Benefits Realization: Program Monitoring through Middle-out Balanced Scorecard
Approach
(“Managing Vision”)
Srinivasa-Desikan Raghavan,
Tata Consultancy Services
--------------------------------------------------------------
ABSTRACT
Large transformation programs, as part of any corporate initiatives, are always tied to their intended
‘benefits’ as objectives of the programs. Even the well-endowed Program Management practitioners
usually get sidetracked by focusing on the execution of the program and its constituent projects, failing to
follow the well-developed Benefits Management principles, for periodically tracking the benefits (to be)
realized.
Balanced Scorecard (BSC), as a Corporate Strategy Deployment tool, is usually top-down driven. In this
paper, the author intends to describe a ‘Middle-out’ approach to BSC that can be adapted to any program
execution from Benefits Realization view point, given the daily challenges of program monitoring and
control.
A case study, where ‘Middle-out’ approach of BSC was adopted, would be explained in this paper.
Benefits Realization: Program Monitoring through Middle-out Balanced Scorecard
Approach
Srinivasa-Desikan Raghavan,
Tata Consultancy Services, “Nyati Tiara”, Nagar Road, Yerawada, Pune - 411006
(Desikan.r@tcs.com)
1. Introduction: As is evident, when organizations sanction large transformation programs, it would
be on the basis of a logical Business Case. Other than the requirements driven by statutory
processes of regulatory or Government authorities, many of these programs have, besides, solid
commercial end-of-logic but also of other organizational dimensions like People, Processes and
Technology as ‘drivers’ for the justification of budgetary sanctions.
‘Business Benefits’ or simply ‘Benefits’ have come a long way from being buried under Business
Case documents into being a subject of its standing in the body of Project and Program
Management framework. From a program management view point, ‘Benefits’ are the starting
point for Terms of Reference when programs are sanctioned and initiated. But once the
program(s) get into execution mode, benefits realization should become the focus of every
program review that happens at the tactical and strategic layers of the organization. Sadly, this
may not the case at every large programs that organizations run, as, not only the practitioners are
battling the daily grind of program and project management at the operational level but also may
ignore the well-developed Benefits Management framework, as identification of right measures
may be a challenge and monitoring the results of a ‘closed’ program would involve more time and
effort.
The Balanced Scorecard (BSC, henceforth) has been in practice for Corporate Performance
Management and for strategy deployment purposes since early 1990s (Kaplan and Norton, 1992;
1993; 2000). It has been used both at corporate level as well as at the level of a project or a
program. From a ‘performance management’ view point, many corporations have adopted it for
organizational performance and for measuring individuals’ performance from a Human Resource
management view point. From the example of a corporate scorecard getting cascaded to
individual teams’ level, there are cases where BSC had also been used for ‘Project focused IT
Organization’ (Alleman, 2003). From the design point of view, there are many organizations that
exist specializing both in BSC tools and in training (2GC, 2009).
In this paper, the author explains, in brief, a typical Benefits Management life cycle from the
Project and Program Management literature (and also from what is being practiced at Tata
Consultancy Services (TCS) for their customer assignments); describes BSC, which can be a
‘middle-out’ approach compared to the traditional top down way of arriving at scorecards; and
suggests how BSC – Middle –out approach can be used for tracking Benefits Realization in large
programs.
2. Benefits Management framework: The Benefits Management Strategy documentation should
take a cue from the program business case and elaborate upon the following points:
Description of the Program's benefits and where in the organization they will occur
(People, Process and Technology dimensions, besides the corporate financials);
Benefit model showing interrelations and dependencies, amongst intended benefits;
Functions, roles and responsibilities of individuals in the Program and in the larger
organization, as the recipients and the owners of the intended benefits (for benefits
planning and realization);
Review and assessment process for measuring benefits realization; this would be
accomplished by appropriate ‘Toll Gate(s) Review(s)’, along the Program progress.
The following diagram depicts the phases in Benefits Management framework and their
relationship to Program Lifecycle.
Fig 1: Program and Benefits Management Phases
Straw
Model
Metrics
Dovetail
Plan
Initiate – Plan – Mobilize – Execute - Close
a. Phases of Benefits Management: The Benefits Management Guideline is a collection of
activities, frameworks and templates designed to achieve the goal of realizing business values
from the programs. It achieves this via key phases, each with its own purpose and outputs.
Benefits Identification: Before we can plan or measure benefits, we must understand that
outcomes which are the targets of such investment. The Benefits Identification phase is all about
understanding and establishing the strategic intent and identifying the outcomes required
achieving this intent. A ‘Straw Model’ would be arrived at, identifying the relationships amongst, -
Program-end Business Benefits (the identified ‘reasons’ or the ‘intents’ for the Program
Business Case;
‘Enablers’ (the dimensions of People, Processes (IT and Business) and the Technology
drivers);
‘Intermediate Benefits’: this is a critical step for identifying those ‘deliverables’ or
‘outcomes’ of intermediate stages of the Program, which would be then the drivers for
final Program Benefits.
Benefits Analysis: The focus of this step is to quantify the benefits in terms of measurable units.
Metrics, which can be tagged to each identified benefits along with Straw Model, would facilitate
drawing up of relationships amongst these benefits, along the lines of BSC, viz., ‘lead’ and ‘lag’
indicators. This would also facilitate testing hypotheses of ‘cause-and-effect’ relationships along
various, identified benefits, taking the cue from the BSC metaphor.
Benefits Planning: A plan is then created, which includes additional details such as the owner,
the target to be achieved and the units with which to measure benefits, via related projects’
deliverables. It also includes the necessary arrangements and infrastructure needed to be in
place to realize the benefits.
From the view point of program management phases, getting aligned to Benefits Management
phases, it should be noted that any Benefits Realization Plan should be dovetailed to Program
Plan, so that activities related to monitoring benefits accrual could be integrated with Program
Plan and then monitored.
Benefits Realization: Realizing the benefits is then achieved by monitoring progress towards the
planned outcomes, linked to the deliverables of appropriate project or group of projects. An
example could be a new Billing System or an Inventory System, whose efficiency parameters like
Speed, Capacity or Number of Transactions can be numerically verified and be compared with
the earlier systems. Deviations from plan can be picked up early, with appropriate corrective
action being planned and taken up. Throughout this process the business case should be
updated and maintained as there will inevitably be differences between what was initially
proposed and what is attainable as the program progresses.
Benefits Reporting: Reporting of metrics related to the identified-benefits (‘actual versus
planned’) is provided to the Governance body in accordance with the plan, facilitating
accountability of performance of new systems in place, as deliverables and outcomes of the
program are getting realized.
The final review and evaluation of benefits should ideally be completed after the business
transformation has fully completed and changes are embedded into the subsequent operations,
as ‘business as usual’. This is can take several months after a system ‘go-live’.
The following section explains the BSC from a middle-out approach to designing score cards.
3. BSC design – the ‘Middle out’
There are cases in literature (Alleman, 2003), where BSC was used as a pure Project
Management element, complementing the traditional project management and control
mechanism. But the design of BSC was attempted from a top down approach. Goold et al.
(1994), describe three types of ‘Parenting Styles’, viz. strategic planning, strategic control and
financial control, for the roles and responsibilities between corporate and organisational units.
These types of styles also influence the role the corporate would adopt in the design and usage
of BSC across corporate and business units (De Waal, 2007). Usually for large programs, we can
adopt a method that has parallel to ‘strategic control’ style, wherein the corporate (the Program
Vision, in this case) would influence the design of scorecard, but it would be the Business
Benefits Plan that would influence the usage of it.
When a program gets sanctioned, the program sponsor, steering committee, business
stakeholders and the program and project managers go through the Benefits Management steps
(Identify, Analyse, Plan) to develop a Straw Model, Metrics and their BSC relationships and thus,
a first cut BSC for the program, much akin to a Corporate BSC is arrived at.
In this approach, the program core team would work out multiple iterations, to arrive at individual
scorecards across the individual projects (re-using many prevailing project measures) and
connecting them to the Program BSC, to arrive at a consensus that is aligned with the proposed
Benefits metrics. One would be able to retain many measures that can be used at individual
project teams’ level, while choosing the ones that would get ‘aggregated’ at program level
Benefits scorecard. Thus, program Benefits Realization expectations (metrics) were typically
‘cascaded’ downwards as BSC measures (from Program Benefits BSC to Projects Teams’
Delivery – Benefits BSC), while re-using typical project delivery measures for ‘aggregating’
upwards.
3.1.Characteristics of BSC design – the ‘Middle out’
The design process is typically recursive at each time when a new project team is added to the
program portfolio and / or when the Program Benefits or Business case is changed due to
unexpected events; and that the participating project team contributes to the BSC Benefits BSC
design more, by way of carrying forward their set of existing measures. Thus we would prefer to
call the design approach the ‘Middle-out’, compared to top down mode of designing scorecards.
The following steps would describe the process of this design approach:
1. Start-up / or from a previous steady state phase: Existing islands of projects in the Program
portfolio, (with Identified & Analysed Benefits, independent Service Level Agreements (SLA), Key
Performance Indicators (KPI) and measures) focus on their operational efficiency, project
management and control, besides monitoring for Risk management and Benefits Management.
2. Coalescence phase: When a new program is sanctioned, driven by the program vision and goals,
coalescence comes into play. The steps in this phase are -
1. Select pilot projects that have similar and comparable SLAs and KPIs and Delivery
Benefits metrics.
2. Derive ‘tactical themes’ as opposed to Corporate Strategic Themes. (The example is –
Project Delivery Benefits as opposed to Program Vision BSC).
3. Develop Strategy Map and the Benefits Straw Map from the new Delivery Benefits goals
and the identified program benefits to derive the new set of Benefits measures.
4. Assign targets with tolerance ranges (Green / Amber / Red) for the finalized measures
that would drive the projects’ and program goals to fruition.
5. Analyse new risk/impediments profiles and mitigation plans.
6. Derive the new governance model, Benefits Straw Model and Metrics; get approval for
the same.
3. Communication Phase: Publish the Program performance and Benefits Scorecard to
stakeholders and draw up communication and change management plans. (Town hall meetings,
Training, Kiosks for Demonstrations, etc. as required).
4. Implementation Phase: Go Live and monitor. (Closure / start steady state phase)
5. Iterate from ‘Coalescence’, when new projects join.
The following figure (Fig. 2) depicts the design elements.
Fig 2: Strategy Maps for BSC Design Middle-Out
We can compare the traditional Balanced Scorecard approach (the first generation) with the
middle-out approach in the following way (Table 1).
BSC Top Down BSC Middle-Out
Starts at Organizational top;
Corporate Vision driven SLAs / KPI
Focus on Customer – Vendor
Relationship, Portfolio / Program
Objectives; Benefits driven SLAs
Long Term planned (3-5 years) Short Term focused (1-2 years)
Start from Financial goals
(Perspective) and derive other
Perspectives. Identify Strategic
Initiatives (as relevant).
Start from Customer Expectations on
Portfolio & program Benefits and
distribute Delivery metrics and SLAs
across relevant BSC Perspectives
Usually top-down approach to BSC ‘Middle-out’ design’; iterative process of
top-down (from Portfolio Benefits and
design SLAs) and bottom-up, where the
quantum of contribution is more from
Projects’ level (Delivery Benefits and
operational parameters for arriving at
measures and targets).
Strategy Maps are enablers for
BSC design; they validate the
Strategic Themes.
Strategy Maps and Benefits Straw maps
drive the design.
Changes to Dash board measures
are generally minimal at Corporate
level BSC.
Flexible to changes to measures or their
targets both at Projects’ level and at
‘Internal Processes’ Perspective of
individual Scorecards.
Table 1: Comparison of BSC Design approaches
Thus, the Program Benefits Scorecard can evolve from the relationship to individual projects’
level BSCs easily. Also, the scorecard structure (parent – children scorecards) can be extended
to more projects / changed Business Cases, at different ‘coalescence’ phases, as the maturity of
Benefits Management in the program organization grows.
3.2.Performance Index
For the purpose of monitoring performance, as well for the purpose of rewards recognition, the
individual measures can be given ‘weights’ (though, during the time of piloting, the weights can be
set to a value of 1) and their performance deviation can be measured at regular intervals. The
individual measures’ performance values can then aggregated for specific BSC (4) perspectives,
as well as at individual scorecard levels. Thus we would have various ‘weighted performance of
measures’, which are called Performance Indices (PI) on the scorecards. This idea can help the
program in a significant way, by comparing PIs across various perspectives, across scorecards
as well as across individual teams.
Thus Benefits Realization can be monitored through a set of ‘lead’ and ‘lag’ measures across
various projects that make up the program, while PIs can also help in identifying the cause-and-
effect’ hypotheses.
4. Recommendation for BSC Implementation
The launch preparation phase would typically last about 4 weeks, when internal marketing
campaign should be conducted. The project teams, project and program manager(s), and the
program core team would then freeze the scorecard elements (that include the benefits’
measures, negotiated targets and their target deviation zones) and address the program
roadblocks and issues. The key elements for scripting a success story of Program Benefits BSC
implementation are the town hall meetings with individual teams and stakeholders, content-rich
collaterals for internal marketing purposes and self-running demonstration kits from the program
portal for the user groups.
In the final mode of governance, we should superpose the new Benefits BSC based program
review, while retaining the existing delivery performance review mechanisms at the Program /
Project level, wherever required. This would help the program to track important program specific
benefits’ measures, while facilitating the need-driven data drill down at individual projects’ level.
Also more importantly, the adoption of BSC dashboard would facilitate better corporate
communication on business, program and project specific audiences, while parallel tracking the
Benefits metrics for their performance.
5. Some closing thoughts
Our focus in this paper has been that BSC dashboard will be the link in corporate communication
amongst business, IT-program and IT-project teams that have both delivery based and benefits
based BSC metrics, given the importance of tracking the program goals through their benefits.
Given below (Fig. 3) is an example of Program BSC (for the sake of confidentiality, we have
masked the actual numbers; data points from April-09 onwards were re-constructed for display).
Fig 3: BSC Program scorecard
***
Sr # Performance Measure Unit KPI Target Frequency Apr '09
Trend
May
'09
Trend
Jun '09
Trend
Finance
1 TCO Savings (Direct / Indirect) $ N Half yearly
2 Sprint Burnup rate $ Y Monthly
Customer 0.80 0.80 0.80
3 Customer Satisfaction Index (Overall) % Y 90% Half yearly 84% 84% 84%
4 CSI - Most important parameters rated low % Y 10% Half yearly 50% 11% 11%
5
CSI - Most important Service & Business Goals
parameters rated high
% Y 80% Half yearly 86% 86% 86%
6 Customer Appreciations # N Monthly 8 9 6
7 Customer Complaints # N Monthly 0 0 3
8 Quality of Service (from annual survey) # N Yearly
Process & Delivery 0.54 0.54 0.66
9 Post Delivery Defects # Y 5 Monthly 2 4 4
10 Sprint review Meeting attendance % Y 100% Monthly 100 100 90
11 Monthly Governance % Y 100% Monthly 33% 67% 60%
12 Velocity (per Sprint) (Total) # Y 15 Monthly 14 14 14
13 Velocity (per Sprint) (per Scrum team) # Y 3 Monthly 3 3 3
14 Burn down deviation (per Sprint) % Y 5% Monthly 8.0% 8.0% 9.0%
15 SLA compliance to response time (Resources SLA) % Y 95% Monthly 99.7% 99.6% 99.4%
16 SLA compliance to resolution time (Resources SLA) % Y 95% Monthly 97.0% 96.6% 96.7%
Learning, People & Competency 0.40 0.90 0.90
17 Compliance to minimum competency level % Y 100% Monthly 80% 80% 80%
18 Unplanned Attrition in critical phases # Y 0 Monthly 1 0 0
19 Upload activity of assets into KM system # N Monthly 0 0 0
20 Reference activity of assets in KM system # N Monthly 0 0 0
Portfolio Performance Index 0.58 0.58 0.72
0
References
2GC (2009), “Performance Management & 3
rd
Generation Balanced Scorecard”, 2GC Active
Management, <www.2gc.co.uk>, (Accessed 02/01/2010).
Advanced Development Methods, (2003), “Scrum Methodology: Incremental, Iterative Software
Development from Agile processes”, <www.controlchaos.com> (Accessed 02/01/2010).
Alleman, G.B. (2003), “Using Balanced Scorecard to Build a Project Focused IT Organization”, in
Proceedings of Balanced Scorecard Conference, San Francisco.
De Waal, A. (2007), “Strategic Performance Management: A managerial and behavioural
approach”, Palgrave Macmillan, New York.
Goold, M., Campbell, A. and Alexander, M., (1994), “Corporate Level Strategy: Creating value in
the multibusiness company”, Wiley, New York.
Kaplan, R.S. and Norton, D.P. (1992), “The balanced scorecard: measures that drive
performance”, Harvard Business Review, January-February 1992, pp. 71-80.
Kaplan, R.S. and Norton, D.P. (1993), “Putting the Balanced Scorecard to Work”, Harvard
Business Review, September – October, 2-16.
Kaplan, R.S. and Norton, D.P. (2000), “The Strategy-Focused Organization: How balanced
scorecard companies thrive in the new business environment”, Harvard Business School Press,
Boston, Massachusetts.
Sliger, M. (2007), “A Project Manager’s Survival Guide to Going Agile”, Rally Software
Development Corp. < www.rallydev.com > (Accessed 02/01/2010).
================================end of text==============================
Srinivasa desikanraghavan

Más contenido relacionado

La actualidad más candente

Presentation by Gaurav Sapra
Presentation by Gaurav SapraPresentation by Gaurav Sapra
Presentation by Gaurav SapraPMI_IREP_TP
 
Presentation by subhajit bhattacharya1
Presentation by subhajit bhattacharya1Presentation by subhajit bhattacharya1
Presentation by subhajit bhattacharya1PMI_IREP_TP
 
Presentation by piyush jain
Presentation by piyush jainPresentation by piyush jain
Presentation by piyush jainPMI_IREP_TP
 
Presentation by anipriya p
Presentation by anipriya pPresentation by anipriya p
Presentation by anipriya pPMI_IREP_TP
 
Keys To Successful Governance with SOA
Keys To Successful Governance with SOAKeys To Successful Governance with SOA
Keys To Successful Governance with SOANathaniel Palmer
 
Presentation by jayanta debnath
Presentation by jayanta debnathPresentation by jayanta debnath
Presentation by jayanta debnathPMI_IREP_TP
 
Project, Program & Portfolio Management
Project, Program & Portfolio ManagementProject, Program & Portfolio Management
Project, Program & Portfolio ManagementAnand Subramaniam
 
Business Readiness Assessment &amp; Ocm Platform
Business Readiness Assessment &amp; Ocm PlatformBusiness Readiness Assessment &amp; Ocm Platform
Business Readiness Assessment &amp; Ocm PlatformEduardo Muniz
 
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...TURKI , PMP
 
Benefit Management; How to fill multi gaps with only one bridge?
Benefit Management; How to fill multi gaps with only one bridge?Benefit Management; How to fill multi gaps with only one bridge?
Benefit Management; How to fill multi gaps with only one bridge?Imad Alsadeq
 
Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5pankajsh10
 
Efficacy of Project Management,
Efficacy of Project Management, Efficacy of Project Management,
Efficacy of Project Management, Assignment Studio
 
Program management - Fundamentals
Program management   - FundamentalsProgram management   - Fundamentals
Program management - FundamentalsJulen Mohanty
 
T2 - T2S Consolidation | How to be compliant in time?
T2 - T2S Consolidation | How to be compliant in time?T2 - T2S Consolidation | How to be compliant in time?
T2 - T2S Consolidation | How to be compliant in time?PwC Italy
 
Organisational Change Management in ERP Projects
Organisational Change Management in ERP Projects Organisational Change Management in ERP Projects
Organisational Change Management in ERP Projects Lumenia Consulting
 
Notes on balanced scorecard
Notes on balanced scorecardNotes on balanced scorecard
Notes on balanced scorecardGlen Alleman
 

La actualidad más candente (20)

Presentation by Gaurav Sapra
Presentation by Gaurav SapraPresentation by Gaurav Sapra
Presentation by Gaurav Sapra
 
Presentation by subhajit bhattacharya1
Presentation by subhajit bhattacharya1Presentation by subhajit bhattacharya1
Presentation by subhajit bhattacharya1
 
Presentation by piyush jain
Presentation by piyush jainPresentation by piyush jain
Presentation by piyush jain
 
Presentation by anipriya p
Presentation by anipriya pPresentation by anipriya p
Presentation by anipriya p
 
OCM Overview
OCM OverviewOCM Overview
OCM Overview
 
Keys To Successful Governance with SOA
Keys To Successful Governance with SOAKeys To Successful Governance with SOA
Keys To Successful Governance with SOA
 
Presentation by jayanta debnath
Presentation by jayanta debnathPresentation by jayanta debnath
Presentation by jayanta debnath
 
Project, Program & Portfolio Management
Project, Program & Portfolio ManagementProject, Program & Portfolio Management
Project, Program & Portfolio Management
 
Business Readiness Assessment &amp; Ocm Platform
Business Readiness Assessment &amp; Ocm PlatformBusiness Readiness Assessment &amp; Ocm Platform
Business Readiness Assessment &amp; Ocm Platform
 
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...
Inform the selection of 5 efficiency and 8 effectiveness measures. This frame...
 
Benefit Management; How to fill multi gaps with only one bridge?
Benefit Management; How to fill multi gaps with only one bridge?Benefit Management; How to fill multi gaps with only one bridge?
Benefit Management; How to fill multi gaps with only one bridge?
 
Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5
 
Pm Student Ho
Pm Student HoPm Student Ho
Pm Student Ho
 
Efficacy of Project Management,
Efficacy of Project Management, Efficacy of Project Management,
Efficacy of Project Management,
 
Program management - Fundamentals
Program management   - FundamentalsProgram management   - Fundamentals
Program management - Fundamentals
 
Balanced scorecard for effective project selection process
Balanced scorecard for effective project selection processBalanced scorecard for effective project selection process
Balanced scorecard for effective project selection process
 
Governance
GovernanceGovernance
Governance
 
T2 - T2S Consolidation | How to be compliant in time?
T2 - T2S Consolidation | How to be compliant in time?T2 - T2S Consolidation | How to be compliant in time?
T2 - T2S Consolidation | How to be compliant in time?
 
Organisational Change Management in ERP Projects
Organisational Change Management in ERP Projects Organisational Change Management in ERP Projects
Organisational Change Management in ERP Projects
 
Notes on balanced scorecard
Notes on balanced scorecardNotes on balanced scorecard
Notes on balanced scorecard
 

Similar a Srinivasa desikanraghavan

Strategy MapsOnce change leaders have framed their vision and st.docx
Strategy MapsOnce change leaders have framed their vision and st.docxStrategy MapsOnce change leaders have framed their vision and st.docx
Strategy MapsOnce change leaders have framed their vision and st.docxsusanschei
 
EFFICACY OF PROJECT MANAGEMENT
EFFICACY OF PROJECT MANAGEMENTEFFICACY OF PROJECT MANAGEMENT
EFFICACY OF PROJECT MANAGEMENTAssignment Studio
 
Steps to blueprint successful erp projects immortal
Steps to blueprint successful erp projects immortalSteps to blueprint successful erp projects immortal
Steps to blueprint successful erp projects immortalImmortal Technologies
 
SHRM HR Metrics.pdf
SHRM HR Metrics.pdfSHRM HR Metrics.pdf
SHRM HR Metrics.pdftrunbate
 
Performance management government
Performance management governmentPerformance management government
Performance management governmentchatwijustin5010
 
Rinat Galyautdinov: Measurement concept of operation
Rinat Galyautdinov: Measurement concept of operationRinat Galyautdinov: Measurement concept of operation
Rinat Galyautdinov: Measurement concept of operationRinat Galyautdinov
 
Measurement_Information Needs_paper_Crosstalk
Measurement_Information Needs_paper_CrosstalkMeasurement_Information Needs_paper_Crosstalk
Measurement_Information Needs_paper_Crosstalkpbaxter
 
How to get started - managing a programme
How to get started - managing a programmeHow to get started - managing a programme
How to get started - managing a programmeMaven
 
Benefits-led decision making drives value maximisation white paper
Benefits-led decision making drives value maximisation white paperBenefits-led decision making drives value maximisation white paper
Benefits-led decision making drives value maximisation white paperAssociation for Project Management
 
oracle-hbr-campaign-brochure-eb3-v7-2288406
oracle-hbr-campaign-brochure-eb3-v7-2288406oracle-hbr-campaign-brochure-eb3-v7-2288406
oracle-hbr-campaign-brochure-eb3-v7-2288406Mike Metcalf
 
Effective Talent Management Strategy: Adapting Practices and Plans
Effective Talent Management Strategy: Adapting Practices and PlansEffective Talent Management Strategy: Adapting Practices and Plans
Effective Talent Management Strategy: Adapting Practices and PlansWowledge
 
Strategy MapsOnce change leaders have framed their vision and st.docx
Strategy MapsOnce change leaders have framed their vision and st.docxStrategy MapsOnce change leaders have framed their vision and st.docx
Strategy MapsOnce change leaders have framed their vision and st.docxflorriezhamphrey3065
 
006 benefits &amp; knowledge management
006 benefits &amp; knowledge  management006 benefits &amp; knowledge  management
006 benefits &amp; knowledge managementdrdej19
 
006 benefits &amp; knowledge management
006 benefits &amp; knowledge  management006 benefits &amp; knowledge  management
006 benefits &amp; knowledge managementDr Fereidoun Dejahang
 

Similar a Srinivasa desikanraghavan (20)

Strategy MapsOnce change leaders have framed their vision and st.docx
Strategy MapsOnce change leaders have framed their vision and st.docxStrategy MapsOnce change leaders have framed their vision and st.docx
Strategy MapsOnce change leaders have framed their vision and st.docx
 
A white paper on Program Management
A white paper on Program ManagementA white paper on Program Management
A white paper on Program Management
 
EFFICACY OF PROJECT MANAGEMENT
EFFICACY OF PROJECT MANAGEMENTEFFICACY OF PROJECT MANAGEMENT
EFFICACY OF PROJECT MANAGEMENT
 
Benefits and knowledge management
Benefits and knowledge  managementBenefits and knowledge  management
Benefits and knowledge management
 
PROGRAMME MANAGEMENT BEST PRATICE
PROGRAMME MANAGEMENT BEST PRATICEPROGRAMME MANAGEMENT BEST PRATICE
PROGRAMME MANAGEMENT BEST PRATICE
 
Steps to blueprint successful erp projects immortal
Steps to blueprint successful erp projects immortalSteps to blueprint successful erp projects immortal
Steps to blueprint successful erp projects immortal
 
SHRM HR Metrics.pdf
SHRM HR Metrics.pdfSHRM HR Metrics.pdf
SHRM HR Metrics.pdf
 
Performance management government
Performance management governmentPerformance management government
Performance management government
 
Rinat Galyautdinov: Measurement concept of operation
Rinat Galyautdinov: Measurement concept of operationRinat Galyautdinov: Measurement concept of operation
Rinat Galyautdinov: Measurement concept of operation
 
Measurement_Information Needs_paper_Crosstalk
Measurement_Information Needs_paper_CrosstalkMeasurement_Information Needs_paper_Crosstalk
Measurement_Information Needs_paper_Crosstalk
 
Erp-PMO
Erp-PMOErp-PMO
Erp-PMO
 
How to get started - managing a programme
How to get started - managing a programmeHow to get started - managing a programme
How to get started - managing a programme
 
Benchmarking Article
Benchmarking ArticleBenchmarking Article
Benchmarking Article
 
Benefits-led decision making drives value maximisation white paper
Benefits-led decision making drives value maximisation white paperBenefits-led decision making drives value maximisation white paper
Benefits-led decision making drives value maximisation white paper
 
oracle-hbr-campaign-brochure-eb3-v7-2288406
oracle-hbr-campaign-brochure-eb3-v7-2288406oracle-hbr-campaign-brochure-eb3-v7-2288406
oracle-hbr-campaign-brochure-eb3-v7-2288406
 
Effective Talent Management Strategy: Adapting Practices and Plans
Effective Talent Management Strategy: Adapting Practices and PlansEffective Talent Management Strategy: Adapting Practices and Plans
Effective Talent Management Strategy: Adapting Practices and Plans
 
Implementation and Evaluation
Implementation and EvaluationImplementation and Evaluation
Implementation and Evaluation
 
Strategy MapsOnce change leaders have framed their vision and st.docx
Strategy MapsOnce change leaders have framed their vision and st.docxStrategy MapsOnce change leaders have framed their vision and st.docx
Strategy MapsOnce change leaders have framed their vision and st.docx
 
006 benefits &amp; knowledge management
006 benefits &amp; knowledge  management006 benefits &amp; knowledge  management
006 benefits &amp; knowledge management
 
006 benefits &amp; knowledge management
006 benefits &amp; knowledge  management006 benefits &amp; knowledge  management
006 benefits &amp; knowledge management
 

Más de PMI2011

Bhavesh pmi final
Bhavesh  pmi finalBhavesh  pmi final
Bhavesh pmi finalPMI2011
 
Day 1 1410 - 1455 - pearl 2 - vijay sane
Day 1   1410 - 1455 - pearl 2 - vijay saneDay 1   1410 - 1455 - pearl 2 - vijay sane
Day 1 1410 - 1455 - pearl 2 - vijay sanePMI2011
 
Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
Day 1   1620 - 1705 - maple - pranabendu bhattacharyyaDay 1   1620 - 1705 - maple - pranabendu bhattacharyya
Day 1 1620 - 1705 - maple - pranabendu bhattacharyyaPMI2011
 
Wilso anandaraj balasubramaniankrishnamurthy
Wilso anandaraj balasubramaniankrishnamurthyWilso anandaraj balasubramaniankrishnamurthy
Wilso anandaraj balasubramaniankrishnamurthyPMI2011
 
Vs velan dchakravarty_ppchakraborti
Vs velan dchakravarty_ppchakrabortiVs velan dchakravarty_ppchakraborti
Vs velan dchakravarty_ppchakrabortiPMI2011
 
Vineet jain
Vineet jainVineet jain
Vineet jainPMI2011
 
Yamuna padmanaban
Yamuna padmanabanYamuna padmanaban
Yamuna padmanabanPMI2011
 
Vimal kumarkhanna
Vimal kumarkhannaVimal kumarkhanna
Vimal kumarkhannaPMI2011
 
Venkatraman l
Venkatraman lVenkatraman l
Venkatraman lPMI2011
 
Soumen de
Soumen deSoumen de
Soumen dePMI2011
 
Sujit sopan barhate
Sujit sopan barhateSujit sopan barhate
Sujit sopan barhatePMI2011
 
Sharad pandey abhisek goswami
Sharad pandey abhisek goswamiSharad pandey abhisek goswami
Sharad pandey abhisek goswamiPMI2011
 
Soma roy sarkar
Soma roy sarkarSoma roy sarkar
Soma roy sarkarPMI2011
 
Shallu soni mymoonshabana_lavanya raghuraman
Shallu soni mymoonshabana_lavanya raghuramanShallu soni mymoonshabana_lavanya raghuraman
Shallu soni mymoonshabana_lavanya raghuramanPMI2011
 
Regeena pererira sujithn_rai_suchitrajoyceb
Regeena pererira sujithn_rai_suchitrajoycebRegeena pererira sujithn_rai_suchitrajoyceb
Regeena pererira sujithn_rai_suchitrajoycebPMI2011
 
Ramesh ganiga
Ramesh ganigaRamesh ganiga
Ramesh ganigaPMI2011
 
Pranabendu
PranabenduPranabendu
PranabenduPMI2011
 
Rt sundari ashutosh_pandey
Rt sundari ashutosh_pandeyRt sundari ashutosh_pandey
Rt sundari ashutosh_pandeyPMI2011
 
Pradeep n singh_praveenkyadav
Pradeep n singh_praveenkyadavPradeep n singh_praveenkyadav
Pradeep n singh_praveenkyadavPMI2011
 
Parvathi karthik
Parvathi karthikParvathi karthik
Parvathi karthikPMI2011
 

Más de PMI2011 (20)

Bhavesh pmi final
Bhavesh  pmi finalBhavesh  pmi final
Bhavesh pmi final
 
Day 1 1410 - 1455 - pearl 2 - vijay sane
Day 1   1410 - 1455 - pearl 2 - vijay saneDay 1   1410 - 1455 - pearl 2 - vijay sane
Day 1 1410 - 1455 - pearl 2 - vijay sane
 
Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
Day 1   1620 - 1705 - maple - pranabendu bhattacharyyaDay 1   1620 - 1705 - maple - pranabendu bhattacharyya
Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
 
Wilso anandaraj balasubramaniankrishnamurthy
Wilso anandaraj balasubramaniankrishnamurthyWilso anandaraj balasubramaniankrishnamurthy
Wilso anandaraj balasubramaniankrishnamurthy
 
Vs velan dchakravarty_ppchakraborti
Vs velan dchakravarty_ppchakrabortiVs velan dchakravarty_ppchakraborti
Vs velan dchakravarty_ppchakraborti
 
Vineet jain
Vineet jainVineet jain
Vineet jain
 
Yamuna padmanaban
Yamuna padmanabanYamuna padmanaban
Yamuna padmanaban
 
Vimal kumarkhanna
Vimal kumarkhannaVimal kumarkhanna
Vimal kumarkhanna
 
Venkatraman l
Venkatraman lVenkatraman l
Venkatraman l
 
Soumen de
Soumen deSoumen de
Soumen de
 
Sujit sopan barhate
Sujit sopan barhateSujit sopan barhate
Sujit sopan barhate
 
Sharad pandey abhisek goswami
Sharad pandey abhisek goswamiSharad pandey abhisek goswami
Sharad pandey abhisek goswami
 
Soma roy sarkar
Soma roy sarkarSoma roy sarkar
Soma roy sarkar
 
Shallu soni mymoonshabana_lavanya raghuraman
Shallu soni mymoonshabana_lavanya raghuramanShallu soni mymoonshabana_lavanya raghuraman
Shallu soni mymoonshabana_lavanya raghuraman
 
Regeena pererira sujithn_rai_suchitrajoyceb
Regeena pererira sujithn_rai_suchitrajoycebRegeena pererira sujithn_rai_suchitrajoyceb
Regeena pererira sujithn_rai_suchitrajoyceb
 
Ramesh ganiga
Ramesh ganigaRamesh ganiga
Ramesh ganiga
 
Pranabendu
PranabenduPranabendu
Pranabendu
 
Rt sundari ashutosh_pandey
Rt sundari ashutosh_pandeyRt sundari ashutosh_pandey
Rt sundari ashutosh_pandey
 
Pradeep n singh_praveenkyadav
Pradeep n singh_praveenkyadavPradeep n singh_praveenkyadav
Pradeep n singh_praveenkyadav
 
Parvathi karthik
Parvathi karthikParvathi karthik
Parvathi karthik
 

Último

Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxappkodes
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in PhilippinesDavidSamuel525586
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
PB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal BrandPB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal BrandSharisaBethune
 

Último (20)

Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptx
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in Philippines
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
PB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal BrandPB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal Brand
 

Srinivasa desikanraghavan

  • 1. Benefits Realization: Program Monitoring through Middle-out Balanced Scorecard Approach (“Managing Vision”) Srinivasa-Desikan Raghavan, Tata Consultancy Services -------------------------------------------------------------- ABSTRACT Large transformation programs, as part of any corporate initiatives, are always tied to their intended ‘benefits’ as objectives of the programs. Even the well-endowed Program Management practitioners usually get sidetracked by focusing on the execution of the program and its constituent projects, failing to follow the well-developed Benefits Management principles, for periodically tracking the benefits (to be) realized. Balanced Scorecard (BSC), as a Corporate Strategy Deployment tool, is usually top-down driven. In this paper, the author intends to describe a ‘Middle-out’ approach to BSC that can be adapted to any program execution from Benefits Realization view point, given the daily challenges of program monitoring and control. A case study, where ‘Middle-out’ approach of BSC was adopted, would be explained in this paper.
  • 2. Benefits Realization: Program Monitoring through Middle-out Balanced Scorecard Approach Srinivasa-Desikan Raghavan, Tata Consultancy Services, “Nyati Tiara”, Nagar Road, Yerawada, Pune - 411006 (Desikan.r@tcs.com) 1. Introduction: As is evident, when organizations sanction large transformation programs, it would be on the basis of a logical Business Case. Other than the requirements driven by statutory processes of regulatory or Government authorities, many of these programs have, besides, solid commercial end-of-logic but also of other organizational dimensions like People, Processes and Technology as ‘drivers’ for the justification of budgetary sanctions. ‘Business Benefits’ or simply ‘Benefits’ have come a long way from being buried under Business Case documents into being a subject of its standing in the body of Project and Program Management framework. From a program management view point, ‘Benefits’ are the starting point for Terms of Reference when programs are sanctioned and initiated. But once the program(s) get into execution mode, benefits realization should become the focus of every program review that happens at the tactical and strategic layers of the organization. Sadly, this may not the case at every large programs that organizations run, as, not only the practitioners are battling the daily grind of program and project management at the operational level but also may ignore the well-developed Benefits Management framework, as identification of right measures may be a challenge and monitoring the results of a ‘closed’ program would involve more time and effort. The Balanced Scorecard (BSC, henceforth) has been in practice for Corporate Performance Management and for strategy deployment purposes since early 1990s (Kaplan and Norton, 1992; 1993; 2000). It has been used both at corporate level as well as at the level of a project or a program. From a ‘performance management’ view point, many corporations have adopted it for organizational performance and for measuring individuals’ performance from a Human Resource management view point. From the example of a corporate scorecard getting cascaded to individual teams’ level, there are cases where BSC had also been used for ‘Project focused IT Organization’ (Alleman, 2003). From the design point of view, there are many organizations that exist specializing both in BSC tools and in training (2GC, 2009). In this paper, the author explains, in brief, a typical Benefits Management life cycle from the Project and Program Management literature (and also from what is being practiced at Tata Consultancy Services (TCS) for their customer assignments); describes BSC, which can be a ‘middle-out’ approach compared to the traditional top down way of arriving at scorecards; and
  • 3. suggests how BSC – Middle –out approach can be used for tracking Benefits Realization in large programs. 2. Benefits Management framework: The Benefits Management Strategy documentation should take a cue from the program business case and elaborate upon the following points: Description of the Program's benefits and where in the organization they will occur (People, Process and Technology dimensions, besides the corporate financials); Benefit model showing interrelations and dependencies, amongst intended benefits; Functions, roles and responsibilities of individuals in the Program and in the larger organization, as the recipients and the owners of the intended benefits (for benefits planning and realization); Review and assessment process for measuring benefits realization; this would be accomplished by appropriate ‘Toll Gate(s) Review(s)’, along the Program progress. The following diagram depicts the phases in Benefits Management framework and their relationship to Program Lifecycle. Fig 1: Program and Benefits Management Phases Straw Model Metrics Dovetail Plan Initiate – Plan – Mobilize – Execute - Close
  • 4. a. Phases of Benefits Management: The Benefits Management Guideline is a collection of activities, frameworks and templates designed to achieve the goal of realizing business values from the programs. It achieves this via key phases, each with its own purpose and outputs. Benefits Identification: Before we can plan or measure benefits, we must understand that outcomes which are the targets of such investment. The Benefits Identification phase is all about understanding and establishing the strategic intent and identifying the outcomes required achieving this intent. A ‘Straw Model’ would be arrived at, identifying the relationships amongst, - Program-end Business Benefits (the identified ‘reasons’ or the ‘intents’ for the Program Business Case; ‘Enablers’ (the dimensions of People, Processes (IT and Business) and the Technology drivers); ‘Intermediate Benefits’: this is a critical step for identifying those ‘deliverables’ or ‘outcomes’ of intermediate stages of the Program, which would be then the drivers for final Program Benefits. Benefits Analysis: The focus of this step is to quantify the benefits in terms of measurable units. Metrics, which can be tagged to each identified benefits along with Straw Model, would facilitate drawing up of relationships amongst these benefits, along the lines of BSC, viz., ‘lead’ and ‘lag’ indicators. This would also facilitate testing hypotheses of ‘cause-and-effect’ relationships along various, identified benefits, taking the cue from the BSC metaphor. Benefits Planning: A plan is then created, which includes additional details such as the owner, the target to be achieved and the units with which to measure benefits, via related projects’ deliverables. It also includes the necessary arrangements and infrastructure needed to be in place to realize the benefits. From the view point of program management phases, getting aligned to Benefits Management phases, it should be noted that any Benefits Realization Plan should be dovetailed to Program Plan, so that activities related to monitoring benefits accrual could be integrated with Program Plan and then monitored. Benefits Realization: Realizing the benefits is then achieved by monitoring progress towards the planned outcomes, linked to the deliverables of appropriate project or group of projects. An example could be a new Billing System or an Inventory System, whose efficiency parameters like Speed, Capacity or Number of Transactions can be numerically verified and be compared with the earlier systems. Deviations from plan can be picked up early, with appropriate corrective action being planned and taken up. Throughout this process the business case should be updated and maintained as there will inevitably be differences between what was initially proposed and what is attainable as the program progresses.
  • 5. Benefits Reporting: Reporting of metrics related to the identified-benefits (‘actual versus planned’) is provided to the Governance body in accordance with the plan, facilitating accountability of performance of new systems in place, as deliverables and outcomes of the program are getting realized. The final review and evaluation of benefits should ideally be completed after the business transformation has fully completed and changes are embedded into the subsequent operations, as ‘business as usual’. This is can take several months after a system ‘go-live’. The following section explains the BSC from a middle-out approach to designing score cards. 3. BSC design – the ‘Middle out’ There are cases in literature (Alleman, 2003), where BSC was used as a pure Project Management element, complementing the traditional project management and control mechanism. But the design of BSC was attempted from a top down approach. Goold et al. (1994), describe three types of ‘Parenting Styles’, viz. strategic planning, strategic control and financial control, for the roles and responsibilities between corporate and organisational units. These types of styles also influence the role the corporate would adopt in the design and usage of BSC across corporate and business units (De Waal, 2007). Usually for large programs, we can adopt a method that has parallel to ‘strategic control’ style, wherein the corporate (the Program Vision, in this case) would influence the design of scorecard, but it would be the Business Benefits Plan that would influence the usage of it. When a program gets sanctioned, the program sponsor, steering committee, business stakeholders and the program and project managers go through the Benefits Management steps (Identify, Analyse, Plan) to develop a Straw Model, Metrics and their BSC relationships and thus, a first cut BSC for the program, much akin to a Corporate BSC is arrived at. In this approach, the program core team would work out multiple iterations, to arrive at individual scorecards across the individual projects (re-using many prevailing project measures) and connecting them to the Program BSC, to arrive at a consensus that is aligned with the proposed Benefits metrics. One would be able to retain many measures that can be used at individual project teams’ level, while choosing the ones that would get ‘aggregated’ at program level Benefits scorecard. Thus, program Benefits Realization expectations (metrics) were typically ‘cascaded’ downwards as BSC measures (from Program Benefits BSC to Projects Teams’ Delivery – Benefits BSC), while re-using typical project delivery measures for ‘aggregating’ upwards. 3.1.Characteristics of BSC design – the ‘Middle out’ The design process is typically recursive at each time when a new project team is added to the program portfolio and / or when the Program Benefits or Business case is changed due to
  • 6. unexpected events; and that the participating project team contributes to the BSC Benefits BSC design more, by way of carrying forward their set of existing measures. Thus we would prefer to call the design approach the ‘Middle-out’, compared to top down mode of designing scorecards. The following steps would describe the process of this design approach: 1. Start-up / or from a previous steady state phase: Existing islands of projects in the Program portfolio, (with Identified & Analysed Benefits, independent Service Level Agreements (SLA), Key Performance Indicators (KPI) and measures) focus on their operational efficiency, project management and control, besides monitoring for Risk management and Benefits Management. 2. Coalescence phase: When a new program is sanctioned, driven by the program vision and goals, coalescence comes into play. The steps in this phase are - 1. Select pilot projects that have similar and comparable SLAs and KPIs and Delivery Benefits metrics. 2. Derive ‘tactical themes’ as opposed to Corporate Strategic Themes. (The example is – Project Delivery Benefits as opposed to Program Vision BSC). 3. Develop Strategy Map and the Benefits Straw Map from the new Delivery Benefits goals and the identified program benefits to derive the new set of Benefits measures. 4. Assign targets with tolerance ranges (Green / Amber / Red) for the finalized measures that would drive the projects’ and program goals to fruition. 5. Analyse new risk/impediments profiles and mitigation plans. 6. Derive the new governance model, Benefits Straw Model and Metrics; get approval for the same. 3. Communication Phase: Publish the Program performance and Benefits Scorecard to stakeholders and draw up communication and change management plans. (Town hall meetings, Training, Kiosks for Demonstrations, etc. as required). 4. Implementation Phase: Go Live and monitor. (Closure / start steady state phase) 5. Iterate from ‘Coalescence’, when new projects join. The following figure (Fig. 2) depicts the design elements.
  • 7. Fig 2: Strategy Maps for BSC Design Middle-Out We can compare the traditional Balanced Scorecard approach (the first generation) with the middle-out approach in the following way (Table 1). BSC Top Down BSC Middle-Out Starts at Organizational top; Corporate Vision driven SLAs / KPI Focus on Customer – Vendor Relationship, Portfolio / Program Objectives; Benefits driven SLAs Long Term planned (3-5 years) Short Term focused (1-2 years) Start from Financial goals (Perspective) and derive other Perspectives. Identify Strategic Initiatives (as relevant). Start from Customer Expectations on Portfolio & program Benefits and distribute Delivery metrics and SLAs across relevant BSC Perspectives Usually top-down approach to BSC ‘Middle-out’ design’; iterative process of top-down (from Portfolio Benefits and
  • 8. design SLAs) and bottom-up, where the quantum of contribution is more from Projects’ level (Delivery Benefits and operational parameters for arriving at measures and targets). Strategy Maps are enablers for BSC design; they validate the Strategic Themes. Strategy Maps and Benefits Straw maps drive the design. Changes to Dash board measures are generally minimal at Corporate level BSC. Flexible to changes to measures or their targets both at Projects’ level and at ‘Internal Processes’ Perspective of individual Scorecards. Table 1: Comparison of BSC Design approaches Thus, the Program Benefits Scorecard can evolve from the relationship to individual projects’ level BSCs easily. Also, the scorecard structure (parent – children scorecards) can be extended to more projects / changed Business Cases, at different ‘coalescence’ phases, as the maturity of Benefits Management in the program organization grows. 3.2.Performance Index For the purpose of monitoring performance, as well for the purpose of rewards recognition, the individual measures can be given ‘weights’ (though, during the time of piloting, the weights can be set to a value of 1) and their performance deviation can be measured at regular intervals. The individual measures’ performance values can then aggregated for specific BSC (4) perspectives, as well as at individual scorecard levels. Thus we would have various ‘weighted performance of measures’, which are called Performance Indices (PI) on the scorecards. This idea can help the program in a significant way, by comparing PIs across various perspectives, across scorecards as well as across individual teams. Thus Benefits Realization can be monitored through a set of ‘lead’ and ‘lag’ measures across various projects that make up the program, while PIs can also help in identifying the cause-and- effect’ hypotheses. 4. Recommendation for BSC Implementation The launch preparation phase would typically last about 4 weeks, when internal marketing campaign should be conducted. The project teams, project and program manager(s), and the
  • 9. program core team would then freeze the scorecard elements (that include the benefits’ measures, negotiated targets and their target deviation zones) and address the program roadblocks and issues. The key elements for scripting a success story of Program Benefits BSC implementation are the town hall meetings with individual teams and stakeholders, content-rich collaterals for internal marketing purposes and self-running demonstration kits from the program portal for the user groups. In the final mode of governance, we should superpose the new Benefits BSC based program review, while retaining the existing delivery performance review mechanisms at the Program / Project level, wherever required. This would help the program to track important program specific benefits’ measures, while facilitating the need-driven data drill down at individual projects’ level. Also more importantly, the adoption of BSC dashboard would facilitate better corporate communication on business, program and project specific audiences, while parallel tracking the Benefits metrics for their performance. 5. Some closing thoughts Our focus in this paper has been that BSC dashboard will be the link in corporate communication amongst business, IT-program and IT-project teams that have both delivery based and benefits based BSC metrics, given the importance of tracking the program goals through their benefits. Given below (Fig. 3) is an example of Program BSC (for the sake of confidentiality, we have masked the actual numbers; data points from April-09 onwards were re-constructed for display).
  • 10. Fig 3: BSC Program scorecard *** Sr # Performance Measure Unit KPI Target Frequency Apr '09 Trend May '09 Trend Jun '09 Trend Finance 1 TCO Savings (Direct / Indirect) $ N Half yearly 2 Sprint Burnup rate $ Y Monthly Customer 0.80 0.80 0.80 3 Customer Satisfaction Index (Overall) % Y 90% Half yearly 84% 84% 84% 4 CSI - Most important parameters rated low % Y 10% Half yearly 50% 11% 11% 5 CSI - Most important Service & Business Goals parameters rated high % Y 80% Half yearly 86% 86% 86% 6 Customer Appreciations # N Monthly 8 9 6 7 Customer Complaints # N Monthly 0 0 3 8 Quality of Service (from annual survey) # N Yearly Process & Delivery 0.54 0.54 0.66 9 Post Delivery Defects # Y 5 Monthly 2 4 4 10 Sprint review Meeting attendance % Y 100% Monthly 100 100 90 11 Monthly Governance % Y 100% Monthly 33% 67% 60% 12 Velocity (per Sprint) (Total) # Y 15 Monthly 14 14 14 13 Velocity (per Sprint) (per Scrum team) # Y 3 Monthly 3 3 3 14 Burn down deviation (per Sprint) % Y 5% Monthly 8.0% 8.0% 9.0% 15 SLA compliance to response time (Resources SLA) % Y 95% Monthly 99.7% 99.6% 99.4% 16 SLA compliance to resolution time (Resources SLA) % Y 95% Monthly 97.0% 96.6% 96.7% Learning, People & Competency 0.40 0.90 0.90 17 Compliance to minimum competency level % Y 100% Monthly 80% 80% 80% 18 Unplanned Attrition in critical phases # Y 0 Monthly 1 0 0 19 Upload activity of assets into KM system # N Monthly 0 0 0 20 Reference activity of assets in KM system # N Monthly 0 0 0 Portfolio Performance Index 0.58 0.58 0.72 0
  • 11. References 2GC (2009), “Performance Management & 3 rd Generation Balanced Scorecard”, 2GC Active Management, <www.2gc.co.uk>, (Accessed 02/01/2010). Advanced Development Methods, (2003), “Scrum Methodology: Incremental, Iterative Software Development from Agile processes”, <www.controlchaos.com> (Accessed 02/01/2010). Alleman, G.B. (2003), “Using Balanced Scorecard to Build a Project Focused IT Organization”, in Proceedings of Balanced Scorecard Conference, San Francisco. De Waal, A. (2007), “Strategic Performance Management: A managerial and behavioural approach”, Palgrave Macmillan, New York. Goold, M., Campbell, A. and Alexander, M., (1994), “Corporate Level Strategy: Creating value in the multibusiness company”, Wiley, New York. Kaplan, R.S. and Norton, D.P. (1992), “The balanced scorecard: measures that drive performance”, Harvard Business Review, January-February 1992, pp. 71-80. Kaplan, R.S. and Norton, D.P. (1993), “Putting the Balanced Scorecard to Work”, Harvard Business Review, September – October, 2-16. Kaplan, R.S. and Norton, D.P. (2000), “The Strategy-Focused Organization: How balanced scorecard companies thrive in the new business environment”, Harvard Business School Press, Boston, Massachusetts. Sliger, M. (2007), “A Project Manager’s Survival Guide to Going Agile”, Rally Software Development Corp. < www.rallydev.com > (Accessed 02/01/2010). ================================end of text==============================