The document summarizes construction and infrastructure opportunities at Marine Corps bases in Eastern North Carolina. It outlines various project types including military construction projects, renovation and repair projects, and energy initiatives. Recent and planned funding levels are also discussed, with fiscal year 2012 representing the last large year of funding before returning to normal levels. Opportunities exist for prime contractors, subcontractors, and small businesses on projects ranging from thousands to hundreds of millions of dollars.
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
MCIEast
1. Marine Corps Installations East NCMBC Federal Construction and Infrastructure Summit 20 OCT 2011 Tony Sholar, P.E. Facilities Manager Installations & Environment Marine Corps Installations East
2. MCIEAST Installations MCAF Quantico MCAS Cherry Point MCAS New River MCB Camp Lejeune MCAS Beaufort MCLB Albany MCSF Blount Island MCIEAST Camp Lejeune
3.
4. Camp Lejeune, New River and Cherry Point MILCON History Fiscal Year Millions of Dollars Record Year
5.
6. MARSOC Complex Cost: $257.5M CCD: Oct 11 FY 09 BEQ (11 Buildings) Cost: $191.4M CCD: Sep 12 P1096B/P1113 TT & Midway Park CDC’s Cost: $16.0M, CCD: Dec 11 Wallace Creek Ph II Cost: $141.1M CCD: Jun 13 Wallace Creek Ph I Cost: $195.8M, CCD: Oct 11 P882/1212 Dining Facilities Cost: $26.1M CCD: Sep 11 P1163/1164 Main & Piney Green Gates Cost: $12.6M, CCD: Oct 11 P1157/1188 Brewster CDC’s Cost: $16.1M, CCD: Oct 11 P1160 Physical Fitness Center Cost: $19.2M , CCD: Apr 12 P031 Multi-Purpose Machine Gun Range Cost: $15.1M CCD: Dec 11 MCB Camp Lejeune P1382 New Base Entry Point & Road, PH 1 Cost: $43.5M, CCD: Jan 13 P1269 TECOM (SOI) Devil Dog Cost: $9.5M, CCD: Dec 12 P-1269B Verona Loop & K-Range Water Line Cost: $8.2M, Plan Award: 03 Oct 11 P1268 TECOM (SOI) Camp Geiger Cost: $22.2M, CCD: Apr 13 P032 Infantry Plt Battle Course Cost: $15.3M, CCD: Mar 13 P1136 Mod. “K” Range Ph. II Cost: $12.4M, CCD: Apr 12 P-1187B Stone Bay Exchange Cost: $1.6M CCD: Dec 12 P1311 Infotech/Telecom Complex Cost: $29.8M, CCD: Jul 14 P-1357 (ARRA) CDC Cost: $7.5M, CCD: Feb 12 P1310 Pre-Trial Detainee Fac. Cost: $13.2M, CCD: May 12 P-1266 CHB Area Utility Expansion Cost: $16.6M CCD: Jun 13 P1247B Skeet Range Addition Cost: $1.6M, CCD: Dec 11 P1330/1378 Wounded Warrior H&C and HQ Cost: $13.3M, CCD: Apr 12 P1857/1331 Hospital Addition & Renovation Cost: $57.4M, CCD: Jan 15 P1304 MP Working Dog Kennel Cost: $4.5M, CCD: Mar 12 P-1266C Water Wells Cost: $2.7M, CCD: Nov 12 P-1266B Steam Plant Modifications Cost: $1.5M CCD: Oct 11 P-1268B Camp Geiger Access Upgrades Cost: $11.3M, Plan Award: 31 Oct 11 Under Construction Funded Awaiting Award FY07-FY10 MILCON PROJECTS
7. MCB Camp Lejeune FY-12 P-1383 New Entry Road, PH 2 Cost: $80.3M , Plan Award: 20 Dec 11 FY-11 P-Q419 MARSOC Battalion Aid Station Expansion Cost: $2.0M Plan Award: 28 Oct 11 P1256 Mess Hall Addition Cost: $1.2M, CCD: Nov 12 P1319 Camp Johnson BEQ Cost: $39.9M CCD: Aug 13 P1246 EOD Addition Cost: $5.2M CCD: Aug 12 P-1249/1322/1323 Wallace Creek North BEQs & Armory Cost: $79.5M CCD: Jul 13 FY-12 P-138 Wallace Creek, BEQ Cost: $27.1M, Plan Award: 29 Jun 12 P004 SOI Motor Trans./ Comm Maint. Facility Cost: $10.9M CCD: Dec 12 P-1034/P-1240 ANGLICO/Intel Maint/Ops Complex Cost: $92.6M CCD: Feb 14 FY-11 P-1286 Stone Bay BEQ Cost: $27.8M Plan Award: 25 Aug 11 FY-11 P-1251/1254 BEQs Cost: $71.8M Plan Award: 31 Aug 11 FY-11 P-1264 HP Utility Expansion Cost: $56.5M Plan Award: 31 Aug 11 FY-11 P-1265 FC Utility Expansion Cost: $56.5M Plan Award: 31 Aug 11 FY-12 P-1253 2D Combat Eng. Maint/OPS Cost: $66.4M , Plan Award: 30 Mar 12 FY-12 P-030 Squad Battle Course Cost: $14.5M Plan Award: 29 Jun 12 P1267 Mess Hall, French Creek Cost: $14.8M, CCD: Feb 13 P1317 BEQ, French Creek Cost: $31.6M, CCD: Aug 13 P1400 Energy Initiative – PV Cost: $7.5M, CCD: Nov 12 FY-11 P-5602 Replace School, TT II Cost: $17M, Plan Award: 05 Aug 11 FY-12 P-1285 MARSOC Armory Facility Expansion Cost: $6.7M Plan Award: 15 Mar 12 Under Construction Design Authorization FY11-FY12 MILCON PROJECTS