz
188 to 860
Advantages of Hydroelectric Power
Fuel is not burned so there is minimal pollution
Water to run the power plant is provided free by
nature
Hydropower plays a major role in reducing
greenhouse gas emissions
Relatively low operations and maintenance costs
The technology is reliable and proven over time
It's renewable - rainfall renews the water in the
reservoir, so the fuel is almost always there
Disadvantages of Hydroelectric Power
High investment costs
Hydrology dependent (precipitation)
In some cases, inundation of land and wildlife
habitat
In some cases, loss or modification of fish habitat
Fish entrainment or passage restriction
In some cases, changes in reservoir and stream
water quality
In some cases, displacement of local populations
Classification of Hydel Plants
1. Classification based on storage characteristics
 Run-off river plants
- Utilize the minimum flow of a river
- Do not have appreciable storage on the u/s side
- Suitable only on perennial rivers
 Storage plants
- It has an upstream storage reservoir
- Continuous firm power generation is possible
 Pumped storage plants
- Power is generated during peak hours, but during off-peak hours water is
pumped back from the tail water pool to head water pool for future use
- Primarily meant for assisting an existing thermal or other hydel plant
 Tidal plants
- Works on the principle that there is a rise in sea water
during high tide period and fall during the low ebb
period
- The tidal range, i.e. the difference between high and
low tide levels is utilized to generate power
2. Classification according to functional basis
 Base load plants
- These are the plants which are capable of substantially
continuous operation in the base of the load curve throughout
the year
 Peak load plants
- It is a hydel plant designed and constructed primarily for taking
care of the peak load of a power system
3. Classification based on the basis of head
 Micro head plants – H = 10 m to 20 m
 Low head plants – H <= 30 m
 Medium head plants – H = 30 m to 250 m
 High head plants – H > 250 m
Important Terms Connected With Hydropower
 Water Power Potential
- It is the amount of power generated when Q cumecs of water
is allowed to fall through a head difference of H meters and is
given by:
P = η γ Q H
 Normal Water Level (NWL)
- It is the highest elevation of water level that can be
maintained in the reservoir without any spillway discharge
 Minimum Water Level (MWL)
- It is the elevation of the water level which produces minimum
net head on the power units (i.e. 60% of the design head)
 Rated Head – The head at which the turbine functioning at
full gate opening will produce a power output, equal to that
specified on the name plate of the turbine.
 Gross Head – It is the difference in water level elevation at the
point of diversion of water for the hydel scheme and the point
of return of water back to the river.
 Operating Head – It is the difference between the elevation of
water surface in the fore-bay and the tailrace after making
due allowance for approach and exit velocity heads
 Net Head or Effective Head – It is the difference of head at the
point of entry and exit of turbine and includes the respective
velocity and pressure heads at both places
 Installed Capacity – It is the total capacity in kilowatts or
million kilowatts of all the turbine generator units installed in
a power house.
 Dependable Capacity – It is the load carrying capability of the
power house with respect to the load characteristics during a
specified time interval
 Load Factor (LF) – It is defined as the ratio of the average load
over a certain period of time to the peak load during the same
period
 Utilization Factor (UF) or Plant Use Factor
Average load over a certain period
Peak load during that period
Load Factor 
Water actually utilized for power production
Water available in the river
UF 
 Capacity Factor or Plant Factor – It is the ratio of average output
of the plant for a given period of time to the plant capacity or, it
can also be defined as:
 Firm Power – The net amount of power which is continuously
available from a plant without any break on firm or guaranteed
basis.
 Secondary Power – The excess power available over the firm
power during the off peak hours or during monsoon season
 Power Factor – It is the ratio of actual power in kilowatts to the
apparent power in kilo volt amperes (KVA)
Energy actually produced in a given time
Max. energy that can be produced by the plant during the same time
CF 
Principal Components of a Hydroelectric
Scheme
 The fore-bay
 Intake structure
 Penstocks
 Surge tank or surge chambers
 Turbines
 Power house
 Draft tube
 The tailrace
Components of a Hydroelectric Power Plant
1. Forebay
 An enlarged body of water provided just in front of the penstock
 It is provided in the case of run-of-river plants and storage plants
when the power house is located far away from the dam
 The main function of forebay is to provide a small balancing
storage upstream of the power house
2. Intake structures
 The water from the reservoir or forebay is let into the penstocks
through intake structure
 The main components of an intake structure are trash racks and
gates
 Trash rack is provided to prevent the entry of debris into the water
passage of hydropower plant
 The gates are provided to control the entry of water into the
penstocks
3. Penstocks
 Penstocks are the pipes of large diameter used for conveying
water from the reservoir to the turbines
 A sufficient water depth should be provided above the penstock
entrance to avoid formation of vortices which may carry air into
the penstock and result in lowered turbine efficiency and
undesirable pressure surges
4. Surge tanks
 A surge tank is a cylindrical open-topped storage tank which is
connected to the penstock at a suitable point.
 These are provided to relieve the penstocks of excess pressure
caused by water hammer
 They also provide additional supply of water when the turbines
are in need of more water on account of increased load
 A surge tank should be provided as close to the power house as is
possible
4. Power house
 It is a structure which houses the various hydraulic and electric
equipment
 The various hydraulic equipments are turbines, gates or gate
valves, governors, etc.
 The various electrical equipments are, generators, transformers,
switching equipments, transmission lines and transmission
structures
5. Turbines
 The machine which converts hydraulic energy to mechanical
energy, and finally to electrical energy
6. Tail race
 A channel into which the water is discharged after passing
through the turbines
7. Draft tube: - An elongated pipe connecting turbine to tail race
Example Problems
Example 1: Three turbo-generators each of capacity 10000 kW have
been installed at a hydel power station. During a certain period of
load, the load on the plant varies from 12000 kW to 26000 kW.
Calculate (i) total installed capacity, (ii) load factor, (iii) plant factor
and (iv) utilization factor.
Example 2 : During a low water week a river has an average daily
flow of 32 m3/sec with a fluctuation during the day requiring a
pondage capacity of approximately 15% of the daily discharge. a HEP
is to be located on the river which will operate 5 days a week, 24
hours a day, but will supply power at varying rate such that the daily
load factor is 55% corresponding to which the pondage required is
equal to 0.2 times the mean flow to the turbine. On Saturday and
Sunday all the flow is ponded for use on rest of the days.
Contd.
If the effective head on the turbines when the pond is full is to be 25
m and the maximum allowable fluctuation in pond level is 1 m find
(a) the surface area of the pond to satisfy all the operating
conditions, (b) the weekly output at the switch board in kwh.
Assume turbine efficiency 55% and generator efficiency 92%

Más contenido relacionado

La actualidad más candente

Classification of hydro power plant
Classification of hydro power plantClassification of hydro power plant
Classification of hydro power plantSatish Taji
 
Hydal power plant
Hydal power plantHydal power plant
Hydal power plantJUNAID SK
 
Water resources planning and development m5
Water resources planning and development m5Water resources planning and development m5
Water resources planning and development m5Bibhabasu Mohanty
 
Hyetograph and hydrograph analysis
Hyetograph and hydrograph analysisHyetograph and hydrograph analysis
Hyetograph and hydrograph analysisvivek gami
 
Elements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTSElements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTSRaju D
 
PUMPED STORAGE PLANT
PUMPED STORAGE PLANTPUMPED STORAGE PLANT
PUMPED STORAGE PLANTNilanjana Sen
 
Unit_IV-HYDRO ELECTRIC POWER PLANTS
Unit_IV-HYDRO ELECTRIC POWER PLANTSUnit_IV-HYDRO ELECTRIC POWER PLANTS
Unit_IV-HYDRO ELECTRIC POWER PLANTSS.Vijaya Bhaskar
 
Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant Prasad Vejendla
 
Energy dissipators
Energy dissipatorsEnergy dissipators
Energy dissipatorsRahul Gupta
 
Module 2 ch-1 heytograph and hydrology analysis
Module 2 ch-1 heytograph and hydrology analysisModule 2 ch-1 heytograph and hydrology analysis
Module 2 ch-1 heytograph and hydrology analysisAnkit Patel
 
Water resource management
Water resource management  Water resource management
Water resource management Rohan Mohite
 
Design of Lined Canal and Canal Lining
Design of Lined Canal and Canal LiningDesign of Lined Canal and Canal Lining
Design of Lined Canal and Canal LiningRamanuj Jaldhari
 
Dam safety & Safety Devices
Dam safety & Safety DevicesDam safety & Safety Devices
Dam safety & Safety DevicesTushar Dholakia
 
energy dissipator in hydraulic structure
energy dissipator  in  hydraulic structure energy dissipator  in  hydraulic structure
energy dissipator in hydraulic structure Kiran Jadhav
 
Chapter 2 open channel hydraulics
Chapter 2 open channel hydraulicsChapter 2 open channel hydraulics
Chapter 2 open channel hydraulicsMohsin Siddique
 
Flood frequency analyses
Flood frequency analysesFlood frequency analyses
Flood frequency analysesvivek gami
 

La actualidad más candente (20)

Classification of hydro power plant
Classification of hydro power plantClassification of hydro power plant
Classification of hydro power plant
 
Hydro Power Plants
Hydro Power PlantsHydro Power Plants
Hydro Power Plants
 
Hydal power plant
Hydal power plantHydal power plant
Hydal power plant
 
Water resources planning and development m5
Water resources planning and development m5Water resources planning and development m5
Water resources planning and development m5
 
Hyetograph and hydrograph analysis
Hyetograph and hydrograph analysisHyetograph and hydrograph analysis
Hyetograph and hydrograph analysis
 
Elements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTSElements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTS
 
PUMPED STORAGE PLANT
PUMPED STORAGE PLANTPUMPED STORAGE PLANT
PUMPED STORAGE PLANT
 
Unit_IV-HYDRO ELECTRIC POWER PLANTS
Unit_IV-HYDRO ELECTRIC POWER PLANTSUnit_IV-HYDRO ELECTRIC POWER PLANTS
Unit_IV-HYDRO ELECTRIC POWER PLANTS
 
Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant
 
Energy dissipators
Energy dissipatorsEnergy dissipators
Energy dissipators
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Module 2 ch-1 heytograph and hydrology analysis
Module 2 ch-1 heytograph and hydrology analysisModule 2 ch-1 heytograph and hydrology analysis
Module 2 ch-1 heytograph and hydrology analysis
 
Water resource management
Water resource management  Water resource management
Water resource management
 
Weir and barrage lecture
Weir and barrage lectureWeir and barrage lecture
Weir and barrage lecture
 
Design of Lined Canal and Canal Lining
Design of Lined Canal and Canal LiningDesign of Lined Canal and Canal Lining
Design of Lined Canal and Canal Lining
 
Ch4 surface runoff
Ch4 surface runoffCh4 surface runoff
Ch4 surface runoff
 
Dam safety & Safety Devices
Dam safety & Safety DevicesDam safety & Safety Devices
Dam safety & Safety Devices
 
energy dissipator in hydraulic structure
energy dissipator  in  hydraulic structure energy dissipator  in  hydraulic structure
energy dissipator in hydraulic structure
 
Chapter 2 open channel hydraulics
Chapter 2 open channel hydraulicsChapter 2 open channel hydraulics
Chapter 2 open channel hydraulics
 
Flood frequency analyses
Flood frequency analysesFlood frequency analyses
Flood frequency analyses
 

Destacado

PRINCIPLES OF HYDROPOWER ENGINEERING
PRINCIPLES OF HYDROPOWERENGINEERINGPRINCIPLES OF HYDROPOWERENGINEERING
PRINCIPLES OF HYDROPOWER ENGINEERINGArkan Hamza Gardi
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plantYuri Melliza
 
Hydro power-plant
Hydro power-plantHydro power-plant
Hydro power-plantpranavn007
 
Epgpptfinal 141112142403-conversion-gate02
Epgpptfinal 141112142403-conversion-gate02Epgpptfinal 141112142403-conversion-gate02
Epgpptfinal 141112142403-conversion-gate02chandugolsar
 
Hydropower slide show.
Hydropower slide show.Hydropower slide show.
Hydropower slide show.abdulla4p34h
 
Application of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationApplication of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationAmeen San
 
Ppt on diff. load curve
Ppt on diff. load curvePpt on diff. load curve
Ppt on diff. load curveCraZzy Shubh
 
Sources of energy
Sources of energySources of energy
Sources of energyRobin Dabur
 
Presentation=sardar sarovar hydro power plant
Presentation=sardar sarovar hydro power plantPresentation=sardar sarovar hydro power plant
Presentation=sardar sarovar hydro power plantvishal Barvaliya
 
electrical distribution system ppt/13b61a0221
electrical distribution system ppt/13b61a0221electrical distribution system ppt/13b61a0221
electrical distribution system ppt/13b61a0221saikrishna kandhikatla
 
Energy conservation ppt
Energy conservation ppt  Energy conservation ppt
Energy conservation ppt Dixit Sethi
 
Hydro electric power plant lecture
Hydro electric power plant lectureHydro electric power plant lecture
Hydro electric power plant lecturec3b2a1
 
Hydrologic Cycle
Hydrologic  CycleHydrologic  Cycle
Hydrologic Cycletnewberry
 
Hydro power ppt
Hydro power pptHydro power ppt
Hydro power pptsrgirlsdk
 
Hydro Power Plant
Hydro Power PlantHydro Power Plant
Hydro Power Planttavinav
 
Water supply system
Water supply systemWater supply system
Water supply systemaishah
 
Greenhouse Effect.
Greenhouse Effect.Greenhouse Effect.
Greenhouse Effect.SabaAnwar11
 
P.P.T on water distribution system by Manish Pandey
P.P.T on water distribution system by Manish PandeyP.P.T on water distribution system by Manish Pandey
P.P.T on water distribution system by Manish PandeyManish Pandey
 

Destacado (20)

PRINCIPLES OF HYDROPOWER ENGINEERING
PRINCIPLES OF HYDROPOWERENGINEERINGPRINCIPLES OF HYDROPOWERENGINEERING
PRINCIPLES OF HYDROPOWER ENGINEERING
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Hydro power-plant
Hydro power-plantHydro power-plant
Hydro power-plant
 
Epgpptfinal 141112142403-conversion-gate02
Epgpptfinal 141112142403-conversion-gate02Epgpptfinal 141112142403-conversion-gate02
Epgpptfinal 141112142403-conversion-gate02
 
Hydropower slide show.
Hydropower slide show.Hydropower slide show.
Hydropower slide show.
 
Application of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationApplication of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage Regulation
 
Ppt on diff. load curve
Ppt on diff. load curvePpt on diff. load curve
Ppt on diff. load curve
 
Sources of energy
Sources of energySources of energy
Sources of energy
 
Presentation=sardar sarovar hydro power plant
Presentation=sardar sarovar hydro power plantPresentation=sardar sarovar hydro power plant
Presentation=sardar sarovar hydro power plant
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
electrical distribution system ppt/13b61a0221
electrical distribution system ppt/13b61a0221electrical distribution system ppt/13b61a0221
electrical distribution system ppt/13b61a0221
 
The Hydrologic Cycle
The Hydrologic CycleThe Hydrologic Cycle
The Hydrologic Cycle
 
Energy conservation ppt
Energy conservation ppt  Energy conservation ppt
Energy conservation ppt
 
Hydro electric power plant lecture
Hydro electric power plant lectureHydro electric power plant lecture
Hydro electric power plant lecture
 
Hydrologic Cycle
Hydrologic  CycleHydrologic  Cycle
Hydrologic Cycle
 
Hydro power ppt
Hydro power pptHydro power ppt
Hydro power ppt
 
Hydro Power Plant
Hydro Power PlantHydro Power Plant
Hydro Power Plant
 
Water supply system
Water supply systemWater supply system
Water supply system
 
Greenhouse Effect.
Greenhouse Effect.Greenhouse Effect.
Greenhouse Effect.
 
P.P.T on water distribution system by Manish Pandey
P.P.T on water distribution system by Manish PandeyP.P.T on water distribution system by Manish Pandey
P.P.T on water distribution system by Manish Pandey
 

Similar a HYDROELECTRIC POWER

Calculation Efficiency of 2GW Hydropower Plant.
Calculation Efficiency of 2GW Hydropower Plant.Calculation Efficiency of 2GW Hydropower Plant.
Calculation Efficiency of 2GW Hydropower Plant.Salman Jailani
 
Calculation Efficiency of 5GW Hydropower Plant.
Calculation Efficiency of 5GW Hydropower Plant.Calculation Efficiency of 5GW Hydropower Plant.
Calculation Efficiency of 5GW Hydropower Plant.Salman Jailani
 
HYDRO-ELECTRIC POWER PLANT
HYDRO-ELECTRIC POWER PLANTHYDRO-ELECTRIC POWER PLANT
HYDRO-ELECTRIC POWER PLANTKiranmoy Samanta
 
Unit-4-POWER FROM RENEWABLE ENERGY.ppt
Unit-4-POWER FROM RENEWABLE ENERGY.pptUnit-4-POWER FROM RENEWABLE ENERGY.ppt
Unit-4-POWER FROM RENEWABLE ENERGY.pptdharma raja`
 
To study working of each component of hydro power plant?
To study working of each component of hydro power plant?To study working of each component of hydro power plant?
To study working of each component of hydro power plant?Salman Jailani
 
Hydroelectric powerplant
Hydroelectric powerplantHydroelectric powerplant
Hydroelectric powerplantGurkirat Singh
 
Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008Pratik Diyora
 
Hydro power by salik haroon abbasi
Hydro  power by salik haroon abbasiHydro  power by salik haroon abbasi
Hydro power by salik haroon abbasiSalik Haroon Abbasi
 
HYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in India
HYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in IndiaHYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in India
HYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in IndiaMayurjyotiNeog
 
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptxWajidMalik27
 
RES Lecture 18 Hydro.pptx
RES Lecture 18 Hydro.pptxRES Lecture 18 Hydro.pptx
RES Lecture 18 Hydro.pptxEngr umar
 
Hydroelectric power plant
Hydroelectric power plantHydroelectric power plant
Hydroelectric power plantMuddassar Awan
 
Hydroelectric power plant
Hydroelectric power plantHydroelectric power plant
Hydroelectric power plantMuddassar Awan
 
Earth Sci Report (With Animations) (2).pptx
Earth Sci Report (With Animations) (2).pptxEarth Sci Report (With Animations) (2).pptx
Earth Sci Report (With Animations) (2).pptxChrisLibarios
 
hydro power ppt in digital ekectronics ppt
hydro power ppt in digital ekectronics  ppthydro power ppt in digital ekectronics  ppt
hydro power ppt in digital ekectronics pptkumarankit06875
 

Similar a HYDROELECTRIC POWER (20)

Hydropower part -I.pptx
Hydropower part -I.pptxHydropower part -I.pptx
Hydropower part -I.pptx
 
Calculation Efficiency of 2GW Hydropower Plant.
Calculation Efficiency of 2GW Hydropower Plant.Calculation Efficiency of 2GW Hydropower Plant.
Calculation Efficiency of 2GW Hydropower Plant.
 
Calculation Efficiency of 5GW Hydropower Plant.
Calculation Efficiency of 5GW Hydropower Plant.Calculation Efficiency of 5GW Hydropower Plant.
Calculation Efficiency of 5GW Hydropower Plant.
 
HYDRO-ELECTRIC POWER PLANT
HYDRO-ELECTRIC POWER PLANTHYDRO-ELECTRIC POWER PLANT
HYDRO-ELECTRIC POWER PLANT
 
hydro power plant
hydro power planthydro power plant
hydro power plant
 
Hydro plant.docx
Hydro plant.docxHydro plant.docx
Hydro plant.docx
 
Unit-4-POWER FROM RENEWABLE ENERGY.ppt
Unit-4-POWER FROM RENEWABLE ENERGY.pptUnit-4-POWER FROM RENEWABLE ENERGY.ppt
Unit-4-POWER FROM RENEWABLE ENERGY.ppt
 
To study working of each component of hydro power plant?
To study working of each component of hydro power plant?To study working of each component of hydro power plant?
To study working of each component of hydro power plant?
 
Hydroelectric powerplant
Hydroelectric powerplantHydroelectric powerplant
Hydroelectric powerplant
 
Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008
 
Hydro power by salik haroon abbasi
Hydro  power by salik haroon abbasiHydro  power by salik haroon abbasi
Hydro power by salik haroon abbasi
 
HYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in India
HYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in IndiaHYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in India
HYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in India
 
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
 
Hydroelectric powerplant
Hydroelectric powerplant Hydroelectric powerplant
Hydroelectric powerplant
 
Hydro power
Hydro powerHydro power
Hydro power
 
RES Lecture 18 Hydro.pptx
RES Lecture 18 Hydro.pptxRES Lecture 18 Hydro.pptx
RES Lecture 18 Hydro.pptx
 
Hydroelectric power plant
Hydroelectric power plantHydroelectric power plant
Hydroelectric power plant
 
Hydroelectric power plant
Hydroelectric power plantHydroelectric power plant
Hydroelectric power plant
 
Earth Sci Report (With Animations) (2).pptx
Earth Sci Report (With Animations) (2).pptxEarth Sci Report (With Animations) (2).pptx
Earth Sci Report (With Animations) (2).pptx
 
hydro power ppt in digital ekectronics ppt
hydro power ppt in digital ekectronics  ppthydro power ppt in digital ekectronics  ppt
hydro power ppt in digital ekectronics ppt
 

Último

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 

Último (20)

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 

HYDROELECTRIC POWER

  • 1.
  • 2. What is Hydroelectric Power?  Hydroelectricity is a term referring to the electricity generated by hydro power  A hydropower development is essentially to utilize the hydraulic power possessed by the water flowing in a stream and to develop from it electric power through hydraulic turbines coupled to electric generators  The total amount of hydroelectric power that would be made available from a stream depends on continuous flow rate of the stream and the head possessed by the flowing water
  • 3.
  • 4.
  • 5. Lay out of typical hydroelectric power scheme
  • 6. Comparison of Hydroelectric and Thermal Power Plants Criterion Hydroelectric Power Plant Thermal Power Plant 1. Initial cost and life expectancy Higher initial cost due to costly infrastructure such as dam, spillway, et., and its location at a place far off from the consumer or load centre Lower initial cost due to its proximity to consumer or load centre Higher life expectancy, may be about 50 years Lower life expectancy 2. operation, maintenance and repair (OMR) cost Low OMR cost due to no fuel cost High OMR cost due to costly fuel and the cost of fuel transport Less maintenance and repair cost and staff needed for operation is less High maintenance and repair cost and staff needed for operation is more Water is replenished every year an put to non-consumable use. However, supply of water may be erratic year after year Non-replenishable source Low taxes due to its location in remote areas High taxes due to its location near cities
  • 7. Criterion Hydroelectric power plant Thermal power plant 3. Transmission losses More due to long transmission lines Less due to short transmission lines 4. Pollution No problem of pollution or ecological unbalance later Causes air pollution as well as stream pollution resulting in ecological imbalance unless cooling towers or cooling ponds are provided No waste product and hence no problem of its disposal Problem of haulage and disposal of waste product viz., smoke, ash etc. 5. Actuating time A few seconds to 3 to 4 minutes depending on the length of conduit About 30 minutes Quite suitable to take up peak load Not suitable for use as peak load plants
  • 8. Selection of Suitable Types of Turbines S.No Head in meters Type of turbine Specific speed 1 300 or more Pelton wheel, single or multiple jet 8.5 to 47 2 150 to 300 Pelton or Francis 30 to 85 3 60 to 150 Francis or Deriaz 85 to 188 4 Less than 60 Kaplan or Deriaz 188 to 860
  • 9. Advantages of Hydroelectric Power Fuel is not burned so there is minimal pollution Water to run the power plant is provided free by nature Hydropower plays a major role in reducing greenhouse gas emissions Relatively low operations and maintenance costs The technology is reliable and proven over time It's renewable - rainfall renews the water in the reservoir, so the fuel is almost always there
  • 10. Disadvantages of Hydroelectric Power High investment costs Hydrology dependent (precipitation) In some cases, inundation of land and wildlife habitat In some cases, loss or modification of fish habitat Fish entrainment or passage restriction In some cases, changes in reservoir and stream water quality In some cases, displacement of local populations
  • 11. Classification of Hydel Plants 1. Classification based on storage characteristics  Run-off river plants - Utilize the minimum flow of a river - Do not have appreciable storage on the u/s side - Suitable only on perennial rivers
  • 12.  Storage plants - It has an upstream storage reservoir - Continuous firm power generation is possible  Pumped storage plants - Power is generated during peak hours, but during off-peak hours water is pumped back from the tail water pool to head water pool for future use - Primarily meant for assisting an existing thermal or other hydel plant
  • 13.  Tidal plants - Works on the principle that there is a rise in sea water during high tide period and fall during the low ebb period - The tidal range, i.e. the difference between high and low tide levels is utilized to generate power
  • 14. 2. Classification according to functional basis  Base load plants - These are the plants which are capable of substantially continuous operation in the base of the load curve throughout the year  Peak load plants - It is a hydel plant designed and constructed primarily for taking care of the peak load of a power system 3. Classification based on the basis of head  Micro head plants – H = 10 m to 20 m  Low head plants – H <= 30 m  Medium head plants – H = 30 m to 250 m  High head plants – H > 250 m
  • 15. Important Terms Connected With Hydropower  Water Power Potential - It is the amount of power generated when Q cumecs of water is allowed to fall through a head difference of H meters and is given by: P = η γ Q H  Normal Water Level (NWL) - It is the highest elevation of water level that can be maintained in the reservoir without any spillway discharge  Minimum Water Level (MWL) - It is the elevation of the water level which produces minimum net head on the power units (i.e. 60% of the design head)
  • 16.  Rated Head – The head at which the turbine functioning at full gate opening will produce a power output, equal to that specified on the name plate of the turbine.  Gross Head – It is the difference in water level elevation at the point of diversion of water for the hydel scheme and the point of return of water back to the river.  Operating Head – It is the difference between the elevation of water surface in the fore-bay and the tailrace after making due allowance for approach and exit velocity heads  Net Head or Effective Head – It is the difference of head at the point of entry and exit of turbine and includes the respective velocity and pressure heads at both places
  • 17.  Installed Capacity – It is the total capacity in kilowatts or million kilowatts of all the turbine generator units installed in a power house.  Dependable Capacity – It is the load carrying capability of the power house with respect to the load characteristics during a specified time interval  Load Factor (LF) – It is defined as the ratio of the average load over a certain period of time to the peak load during the same period  Utilization Factor (UF) or Plant Use Factor Average load over a certain period Peak load during that period Load Factor  Water actually utilized for power production Water available in the river UF 
  • 18.  Capacity Factor or Plant Factor – It is the ratio of average output of the plant for a given period of time to the plant capacity or, it can also be defined as:  Firm Power – The net amount of power which is continuously available from a plant without any break on firm or guaranteed basis.  Secondary Power – The excess power available over the firm power during the off peak hours or during monsoon season  Power Factor – It is the ratio of actual power in kilowatts to the apparent power in kilo volt amperes (KVA) Energy actually produced in a given time Max. energy that can be produced by the plant during the same time CF 
  • 19. Principal Components of a Hydroelectric Scheme  The fore-bay  Intake structure  Penstocks  Surge tank or surge chambers  Turbines  Power house  Draft tube  The tailrace
  • 20. Components of a Hydroelectric Power Plant
  • 21. 1. Forebay  An enlarged body of water provided just in front of the penstock  It is provided in the case of run-of-river plants and storage plants when the power house is located far away from the dam  The main function of forebay is to provide a small balancing storage upstream of the power house 2. Intake structures  The water from the reservoir or forebay is let into the penstocks through intake structure  The main components of an intake structure are trash racks and gates  Trash rack is provided to prevent the entry of debris into the water passage of hydropower plant  The gates are provided to control the entry of water into the penstocks
  • 22. 3. Penstocks  Penstocks are the pipes of large diameter used for conveying water from the reservoir to the turbines  A sufficient water depth should be provided above the penstock entrance to avoid formation of vortices which may carry air into the penstock and result in lowered turbine efficiency and undesirable pressure surges 4. Surge tanks  A surge tank is a cylindrical open-topped storage tank which is connected to the penstock at a suitable point.  These are provided to relieve the penstocks of excess pressure caused by water hammer  They also provide additional supply of water when the turbines are in need of more water on account of increased load  A surge tank should be provided as close to the power house as is possible
  • 23. 4. Power house  It is a structure which houses the various hydraulic and electric equipment  The various hydraulic equipments are turbines, gates or gate valves, governors, etc.  The various electrical equipments are, generators, transformers, switching equipments, transmission lines and transmission structures 5. Turbines  The machine which converts hydraulic energy to mechanical energy, and finally to electrical energy 6. Tail race  A channel into which the water is discharged after passing through the turbines 7. Draft tube: - An elongated pipe connecting turbine to tail race
  • 24. Example Problems Example 1: Three turbo-generators each of capacity 10000 kW have been installed at a hydel power station. During a certain period of load, the load on the plant varies from 12000 kW to 26000 kW. Calculate (i) total installed capacity, (ii) load factor, (iii) plant factor and (iv) utilization factor. Example 2 : During a low water week a river has an average daily flow of 32 m3/sec with a fluctuation during the day requiring a pondage capacity of approximately 15% of the daily discharge. a HEP is to be located on the river which will operate 5 days a week, 24 hours a day, but will supply power at varying rate such that the daily load factor is 55% corresponding to which the pondage required is equal to 0.2 times the mean flow to the turbine. On Saturday and Sunday all the flow is ponded for use on rest of the days.
  • 25. Contd. If the effective head on the turbines when the pond is full is to be 25 m and the maximum allowable fluctuation in pond level is 1 m find (a) the surface area of the pond to satisfy all the operating conditions, (b) the weekly output at the switch board in kwh. Assume turbine efficiency 55% and generator efficiency 92%