SlideShare una empresa de Scribd logo
1 de 40
Descargar para leer sin conexión
NASA Baseline
Performance Review
       (BPR)
      Steven Noneman, NASA HQ
     Robert Woods, Perot Systems
     Office of Program Analysis and
                Evaluation
      Office of the Chief Engineer

       Program Management Challenge,
               Galveston, TX
               February 2010


             Used with Permission
Presentation Purpose


•   Describe NASA’s Baseline Performance Review
    (BPR) to the greater NASA community at PM
    Challenge 2010.
       Characterize the BPR objectives, scope, process, and
        products
       Summarize NASA’s technique for monitoring Agency
        performance against its baseline plans




                                                               2
Contents


•   BPR History
•   BPR Objectives
•   BPR Scope, Participants
•   BPR Process
•   Sample BPR Meeting Agenda
•   Sample BPR Analysis Content
•   Summary




                                  3
BPR History and Context

• In the spring of 2006, the Office of the Chief Engineer (OCE) was given the action by the
  Associate Administrator to develop a State of the Agency (SoA) process that provides the
  Agency Project Management Council (APMC) an independent top level view of the status of
  the Agency’s programs and projects.
• The first SoA presentation, to the Agency PMC, was by the Science Mission Directorate
  (SMD) in August of 2006. The process has matured and continued to meet the objectives
  outlined by the Associate Administrator, the Associate Deputy Administrator, the Chief
  Engineer (CE) and the various stakeholders. The SoA evolved to a distinct monthly meeting
  in December 2007 and was officially entitled the Baseline Performance Review (BPR).
• The BPR instituted a modified “balanced score card stop-light chart” process based on
  metrics encompassed in a core set of functional area questions and supporting raw data.
• Participants from the projects, programs, Centers, Mission Directorates (MDs) and Mission
  Support Offices respond monthly to each core area question based on provided thresholds
  and key metrics for use in internal and external reporting.
• All Mission Directorates are reporting at the BPR meeting the findings of the independent
  process.
BPR Objectives


•   Provide NASA Senior Leadership comprehensive,
    integrated, and objective information that describes the
    “performance-to-plan” of the Agency’s programs,
    projects, and institutional capabilities.
       A single place to see the full execution context of the Agency
•   Assure open cross-functional communications among
    NASA’s organizations to enhance Agency performance.
•   Identify and analyze performance trends and cross-
    cutting or systemic issues and risks
•   Serve the Agency’s decision making Councils as their
    ”execution arm”
       Within the NASA Governance model, the BPR is distinct from
        the decision-making Strategic Management, Program
        Management, and Operations Management Councils
       BPR is “action-oriented” to improve performance and inform
        Agency decision authorities of issues needing attention.
                                                                         5
BPR Scope and Participants

•   The BPR is co-chaired by the NASA Associate Administrator and the
    Associate Deputy Administrator.
•   Membership includes the heads of NASA Staff Offices, Mission
    Directorates, Mission Support Offices, and its ten Field Centers.
•   Mission Support functions (e.g., finance, workforce, acquisition,
    infrastructure, IT, etc.) report monthly and Small Business and
    Diversity and Equal opportunity report quarterly.
•   Mission Directorates (covering all program areas) report monthly with
    one (and sometimes 2) “highlighted” in greater detail.
•   The Office of the Chief Engineer (OCE) leads a team of “independent
    assessors” from OCE, Program Analysis and Evaluation (PA&E), and
    Office of Safety Mission Assurance that analyze programs’ and
    projects’ performance.
        “Green/Yellow/Red” criteria were established to assess of technical, cost,
         schedule, and programmatic performance are provided monthly for all
         Mission Directorates.
•   PA&E provides the BPR Coordinator who manages the review by
    setting agendas, tracking actions, and assisting the co-chairs, OCE,
    and BPR participants.
                                                                                      6
BPR Detailed Process Flow

                                                                                                         3
                                                                                                               MD issue
                                                                                                               charts
                           1    Mission                                                           MDs
                                Directorates
                                                                                           GYR rankings for
                           2   Mission Support                                             projects and
OCE sends out                  Offices                                                     programs from the
                                                   OCE                      (OCE,
notifications to                                   consolidates             OSMA, and      Assessor Group         OCE
                           3
users who answer               NASA Centers        input from               PA & E)                               generates
questions                                          stakeholders             Assessor                              BPR
                                                   1- 5                     Group                                 package
                           4
                                Programs

                           5                                              Technical
                                Projects                                  X-Cutting,         OCE
                                                                          PCA Status       reps. for
                                                                                             MDs
                                                                               Non-                               Package
                                                                               Technical                          briefing to
                                                                               X-Cutting                          CE for
                                                                      3
         OCE feedback and                                                                                         approval
         Action items on BPR                                                                  PA & E
         process                                                  BPR                        reps. for
                                                    OCE           Package is
                                  Package                                                      MDs
                                                  Provides        available
                                 presented       Exe. Sum.        for Read-
                                 at the BPR
                                                                  only
                                                                  viewing
                                                                  from site
Example Outcomes/Results

•   Cross-cutting issues
       Across missions, faulty material was discovered resulting in a mitigation
        process for the materials use saving time and resources.
•   Organizational communication issues
       Turned a conflict between projects on thermal protection systems into a
        collaboration between the major development projects who previously
        were competing for shared resources.
•   Mission support issues
       Workforce planning resolution was expedited when a project was
        confronted with changes resulting in 500 people at a Center
        needing reassignment because the project was delayed 2 years.
•   Senior leaders as an “Execution Board of Directors”
       Leadership asked and Centers provided additional workforce during
        transition to the NASA Support and Services Center because invoices
        were not getting paid on time, which had been costing projects late fees.
•   Mission specific issues
       Timely communication resulted in a Center director de-conflicting a
        vendors schedule between 2 NASA projects from different Centers.
BPR Project Questions
                                                                                                                 O
                                                                                                                 f




                                                                                                                                                       Mission Directorate
                                                                                                                 fi
                                                                                                                 c
                                                                                                                 e
                                                                                                                 o




                                                                                                                                         Program
                                                                                                                          Project
                                                                                                                 f
                                                                                GUIDANCE FOR R&T                 P
                                                                                                                 r
             QUESTIONS                              THRESHOLDS                     PROGRAMS/                     o
                                                                                                                 c
                                                                                    PROJECTS                     u
                                                                                                                 r
                                                                                                                 e
                                                                                                                 m
                                                                                                                 e
                                                                                                                 n
                                                                                                                 t                                                           COMMENTS
                                              G                                                                                     R
                                                                                * What is the status and level
                                                       G=Yes or <10%,             of maturity of the research
 Are your top level requirements(such as                10%<Y<=20%                        objectives?
                                                requirements/objectives not        * Have you baselined the
     KPP's) or objectives stable and                                           state of the art/knowledge and
                                                   stable or established/                                                                                                    Unknowns and lack of
          established/baselined?                     baselined, R>20%                 are moving off this                                                                    clarity with Lunar
                                                 requirements not stable or        accordingly toward those                                                                  requirements specific to
                                                   established/ baselined                 objectives?                 X             Y              X                         technology development.
                                                       G=Yes, Y<=20%
   Are you on track to meet your top level      requirements/ objectives not
          requirements/ objectives?           on track, R>20% requirements/
                                                   objectives not on track                                            X             G              X
                                                                                 Has requirement feasability
Does the project/program have plans that                                         been established and have
    meet the needs/ objectives of the            G=Yes, Y=minor weakness          requirements flowed down
           community customer?                 identified, R=major weakness with traceability from customer
                                                           identified                       needs?                    X             G              X
                                                 G=Yes, Y=minor weakness
Are the results of research/ technology being
                                               identified, R=major weakness
            widely disseminated?
                                                           identified                                                 X             G              X
                                                 G= On track to complete all
  What is the readiness to support the next   deliverables with no delay, R=
                    Review?                   Not on track for deliverables or
                                                       delay necessary                                                X             NA             X
                                               G= All actions complete, Y>=
  What is the status of actions from the last
                                              50% of actions complete, R <=
                    review?
                                                  50% of actions complete                                             X             NA             X




                                                                                                                                                                                                        9
BPR Project Questions
                                                                                                                                                           Currently, more than 1 risk is
                                                               G= All "green" or equivalent, Y=     * Is the risk posture or your research
What is your overall risk status/ posture (i.e. risk plan/ 5                                                                                               red.
                                                                Any "yellow" but no "red" or           portfolio balanced and have you
                       x 5 matrix)?                             equivalent, R= Any "red" or       identified the top risks to the success of
                                                                          equivalent                       your research objectives?           X   R   X
                                                             G= Can be resolved within
Are risks manageable and appropriate ( i.e. risk plan/ 5 available resources, Y= Can't be
                      x 5 matrix)?                        resolved by project but can with
                                                             other resources, R= Only
                                                         resolveable by Agency resources                                                       X   G   X
   Are technologies sufficiently mature (i.e. TRL or
 equivalent) at this point, or expected to be mature in G=yes, Y=one is no, R=more than
           time, per program/ project plans?                          one no                                                                   X   G   X

   Will all the externally reported performance goals          G=all req met, Y= 1 not met, R=
          (Annual Performance Goals)be met?                          more than 1 not met                                                       X   G   X
   Have the externally reported performance goals
             changed within the current year?                           G=no, R=yes                                                            X   G   X
Are the externally reported performance goals per your
                           plan?                                        G=yes, R=no                                                            X   G   X

                                                               G= no, Y= has changed once, R=
    Has the life-cycle budget (LCB)/ top line budget
                                                                changed more than one time in
              changed since last reported?
                                                                 same phase or last 6 months                                                   X   G   X
                                                               G= no, Y= has changed once, R=
   Has the current year funding changed since last
                                                                changed more than one time in
                      reported?
                                                                 same phase or last 6 months                                                   X   G   X
                                                                   Overrun 0<=G<5% LCB,
   Are costs over/ under running your phasing plan?                 5%LCB<=Y<10%LCB,
                                                                        10%LCB<=R                                                              X   G   X
   Is there a significant need to reallocate resources
   between Centers in order to accomplish technical
                          tasks?                                      G=no, R=yes                                                              X   G   X
 Is the current year funding per the approved baseline          90<=G<100%, 80%<=Y<90%,
                           plan?                                         R<80%                                                                 X   G   X
What is the difference between your current estimate at            Difference of 0<=G<5%,          * Are the cost estimates for obtaining
         completion and budget at completion?                      5%<=Y<10%, 10%<=R                your research objectives still valid?      X   G   X
 Are mechanisms in place and functioning properly to
ensure that NASA receives external funding and sends
         out funding to others in proper time?                          G=no, R=yes                                                            X   G   X
For projects/ programs over $250M over 5 years, is the
 project/ program cost per baseline plan and beneath                                                                 NA
     congressional limits (15% of Baseline plan)?      0<=G<5%, 5%<=Y<10%, 10%<=R                                                              X   G   X

                                                                                                                                                                                    10
BPR Project Questions

Are major milestones (per Integrated Master Schedule G=Next major milestone slippage less             * Are the schedule estimates for
              or equivalent) being met?              or equal to 45 days, Y=Greater than 45            obtaining your major research
                                                     but less than 90, R= Greater than 90             objectives milestones still valid?         X   G   X
                                                                                                    * For those Outcomes/APGs that are
        Are all GPRA milestones on schedule?                                                         also key milestones are they still on
                                                              G=Yes, Y= 30-60 days behind, R=        track for completion per the annual
                                                              greater than 60 days behind                     performance plan?                  X   G   X
Has the schedule been significantly impacted since last    G=No change, Y=Change but no
                     reported?                          schedule slippage, R=Change but with
                                                                  schedule slippage                                                              X   G   X
For projects/ programs over $250M over 5 years, is the
  project/ program under congressional limits for key G=Next major milestone slippage less                           NA
       milestone slippage (less than 6 months)?        or equal to 45 days, Y=Greater than 45
                                                       but less than 90, R= Greater than 90                                                      X   G   X

Are all external agreements in place and executing per
                        plan?                                           G = yes , R = no                                                         X   G   X
Are key partners delivering their commitments on time?                  G = yes , R = no                                                         X   G   X
 Have key partners changed their commitments since
                   last reported?                                       G = no , R = yes                                                         X   G   X
Are critical contracts in place and executing per plan?                 G = yes , R = no                                                         X   G   X
 Are undefinitized contract actions within guidelines?                  G = yes , R = no                                                         X   G   X
                                                                                                                                             X
    Are existing facilities available (or do results of
  required infrastructure assessment/business case
analysis show existing facilities are available to support      G=Yes, Y=No - scheduling issue.
                     the activities)?                            R=No - need to refurb or build                                                  X   G   X

 Are all critical staff and skills identified and available    90% Critical staff<=G<100%Critical
                          per plan?                            staff, 80%<=Y<90%, R<80% critical
                                                                               staff                                                             X   G   X

Are all support staff and skills identified and available 90% Critical staff<=G<100%Critical
                       per plan?                          staff, 80%<=Y<90%, R<80% critical
                                                                          staff                                                                  X   G   X
                                                           G=Y, Y= 1 required document not
Are required documents per Agency and Center policy
                                                          complete, R> required document not
  complete (i.e, FAD, PCA, Program/Project Plan)?
                                                                       complete                                                                  X   G   X



                                                                                                                                                             11
Sample BPR Agenda

10:00   Opening Remarks, Actions                                       Associate Administrator, Coordinator
10:05   Recovery Implementation Status                                 Recovery Act Implementation Team
10:15   Mission Support Reports
        - Finance                                                      Office of the Chief Financial Officer
        - Workforce                                                    Office of Human Capital Management
        - Acquisition                                                  Office of Procurement
         - Infrastructure                                              Office of Infrastructure
11:30   Highlighted Mission Support: Small Business Programs*          Office of Small Business Programs
12:00   Lunch
12:15   Agency Aggregate Assessments
        OSMA Safety Assessment: NASA Mishap Posture                    Office of Safety and Mission Assurance
        Cross Cutting Non-Technical Issues                             Program Analysis and Evaluation
        - Special Topic: 2nd Quarter OMB Cost/Schedule Report
        Cross Cutting Technical Issues                                 Office of the Chief Engineer
        - Special Topic: Flight S/W Complexity                         Jet Propulsion Lab
        Documents Compliance                                           Office of the Chief Engineer
        Life Cycle Milestone Schedule                                  Office of the Chief Engineer
        Center Summaries (Programs/Projects and Institutional)         Center Representatives
2:45    Roll-up of MD Programs/Projects                                Office of the Chief Engineer
         - JWST Project On-going Status/Recovery Plans                 Science Mission Directorate
3:30    Highlighted Mission Directorate                                Office of the Chief Engineer
        Space Ops Mission Directorate (SOMD) Assessment*                Space Operations Mission Directorate
        Launch Services Program Status/Recovery Plan                   Space Operations Mission Directorate
4:45    Action Summary                                                 Coordinator
5:00    Adjourn                           *Specific topic is rotated   Associate Administrator
                                                                                                                12
Samples of BPR Analysis Content


•   Finance
•   Workforce
•   Acquisition
•   Small Business
•   Infrastructure
•   Safety and Mishaps
•   Crosscutting Issues
•   Field Center Summaries
•   Independent Assessments of Programs and Projects
    (“Stoplight” ratings)



                                                       13
For NASA Internal Use Only   14
Workforce Metrics




                    15
Undefinitized Contract Action (UCA) Status
                  February 27 – March 27, 2009

                 16
                 14
                                                                         1   $1.3B

                 12
Number of UCAs




                                                                         4   $27M
                 10

                  8
                  6
                                                                             $836M
                  4                                                                                                8
                                                                         9
                  2         1    $35M


                            2            1   $3.5M
                                                                                     4
                  0                      1   $700K             1                               1
                                 $749K




                                                                                                                         10
                        1


                                    2


                                               3


                                                           4


                                                                     5


                                                                               6


                                                                                           7


                                                                                                     8


                                                                                                               9
                      er


                                  er


                                             er


                                                         er


                                                                   er


                                                                             er


                                                                                         er


                                                                                                   er


                                                                                                             er


                                                                                                                       er
                     t


                                   t


                                            t


                                                        t


                                                                  t


                                                                            t


                                                                                        t


                                                                                                   t


                                                                                                            t
                  en


                                en


                                         en


                                                     en


                                                               en


                                                                         en


                                                                                     en


                                                                                                en


                                                                                                         en



                                                                                                                      t
                                                                                                                   en
                 C


                            C


                                         C


                                                     C


                                                               C


                                                                         C


                                                                                     C


                                                                                               C


                                                                                                         C


                                                                                                                   C
                                                     1-180 Days       180-360 Days             >360 Days
FY08 Federal Agency
            Prime Small Business Dollars Overview
                                 Top Seven Agencies w/o DOD
           General Services
            Administration

       Department of Justice

    Department of Homeland
           Security
     Department of Veterans     SB Dollars
            Affairs             Total Dollars Obligated
National Aeronautics & Space
       Administration

  Health and Human Services


       Department of Energy

                           $0              $5,000            $10,000           $15,000   $20,000   $25,000

                                                                In Million $


                                      Total Dollars       Small Business Dollars
BPR: I&A Functional Areas
                         ARC DFRC   GRC GSFC   JPL JSC KSC LaRC   MSFC   SSC                                 Remarks
Facilities
                                                                               JSC damage from Ike could impact JWST Project.. Chamber A MOU
                         G    G     G    G     G    Y   G   G      G     G     and Management Plan not complete. Concern about communication
 Design & Construction                                                         between Eng Div and Facil Div at JSC
                                                                               Facility repair backlog is 8.6% of facility value with increasing
                          Y   Y      Y   Y     Y    R   Y   Y      Y      Y    trend.JSC damage from Ike could impact SOMD Operations
 Facility Maintenance
                                                                               DFRC, KSC, and SSC were changed to yellow since they have not
                         G    Y     G    Y     G    Y   Y   G      Y      Y    submitted revised Master Plans. GSFC presented new Master Plan,
 Planning/Real Estate                                                          but has not submitted document for formal approval.
Logistics
                                                                                Delay in replacement of critical civil service personnel at GRC and
                                                                               KSC. Also at KSC, a concern existed as retiring civil servants
                                                                               positions were not backfilled. Situation improved by increased use of
                         G    G      Y   G     G    G   G   Y      G      Y    Support Services Contractors. Sinlge point failure for multiple
                                                                               logistics functions at LaRC and SSC. Anticipated hire at SSC
 Supply                                                                        currently on hold.
                                                                               Delay in replacement of critical civil service personnel at GRC and
                                                                               KSC. GRC expects to fill vacancy by end of 2008. At KSC, a concern
                                                                               existed as retiring civil servants positions were not backfilled.
                         G    G      Y   G     NA   G   G   Y      G      Y    Situation improved by increased use of Support Services
                                                                               Contractors. Single point failure for multiple log functions at LaRC and
                                                                               SSC. Anticipated hire at SSC currently on hold. GSFC filled HQ
 Equipment                                                                     SEMO position.
                                                                               CFO management control findings related to property management
                                                                               are being addressed, however center IPO staffing concerns to support
                                                                               transition workload and FAR update present an on-going staffing
                          Y   Y      Y   Y     Y    Y   Y   Y      Y      Y    issue. JSC in process of filling Contract Property Administrator
                                                                               position. JSC also submitted request to fill the following: 2 positions
                                                                               for Property Disposal, 1 position for Shuttle Clerical (Property) and 1
                                                                               position for Packing/Shipping in Transportation.
 Contract Property
                                                                               Agency risk for not meeting EO 13423 (alternate fuel): discussions
                                                                               with MSFC to resolve center contribution ongoing. Single point failure
                                                                               for multiple log functions at SSC, anticipated hire currently on hold.
                         G    G     G    Y     G    G   G   Y      Y      Y    GSFC loss of CNG capability for approx. 13 vehicles. KSC added
                                                                               additional contractor to assist with transportation functions. At LaRC,
                                                                               TO/SEMO is one person, he will be out in Jan. (medical leave) no
 Transportation                                                                replacement appointed.
                                                                               Increase in excess property workload due to Shuttle and Hubble
                         G    G     G    Y     G    Y   Y   G      Y      Y    disposition at GSFC, MSFC, KSC, SSC & JSC. Single point failure
 Property Disposal                                                             for multiple log functions at SSC.
NASA and Contractor Safety Statistics
                                 Dashboards


                                   February Mishap
                                   OCO




Jan 2008 – Mar 2008   Jan 2009 - Mar 2009      Jan 2008 – Mar 2008   Jan 2009 - Mar 2009   Jan 2008 - Mar 2008   Jan 2009 - Mar 2009



      March Mishaps:
      • No Type A Mishaps
      • One Type B Mishap: DRC- (Deluge System Release in Shuttle Hangar - 3/13/09)
      • One Potential Type B Mishap: DRC- (Global Hawk Electronics Failure 3/12/09) – currently a Type D
      Data does not include 4/2/09 Type B Mishap: Water Drill mishap resulting in multiple amputations
      Close Call Incidents Show An Increase From Previous Reporting Period (Jan – Mar 2008).
False Material Certification                                                      Status as of: Date x, 200x
• Issue Description: Company xyz, manufacturer of a material used in flight hardware, was indicted on federal
 charges of issuing false material certifications for supplies they sold. Material of uncertain pedigree may
 have been used by NASA projects.

          Mission Directorate Impact
           MD 1                                 MD 2                             MD 3                            MD 4
                               • Cleared: LRO, LCROSS, Ares          • Suspect material found in        • Suspect material found
• No use of Suspect
                                 I-X, J2-X, Orion PA-1, HRP            Kepler spacecraft in a             on the Taurus and Delta
  material determined as         ISS Experiments & ETDP                                                   IV vehicles used by
                                                                       critical area wherein failure
  yet                          • No other project                      could be catastrophic.             OCO, Glory, and NRO L-
• Supplier traceability          assessments required                • Suspect material also found        26.
  investigation still                                                  in the AIA instrument on         • NRO mission cleared.
  underway                                                             SDO.                             • SSP & ISS cleared.
                                                                     • Other projects are               • LSP - All vehicles now
                                                                       investigating usage.               cleared.

Information on Agency Actions and Status (Estimated Completion)                                      POC: Ken Ledbetter
  • The Kepler project procured material from Company xyz who obtained some of the material from Company xxx Inc, including
    the material for the Telescope Spider Hub Assembly. Company xyz had 46 different material procurements. The Kepler
    project performed tests on residual material at xyz and confirmed that it was sufficient to satisfy their mission application.
  • GIDEP indicates earliest occurrence was no later than 2002 with the latest false certification in 7/03 for a purchase order in
    11/04 by Company xyz.
  • SDO project also found suspect material in the AIA instrument. AIA has now been cleared.
  • Centers responding with evaluations on a project-by-project basis.




 • Top Level Description/ Status: Material found to have uncertain pedigree due to false certifications. Extent of usage
   in NASA projects and resulting impact, are under investigation.
Agency Programs: PCA Status
                                                       Highlight indicates change from previous report
  MD                  Formulation                                                                     Implementation
SMD       Astrophysics                                      Planetary Science                             Astrophysics
          Physics of the Cosmos                    G        Discovery (8/19/08)                       Y   SOFIA (7/26/07)
          Cosmic Origins                           Y        Mars Exploration (1/26/07)                G   Hubble Space Telescope (2/27/09)
                                                   G        New Frontiers (3/18/08)                   G   Fermi (formerly GLAST) (8/18/08)
          Planetary Science                                 Heliophysics                              G   James Webb Space Telescope (3/17/09)
                                                   G
          Lunar Quest                                       Explorer (2/2/09)                         G   ExoPlanet Exploration (4/14/09)
                                                   G        Living with a Star (8/25/08)                  Earth Science
                                                   G        New Millennium (10/6/08)                  G   Earth Systematic Missions (4/14/08)
                                                   Y        Solar Terrestrial Probes (12/21/07)       G   ESSP (4/25/08)




ESMD      Constellation (in                        G        Human Research (5/21/07) Rev A in Rev         Lunar Precursor Robotic (Waived requirement)
          development; expect                               Technology Development (10/21/07)
                                                   G
          approval at KDP-II)

ARMD
                                                   G        Airspace Systems (9/14/2007)              G   Fundamental Aeronautics (5/21/07)
                                                   G        Aviation Safety (9/17/2007)               G   Aeronautics Test (5/21/07)


SOMD                                               G        ISS (8/01/08)                             G   SSP (1/26/07)
                                                   G        LSP (1/28/08)                             G   SCaN (10/16/08)
                                                   G        RPT (1/23/09)                             G   TDRS K/L (4/18/07)
                                                            CHSP (waived requirement)
PCA Status Legend      Dates are last signed PCA

  G    = Signed PCA with no update required             Y     = MD has identified for update      R   = No signed PCA     BLACK = NA

February 2010                                                                                                                                    21
Agency Review Schedule




February 2010         For NASA Internal Use Only
NASA Monthly Baseline Performance Review (BPR)
                                                    GSFC Center Summary Input
                                                              Highlights from 11/17/2009

                          Programs/Projects                                       Technical Authority/Mission Support/Institutional
                          Summary Performance                                                     Institutional Risk to Mission
  ESMD:
    ESP                                                                    Budget/Finance:
    LRO – Supported LCROSS Lunar Impact, data being analyzed.                   Grants reconciliation and transition: The ORR for the Phase 2 transition
  Transition to SSMO will occur in December.                               to NSSC is scheduled for November 30th; will complete GSFC transition
  SMD:                                                                     activities.
    HST- SM4 SMOV activities complete.                                     Workforce:
               – Working possible options to increase FY10 reserves. OTE       Early Career Hiring: FY09 - 66 on-board; FY10 – 10 with an additional
  CDR complete.                                                            10 offers accepted and negotiating dates.
     GLORY- Successful CMC and ESD rebaseline reviews conducted. LV
  actions being worked prior to DPMC.
                                                                           Acquisition:
     GPM – Re-planned road to KDP-C. Working toward Mission CDR                Aerospace Corp. Support: Consolidated Agency contracting approach
  planned for December 14-17th.                                            being pursued. GSFC had restricted authorization to use the existing GSFC
     LDCM                                                                  contract for critical tasks ending in December. “Authorization” to seek
                                                                           services on the Airforce contract granted but is not expected to save
     NPP - Systemic issues with systems engineering and mission            resources and requires unnecessary actions.
  assurance escapes on IPO-provided instruments reduce confidence in
  Instrument life expectancy to be less than the 5-year design life.           SCNS contract protest activities continue. NENS contract has been
     MMS – S Band antenna height change complete. Swedish Univ, KTH        extended through April 2010. The delayed transition from NENS to SCNS
  ability to deliver Spin Plane Probe Electric Field Instruments.          continues to impact the contractor’s ability to retain experienced employees
                                                                           to perform the work.
     RBSP–Schedule delays are being worked.                                • Agency-level protests denied on August 11th and the Corrective Action
    SDO – LRD is 2/3/2010. AIA Hopa Circuit anomaly.                       Plan (CAP) implementation was initiated on August 17th.
    SAM – Power Distribution Box is integrated onto the flight suite.      • A protest was submitted on August 21st to GAO with regard to the CAP.
   GOES-R – ITT performance on ABI.                                        CAP implementation permitted to continue. GAO decision due NLT
                                                                           November 30th.
    NOAA Climate Sensors                                                   • Congressional request for information with regard to the CAP was
  SOMD:                                                                    submitted October 22nd.
    Ground Network           Space Network- See Acquisition, SCNS.
    TDRS – Continue to Work with BSS regarding requirements flow-down
  to subcontractors.
      SGSS – RFP development activities continue.
      ELC – Successful SMSR October 23rd. Decks #1 and #2 were
  Launched November 16th.

February 2010                                                                                                                                       23
SMD Overview
                     November 2009




  Status:
      – 2 project rated Red overall: NPP, SOFIA
      – 4 projects rated Yellow overall: JWST, MSL, Juno, Glory
      – SOFIA changed from Yellow to Red due to eroding schedule, cost issues & delay in rebaseline APMC.
      – Juno progress degraded from Green to Yellow; Glory returned to Yellow pending replan DPMC.
      – Replan DPMCs pending on Glory, Aquarius, & MSL.
      – MRO in safemode due to computer resets; Restarts unsuccessful for Last IceSat laser failure

  Technical                                                            Schedule
  Planetary: MSL actuators. MRO safemode implications on               Astrophysics:
  developing missions using heritage avionics (e.g. Juno,              Earth Sci: Glory Taurus XL return to flight schedule. Potential
  GRAIL, MAVEN)                                                        further NPP launch delays from instrument rework.
  All: Continued difficulties developing instruments; Implications
  from usage of Western Titanium.

   Cost                                                                Programmatic
   Planetary: Funding of MSL slip severely impacts division            All: Access to Space continues to be an issue: Delta II
   Astrophysics: Overall division budget issues, esp JWST.             replacement; Taurus XL failure, & impact on Glory. Very
                                                                       crowded launch manifest in fall 2011.

     Watch list Items:
                Uncertainty of SMAP launch date for project planning


February 2010                                            For NASA Internal Use Only                                                24
ESMD Projects Status Roll Up Continued
2009 Month          A        B            C           D
                                                                                          COMMENTS

                S   O   N   S O   N   S   O   N   S       O   N
                                                  Y       Y   G
                                                                  Successful Launch!! October 28, 2009 at 11:30 am ET

                                                                  Post-Flight Data Review working group will meet twice a
                                                                  week to review progress of data collection and reduction

Ares I-X                                                          The first stage solid rocket motor recovered; hardware
                                                                  disposition is in progress; data recorder removed and
                                                                  shipped to Lockheed Martin. Lockheed Martin who will
                                                                  provide best and final set of all flight data from a
                                                                  combination of data from telemetry and the on-board
                                                                  recorder
  Lunar                                                           Insufficient funds in PMR09 budget to meet HLR in 2020.
 Surface                                                            Constrained to “study only” after FY2010.
 Systems




February 2010                                                                                                                25
PSD Budget Reporting Matrix (11/16/09)
                                                External                             Internal
         Project                MPAR                             OMB Qtrly
                              (Baseline)      IBPD (FY10)*1       (4QFY09)      PCA/PRLA/other*2
         Development            $968.6          $1,631.0          $1,719.9            $1657 ₃
  MSL    LCC                   $1,642.2         $2,299.3          $2,394.3           $2,318.5
         LRD                   Sep 2009         Oct 2011           Nov-11             Oct-11

       Development              $427.0           $427.0            $427.0             $407.7
 GRAIL LCC                      $496.2          $465.6M*           $496.2             $468.2
       LRD                     Sep 2011         Sep 2011          Sep 2011           Sep 2011

         Development            $742.3           $742.3            $742.3             $695.3
 JUNO    LCC                   $1,107.0        $1,091.9M*         $1,107.0           $1,050.0
         LRD                   Aug 2011         Aug 2011          Aug 2011            Aug-11

*1 - IBPD is updated through N2 automatically and as of 4-15-9 N2 has not been updated to reflect
the FY09 Op Plan Changes nor the GRAIL and Juno KDP-C decisions.
*2 - The PCA (Program Commitment Agreement) is located in Science Works under Requirements
Management system, Planetary Science, Program, Key Document PCA, and KPD
*3 - MSL project assumes an approved $13.4M adjustment from Phase E to Phase C/D, which is
NOT included in the $1657M internal development number.


                                                                                                    26
Oct Nov
                                                JWST                                YY     Y


Status: In Phase C




 Y      Technical:                                 G    Schedule:

 • NIRCam off-axis image quality                  • WATCH: Low near-term reserves pose a
 • NIRSpec microshutter separation - decision     threat to LRD.
 to change coating




 R      Cost:                                      G    Programmatic:
• FY'10 reserves negative & FY'11 reserves
only 0.9%
• Project requested $20M addition to FY'10
reserves. HQ told project to continue to fund
JSC facility mod, with decision on extra $20M
in 4-6 weeks.
Summary


•   NASA Senior Management monitors Agency-Wide
    performance monthly through its baseline Performance
    Review (BPR) Process
       Each Program area is assessed quarterly on a rotating basis
•   The automated tool is coming online at MSFC
•   BPR continues to evolve and improve
Backup Charts




                29
BPR Actions and Status

7.23.2009 BPR Meeting
• 2009-07-026: PA&E – Revisit the FY09 Q3 Contract reporting chart
   to clarify the way the information is being conveyed. (E.g. Contract
   base value apparent misalignment with LCC.)
   Due: October 2009 BPR

   Status: Propose to CLOSE. PA&E has met with ESMD to identify how
   to add clarity to this reporting. ESMD will provide additional
   information that clarifies the contract values. Interim information was
   presented in September BPR by PA&E. ESMD has provided data from
   the Ares I and Orion. Language has been added to the contract chart to
   explain what contracts are and are not included in contract reporting to
   OMB.
Assessment Color Criteria
Green Criteria

 A Category for a Project is Green if:
 There are minimal programmatic issues and adequate margin (budget reserve,
schedule slack, technical margin), or capability (for operational missions), to
complete the Project on plan.

 A Project is Green overall if:
 All 4 categories are Green, or
 One or more are Yellow and the issues are collectively not a threat/impact to the
project by virtue of their being solvable within the project's planned resources.
(Margin in one category may provide capability to resolve a lack of margin in another
category.)

 A Program is Green if:
 The constituent projects are Green overall, or are Yellow with realistic, defined plans
to return to green and all other program elements are on budget and schedule.
Yellow Criteria

A Category for a Project is Yellow if:
The remaining margin within the category appears inadequate to meet Project
requirements or external commitments, however, mitigation plans are in place or in
development to recover margin and achieve commitments within the available
resources of the Project. (For operational projects in the technical category "margin"
may be interpreted as operational capabilities.)

A Project is Yellow overall if:
Any one category is Red, the overall is at least Yellow, or
One or more categories are Yellow and the issues are collectively a threat to the
project's ability to meet their commitments within the project's planned resources.

A Program is Yellow if:
Any of its constituent projects are Red overall, or if one or more are Yellow and the
issues are collectively a threat to the Program's ability to meet its commitments
within planned resources.
Red Criteria

A Category for a Project is Red if:
There is minimal margin or negative margin within the category such that the
Project is estimated not to meet its requirements or commitments without significant
impact to other categories. There is high risk that the Project will require external
resources or relief from performance or programmatic requirements.

A Project is Red overall if:
One or more categories are Red, and it is estimated that the Project will not have
sufficient resources to meet its commitments.

A Program is Red if:
Most of its constituent projects are Red overall, or if one or more are Red and the
issues are collectively a threat to the Program's ability to meet its commitments.
Assessment Rubric for Space Flight Projects and Multi-Project Programs



                   Cost                                          Schedule                                          Technical                                       Programmatic
Cost estimates remain consistent with cost       Schedule progress remains consistent with          Technical progress remains consistent with        Programmatic performance remains consistent
commitments:                                     schedule commitments:                              technical commitments:                            with program/project requirements:
-- Formulation: Current estimated                -- Formulation: The current estimated              -- Formulation: The project/program is            -- Formulation: An approved FAD is in place and
formulation costs are consistent with the        authority-to-proceed to implementation date is     making planned progress in developing             planned progress is being made in completing
program FAD.                                     at or before the FAD.                              technical design, reliability, safety, and risk   programmatic arrangements necessary to enter
-- Development: Current estimated LCC at         -- Development: Current estimated operational      mitigation requirements necessary to              development as planned.
completion is at or below the LCC                readiness date (ORD) is at or before the ORD       proceed to implementation as planned.             -- Development: Top-level objectives and
commitment. For multi-project programs, the      commitment. For multi-project programs, the        -- Development: Technical requirements            programmatic requirements in the plan are stable
current cost estimate by year for the            current estimated schedule for planned start       are stable and progress and risk                  and programmatic capabilities are being
program’s projects, including reserve, is        dates for future projects is consistent with the   management is consistent with plan while          developed/ managed as planned. Plans are
within the 5 year cost run-out in the program    program plan.                                      maintaining safety. For multi-project             consistent with 7120.5 or necessary waivers are
plan. The program is consistently executing      -- Operations: Planned operations, including       programs, any lack of planned technical           in place. A multi-project program is effectively
its projects within their cost cap or            maintenance, are proceeding on schedule.           progress at the project level is not resulting    managing its projects, with new projects
commitment.                                      and there are minimal issues and adequate          in an increased risk to the program’s             beginning per the Program Plan.
-- Operations: Annual operational costs are      schedule margin to complete the Program or         technical commitments and objectives.             -- Operations. Operational requirements are
at or below planned costs for these              Project on plan:                                   -- Operations: Operational systems are            stable consistent with plan, and operations are
operations                                       --Funded schedule reserves & phasing are           delivering the planned level of services and      being managed as planned. Retirement/ transition
and there are minimal issues and adequate        consistent with plan and are being drawn down      reliability, with a general trend towards         plans are being developed/ implemented
cost margin (budget reserve) to complete         at a rate consistent with plan and emergent        improved safety, and efficiency.                  consistent with the timing for these events.
the Program or Project on plan:                  schedule risks/threats. For multi-project          and there are minimal issues and adequate         and there are minimal issues and adequate
-Lifecycle cost reserves are consistent with     programs, any faster-than-planned project          technical margin to complete the Program          programmatic flexibility to complete the Program
plan and are being drawn down at a rate          draw-down of schedule reserve is not               or Project on plan:                               or Project on plan:
consistent with plan and emergent cost           impinging on the ability of the program to meet    -- Technical reserves are being drawn down        --Key contract actions are being undertaken and
risks/threats. For multi-project programs,       its overall schedule commitments.                  are consistent with plan; technical               completed as planned. The multi-project
reserves are being managed consistent with       --Key interim milestones (KDP as well as WBS       difficulties/risks encountered are typical for    program’s acquisition strategy (both contracted
the annual reserves planned for each             milestones) being met.                             this type of project/program and are being        and in-house) is resulting in the timely start of
project.                                         -- For multi-project programs, any delay in        mitigated or controlled as required to make       projects and delivery of project elements.
-- The project/program will not require          project schedule is not jeopardizing inputs        planned technical progress.                       --Key critical workforce, access to key facilities,
additional funds to complete the current         required for another project or resulting in an    -- Are consistent with the requirements of        EVM, and management systems are in place
fiscal year with required carryover.             increased risk to the program’s schedule           safety, reliability & quality assurance, and      consistent with plan.
-- Phasing of cost reserves are consistent       commitments.                                       incorporate good systems engineering &            --Key partnerships are in place and operating as
with emergent risks or threats.                  -- External partners are providing key             integration practice.                             planned; external requirements are stable; and
-- Current year budget level and timing of       deliverables on schedule.                          -- External partners are making planned           there are no other factors external to the
funds distribution are consistent with plan or                                                      technical progress and external events            project/program (e.g., new Agency requirements)
commitments are not threatened as a result                                                          (e.g., import approvals) are not altering         which are significantly disrupting planned
of any or delay in current year funding.                                                            technical requirements.                           project/program management.
-- External partners are providing key                                                              -- For operational projects, the ground and
resources as planned.                                                                               in-flight hardware is operating satisfactorily
                                                                                                    on prime or backup units and mission
                                                                                                    requirements are being met.
Assessment Rubric for Space Flight Projects and Multi-Project Programs (continued)


                   Cost                                          Schedule                                          Technical                                        Programmatic

In general, the program or project follows       In general, the program or project follows the     In general, the program or project follows        In general, programmatic performance remains
         the green assessment guidelines,               green assessment guidelines, but                   the green assessment guidelines,                  consistent with program/project
         but cost commitments are now                   schedule commitments are now                       but technical commitments are now                 requirements for a green assessment, but
         threatened.                                    threatened.                                        threatened:                                       remaining programmatic flexibility may be
Remaining cost margin appears inadequate         Remaining schedule margin appears                  Remaining technical margins appear                        inadequate to meet requirements due to
         to meet requirements due to one or              inadequate to meet requirements due                inadequate to meet requirements                   one or more of the following programmatic
         more of the following deviations from
                                                         to one or more of the following                    due to one or more of the following               deviations from plan however, mitigation
         plan, however, mitigation plans are
                                                         deviations from plan, however,                     technical deviations from plan                    plans are in place or in development to
         in place or in development to
                                                         mitigation plans are in place or in                however, mitigation plans are in                  recover margin and achieve commitments
         recover margin and achieve
                                                         development to recover margin and                  place or in development to recover                within the planned resources:
         commitments within the planned
                                                         achieve commitments within the                     margin and achieve commitments            -- Key contract actions are not being undertaken
         resources of the Program or Project:
                                                         planned resources:                                 within the planned resources:                     or completed as planned.
-- Lifecycle cost reserves (including those
                                                 -- Schedule reserves are being drawn down          -- Technical reserves are being drawn down        -- A multi-project program’s acquisition strategy
         held at the program level) are being
                                                         faster than planned or as required for             at a rate inconsistent with plan; or              (both contracted and in-house) is not
         drawn down faster than planned or
                                                         emergent schedule risks/threats.                   technical difficulties/risks                      resulting in the timely start of projects and
         required for emergent cost
                                                 -- Key interim milestones (KDP and/or WBS                  encountered exceed those which                    delivery of project elements.
         risks/threats.
                                                         milestones) have slipped.                          are typical for this type of              -- Key critical workforce, access to key facilities,
-- Phasing of cost reserves are inconsistent
                                                 -- For multi-project programs, delay in project            project/program or are not being                  EVM, and management systems are not
         with emergent risks or threats.
                                                         schedules is resulting in an increased             mitigated or controlled as required               consistent with plan..
-- Current year cost growth is exceeding
                                                         risk to the program’s schedule                     to make planned technical progress.       -- Key partnerships are not in place or operating
         planned current year cost reserves
                                                         commitments.                               -- Are not consistent in some key areas with              as planned; external requirements are not
         and will require a re-phasing of the
                                                 -- External partners are delayed in providing              the requirements of safety, reliability           stable; or there are other factors external
         annual budget in order to complete
                                                         key deliverables or external factors are           & quality assurance, and the                      to the project/program (e.g., new Agency
         the fiscal year with required
                                                         delaying completion of a key milestone.            incorporation of good systems                     requirements) which are significantly
         carryover.
                                                                                                            engineering & integration practice.               disrupting planned project/program
 -- A reduction in current year budget or
                                                                                                    -- External partners are not making planned               management.
         slow- down in funds distribution will
                                                                                                            technical progress or external
         require the project/program to
                                                                                                            events (e.g., import approvals) are
         rephrase future year annual costs.
                                                                                                            altering technical requirements.
-- External partner changes or factors
                                                                                                    -- For operational projects, ground or flight
         external to the project/program are
                                                                                                            capabilities have been curtailed, but
         placing additional pressure on
                                                                                                            plans are in work to recover the
         project/program costs.
                                                                                                            capability or develop a workaround
-- For operating missions, in flight anomalies
                                                                                                            such that mission requirements will
         are draining cost reserves.
                                                                                                            still be met.
Assessment Rubric for Space Flight Projects and Multi-Project Programs (continued)

                   Cost                                            Schedule                                           Technical                                        Programmatic
The Program or Project is estimated not to        The Program or Project is estimated not to           The Program or Project is estimated not to        The Program or Project is estimated not to be
         meet its cost commitments without                 meet its schedule commitments without               meet its technical requirements                   able to meet its requirements due to
         significant impact to other                       significant impact to other categories.             without significant impact to other               programmatic issues affecting the other
         categories.                                       The key end-of-phase KDP milestones                 categories:.                                      categories.
Depending on phase, the project's                          are unlikely to be met.                     A project in formulation is not making the        A formulation project has failed to make the
         formulation costs, or development        For multi-project programs, the planned start-               technical progress required to enter              programmatic progress required to be
         costs, or annual operating costs                  up of future projects is delayed beyond             development.                                      confirmed for development.
         are exceeding the planned budget                  program commitments or objectives.          For a project in development, technical           A development project lacks an approved plan or
         beyond all planned reserves.             For operations missions, the current                         failures or delays preclude the                   has failed to implement that plan
For multi-project programs, total annual                   operations schedule is insufficient to              project from being able to meet its               consistent with meeting its commitments.
         costs for the program’s projects                  meet project commitments or the                     technical requirements and                        The multi-project program lacks an
         exceed the program’s 5 year                       mission failed prior to the planned end-            commitments.                                      approved PCA or project plan, or has
         planned run-out, including reserves.              of-operations date. For multi-project       There is minimal or negative technical                    failed to implement the projects require to
There is minimal or negative cost margin                   programs: The current operations                    margin such that there is high risk               meet its commitments.
         such that there is high risk that the             schedule is insufficient to meet                    that the Program or Project will          There is limited or no programmatic flexibility such
         Program or Project will require                   program commitments or the failure of               require additional technical                      that there is high risk that the Program or
         additional funding or relief from                 one or missions prior to the planned                resources or relief from performance              Project will require relief from performance
         performance or programmatic                       end date has resulted in the project not            or programmatic requirements due                  or programmatic requirements due to one
         requirements due to one or more of                being able to meet its commitments or               to one or more of the following                   or more of the following deviations from
         the following deviations from plan for            objectives.                                         technical deviations from plan for                plan for which the project/ program has
         a realistic recovery strategy has not    There is minimal or negative schedule margin                 which the project or program has                  not identified a realistic strategy for
         been identified:                                  is such that there is high risk that the            not identified a realistic strategy for           recovery:
-- Lifecycle cost reserves (including those                Program or Project will require                     recovery:                                 --Key contract actions are not being undertaken
         held at the program level) are being              additional schedule or relief from          -- Technical reserves are being drawn down                or completed as required. The multi-
         drawn down at an unsustainable                    performance or programmatic                         at an unsustainable rate or                       project program’s acquisition strategy
         rate and remaining reserves are                   requirements due to one or more of the              emergent technical difficulties, risks,           (both contracted and in-house) is not
         insufficient given emergent                       following deviations from plan for which            or threats are not being resolved as              resulting in the timely start of projects and
         risks/threats.                                    a realistic strategy for recovery has not           required to meet the technical                    delivery of project elements.
-- Phasing of cost reserves are inconsistent               been identified:                                    commitments.                              --Key critical workforce, availability of key
         with emergent risks or threats.          -- Schedule reserves are being drawn down at         -- Are not consistent with the requirements               facilities, EVM, and management systems
-- Current year cost growth exceeds                        an unsustainable rate and remaining                 of safety, reliability & quality                  are missing or inconsistent with meeting
         planned costs and cannot be                       reserves are insufficient given                     assurance, and the incorporation of               the project’s commitments.
         accommodated by rephrasing                        emergent risks/threats.                             good systems engineering &                --Key planned partnerships did not materialize,
         annual costs.                            -- A slip of one or more key interim milestones              integration practice.                             quit or not to delivering consistent with
-- A reduction or delay in current year                    (KDP and/or WBS milestones) is              -- Lack of technical progress by external                 project/program commitments; unstable or
         funding is inconsistent with                      inconsistent with the planned ORD.                  partners or external events (e.g.,                newly emergent external requirements are
         maintaining the overall LCC                       For programs, delay in project                      import approvals) are inconsistent                not implementable; or other external
         commitment.                                       schedules is inconsistent with                      with meeting the project/program                  developments are inconsistent with the
-- A loss of key external partners or                      program’s schedule commitments.                     technical requirements,                           project/program commitments.
         resources is inconsistent with           -- An external partner delays or delays caused               commitments, or objectives, or
         keeping the project or program                    by other external factors are                       additional/different external cannot
         within planned costs.                             inconsistent with the planned ORD.                  be met within plan.
-- For operational projects, in-flight                     For multi-project programs, delays          -- For operational missions, in-flight
         anomalies have drained all cost                   caused by external factors are                      anomalies have used up
         reserves and the project will need                inconsistent with the program’s                     redundancy and made it unlikely
         more funds to complete the prime                  schedule commitments.                               that the mission will achieve its
         mission.                                                                                              mission requirements.
BPR Process Organizational
                        Structure                      As of June 3, 2008




                       Associate Administrator
                        And Associate Deputy
                           Administrator


                                Chief
                               Engineer


                         Division Chief for
                          Engineering and
                         Program & Project
                           Management


                                BPR
                             Team Lead




February 2010             For NASA Internal Use Only                   38
BPR Process Organizational
                                          Structure                                                                              As of June 3, 2008

                                                                      BPR
                                   Executive
                                   Secretariat                     Team Lead




            PA&E                     Technical                  OSMA                  OCE Admin             Center          OCE MD P&P
          Team Lead                Cross-Cutting              Team Lead                Support              POC’s           Assessment
                                       Team                                                                                    Lead



     Institutional          Non-            Special Topic /                Program       Mission                 Mission       OSMA         PA&E
     Assessment          Technical           Root Cause                       &         Directorate   Centers    Support      Assessor     Assessor
     Team Lead          Cross Cutting       Analysis Lead                  Projects         (*)                  Offices
                                                                                                                               (One representative
                                                                                                                                 from each MD)
         MSO
    Representatives


                 I&A
                 IT
                 OCFO
                 OHCM
                 OPII
                 PROC




                                                                                                          (*) One representative from each

February 2010                                                  For NASA Internal Use Only                                                            39
Primary BPR Deliverables


•   Monthly meeting BPR presentation package
•   Executive summary and pre-brief
•   Meeting Summary Notes and Post-brief
•   Executive Summary for the Administrator and Deputy Administrator
•   Meeting Actions List and tracking




                                                                       40

Más contenido relacionado

La actualidad más candente

Mckenzie.merle
Mckenzie.merleMckenzie.merle
Mckenzie.merleNASAPMC
 
Hal bell
Hal bellHal bell
Hal bellNASAPMC
 
Ed.mango
Ed.mangoEd.mango
Ed.mangoNASAPMC
 
L9 Planning Tools And Techniques
L9 Planning Tools And TechniquesL9 Planning Tools And Techniques
L9 Planning Tools And TechniquesGajanan Bochare
 
Capstone Senior Design Projects Comprehensive
Capstone Senior Design Projects ComprehensiveCapstone Senior Design Projects Comprehensive
Capstone Senior Design Projects ComprehensiveJean Koster
 
Doug.sander
Doug.sanderDoug.sander
Doug.sanderNASAPMC
 
IQPC's 8th Shutdowns and Turnarounds 2011
IQPC's 8th Shutdowns and Turnarounds 2011IQPC's 8th Shutdowns and Turnarounds 2011
IQPC's 8th Shutdowns and Turnarounds 2011JBScott44
 
Virscidian Poster Pittcon 2010
Virscidian Poster Pittcon 2010Virscidian Poster Pittcon 2010
Virscidian Poster Pittcon 2010Mark Bayliss
 
Mapping supply chains
Mapping supply chainsMapping supply chains
Mapping supply chainsArkkkky
 
Teti Presentation Metro Md Meeting 9 15 2010
Teti Presentation Metro Md Meeting   9 15 2010Teti Presentation Metro Md Meeting   9 15 2010
Teti Presentation Metro Md Meeting 9 15 2010cmteti
 

La actualidad más candente (14)

Mckenzie.merle
Mckenzie.merleMckenzie.merle
Mckenzie.merle
 
Hal bell
Hal bellHal bell
Hal bell
 
Ed.mango
Ed.mangoEd.mango
Ed.mango
 
Transition GPS MSC CCC crash course
Transition GPS MSC CCC crash courseTransition GPS MSC CCC crash course
Transition GPS MSC CCC crash course
 
L9 Planning Tools And Techniques
L9 Planning Tools And TechniquesL9 Planning Tools And Techniques
L9 Planning Tools And Techniques
 
Capstone Senior Design Projects Comprehensive
Capstone Senior Design Projects ComprehensiveCapstone Senior Design Projects Comprehensive
Capstone Senior Design Projects Comprehensive
 
Neqc poster
Neqc posterNeqc poster
Neqc poster
 
Doug.sander
Doug.sanderDoug.sander
Doug.sander
 
IQPC's 8th Shutdowns and Turnarounds 2011
IQPC's 8th Shutdowns and Turnarounds 2011IQPC's 8th Shutdowns and Turnarounds 2011
IQPC's 8th Shutdowns and Turnarounds 2011
 
SFP Firm Profile
SFP Firm ProfileSFP Firm Profile
SFP Firm Profile
 
Virscidian Poster Pittcon 2010
Virscidian Poster Pittcon 2010Virscidian Poster Pittcon 2010
Virscidian Poster Pittcon 2010
 
Mapping supply chains
Mapping supply chainsMapping supply chains
Mapping supply chains
 
Cc doc-consult-ref
Cc doc-consult-refCc doc-consult-ref
Cc doc-consult-ref
 
Teti Presentation Metro Md Meeting 9 15 2010
Teti Presentation Metro Md Meeting   9 15 2010Teti Presentation Metro Md Meeting   9 15 2010
Teti Presentation Metro Md Meeting 9 15 2010
 

Similar a Steven noneman

Bilardo2 15-2012
Bilardo2 15-2012Bilardo2 15-2012
Bilardo2 15-2012NASAPMC
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.rNASAPMC
 
Ortiz.james
Ortiz.jamesOrtiz.james
Ortiz.jamesNASAPMC
 
Geyer.m.sasaki.c
Geyer.m.sasaki.cGeyer.m.sasaki.c
Geyer.m.sasaki.cNASAPMC
 
Keer.beth
Keer.bethKeer.beth
Keer.bethNASAPMC
 
Keer.beth
Keer.bethKeer.beth
Keer.bethNASAPMC
 
Harrison.g.poole.k
Harrison.g.poole.kHarrison.g.poole.k
Harrison.g.poole.kNASAPMC
 
James.ortiz
James.ortizJames.ortiz
James.ortizNASAPMC
 
Amer.tahani
Amer.tahaniAmer.tahani
Amer.tahaniNASAPMC
 
RBC Portfolio Slides English
RBC Portfolio Slides EnglishRBC Portfolio Slides English
RBC Portfolio Slides EnglishRudolf Bartels
 
William.miller.pmc2010
William.miller.pmc2010William.miller.pmc2010
William.miller.pmc2010NASAPMC
 
William.miller.pmc2010
William.miller.pmc2010William.miller.pmc2010
William.miller.pmc2010NASAPMC
 
Lau.cheevon
Lau.cheevonLau.cheevon
Lau.cheevonNASAPMC
 
Nek e am_overview_2010_1f.ppt [compatibility m
Nek e am_overview_2010_1f.ppt [compatibility mNek e am_overview_2010_1f.ppt [compatibility m
Nek e am_overview_2010_1f.ppt [compatibility mOracle Hrvatska
 
DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.Chris Carson
 
Borchardt.heidemarie
Borchardt.heidemarieBorchardt.heidemarie
Borchardt.heidemarieNASAPMC
 

Similar a Steven noneman (20)

Bilardo2 15-2012
Bilardo2 15-2012Bilardo2 15-2012
Bilardo2 15-2012
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.r
 
Ortiz.james
Ortiz.jamesOrtiz.james
Ortiz.james
 
Geyer.m.sasaki.c
Geyer.m.sasaki.cGeyer.m.sasaki.c
Geyer.m.sasaki.c
 
Pms opes
Pms opesPms opes
Pms opes
 
Keer.beth
Keer.bethKeer.beth
Keer.beth
 
Keer.beth
Keer.bethKeer.beth
Keer.beth
 
Harrison.g.poole.k
Harrison.g.poole.kHarrison.g.poole.k
Harrison.g.poole.k
 
James.ortiz
James.ortizJames.ortiz
James.ortiz
 
Amer.tahani
Amer.tahaniAmer.tahani
Amer.tahani
 
RBC Portfolio Slides English
RBC Portfolio Slides EnglishRBC Portfolio Slides English
RBC Portfolio Slides English
 
William.miller.pmc2010
William.miller.pmc2010William.miller.pmc2010
William.miller.pmc2010
 
William.miller.pmc2010
William.miller.pmc2010William.miller.pmc2010
William.miller.pmc2010
 
Lau.cheevon
Lau.cheevonLau.cheevon
Lau.cheevon
 
Metric mgt 3 day timetable
Metric mgt     3 day timetableMetric mgt     3 day timetable
Metric mgt 3 day timetable
 
DPPM1
DPPM1DPPM1
DPPM1
 
Nek e am_overview_2010_1f.ppt [compatibility m
Nek e am_overview_2010_1f.ppt [compatibility mNek e am_overview_2010_1f.ppt [compatibility m
Nek e am_overview_2010_1f.ppt [compatibility m
 
Ortiz
OrtizOrtiz
Ortiz
 
DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.
 
Borchardt.heidemarie
Borchardt.heidemarieBorchardt.heidemarie
Borchardt.heidemarie
 

Más de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 

Más de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Último

The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...gurkirankumar98700
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhisoniya singh
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 

Último (20)

The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 

Steven noneman

  • 1. NASA Baseline Performance Review (BPR) Steven Noneman, NASA HQ Robert Woods, Perot Systems Office of Program Analysis and Evaluation Office of the Chief Engineer Program Management Challenge, Galveston, TX February 2010 Used with Permission
  • 2. Presentation Purpose • Describe NASA’s Baseline Performance Review (BPR) to the greater NASA community at PM Challenge 2010.  Characterize the BPR objectives, scope, process, and products  Summarize NASA’s technique for monitoring Agency performance against its baseline plans 2
  • 3. Contents • BPR History • BPR Objectives • BPR Scope, Participants • BPR Process • Sample BPR Meeting Agenda • Sample BPR Analysis Content • Summary 3
  • 4. BPR History and Context • In the spring of 2006, the Office of the Chief Engineer (OCE) was given the action by the Associate Administrator to develop a State of the Agency (SoA) process that provides the Agency Project Management Council (APMC) an independent top level view of the status of the Agency’s programs and projects. • The first SoA presentation, to the Agency PMC, was by the Science Mission Directorate (SMD) in August of 2006. The process has matured and continued to meet the objectives outlined by the Associate Administrator, the Associate Deputy Administrator, the Chief Engineer (CE) and the various stakeholders. The SoA evolved to a distinct monthly meeting in December 2007 and was officially entitled the Baseline Performance Review (BPR). • The BPR instituted a modified “balanced score card stop-light chart” process based on metrics encompassed in a core set of functional area questions and supporting raw data. • Participants from the projects, programs, Centers, Mission Directorates (MDs) and Mission Support Offices respond monthly to each core area question based on provided thresholds and key metrics for use in internal and external reporting. • All Mission Directorates are reporting at the BPR meeting the findings of the independent process.
  • 5. BPR Objectives • Provide NASA Senior Leadership comprehensive, integrated, and objective information that describes the “performance-to-plan” of the Agency’s programs, projects, and institutional capabilities.  A single place to see the full execution context of the Agency • Assure open cross-functional communications among NASA’s organizations to enhance Agency performance. • Identify and analyze performance trends and cross- cutting or systemic issues and risks • Serve the Agency’s decision making Councils as their ”execution arm”  Within the NASA Governance model, the BPR is distinct from the decision-making Strategic Management, Program Management, and Operations Management Councils  BPR is “action-oriented” to improve performance and inform Agency decision authorities of issues needing attention. 5
  • 6. BPR Scope and Participants • The BPR is co-chaired by the NASA Associate Administrator and the Associate Deputy Administrator. • Membership includes the heads of NASA Staff Offices, Mission Directorates, Mission Support Offices, and its ten Field Centers. • Mission Support functions (e.g., finance, workforce, acquisition, infrastructure, IT, etc.) report monthly and Small Business and Diversity and Equal opportunity report quarterly. • Mission Directorates (covering all program areas) report monthly with one (and sometimes 2) “highlighted” in greater detail. • The Office of the Chief Engineer (OCE) leads a team of “independent assessors” from OCE, Program Analysis and Evaluation (PA&E), and Office of Safety Mission Assurance that analyze programs’ and projects’ performance.  “Green/Yellow/Red” criteria were established to assess of technical, cost, schedule, and programmatic performance are provided monthly for all Mission Directorates. • PA&E provides the BPR Coordinator who manages the review by setting agendas, tracking actions, and assisting the co-chairs, OCE, and BPR participants. 6
  • 7. BPR Detailed Process Flow 3 MD issue charts 1 Mission MDs Directorates GYR rankings for 2 Mission Support projects and OCE sends out Offices programs from the OCE (OCE, notifications to consolidates OSMA, and Assessor Group OCE 3 users who answer NASA Centers input from PA & E) generates questions stakeholders Assessor BPR 1- 5 Group package 4 Programs 5 Technical Projects X-Cutting, OCE PCA Status reps. for MDs Non- Package Technical briefing to X-Cutting CE for 3 OCE feedback and approval Action items on BPR PA & E process BPR reps. for OCE Package is Package MDs Provides available presented Exe. Sum. for Read- at the BPR only viewing from site
  • 8. Example Outcomes/Results • Cross-cutting issues  Across missions, faulty material was discovered resulting in a mitigation process for the materials use saving time and resources. • Organizational communication issues  Turned a conflict between projects on thermal protection systems into a collaboration between the major development projects who previously were competing for shared resources. • Mission support issues  Workforce planning resolution was expedited when a project was confronted with changes resulting in 500 people at a Center needing reassignment because the project was delayed 2 years. • Senior leaders as an “Execution Board of Directors”  Leadership asked and Centers provided additional workforce during transition to the NASA Support and Services Center because invoices were not getting paid on time, which had been costing projects late fees. • Mission specific issues  Timely communication resulted in a Center director de-conflicting a vendors schedule between 2 NASA projects from different Centers.
  • 9. BPR Project Questions O f Mission Directorate fi c e o Program Project f GUIDANCE FOR R&T P r QUESTIONS THRESHOLDS PROGRAMS/ o c PROJECTS u r e m e n t COMMENTS G R * What is the status and level G=Yes or <10%, of maturity of the research Are your top level requirements(such as 10%<Y<=20% objectives? requirements/objectives not * Have you baselined the KPP's) or objectives stable and state of the art/knowledge and stable or established/ Unknowns and lack of established/baselined? baselined, R>20% are moving off this clarity with Lunar requirements not stable or accordingly toward those requirements specific to established/ baselined objectives? X Y X technology development. G=Yes, Y<=20% Are you on track to meet your top level requirements/ objectives not requirements/ objectives? on track, R>20% requirements/ objectives not on track X G X Has requirement feasability Does the project/program have plans that been established and have meet the needs/ objectives of the G=Yes, Y=minor weakness requirements flowed down community customer? identified, R=major weakness with traceability from customer identified needs? X G X G=Yes, Y=minor weakness Are the results of research/ technology being identified, R=major weakness widely disseminated? identified X G X G= On track to complete all What is the readiness to support the next deliverables with no delay, R= Review? Not on track for deliverables or delay necessary X NA X G= All actions complete, Y>= What is the status of actions from the last 50% of actions complete, R <= review? 50% of actions complete X NA X 9
  • 10. BPR Project Questions Currently, more than 1 risk is G= All "green" or equivalent, Y= * Is the risk posture or your research What is your overall risk status/ posture (i.e. risk plan/ 5 red. Any "yellow" but no "red" or portfolio balanced and have you x 5 matrix)? equivalent, R= Any "red" or identified the top risks to the success of equivalent your research objectives? X R X G= Can be resolved within Are risks manageable and appropriate ( i.e. risk plan/ 5 available resources, Y= Can't be x 5 matrix)? resolved by project but can with other resources, R= Only resolveable by Agency resources X G X Are technologies sufficiently mature (i.e. TRL or equivalent) at this point, or expected to be mature in G=yes, Y=one is no, R=more than time, per program/ project plans? one no X G X Will all the externally reported performance goals G=all req met, Y= 1 not met, R= (Annual Performance Goals)be met? more than 1 not met X G X Have the externally reported performance goals changed within the current year? G=no, R=yes X G X Are the externally reported performance goals per your plan? G=yes, R=no X G X G= no, Y= has changed once, R= Has the life-cycle budget (LCB)/ top line budget changed more than one time in changed since last reported? same phase or last 6 months X G X G= no, Y= has changed once, R= Has the current year funding changed since last changed more than one time in reported? same phase or last 6 months X G X Overrun 0<=G<5% LCB, Are costs over/ under running your phasing plan? 5%LCB<=Y<10%LCB, 10%LCB<=R X G X Is there a significant need to reallocate resources between Centers in order to accomplish technical tasks? G=no, R=yes X G X Is the current year funding per the approved baseline 90<=G<100%, 80%<=Y<90%, plan? R<80% X G X What is the difference between your current estimate at Difference of 0<=G<5%, * Are the cost estimates for obtaining completion and budget at completion? 5%<=Y<10%, 10%<=R your research objectives still valid? X G X Are mechanisms in place and functioning properly to ensure that NASA receives external funding and sends out funding to others in proper time? G=no, R=yes X G X For projects/ programs over $250M over 5 years, is the project/ program cost per baseline plan and beneath NA congressional limits (15% of Baseline plan)? 0<=G<5%, 5%<=Y<10%, 10%<=R X G X 10
  • 11. BPR Project Questions Are major milestones (per Integrated Master Schedule G=Next major milestone slippage less * Are the schedule estimates for or equivalent) being met? or equal to 45 days, Y=Greater than 45 obtaining your major research but less than 90, R= Greater than 90 objectives milestones still valid? X G X * For those Outcomes/APGs that are Are all GPRA milestones on schedule? also key milestones are they still on G=Yes, Y= 30-60 days behind, R= track for completion per the annual greater than 60 days behind performance plan? X G X Has the schedule been significantly impacted since last G=No change, Y=Change but no reported? schedule slippage, R=Change but with schedule slippage X G X For projects/ programs over $250M over 5 years, is the project/ program under congressional limits for key G=Next major milestone slippage less NA milestone slippage (less than 6 months)? or equal to 45 days, Y=Greater than 45 but less than 90, R= Greater than 90 X G X Are all external agreements in place and executing per plan? G = yes , R = no X G X Are key partners delivering their commitments on time? G = yes , R = no X G X Have key partners changed their commitments since last reported? G = no , R = yes X G X Are critical contracts in place and executing per plan? G = yes , R = no X G X Are undefinitized contract actions within guidelines? G = yes , R = no X G X X Are existing facilities available (or do results of required infrastructure assessment/business case analysis show existing facilities are available to support G=Yes, Y=No - scheduling issue. the activities)? R=No - need to refurb or build X G X Are all critical staff and skills identified and available 90% Critical staff<=G<100%Critical per plan? staff, 80%<=Y<90%, R<80% critical staff X G X Are all support staff and skills identified and available 90% Critical staff<=G<100%Critical per plan? staff, 80%<=Y<90%, R<80% critical staff X G X G=Y, Y= 1 required document not Are required documents per Agency and Center policy complete, R> required document not complete (i.e, FAD, PCA, Program/Project Plan)? complete X G X 11
  • 12. Sample BPR Agenda 10:00 Opening Remarks, Actions Associate Administrator, Coordinator 10:05 Recovery Implementation Status Recovery Act Implementation Team 10:15 Mission Support Reports - Finance Office of the Chief Financial Officer - Workforce Office of Human Capital Management - Acquisition Office of Procurement - Infrastructure Office of Infrastructure 11:30 Highlighted Mission Support: Small Business Programs* Office of Small Business Programs 12:00 Lunch 12:15 Agency Aggregate Assessments OSMA Safety Assessment: NASA Mishap Posture Office of Safety and Mission Assurance Cross Cutting Non-Technical Issues Program Analysis and Evaluation - Special Topic: 2nd Quarter OMB Cost/Schedule Report Cross Cutting Technical Issues Office of the Chief Engineer - Special Topic: Flight S/W Complexity Jet Propulsion Lab Documents Compliance Office of the Chief Engineer Life Cycle Milestone Schedule Office of the Chief Engineer Center Summaries (Programs/Projects and Institutional) Center Representatives 2:45 Roll-up of MD Programs/Projects Office of the Chief Engineer - JWST Project On-going Status/Recovery Plans Science Mission Directorate 3:30 Highlighted Mission Directorate Office of the Chief Engineer Space Ops Mission Directorate (SOMD) Assessment* Space Operations Mission Directorate Launch Services Program Status/Recovery Plan Space Operations Mission Directorate 4:45 Action Summary Coordinator 5:00 Adjourn *Specific topic is rotated Associate Administrator 12
  • 13. Samples of BPR Analysis Content • Finance • Workforce • Acquisition • Small Business • Infrastructure • Safety and Mishaps • Crosscutting Issues • Field Center Summaries • Independent Assessments of Programs and Projects (“Stoplight” ratings) 13
  • 14. For NASA Internal Use Only 14
  • 16. Undefinitized Contract Action (UCA) Status February 27 – March 27, 2009 16 14 1 $1.3B 12 Number of UCAs 4 $27M 10 8 6 $836M 4 8 9 2 1 $35M 2 1 $3.5M 4 0 1 $700K 1 1 $749K 10 1 2 3 4 5 6 7 8 9 er er er er er er er er er er t t t t t t t t t en en en en en en en en en t en C C C C C C C C C C 1-180 Days 180-360 Days >360 Days
  • 17. FY08 Federal Agency Prime Small Business Dollars Overview Top Seven Agencies w/o DOD General Services Administration Department of Justice Department of Homeland Security Department of Veterans SB Dollars Affairs Total Dollars Obligated National Aeronautics & Space Administration Health and Human Services Department of Energy $0 $5,000 $10,000 $15,000 $20,000 $25,000 In Million $ Total Dollars Small Business Dollars
  • 18. BPR: I&A Functional Areas ARC DFRC GRC GSFC JPL JSC KSC LaRC MSFC SSC Remarks Facilities JSC damage from Ike could impact JWST Project.. Chamber A MOU G G G G G Y G G G G and Management Plan not complete. Concern about communication Design & Construction between Eng Div and Facil Div at JSC Facility repair backlog is 8.6% of facility value with increasing Y Y Y Y Y R Y Y Y Y trend.JSC damage from Ike could impact SOMD Operations Facility Maintenance DFRC, KSC, and SSC were changed to yellow since they have not G Y G Y G Y Y G Y Y submitted revised Master Plans. GSFC presented new Master Plan, Planning/Real Estate but has not submitted document for formal approval. Logistics Delay in replacement of critical civil service personnel at GRC and KSC. Also at KSC, a concern existed as retiring civil servants positions were not backfilled. Situation improved by increased use of G G Y G G G G Y G Y Support Services Contractors. Sinlge point failure for multiple logistics functions at LaRC and SSC. Anticipated hire at SSC Supply currently on hold. Delay in replacement of critical civil service personnel at GRC and KSC. GRC expects to fill vacancy by end of 2008. At KSC, a concern existed as retiring civil servants positions were not backfilled. G G Y G NA G G Y G Y Situation improved by increased use of Support Services Contractors. Single point failure for multiple log functions at LaRC and SSC. Anticipated hire at SSC currently on hold. GSFC filled HQ Equipment SEMO position. CFO management control findings related to property management are being addressed, however center IPO staffing concerns to support transition workload and FAR update present an on-going staffing Y Y Y Y Y Y Y Y Y Y issue. JSC in process of filling Contract Property Administrator position. JSC also submitted request to fill the following: 2 positions for Property Disposal, 1 position for Shuttle Clerical (Property) and 1 position for Packing/Shipping in Transportation. Contract Property Agency risk for not meeting EO 13423 (alternate fuel): discussions with MSFC to resolve center contribution ongoing. Single point failure for multiple log functions at SSC, anticipated hire currently on hold. G G G Y G G G Y Y Y GSFC loss of CNG capability for approx. 13 vehicles. KSC added additional contractor to assist with transportation functions. At LaRC, TO/SEMO is one person, he will be out in Jan. (medical leave) no Transportation replacement appointed. Increase in excess property workload due to Shuttle and Hubble G G G Y G Y Y G Y Y disposition at GSFC, MSFC, KSC, SSC & JSC. Single point failure Property Disposal for multiple log functions at SSC.
  • 19. NASA and Contractor Safety Statistics Dashboards February Mishap OCO Jan 2008 – Mar 2008 Jan 2009 - Mar 2009 Jan 2008 – Mar 2008 Jan 2009 - Mar 2009 Jan 2008 - Mar 2008 Jan 2009 - Mar 2009 March Mishaps: • No Type A Mishaps • One Type B Mishap: DRC- (Deluge System Release in Shuttle Hangar - 3/13/09) • One Potential Type B Mishap: DRC- (Global Hawk Electronics Failure 3/12/09) – currently a Type D Data does not include 4/2/09 Type B Mishap: Water Drill mishap resulting in multiple amputations Close Call Incidents Show An Increase From Previous Reporting Period (Jan – Mar 2008).
  • 20. False Material Certification Status as of: Date x, 200x • Issue Description: Company xyz, manufacturer of a material used in flight hardware, was indicted on federal charges of issuing false material certifications for supplies they sold. Material of uncertain pedigree may have been used by NASA projects. Mission Directorate Impact MD 1 MD 2 MD 3 MD 4 • Cleared: LRO, LCROSS, Ares • Suspect material found in • Suspect material found • No use of Suspect I-X, J2-X, Orion PA-1, HRP Kepler spacecraft in a on the Taurus and Delta material determined as ISS Experiments & ETDP IV vehicles used by critical area wherein failure yet • No other project could be catastrophic. OCO, Glory, and NRO L- • Supplier traceability assessments required • Suspect material also found 26. investigation still in the AIA instrument on • NRO mission cleared. underway SDO. • SSP & ISS cleared. • Other projects are • LSP - All vehicles now investigating usage. cleared. Information on Agency Actions and Status (Estimated Completion) POC: Ken Ledbetter • The Kepler project procured material from Company xyz who obtained some of the material from Company xxx Inc, including the material for the Telescope Spider Hub Assembly. Company xyz had 46 different material procurements. The Kepler project performed tests on residual material at xyz and confirmed that it was sufficient to satisfy their mission application. • GIDEP indicates earliest occurrence was no later than 2002 with the latest false certification in 7/03 for a purchase order in 11/04 by Company xyz. • SDO project also found suspect material in the AIA instrument. AIA has now been cleared. • Centers responding with evaluations on a project-by-project basis. • Top Level Description/ Status: Material found to have uncertain pedigree due to false certifications. Extent of usage in NASA projects and resulting impact, are under investigation.
  • 21. Agency Programs: PCA Status Highlight indicates change from previous report MD Formulation Implementation SMD Astrophysics Planetary Science Astrophysics Physics of the Cosmos G Discovery (8/19/08) Y SOFIA (7/26/07) Cosmic Origins Y Mars Exploration (1/26/07) G Hubble Space Telescope (2/27/09) G New Frontiers (3/18/08) G Fermi (formerly GLAST) (8/18/08) Planetary Science Heliophysics G James Webb Space Telescope (3/17/09) G Lunar Quest Explorer (2/2/09) G ExoPlanet Exploration (4/14/09) G Living with a Star (8/25/08) Earth Science G New Millennium (10/6/08) G Earth Systematic Missions (4/14/08) Y Solar Terrestrial Probes (12/21/07) G ESSP (4/25/08) ESMD Constellation (in G Human Research (5/21/07) Rev A in Rev Lunar Precursor Robotic (Waived requirement) development; expect Technology Development (10/21/07) G approval at KDP-II) ARMD G Airspace Systems (9/14/2007) G Fundamental Aeronautics (5/21/07) G Aviation Safety (9/17/2007) G Aeronautics Test (5/21/07) SOMD G ISS (8/01/08) G SSP (1/26/07) G LSP (1/28/08) G SCaN (10/16/08) G RPT (1/23/09) G TDRS K/L (4/18/07) CHSP (waived requirement) PCA Status Legend Dates are last signed PCA G = Signed PCA with no update required Y = MD has identified for update R = No signed PCA BLACK = NA February 2010 21
  • 22. Agency Review Schedule February 2010 For NASA Internal Use Only
  • 23. NASA Monthly Baseline Performance Review (BPR) GSFC Center Summary Input Highlights from 11/17/2009 Programs/Projects Technical Authority/Mission Support/Institutional Summary Performance Institutional Risk to Mission ESMD: ESP Budget/Finance: LRO – Supported LCROSS Lunar Impact, data being analyzed. Grants reconciliation and transition: The ORR for the Phase 2 transition Transition to SSMO will occur in December. to NSSC is scheduled for November 30th; will complete GSFC transition SMD: activities. HST- SM4 SMOV activities complete. Workforce: – Working possible options to increase FY10 reserves. OTE Early Career Hiring: FY09 - 66 on-board; FY10 – 10 with an additional CDR complete. 10 offers accepted and negotiating dates. GLORY- Successful CMC and ESD rebaseline reviews conducted. LV actions being worked prior to DPMC. Acquisition: GPM – Re-planned road to KDP-C. Working toward Mission CDR Aerospace Corp. Support: Consolidated Agency contracting approach planned for December 14-17th. being pursued. GSFC had restricted authorization to use the existing GSFC LDCM contract for critical tasks ending in December. “Authorization” to seek services on the Airforce contract granted but is not expected to save NPP - Systemic issues with systems engineering and mission resources and requires unnecessary actions. assurance escapes on IPO-provided instruments reduce confidence in Instrument life expectancy to be less than the 5-year design life. SCNS contract protest activities continue. NENS contract has been MMS – S Band antenna height change complete. Swedish Univ, KTH extended through April 2010. The delayed transition from NENS to SCNS ability to deliver Spin Plane Probe Electric Field Instruments. continues to impact the contractor’s ability to retain experienced employees to perform the work. RBSP–Schedule delays are being worked. • Agency-level protests denied on August 11th and the Corrective Action SDO – LRD is 2/3/2010. AIA Hopa Circuit anomaly. Plan (CAP) implementation was initiated on August 17th. SAM – Power Distribution Box is integrated onto the flight suite. • A protest was submitted on August 21st to GAO with regard to the CAP. GOES-R – ITT performance on ABI. CAP implementation permitted to continue. GAO decision due NLT November 30th. NOAA Climate Sensors • Congressional request for information with regard to the CAP was SOMD: submitted October 22nd. Ground Network Space Network- See Acquisition, SCNS. TDRS – Continue to Work with BSS regarding requirements flow-down to subcontractors. SGSS – RFP development activities continue. ELC – Successful SMSR October 23rd. Decks #1 and #2 were Launched November 16th. February 2010 23
  • 24. SMD Overview November 2009 Status: – 2 project rated Red overall: NPP, SOFIA – 4 projects rated Yellow overall: JWST, MSL, Juno, Glory – SOFIA changed from Yellow to Red due to eroding schedule, cost issues & delay in rebaseline APMC. – Juno progress degraded from Green to Yellow; Glory returned to Yellow pending replan DPMC. – Replan DPMCs pending on Glory, Aquarius, & MSL. – MRO in safemode due to computer resets; Restarts unsuccessful for Last IceSat laser failure Technical Schedule Planetary: MSL actuators. MRO safemode implications on Astrophysics: developing missions using heritage avionics (e.g. Juno, Earth Sci: Glory Taurus XL return to flight schedule. Potential GRAIL, MAVEN) further NPP launch delays from instrument rework. All: Continued difficulties developing instruments; Implications from usage of Western Titanium. Cost Programmatic Planetary: Funding of MSL slip severely impacts division All: Access to Space continues to be an issue: Delta II Astrophysics: Overall division budget issues, esp JWST. replacement; Taurus XL failure, & impact on Glory. Very crowded launch manifest in fall 2011. Watch list Items: Uncertainty of SMAP launch date for project planning February 2010 For NASA Internal Use Only 24
  • 25. ESMD Projects Status Roll Up Continued 2009 Month A B C D COMMENTS S O N S O N S O N S O N Y Y G Successful Launch!! October 28, 2009 at 11:30 am ET Post-Flight Data Review working group will meet twice a week to review progress of data collection and reduction Ares I-X The first stage solid rocket motor recovered; hardware disposition is in progress; data recorder removed and shipped to Lockheed Martin. Lockheed Martin who will provide best and final set of all flight data from a combination of data from telemetry and the on-board recorder Lunar Insufficient funds in PMR09 budget to meet HLR in 2020. Surface Constrained to “study only” after FY2010. Systems February 2010 25
  • 26. PSD Budget Reporting Matrix (11/16/09) External Internal Project MPAR OMB Qtrly (Baseline) IBPD (FY10)*1 (4QFY09) PCA/PRLA/other*2 Development $968.6 $1,631.0 $1,719.9 $1657 ₃ MSL LCC $1,642.2 $2,299.3 $2,394.3 $2,318.5 LRD Sep 2009 Oct 2011 Nov-11 Oct-11 Development $427.0 $427.0 $427.0 $407.7 GRAIL LCC $496.2 $465.6M* $496.2 $468.2 LRD Sep 2011 Sep 2011 Sep 2011 Sep 2011 Development $742.3 $742.3 $742.3 $695.3 JUNO LCC $1,107.0 $1,091.9M* $1,107.0 $1,050.0 LRD Aug 2011 Aug 2011 Aug 2011 Aug-11 *1 - IBPD is updated through N2 automatically and as of 4-15-9 N2 has not been updated to reflect the FY09 Op Plan Changes nor the GRAIL and Juno KDP-C decisions. *2 - The PCA (Program Commitment Agreement) is located in Science Works under Requirements Management system, Planetary Science, Program, Key Document PCA, and KPD *3 - MSL project assumes an approved $13.4M adjustment from Phase E to Phase C/D, which is NOT included in the $1657M internal development number. 26
  • 27. Oct Nov JWST YY Y Status: In Phase C Y Technical: G Schedule: • NIRCam off-axis image quality • WATCH: Low near-term reserves pose a • NIRSpec microshutter separation - decision threat to LRD. to change coating R Cost: G Programmatic: • FY'10 reserves negative & FY'11 reserves only 0.9% • Project requested $20M addition to FY'10 reserves. HQ told project to continue to fund JSC facility mod, with decision on extra $20M in 4-6 weeks.
  • 28. Summary • NASA Senior Management monitors Agency-Wide performance monthly through its baseline Performance Review (BPR) Process  Each Program area is assessed quarterly on a rotating basis • The automated tool is coming online at MSFC • BPR continues to evolve and improve
  • 30. BPR Actions and Status 7.23.2009 BPR Meeting • 2009-07-026: PA&E – Revisit the FY09 Q3 Contract reporting chart to clarify the way the information is being conveyed. (E.g. Contract base value apparent misalignment with LCC.) Due: October 2009 BPR Status: Propose to CLOSE. PA&E has met with ESMD to identify how to add clarity to this reporting. ESMD will provide additional information that clarifies the contract values. Interim information was presented in September BPR by PA&E. ESMD has provided data from the Ares I and Orion. Language has been added to the contract chart to explain what contracts are and are not included in contract reporting to OMB.
  • 32. Green Criteria A Category for a Project is Green if: There are minimal programmatic issues and adequate margin (budget reserve, schedule slack, technical margin), or capability (for operational missions), to complete the Project on plan. A Project is Green overall if: All 4 categories are Green, or One or more are Yellow and the issues are collectively not a threat/impact to the project by virtue of their being solvable within the project's planned resources. (Margin in one category may provide capability to resolve a lack of margin in another category.) A Program is Green if: The constituent projects are Green overall, or are Yellow with realistic, defined plans to return to green and all other program elements are on budget and schedule.
  • 33. Yellow Criteria A Category for a Project is Yellow if: The remaining margin within the category appears inadequate to meet Project requirements or external commitments, however, mitigation plans are in place or in development to recover margin and achieve commitments within the available resources of the Project. (For operational projects in the technical category "margin" may be interpreted as operational capabilities.) A Project is Yellow overall if: Any one category is Red, the overall is at least Yellow, or One or more categories are Yellow and the issues are collectively a threat to the project's ability to meet their commitments within the project's planned resources. A Program is Yellow if: Any of its constituent projects are Red overall, or if one or more are Yellow and the issues are collectively a threat to the Program's ability to meet its commitments within planned resources.
  • 34. Red Criteria A Category for a Project is Red if: There is minimal margin or negative margin within the category such that the Project is estimated not to meet its requirements or commitments without significant impact to other categories. There is high risk that the Project will require external resources or relief from performance or programmatic requirements. A Project is Red overall if: One or more categories are Red, and it is estimated that the Project will not have sufficient resources to meet its commitments. A Program is Red if: Most of its constituent projects are Red overall, or if one or more are Red and the issues are collectively a threat to the Program's ability to meet its commitments.
  • 35. Assessment Rubric for Space Flight Projects and Multi-Project Programs Cost Schedule Technical Programmatic Cost estimates remain consistent with cost Schedule progress remains consistent with Technical progress remains consistent with Programmatic performance remains consistent commitments: schedule commitments: technical commitments: with program/project requirements: -- Formulation: Current estimated -- Formulation: The current estimated -- Formulation: The project/program is -- Formulation: An approved FAD is in place and formulation costs are consistent with the authority-to-proceed to implementation date is making planned progress in developing planned progress is being made in completing program FAD. at or before the FAD. technical design, reliability, safety, and risk programmatic arrangements necessary to enter -- Development: Current estimated LCC at -- Development: Current estimated operational mitigation requirements necessary to development as planned. completion is at or below the LCC readiness date (ORD) is at or before the ORD proceed to implementation as planned. -- Development: Top-level objectives and commitment. For multi-project programs, the commitment. For multi-project programs, the -- Development: Technical requirements programmatic requirements in the plan are stable current cost estimate by year for the current estimated schedule for planned start are stable and progress and risk and programmatic capabilities are being program’s projects, including reserve, is dates for future projects is consistent with the management is consistent with plan while developed/ managed as planned. Plans are within the 5 year cost run-out in the program program plan. maintaining safety. For multi-project consistent with 7120.5 or necessary waivers are plan. The program is consistently executing -- Operations: Planned operations, including programs, any lack of planned technical in place. A multi-project program is effectively its projects within their cost cap or maintenance, are proceeding on schedule. progress at the project level is not resulting managing its projects, with new projects commitment. and there are minimal issues and adequate in an increased risk to the program’s beginning per the Program Plan. -- Operations: Annual operational costs are schedule margin to complete the Program or technical commitments and objectives. -- Operations. Operational requirements are at or below planned costs for these Project on plan: -- Operations: Operational systems are stable consistent with plan, and operations are operations --Funded schedule reserves & phasing are delivering the planned level of services and being managed as planned. Retirement/ transition and there are minimal issues and adequate consistent with plan and are being drawn down reliability, with a general trend towards plans are being developed/ implemented cost margin (budget reserve) to complete at a rate consistent with plan and emergent improved safety, and efficiency. consistent with the timing for these events. the Program or Project on plan: schedule risks/threats. For multi-project and there are minimal issues and adequate and there are minimal issues and adequate -Lifecycle cost reserves are consistent with programs, any faster-than-planned project technical margin to complete the Program programmatic flexibility to complete the Program plan and are being drawn down at a rate draw-down of schedule reserve is not or Project on plan: or Project on plan: consistent with plan and emergent cost impinging on the ability of the program to meet -- Technical reserves are being drawn down --Key contract actions are being undertaken and risks/threats. For multi-project programs, its overall schedule commitments. are consistent with plan; technical completed as planned. The multi-project reserves are being managed consistent with --Key interim milestones (KDP as well as WBS difficulties/risks encountered are typical for program’s acquisition strategy (both contracted the annual reserves planned for each milestones) being met. this type of project/program and are being and in-house) is resulting in the timely start of project. -- For multi-project programs, any delay in mitigated or controlled as required to make projects and delivery of project elements. -- The project/program will not require project schedule is not jeopardizing inputs planned technical progress. --Key critical workforce, access to key facilities, additional funds to complete the current required for another project or resulting in an -- Are consistent with the requirements of EVM, and management systems are in place fiscal year with required carryover. increased risk to the program’s schedule safety, reliability & quality assurance, and consistent with plan. -- Phasing of cost reserves are consistent commitments. incorporate good systems engineering & --Key partnerships are in place and operating as with emergent risks or threats. -- External partners are providing key integration practice. planned; external requirements are stable; and -- Current year budget level and timing of deliverables on schedule. -- External partners are making planned there are no other factors external to the funds distribution are consistent with plan or technical progress and external events project/program (e.g., new Agency requirements) commitments are not threatened as a result (e.g., import approvals) are not altering which are significantly disrupting planned of any or delay in current year funding. technical requirements. project/program management. -- External partners are providing key -- For operational projects, the ground and resources as planned. in-flight hardware is operating satisfactorily on prime or backup units and mission requirements are being met.
  • 36. Assessment Rubric for Space Flight Projects and Multi-Project Programs (continued) Cost Schedule Technical Programmatic In general, the program or project follows In general, the program or project follows the In general, the program or project follows In general, programmatic performance remains the green assessment guidelines, green assessment guidelines, but the green assessment guidelines, consistent with program/project but cost commitments are now schedule commitments are now but technical commitments are now requirements for a green assessment, but threatened. threatened. threatened: remaining programmatic flexibility may be Remaining cost margin appears inadequate Remaining schedule margin appears Remaining technical margins appear inadequate to meet requirements due to to meet requirements due to one or inadequate to meet requirements due inadequate to meet requirements one or more of the following programmatic more of the following deviations from to one or more of the following due to one or more of the following deviations from plan however, mitigation plan, however, mitigation plans are deviations from plan, however, technical deviations from plan plans are in place or in development to in place or in development to mitigation plans are in place or in however, mitigation plans are in recover margin and achieve commitments recover margin and achieve development to recover margin and place or in development to recover within the planned resources: commitments within the planned achieve commitments within the margin and achieve commitments -- Key contract actions are not being undertaken resources of the Program or Project: planned resources: within the planned resources: or completed as planned. -- Lifecycle cost reserves (including those -- Schedule reserves are being drawn down -- Technical reserves are being drawn down -- A multi-project program’s acquisition strategy held at the program level) are being faster than planned or as required for at a rate inconsistent with plan; or (both contracted and in-house) is not drawn down faster than planned or emergent schedule risks/threats. technical difficulties/risks resulting in the timely start of projects and required for emergent cost -- Key interim milestones (KDP and/or WBS encountered exceed those which delivery of project elements. risks/threats. milestones) have slipped. are typical for this type of -- Key critical workforce, access to key facilities, -- Phasing of cost reserves are inconsistent -- For multi-project programs, delay in project project/program or are not being EVM, and management systems are not with emergent risks or threats. schedules is resulting in an increased mitigated or controlled as required consistent with plan.. -- Current year cost growth is exceeding risk to the program’s schedule to make planned technical progress. -- Key partnerships are not in place or operating planned current year cost reserves commitments. -- Are not consistent in some key areas with as planned; external requirements are not and will require a re-phasing of the -- External partners are delayed in providing the requirements of safety, reliability stable; or there are other factors external annual budget in order to complete key deliverables or external factors are & quality assurance, and the to the project/program (e.g., new Agency the fiscal year with required delaying completion of a key milestone. incorporation of good systems requirements) which are significantly carryover. engineering & integration practice. disrupting planned project/program -- A reduction in current year budget or -- External partners are not making planned management. slow- down in funds distribution will technical progress or external require the project/program to events (e.g., import approvals) are rephrase future year annual costs. altering technical requirements. -- External partner changes or factors -- For operational projects, ground or flight external to the project/program are capabilities have been curtailed, but placing additional pressure on plans are in work to recover the project/program costs. capability or develop a workaround -- For operating missions, in flight anomalies such that mission requirements will are draining cost reserves. still be met.
  • 37. Assessment Rubric for Space Flight Projects and Multi-Project Programs (continued) Cost Schedule Technical Programmatic The Program or Project is estimated not to The Program or Project is estimated not to The Program or Project is estimated not to The Program or Project is estimated not to be meet its cost commitments without meet its schedule commitments without meet its technical requirements able to meet its requirements due to significant impact to other significant impact to other categories. without significant impact to other programmatic issues affecting the other categories. The key end-of-phase KDP milestones categories:. categories. Depending on phase, the project's are unlikely to be met. A project in formulation is not making the A formulation project has failed to make the formulation costs, or development For multi-project programs, the planned start- technical progress required to enter programmatic progress required to be costs, or annual operating costs up of future projects is delayed beyond development. confirmed for development. are exceeding the planned budget program commitments or objectives. For a project in development, technical A development project lacks an approved plan or beyond all planned reserves. For operations missions, the current failures or delays preclude the has failed to implement that plan For multi-project programs, total annual operations schedule is insufficient to project from being able to meet its consistent with meeting its commitments. costs for the program’s projects meet project commitments or the technical requirements and The multi-project program lacks an exceed the program’s 5 year mission failed prior to the planned end- commitments. approved PCA or project plan, or has planned run-out, including reserves. of-operations date. For multi-project There is minimal or negative technical failed to implement the projects require to There is minimal or negative cost margin programs: The current operations margin such that there is high risk meet its commitments. such that there is high risk that the schedule is insufficient to meet that the Program or Project will There is limited or no programmatic flexibility such Program or Project will require program commitments or the failure of require additional technical that there is high risk that the Program or additional funding or relief from one or missions prior to the planned resources or relief from performance Project will require relief from performance performance or programmatic end date has resulted in the project not or programmatic requirements due or programmatic requirements due to one requirements due to one or more of being able to meet its commitments or to one or more of the following or more of the following deviations from the following deviations from plan for objectives. technical deviations from plan for plan for which the project/ program has a realistic recovery strategy has not There is minimal or negative schedule margin which the project or program has not identified a realistic strategy for been identified: is such that there is high risk that the not identified a realistic strategy for recovery: -- Lifecycle cost reserves (including those Program or Project will require recovery: --Key contract actions are not being undertaken held at the program level) are being additional schedule or relief from -- Technical reserves are being drawn down or completed as required. The multi- drawn down at an unsustainable performance or programmatic at an unsustainable rate or project program’s acquisition strategy rate and remaining reserves are requirements due to one or more of the emergent technical difficulties, risks, (both contracted and in-house) is not insufficient given emergent following deviations from plan for which or threats are not being resolved as resulting in the timely start of projects and risks/threats. a realistic strategy for recovery has not required to meet the technical delivery of project elements. -- Phasing of cost reserves are inconsistent been identified: commitments. --Key critical workforce, availability of key with emergent risks or threats. -- Schedule reserves are being drawn down at -- Are not consistent with the requirements facilities, EVM, and management systems -- Current year cost growth exceeds an unsustainable rate and remaining of safety, reliability & quality are missing or inconsistent with meeting planned costs and cannot be reserves are insufficient given assurance, and the incorporation of the project’s commitments. accommodated by rephrasing emergent risks/threats. good systems engineering & --Key planned partnerships did not materialize, annual costs. -- A slip of one or more key interim milestones integration practice. quit or not to delivering consistent with -- A reduction or delay in current year (KDP and/or WBS milestones) is -- Lack of technical progress by external project/program commitments; unstable or funding is inconsistent with inconsistent with the planned ORD. partners or external events (e.g., newly emergent external requirements are maintaining the overall LCC For programs, delay in project import approvals) are inconsistent not implementable; or other external commitment. schedules is inconsistent with with meeting the project/program developments are inconsistent with the -- A loss of key external partners or program’s schedule commitments. technical requirements, project/program commitments. resources is inconsistent with -- An external partner delays or delays caused commitments, or objectives, or keeping the project or program by other external factors are additional/different external cannot within planned costs. inconsistent with the planned ORD. be met within plan. -- For operational projects, in-flight For multi-project programs, delays -- For operational missions, in-flight anomalies have drained all cost caused by external factors are anomalies have used up reserves and the project will need inconsistent with the program’s redundancy and made it unlikely more funds to complete the prime schedule commitments. that the mission will achieve its mission. mission requirements.
  • 38. BPR Process Organizational Structure As of June 3, 2008 Associate Administrator And Associate Deputy Administrator Chief Engineer Division Chief for Engineering and Program & Project Management BPR Team Lead February 2010 For NASA Internal Use Only 38
  • 39. BPR Process Organizational Structure As of June 3, 2008 BPR Executive Secretariat Team Lead PA&E Technical OSMA OCE Admin Center OCE MD P&P Team Lead Cross-Cutting Team Lead Support POC’s Assessment Team Lead Institutional Non- Special Topic / Program Mission Mission OSMA PA&E Assessment Technical Root Cause & Directorate Centers Support Assessor Assessor Team Lead Cross Cutting Analysis Lead Projects (*) Offices (One representative from each MD) MSO Representatives I&A IT OCFO OHCM OPII PROC (*) One representative from each February 2010 For NASA Internal Use Only 39
  • 40. Primary BPR Deliverables • Monthly meeting BPR presentation package • Executive summary and pre-brief • Meeting Summary Notes and Post-brief • Executive Summary for the Administrator and Deputy Administrator • Meeting Actions List and tracking 40