SlideShare una empresa de Scribd logo
1 de 10
© 2013 Chevron
TTA CY Spool Installation
DMAIC Control Phase Gate
Michael Anthony
Michael Job
TTA-MCK
June 2015
© 2014 Chevron
Problem Statement
 Over the past 3 years in Cymric, failures in Check Valves at Gauge
Setting slots have been leading to pipe wall erosion loss, causing
pipes to leak thus creating environmental and safety concerns for
operations, while also leading to down oil and maintenance cost, a
minimum of about $1500 per failure leak.
2
© 2014 Chevron
Project Background
 CVX / KSI are required to change out existing check valves to pipe
spools on all active Diatomite wells in TTA-MCK.
 List was created of existing check valves on gauge setting slots that
needed to be changed.
 Project handed to KSI Maintenance for installation of pipe spools.
 CVX required to take well off production for spool installation.
Scheduling work with existing well shutdowns avoids doubling downoil
3
© 2014 Chevron
IPO
4
+
Low
0
KSI Crews,API
Spools Complete,Down Oil
Spools
Choke Inspection Queue
Outputs
Inputs
Process:
Spool Installation
Goal
Down Oil
($/barrel)
Safety
(TRIR)
Weather
Check Valves:
Sell / Return for
refurbishment
© 2014 Chevron
Current State
 Spool installations scheduled for maintenance crews to do individually
based off issued work-orders for each well
 Well isolated previous to each scheduled installation
 KSI crew mobilize, issued permits, isolate / loto, and demobilize for
each spool installation
5
© 2014 Chevron
Future State
 Spool installation added on to choke / temperature inspections or
other Maintenance work occurring on wells that need spool
installations
6
© 2014 Chevron
Sustainability / Scalability
Sustainability
 KSI / CVX continue to identify opportunities to eliminate redundant
work
 Spool installations continue to be scheduled with other maintenance
work to avoid double isolation and well downtime
 When Diatomite inactive slots are brought back online check valves
are replaced
Scalability
 All CVX operations examine scheduled work and how to best
combine existing work to eliminate isolation and well downtime
 Combine PM’s, Repairs, Maintenance / Construction Work that have
the same isolation points or permits issued
7
© 2013 Chevron
Financial Verification
8
Month
1. Spools
Installed
2. Capital
Avoidance
3. Oil LS Price 4. Barrels Saved
5. Down Oil
Avoidance
6. Valve
Refurbishment / Sale
7. Total Per
Month
8. AFB
November 2 325.60$ 56.15$ 52 2,901.3$ 3,226.9$ 3,283.0$
December 16 2,604.80$ 36.30$ 413 14,984.6$ 17,589.4$ 20,872.5$
January 18 2,930.40$ 29.30$ 465 13,624.5$ 16,554.9$ 37,427.4$
February 14 2,279.20$ 35.67$ 362 12,898.90$ 15,178.1$ 52,605.5$
March 8 1,302.40$ 31.77$ 207 6,565.80$ 7,868.2$ 60,473.7$
April 6 976.80$ 41.50$ 155 6,432.50$ 7,409.3$ 67,883.0$
May
June
July 58,498.20$ 58,498.20$ 126,381.16$
August
September
October
November
December
January
(8) AFB: Project Total
(1) Spools Installed: Monitored by KSI Superintendent, reported installations based off workorders complete
(3) LS Oil Price: Based off CVX LS monthly oil price
(4) Barrels Saved:
Assumptions
(5) Down Oil Avoidance: Oil LS Price xBarrels Saved = Down Oil Avoidance
(7) Total Per Month: Capital Avoidance + Down Oil Avoidance
© 2013 Chevron
Non-AFB Verification
9
CATEGORY METRIC METRIC BASELINE AFTER IMPROVEMENT Unit of Measure
HES At risk behaviors Workers' Compensation Costs Hours
Touch Points Loss of Containment
Distance Driven Compliance Rate
Risk Exposure TRIR
Risk Exposure inference Rate DAFWR
Time Between Motor Vehicle Crash First Aids
Risk Priority Number Near Misses
CATEGORY METRIC METRIC BASELINE AFTER IMPROVEMENT Unit of Measure
Quality Turn over rate Sigma level Percentage
Unplanned Absenteeism Rate First Pass Yield
Ideas Generated Mean Time to Repair
Personnel Participating Mean Time Between Failure
Tool Utilization Preventive Maintenance
Standard Operating Procedures Handoffs
Cp: Potential Process Capability Decision / Approval Points
Cpk: Actual Process Capability Recycles / Rework
Reliability Standardization
Availability Proportion Defective
CATEGORY METRIC METRIC BASELINE AFTER IMPROVEMENT Unit of Measure
Time Cycle Time Non-value Added Process Steps Hours
Wait Time Value Added Time Rate
Man Hours Operational Effectiveness Rate
1 HR Per Spool
Isolation
0 HR Per Spool Isolation
Total # of Check Valves
Installed x1 HR
Turnaround Time Production Acceleration
Overtime Lead Time
Throughput time Process Cycle Efficiency
CATEGORY METRIC METRIC BASELINE AFTER IMPROVEMENT Unit of Measure
Cost Implied Future Value Early Payment Discount Hours
Labor Productivity Space Utilization
Cost Per Transaction Full Time Equivalent (FTE) Value
Assumptions
Total of 192 Spools must be replaced 1 HR x 192 Spools
© 2013 Chevron
SJVBU Lean Sigma Project Summary for Adoption Sharing
Before:
 Check valves are required to
be replaced with spools
 Spools installations
scheduled and installed
After:
 Spools installed with other well
and gauge setting shutdowns
 Spools installed with choke
inspections
 1 hr. gain in time required to
install spool with process.
10
Lessons Learned, Predicted AFB, and Scalability Summary:
• Lessons Learned: Communication between foreman and engineers enables combination of
work to avoid additional shutdowns
• AFB: $150,000
• Scalability: Combining work through-out departments and between foreman
Graphic(s) or Picture(s):
Before
After

Más contenido relacionado

La actualidad más candente

Innovation Proj PVC Paste TeraHertz
Innovation Proj PVC Paste TeraHertzInnovation Proj PVC Paste TeraHertz
Innovation Proj PVC Paste TeraHertz
Raymond Shen
 
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATIONNRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
Elliott Molnar
 
Unlocking slide after flattening 5-20
Unlocking slide after flattening 5-20Unlocking slide after flattening 5-20
Unlocking slide after flattening 5-20
John Zill
 

La actualidad más candente (10)

Partial Repowering of Wind Turbines: technical risks, opportunities and trends
Partial Repowering of Wind Turbines: technical risks, opportunities and trendsPartial Repowering of Wind Turbines: technical risks, opportunities and trends
Partial Repowering of Wind Turbines: technical risks, opportunities and trends
 
OpenText Live: Modeling your business processes to new ways of working
OpenText Live: Modeling your business processes to new ways of workingOpenText Live: Modeling your business processes to new ways of working
OpenText Live: Modeling your business processes to new ways of working
 
RAT
RATRAT
RAT
 
Innovation Proj PVC Paste TeraHertz
Innovation Proj PVC Paste TeraHertzInnovation Proj PVC Paste TeraHertz
Innovation Proj PVC Paste TeraHertz
 
Zeco slide show brochure
Zeco slide show brochureZeco slide show brochure
Zeco slide show brochure
 
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATIONNRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
 
Zeco
Zeco Zeco
Zeco
 
Zeco Brochure
Zeco BrochureZeco Brochure
Zeco Brochure
 
iFluids Lean Six Sigma Case Study oil & gas
iFluids Lean Six Sigma Case Study oil & gasiFluids Lean Six Sigma Case Study oil & gas
iFluids Lean Six Sigma Case Study oil & gas
 
Unlocking slide after flattening 5-20
Unlocking slide after flattening 5-20Unlocking slide after flattening 5-20
Unlocking slide after flattening 5-20
 

Similar a 8. DMAIC Control Phase Gate - Spool Installation

Andrew Chant\'s CanWEA O & M Presentation
Andrew Chant\'s CanWEA  O  & M  PresentationAndrew Chant\'s CanWEA  O  & M  Presentation
Andrew Chant\'s CanWEA O & M Presentation
mtingle
 
Winter Newsletter 1.12.16
Winter Newsletter 1.12.16Winter Newsletter 1.12.16
Winter Newsletter 1.12.16
fidge72
 
Storyboard_SPS_Payroll
Storyboard_SPS_PayrollStoryboard_SPS_Payroll
Storyboard_SPS_Payroll
Balaguru SP
 
BW-WhentoCleanAirCondensers-WhitePaper
BW-WhentoCleanAirCondensers-WhitePaperBW-WhentoCleanAirCondensers-WhitePaper
BW-WhentoCleanAirCondensers-WhitePaper
Dennis Miller
 
How to Instill a Culture of Reliability - "The Big Bang"
How to Instill a Culture of Reliability - "The Big Bang"How to Instill a Culture of Reliability - "The Big Bang"
How to Instill a Culture of Reliability - "The Big Bang"
ARMS Reliability
 
presentacion OEE para la gestion de flota en mina
presentacion OEE para la gestion de flota en minapresentacion OEE para la gestion de flota en mina
presentacion OEE para la gestion de flota en mina
ALVAROALEJANDROANGUL
 
FC VSM Presentation Future State Aug 5 -7 2013
FC VSM Presentation Future State Aug 5 -7  2013FC VSM Presentation Future State Aug 5 -7  2013
FC VSM Presentation Future State Aug 5 -7 2013
Donna Skala
 
EECO2 GMP critical HVAC energy cost reduction
EECO2 GMP critical HVAC energy cost reductionEECO2 GMP critical HVAC energy cost reduction
EECO2 GMP critical HVAC energy cost reduction
Keith Beattie
 

Similar a 8. DMAIC Control Phase Gate - Spool Installation (20)

A practical approach to pharmaceutical HVAC energy reduction
A practical approach to pharmaceutical HVAC energy reductionA practical approach to pharmaceutical HVAC energy reduction
A practical approach to pharmaceutical HVAC energy reduction
 
Maintenance
MaintenanceMaintenance
Maintenance
 
Combi Systems: Lessons Learned from the Field
Combi Systems: Lessons Learned from the FieldCombi Systems: Lessons Learned from the Field
Combi Systems: Lessons Learned from the Field
 
Andrew Chant\'s CanWEA O & M Presentation
Andrew Chant\'s CanWEA  O  & M  PresentationAndrew Chant\'s CanWEA  O  & M  Presentation
Andrew Chant\'s CanWEA O & M Presentation
 
TPCIL VIVEK
TPCIL VIVEKTPCIL VIVEK
TPCIL VIVEK
 
Expansion of-water-treatment-plant
Expansion of-water-treatment-plantExpansion of-water-treatment-plant
Expansion of-water-treatment-plant
 
Winter Newsletter 1.12.16
Winter Newsletter 1.12.16Winter Newsletter 1.12.16
Winter Newsletter 1.12.16
 
Transition to online AMS reduces maintenance costs and improves operations
Transition to online AMS reduces maintenance costs and improves operationsTransition to online AMS reduces maintenance costs and improves operations
Transition to online AMS reduces maintenance costs and improves operations
 
Re con
Re conRe con
Re con
 
Storyboard_SPS_Payroll
Storyboard_SPS_PayrollStoryboard_SPS_Payroll
Storyboard_SPS_Payroll
 
BW-WhentoCleanAirCondensers-WhitePaper
BW-WhentoCleanAirCondensers-WhitePaperBW-WhentoCleanAirCondensers-WhitePaper
BW-WhentoCleanAirCondensers-WhitePaper
 
How to Instill a Culture of Reliability - "The Big Bang"
How to Instill a Culture of Reliability - "The Big Bang"How to Instill a Culture of Reliability - "The Big Bang"
How to Instill a Culture of Reliability - "The Big Bang"
 
CD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseCD 2016 March - Advisian Showcase
CD 2016 March - Advisian Showcase
 
Overall Equipment.pdf
Overall Equipment.pdfOverall Equipment.pdf
Overall Equipment.pdf
 
presentacion OEE para la gestion de flota en mina
presentacion OEE para la gestion de flota en minapresentacion OEE para la gestion de flota en mina
presentacion OEE para la gestion de flota en mina
 
OEE Training PPT for analize machine performance.pdf
OEE Training PPT for analize machine performance.pdfOEE Training PPT for analize machine performance.pdf
OEE Training PPT for analize machine performance.pdf
 
FC VSM Presentation Future State Aug 5 -7 2013
FC VSM Presentation Future State Aug 5 -7  2013FC VSM Presentation Future State Aug 5 -7  2013
FC VSM Presentation Future State Aug 5 -7 2013
 
An introduction to EECO2-Energy Efficiency Consultancy Limited
An introduction to EECO2-Energy Efficiency Consultancy LimitedAn introduction to EECO2-Energy Efficiency Consultancy Limited
An introduction to EECO2-Energy Efficiency Consultancy Limited
 
EECO2 GMP critical HVAC energy cost reduction
EECO2 GMP critical HVAC energy cost reductionEECO2 GMP critical HVAC energy cost reduction
EECO2 GMP critical HVAC energy cost reduction
 
Duke Energy - Case Study
Duke Energy - Case StudyDuke Energy - Case Study
Duke Energy - Case Study
 

8. DMAIC Control Phase Gate - Spool Installation

  • 1. © 2013 Chevron TTA CY Spool Installation DMAIC Control Phase Gate Michael Anthony Michael Job TTA-MCK June 2015
  • 2. © 2014 Chevron Problem Statement  Over the past 3 years in Cymric, failures in Check Valves at Gauge Setting slots have been leading to pipe wall erosion loss, causing pipes to leak thus creating environmental and safety concerns for operations, while also leading to down oil and maintenance cost, a minimum of about $1500 per failure leak. 2
  • 3. © 2014 Chevron Project Background  CVX / KSI are required to change out existing check valves to pipe spools on all active Diatomite wells in TTA-MCK.  List was created of existing check valves on gauge setting slots that needed to be changed.  Project handed to KSI Maintenance for installation of pipe spools.  CVX required to take well off production for spool installation. Scheduling work with existing well shutdowns avoids doubling downoil 3
  • 4. © 2014 Chevron IPO 4 + Low 0 KSI Crews,API Spools Complete,Down Oil Spools Choke Inspection Queue Outputs Inputs Process: Spool Installation Goal Down Oil ($/barrel) Safety (TRIR) Weather Check Valves: Sell / Return for refurbishment
  • 5. © 2014 Chevron Current State  Spool installations scheduled for maintenance crews to do individually based off issued work-orders for each well  Well isolated previous to each scheduled installation  KSI crew mobilize, issued permits, isolate / loto, and demobilize for each spool installation 5
  • 6. © 2014 Chevron Future State  Spool installation added on to choke / temperature inspections or other Maintenance work occurring on wells that need spool installations 6
  • 7. © 2014 Chevron Sustainability / Scalability Sustainability  KSI / CVX continue to identify opportunities to eliminate redundant work  Spool installations continue to be scheduled with other maintenance work to avoid double isolation and well downtime  When Diatomite inactive slots are brought back online check valves are replaced Scalability  All CVX operations examine scheduled work and how to best combine existing work to eliminate isolation and well downtime  Combine PM’s, Repairs, Maintenance / Construction Work that have the same isolation points or permits issued 7
  • 8. © 2013 Chevron Financial Verification 8 Month 1. Spools Installed 2. Capital Avoidance 3. Oil LS Price 4. Barrels Saved 5. Down Oil Avoidance 6. Valve Refurbishment / Sale 7. Total Per Month 8. AFB November 2 325.60$ 56.15$ 52 2,901.3$ 3,226.9$ 3,283.0$ December 16 2,604.80$ 36.30$ 413 14,984.6$ 17,589.4$ 20,872.5$ January 18 2,930.40$ 29.30$ 465 13,624.5$ 16,554.9$ 37,427.4$ February 14 2,279.20$ 35.67$ 362 12,898.90$ 15,178.1$ 52,605.5$ March 8 1,302.40$ 31.77$ 207 6,565.80$ 7,868.2$ 60,473.7$ April 6 976.80$ 41.50$ 155 6,432.50$ 7,409.3$ 67,883.0$ May June July 58,498.20$ 58,498.20$ 126,381.16$ August September October November December January (8) AFB: Project Total (1) Spools Installed: Monitored by KSI Superintendent, reported installations based off workorders complete (3) LS Oil Price: Based off CVX LS monthly oil price (4) Barrels Saved: Assumptions (5) Down Oil Avoidance: Oil LS Price xBarrels Saved = Down Oil Avoidance (7) Total Per Month: Capital Avoidance + Down Oil Avoidance
  • 9. © 2013 Chevron Non-AFB Verification 9 CATEGORY METRIC METRIC BASELINE AFTER IMPROVEMENT Unit of Measure HES At risk behaviors Workers' Compensation Costs Hours Touch Points Loss of Containment Distance Driven Compliance Rate Risk Exposure TRIR Risk Exposure inference Rate DAFWR Time Between Motor Vehicle Crash First Aids Risk Priority Number Near Misses CATEGORY METRIC METRIC BASELINE AFTER IMPROVEMENT Unit of Measure Quality Turn over rate Sigma level Percentage Unplanned Absenteeism Rate First Pass Yield Ideas Generated Mean Time to Repair Personnel Participating Mean Time Between Failure Tool Utilization Preventive Maintenance Standard Operating Procedures Handoffs Cp: Potential Process Capability Decision / Approval Points Cpk: Actual Process Capability Recycles / Rework Reliability Standardization Availability Proportion Defective CATEGORY METRIC METRIC BASELINE AFTER IMPROVEMENT Unit of Measure Time Cycle Time Non-value Added Process Steps Hours Wait Time Value Added Time Rate Man Hours Operational Effectiveness Rate 1 HR Per Spool Isolation 0 HR Per Spool Isolation Total # of Check Valves Installed x1 HR Turnaround Time Production Acceleration Overtime Lead Time Throughput time Process Cycle Efficiency CATEGORY METRIC METRIC BASELINE AFTER IMPROVEMENT Unit of Measure Cost Implied Future Value Early Payment Discount Hours Labor Productivity Space Utilization Cost Per Transaction Full Time Equivalent (FTE) Value Assumptions Total of 192 Spools must be replaced 1 HR x 192 Spools
  • 10. © 2013 Chevron SJVBU Lean Sigma Project Summary for Adoption Sharing Before:  Check valves are required to be replaced with spools  Spools installations scheduled and installed After:  Spools installed with other well and gauge setting shutdowns  Spools installed with choke inspections  1 hr. gain in time required to install spool with process. 10 Lessons Learned, Predicted AFB, and Scalability Summary: • Lessons Learned: Communication between foreman and engineers enables combination of work to avoid additional shutdowns • AFB: $150,000 • Scalability: Combining work through-out departments and between foreman Graphic(s) or Picture(s): Before After