PM Challenge 2012



                            Right Sizing Your
                            Project/Program
                           Design Review Plan

                            PM Challenge 2012


                          Charles Armstrong
 Focus on the Objective   National Aeronautics and Space Administration
                          Orion VIO SE&I Plans & Processes Manager
                          charles.h.armstrong@nasa.gov
                          281-244-6315

                          Tony Byers
                          Lockheed Martin Space Systems Company
                          Software Systems & Data Sr. Manager
                          anthony.w.byers@lmco.com
                          303-977-4389

Evolve and Excel
Agenda

• Introduction
• Program/Project Design Review Approach
    • Planning
    • Technical & Peer Reviews
    • Component Design Reviews
    • Subsystem Design Reviews
    • System Level Reviews
    • Boards & Panels

• Summary
    • Affordability
    • Time-line Comparison
    • Conclusion

• Closing Remarks
                                           2
Right Sizing Your Design
 PM Challenge 2012                         Review Plan




                          Introduction


 Focus on the Objective




Evolve and Excel
Introduction

•    Presentation Focus:
      •    Historically, NASA major milestone reviews have been conducted by allowing participation
           by a large number of agency personnel.
            • Review a wide range of materials
            • Write a large number of candidate issues in the form of RIDs
                  • Very expensive
                  • Significant infrastructure and logistics
                  • Large effort to review, disposition, and close

      •    Using the lessons learned from previous Programs/Projects a streamlined integrated
           approach to conducting major design reviews is proposed.
            • Recognizes ongoing insight/oversight as part of the design review plan
            • Expands the use of lower level design reviews (Design products / documentation
                Tech/Peer Reviews, Component Reviews, and Subsystem Reviews)
                  • Uses highly qualified personnel - Limits participation to individuals with an
                      identified ability to make a value-added contribution
                  • Changes the way issues are identified and vetted

      If successful, this methodology will reduce the cost of conducting major milestone reviews and set the new
    4
                          standard for the conduct of major milestone reviews within the agency.
Management Challenges

• Planning Challenges
    – Develop and execute a program/project technical life-cycle review
      (SRR, SDR, PDR, CDR) process that ensures NASA’s next generation products can
      meet all mission objectives and satisfy requirements with acceptable risk
    – Develop a multi-tiered approach that ensures the integrated system
      (components, subsystems, system) is reviewed to ensure the design approach is at a
      sufficient level of maturity to proceed to the next life-cycle phase.
    – Maintain an eye on affordability
        – Balance thoroughness and schedule. The desire to review every aspect of the
          design down to the lowest possible level must be balanced against the available
          time to execute the review as to not delay the development activities
          unnecessarily.
        – Balance inclusion and efficiency. Develop a process that ensures all
          stakeholders have an adequate time to participate and provide input helping to
          shape the design, ensure mission success, and ultimately provide a safe crew
          exploration vehicle.

                                                                                            5
Management Challenges

• Execution Challenges
    – Communicate the expectations to an often diverse personnel organization consisting
      of NASA, prime contractor, and many support contractors
    – Balance the desire to improve the design with the need to efficiently transition to the
      next life-cycle phase
        – From the time a baseline is struck, a lot of potential energy develops to revisit
          the requirements (did we miss something?) and improve the design (could it be
          better?)
             – This energy must be managed to ensure that identified issues and design
               refinement are necessary to ensure mission success (including crew safety
               for human spaceflight) and not simply to resolve an “I would have did it
               differently” comment
             – Review products must align as closely as possible to the baseline
    – Monitor and control process execution throughout the duration of the effort



                                                                                                6
Right Sizing Your Design
 PM Challenge 2012                                   Review Plan




                          Program/Project Design
                             Review Approach
                            • Planning
                            • Technical & Peer Reviews
                            • Component Design Reviews
                            • Subsystem Design Reviews
 Focus on the Objective
                            • System Level Reviews
                            • Boards & Panels




Evolve and Excel
Design Review Planning
•   Form a review integration team
     – Identify and assign a manager to lead the major design review (NASA & Prime
       Contractor)
     – Identify a lead from each IPT
     – Identify key participants from other groups (Planning, Configuration & Data
       Management, Subcontracts, etc.)
     – Ensure joint NASA/Prime Contractor support in each area, where possible

•   Define review
     – Review NASA / Industry review guidance
     – Review program documentation
          • Statement of Objectives, Statement of Work, Systems Engineering Management Plan, etc.
     – Define review scope
          • Baselines (Technical, Schedule, & Cost)
          • Level of penetration (Component, Subsystem, System)        Be cognizant of the applicable
     – Define review objectives                                        program / project phase
     – Define Entry and Success Criteria
Design Review Planning
•   Develop the detailed review process
     – Include how each review is supposed to be executed
     – Include how issues are recorded, communicated, tracked, and closed
         • Increase formality as you increase integration
              – Technical / Peer reviews – lower formality
              – Subsystem & System level reviews – increased formality (RIDs, etc.)
         • Ensure open issues can move from review to review to minimize duplication


•   Define Review Participants
     – Determine Chair(s)
     – Define roles and responsibilities (Chairs, Reviewers, Program/Project Team, etc.)
     – Include Program/Project leadership
     – Include external stakeholders in component level reviews (other interfacing
       components, subsystems, etc.)
     – Include external stakeholders in Subsystem and System level reviews
       (Engineering, Safety, Crew office, Mission Operations, other NASA Centers, etc.)
     – Include independent reviewers (especially important as you progress to subsystem and
       system level reviews where SRB participation is expected)
Design Review Planning

• Develop detailed schedule
   – Include all lower level reviews that are determined to be a part of the overall major
     milestone design review process
        • Example: Orion included technical / peer reviews for PDR products, Subsystem Design
          Reviews, and System Level Reviews
   – Include all products that are determined to make up the review data package
        • Example: Requirements, Plans, Drawings, CAD Models, Design Data Books, etc.
   – Incorporate dependencies where possible
        • Example: Component PDRs required to be completed and products needing to be
          developed prior to a subsystem design review
   – Ensure owners of all products and reviews are identified (NASA & Contractor)
   – Develop a process to ensure schedule is updated / managed
   – Develop the list of metrics / reports that will be utilized to track performance
Design Review Planning

• Document the plan
  • Formalize the overall review process
       • All significant stakeholders
         organizations will participate in review
         of document prior to release
       • Ensures leadership has agreed to plan
  • Document the requirements and
    associated documentation baseline for
    review
  • Incorporate NPR 7123.1A criteria into
    plan (including any tailoring)
  • Serves as the primary method of
    documenting all agreements regarding
    method to meet the review criteria
  • Place under configuration control
  • Use as a reference throughout the
    execution to ensure the process is
    adhered to
                                                    11
Right Sizing Your Design
 PM Challenge 2012                                    Review Plan




                          Program/Project Design
                             Review Approach
                            • Planning
                            • Technical / Peer Reviews
                            • Component Design Reviews
                            • Subsystem Design Reviews
 Focus on the Objective
                            • System Level Reviews
                            • Boards & Panels




Evolve and Excel
Technical / Peer Reviews
•        A significant amount of oversight occurs throughout the life-cycle of the project
          – This interaction serves to familiarize the reviewers with the lower level details and provides an
            opportunity to identify and resolve issues early in the review process


•        Technical / Peer reviews provide an opportunity to perform technical assessment and to
         focus content for the next tier of reviews (Component, Subsystem, & System PDRs/CDRs)

•        Technical / Peer Review Purpose / Objectives
          – NASA and Contractor Subject Matter Experts (SMEs) assess the technical progress and quality of
            design related products (could be a DRD or parts of a DRD)
          – Work to identify and solve design, document, process issues
          – Ensure the Product accurately represents the appropriate baseline configuration / architecture
          – Ensure the Product fulfills the DRD Description provided by NASA
          – Provides joint NASA/Contractor forum with Intra-Subsystem and Cross-Subsystem Participation
          – Serves as a foundational review supporting follow-on reviews that culminate in a successful design
            life-cycle milestone review – Iterative when required




    13
            Tech Reviews are “Roll up the sleeves” reviews of the products that support or represent the design
Technical / Peer Reviews
•   Key Lessons Learned
     – Enhance Technical Reviews of the design work products and ensure correct participation
           • Consistency of technical review process important – tracking of issues / conduct of review
     – Identify the tech review of most importance – i.e. Design Data Books provide an opportunity
       to review the design at the subsystem level prior to a Subsystem PDR/CDR
     – Provide TR participants the data product(s) 5 to 10 days prior to the review
     – Ensure review dates are documented in a easily accessible integrated schedule
           • Work to deconflict schedules where possible to ensure appropriate participation
     – Identify minimum required stakeholders for a successful TR
           • TRs must be given high priority by each appropriate organization
                 – Be willing to reschedule the review if the right personnel cannot attend
           • Appropriate SMEs are expected to support DRD TRs
     – For all contractor developed DRDs, assign a NASA POC to ensure stakeholder selection is
       correct and the work product receives adequate review
           • Official delivery to NASA occurs after the TR/PR


    Orion conducted 316 Technical / Peer Reviews for 224 PDR Data Package Products. Reviews were successful
     in identifying and resolving many issues. However, open review findings were not rolled up to higher level
       reviews. Thus creating significant duplication of actions / RIDs in Subsystem and System level reviews.
Right Sizing Your Design
 PM Challenge 2012                                   Review Plan




                          Program/Project Design
                             Review Approach
                            • Planning
                            • Technical & Peer Reviews
                            • Component Design Reviews
                            • Subsystem Design Reviews
 Focus on the Objective
                            • System Level Reviews
                            • Boards & Panels




Evolve and Excel
Component Design Reviews

• Component Design Reviews provide stakeholders the opportunity to review
  component designs and associated interfaces and to ensure component is on
  track to transition to product implementation

• Component Design Review Purpose / Objectives
    – Ensures products provide objective evidence that the component design meets all
      requirements with acceptable risk and within cost and schedule constraints
    – Serves as a face-to-face open forum with NASA/Contractor SMEs, Subsystem Leads and other
      stakeholders to raise issues/concerns, answer questions or clarify design details
    – Review open liens and forward plans
    – Review analysis updates, based on continuous refinement of element designs
    – *Review design against functional and performance specifications
    – *Evaluate technical adequacy / maturity of design
    – Ensure interfaces have been identified and defined
    – *Review the verification and test approach
    – Assess the results of producibility analyses conducted on system hardware
    – Identify and address high risk elements of the design
    – *Review the readiness to proceed to fabrication, assembly, integration and test

                                       * Maturity expectations based on what is needed to proceed to the next life-cycle phase
Component Design Reviews
• Key Lessons Learned
    – Ensure component level reviews are incorporated into your larger design review
      plan
          • Identify what component level reviews must be complete prior to the next level of
            assembly design review (i.e. Subsystem) - ~90% ideal
          • Include data products in plan/schedule
    – Develop a consistent approach and expectations for conducting each component
      level review
          • This includes minimum common entrance and success criteria
                – Leads can then add to the criteria to further define expectations
          • Identify a common set of participants (typically systems engineering) that can participate
            in similar component reviews to ensure consistency
    – Conduct review where the work will be completed



   Properly executed component level reviews can significantly reduce the effort required to address identified
      issues. If not found until later reviews, (Subsystem or System) impacts may reverse lower review level
                                             decisions and cause rework.
Right Sizing Your Design
 PM Challenge 2012                                   Review Plan




                          Program/Project Design
                             Review Approach
                            • Planning
                            • Technical & Peer Reviews
                            • Component Design Reviews
                            • Subsystem Design Reviews
 Focus on the Objective
                            • System Level Reviews
                            • Boards & Panels




Evolve and Excel
Subsystem Design Reviews
•        Subsystem Design Reviews provide stakeholders the opportunity to review subsystem
         and associated component designs including GFE and ADP as appropriate.

•        Subsystem Design Review Purpose / Objectives
          – Ensures products provide objective evidence that the subsystem design meets all
            requirements with acceptable risk and within cost and schedule constraints
          – Review and drill into the detailed design that is documented in the technical design products
            for each subsystem/component
          – Serves as a face-to-face open forum with NASA/Contractor SMEs, Subsystem Leads and other
            stakeholders to raise issues/concerns, answer questions or clarify design details
          – Review open liens and forward plans for each Subsystem
          – Provides a forum for subsystems to horizontally integrate
          – *Review design against functional and performance specifications
          – *Evaluate technical adequacy / maturity of design
                • Ensure interfaces have been identified and defined
          –   *Review the verification and test approach
          –   *Review the readiness to proceed to fabrication, assembly, integration and test
          –   *Review the operation limits and constraints on the system
          –   Review associated risks and risk management strategies

         Using the entrance and success criteria, the Subsystem Design Review (PDR/CDR) will establish the basis
                                    for proceeding to system level review (PDR/CDR)
    19
                                                   * Maturity expectations based on what is needed to proceed to the next life-cycle phase
Subsystem Design Reviews
•   Key Lessons Learned
     – Improve the efficiency and effectiveness of the reviews.
           • Ensure adequate time is given during each Subsystem Design Review to display/discuss the design
                 – Implement Interactive Reading Rooms (IRRs) – Drawings and design documentation available in via electronic
                   and select hard copy form
                        » Ensure SMEs are available in the IRRs to answer/discuss design questions
                 – Minimize “all PowerPoint” reviews – review the design material / documentation
           • General Improvements to Process
                 – Allocate time to caucus after the review
                        » Review identified issues and ensure POCs / preliminary closure plans are established for all actions
           • Stack / overlap reviews where possible
                 – Be cognizant of resources that need to support more than one review – deconflict where possible
                 – No more than 3-4 Subsystem Design Reviews in parallel




    Orion conducted 18 PDR Subsystem Design Reviews over 5 weeks. 3 to 4 SSDRs were conducted in parallel.
    Overall this approach was highly successful and minimized the time span of the review. Reviews were held
     in a common location and review participants could move between reviews if necessary. Daily caucuses
     were held at the end of each day often resulting in 12 to 14 hour days. Future approach will shorten the
    review day to allow for caucuses to occur in a 8 or 9 hour day. Post review days will be allocated to caucus
                             completion to ensure actions are properly dispositioned.
Right Sizing Your Design
 PM Challenge 2012                                   Review Plan




                          Program/Project Design
                             Review Approach
                            • Planning
                            • Technical & Peer Reviews
                            • Component Design Reviews
                            • Subsystem Design Reviews
 Focus on the Objective
                            • System Level Reviews
                            • Boards & Panels




Evolve and Excel
System Level Design Reviews
•        Systems level reviews provide an opportunity to look across the system while emphasizing
         areas needing additional focus
          – Reviews may be conducted separately similar to the subsystem reviews or as one larger integrated
            review
                •   *Orion’s “DRAFT” CDR plan conducts three focused system level reviews (1 to 2 days each) prior to the
                    subsystem level reviews focusing on:
                       – System Analysis Review will be held to review the integrated analysis products that apply to multiple
                          subsystems (Aerosciences Environments, Loads and Dynamics, Thermal
                          Analysis, MMOD, Radiation, EMI/EMC, Mass, etc.)
                       – Test & Verification Approach / Plan
                       – Safety & Mission Assurance
                •   *Orion will then follow the subsystem level design reviews with a 5 day System level Integrated Vehicle Design
                    Review (IVDR)
                       – The IVDR is treated similar to the SSDRs
                              » All design DRDs that did not trace to an SSDR will trace to the IVDR
                       – Topics included Ground/Flight Operations, Integrated Vehicle Performance and Margins (operational
                          mitigations to hazards), Integrated Aborts Performance and Margins, Critical Events as a function of
                          mission, External Interfaces, Logistics, Module Interfaces, Integrated Module and System Test and
                          Verification Summary, Module and System Assembly, Integration, and Production, and Vehicle level
                          hazards and reliability
          – Results of review(s) satisfy the traditional major milestone entry and success criteria




    22                                          * Orion is current planning effort captures this approach. However, lessons learned from the flight
                                                  test program may allow for further streamlining.
System Level Design Reviews
•        System Level Design Review Purpose / Objectives
          –   Provide a focused review of the integrated system
          –   Review open liens and forward plans including a roll up from all lower level reviews
          –   *Ensure that all system requirements have been allocated, the requirements are complete, and flow down is
              adequate to verify system performance
          –   *Confirm verification methods have been defined are consistent with the vehicle design
          –   *Ensure test approach and plans are at the appropriate level of maturity
          –   *Demonstrate the system design meets requirements at the system, subsystem and component levels (within
              margins) with acceptable risk and within cost and schedule constraints (including interface requirements)
          –   *Ensure ICDs are appropriately matured to proceed with fabrication, assembly, integration, and test
          –   *Review of the system level design products including engineering drawings, CAD
              Models, MELs, specifications, ICDs, schematics, analysis plots, trade study results, etc.
          –   Present system configuration by mission phase
               •       Example: Vehicle integration thru launch site delivery, on-pad operations, launch, ascent, on-orbit phases, re-
                       entry, landing and recovery
                   •   *Demonstrate that the system configuration is a closes within all specified margins
          –   Ensure that technical and programmatic risks are identified and listed in order of criticality, and that risk
              mitigation plans are drafted.
          –   Present a full baseline of cost and schedules (often handled in a splinter session)
          –   Establish the basis and a viable path for proceeding to the next life-cycle phase, including interim milestones
              and entrance/success criteria.
         The System Level Design Review establishes the basis and a viable path for proceeding to the next life-cycle
                            phase, including interim milestones and entrance/success criteria.
    23
                                                               * Maturity expectations based on what is needed to proceed to the next life-cycle phase
System Level Design Reviews
•   Key Lessons Learned
     – Avoid PowerPoint only Design Reviews – allow time to review the actual design products
     – An auditorium type of review does not facilitate adequate interaction between the reviewers
       and the design team – control review team size
           • Remote reviewers can feed in room participants
     – Ensure key review participants are participating on site
           • Reviewers attending by Webex and telecon were less effective
     – Improve how contractual/cost issues are addressed during reviews
     – Ensure open issues can move from review to review to minimize duplication
           • Ensure actions from lower level reviews are not rewritten in each higher level review
                  – Provide feedback to initiators
           • Minimize duplication of Pre-declared actions/RIDs, SSDR actions, and Errata
           • Minimize RIDs/issues being discussed several times during the review process – when issue arises
             gather the SMEs and make an effective decision




     A key streamlining goal is to improve the overall quality of RIDs while reducing the number of RIDs against
                                       known, out of scope or duplicate issues.
System Level Design Reviews

Key Lessons Learned – Orion Example

 Orion PDR Sponsored RIDs by Discipline • 170 DRDs Delivered & Reviewed
                                                                                                            –   100,000+ pages of design, process, and
                             Wiring, 40                                                                         plan documentation
                      EGSE, 43
                                             Other, 272
                                                                                                            –   Requirements, Interface
                                                                                                                Definition, Drawings, Verification
                LRS, 57                                              Av & Sw , 605
                                                                         Av: Comm & Track, 22
                                                                                                                Details, General Plans, etc.
      Crew Systems, 88                                                                  Av: C&DH, 30

                T&V, 204                                                         ICDs, 107             • 1470 RID Initiators (DRD Reviewers)
Hazard Analysis, 45
                                                                                                            –   520 unique initiators wrote a RID (35.4%)
            GN&C, 65                                                        CM, 452                         –   399 unique initiators with an approved RID
      Pyrotechnics, 88                                                                                          (76.7%)
          Propulsion, 76

                 EPS, 103

                  ECLSS, 124
                                                                      LAS, 267                         • 3625 Sponsored RIDs
                            SM, 126
                                                                    Con Ops, 204                            –   2049 were approved (56.5%)
                                                     Vehicle, 142
                                 Mech, 115
                                             ICCS, 120




    A key CDR streamlining goal is to improve the overall quality of RIDs while reducing the number of RIDs against
   25
                                        known, out of scope or duplicate issues.
What is a Good RID?
•   What is a good RID?
     –   A “new” design related issue
     –   Accurately describes the design related issue consistent with the RID criteria
     –   Provides the details of where the issue was found
          •   For DRD related RIDs (section, page, etc)
          •   For Architecture Element RIDs with no DRD referenced (chart, conversation, etc.)
     –   Provides a sufficiently detailed recommended resolution
     –   Stays within the scope of PDR expectations
     –   For requirements, provides correct “from” language and recommends “to” language

                          An issue that has not previously been identified.
•   What is a bad RID?
     –   Incomplete issue identification
     –   No recommended resolution
     –   Recommended resolution of “fix this”
     –   Editorial comment (spelling, grammar, etc.)
     –   RID that expands on errata or duplicates a Pre-Declared RID
     –   Post PDR level of maturity / unrealistic expectations
     –   RID written against a baselined or reference document (Examples: SRD, S/C Spec)
     –   RID entered by someone other than the original initiator without documenting the original initiator
     –   RID written against a previously made project decision (VICB, CPCB, etc.) without new data or evidence
         to challenge the decision


                              Don’t tell us something we already know!!!
Right Sizing Your Design
 PM Challenge 2012                                   Review Plan




                          Program/Project Design
                             Review Approach
                            • Planning
                            • Technical & Peer Reviews
                            • Component Design Reviews
                            • Subsystem Design Reviews
 Focus on the Objective
                            • System Level Reviews
                            • Boards & Panels




Evolve and Excel
Boards & Panels

• There are a number of boards and panels that can be implemented during a
  review process depending on the size and complexity of the review
    – Caucus Teams
        • Made up of the lower level review chair(s) and the key leads of products being reviewed
             – May be implemented for Subsystem design reviews and system level reviews
             – Not recommended for Tech/Peer reviews
        • Focus is to resolve issues (disposition actions) that arise in the review quickly allowing
          the team to not repeat the action later in the review and to facilitate the design team’s
          ability to rapidly start resolving the issue
    – Management Review Team
        • Made up of the Program Manager and key direct reports
             – May be implemented for Subsystem design reviews and system level reviews
             – Not recommended for Tech/Peer reviews
        • Focus is to resolve program level issues that extend beyond a Subsystem or IPT lead’s
          purview
    – Screening Team
        • Often led by systems engineering with key subject matter expert support
        • Focus is on quickly reviewing and bucket RIDs into categories (subsystems, orgs, etc.) for
          later disposition
Boards & Panels

• There are a number of boards and panels that can be implemented during a
  review process depending on the size and complexity of the review
    – Disposition Teams
        • Often led by IPT Leads with key subject matter expert support
        • Focus is on ensuring all open issues (RIDs/actions) are dispositioned and an effective path
          to closure is established
    – Pre-Board
        • Serves a preparatory board for the later review board
        • Often chaired by the Deputy Program/Project Manager, Chief Systems Engineer, or Chief
          Engineer
        • Focus is on:
             – Resolving and dispositioning elevated or disputed RIDs
             – Elevating unresolved issues to the Board
             – Identifying issues that need to go forward to the Board (due to significant cost, schedule, or
               technical impact/risk)
             – Providing the Initial evaluation of the project’s success in meeting the entrance/success criteria
Boards & Panels

• There are a number of boards and panels that can be implemented during a
  review process depending on the size and complexity of the review
    – Board
        • Chaired by the Program/Project Manager
        • Focus is on:
              – Resolving and dispositioning elevated or disputed RIDs
              – Evaluating the Project’s success in meeting the PDR success criteria
              – Approving the basis of and viable path for proceeding to the next life-cycle phase
Boards and Panels
•    Key Lessons Learned
       – Caucuses
             • Resist the desire to include everyone – keep the team small and bring in key SMEs as needed
                    – Helps ensure the process does not take longer than necessary
             • Allow for additional time post review to disposition any remaining issues/actions
       – Screening and Disposition Teams
             • Pay particular attention in selection Team leadership and identifying SMEs to support
                    – Significant time can be lost by tracking down the correct person who understands the issue and can
                      recommend a corrective action
       – Pre-Board and Board
             • Avoid the desire to start the Board the day after the System Level Reviews (be flexible)
                    –   A few days extra to resolve conflicts between design team and RID initiators can ensure the appropriate action is taken to
                        resolve issues




                                      Ensure sufficient time to review RIDs/Actions
    Allow enough time to process all of the actions and roll up the action closure status from the lower level reviews
Right Sizing Your Design
 PM Challenge 2012                                   Review Plan




                                 Summary
                          • Time-line Example
                          • Affordability
                          • Conclusion


 Focus on the Objective




Evolve and Excel
Time-line Example
Large Complex Program/Project*
Month 1   Month 2     Month 3       Month 4          Month 5           Month 6     Month 7       Month 8    Month 9         Month 10        Month 11     Month 12

          Planning


                Work Product (Plans, Drawings, Rqmts, etc.) Tech / Peer Reviews


                                             Component Level Reviews

                                         Work Product Delivery (NLT 2 weeks prior to applicable SS/Sys Reviews)

                                                              Work Product Review (outside of reviews )
                            Results (actions / RIDs) flowed into the
                            applicable review for disposition                    System Level Review(s)
                                                                                    (Environments, Etc.)

                                                                                                              Subsystem Level Reviews

                                                                                          Caucuses
                                                                            Management Review Team
                                                                                                                       System Level Review
                                                                                                                                  (Vehicle)
                                                                                                               Screening & Disposition Teams
                                                                                                                  Reviews all open issues to date and
                                                                                                                  ensures appropriate dispositions
                                                                                                                  are developed
                                                                                                                                                    Pre-Board

                                                                                                                                                            Board

Month 1   Month 2     Month 3       Month 4          Month 5           Month 6     Month 7       Month 8    Month 9         Month 10        Month 11     Month 12

                                              * Notional time-line – duration and number of design review elements dependent on many factors
                                                (Scope, complexity, volume of products to be reviewed, number of participants required, available time to conduct
Right Sizing Your Design
 PM Challenge 2012                                   Review Plan




                                 Summary
                          • Time-line example
                          • Affordability
                          • Conclusion


 Focus on the Objective




Evolve and Excel
Affordability

• When planning and executing your design review affordability should remain
  a constant theme weaved throughout ensuring optimal solutions are chosen

• Key areas to focus on:
    – Balance thoroughness and schedule
         • The desire to review every aspect of the design down to the lowest possible level must
           be balanced against the available time to execute the review as to not delay the
           development activities unnecessarily
    – Balance inclusion and efficiency
         • Develop a process that ensures all stakeholders have an adequate time to participate and
           provide input helping to shape the design, ensure mission success, and ultimately
           provide a safe crew exploration vehicle
    – Including stakeholders in the planning process
    – Review documents for duplication and remove or minimize early in program /
      project life cycle
    – Utilize ongoing lower level reviews to provide relevant insight as part of the larger
      major milestone review process (technical and peer reviews, component level
      design reviews, etc.)
Affordability

• Key areas to focus on:
     – Communicate expectations early and often to minimize lost time due to out of
       scope comments, actions, etc.
     – Ensure government/contractor joint development of process and associated
       expectations, including entry and success criteria
     – Consider work location, amount of travel needed, etc. when determining plan and
       choosing review locations
     – Overlay review schedule with program/project schedule and work to minimize
       disruptions and in ongoing program/project efforts
     – Track issues/actions throughout entire process to minimize duplication
          • Ensure adequate dispositions are developed the first time
     – Look to other programs/projects during planning phase
          • Take advantage of lessons learned

• “Affordability remains the most significant issue facing the Agency and in particular
  human spaceflight.” – Heft Steering Committee
• Future NASA space programs must be affordable, sustainable and realistic to survive
  political and funding dangers… - Charles Bolden, AIAA Conference Jan 2011
Right Sizing Your Design
 PM Challenge 2012                                   Review Plan




                                 Summary
                          • Time-line example
                          • Affordability
                          • Conclusion


 Focus on the Objective




Evolve and Excel
Keys to Review Success
                                        (Operational Excellence)

•   Teamwork
     – Create a joint NASA/Contractor Program Integration Team (PIT) to ensure common expectations are
       communicated across the NASA, Prime Contractor, and support contractor teams
          • Key personnel from each IPT should be included in team
          • Incorporate planning and C&DM personnel into team

•   Communication
     – Communicate early and often
     – Conduct a series of TIMs and Training Sessions with each of the leads (Subsystem/System) to
       develop common expectations and identify issues needing resolution prior to Review
     – Institute multiple statuses and forums targeting all stakeholders (memos, status meetings, etc.)

•   Commitment
     – Assigned a manager responsible for ensuring review success (NASA & Prime Contractor)
     – Routinely stress the importance of attaining the appropriate level of design maturity with the goal
       of “Get it right the 1st time”
     – Routinely communicate the review expectations and monitor status weekly

•   Accountability
     – Ensure Leads take ownership of their respective lower level review preparation and execution
     – Develop a detailed schedule to manage the reviews including data package review and delivery
     – Develop detailed metrics for tracking all deliverables by Component, Subsystem, and System

                                                                                                             38
Conclusion

• Develop and execute a program/project technical life-cycle review
  (SRR, SDR, PDR, CDR) process that ensures NASA’s next generation products
  can meet all mission objectives and satisfy requirements with acceptable risk

• Use lessons learned from previous Programs/Projects to develop a multi-tiered
  approach that ensures the integrated system
  (components, subsystems, system) is reviewed to ensure the design approach
  is at a sufficient level of maturity to proceed to the next life-cycle phase.
    – Expanded use of lower level design reviews (Design products / documentation
      Tech/Peer Reviews, Component Reviews, and Subsystem Reviews) help to ensure a
      thorough review while better integrating with ongoing program activities


• When planning and executing your design review keep an eye on affordability
Right Sizing Your Design
 PM Challenge 2012                         Review Plan




                          Questions ???


 Focus on the Objective




Evolve and Excel

Más contenido relacionado

La actualidad más candente

Law.richard
Law.richardLaw.richard
Law.richardNASAPMC
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joeNASAPMC
 
Matt.gonzales
Matt.gonzalesMatt.gonzales
Matt.gonzalesNASAPMC
 
Horn thomas
Horn thomasHorn thomas
Horn thomasNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
Bauer.frank
Bauer.frankBauer.frank
Bauer.frankNASAPMC
 
Terry.conroy
Terry.conroyTerry.conroy
Terry.conroyNASAPMC
 
Thomas.mc vittie
Thomas.mc vittieThomas.mc vittie
Thomas.mc vittieNASAPMC
 
Vonnie simonsen
Vonnie simonsenVonnie simonsen
Vonnie simonsenNASAPMC
 
Murphy.dar jean.jean
Murphy.dar jean.jeanMurphy.dar jean.jean
Murphy.dar jean.jeanNASAPMC
 
Louis.cioletti
Louis.ciolettiLouis.cioletti
Louis.ciolettiNASAPMC
 
Backup darren elliott
Backup darren elliottBackup darren elliott
Backup darren elliottNASAPMC
 
Baldwin.kristen
Baldwin.kristenBaldwin.kristen
Baldwin.kristenNASAPMC
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthewNASAPMC
 
Harvey elliott
Harvey elliottHarvey elliott
Harvey elliottNASAPMC
 
Carol.mullenax
Carol.mullenaxCarol.mullenax
Carol.mullenaxNASAPMC
 
Chen.tim
Chen.timChen.tim
Chen.timNASAPMC
 
Sandra smalley
Sandra smalleySandra smalley
Sandra smalleyNASAPMC
 
Noneman.steven
Noneman.stevenNoneman.steven
Noneman.stevenNASAPMC
 

La actualidad más candente (20)

Law.richard
Law.richardLaw.richard
Law.richard
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joe
 
Matt.gonzales
Matt.gonzalesMatt.gonzales
Matt.gonzales
 
Horn thomas
Horn thomasHorn thomas
Horn thomas
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
Bauer.frank
Bauer.frankBauer.frank
Bauer.frank
 
Terry.conroy
Terry.conroyTerry.conroy
Terry.conroy
 
Thomas.mc vittie
Thomas.mc vittieThomas.mc vittie
Thomas.mc vittie
 
Vonnie simonsen
Vonnie simonsenVonnie simonsen
Vonnie simonsen
 
Murphy.dar jean.jean
Murphy.dar jean.jeanMurphy.dar jean.jean
Murphy.dar jean.jean
 
Louis.cioletti
Louis.ciolettiLouis.cioletti
Louis.cioletti
 
Backup darren elliott
Backup darren elliottBackup darren elliott
Backup darren elliott
 
Baldwin.kristen
Baldwin.kristenBaldwin.kristen
Baldwin.kristen
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthew
 
Harvey elliott
Harvey elliottHarvey elliott
Harvey elliott
 
Carol.mullenax
Carol.mullenaxCarol.mullenax
Carol.mullenax
 
Chen.tim
Chen.timChen.tim
Chen.tim
 
Sandra smalley
Sandra smalleySandra smalley
Sandra smalley
 
Symons
SymonsSymons
Symons
 
Noneman.steven
Noneman.stevenNoneman.steven
Noneman.steven
 

Similar a C armstrong tbyers

Rational Unified Process
Rational Unified ProcessRational Unified Process
Rational Unified ProcessKumar
 
Charles.armstrong
Charles.armstrongCharles.armstrong
Charles.armstrongNASAPMC
 
Charles.armstrong
Charles.armstrongCharles.armstrong
Charles.armstrongNASAPMC
 
Software management framework
Software management frameworkSoftware management framework
Software management frameworkKuppusamy P
 
Key Considerations for a Successful Hyperion Planning Implementation
Key Considerations for a Successful Hyperion Planning ImplementationKey Considerations for a Successful Hyperion Planning Implementation
Key Considerations for a Successful Hyperion Planning ImplementationAlithya
 
103240-The-New-Way-of-Thinking-Our-Implementation-experience-with-Oracle-HCM-...
103240-The-New-Way-of-Thinking-Our-Implementation-experience-with-Oracle-HCM-...103240-The-New-Way-of-Thinking-Our-Implementation-experience-with-Oracle-HCM-...
103240-The-New-Way-of-Thinking-Our-Implementation-experience-with-Oracle-HCM-...ssuser835d1a
 
Software management disciplines
Software management disciplinesSoftware management disciplines
Software management disciplinesKuppusamy P
 
Scrum Process For Offshore Team
Scrum Process For Offshore TeamScrum Process For Offshore Team
Scrum Process For Offshore TeamPaul Nguyen
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
Practical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital ProjectsPractical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital ProjectsPMA Consultants
 
Project Initiation Document
Project Initiation DocumentProject Initiation Document
Project Initiation DocumentDave Angelow
 
Time management
Time management Time management
Time management Pm Joe
 
Rational unified process lecture-5
Rational unified process lecture-5Rational unified process lecture-5
Rational unified process lecture-5MujiAhsan
 
Benefits of implementing primavera p6 r8.1 and integration to oracle ppt
Benefits of implementing primavera p6 r8.1 and integration to oracle pptBenefits of implementing primavera p6 r8.1 and integration to oracle ppt
Benefits of implementing primavera p6 r8.1 and integration to oracle pptp6academy
 

Similar a C armstrong tbyers (20)

SPM_UNIT-2.pptx
SPM_UNIT-2.pptxSPM_UNIT-2.pptx
SPM_UNIT-2.pptx
 
Rational Unified Process
Rational Unified ProcessRational Unified Process
Rational Unified Process
 
Charles.armstrong
Charles.armstrongCharles.armstrong
Charles.armstrong
 
Charles.armstrong
Charles.armstrongCharles.armstrong
Charles.armstrong
 
Software management framework
Software management frameworkSoftware management framework
Software management framework
 
Key Considerations for a Successful Hyperion Planning Implementation
Key Considerations for a Successful Hyperion Planning ImplementationKey Considerations for a Successful Hyperion Planning Implementation
Key Considerations for a Successful Hyperion Planning Implementation
 
103240-The-New-Way-of-Thinking-Our-Implementation-experience-with-Oracle-HCM-...
103240-The-New-Way-of-Thinking-Our-Implementation-experience-with-Oracle-HCM-...103240-The-New-Way-of-Thinking-Our-Implementation-experience-with-Oracle-HCM-...
103240-The-New-Way-of-Thinking-Our-Implementation-experience-with-Oracle-HCM-...
 
Software management disciplines
Software management disciplinesSoftware management disciplines
Software management disciplines
 
Scrum Process For Offshore Team
Scrum Process For Offshore TeamScrum Process For Offshore Team
Scrum Process For Offshore Team
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Practical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital ProjectsPractical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital Projects
 
Sysdev
SysdevSysdev
Sysdev
 
WBS PROJECT
WBS PROJECTWBS PROJECT
WBS PROJECT
 
Project Initiation Document
Project Initiation DocumentProject Initiation Document
Project Initiation Document
 
Unified process
Unified processUnified process
Unified process
 
Time management
Time management Time management
Time management
 
Rational unified process lecture-5
Rational unified process lecture-5Rational unified process lecture-5
Rational unified process lecture-5
 
6396901
63969016396901
6396901
 
Benefits of implementing primavera p6 r8.1 and integration to oracle ppt
Benefits of implementing primavera p6 r8.1 and integration to oracle pptBenefits of implementing primavera p6 r8.1 and integration to oracle ppt
Benefits of implementing primavera p6 r8.1 and integration to oracle ppt
 
Rup
RupRup
Rup
 

Más de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerryNASAPMC
 
Mitskevich amanda
Mitskevich amandaMitskevich amanda
Mitskevich amandaNASAPMC
 

Más de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
 
Mitskevich amanda
Mitskevich amandaMitskevich amanda
Mitskevich amanda
 

Último

Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoffsammart93
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Victor Rentea
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...DianaGray10
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...Zilliz
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusZilliz
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century educationjfdjdjcjdnsjd
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobeapidays
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MIND CTI
 
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelMcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelDeepika Singh
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyKhushali Kathiriya
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDropbox
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...apidays
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Victor Rentea
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWERMadyBayot
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Bhuvaneswari Subramani
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistandanishmna97
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Jeffrey Haguewood
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...apidays
 

Último (20)

Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with Milvus
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelMcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistan
 
Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 

C armstrong tbyers

  • 1. PM Challenge 2012 Right Sizing Your Project/Program Design Review Plan PM Challenge 2012 Charles Armstrong Focus on the Objective National Aeronautics and Space Administration Orion VIO SE&I Plans & Processes Manager charles.h.armstrong@nasa.gov 281-244-6315 Tony Byers Lockheed Martin Space Systems Company Software Systems & Data Sr. Manager anthony.w.byers@lmco.com 303-977-4389 Evolve and Excel
  • 2. Agenda • Introduction • Program/Project Design Review Approach • Planning • Technical & Peer Reviews • Component Design Reviews • Subsystem Design Reviews • System Level Reviews • Boards & Panels • Summary • Affordability • Time-line Comparison • Conclusion • Closing Remarks 2
  • 3. Right Sizing Your Design PM Challenge 2012 Review Plan Introduction Focus on the Objective Evolve and Excel
  • 4. Introduction • Presentation Focus: • Historically, NASA major milestone reviews have been conducted by allowing participation by a large number of agency personnel. • Review a wide range of materials • Write a large number of candidate issues in the form of RIDs • Very expensive • Significant infrastructure and logistics • Large effort to review, disposition, and close • Using the lessons learned from previous Programs/Projects a streamlined integrated approach to conducting major design reviews is proposed. • Recognizes ongoing insight/oversight as part of the design review plan • Expands the use of lower level design reviews (Design products / documentation Tech/Peer Reviews, Component Reviews, and Subsystem Reviews) • Uses highly qualified personnel - Limits participation to individuals with an identified ability to make a value-added contribution • Changes the way issues are identified and vetted If successful, this methodology will reduce the cost of conducting major milestone reviews and set the new 4 standard for the conduct of major milestone reviews within the agency.
  • 5. Management Challenges • Planning Challenges – Develop and execute a program/project technical life-cycle review (SRR, SDR, PDR, CDR) process that ensures NASA’s next generation products can meet all mission objectives and satisfy requirements with acceptable risk – Develop a multi-tiered approach that ensures the integrated system (components, subsystems, system) is reviewed to ensure the design approach is at a sufficient level of maturity to proceed to the next life-cycle phase. – Maintain an eye on affordability – Balance thoroughness and schedule. The desire to review every aspect of the design down to the lowest possible level must be balanced against the available time to execute the review as to not delay the development activities unnecessarily. – Balance inclusion and efficiency. Develop a process that ensures all stakeholders have an adequate time to participate and provide input helping to shape the design, ensure mission success, and ultimately provide a safe crew exploration vehicle. 5
  • 6. Management Challenges • Execution Challenges – Communicate the expectations to an often diverse personnel organization consisting of NASA, prime contractor, and many support contractors – Balance the desire to improve the design with the need to efficiently transition to the next life-cycle phase – From the time a baseline is struck, a lot of potential energy develops to revisit the requirements (did we miss something?) and improve the design (could it be better?) – This energy must be managed to ensure that identified issues and design refinement are necessary to ensure mission success (including crew safety for human spaceflight) and not simply to resolve an “I would have did it differently” comment – Review products must align as closely as possible to the baseline – Monitor and control process execution throughout the duration of the effort 6
  • 7. Right Sizing Your Design PM Challenge 2012 Review Plan Program/Project Design Review Approach • Planning • Technical & Peer Reviews • Component Design Reviews • Subsystem Design Reviews Focus on the Objective • System Level Reviews • Boards & Panels Evolve and Excel
  • 8. Design Review Planning • Form a review integration team – Identify and assign a manager to lead the major design review (NASA & Prime Contractor) – Identify a lead from each IPT – Identify key participants from other groups (Planning, Configuration & Data Management, Subcontracts, etc.) – Ensure joint NASA/Prime Contractor support in each area, where possible • Define review – Review NASA / Industry review guidance – Review program documentation • Statement of Objectives, Statement of Work, Systems Engineering Management Plan, etc. – Define review scope • Baselines (Technical, Schedule, & Cost) • Level of penetration (Component, Subsystem, System) Be cognizant of the applicable – Define review objectives program / project phase – Define Entry and Success Criteria
  • 9. Design Review Planning • Develop the detailed review process – Include how each review is supposed to be executed – Include how issues are recorded, communicated, tracked, and closed • Increase formality as you increase integration – Technical / Peer reviews – lower formality – Subsystem & System level reviews – increased formality (RIDs, etc.) • Ensure open issues can move from review to review to minimize duplication • Define Review Participants – Determine Chair(s) – Define roles and responsibilities (Chairs, Reviewers, Program/Project Team, etc.) – Include Program/Project leadership – Include external stakeholders in component level reviews (other interfacing components, subsystems, etc.) – Include external stakeholders in Subsystem and System level reviews (Engineering, Safety, Crew office, Mission Operations, other NASA Centers, etc.) – Include independent reviewers (especially important as you progress to subsystem and system level reviews where SRB participation is expected)
  • 10. Design Review Planning • Develop detailed schedule – Include all lower level reviews that are determined to be a part of the overall major milestone design review process • Example: Orion included technical / peer reviews for PDR products, Subsystem Design Reviews, and System Level Reviews – Include all products that are determined to make up the review data package • Example: Requirements, Plans, Drawings, CAD Models, Design Data Books, etc. – Incorporate dependencies where possible • Example: Component PDRs required to be completed and products needing to be developed prior to a subsystem design review – Ensure owners of all products and reviews are identified (NASA & Contractor) – Develop a process to ensure schedule is updated / managed – Develop the list of metrics / reports that will be utilized to track performance
  • 11. Design Review Planning • Document the plan • Formalize the overall review process • All significant stakeholders organizations will participate in review of document prior to release • Ensures leadership has agreed to plan • Document the requirements and associated documentation baseline for review • Incorporate NPR 7123.1A criteria into plan (including any tailoring) • Serves as the primary method of documenting all agreements regarding method to meet the review criteria • Place under configuration control • Use as a reference throughout the execution to ensure the process is adhered to 11
  • 12. Right Sizing Your Design PM Challenge 2012 Review Plan Program/Project Design Review Approach • Planning • Technical / Peer Reviews • Component Design Reviews • Subsystem Design Reviews Focus on the Objective • System Level Reviews • Boards & Panels Evolve and Excel
  • 13. Technical / Peer Reviews • A significant amount of oversight occurs throughout the life-cycle of the project – This interaction serves to familiarize the reviewers with the lower level details and provides an opportunity to identify and resolve issues early in the review process • Technical / Peer reviews provide an opportunity to perform technical assessment and to focus content for the next tier of reviews (Component, Subsystem, & System PDRs/CDRs) • Technical / Peer Review Purpose / Objectives – NASA and Contractor Subject Matter Experts (SMEs) assess the technical progress and quality of design related products (could be a DRD or parts of a DRD) – Work to identify and solve design, document, process issues – Ensure the Product accurately represents the appropriate baseline configuration / architecture – Ensure the Product fulfills the DRD Description provided by NASA – Provides joint NASA/Contractor forum with Intra-Subsystem and Cross-Subsystem Participation – Serves as a foundational review supporting follow-on reviews that culminate in a successful design life-cycle milestone review – Iterative when required 13 Tech Reviews are “Roll up the sleeves” reviews of the products that support or represent the design
  • 14. Technical / Peer Reviews • Key Lessons Learned – Enhance Technical Reviews of the design work products and ensure correct participation • Consistency of technical review process important – tracking of issues / conduct of review – Identify the tech review of most importance – i.e. Design Data Books provide an opportunity to review the design at the subsystem level prior to a Subsystem PDR/CDR – Provide TR participants the data product(s) 5 to 10 days prior to the review – Ensure review dates are documented in a easily accessible integrated schedule • Work to deconflict schedules where possible to ensure appropriate participation – Identify minimum required stakeholders for a successful TR • TRs must be given high priority by each appropriate organization – Be willing to reschedule the review if the right personnel cannot attend • Appropriate SMEs are expected to support DRD TRs – For all contractor developed DRDs, assign a NASA POC to ensure stakeholder selection is correct and the work product receives adequate review • Official delivery to NASA occurs after the TR/PR Orion conducted 316 Technical / Peer Reviews for 224 PDR Data Package Products. Reviews were successful in identifying and resolving many issues. However, open review findings were not rolled up to higher level reviews. Thus creating significant duplication of actions / RIDs in Subsystem and System level reviews.
  • 15. Right Sizing Your Design PM Challenge 2012 Review Plan Program/Project Design Review Approach • Planning • Technical & Peer Reviews • Component Design Reviews • Subsystem Design Reviews Focus on the Objective • System Level Reviews • Boards & Panels Evolve and Excel
  • 16. Component Design Reviews • Component Design Reviews provide stakeholders the opportunity to review component designs and associated interfaces and to ensure component is on track to transition to product implementation • Component Design Review Purpose / Objectives – Ensures products provide objective evidence that the component design meets all requirements with acceptable risk and within cost and schedule constraints – Serves as a face-to-face open forum with NASA/Contractor SMEs, Subsystem Leads and other stakeholders to raise issues/concerns, answer questions or clarify design details – Review open liens and forward plans – Review analysis updates, based on continuous refinement of element designs – *Review design against functional and performance specifications – *Evaluate technical adequacy / maturity of design – Ensure interfaces have been identified and defined – *Review the verification and test approach – Assess the results of producibility analyses conducted on system hardware – Identify and address high risk elements of the design – *Review the readiness to proceed to fabrication, assembly, integration and test * Maturity expectations based on what is needed to proceed to the next life-cycle phase
  • 17. Component Design Reviews • Key Lessons Learned – Ensure component level reviews are incorporated into your larger design review plan • Identify what component level reviews must be complete prior to the next level of assembly design review (i.e. Subsystem) - ~90% ideal • Include data products in plan/schedule – Develop a consistent approach and expectations for conducting each component level review • This includes minimum common entrance and success criteria – Leads can then add to the criteria to further define expectations • Identify a common set of participants (typically systems engineering) that can participate in similar component reviews to ensure consistency – Conduct review where the work will be completed Properly executed component level reviews can significantly reduce the effort required to address identified issues. If not found until later reviews, (Subsystem or System) impacts may reverse lower review level decisions and cause rework.
  • 18. Right Sizing Your Design PM Challenge 2012 Review Plan Program/Project Design Review Approach • Planning • Technical & Peer Reviews • Component Design Reviews • Subsystem Design Reviews Focus on the Objective • System Level Reviews • Boards & Panels Evolve and Excel
  • 19. Subsystem Design Reviews • Subsystem Design Reviews provide stakeholders the opportunity to review subsystem and associated component designs including GFE and ADP as appropriate. • Subsystem Design Review Purpose / Objectives – Ensures products provide objective evidence that the subsystem design meets all requirements with acceptable risk and within cost and schedule constraints – Review and drill into the detailed design that is documented in the technical design products for each subsystem/component – Serves as a face-to-face open forum with NASA/Contractor SMEs, Subsystem Leads and other stakeholders to raise issues/concerns, answer questions or clarify design details – Review open liens and forward plans for each Subsystem – Provides a forum for subsystems to horizontally integrate – *Review design against functional and performance specifications – *Evaluate technical adequacy / maturity of design • Ensure interfaces have been identified and defined – *Review the verification and test approach – *Review the readiness to proceed to fabrication, assembly, integration and test – *Review the operation limits and constraints on the system – Review associated risks and risk management strategies Using the entrance and success criteria, the Subsystem Design Review (PDR/CDR) will establish the basis for proceeding to system level review (PDR/CDR) 19 * Maturity expectations based on what is needed to proceed to the next life-cycle phase
  • 20. Subsystem Design Reviews • Key Lessons Learned – Improve the efficiency and effectiveness of the reviews. • Ensure adequate time is given during each Subsystem Design Review to display/discuss the design – Implement Interactive Reading Rooms (IRRs) – Drawings and design documentation available in via electronic and select hard copy form » Ensure SMEs are available in the IRRs to answer/discuss design questions – Minimize “all PowerPoint” reviews – review the design material / documentation • General Improvements to Process – Allocate time to caucus after the review » Review identified issues and ensure POCs / preliminary closure plans are established for all actions • Stack / overlap reviews where possible – Be cognizant of resources that need to support more than one review – deconflict where possible – No more than 3-4 Subsystem Design Reviews in parallel Orion conducted 18 PDR Subsystem Design Reviews over 5 weeks. 3 to 4 SSDRs were conducted in parallel. Overall this approach was highly successful and minimized the time span of the review. Reviews were held in a common location and review participants could move between reviews if necessary. Daily caucuses were held at the end of each day often resulting in 12 to 14 hour days. Future approach will shorten the review day to allow for caucuses to occur in a 8 or 9 hour day. Post review days will be allocated to caucus completion to ensure actions are properly dispositioned.
  • 21. Right Sizing Your Design PM Challenge 2012 Review Plan Program/Project Design Review Approach • Planning • Technical & Peer Reviews • Component Design Reviews • Subsystem Design Reviews Focus on the Objective • System Level Reviews • Boards & Panels Evolve and Excel
  • 22. System Level Design Reviews • Systems level reviews provide an opportunity to look across the system while emphasizing areas needing additional focus – Reviews may be conducted separately similar to the subsystem reviews or as one larger integrated review • *Orion’s “DRAFT” CDR plan conducts three focused system level reviews (1 to 2 days each) prior to the subsystem level reviews focusing on: – System Analysis Review will be held to review the integrated analysis products that apply to multiple subsystems (Aerosciences Environments, Loads and Dynamics, Thermal Analysis, MMOD, Radiation, EMI/EMC, Mass, etc.) – Test & Verification Approach / Plan – Safety & Mission Assurance • *Orion will then follow the subsystem level design reviews with a 5 day System level Integrated Vehicle Design Review (IVDR) – The IVDR is treated similar to the SSDRs » All design DRDs that did not trace to an SSDR will trace to the IVDR – Topics included Ground/Flight Operations, Integrated Vehicle Performance and Margins (operational mitigations to hazards), Integrated Aborts Performance and Margins, Critical Events as a function of mission, External Interfaces, Logistics, Module Interfaces, Integrated Module and System Test and Verification Summary, Module and System Assembly, Integration, and Production, and Vehicle level hazards and reliability – Results of review(s) satisfy the traditional major milestone entry and success criteria 22 * Orion is current planning effort captures this approach. However, lessons learned from the flight test program may allow for further streamlining.
  • 23. System Level Design Reviews • System Level Design Review Purpose / Objectives – Provide a focused review of the integrated system – Review open liens and forward plans including a roll up from all lower level reviews – *Ensure that all system requirements have been allocated, the requirements are complete, and flow down is adequate to verify system performance – *Confirm verification methods have been defined are consistent with the vehicle design – *Ensure test approach and plans are at the appropriate level of maturity – *Demonstrate the system design meets requirements at the system, subsystem and component levels (within margins) with acceptable risk and within cost and schedule constraints (including interface requirements) – *Ensure ICDs are appropriately matured to proceed with fabrication, assembly, integration, and test – *Review of the system level design products including engineering drawings, CAD Models, MELs, specifications, ICDs, schematics, analysis plots, trade study results, etc. – Present system configuration by mission phase • Example: Vehicle integration thru launch site delivery, on-pad operations, launch, ascent, on-orbit phases, re- entry, landing and recovery • *Demonstrate that the system configuration is a closes within all specified margins – Ensure that technical and programmatic risks are identified and listed in order of criticality, and that risk mitigation plans are drafted. – Present a full baseline of cost and schedules (often handled in a splinter session) – Establish the basis and a viable path for proceeding to the next life-cycle phase, including interim milestones and entrance/success criteria. The System Level Design Review establishes the basis and a viable path for proceeding to the next life-cycle phase, including interim milestones and entrance/success criteria. 23 * Maturity expectations based on what is needed to proceed to the next life-cycle phase
  • 24. System Level Design Reviews • Key Lessons Learned – Avoid PowerPoint only Design Reviews – allow time to review the actual design products – An auditorium type of review does not facilitate adequate interaction between the reviewers and the design team – control review team size • Remote reviewers can feed in room participants – Ensure key review participants are participating on site • Reviewers attending by Webex and telecon were less effective – Improve how contractual/cost issues are addressed during reviews – Ensure open issues can move from review to review to minimize duplication • Ensure actions from lower level reviews are not rewritten in each higher level review – Provide feedback to initiators • Minimize duplication of Pre-declared actions/RIDs, SSDR actions, and Errata • Minimize RIDs/issues being discussed several times during the review process – when issue arises gather the SMEs and make an effective decision A key streamlining goal is to improve the overall quality of RIDs while reducing the number of RIDs against known, out of scope or duplicate issues.
  • 25. System Level Design Reviews Key Lessons Learned – Orion Example Orion PDR Sponsored RIDs by Discipline • 170 DRDs Delivered & Reviewed – 100,000+ pages of design, process, and Wiring, 40 plan documentation EGSE, 43 Other, 272 – Requirements, Interface Definition, Drawings, Verification LRS, 57 Av & Sw , 605 Av: Comm & Track, 22 Details, General Plans, etc. Crew Systems, 88 Av: C&DH, 30 T&V, 204 ICDs, 107 • 1470 RID Initiators (DRD Reviewers) Hazard Analysis, 45 – 520 unique initiators wrote a RID (35.4%) GN&C, 65 CM, 452 – 399 unique initiators with an approved RID Pyrotechnics, 88 (76.7%) Propulsion, 76 EPS, 103 ECLSS, 124 LAS, 267 • 3625 Sponsored RIDs SM, 126 Con Ops, 204 – 2049 were approved (56.5%) Vehicle, 142 Mech, 115 ICCS, 120 A key CDR streamlining goal is to improve the overall quality of RIDs while reducing the number of RIDs against 25 known, out of scope or duplicate issues.
  • 26. What is a Good RID? • What is a good RID? – A “new” design related issue – Accurately describes the design related issue consistent with the RID criteria – Provides the details of where the issue was found • For DRD related RIDs (section, page, etc) • For Architecture Element RIDs with no DRD referenced (chart, conversation, etc.) – Provides a sufficiently detailed recommended resolution – Stays within the scope of PDR expectations – For requirements, provides correct “from” language and recommends “to” language An issue that has not previously been identified. • What is a bad RID? – Incomplete issue identification – No recommended resolution – Recommended resolution of “fix this” – Editorial comment (spelling, grammar, etc.) – RID that expands on errata or duplicates a Pre-Declared RID – Post PDR level of maturity / unrealistic expectations – RID written against a baselined or reference document (Examples: SRD, S/C Spec) – RID entered by someone other than the original initiator without documenting the original initiator – RID written against a previously made project decision (VICB, CPCB, etc.) without new data or evidence to challenge the decision Don’t tell us something we already know!!!
  • 27. Right Sizing Your Design PM Challenge 2012 Review Plan Program/Project Design Review Approach • Planning • Technical & Peer Reviews • Component Design Reviews • Subsystem Design Reviews Focus on the Objective • System Level Reviews • Boards & Panels Evolve and Excel
  • 28. Boards & Panels • There are a number of boards and panels that can be implemented during a review process depending on the size and complexity of the review – Caucus Teams • Made up of the lower level review chair(s) and the key leads of products being reviewed – May be implemented for Subsystem design reviews and system level reviews – Not recommended for Tech/Peer reviews • Focus is to resolve issues (disposition actions) that arise in the review quickly allowing the team to not repeat the action later in the review and to facilitate the design team’s ability to rapidly start resolving the issue – Management Review Team • Made up of the Program Manager and key direct reports – May be implemented for Subsystem design reviews and system level reviews – Not recommended for Tech/Peer reviews • Focus is to resolve program level issues that extend beyond a Subsystem or IPT lead’s purview – Screening Team • Often led by systems engineering with key subject matter expert support • Focus is on quickly reviewing and bucket RIDs into categories (subsystems, orgs, etc.) for later disposition
  • 29. Boards & Panels • There are a number of boards and panels that can be implemented during a review process depending on the size and complexity of the review – Disposition Teams • Often led by IPT Leads with key subject matter expert support • Focus is on ensuring all open issues (RIDs/actions) are dispositioned and an effective path to closure is established – Pre-Board • Serves a preparatory board for the later review board • Often chaired by the Deputy Program/Project Manager, Chief Systems Engineer, or Chief Engineer • Focus is on: – Resolving and dispositioning elevated or disputed RIDs – Elevating unresolved issues to the Board – Identifying issues that need to go forward to the Board (due to significant cost, schedule, or technical impact/risk) – Providing the Initial evaluation of the project’s success in meeting the entrance/success criteria
  • 30. Boards & Panels • There are a number of boards and panels that can be implemented during a review process depending on the size and complexity of the review – Board • Chaired by the Program/Project Manager • Focus is on: – Resolving and dispositioning elevated or disputed RIDs – Evaluating the Project’s success in meeting the PDR success criteria – Approving the basis of and viable path for proceeding to the next life-cycle phase
  • 31. Boards and Panels • Key Lessons Learned – Caucuses • Resist the desire to include everyone – keep the team small and bring in key SMEs as needed – Helps ensure the process does not take longer than necessary • Allow for additional time post review to disposition any remaining issues/actions – Screening and Disposition Teams • Pay particular attention in selection Team leadership and identifying SMEs to support – Significant time can be lost by tracking down the correct person who understands the issue and can recommend a corrective action – Pre-Board and Board • Avoid the desire to start the Board the day after the System Level Reviews (be flexible) – A few days extra to resolve conflicts between design team and RID initiators can ensure the appropriate action is taken to resolve issues Ensure sufficient time to review RIDs/Actions Allow enough time to process all of the actions and roll up the action closure status from the lower level reviews
  • 32. Right Sizing Your Design PM Challenge 2012 Review Plan Summary • Time-line Example • Affordability • Conclusion Focus on the Objective Evolve and Excel
  • 33. Time-line Example Large Complex Program/Project* Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11 Month 12 Planning Work Product (Plans, Drawings, Rqmts, etc.) Tech / Peer Reviews Component Level Reviews Work Product Delivery (NLT 2 weeks prior to applicable SS/Sys Reviews) Work Product Review (outside of reviews ) Results (actions / RIDs) flowed into the applicable review for disposition System Level Review(s) (Environments, Etc.) Subsystem Level Reviews Caucuses Management Review Team System Level Review (Vehicle) Screening & Disposition Teams Reviews all open issues to date and ensures appropriate dispositions are developed Pre-Board Board Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11 Month 12 * Notional time-line – duration and number of design review elements dependent on many factors (Scope, complexity, volume of products to be reviewed, number of participants required, available time to conduct
  • 34. Right Sizing Your Design PM Challenge 2012 Review Plan Summary • Time-line example • Affordability • Conclusion Focus on the Objective Evolve and Excel
  • 35. Affordability • When planning and executing your design review affordability should remain a constant theme weaved throughout ensuring optimal solutions are chosen • Key areas to focus on: – Balance thoroughness and schedule • The desire to review every aspect of the design down to the lowest possible level must be balanced against the available time to execute the review as to not delay the development activities unnecessarily – Balance inclusion and efficiency • Develop a process that ensures all stakeholders have an adequate time to participate and provide input helping to shape the design, ensure mission success, and ultimately provide a safe crew exploration vehicle – Including stakeholders in the planning process – Review documents for duplication and remove or minimize early in program / project life cycle – Utilize ongoing lower level reviews to provide relevant insight as part of the larger major milestone review process (technical and peer reviews, component level design reviews, etc.)
  • 36. Affordability • Key areas to focus on: – Communicate expectations early and often to minimize lost time due to out of scope comments, actions, etc. – Ensure government/contractor joint development of process and associated expectations, including entry and success criteria – Consider work location, amount of travel needed, etc. when determining plan and choosing review locations – Overlay review schedule with program/project schedule and work to minimize disruptions and in ongoing program/project efforts – Track issues/actions throughout entire process to minimize duplication • Ensure adequate dispositions are developed the first time – Look to other programs/projects during planning phase • Take advantage of lessons learned • “Affordability remains the most significant issue facing the Agency and in particular human spaceflight.” – Heft Steering Committee • Future NASA space programs must be affordable, sustainable and realistic to survive political and funding dangers… - Charles Bolden, AIAA Conference Jan 2011
  • 37. Right Sizing Your Design PM Challenge 2012 Review Plan Summary • Time-line example • Affordability • Conclusion Focus on the Objective Evolve and Excel
  • 38. Keys to Review Success (Operational Excellence) • Teamwork – Create a joint NASA/Contractor Program Integration Team (PIT) to ensure common expectations are communicated across the NASA, Prime Contractor, and support contractor teams • Key personnel from each IPT should be included in team • Incorporate planning and C&DM personnel into team • Communication – Communicate early and often – Conduct a series of TIMs and Training Sessions with each of the leads (Subsystem/System) to develop common expectations and identify issues needing resolution prior to Review – Institute multiple statuses and forums targeting all stakeholders (memos, status meetings, etc.) • Commitment – Assigned a manager responsible for ensuring review success (NASA & Prime Contractor) – Routinely stress the importance of attaining the appropriate level of design maturity with the goal of “Get it right the 1st time” – Routinely communicate the review expectations and monitor status weekly • Accountability – Ensure Leads take ownership of their respective lower level review preparation and execution – Develop a detailed schedule to manage the reviews including data package review and delivery – Develop detailed metrics for tracking all deliverables by Component, Subsystem, and System 38
  • 39. Conclusion • Develop and execute a program/project technical life-cycle review (SRR, SDR, PDR, CDR) process that ensures NASA’s next generation products can meet all mission objectives and satisfy requirements with acceptable risk • Use lessons learned from previous Programs/Projects to develop a multi-tiered approach that ensures the integrated system (components, subsystems, system) is reviewed to ensure the design approach is at a sufficient level of maturity to proceed to the next life-cycle phase. – Expanded use of lower level design reviews (Design products / documentation Tech/Peer Reviews, Component Reviews, and Subsystem Reviews) help to ensure a thorough review while better integrating with ongoing program activities • When planning and executing your design review keep an eye on affordability
  • 40. Right Sizing Your Design PM Challenge 2012 Review Plan Questions ??? Focus on the Objective Evolve and Excel