The document describes NASA's Baseline Performance Review (BPR) process. The BPR:
- Monitors NASA's performance against its baseline plans on a monthly basis.
- Provides senior NASA leadership with integrated performance information on programs, projects, and institutional capabilities.
- Identifies performance trends, cross-cutting issues, and risks to help inform decision making.
Independent assessors from NASA offices analyze program and project performance using a "green/yellow/red" rating system. The BPR process involves monthly reporting from Mission Directorates and other offices, as well as analysis of risks, costs, schedules, and other metrics. The BPR is intended to improve NASA performance and communication across the agency
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Steven noneman
1. NASA Baseline
Performance Review
(BPR)
Steven Noneman, NASA HQ
Robert Woods, Perot Systems
Office of Program Analysis and
Evaluation
Office of the Chief Engineer
Program Management Challenge,
Galveston, TX
February 2010
Used with Permission
2. Presentation Purpose
• Describe NASA’s Baseline Performance Review
(BPR) to the greater NASA community at PM
Challenge 2010.
Characterize the BPR objectives, scope, process, and
products
Summarize NASA’s technique for monitoring Agency
performance against its baseline plans
2
4. BPR History and Context
• In the spring of 2006, the Office of the Chief Engineer (OCE) was given the action by the
Associate Administrator to develop a State of the Agency (SoA) process that provides the
Agency Project Management Council (APMC) an independent top level view of the status of
the Agency’s programs and projects.
• The first SoA presentation, to the Agency PMC, was by the Science Mission Directorate
(SMD) in August of 2006. The process has matured and continued to meet the objectives
outlined by the Associate Administrator, the Associate Deputy Administrator, the Chief
Engineer (CE) and the various stakeholders. The SoA evolved to a distinct monthly meeting
in December 2007 and was officially entitled the Baseline Performance Review (BPR).
• The BPR instituted a modified “balanced score card stop-light chart” process based on
metrics encompassed in a core set of functional area questions and supporting raw data.
• Participants from the projects, programs, Centers, Mission Directorates (MDs) and Mission
Support Offices respond monthly to each core area question based on provided thresholds
and key metrics for use in internal and external reporting.
• All Mission Directorates are reporting at the BPR meeting the findings of the independent
process.
5. BPR Objectives
• Provide NASA Senior Leadership comprehensive,
integrated, and objective information that describes the
“performance-to-plan” of the Agency’s programs,
projects, and institutional capabilities.
A single place to see the full execution context of the Agency
• Assure open cross-functional communications among
NASA’s organizations to enhance Agency performance.
• Identify and analyze performance trends and cross-
cutting or systemic issues and risks
• Serve the Agency’s decision making Councils as their
”execution arm”
Within the NASA Governance model, the BPR is distinct from
the decision-making Strategic Management, Program
Management, and Operations Management Councils
BPR is “action-oriented” to improve performance and inform
Agency decision authorities of issues needing attention.
5
6. BPR Scope and Participants
• The BPR is co-chaired by the NASA Associate Administrator and the
Associate Deputy Administrator.
• Membership includes the heads of NASA Staff Offices, Mission
Directorates, Mission Support Offices, and its ten Field Centers.
• Mission Support functions (e.g., finance, workforce, acquisition,
infrastructure, IT, etc.) report monthly and Small Business and
Diversity and Equal opportunity report quarterly.
• Mission Directorates (covering all program areas) report monthly with
one (and sometimes 2) “highlighted” in greater detail.
• The Office of the Chief Engineer (OCE) leads a team of “independent
assessors” from OCE, Program Analysis and Evaluation (PA&E), and
Office of Safety Mission Assurance that analyze programs’ and
projects’ performance.
“Green/Yellow/Red” criteria were established to assess of technical, cost,
schedule, and programmatic performance are provided monthly for all
Mission Directorates.
• PA&E provides the BPR Coordinator who manages the review by
setting agendas, tracking actions, and assisting the co-chairs, OCE,
and BPR participants.
6
7. BPR Detailed Process Flow
3
MD issue
charts
1 Mission MDs
Directorates
GYR rankings for
2 Mission Support projects and
OCE sends out Offices programs from the
OCE (OCE,
notifications to consolidates OSMA, and Assessor Group OCE
3
users who answer NASA Centers input from PA & E) generates
questions stakeholders Assessor BPR
1- 5 Group package
4
Programs
5 Technical
Projects X-Cutting, OCE
PCA Status reps. for
MDs
Non- Package
Technical briefing to
X-Cutting CE for
3
OCE feedback and approval
Action items on BPR PA & E
process BPR reps. for
OCE Package is
Package MDs
Provides available
presented Exe. Sum. for Read-
at the BPR
only
viewing
from site
8. Example Outcomes/Results
• Cross-cutting issues
Across missions, faulty material was discovered resulting in a mitigation
process for the materials use saving time and resources.
• Organizational communication issues
Turned a conflict between projects on thermal protection systems into a
collaboration between the major development projects who previously
were competing for shared resources.
• Mission support issues
Workforce planning resolution was expedited when a project was
confronted with changes resulting in 500 people at a Center
needing reassignment because the project was delayed 2 years.
• Senior leaders as an “Execution Board of Directors”
Leadership asked and Centers provided additional workforce during
transition to the NASA Support and Services Center because invoices
were not getting paid on time, which had been costing projects late fees.
• Mission specific issues
Timely communication resulted in a Center director de-conflicting a
vendors schedule between 2 NASA projects from different Centers.
9. BPR Project Questions
O
f
Mission Directorate
fi
c
e
o
Program
Project
f
GUIDANCE FOR R&T P
r
QUESTIONS THRESHOLDS PROGRAMS/ o
c
PROJECTS u
r
e
m
e
n
t COMMENTS
G R
* What is the status and level
G=Yes or <10%, of maturity of the research
Are your top level requirements(such as 10%<Y<=20% objectives?
requirements/objectives not * Have you baselined the
KPP's) or objectives stable and state of the art/knowledge and
stable or established/ Unknowns and lack of
established/baselined? baselined, R>20% are moving off this clarity with Lunar
requirements not stable or accordingly toward those requirements specific to
established/ baselined objectives? X Y X technology development.
G=Yes, Y<=20%
Are you on track to meet your top level requirements/ objectives not
requirements/ objectives? on track, R>20% requirements/
objectives not on track X G X
Has requirement feasability
Does the project/program have plans that been established and have
meet the needs/ objectives of the G=Yes, Y=minor weakness requirements flowed down
community customer? identified, R=major weakness with traceability from customer
identified needs? X G X
G=Yes, Y=minor weakness
Are the results of research/ technology being
identified, R=major weakness
widely disseminated?
identified X G X
G= On track to complete all
What is the readiness to support the next deliverables with no delay, R=
Review? Not on track for deliverables or
delay necessary X NA X
G= All actions complete, Y>=
What is the status of actions from the last
50% of actions complete, R <=
review?
50% of actions complete X NA X
9
10. BPR Project Questions
Currently, more than 1 risk is
G= All "green" or equivalent, Y= * Is the risk posture or your research
What is your overall risk status/ posture (i.e. risk plan/ 5 red.
Any "yellow" but no "red" or portfolio balanced and have you
x 5 matrix)? equivalent, R= Any "red" or identified the top risks to the success of
equivalent your research objectives? X R X
G= Can be resolved within
Are risks manageable and appropriate ( i.e. risk plan/ 5 available resources, Y= Can't be
x 5 matrix)? resolved by project but can with
other resources, R= Only
resolveable by Agency resources X G X
Are technologies sufficiently mature (i.e. TRL or
equivalent) at this point, or expected to be mature in G=yes, Y=one is no, R=more than
time, per program/ project plans? one no X G X
Will all the externally reported performance goals G=all req met, Y= 1 not met, R=
(Annual Performance Goals)be met? more than 1 not met X G X
Have the externally reported performance goals
changed within the current year? G=no, R=yes X G X
Are the externally reported performance goals per your
plan? G=yes, R=no X G X
G= no, Y= has changed once, R=
Has the life-cycle budget (LCB)/ top line budget
changed more than one time in
changed since last reported?
same phase or last 6 months X G X
G= no, Y= has changed once, R=
Has the current year funding changed since last
changed more than one time in
reported?
same phase or last 6 months X G X
Overrun 0<=G<5% LCB,
Are costs over/ under running your phasing plan? 5%LCB<=Y<10%LCB,
10%LCB<=R X G X
Is there a significant need to reallocate resources
between Centers in order to accomplish technical
tasks? G=no, R=yes X G X
Is the current year funding per the approved baseline 90<=G<100%, 80%<=Y<90%,
plan? R<80% X G X
What is the difference between your current estimate at Difference of 0<=G<5%, * Are the cost estimates for obtaining
completion and budget at completion? 5%<=Y<10%, 10%<=R your research objectives still valid? X G X
Are mechanisms in place and functioning properly to
ensure that NASA receives external funding and sends
out funding to others in proper time? G=no, R=yes X G X
For projects/ programs over $250M over 5 years, is the
project/ program cost per baseline plan and beneath NA
congressional limits (15% of Baseline plan)? 0<=G<5%, 5%<=Y<10%, 10%<=R X G X
10
11. BPR Project Questions
Are major milestones (per Integrated Master Schedule G=Next major milestone slippage less * Are the schedule estimates for
or equivalent) being met? or equal to 45 days, Y=Greater than 45 obtaining your major research
but less than 90, R= Greater than 90 objectives milestones still valid? X G X
* For those Outcomes/APGs that are
Are all GPRA milestones on schedule? also key milestones are they still on
G=Yes, Y= 30-60 days behind, R= track for completion per the annual
greater than 60 days behind performance plan? X G X
Has the schedule been significantly impacted since last G=No change, Y=Change but no
reported? schedule slippage, R=Change but with
schedule slippage X G X
For projects/ programs over $250M over 5 years, is the
project/ program under congressional limits for key G=Next major milestone slippage less NA
milestone slippage (less than 6 months)? or equal to 45 days, Y=Greater than 45
but less than 90, R= Greater than 90 X G X
Are all external agreements in place and executing per
plan? G = yes , R = no X G X
Are key partners delivering their commitments on time? G = yes , R = no X G X
Have key partners changed their commitments since
last reported? G = no , R = yes X G X
Are critical contracts in place and executing per plan? G = yes , R = no X G X
Are undefinitized contract actions within guidelines? G = yes , R = no X G X
X
Are existing facilities available (or do results of
required infrastructure assessment/business case
analysis show existing facilities are available to support G=Yes, Y=No - scheduling issue.
the activities)? R=No - need to refurb or build X G X
Are all critical staff and skills identified and available 90% Critical staff<=G<100%Critical
per plan? staff, 80%<=Y<90%, R<80% critical
staff X G X
Are all support staff and skills identified and available 90% Critical staff<=G<100%Critical
per plan? staff, 80%<=Y<90%, R<80% critical
staff X G X
G=Y, Y= 1 required document not
Are required documents per Agency and Center policy
complete, R> required document not
complete (i.e, FAD, PCA, Program/Project Plan)?
complete X G X
11
12. Sample BPR Agenda
10:00 Opening Remarks, Actions Associate Administrator, Coordinator
10:05 Recovery Implementation Status Recovery Act Implementation Team
10:15 Mission Support Reports
- Finance Office of the Chief Financial Officer
- Workforce Office of Human Capital Management
- Acquisition Office of Procurement
- Infrastructure Office of Infrastructure
11:30 Highlighted Mission Support: Small Business Programs* Office of Small Business Programs
12:00 Lunch
12:15 Agency Aggregate Assessments
OSMA Safety Assessment: NASA Mishap Posture Office of Safety and Mission Assurance
Cross Cutting Non-Technical Issues Program Analysis and Evaluation
- Special Topic: 2nd Quarter OMB Cost/Schedule Report
Cross Cutting Technical Issues Office of the Chief Engineer
- Special Topic: Flight S/W Complexity Jet Propulsion Lab
Documents Compliance Office of the Chief Engineer
Life Cycle Milestone Schedule Office of the Chief Engineer
Center Summaries (Programs/Projects and Institutional) Center Representatives
2:45 Roll-up of MD Programs/Projects Office of the Chief Engineer
- JWST Project On-going Status/Recovery Plans Science Mission Directorate
3:30 Highlighted Mission Directorate Office of the Chief Engineer
Space Ops Mission Directorate (SOMD) Assessment* Space Operations Mission Directorate
Launch Services Program Status/Recovery Plan Space Operations Mission Directorate
4:45 Action Summary Coordinator
5:00 Adjourn *Specific topic is rotated Associate Administrator
12
13. Samples of BPR Analysis Content
• Finance
• Workforce
• Acquisition
• Small Business
• Infrastructure
• Safety and Mishaps
• Crosscutting Issues
• Field Center Summaries
• Independent Assessments of Programs and Projects
(“Stoplight” ratings)
13
16. Undefinitized Contract Action (UCA) Status
February 27 – March 27, 2009
16
14
1 $1.3B
12
Number of UCAs
4 $27M
10
8
6
$836M
4 8
9
2 1 $35M
2 1 $3.5M
4
0 1 $700K 1 1
$749K
10
1
2
3
4
5
6
7
8
9
er
er
er
er
er
er
er
er
er
er
t
t
t
t
t
t
t
t
t
en
en
en
en
en
en
en
en
en
t
en
C
C
C
C
C
C
C
C
C
C
1-180 Days 180-360 Days >360 Days
17. FY08 Federal Agency
Prime Small Business Dollars Overview
Top Seven Agencies w/o DOD
General Services
Administration
Department of Justice
Department of Homeland
Security
Department of Veterans SB Dollars
Affairs Total Dollars Obligated
National Aeronautics & Space
Administration
Health and Human Services
Department of Energy
$0 $5,000 $10,000 $15,000 $20,000 $25,000
In Million $
Total Dollars Small Business Dollars
18. BPR: I&A Functional Areas
ARC DFRC GRC GSFC JPL JSC KSC LaRC MSFC SSC Remarks
Facilities
JSC damage from Ike could impact JWST Project.. Chamber A MOU
G G G G G Y G G G G and Management Plan not complete. Concern about communication
Design & Construction between Eng Div and Facil Div at JSC
Facility repair backlog is 8.6% of facility value with increasing
Y Y Y Y Y R Y Y Y Y trend.JSC damage from Ike could impact SOMD Operations
Facility Maintenance
DFRC, KSC, and SSC were changed to yellow since they have not
G Y G Y G Y Y G Y Y submitted revised Master Plans. GSFC presented new Master Plan,
Planning/Real Estate but has not submitted document for formal approval.
Logistics
Delay in replacement of critical civil service personnel at GRC and
KSC. Also at KSC, a concern existed as retiring civil servants
positions were not backfilled. Situation improved by increased use of
G G Y G G G G Y G Y Support Services Contractors. Sinlge point failure for multiple
logistics functions at LaRC and SSC. Anticipated hire at SSC
Supply currently on hold.
Delay in replacement of critical civil service personnel at GRC and
KSC. GRC expects to fill vacancy by end of 2008. At KSC, a concern
existed as retiring civil servants positions were not backfilled.
G G Y G NA G G Y G Y Situation improved by increased use of Support Services
Contractors. Single point failure for multiple log functions at LaRC and
SSC. Anticipated hire at SSC currently on hold. GSFC filled HQ
Equipment SEMO position.
CFO management control findings related to property management
are being addressed, however center IPO staffing concerns to support
transition workload and FAR update present an on-going staffing
Y Y Y Y Y Y Y Y Y Y issue. JSC in process of filling Contract Property Administrator
position. JSC also submitted request to fill the following: 2 positions
for Property Disposal, 1 position for Shuttle Clerical (Property) and 1
position for Packing/Shipping in Transportation.
Contract Property
Agency risk for not meeting EO 13423 (alternate fuel): discussions
with MSFC to resolve center contribution ongoing. Single point failure
for multiple log functions at SSC, anticipated hire currently on hold.
G G G Y G G G Y Y Y GSFC loss of CNG capability for approx. 13 vehicles. KSC added
additional contractor to assist with transportation functions. At LaRC,
TO/SEMO is one person, he will be out in Jan. (medical leave) no
Transportation replacement appointed.
Increase in excess property workload due to Shuttle and Hubble
G G G Y G Y Y G Y Y disposition at GSFC, MSFC, KSC, SSC & JSC. Single point failure
Property Disposal for multiple log functions at SSC.
19. NASA and Contractor Safety Statistics
Dashboards
February Mishap
OCO
Jan 2008 – Mar 2008 Jan 2009 - Mar 2009 Jan 2008 – Mar 2008 Jan 2009 - Mar 2009 Jan 2008 - Mar 2008 Jan 2009 - Mar 2009
March Mishaps:
• No Type A Mishaps
• One Type B Mishap: DRC- (Deluge System Release in Shuttle Hangar - 3/13/09)
• One Potential Type B Mishap: DRC- (Global Hawk Electronics Failure 3/12/09) – currently a Type D
Data does not include 4/2/09 Type B Mishap: Water Drill mishap resulting in multiple amputations
Close Call Incidents Show An Increase From Previous Reporting Period (Jan – Mar 2008).
20. False Material Certification Status as of: Date x, 200x
• Issue Description: Company xyz, manufacturer of a material used in flight hardware, was indicted on federal
charges of issuing false material certifications for supplies they sold. Material of uncertain pedigree may
have been used by NASA projects.
Mission Directorate Impact
MD 1 MD 2 MD 3 MD 4
• Cleared: LRO, LCROSS, Ares • Suspect material found in • Suspect material found
• No use of Suspect
I-X, J2-X, Orion PA-1, HRP Kepler spacecraft in a on the Taurus and Delta
material determined as ISS Experiments & ETDP IV vehicles used by
critical area wherein failure
yet • No other project could be catastrophic. OCO, Glory, and NRO L-
• Supplier traceability assessments required • Suspect material also found 26.
investigation still in the AIA instrument on • NRO mission cleared.
underway SDO. • SSP & ISS cleared.
• Other projects are • LSP - All vehicles now
investigating usage. cleared.
Information on Agency Actions and Status (Estimated Completion) POC: Ken Ledbetter
• The Kepler project procured material from Company xyz who obtained some of the material from Company xxx Inc, including
the material for the Telescope Spider Hub Assembly. Company xyz had 46 different material procurements. The Kepler
project performed tests on residual material at xyz and confirmed that it was sufficient to satisfy their mission application.
• GIDEP indicates earliest occurrence was no later than 2002 with the latest false certification in 7/03 for a purchase order in
11/04 by Company xyz.
• SDO project also found suspect material in the AIA instrument. AIA has now been cleared.
• Centers responding with evaluations on a project-by-project basis.
• Top Level Description/ Status: Material found to have uncertain pedigree due to false certifications. Extent of usage
in NASA projects and resulting impact, are under investigation.
21. Agency Programs: PCA Status
Highlight indicates change from previous report
MD Formulation Implementation
SMD Astrophysics Planetary Science Astrophysics
Physics of the Cosmos G Discovery (8/19/08) Y SOFIA (7/26/07)
Cosmic Origins Y Mars Exploration (1/26/07) G Hubble Space Telescope (2/27/09)
G New Frontiers (3/18/08) G Fermi (formerly GLAST) (8/18/08)
Planetary Science Heliophysics G James Webb Space Telescope (3/17/09)
G
Lunar Quest Explorer (2/2/09) G ExoPlanet Exploration (4/14/09)
G Living with a Star (8/25/08) Earth Science
G New Millennium (10/6/08) G Earth Systematic Missions (4/14/08)
Y Solar Terrestrial Probes (12/21/07) G ESSP (4/25/08)
ESMD Constellation (in G Human Research (5/21/07) Rev A in Rev Lunar Precursor Robotic (Waived requirement)
development; expect Technology Development (10/21/07)
G
approval at KDP-II)
ARMD
G Airspace Systems (9/14/2007) G Fundamental Aeronautics (5/21/07)
G Aviation Safety (9/17/2007) G Aeronautics Test (5/21/07)
SOMD G ISS (8/01/08) G SSP (1/26/07)
G LSP (1/28/08) G SCaN (10/16/08)
G RPT (1/23/09) G TDRS K/L (4/18/07)
CHSP (waived requirement)
PCA Status Legend Dates are last signed PCA
G = Signed PCA with no update required Y = MD has identified for update R = No signed PCA BLACK = NA
February 2010 21
23. NASA Monthly Baseline Performance Review (BPR)
GSFC Center Summary Input
Highlights from 11/17/2009
Programs/Projects Technical Authority/Mission Support/Institutional
Summary Performance Institutional Risk to Mission
ESMD:
ESP Budget/Finance:
LRO – Supported LCROSS Lunar Impact, data being analyzed. Grants reconciliation and transition: The ORR for the Phase 2 transition
Transition to SSMO will occur in December. to NSSC is scheduled for November 30th; will complete GSFC transition
SMD: activities.
HST- SM4 SMOV activities complete. Workforce:
– Working possible options to increase FY10 reserves. OTE Early Career Hiring: FY09 - 66 on-board; FY10 – 10 with an additional
CDR complete. 10 offers accepted and negotiating dates.
GLORY- Successful CMC and ESD rebaseline reviews conducted. LV
actions being worked prior to DPMC.
Acquisition:
GPM – Re-planned road to KDP-C. Working toward Mission CDR Aerospace Corp. Support: Consolidated Agency contracting approach
planned for December 14-17th. being pursued. GSFC had restricted authorization to use the existing GSFC
LDCM contract for critical tasks ending in December. “Authorization” to seek
services on the Airforce contract granted but is not expected to save
NPP - Systemic issues with systems engineering and mission resources and requires unnecessary actions.
assurance escapes on IPO-provided instruments reduce confidence in
Instrument life expectancy to be less than the 5-year design life. SCNS contract protest activities continue. NENS contract has been
MMS – S Band antenna height change complete. Swedish Univ, KTH extended through April 2010. The delayed transition from NENS to SCNS
ability to deliver Spin Plane Probe Electric Field Instruments. continues to impact the contractor’s ability to retain experienced employees
to perform the work.
RBSP–Schedule delays are being worked. • Agency-level protests denied on August 11th and the Corrective Action
SDO – LRD is 2/3/2010. AIA Hopa Circuit anomaly. Plan (CAP) implementation was initiated on August 17th.
SAM – Power Distribution Box is integrated onto the flight suite. • A protest was submitted on August 21st to GAO with regard to the CAP.
GOES-R – ITT performance on ABI. CAP implementation permitted to continue. GAO decision due NLT
November 30th.
NOAA Climate Sensors • Congressional request for information with regard to the CAP was
SOMD: submitted October 22nd.
Ground Network Space Network- See Acquisition, SCNS.
TDRS – Continue to Work with BSS regarding requirements flow-down
to subcontractors.
SGSS – RFP development activities continue.
ELC – Successful SMSR October 23rd. Decks #1 and #2 were
Launched November 16th.
February 2010 23
24. SMD Overview
November 2009
Status:
– 2 project rated Red overall: NPP, SOFIA
– 4 projects rated Yellow overall: JWST, MSL, Juno, Glory
– SOFIA changed from Yellow to Red due to eroding schedule, cost issues & delay in rebaseline APMC.
– Juno progress degraded from Green to Yellow; Glory returned to Yellow pending replan DPMC.
– Replan DPMCs pending on Glory, Aquarius, & MSL.
– MRO in safemode due to computer resets; Restarts unsuccessful for Last IceSat laser failure
Technical Schedule
Planetary: MSL actuators. MRO safemode implications on Astrophysics:
developing missions using heritage avionics (e.g. Juno, Earth Sci: Glory Taurus XL return to flight schedule. Potential
GRAIL, MAVEN) further NPP launch delays from instrument rework.
All: Continued difficulties developing instruments; Implications
from usage of Western Titanium.
Cost Programmatic
Planetary: Funding of MSL slip severely impacts division All: Access to Space continues to be an issue: Delta II
Astrophysics: Overall division budget issues, esp JWST. replacement; Taurus XL failure, & impact on Glory. Very
crowded launch manifest in fall 2011.
Watch list Items:
Uncertainty of SMAP launch date for project planning
February 2010 For NASA Internal Use Only 24
25. ESMD Projects Status Roll Up Continued
2009 Month A B C D
COMMENTS
S O N S O N S O N S O N
Y Y G
Successful Launch!! October 28, 2009 at 11:30 am ET
Post-Flight Data Review working group will meet twice a
week to review progress of data collection and reduction
Ares I-X The first stage solid rocket motor recovered; hardware
disposition is in progress; data recorder removed and
shipped to Lockheed Martin. Lockheed Martin who will
provide best and final set of all flight data from a
combination of data from telemetry and the on-board
recorder
Lunar Insufficient funds in PMR09 budget to meet HLR in 2020.
Surface Constrained to “study only” after FY2010.
Systems
February 2010 25
26. PSD Budget Reporting Matrix (11/16/09)
External Internal
Project MPAR OMB Qtrly
(Baseline) IBPD (FY10)*1 (4QFY09) PCA/PRLA/other*2
Development $968.6 $1,631.0 $1,719.9 $1657 ₃
MSL LCC $1,642.2 $2,299.3 $2,394.3 $2,318.5
LRD Sep 2009 Oct 2011 Nov-11 Oct-11
Development $427.0 $427.0 $427.0 $407.7
GRAIL LCC $496.2 $465.6M* $496.2 $468.2
LRD Sep 2011 Sep 2011 Sep 2011 Sep 2011
Development $742.3 $742.3 $742.3 $695.3
JUNO LCC $1,107.0 $1,091.9M* $1,107.0 $1,050.0
LRD Aug 2011 Aug 2011 Aug 2011 Aug-11
*1 - IBPD is updated through N2 automatically and as of 4-15-9 N2 has not been updated to reflect
the FY09 Op Plan Changes nor the GRAIL and Juno KDP-C decisions.
*2 - The PCA (Program Commitment Agreement) is located in Science Works under Requirements
Management system, Planetary Science, Program, Key Document PCA, and KPD
*3 - MSL project assumes an approved $13.4M adjustment from Phase E to Phase C/D, which is
NOT included in the $1657M internal development number.
26
27. Oct Nov
JWST YY Y
Status: In Phase C
Y Technical: G Schedule:
• NIRCam off-axis image quality • WATCH: Low near-term reserves pose a
• NIRSpec microshutter separation - decision threat to LRD.
to change coating
R Cost: G Programmatic:
• FY'10 reserves negative & FY'11 reserves
only 0.9%
• Project requested $20M addition to FY'10
reserves. HQ told project to continue to fund
JSC facility mod, with decision on extra $20M
in 4-6 weeks.
28. Summary
• NASA Senior Management monitors Agency-Wide
performance monthly through its baseline Performance
Review (BPR) Process
Each Program area is assessed quarterly on a rotating basis
• The automated tool is coming online at MSFC
• BPR continues to evolve and improve
30. BPR Actions and Status
7.23.2009 BPR Meeting
• 2009-07-026: PA&E – Revisit the FY09 Q3 Contract reporting chart
to clarify the way the information is being conveyed. (E.g. Contract
base value apparent misalignment with LCC.)
Due: October 2009 BPR
Status: Propose to CLOSE. PA&E has met with ESMD to identify how
to add clarity to this reporting. ESMD will provide additional
information that clarifies the contract values. Interim information was
presented in September BPR by PA&E. ESMD has provided data from
the Ares I and Orion. Language has been added to the contract chart to
explain what contracts are and are not included in contract reporting to
OMB.
32. Green Criteria
A Category for a Project is Green if:
There are minimal programmatic issues and adequate margin (budget reserve,
schedule slack, technical margin), or capability (for operational missions), to
complete the Project on plan.
A Project is Green overall if:
All 4 categories are Green, or
One or more are Yellow and the issues are collectively not a threat/impact to the
project by virtue of their being solvable within the project's planned resources.
(Margin in one category may provide capability to resolve a lack of margin in another
category.)
A Program is Green if:
The constituent projects are Green overall, or are Yellow with realistic, defined plans
to return to green and all other program elements are on budget and schedule.
33. Yellow Criteria
A Category for a Project is Yellow if:
The remaining margin within the category appears inadequate to meet Project
requirements or external commitments, however, mitigation plans are in place or in
development to recover margin and achieve commitments within the available
resources of the Project. (For operational projects in the technical category "margin"
may be interpreted as operational capabilities.)
A Project is Yellow overall if:
Any one category is Red, the overall is at least Yellow, or
One or more categories are Yellow and the issues are collectively a threat to the
project's ability to meet their commitments within the project's planned resources.
A Program is Yellow if:
Any of its constituent projects are Red overall, or if one or more are Yellow and the
issues are collectively a threat to the Program's ability to meet its commitments
within planned resources.
34. Red Criteria
A Category for a Project is Red if:
There is minimal margin or negative margin within the category such that the
Project is estimated not to meet its requirements or commitments without significant
impact to other categories. There is high risk that the Project will require external
resources or relief from performance or programmatic requirements.
A Project is Red overall if:
One or more categories are Red, and it is estimated that the Project will not have
sufficient resources to meet its commitments.
A Program is Red if:
Most of its constituent projects are Red overall, or if one or more are Red and the
issues are collectively a threat to the Program's ability to meet its commitments.
35. Assessment Rubric for Space Flight Projects and Multi-Project Programs
Cost Schedule Technical Programmatic
Cost estimates remain consistent with cost Schedule progress remains consistent with Technical progress remains consistent with Programmatic performance remains consistent
commitments: schedule commitments: technical commitments: with program/project requirements:
-- Formulation: Current estimated -- Formulation: The current estimated -- Formulation: The project/program is -- Formulation: An approved FAD is in place and
formulation costs are consistent with the authority-to-proceed to implementation date is making planned progress in developing planned progress is being made in completing
program FAD. at or before the FAD. technical design, reliability, safety, and risk programmatic arrangements necessary to enter
-- Development: Current estimated LCC at -- Development: Current estimated operational mitigation requirements necessary to development as planned.
completion is at or below the LCC readiness date (ORD) is at or before the ORD proceed to implementation as planned. -- Development: Top-level objectives and
commitment. For multi-project programs, the commitment. For multi-project programs, the -- Development: Technical requirements programmatic requirements in the plan are stable
current cost estimate by year for the current estimated schedule for planned start are stable and progress and risk and programmatic capabilities are being
program’s projects, including reserve, is dates for future projects is consistent with the management is consistent with plan while developed/ managed as planned. Plans are
within the 5 year cost run-out in the program program plan. maintaining safety. For multi-project consistent with 7120.5 or necessary waivers are
plan. The program is consistently executing -- Operations: Planned operations, including programs, any lack of planned technical in place. A multi-project program is effectively
its projects within their cost cap or maintenance, are proceeding on schedule. progress at the project level is not resulting managing its projects, with new projects
commitment. and there are minimal issues and adequate in an increased risk to the program’s beginning per the Program Plan.
-- Operations: Annual operational costs are schedule margin to complete the Program or technical commitments and objectives. -- Operations. Operational requirements are
at or below planned costs for these Project on plan: -- Operations: Operational systems are stable consistent with plan, and operations are
operations --Funded schedule reserves & phasing are delivering the planned level of services and being managed as planned. Retirement/ transition
and there are minimal issues and adequate consistent with plan and are being drawn down reliability, with a general trend towards plans are being developed/ implemented
cost margin (budget reserve) to complete at a rate consistent with plan and emergent improved safety, and efficiency. consistent with the timing for these events.
the Program or Project on plan: schedule risks/threats. For multi-project and there are minimal issues and adequate and there are minimal issues and adequate
-Lifecycle cost reserves are consistent with programs, any faster-than-planned project technical margin to complete the Program programmatic flexibility to complete the Program
plan and are being drawn down at a rate draw-down of schedule reserve is not or Project on plan: or Project on plan:
consistent with plan and emergent cost impinging on the ability of the program to meet -- Technical reserves are being drawn down --Key contract actions are being undertaken and
risks/threats. For multi-project programs, its overall schedule commitments. are consistent with plan; technical completed as planned. The multi-project
reserves are being managed consistent with --Key interim milestones (KDP as well as WBS difficulties/risks encountered are typical for program’s acquisition strategy (both contracted
the annual reserves planned for each milestones) being met. this type of project/program and are being and in-house) is resulting in the timely start of
project. -- For multi-project programs, any delay in mitigated or controlled as required to make projects and delivery of project elements.
-- The project/program will not require project schedule is not jeopardizing inputs planned technical progress. --Key critical workforce, access to key facilities,
additional funds to complete the current required for another project or resulting in an -- Are consistent with the requirements of EVM, and management systems are in place
fiscal year with required carryover. increased risk to the program’s schedule safety, reliability & quality assurance, and consistent with plan.
-- Phasing of cost reserves are consistent commitments. incorporate good systems engineering & --Key partnerships are in place and operating as
with emergent risks or threats. -- External partners are providing key integration practice. planned; external requirements are stable; and
-- Current year budget level and timing of deliverables on schedule. -- External partners are making planned there are no other factors external to the
funds distribution are consistent with plan or technical progress and external events project/program (e.g., new Agency requirements)
commitments are not threatened as a result (e.g., import approvals) are not altering which are significantly disrupting planned
of any or delay in current year funding. technical requirements. project/program management.
-- External partners are providing key -- For operational projects, the ground and
resources as planned. in-flight hardware is operating satisfactorily
on prime or backup units and mission
requirements are being met.
36. Assessment Rubric for Space Flight Projects and Multi-Project Programs (continued)
Cost Schedule Technical Programmatic
In general, the program or project follows In general, the program or project follows the In general, the program or project follows In general, programmatic performance remains
the green assessment guidelines, green assessment guidelines, but the green assessment guidelines, consistent with program/project
but cost commitments are now schedule commitments are now but technical commitments are now requirements for a green assessment, but
threatened. threatened. threatened: remaining programmatic flexibility may be
Remaining cost margin appears inadequate Remaining schedule margin appears Remaining technical margins appear inadequate to meet requirements due to
to meet requirements due to one or inadequate to meet requirements due inadequate to meet requirements one or more of the following programmatic
more of the following deviations from
to one or more of the following due to one or more of the following deviations from plan however, mitigation
plan, however, mitigation plans are
deviations from plan, however, technical deviations from plan plans are in place or in development to
in place or in development to
mitigation plans are in place or in however, mitigation plans are in recover margin and achieve commitments
recover margin and achieve
development to recover margin and place or in development to recover within the planned resources:
commitments within the planned
achieve commitments within the margin and achieve commitments -- Key contract actions are not being undertaken
resources of the Program or Project:
planned resources: within the planned resources: or completed as planned.
-- Lifecycle cost reserves (including those
-- Schedule reserves are being drawn down -- Technical reserves are being drawn down -- A multi-project program’s acquisition strategy
held at the program level) are being
faster than planned or as required for at a rate inconsistent with plan; or (both contracted and in-house) is not
drawn down faster than planned or
emergent schedule risks/threats. technical difficulties/risks resulting in the timely start of projects and
required for emergent cost
-- Key interim milestones (KDP and/or WBS encountered exceed those which delivery of project elements.
risks/threats.
milestones) have slipped. are typical for this type of -- Key critical workforce, access to key facilities,
-- Phasing of cost reserves are inconsistent
-- For multi-project programs, delay in project project/program or are not being EVM, and management systems are not
with emergent risks or threats.
schedules is resulting in an increased mitigated or controlled as required consistent with plan..
-- Current year cost growth is exceeding
risk to the program’s schedule to make planned technical progress. -- Key partnerships are not in place or operating
planned current year cost reserves
commitments. -- Are not consistent in some key areas with as planned; external requirements are not
and will require a re-phasing of the
-- External partners are delayed in providing the requirements of safety, reliability stable; or there are other factors external
annual budget in order to complete
key deliverables or external factors are & quality assurance, and the to the project/program (e.g., new Agency
the fiscal year with required
delaying completion of a key milestone. incorporation of good systems requirements) which are significantly
carryover.
engineering & integration practice. disrupting planned project/program
-- A reduction in current year budget or
-- External partners are not making planned management.
slow- down in funds distribution will
technical progress or external
require the project/program to
events (e.g., import approvals) are
rephrase future year annual costs.
altering technical requirements.
-- External partner changes or factors
-- For operational projects, ground or flight
external to the project/program are
capabilities have been curtailed, but
placing additional pressure on
plans are in work to recover the
project/program costs.
capability or develop a workaround
-- For operating missions, in flight anomalies
such that mission requirements will
are draining cost reserves.
still be met.
37. Assessment Rubric for Space Flight Projects and Multi-Project Programs (continued)
Cost Schedule Technical Programmatic
The Program or Project is estimated not to The Program or Project is estimated not to The Program or Project is estimated not to The Program or Project is estimated not to be
meet its cost commitments without meet its schedule commitments without meet its technical requirements able to meet its requirements due to
significant impact to other significant impact to other categories. without significant impact to other programmatic issues affecting the other
categories. The key end-of-phase KDP milestones categories:. categories.
Depending on phase, the project's are unlikely to be met. A project in formulation is not making the A formulation project has failed to make the
formulation costs, or development For multi-project programs, the planned start- technical progress required to enter programmatic progress required to be
costs, or annual operating costs up of future projects is delayed beyond development. confirmed for development.
are exceeding the planned budget program commitments or objectives. For a project in development, technical A development project lacks an approved plan or
beyond all planned reserves. For operations missions, the current failures or delays preclude the has failed to implement that plan
For multi-project programs, total annual operations schedule is insufficient to project from being able to meet its consistent with meeting its commitments.
costs for the program’s projects meet project commitments or the technical requirements and The multi-project program lacks an
exceed the program’s 5 year mission failed prior to the planned end- commitments. approved PCA or project plan, or has
planned run-out, including reserves. of-operations date. For multi-project There is minimal or negative technical failed to implement the projects require to
There is minimal or negative cost margin programs: The current operations margin such that there is high risk meet its commitments.
such that there is high risk that the schedule is insufficient to meet that the Program or Project will There is limited or no programmatic flexibility such
Program or Project will require program commitments or the failure of require additional technical that there is high risk that the Program or
additional funding or relief from one or missions prior to the planned resources or relief from performance Project will require relief from performance
performance or programmatic end date has resulted in the project not or programmatic requirements due or programmatic requirements due to one
requirements due to one or more of being able to meet its commitments or to one or more of the following or more of the following deviations from
the following deviations from plan for objectives. technical deviations from plan for plan for which the project/ program has
a realistic recovery strategy has not There is minimal or negative schedule margin which the project or program has not identified a realistic strategy for
been identified: is such that there is high risk that the not identified a realistic strategy for recovery:
-- Lifecycle cost reserves (including those Program or Project will require recovery: --Key contract actions are not being undertaken
held at the program level) are being additional schedule or relief from -- Technical reserves are being drawn down or completed as required. The multi-
drawn down at an unsustainable performance or programmatic at an unsustainable rate or project program’s acquisition strategy
rate and remaining reserves are requirements due to one or more of the emergent technical difficulties, risks, (both contracted and in-house) is not
insufficient given emergent following deviations from plan for which or threats are not being resolved as resulting in the timely start of projects and
risks/threats. a realistic strategy for recovery has not required to meet the technical delivery of project elements.
-- Phasing of cost reserves are inconsistent been identified: commitments. --Key critical workforce, availability of key
with emergent risks or threats. -- Schedule reserves are being drawn down at -- Are not consistent with the requirements facilities, EVM, and management systems
-- Current year cost growth exceeds an unsustainable rate and remaining of safety, reliability & quality are missing or inconsistent with meeting
planned costs and cannot be reserves are insufficient given assurance, and the incorporation of the project’s commitments.
accommodated by rephrasing emergent risks/threats. good systems engineering & --Key planned partnerships did not materialize,
annual costs. -- A slip of one or more key interim milestones integration practice. quit or not to delivering consistent with
-- A reduction or delay in current year (KDP and/or WBS milestones) is -- Lack of technical progress by external project/program commitments; unstable or
funding is inconsistent with inconsistent with the planned ORD. partners or external events (e.g., newly emergent external requirements are
maintaining the overall LCC For programs, delay in project import approvals) are inconsistent not implementable; or other external
commitment. schedules is inconsistent with with meeting the project/program developments are inconsistent with the
-- A loss of key external partners or program’s schedule commitments. technical requirements, project/program commitments.
resources is inconsistent with -- An external partner delays or delays caused commitments, or objectives, or
keeping the project or program by other external factors are additional/different external cannot
within planned costs. inconsistent with the planned ORD. be met within plan.
-- For operational projects, in-flight For multi-project programs, delays -- For operational missions, in-flight
anomalies have drained all cost caused by external factors are anomalies have used up
reserves and the project will need inconsistent with the program’s redundancy and made it unlikely
more funds to complete the prime schedule commitments. that the mission will achieve its
mission. mission requirements.
38. BPR Process Organizational
Structure As of June 3, 2008
Associate Administrator
And Associate Deputy
Administrator
Chief
Engineer
Division Chief for
Engineering and
Program & Project
Management
BPR
Team Lead
February 2010 For NASA Internal Use Only 38
39. BPR Process Organizational
Structure As of June 3, 2008
BPR
Executive
Secretariat Team Lead
PA&E Technical OSMA OCE Admin Center OCE MD P&P
Team Lead Cross-Cutting Team Lead Support POC’s Assessment
Team Lead
Institutional Non- Special Topic / Program Mission Mission OSMA PA&E
Assessment Technical Root Cause & Directorate Centers Support Assessor Assessor
Team Lead Cross Cutting Analysis Lead Projects (*) Offices
(One representative
from each MD)
MSO
Representatives
I&A
IT
OCFO
OHCM
OPII
PROC
(*) One representative from each
February 2010 For NASA Internal Use Only 39
40. Primary BPR Deliverables
• Monthly meeting BPR presentation package
• Executive summary and pre-brief
• Meeting Summary Notes and Post-brief
• Executive Summary for the Administrator and Deputy Administrator
• Meeting Actions List and tracking
40