TAUNTON REGIONAL
WASTE MANAGEMENT FACILITY

        AN OVERVIEW


               Presented by
    Interstate Waste Technologies, Inc.




             February 13, 2012
IWT PROJECT TEAM
• IWT/IBC
  – Selected “Preferred Proposer” by the City
  – Will finance, own and manage the project
  – IBC and related companies have developed projects
    for 50 years – 2012 value $3.5 billion
• Technology Partners
  – Greenstar; Thermoselect; Casale; ExxonMobil
• RTP Environmental
  – Will prepare environmental permits
  – Experienced in permitting waste processing facilities
  – Offices through US

                                                            2
IWT PROJECT TEAM
• CH2M Hill
  – Gasification process engineer
  – Experienced in gasification technology
  – One of the largest engineering companies in US
• SNC Lavalin
  – Top 10 Engineering News Record list of construction
    companies worldwide
  – Will design and construct the facility
  – Will guarantee their work and provide payment and
    performance bonds
  – Involved in 100+ projects worldwide
  – Experienced in designing and building alternative
    fuels projects

                                                          3
IWT PROJECT TEAM
• NAES
   – Operation & Maintenance contractor
   – Operates 130 facilities throughout US
• Project Finance
   – RLR Consultants; Morgan Stanley
   – Experienced in financing infrastructure projects
     including waste to energy facilities
• All team members technically and financially
  qualified to perform their scope of work for the
  Taunton project
• All team members have made presentations to
  representatives of the City and its consultants

                                                        4
INDEPENDENT THIRD PARTY
                 EVALUATION OF
               IWT & TECHNOLOGY
•   The County of Los Angeles commissioned an independently prepared
    comprehensive report to evaluate commercially available non-incineration
    waste processing technologies beginning in 2004

•   URS, our nation’s largest engineering firm prepared the report and
    concluded the following:
     – Based on supplier credibility, existing operational experience,
        completeness of engineering, landfill diversion, permitability and
        economics, IWT and the Thermoselect technology were ranked #1

•   The entire report can be found at IWT’s website: iwtonline.com. Go to the
    About Us page, click on the Independent Third Party Evaluations link.

•   IWT is working with the County to identify a site and waste supply for a
    waste to electricity project of the same size proposed for the Taunton
    project


                                                                                5
INDEPENDENT THIRD PARTY
              EVALUATION OF
            IWT & TECHNOLOGY
• The New York City Economic Development
  Corporation and the Department of Sanitation evaluated
  non incineration waste conversion technologies
  beginning in 2003
• The City’s consultants concluded the following:
   – Based on technology readiness, reliability, facility design,
     environmental performance, beneficial use of waste,
     marketability of recycled products and experience and resources
     of the project sponsor, IWT and the Thermoselect technology
     were judged superior
   – The entire evaluation can be found at IWT’s website:
     iwtonline.com. Go to the About Us page, click on the
     Independent Third Party Evaluations link. Scroll to the NYC
     paragraph and click on green highlighted text “evaluated solid
     waste management technologies”.

                                                                       6
PROJECT DESCRIPTION
• Located on 40 acres at the Myles Standish Industrial
  Park
   – Off John Hancock Road, near Beaver School and old incinerator
   – There will be no waste delivery traffic through the City
• Will process an average of 1,500 tons of waste per day
• Front end recycle about 10%
• Process the balance in five Thermoselect waste
  processing modules
• Produces five recycled products for sale
• Produces synthesis gas comprised of H2 and CO
• Syngas is used to manufacture methanol
• The methanol is used to manufacture gasoline
• Gasoline shipped daily by rail from site
• Permitting 14 -18 months; 2 year construction period
                                                                     7
ENVIRONMENTAL BENEFITS
• 100% of the waste is diverted from landfills
• Waste is 100% recycled
• No ash is produced; no ash landfill is required
• No air emissions are produced from the Thermoselect
  system
• Minimal air emissions from gasoline manufacturing
  equipment
• No process water discharges
• Will reduce greenhouse gas emissions compared to
  landfilling the same quantity of waste
    – USEPA has determined that GHG are harmful to our health

                                                                8
PROVEN TECHNOLOGIES
• Thermoselect Gasification Technology
    – Has processed millions of tons of waste beginning in 1992
    – Has reliably & predictably produced syngas comprised of hydrogen and
      carbon monoxide for 20 years
    – Operating in 7 facilities in Japan with no operational or environmental
      issues
    – Judged proven by every major consultant to the US solid waste industry
• Methanol Manufacturing Technology
    – Has reliably manufactured billions of gallons of methanol from syngas
        • 100+ facilities using syngas produced from reforming natural gas
        • 100+ facilities using syngas produced from gasifying coal
• ExxonMobil Methanol to Gasoline Technology (MTG)
    – Reliably operating since 1985 (27 years)
    – Has produced billions of gallons of gasoline from methanol
    – Will guarantee the quantity and quality of gasoline produced




                                                                                9
PROVEN TECHNOLOGY - THERMOSELECT FONDOTOCE, ITALY DEMO FACILITY – START UP 1992




                                                                                  10
PROVEN TECHNOLOGY


                Projects in Japan




                                    11
1st COMMERCIAL MTG PLANT

      SynGas and
      MeOH Generation                                     MTG




          14,500 BPD plant in New Plymouth New Zealand.
      Plant ownership 75% NZ Government and 25% ExxonMobil.




                                                                12
World’s First Coal to Liquids Plant using MTG

                                      MTG Unit




          • First 2nd generation MTG: JAMG plant in Shanxi
            Province China
          • Start Up; June 2009, 2,500 B/D gasoline

                                                             13
ANALYSIS OF THE
  TAUNTON PROJECT’S TECHNOLOGIES
• Gasification of carbon based materials such as coal or MSW or
  reforming natural gas all produce synthesis gas comprised of
  hydrogen and carbon monoxide
• The synthesis gas is used to manufacture methanol
• The source of the syngas is immaterial to and does not affect the
  operation of the methanol production equipment
• 50% of the syngas for the Taunton project will be produced by
  reforming natural gas
• The other 50% of the syngas will be produced by the Thermoselect
  system which has demonstrated its ability to do so for more than 20
  years
• The two syngas sources will be co-mingled and used to manufacture
  methanol and then gasoline
• This technical approach to manufacturing gasoline has been
  commercially demonstrated for decades



                                                                        14
PROJECTS INCORPORATING
        SIMILAR TECHNOLOGIES
• The US DOE is sponsoring conversion technologies that process
  waste and manufacture alternative fuels
• Projects under development in US and Canada
• A project similar in size to the Taunton project is being developed in
  Alexandria, Louisiana
    – Project Developer is Sundrop Fuels Inc.
    – Will gasify wastes and steam reform natural gas and manufacture about
      50 million gallons of gasoline (the same size as the Taunton project)
    – Has support of Gov. Jindal who has said “The State of Louisiana is
      proud to take this leadership role by providing great careers for our
      people by supplying innovative solutions for the energy bottleneck in
      our nation.”
    – Sundrop Project will employ approximately the same number of people
      as the Taunton project and cost about the same to build
    – Is about one year ahead of the Taunton project in development
• The Sundrop and Taunton projects will reduce our nation’s
  dependence on foreign oil imports – many projects are following

                                                                              15
TAUNTON/IWT BUSINESS MODEL

• IWT, its partners and project team will:
   – Privately finance and permit, design, construct and operate a
     solid waste management facility
   – Operate Taunton’s Drop Off Station
• No City money will be used to finance the project
• City has no risk associated with financing, building or
  operating the facility
• If the waste to gasoline project is delayed, IWT is
  required to build and operate a waste transfer station to
  ensure the City’s waste is managed
• The City responsibilities are to provide a site, its waste
  and support the project
                                                                     16
PROJECT BENEFITS TO CITY
• Receive waste disposal services for a minimum of 30 years at no
  cost (current value is about $1.5 million per year)
• Receive Host Community Fees of about $1.7 million per year for a
  minimum of 30 years
• The value of the above two items, taking escalation into account
  over a 30 year period is about $153 million or an average of $5.1
  million per year
• Receive 1% of IWT’s annual cash flow for at least 30 years
• At financial closing of the project, the City will receive:
    – $2.25 million to cover its project development cost
    – $1 million for an Environmental Fund
• Receive rent payments on the City owned site for 30 years
  beginning at financial closing
• Receive $20,000 per year for the Neighborhood Advisory
  Committee
• Receive $115,000 per year for operations monitoring of the facility


                                                                        17
SUMMARY
• The Taunton project will provide much needed waste disposal
  capacity for southeastern Massachusetts due to the pending closure
  of 4 landfills whose total capacity is about 2,000 tons per day
• The environmental benefits of the project to southeastern
  Massachusetts are significant
• Will reduce foreign oil imports for at least 30 years
• The project will create about 1.2 million man hours of union
  construction work – Will create additional jobs in equipment
  manufacturing facilities in southeastern Massachusetts
• The project will create about 100 well paying jobs for the 30+ years
  the facility will be in operation
• The economic benefits to the City of Taunton are significant
• We urge the public to support the Taunton project and the City
  Council to approve our contract which will allow the Taunton
  project to proceed

                                                                         18
Contact Information


Interstate Waste Technologies
        Frank Campbell
    Phone: 484-288-9589
Email: frankc@iwtonline.com
   Website: iwtonline.com




                                19

Más contenido relacionado

La actualidad más candente

VERDIS Presentation - APR 2015 - CUSTOMER
VERDIS Presentation - APR 2015 - CUSTOMERVERDIS Presentation - APR 2015 - CUSTOMER
VERDIS Presentation - APR 2015 - CUSTOMER
Jorge Gomez
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1
Dan Caouette
 
Earth_Renewed_CNRGH2.1
Earth_Renewed_CNRGH2.1Earth_Renewed_CNRGH2.1
Earth_Renewed_CNRGH2.1
dCORE
 
Bruce LaCour's Resume
Bruce  LaCour's ResumeBruce  LaCour's Resume
Bruce LaCour's Resume
Bruce LaCour
 
R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017
R S Rajaram
 
Mark thomas presentation
Mark thomas presentationMark thomas presentation
Mark thomas presentation
Green17Creative
 
Avoiding extinction Summer School Prague June 2015
Avoiding extinction Summer School Prague June 2015Avoiding extinction Summer School Prague June 2015
Avoiding extinction Summer School Prague June 2015
Graciela Chichilnisky
 

La actualidad más candente (20)

GE Hitachi. Nuclear Innovation
GE Hitachi. Nuclear InnovationGE Hitachi. Nuclear Innovation
GE Hitachi. Nuclear Innovation
 
VERDIS Presentation - APR 2015 - CUSTOMER
VERDIS Presentation - APR 2015 - CUSTOMERVERDIS Presentation - APR 2015 - CUSTOMER
VERDIS Presentation - APR 2015 - CUSTOMER
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1
 
Green Capitalism: India, August 7, 2014
Green Capitalism: India, August 7, 2014Green Capitalism: India, August 7, 2014
Green Capitalism: India, August 7, 2014
 
Earth_Renewed_CNRGH2.1
Earth_Renewed_CNRGH2.1Earth_Renewed_CNRGH2.1
Earth_Renewed_CNRGH2.1
 
Atlantic Council - Victor Der
Atlantic Council - Victor DerAtlantic Council - Victor Der
Atlantic Council - Victor Der
 
Korean Experience in NPP Construction & SMR
Korean Experience in NPP Construction & SMRKorean Experience in NPP Construction & SMR
Korean Experience in NPP Construction & SMR
 
Bruce LaCour's Resume
Bruce  LaCour's ResumeBruce  LaCour's Resume
Bruce LaCour's Resume
 
Norway – a leading role in CCS development
Norway – a leading role in CCS developmentNorway – a leading role in CCS development
Norway – a leading role in CCS development
 
Law presentation
Law presentationLaw presentation
Law presentation
 
Smictom in fougères region-en
Smictom in fougères region-enSmictom in fougères region-en
Smictom in fougères region-en
 
R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017
 
Ranjith cv
Ranjith cvRanjith cv
Ranjith cv
 
Air Capture & Carbon Negative Technology - Graciela Chichilnisky (October 17,...
Air Capture & Carbon Negative Technology - Graciela Chichilnisky (October 17,...Air Capture & Carbon Negative Technology - Graciela Chichilnisky (October 17,...
Air Capture & Carbon Negative Technology - Graciela Chichilnisky (October 17,...
 
Mark thomas presentation
Mark thomas presentationMark thomas presentation
Mark thomas presentation
 
Global Thermostat: A Profitable Solution to Climate Change
Global Thermostat: A Profitable Solution to Climate ChangeGlobal Thermostat: A Profitable Solution to Climate Change
Global Thermostat: A Profitable Solution to Climate Change
 
Avoiding extinction Summer School Prague June 2015
Avoiding extinction Summer School Prague June 2015Avoiding extinction Summer School Prague June 2015
Avoiding extinction Summer School Prague June 2015
 
BATD131-2015
BATD131-2015BATD131-2015
BATD131-2015
 
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...ASHRAE Virtual Design and Construction Conference March 2021- Development of ...
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...
 
The Role of Carbon Removals-Brussels
The Role of Carbon Removals-Brussels The Role of Carbon Removals-Brussels
The Role of Carbon Removals-Brussels
 

Similar a IWT presentation

Alkcon Corporation Summary
Alkcon Corporation SummaryAlkcon Corporation Summary
Alkcon Corporation Summary
Lauren Scott
 
Savigliano - 15° Convegno Europeo CSG
Savigliano - 15° Convegno Europeo CSGSavigliano - 15° Convegno Europeo CSG
Savigliano - 15° Convegno Europeo CSG
Centro Studi Galileo
 
Summit 05 Presentations 13c Sharpe, Vicky
Summit 05   Presentations   13c   Sharpe, VickySummit 05   Presentations   13c   Sharpe, Vicky
Summit 05 Presentations 13c Sharpe, Vicky
bwatson
 
Apec workshop 2 presentation 8 3 vegar apec workshop 8 presentation v4 3.ppt...
Apec workshop 2 presentation 8 3 vegar apec workshop 8  presentation v4 3.ppt...Apec workshop 2 presentation 8 3 vegar apec workshop 8  presentation v4 3.ppt...
Apec workshop 2 presentation 8 3 vegar apec workshop 8 presentation v4 3.ppt...
Global CCS Institute
 
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
irvan septyan mulyana
 
one_page_teaser_
one_page_teaser_one_page_teaser_
one_page_teaser_
Alex Feerer
 
Summit 05 Cd Prestn 11a Sharpe Sdtc
Summit 05   Cd   Prestn   11a   Sharpe SdtcSummit 05   Cd   Prestn   11a   Sharpe Sdtc
Summit 05 Cd Prestn 11a Sharpe Sdtc
bwatson
 
The Natural Gas Revolution
The Natural Gas RevolutionThe Natural Gas Revolution
The Natural Gas Revolution
SFGFinance
 

Similar a IWT presentation (20)

Alkcon Corporation Summary
Alkcon Corporation SummaryAlkcon Corporation Summary
Alkcon Corporation Summary
 
Savigliano - 15° Convegno Europeo CSG
Savigliano - 15° Convegno Europeo CSGSavigliano - 15° Convegno Europeo CSG
Savigliano - 15° Convegno Europeo CSG
 
Circular Economy Thinking in Construction: A view from UK Manufacturers #CETH...
Circular Economy Thinking in Construction: A view from UK Manufacturers #CETH...Circular Economy Thinking in Construction: A view from UK Manufacturers #CETH...
Circular Economy Thinking in Construction: A view from UK Manufacturers #CETH...
 
A New Separation Technology to Process Tantalite Bearing Minerals
A New Separation Technology to Process Tantalite Bearing MineralsA New Separation Technology to Process Tantalite Bearing Minerals
A New Separation Technology to Process Tantalite Bearing Minerals
 
San Angelo’s Use of Renewable Resources
San Angelo’s Use of Renewable ResourcesSan Angelo’s Use of Renewable Resources
San Angelo’s Use of Renewable Resources
 
Cavalline presentation 4 13-10
Cavalline presentation 4 13-10Cavalline presentation 4 13-10
Cavalline presentation 4 13-10
 
-Project professionals: Ready for the future? Climate change, Leigh Woodcock
 -Project professionals: Ready for the future? Climate change, Leigh Woodcock -Project professionals: Ready for the future? Climate change, Leigh Woodcock
-Project professionals: Ready for the future? Climate change, Leigh Woodcock
 
Summit 05 Presentations 13c Sharpe, Vicky
Summit 05   Presentations   13c   Sharpe, VickySummit 05   Presentations   13c   Sharpe, Vicky
Summit 05 Presentations 13c Sharpe, Vicky
 
Apec workshop 2 presentation 8 3 vegar apec workshop 8 presentation v4 3.ppt...
Apec workshop 2 presentation 8 3 vegar apec workshop 8  presentation v4 3.ppt...Apec workshop 2 presentation 8 3 vegar apec workshop 8  presentation v4 3.ppt...
Apec workshop 2 presentation 8 3 vegar apec workshop 8 presentation v4 3.ppt...
 
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
 
Abengoa's Corporate Presentation
Abengoa's Corporate PresentationAbengoa's Corporate Presentation
Abengoa's Corporate Presentation
 
P07 room 2-_habibie_razak_-_indonesia_-managing_the_construction_of_lng_projects
P07 room 2-_habibie_razak_-_indonesia_-managing_the_construction_of_lng_projectsP07 room 2-_habibie_razak_-_indonesia_-managing_the_construction_of_lng_projects
P07 room 2-_habibie_razak_-_indonesia_-managing_the_construction_of_lng_projects
 
one_page_teaser_
one_page_teaser_one_page_teaser_
one_page_teaser_
 
Pulse Energy Webinar: Sustainability in Cities
Pulse Energy Webinar: Sustainability in CitiesPulse Energy Webinar: Sustainability in Cities
Pulse Energy Webinar: Sustainability in Cities
 
Co-processing in cement kiln Concepts and in Oil and Gas Sector | John Jones,...
Co-processing in cement kiln Concepts and in Oil and Gas Sector | John Jones,...Co-processing in cement kiln Concepts and in Oil and Gas Sector | John Jones,...
Co-processing in cement kiln Concepts and in Oil and Gas Sector | John Jones,...
 
Summit 05 Cd Prestn 11a Sharpe Sdtc
Summit 05   Cd   Prestn   11a   Sharpe SdtcSummit 05   Cd   Prestn   11a   Sharpe Sdtc
Summit 05 Cd Prestn 11a Sharpe Sdtc
 
German perez lifes50+ design summary - deep wind 2018
German perez   lifes50+ design summary - deep wind 2018German perez   lifes50+ design summary - deep wind 2018
German perez lifes50+ design summary - deep wind 2018
 
The Natural Gas Revolution
The Natural Gas RevolutionThe Natural Gas Revolution
The Natural Gas Revolution
 
Shell case study: How should ‘Bion Oil’, an oil & gas giant, expand its busin...
Shell case study: How should ‘Bion Oil’, an oil & gas giant, expand its busin...Shell case study: How should ‘Bion Oil’, an oil & gas giant, expand its busin...
Shell case study: How should ‘Bion Oil’, an oil & gas giant, expand its busin...
 
Natural gas
Natural gasNatural gas
Natural gas
 

Último

Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
Nauman Safdar
 

Último (20)

Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur DubaiUAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
 
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
 
Buy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail AccountsBuy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail Accounts
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 Updated
 
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book nowKalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
 

IWT presentation

  • 1. TAUNTON REGIONAL WASTE MANAGEMENT FACILITY AN OVERVIEW Presented by Interstate Waste Technologies, Inc. February 13, 2012
  • 2. IWT PROJECT TEAM • IWT/IBC – Selected “Preferred Proposer” by the City – Will finance, own and manage the project – IBC and related companies have developed projects for 50 years – 2012 value $3.5 billion • Technology Partners – Greenstar; Thermoselect; Casale; ExxonMobil • RTP Environmental – Will prepare environmental permits – Experienced in permitting waste processing facilities – Offices through US 2
  • 3. IWT PROJECT TEAM • CH2M Hill – Gasification process engineer – Experienced in gasification technology – One of the largest engineering companies in US • SNC Lavalin – Top 10 Engineering News Record list of construction companies worldwide – Will design and construct the facility – Will guarantee their work and provide payment and performance bonds – Involved in 100+ projects worldwide – Experienced in designing and building alternative fuels projects 3
  • 4. IWT PROJECT TEAM • NAES – Operation & Maintenance contractor – Operates 130 facilities throughout US • Project Finance – RLR Consultants; Morgan Stanley – Experienced in financing infrastructure projects including waste to energy facilities • All team members technically and financially qualified to perform their scope of work for the Taunton project • All team members have made presentations to representatives of the City and its consultants 4
  • 5. INDEPENDENT THIRD PARTY EVALUATION OF IWT & TECHNOLOGY • The County of Los Angeles commissioned an independently prepared comprehensive report to evaluate commercially available non-incineration waste processing technologies beginning in 2004 • URS, our nation’s largest engineering firm prepared the report and concluded the following: – Based on supplier credibility, existing operational experience, completeness of engineering, landfill diversion, permitability and economics, IWT and the Thermoselect technology were ranked #1 • The entire report can be found at IWT’s website: iwtonline.com. Go to the About Us page, click on the Independent Third Party Evaluations link. • IWT is working with the County to identify a site and waste supply for a waste to electricity project of the same size proposed for the Taunton project 5
  • 6. INDEPENDENT THIRD PARTY EVALUATION OF IWT & TECHNOLOGY • The New York City Economic Development Corporation and the Department of Sanitation evaluated non incineration waste conversion technologies beginning in 2003 • The City’s consultants concluded the following: – Based on technology readiness, reliability, facility design, environmental performance, beneficial use of waste, marketability of recycled products and experience and resources of the project sponsor, IWT and the Thermoselect technology were judged superior – The entire evaluation can be found at IWT’s website: iwtonline.com. Go to the About Us page, click on the Independent Third Party Evaluations link. Scroll to the NYC paragraph and click on green highlighted text “evaluated solid waste management technologies”. 6
  • 7. PROJECT DESCRIPTION • Located on 40 acres at the Myles Standish Industrial Park – Off John Hancock Road, near Beaver School and old incinerator – There will be no waste delivery traffic through the City • Will process an average of 1,500 tons of waste per day • Front end recycle about 10% • Process the balance in five Thermoselect waste processing modules • Produces five recycled products for sale • Produces synthesis gas comprised of H2 and CO • Syngas is used to manufacture methanol • The methanol is used to manufacture gasoline • Gasoline shipped daily by rail from site • Permitting 14 -18 months; 2 year construction period 7
  • 8. ENVIRONMENTAL BENEFITS • 100% of the waste is diverted from landfills • Waste is 100% recycled • No ash is produced; no ash landfill is required • No air emissions are produced from the Thermoselect system • Minimal air emissions from gasoline manufacturing equipment • No process water discharges • Will reduce greenhouse gas emissions compared to landfilling the same quantity of waste – USEPA has determined that GHG are harmful to our health 8
  • 9. PROVEN TECHNOLOGIES • Thermoselect Gasification Technology – Has processed millions of tons of waste beginning in 1992 – Has reliably & predictably produced syngas comprised of hydrogen and carbon monoxide for 20 years – Operating in 7 facilities in Japan with no operational or environmental issues – Judged proven by every major consultant to the US solid waste industry • Methanol Manufacturing Technology – Has reliably manufactured billions of gallons of methanol from syngas • 100+ facilities using syngas produced from reforming natural gas • 100+ facilities using syngas produced from gasifying coal • ExxonMobil Methanol to Gasoline Technology (MTG) – Reliably operating since 1985 (27 years) – Has produced billions of gallons of gasoline from methanol – Will guarantee the quantity and quality of gasoline produced 9
  • 10. PROVEN TECHNOLOGY - THERMOSELECT FONDOTOCE, ITALY DEMO FACILITY – START UP 1992 10
  • 11. PROVEN TECHNOLOGY Projects in Japan 11
  • 12. 1st COMMERCIAL MTG PLANT SynGas and MeOH Generation MTG 14,500 BPD plant in New Plymouth New Zealand. Plant ownership 75% NZ Government and 25% ExxonMobil. 12
  • 13. World’s First Coal to Liquids Plant using MTG MTG Unit • First 2nd generation MTG: JAMG plant in Shanxi Province China • Start Up; June 2009, 2,500 B/D gasoline 13
  • 14. ANALYSIS OF THE TAUNTON PROJECT’S TECHNOLOGIES • Gasification of carbon based materials such as coal or MSW or reforming natural gas all produce synthesis gas comprised of hydrogen and carbon monoxide • The synthesis gas is used to manufacture methanol • The source of the syngas is immaterial to and does not affect the operation of the methanol production equipment • 50% of the syngas for the Taunton project will be produced by reforming natural gas • The other 50% of the syngas will be produced by the Thermoselect system which has demonstrated its ability to do so for more than 20 years • The two syngas sources will be co-mingled and used to manufacture methanol and then gasoline • This technical approach to manufacturing gasoline has been commercially demonstrated for decades 14
  • 15. PROJECTS INCORPORATING SIMILAR TECHNOLOGIES • The US DOE is sponsoring conversion technologies that process waste and manufacture alternative fuels • Projects under development in US and Canada • A project similar in size to the Taunton project is being developed in Alexandria, Louisiana – Project Developer is Sundrop Fuels Inc. – Will gasify wastes and steam reform natural gas and manufacture about 50 million gallons of gasoline (the same size as the Taunton project) – Has support of Gov. Jindal who has said “The State of Louisiana is proud to take this leadership role by providing great careers for our people by supplying innovative solutions for the energy bottleneck in our nation.” – Sundrop Project will employ approximately the same number of people as the Taunton project and cost about the same to build – Is about one year ahead of the Taunton project in development • The Sundrop and Taunton projects will reduce our nation’s dependence on foreign oil imports – many projects are following 15
  • 16. TAUNTON/IWT BUSINESS MODEL • IWT, its partners and project team will: – Privately finance and permit, design, construct and operate a solid waste management facility – Operate Taunton’s Drop Off Station • No City money will be used to finance the project • City has no risk associated with financing, building or operating the facility • If the waste to gasoline project is delayed, IWT is required to build and operate a waste transfer station to ensure the City’s waste is managed • The City responsibilities are to provide a site, its waste and support the project 16
  • 17. PROJECT BENEFITS TO CITY • Receive waste disposal services for a minimum of 30 years at no cost (current value is about $1.5 million per year) • Receive Host Community Fees of about $1.7 million per year for a minimum of 30 years • The value of the above two items, taking escalation into account over a 30 year period is about $153 million or an average of $5.1 million per year • Receive 1% of IWT’s annual cash flow for at least 30 years • At financial closing of the project, the City will receive: – $2.25 million to cover its project development cost – $1 million for an Environmental Fund • Receive rent payments on the City owned site for 30 years beginning at financial closing • Receive $20,000 per year for the Neighborhood Advisory Committee • Receive $115,000 per year for operations monitoring of the facility 17
  • 18. SUMMARY • The Taunton project will provide much needed waste disposal capacity for southeastern Massachusetts due to the pending closure of 4 landfills whose total capacity is about 2,000 tons per day • The environmental benefits of the project to southeastern Massachusetts are significant • Will reduce foreign oil imports for at least 30 years • The project will create about 1.2 million man hours of union construction work – Will create additional jobs in equipment manufacturing facilities in southeastern Massachusetts • The project will create about 100 well paying jobs for the 30+ years the facility will be in operation • The economic benefits to the City of Taunton are significant • We urge the public to support the Taunton project and the City Council to approve our contract which will allow the Taunton project to proceed 18
  • 19. Contact Information Interstate Waste Technologies Frank Campbell Phone: 484-288-9589 Email: frankc@iwtonline.com Website: iwtonline.com 19