Budget
Planning
Aleksandra Branković
Andrija Pejović
All presentations are available on the PPF5 website: www.ppf5.rs
14 February 2014
Hierarchy of Strategic Documents
Enlargement Package

(EU Enlargement Strategy, EC Progress Report /SAA/ European Partnership)

IPA II Regulation / Rules of Application
Country /Multi-Country Strategy Paper

National Sector Programme or (IPA-specific)
Sector Planning Document -SPD)
Action Documents (ADs)

Annexed: SPDs

(Draft) Action Programme (AP)
Financing Proposal
Commission
Implementing Decision
Project funded by
The European Union

Annexed: ADs
Annexed: AP

Financing Agreement

Government of the Republic
of Serbia
European Integration Office
Sector Planning Document
SPD Template

Purpose

Section 1: Sector
Description

To systematically address the EC criteria for Sector Approach and
show that the sector in question is sufficiently mature to adopt a
Sector Approach. Also the steps being undertaken to increase
sector maturity.
1.4 Mid-term perspectives on national budget and development
assitance

Section 2: Sector
Programme
Rationale

To provide justification for the proposed programme to explain
the focus of IPA assistance within the whole scope of the sector
An overall picture of the problems to be solved with the support
of IPA funded sector support.

Section 3: Sector
Programme
Description

To describe in detail the proposed programme covering: overall
/specific objectives; impact indicators; results; measures &
operations; institutional arrangements for implementation.

Section 4:
Budget

To provide an indicative 3-year sector budget based on all
sources

Section 5:
Annexes
Log Frame
Project funded by
Institutional
The European Union

To provide inputs for the associated Action Documents
Government of the Republic
of Serbia
European Integration Office
Section 4 Sector Support Programme
Budget
SOURCES OF FUNDING
TOTAL
EXPENDIT
URE

SECTOR TITLE

I
B
(
1
)

IN
V
(1
)

EUR
(a)=(b)+(
e)

TOTAL
PUBLIC
EXPENDIT
URE
EUR
(b)=(c)+(
d)

IPA
CONTRIBUTIO
N
EUR
(c)

%
(2)

NATIONAL PUBLIC CONTRIBUTION
Total EUR
(d)=(x)+
(y)+(z)

% Cent
ral
(
EUR
2
(x)
)

Regional/
Local
EUR
(y)

IFIs
EUR
(z)

PRIVATE
CONTRIBU
TION
EUR
(e)

%
(
3
)

Priority 1
Measure
1.1.
Operation
1.1.1.
….
Priority 2
Measure
2.1
Operation
2.1.1.
….
TOTAL IB
TOTAL INV
TOTAL SSP
Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Section 4 Sector Support Programme
Budget
• Similar to IPA I, budget template for Sector fiche
• Standard approach to preparation of budget
• Dismantle Measures and Operations to Contracts
• Preparing Section 4 and „Annex 3: Indicative
Implementation Schedule‟ in parallel

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Exercise for today’s session
Competitiveness Sector Planning Document
(DRAFT!)

 Specific objective 3: The implementation of the
EU-harmonised policies to create a well functioning
market economy improved
Measure 3.1: Improving the policy,
regulatory and institutional framework and
implementation capacities of economic
operators
Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Keep in mind the following:
• PRAG rules/types of contracts
• Co-financing requirements

• N+ rules
• Linkages with national budget planning process

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Indicative determination of contract
value
Three approaches
• Bottom up
• Top down
• Mixed
Sectoral and priority allocation predefined?

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
How to determine value
Service Contract
• The budget includes expert fees (which
includes the margin or profit for the
consulting
• company) which are calculated in relation to
type and number of experts (see table).
• Maximum duration of such project is two
years (sometimes three).

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
How to determine value
Expert fees

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
How to determine value
Other costs:
Incidental expenditure (between 2 & 5, sometimes 10% of
budget):
• Bank charges
• Per diems for experts working outside project base of
operations (e.g. Belgrade)
• Visibility events, translation etc.
• Verification (e.g. around 2% of budget for external auditor
fees)

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Types of Contract and Associated Documents

IPA
Action
Document

P
r
o
c
u
r
e
m
e
n
t

SERVICES

SUPPLIES

Technical
Specifications

WORKS

Bills of
Quantity

GRANTS

Project funded by
The European Union

Terms of
Reference

Guidelines for
Applicants
Government of the Republic
of Serbia
European Integration Office
Service contract-Budget planning-fee
based

First payment:

• for projects up to 12 months: 40%
• for projects between 12 and 24 months: 30%
• for 24 months projects or longer: 20%

Payments during project implementation:
• every 6 months in equal amounts.
Final payment: 10%
Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Service contract-Budget planning-Global
price

• First payment : 60%

• Payments during project implementation: no payments
in most cases, but it depend on the project. If there
are payments: 10% every 6 months.

• Final payment: 40%.

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Service contract-Budget planning-Global
price

• First payment : 60%

• Payments during project implementation: no payments
in most cases, but it depend on the project. If there
are payments: 10% every 6 months.

• Final payment: 40%.

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Supply contract-Budget planning
• First payment : 60%
• Payments during project implementation: in
most of the cases there are no payments.

• Final payment: 40%

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Works contract-Budget planning
• First payment: 10%
• Payments during project implementation:
every month in equal amounts

• Final payment: 10%

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Twinning-Budget planning
• First payment: 20%
• Payments during project implementation:
instalment every three months

• Final payment: 5%

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Grant-Budget planning
First payment: 80%
Payments during project implementation: 0 if
project lasts for 1 year; if project lasts for more
than 1 year additional 10% can be added to
pre-financing later on during project
mplementation. It can be a single payment or
10% can be split up into 5+5% depending on
the project duration.
Final payment: 20% if project lasts for 1 year;
could be 10% if project lasts for
longer than 1 year
Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Exercise• Table 1-Operation
Budget
• Table 2-SPD Section 4
• Table 3-Disbursement
Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
EU co-financing framework
National co-financing framework

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Outline of IPA RAP
• IPA RAP not adopted yet
Financial management
a. Eligibility of expenditure; as regards
specificity of the policy areas, specific provision
may be foreseen in the Financing Agreements.
b. The co-financing concept in principle to be
maintained. Specific criteria to modulate the cofinancing rate set in the IPA Common Strategic
Framework. (to be developed)
Detailed level of the EU contribution laid down
in the respective Financing Agreements.
Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Outline of IPA RAP
Aid intensity and rate of IPA assistance
1. The Commission decision adopting a cooperation programme
shall fix the co-financing rate and the maximum amount of
IPA assistance, based either on:
a) total eligible expenditure, including public and private
expenditure; or
b) public eligible expenditure.
2. The co-financing rate at the level of each [priority axis] shall
not be less than [20 %] and not higher than [85 %] of the
eligible expenditure of a cooperation programme.

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
OLD IPA IR Co-financing requirements
Institution building activities: require a degree of co-financing
by the final beneficiary and/or public funds. Exceptionally and in
dully justified cases, activities may be funded 100% by
Community funds
Administrative co-operation (twinning and TAIEX type of
activities) may be funded 100% by Community funds. If
twinning is involved, clearly state the expected co-financing
budget of the twinning contract. To note that contributions in
kind are not eligible.
Grants: the final beneficiaries may be required to contribute to
the operation‟s eligible costs. In general, final beneficiaries must
contribute a minimum of 10 percent of the project, both for
investment and institution building projects.

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
National framework for co-financing
Budget System Law
Preparation of budgets and financial plans
Article 28
4) Overview of the expected funds from the financial assistance
of the European Union;

5) Estimation of the necessary financial resources to fund the
participation of the Republic of Serbia in implementing of the
financial assistance of the European Union;

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
National framework for co-financing

Budget System Law (Article 68a)
• Budget users are responsible for proper
planning in accordance with agreement
between RS and EU, in the proper
planning of the amount of expenditure
• Budget user who do not funds sufficient
funds for co-financing must redirect
funds form their other budget lines

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Budget system Law-Calendar

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Guidelines for preparation of the Budget
• Co-financing can be provided from public
funds (by definition EU public funds are funds
of budgets, own source revenues , loans
granted to the state) or grants from
international institutions.
• Time frame of planning and implementation of
activities that are co-financed by national
funds under projects financed by EU funds

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Time frame
It is necessary to respect the following rules :

• Activities that are co-financed under the project/sectoral
program defines in project proposals/sectoral programs which
make annual National program;
• The funds for co-financing of projects/sectoral program must
be planned in within the allowable budget limits for every
budget users;
• Bearing in mind that the implementation of the annual IPA
perennial and can not coincides with the national budget year ,
it is the projection plan funds to finance activities that are cofinanced;

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Time frame
• Activities that are considered as co-financing must begin with
the realization after the signature of the Financing Agreement.
Otherwise, the funds which are financed these activities will not
be recognized as part of the co-financing;
• National co-financing should be planned taking into account
the dynamics of implementation of project/program activities.
• When planning the dynamics of negotiation, ie . Payment of
those activities co-financed by public funds, or in predicting the
resources that are need for co-financing the activities of the
project /sectoral program should be take into account the order
of activities listed in the project or in the sectoral program;

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Time frame
• Contracts for the implementation of all project/sectoral
program must be concluded within two or three years from
the date of signature of the Financing agreements depending
on which service is provided specific financial Agreement
within two years after the conclusion of individual contractscontractual obligations to be performed, and the payment of
funds for their implementation is must be completed no later
than one year from the last day set for the execution
particular contract, unless otherwise specified in the
Financing Agreement;
• EC must be aware of implementation of part of the
project/program activities, are co-financed from national
resources;

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Exercise• Table 4-Instructions for
projects financed from
EU funds (IPA)

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
N+ Rules
OPTION 2
Combined annual Programme
(max. 3 years)
PROGRAMME ARCHITECTURE

OPTION 1
Annual Programme

OPTION 3
Multiannual Programme with split
commitments (max. 7 years)

Financing Decision (FD)

Financing Decision covering an
allocation for one year.

Financing Decision covering an
allocation for up to three years with
suspension clause.

Financing Decision covering an
allocation for an initial (maximum)
three years with suspension clause.
Amendment of Financing Decision to
add allocations for consecutive years'
budget allocation at least twice.
Possibly: Commission Decisions for
selection of certain infrastructure
projects (major projects) per year.

Action Programme
(Annex to FD)

Action Programme covering Actions
programmed for one year or Action
Programme covering Actions
programmed for more than one year
and broken down into annual
priorities (=selected Actions).

Action Programme covering Actions
programmed for three or more years
and broken down into priorities for a
maximum of three years.
For these priorities (selected
Actions), it must be clearly identified
whether they are financed from year
N, N+1 or N+2.

Action Programme covering Actions
programmed for up to seven years
without earmarking of Actions by
year.

Budgetary commitment

One budgetary commitment in year
N.

Annual budgetary commitments in N,
N+1 and N+2 (three).

The budgetary commitment is broken
down into seven instalments, one for
each year (through amendments to
original commitment).

Financing Agreement
Project funded by
The European Union

One Financing Agreement.

Financing Agreements to be
concluded for each year or two
amendments to original Financing
Agreement.

Financing Agreements to be signed
covering allocations as specified in
the Financing Decision (maximum
initial allocation of three years) with
suspension clause.
Amendments to Financing Agreement
Government of the Republic
to add allocations for consecutive
of Serbia
years' budget allocation at least
European Integration Office
N+ Rules
Relevant legal framework

Article 189(2) FR
Article 2 CIR

Article 189(2) FR
Article 6(3) CIR

Article 189(3) FR
Article 16 IPA RAP
Article 6(3) CIR

Possible methods of
implementation

Direct and Indirect

Direct and Indirect

Only Indirect

IMPLEMENTATION TIMELINE

Deadline for conclusion of
Financing Agreement

Deadline for conclusion of
procurement contracts and grant
agreements

Deadline for operational
implementation

Deadline for automatic
de-commitment
Project funded by
The European Union

N+1

d+3 from conclusion of Financing
Agreement
“d” the date of conclusion of the
Financing Agreement.

6 years from conclusion of Financing
Agreement

None

N+1 counted from the year of
creation of each yearly commitment

None

d+3 from conclusion of each
Financing Agreement

None

6 years from conclusion of each
Financing Agreement

None

None

Each yearly split commitment
must be spent within five years of its
validation (N+5).
The last split commitment (2020)
Government of the Republic
must be spent within six years of its
of Serbia
validation (N+6). Integration Office
European
Sector Budget
There needs to be a clear link between sector policy & budgeting.
Sector plans should be properly priced & prioritized within a
realistic estimate of the resources available from the national budget
& external donors.
IPA II Sector Support Programmes are planned to be multi-annual
& should be co-financed by predictable, multi-annual national
funding.
It is necessary to provide a brief description of the sector budget
on an annual, & if possible, on a medium-term perspective (3-5
years). Ideally there should be a Medium Term Expenditure
Framework (MTEF) for the sector.
However, development of MTEFs will be gradual, at first
assessments should focus on the existence of credible annual sector
budgets. At minimum, it is crucial to verify whether the sector
budget can be identified in the state budget.

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Path towards Fully-fledged Sector
Support
• Can the sector budget be easily identified in the state
budget?
• What is the nature and scope of the sector budget?
• Does the budget fairly reflect the sector policies and
objectives?
• What type of budget classification system is in use?
• What is the overall level of sector financing?
• Is the share the sector within total government
expenditures increasing?

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Path towards Fully-fledged Sector
Support-MTEF

• If a sector MTEF is in place, key
assessment questions include:
• Is it consistent with declared policies and the national
budget/overall MTEF of the country?
• Is it approved at a political level or is it largely a
technical document?
• If a sector MTEF is foreseen by the government how
can its elaboration be supported by means of the
Sector Support Programme?

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Path towards Fully-fledged Sector
Support-MTEF

• If a sector MTEF is in place, key
assessment questions include:
• Is it consistent with declared policies and the national
budget/overall MTEF of the country?
• Is it approved at a political level or is it largely a
technical document?
• If a sector MTEF is foreseen by the government how
can its elaboration be supported by means of the
Sector Support Programme?

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Path towards Fully-fledged Sector
Support-MTEF
• If a sector MTEF is in place, key assessment
questions include:
•

•
•
•

If an MTEF is already in preparation, has a coherent and broad sector
development plan with appropriate financing framework at sector and
national level been defined/decided at a political level and is it
considered feasible and is it consistent with national/overall MTEF?
If a Sector MTEF is not in place, are appropriate sector allocations
secured and properly stated in the general budget?
Is there an on-going process leading to the setting up of Sector
MTEF?
Based on the analysis, recommendations should be made to the
Government.

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Programatic budgeting
Differences between program and line budget:
Showing:
1. that the purpose of money is spent;
2. how such consumption is linked to strategic
objectives, and
3. what results should be achieved

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Advantages of programme budget
• Provides a single framework for prioritization
of expenditures;
• Improves policy coordination at the
government level, which is crucial for
achieving the national, social and economic
objectives;
• Provides financial context of strategic and
operational plans for budget users;

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Advantages of programme budget
• Allows the government and local authorities
to identify inefficient spending, as well as
areas that do not provide adequate results
and that require more resources;
• Contributes to the improvement of public
administration services through the
evaluation of the relationship of their price
and quality;
• Makes budget more transparent and
understandable for citizens

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Programme budget
• The introduction of program budgeting is of
major importance for the improvement of
public finance, as it enables continuous multiyear financing of priority policies, programs
and projects.
•
•
•

By the end of 2013 a comprehensive preparation of institutions has
been conducted for the introduction of program budgeting.
By the end of 2013, fourteen (14) Serbian intuitions have adopted
program based budget, including SEIO.
During 2014, the preparation of institutions for the introduction of
program budgeting will continue, as it is planned for the 2015
budget year according to the Budget System Law.

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Mid-Term Expenditure Frameworks
(MTEF)
• Mid-Term Expenditure Frameworks (MTEFs) are part of the
existing Fiscal Strategy. They are determined at the level of
budget users and cannot directly be transformed into sector
MTEFs.
• Recently adopted legislation requires the merging of strategic
planning of public policies with the budget process within the
government and the parliament. This will include mandatory
three-year budget planning and the introduction of
programme budgeting by 2015.
• It is planned that MTEFs for sectors will be developed
alongside programme budgeting. For this to be feasible it will
be necessary to ensure correspondence between the budget
programmes and the NAD sectors.

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Strategic Planning and Coordination of Public
Policies
• The guidelines for drafting the strategic documents
were provided in the form of recommendations, and the
uniform information system was introduced for the
collection of data required for the government work
program.
• Draft Methodology for Integrated Strategic Planning
was prepared, and this draft is to be adopted.
• Still, upgrading of strategic planning and coordination
of public policies within the Government should be
considered the priority task in the forthcoming public
administration reform process.

Project funded by
The European Union

Government of the Republic
of Serbia
European Integration Office
Project funded by
The European Union

Government of the Republic of Serbia
European Integration Office

Thank you for your
attention
All presentations are available on the PPF5 website: www.ppf5.rs

More Related Content

What's hot

6_Link LFA to Full application
6_Link LFA to Full application6_Link LFA to Full application
6_Link LFA to Full applicationcsdialogue
 
1_Introduction to Full Application preparation
1_Introduction to Full Application preparation1_Introduction to Full Application preparation
1_Introduction to Full Application preparationcsdialogue
 
Искра Михайлова eng (1)
Искра Михайлова  eng (1)Искра Михайлова  eng (1)
Искра Михайлова eng (1)Emil Hristov
 
The French LoLF - Guy Cazenave-Lacroutz, France
The French LoLF - Guy Cazenave-Lacroutz, FranceThe French LoLF - Guy Cazenave-Lacroutz, France
The French LoLF - Guy Cazenave-Lacroutz, FranceOECD Governance
 
4_Activity schedule and budget
4_Activity schedule and budget4_Activity schedule and budget
4_Activity schedule and budgetcsdialogue
 
Synergies between ESIF funds, Horizon 2020 and other research programmes
Synergies between ESIF funds, Horizon 2020 and other research programmesSynergies between ESIF funds, Horizon 2020 and other research programmes
Synergies between ESIF funds, Horizon 2020 and other research programmesParma Couture
 
Restructuring public spending for efficiency - Martin KELLENERS, Germany
Restructuring public spending for efficiency - Martin KELLENERS, GermanyRestructuring public spending for efficiency - Martin KELLENERS, Germany
Restructuring public spending for efficiency - Martin KELLENERS, GermanyOECD Governance
 
Klaudija Lutovska- IPA CBC & IPARD 2
Klaudija Lutovska- IPA CBC & IPARD 2Klaudija Lutovska- IPA CBC & IPARD 2
Klaudija Lutovska- IPA CBC & IPARD 2Klaudija Lutovska
 
9 10.15am Challenges In Implementing A Performance Framework (P. Perczynski A...
9 10.15am Challenges In Implementing A Performance Framework (P. Perczynski A...9 10.15am Challenges In Implementing A Performance Framework (P. Perczynski A...
9 10.15am Challenges In Implementing A Performance Framework (P. Perczynski A...icgfmconference
 
Step4all guide 3 How to apply and how to manage successful European projects
Step4all guide 3 How to apply and how to manage successful European projectsStep4all guide 3 How to apply and how to manage successful European projects
Step4all guide 3 How to apply and how to manage successful European projectsGIANLUCA COPPOLA
 
Step4all guide 2 Main programs managed by the European Commission
Step4all guide 2   Main programs managed by the European CommissionStep4all guide 2   Main programs managed by the European Commission
Step4all guide 2 Main programs managed by the European CommissionGIANLUCA COPPOLA
 
Prezentare MLPS Comitet Director din 19 noiembrie 2012
Prezentare MLPS Comitet Director din 19 noiembrie 2012Prezentare MLPS Comitet Director din 19 noiembrie 2012
Prezentare MLPS Comitet Director din 19 noiembrie 2012GIZ Moldova
 
the French LoLF - Véronique Fouque, france - eng
the French LoLF - Véronique Fouque, france - engthe French LoLF - Véronique Fouque, france - eng
the French LoLF - Véronique Fouque, france - engOECD Governance
 

What's hot (20)

Iktimed final presentation Marche Reg.
Iktimed final presentation Marche Reg. Iktimed final presentation Marche Reg.
Iktimed final presentation Marche Reg.
 
8_Visibility
8_Visibility8_Visibility
8_Visibility
 
6_Link LFA to Full application
6_Link LFA to Full application6_Link LFA to Full application
6_Link LFA to Full application
 
1_Introduction to Full Application preparation
1_Introduction to Full Application preparation1_Introduction to Full Application preparation
1_Introduction to Full Application preparation
 
Искра Михайлова eng (1)
Искра Михайлова  eng (1)Искра Михайлова  eng (1)
Искра Михайлова eng (1)
 
The French LoLF - Guy Cazenave-Lacroutz, France
The French LoLF - Guy Cazenave-Lacroutz, FranceThe French LoLF - Guy Cazenave-Lacroutz, France
The French LoLF - Guy Cazenave-Lacroutz, France
 
4_Activity schedule and budget
4_Activity schedule and budget4_Activity schedule and budget
4_Activity schedule and budget
 
Synergies between ESIF funds, Horizon 2020 and other research programmes
Synergies between ESIF funds, Horizon 2020 and other research programmesSynergies between ESIF funds, Horizon 2020 and other research programmes
Synergies between ESIF funds, Horizon 2020 and other research programmes
 
Restructuring public spending for efficiency - Martin KELLENERS, Germany
Restructuring public spending for efficiency - Martin KELLENERS, GermanyRestructuring public spending for efficiency - Martin KELLENERS, Germany
Restructuring public spending for efficiency - Martin KELLENERS, Germany
 
7_Monitoring
7_Monitoring7_Monitoring
7_Monitoring
 
Klaudija Lutovska- IPA CBC & IPARD 2
Klaudija Lutovska- IPA CBC & IPARD 2Klaudija Lutovska- IPA CBC & IPARD 2
Klaudija Lutovska- IPA CBC & IPARD 2
 
9 10.15am Challenges In Implementing A Performance Framework (P. Perczynski A...
9 10.15am Challenges In Implementing A Performance Framework (P. Perczynski A...9 10.15am Challenges In Implementing A Performance Framework (P. Perczynski A...
9 10.15am Challenges In Implementing A Performance Framework (P. Perczynski A...
 
Ec 2005 0431_1_en
Ec 2005 0431_1_enEc 2005 0431_1_en
Ec 2005 0431_1_en
 
Interreg
InterregInterreg
Interreg
 
Step4all guide 3 How to apply and how to manage successful European projects
Step4all guide 3 How to apply and how to manage successful European projectsStep4all guide 3 How to apply and how to manage successful European projects
Step4all guide 3 How to apply and how to manage successful European projects
 
Step4all guide 2 Main programs managed by the European Commission
Step4all guide 2   Main programs managed by the European CommissionStep4all guide 2   Main programs managed by the European Commission
Step4all guide 2 Main programs managed by the European Commission
 
2 ipa overview
2 ipa overview2 ipa overview
2 ipa overview
 
Prezentare MLPS Comitet Director din 19 noiembrie 2012
Prezentare MLPS Comitet Director din 19 noiembrie 2012Prezentare MLPS Comitet Director din 19 noiembrie 2012
Prezentare MLPS Comitet Director din 19 noiembrie 2012
 
the French LoLF - Véronique Fouque, france - eng
the French LoLF - Véronique Fouque, france - engthe French LoLF - Véronique Fouque, france - eng
the French LoLF - Véronique Fouque, france - eng
 
The Interreg V-A Romania-Bulgaria Programme: what's next?
The Interreg V-A Romania-Bulgaria Programme: what's next?The Interreg V-A Romania-Bulgaria Programme: what's next?
The Interreg V-A Romania-Bulgaria Programme: what's next?
 

Viewers also liked

Got Budget Cuts? Maximizing Technology
Got Budget Cuts? Maximizing TechnologyGot Budget Cuts? Maximizing Technology
Got Budget Cuts? Maximizing TechnologyUniversity of Oregon
 
The ideal IT budget: Best Practice vs Reality
The ideal IT budget: Best Practice vs RealityThe ideal IT budget: Best Practice vs Reality
The ideal IT budget: Best Practice vs RealityCRMT Digital
 
Conceptual Estimating Technology helps the Texas Army National Guard Stay in ...
Conceptual Estimating Technology helps the Texas Army National Guard Stay in ...Conceptual Estimating Technology helps the Texas Army National Guard Stay in ...
Conceptual Estimating Technology helps the Texas Army National Guard Stay in ...Beck Technology, Ltd.
 
JISC Content programme 2011 13 progress update
JISC Content programme 2011 13 progress updateJISC Content programme 2011 13 progress update
JISC Content programme 2011 13 progress updatePaolaMarchionni
 
Keynote slides: Platform Strategy Creating Exponential Value in a Connected ...
Keynote slides: Platform Strategy Creating Exponential Value  in a Connected ...Keynote slides: Platform Strategy Creating Exponential Value  in a Connected ...
Keynote slides: Platform Strategy Creating Exponential Value in a Connected ...Ross Dawson
 
MIS 13 Customer Relationship Management
MIS 13 Customer Relationship ManagementMIS 13 Customer Relationship Management
MIS 13 Customer Relationship ManagementTushar B Kute
 
PwC: New IT Platform From Strategy Through Execution
PwC: New IT Platform From Strategy Through ExecutionPwC: New IT Platform From Strategy Through Execution
PwC: New IT Platform From Strategy Through ExecutionCA Technologies
 
Technology Budgeting for SMB
Technology Budgeting for SMBTechnology Budgeting for SMB
Technology Budgeting for SMBthomasmking1
 
Budget and budgetary control
Budget and budgetary controlBudget and budgetary control
Budget and budgetary controlSumitBedi57
 
Budget ppt
Budget pptBudget ppt
Budget pptmbachnak
 

Viewers also liked (15)

Got Budget Cuts? Maximizing Technology
Got Budget Cuts? Maximizing TechnologyGot Budget Cuts? Maximizing Technology
Got Budget Cuts? Maximizing Technology
 
The ideal IT budget: Best Practice vs Reality
The ideal IT budget: Best Practice vs RealityThe ideal IT budget: Best Practice vs Reality
The ideal IT budget: Best Practice vs Reality
 
Conceptual Estimating Technology helps the Texas Army National Guard Stay in ...
Conceptual Estimating Technology helps the Texas Army National Guard Stay in ...Conceptual Estimating Technology helps the Texas Army National Guard Stay in ...
Conceptual Estimating Technology helps the Texas Army National Guard Stay in ...
 
JISC Content programme 2011 13 progress update
JISC Content programme 2011 13 progress updateJISC Content programme 2011 13 progress update
JISC Content programme 2011 13 progress update
 
Keynote slides: Platform Strategy Creating Exponential Value in a Connected ...
Keynote slides: Platform Strategy Creating Exponential Value  in a Connected ...Keynote slides: Platform Strategy Creating Exponential Value  in a Connected ...
Keynote slides: Platform Strategy Creating Exponential Value in a Connected ...
 
MIS 13 Customer Relationship Management
MIS 13 Customer Relationship ManagementMIS 13 Customer Relationship Management
MIS 13 Customer Relationship Management
 
PwC: New IT Platform From Strategy Through Execution
PwC: New IT Platform From Strategy Through ExecutionPwC: New IT Platform From Strategy Through Execution
PwC: New IT Platform From Strategy Through Execution
 
Technology Budgeting for SMB
Technology Budgeting for SMBTechnology Budgeting for SMB
Technology Budgeting for SMB
 
Budgeting
BudgetingBudgeting
Budgeting
 
Budgeting.
Budgeting.Budgeting.
Budgeting.
 
Budget
BudgetBudget
Budget
 
BUDGET PROCESS OF THE PHILIPPINE NATIONAL GOVERNMENT
BUDGET PROCESS OF THE PHILIPPINE NATIONAL GOVERNMENTBUDGET PROCESS OF THE PHILIPPINE NATIONAL GOVERNMENT
BUDGET PROCESS OF THE PHILIPPINE NATIONAL GOVERNMENT
 
Budget and budgetary control
Budget and budgetary controlBudget and budgetary control
Budget and budgetary control
 
Budget ppt
Budget pptBudget ppt
Budget ppt
 
Budgeting ppt
Budgeting pptBudgeting ppt
Budgeting ppt
 

Similar to Budget planning training 14022014

EU budget focused on results initiative - Marco Carnaccini, EC
EU budget focused on results initiative - Marco Carnaccini, ECEU budget focused on results initiative - Marco Carnaccini, EC
EU budget focused on results initiative - Marco Carnaccini, ECOECD Governance
 
Financial management baltic scope final
Financial management baltic scope finalFinancial management baltic scope final
Financial management baltic scope finalLaura Melne
 
Infrastructure & PPPs - Colin Forthun, Norway
Infrastructure & PPPs - Colin Forthun, NorwayInfrastructure & PPPs - Colin Forthun, Norway
Infrastructure & PPPs - Colin Forthun, NorwayOECD Governance
 
Budgeting in Croatia - Ivana JAKIR BAJO, Croatia
Budgeting in Croatia - Ivana JAKIR BAJO, CroatiaBudgeting in Croatia - Ivana JAKIR BAJO, Croatia
Budgeting in Croatia - Ivana JAKIR BAJO, CroatiaOECD Governance
 
EU Budget Czech Republic 2014-2020 update November 2014
EU Budget Czech Republic 2014-2020 update November 2014EU Budget Czech Republic 2014-2020 update November 2014
EU Budget Czech Republic 2014-2020 update November 2014Joost Holleman
 
FP7 project negotiation, management and financial rules
FP7 project  negotiation, management and financial rulesFP7 project  negotiation, management and financial rules
FP7 project negotiation, management and financial rulesEuropa Media Trainings
 
MLPS Presentation for the Steering Committee Session from February 21, 2014
MLPS Presentation for the Steering Committee Session from February 21, 2014MLPS Presentation for the Steering Committee Session from February 21, 2014
MLPS Presentation for the Steering Committee Session from February 21, 2014GIZ Moldova
 
Slope wp9, task 9.1, project reporting by Graphitech
Slope wp9, task 9.1, project reporting by GraphitechSlope wp9, task 9.1, project reporting by Graphitech
Slope wp9, task 9.1, project reporting by GraphitechSLOPE Project
 
Presentation of the Modernization of Local Public Services in the RM Project
Presentation of the Modernization of Local Public Services in the RM ProjectPresentation of the Modernization of Local Public Services in the RM Project
Presentation of the Modernization of Local Public Services in the RM ProjectGIZ Moldova
 
FruitBreedomics KOM 30-03-2011 1 management issues
FruitBreedomics KOM 30-03-2011 1 management issuesFruitBreedomics KOM 30-03-2011 1 management issues
FruitBreedomics KOM 30-03-2011 1 management issuesfruitbreedomics
 
OECD, 10th Meeting of CESEE Senior Budget Officials - Gelardina Prodani, Albania
OECD, 10th Meeting of CESEE Senior Budget Officials - Gelardina Prodani, AlbaniaOECD, 10th Meeting of CESEE Senior Budget Officials - Gelardina Prodani, Albania
OECD, 10th Meeting of CESEE Senior Budget Officials - Gelardina Prodani, AlbaniaOECD Governance
 
EU project management training
EU project management trainingEU project management training
EU project management trainingISAR Ednannia
 
2 davor kunc wbif presentation to undp edited
2 davor kunc wbif presentation to undp   edited2 davor kunc wbif presentation to undp   edited
2 davor kunc wbif presentation to undp editedUNDPhr
 

Similar to Budget planning training 14022014 (20)

EU budget focused on results initiative - Marco Carnaccini, EC
EU budget focused on results initiative - Marco Carnaccini, ECEU budget focused on results initiative - Marco Carnaccini, EC
EU budget focused on results initiative - Marco Carnaccini, EC
 
Financial management baltic scope final
Financial management baltic scope finalFinancial management baltic scope final
Financial management baltic scope final
 
Infrastructure & PPPs - Colin Forthun, Norway
Infrastructure & PPPs - Colin Forthun, NorwayInfrastructure & PPPs - Colin Forthun, Norway
Infrastructure & PPPs - Colin Forthun, Norway
 
Budgeting in Croatia - Ivana JAKIR BAJO, Croatia
Budgeting in Croatia - Ivana JAKIR BAJO, CroatiaBudgeting in Croatia - Ivana JAKIR BAJO, Croatia
Budgeting in Croatia - Ivana JAKIR BAJO, Croatia
 
EU Budget Czech Republic 2014-2020 update November 2014
EU Budget Czech Republic 2014-2020 update November 2014EU Budget Czech Republic 2014-2020 update November 2014
EU Budget Czech Republic 2014-2020 update November 2014
 
FP7 project negotiation, management and financial rules
FP7 project  negotiation, management and financial rulesFP7 project  negotiation, management and financial rules
FP7 project negotiation, management and financial rules
 
MLPS Presentation for the Steering Committee Session from February 21, 2014
MLPS Presentation for the Steering Committee Session from February 21, 2014MLPS Presentation for the Steering Committee Session from February 21, 2014
MLPS Presentation for the Steering Committee Session from February 21, 2014
 
Slope wp9, task 9.1, project reporting by Graphitech
Slope wp9, task 9.1, project reporting by GraphitechSlope wp9, task 9.1, project reporting by Graphitech
Slope wp9, task 9.1, project reporting by Graphitech
 
Presentation of the Modernization of Local Public Services in the RM Project
Presentation of the Modernization of Local Public Services in the RM ProjectPresentation of the Modernization of Local Public Services in the RM Project
Presentation of the Modernization of Local Public Services in the RM Project
 
FruitBreedomics KOM 30-03-2011 1 management issues
FruitBreedomics KOM 30-03-2011 1 management issuesFruitBreedomics KOM 30-03-2011 1 management issues
FruitBreedomics KOM 30-03-2011 1 management issues
 
GBPM_2015-04_Minutes_Milan
GBPM_2015-04_Minutes_MilanGBPM_2015-04_Minutes_Milan
GBPM_2015-04_Minutes_Milan
 
Serbia Presentation, PPO, Svetlana Razic, Serbian Practical Experience in PP ...
Serbia Presentation, PPO, Svetlana Razic, Serbian Practical Experience in PP ...Serbia Presentation, PPO, Svetlana Razic, Serbian Practical Experience in PP ...
Serbia Presentation, PPO, Svetlana Razic, Serbian Practical Experience in PP ...
 
OECD, 10th Meeting of CESEE Senior Budget Officials - Gelardina Prodani, Albania
OECD, 10th Meeting of CESEE Senior Budget Officials - Gelardina Prodani, AlbaniaOECD, 10th Meeting of CESEE Senior Budget Officials - Gelardina Prodani, Albania
OECD, 10th Meeting of CESEE Senior Budget Officials - Gelardina Prodani, Albania
 
1.3 contents and processes
1.3 contents and processes1.3 contents and processes
1.3 contents and processes
 
Presentation, Katja Lautar, joint SIGMA ReSPA PIFC regional conference, Skopj...
Presentation, Katja Lautar, joint SIGMA ReSPA PIFC regional conference, Skopj...Presentation, Katja Lautar, joint SIGMA ReSPA PIFC regional conference, Skopj...
Presentation, Katja Lautar, joint SIGMA ReSPA PIFC regional conference, Skopj...
 
Kick off dalane vgs SIU
Kick off dalane vgs SIUKick off dalane vgs SIU
Kick off dalane vgs SIU
 
Presentation by Sue Baxter, from BIS
Presentation by Sue Baxter, from BISPresentation by Sue Baxter, from BIS
Presentation by Sue Baxter, from BIS
 
EU project management training
EU project management trainingEU project management training
EU project management training
 
9 fundraising mapping bokal
9 fundraising mapping bokal9 fundraising mapping bokal
9 fundraising mapping bokal
 
2 davor kunc wbif presentation to undp edited
2 davor kunc wbif presentation to undp   edited2 davor kunc wbif presentation to undp   edited
2 davor kunc wbif presentation to undp edited
 

Recently uploaded

Planetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifePlanetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifeBhavana Pujan Kendra
 
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...SOFTTECHHUB
 
Send Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSendBig4
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...ssuserf63bd7
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers referencessuser2c065e
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxGo for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxRakhi Bazaar
 
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...Hector Del Castillo, CPM, CPMM
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsKnowledgeSeed
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesDoe Paoro
 
NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingrajputmeenakshi733
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...Operational Excellence Consulting
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreNZSG
 
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryEffective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryWhittensFineJewelry1
 

Recently uploaded (20)

Planetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifePlanetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in Life
 
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
 
Send Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.com
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers reference
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxGo for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
 
WAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdfWAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdf
 
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applications
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic Experiences
 
NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors Data
 
digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketing
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource Centre
 
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryEffective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
 

Budget planning training 14022014

  • 1. Project funded by The European Union Government of the Republic of Serbia European Integration Office Budget Planning Aleksandra Branković Andrija Pejović All presentations are available on the PPF5 website: www.ppf5.rs 14 February 2014
  • 2. Hierarchy of Strategic Documents Enlargement Package (EU Enlargement Strategy, EC Progress Report /SAA/ European Partnership) IPA II Regulation / Rules of Application Country /Multi-Country Strategy Paper National Sector Programme or (IPA-specific) Sector Planning Document -SPD) Action Documents (ADs) Annexed: SPDs (Draft) Action Programme (AP) Financing Proposal Commission Implementing Decision Project funded by The European Union Annexed: ADs Annexed: AP Financing Agreement Government of the Republic of Serbia European Integration Office
  • 3. Sector Planning Document SPD Template Purpose Section 1: Sector Description To systematically address the EC criteria for Sector Approach and show that the sector in question is sufficiently mature to adopt a Sector Approach. Also the steps being undertaken to increase sector maturity. 1.4 Mid-term perspectives on national budget and development assitance Section 2: Sector Programme Rationale To provide justification for the proposed programme to explain the focus of IPA assistance within the whole scope of the sector An overall picture of the problems to be solved with the support of IPA funded sector support. Section 3: Sector Programme Description To describe in detail the proposed programme covering: overall /specific objectives; impact indicators; results; measures & operations; institutional arrangements for implementation. Section 4: Budget To provide an indicative 3-year sector budget based on all sources Section 5: Annexes Log Frame Project funded by Institutional The European Union To provide inputs for the associated Action Documents Government of the Republic of Serbia European Integration Office
  • 4. Section 4 Sector Support Programme Budget SOURCES OF FUNDING TOTAL EXPENDIT URE SECTOR TITLE I B ( 1 ) IN V (1 ) EUR (a)=(b)+( e) TOTAL PUBLIC EXPENDIT URE EUR (b)=(c)+( d) IPA CONTRIBUTIO N EUR (c) % (2) NATIONAL PUBLIC CONTRIBUTION Total EUR (d)=(x)+ (y)+(z) % Cent ral ( EUR 2 (x) ) Regional/ Local EUR (y) IFIs EUR (z) PRIVATE CONTRIBU TION EUR (e) % ( 3 ) Priority 1 Measure 1.1. Operation 1.1.1. …. Priority 2 Measure 2.1 Operation 2.1.1. …. TOTAL IB TOTAL INV TOTAL SSP Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 5. Section 4 Sector Support Programme Budget • Similar to IPA I, budget template for Sector fiche • Standard approach to preparation of budget • Dismantle Measures and Operations to Contracts • Preparing Section 4 and „Annex 3: Indicative Implementation Schedule‟ in parallel Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 6. Exercise for today’s session Competitiveness Sector Planning Document (DRAFT!)  Specific objective 3: The implementation of the EU-harmonised policies to create a well functioning market economy improved Measure 3.1: Improving the policy, regulatory and institutional framework and implementation capacities of economic operators Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 7. Keep in mind the following: • PRAG rules/types of contracts • Co-financing requirements • N+ rules • Linkages with national budget planning process Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 8. Indicative determination of contract value Three approaches • Bottom up • Top down • Mixed Sectoral and priority allocation predefined? Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 9. How to determine value Service Contract • The budget includes expert fees (which includes the margin or profit for the consulting • company) which are calculated in relation to type and number of experts (see table). • Maximum duration of such project is two years (sometimes three). Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 10. How to determine value Expert fees Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 11. How to determine value Other costs: Incidental expenditure (between 2 & 5, sometimes 10% of budget): • Bank charges • Per diems for experts working outside project base of operations (e.g. Belgrade) • Visibility events, translation etc. • Verification (e.g. around 2% of budget for external auditor fees) Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 12. Types of Contract and Associated Documents IPA Action Document P r o c u r e m e n t SERVICES SUPPLIES Technical Specifications WORKS Bills of Quantity GRANTS Project funded by The European Union Terms of Reference Guidelines for Applicants Government of the Republic of Serbia European Integration Office
  • 13. Service contract-Budget planning-fee based First payment: • for projects up to 12 months: 40% • for projects between 12 and 24 months: 30% • for 24 months projects or longer: 20% Payments during project implementation: • every 6 months in equal amounts. Final payment: 10% Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 14. Service contract-Budget planning-Global price • First payment : 60% • Payments during project implementation: no payments in most cases, but it depend on the project. If there are payments: 10% every 6 months. • Final payment: 40%. Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 15. Service contract-Budget planning-Global price • First payment : 60% • Payments during project implementation: no payments in most cases, but it depend on the project. If there are payments: 10% every 6 months. • Final payment: 40%. Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 16. Supply contract-Budget planning • First payment : 60% • Payments during project implementation: in most of the cases there are no payments. • Final payment: 40% Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 17. Works contract-Budget planning • First payment: 10% • Payments during project implementation: every month in equal amounts • Final payment: 10% Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 18. Twinning-Budget planning • First payment: 20% • Payments during project implementation: instalment every three months • Final payment: 5% Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 19. Grant-Budget planning First payment: 80% Payments during project implementation: 0 if project lasts for 1 year; if project lasts for more than 1 year additional 10% can be added to pre-financing later on during project mplementation. It can be a single payment or 10% can be split up into 5+5% depending on the project duration. Final payment: 20% if project lasts for 1 year; could be 10% if project lasts for longer than 1 year Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 20. Exercise• Table 1-Operation Budget • Table 2-SPD Section 4 • Table 3-Disbursement Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 21. EU co-financing framework National co-financing framework Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 22. Outline of IPA RAP • IPA RAP not adopted yet Financial management a. Eligibility of expenditure; as regards specificity of the policy areas, specific provision may be foreseen in the Financing Agreements. b. The co-financing concept in principle to be maintained. Specific criteria to modulate the cofinancing rate set in the IPA Common Strategic Framework. (to be developed) Detailed level of the EU contribution laid down in the respective Financing Agreements. Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 23. Outline of IPA RAP Aid intensity and rate of IPA assistance 1. The Commission decision adopting a cooperation programme shall fix the co-financing rate and the maximum amount of IPA assistance, based either on: a) total eligible expenditure, including public and private expenditure; or b) public eligible expenditure. 2. The co-financing rate at the level of each [priority axis] shall not be less than [20 %] and not higher than [85 %] of the eligible expenditure of a cooperation programme. Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 24. OLD IPA IR Co-financing requirements Institution building activities: require a degree of co-financing by the final beneficiary and/or public funds. Exceptionally and in dully justified cases, activities may be funded 100% by Community funds Administrative co-operation (twinning and TAIEX type of activities) may be funded 100% by Community funds. If twinning is involved, clearly state the expected co-financing budget of the twinning contract. To note that contributions in kind are not eligible. Grants: the final beneficiaries may be required to contribute to the operation‟s eligible costs. In general, final beneficiaries must contribute a minimum of 10 percent of the project, both for investment and institution building projects. Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 25. National framework for co-financing Budget System Law Preparation of budgets and financial plans Article 28 4) Overview of the expected funds from the financial assistance of the European Union; 5) Estimation of the necessary financial resources to fund the participation of the Republic of Serbia in implementing of the financial assistance of the European Union; Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 26. National framework for co-financing Budget System Law (Article 68a) • Budget users are responsible for proper planning in accordance with agreement between RS and EU, in the proper planning of the amount of expenditure • Budget user who do not funds sufficient funds for co-financing must redirect funds form their other budget lines Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 27. Budget system Law-Calendar Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 28. Guidelines for preparation of the Budget • Co-financing can be provided from public funds (by definition EU public funds are funds of budgets, own source revenues , loans granted to the state) or grants from international institutions. • Time frame of planning and implementation of activities that are co-financed by national funds under projects financed by EU funds Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 29. Time frame It is necessary to respect the following rules : • Activities that are co-financed under the project/sectoral program defines in project proposals/sectoral programs which make annual National program; • The funds for co-financing of projects/sectoral program must be planned in within the allowable budget limits for every budget users; • Bearing in mind that the implementation of the annual IPA perennial and can not coincides with the national budget year , it is the projection plan funds to finance activities that are cofinanced; Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 30. Time frame • Activities that are considered as co-financing must begin with the realization after the signature of the Financing Agreement. Otherwise, the funds which are financed these activities will not be recognized as part of the co-financing; • National co-financing should be planned taking into account the dynamics of implementation of project/program activities. • When planning the dynamics of negotiation, ie . Payment of those activities co-financed by public funds, or in predicting the resources that are need for co-financing the activities of the project /sectoral program should be take into account the order of activities listed in the project or in the sectoral program; Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 31. Time frame • Contracts for the implementation of all project/sectoral program must be concluded within two or three years from the date of signature of the Financing agreements depending on which service is provided specific financial Agreement within two years after the conclusion of individual contractscontractual obligations to be performed, and the payment of funds for their implementation is must be completed no later than one year from the last day set for the execution particular contract, unless otherwise specified in the Financing Agreement; • EC must be aware of implementation of part of the project/program activities, are co-financed from national resources; Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 32. Exercise• Table 4-Instructions for projects financed from EU funds (IPA) Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 33. N+ Rules OPTION 2 Combined annual Programme (max. 3 years) PROGRAMME ARCHITECTURE OPTION 1 Annual Programme OPTION 3 Multiannual Programme with split commitments (max. 7 years) Financing Decision (FD) Financing Decision covering an allocation for one year. Financing Decision covering an allocation for up to three years with suspension clause. Financing Decision covering an allocation for an initial (maximum) three years with suspension clause. Amendment of Financing Decision to add allocations for consecutive years' budget allocation at least twice. Possibly: Commission Decisions for selection of certain infrastructure projects (major projects) per year. Action Programme (Annex to FD) Action Programme covering Actions programmed for one year or Action Programme covering Actions programmed for more than one year and broken down into annual priorities (=selected Actions). Action Programme covering Actions programmed for three or more years and broken down into priorities for a maximum of three years. For these priorities (selected Actions), it must be clearly identified whether they are financed from year N, N+1 or N+2. Action Programme covering Actions programmed for up to seven years without earmarking of Actions by year. Budgetary commitment One budgetary commitment in year N. Annual budgetary commitments in N, N+1 and N+2 (three). The budgetary commitment is broken down into seven instalments, one for each year (through amendments to original commitment). Financing Agreement Project funded by The European Union One Financing Agreement. Financing Agreements to be concluded for each year or two amendments to original Financing Agreement. Financing Agreements to be signed covering allocations as specified in the Financing Decision (maximum initial allocation of three years) with suspension clause. Amendments to Financing Agreement Government of the Republic to add allocations for consecutive of Serbia years' budget allocation at least European Integration Office
  • 34. N+ Rules Relevant legal framework Article 189(2) FR Article 2 CIR Article 189(2) FR Article 6(3) CIR Article 189(3) FR Article 16 IPA RAP Article 6(3) CIR Possible methods of implementation Direct and Indirect Direct and Indirect Only Indirect IMPLEMENTATION TIMELINE Deadline for conclusion of Financing Agreement Deadline for conclusion of procurement contracts and grant agreements Deadline for operational implementation Deadline for automatic de-commitment Project funded by The European Union N+1 d+3 from conclusion of Financing Agreement “d” the date of conclusion of the Financing Agreement. 6 years from conclusion of Financing Agreement None N+1 counted from the year of creation of each yearly commitment None d+3 from conclusion of each Financing Agreement None 6 years from conclusion of each Financing Agreement None None Each yearly split commitment must be spent within five years of its validation (N+5). The last split commitment (2020) Government of the Republic must be spent within six years of its of Serbia validation (N+6). Integration Office European
  • 35. Sector Budget There needs to be a clear link between sector policy & budgeting. Sector plans should be properly priced & prioritized within a realistic estimate of the resources available from the national budget & external donors. IPA II Sector Support Programmes are planned to be multi-annual & should be co-financed by predictable, multi-annual national funding. It is necessary to provide a brief description of the sector budget on an annual, & if possible, on a medium-term perspective (3-5 years). Ideally there should be a Medium Term Expenditure Framework (MTEF) for the sector. However, development of MTEFs will be gradual, at first assessments should focus on the existence of credible annual sector budgets. At minimum, it is crucial to verify whether the sector budget can be identified in the state budget. Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 36. Path towards Fully-fledged Sector Support • Can the sector budget be easily identified in the state budget? • What is the nature and scope of the sector budget? • Does the budget fairly reflect the sector policies and objectives? • What type of budget classification system is in use? • What is the overall level of sector financing? • Is the share the sector within total government expenditures increasing? Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 37. Path towards Fully-fledged Sector Support-MTEF • If a sector MTEF is in place, key assessment questions include: • Is it consistent with declared policies and the national budget/overall MTEF of the country? • Is it approved at a political level or is it largely a technical document? • If a sector MTEF is foreseen by the government how can its elaboration be supported by means of the Sector Support Programme? Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 38. Path towards Fully-fledged Sector Support-MTEF • If a sector MTEF is in place, key assessment questions include: • Is it consistent with declared policies and the national budget/overall MTEF of the country? • Is it approved at a political level or is it largely a technical document? • If a sector MTEF is foreseen by the government how can its elaboration be supported by means of the Sector Support Programme? Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 39. Path towards Fully-fledged Sector Support-MTEF • If a sector MTEF is in place, key assessment questions include: • • • • If an MTEF is already in preparation, has a coherent and broad sector development plan with appropriate financing framework at sector and national level been defined/decided at a political level and is it considered feasible and is it consistent with national/overall MTEF? If a Sector MTEF is not in place, are appropriate sector allocations secured and properly stated in the general budget? Is there an on-going process leading to the setting up of Sector MTEF? Based on the analysis, recommendations should be made to the Government. Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 40. Programatic budgeting Differences between program and line budget: Showing: 1. that the purpose of money is spent; 2. how such consumption is linked to strategic objectives, and 3. what results should be achieved Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 41. Advantages of programme budget • Provides a single framework for prioritization of expenditures; • Improves policy coordination at the government level, which is crucial for achieving the national, social and economic objectives; • Provides financial context of strategic and operational plans for budget users; Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 42. Advantages of programme budget • Allows the government and local authorities to identify inefficient spending, as well as areas that do not provide adequate results and that require more resources; • Contributes to the improvement of public administration services through the evaluation of the relationship of their price and quality; • Makes budget more transparent and understandable for citizens Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 43. Programme budget • The introduction of program budgeting is of major importance for the improvement of public finance, as it enables continuous multiyear financing of priority policies, programs and projects. • • • By the end of 2013 a comprehensive preparation of institutions has been conducted for the introduction of program budgeting. By the end of 2013, fourteen (14) Serbian intuitions have adopted program based budget, including SEIO. During 2014, the preparation of institutions for the introduction of program budgeting will continue, as it is planned for the 2015 budget year according to the Budget System Law. Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 44. Mid-Term Expenditure Frameworks (MTEF) • Mid-Term Expenditure Frameworks (MTEFs) are part of the existing Fiscal Strategy. They are determined at the level of budget users and cannot directly be transformed into sector MTEFs. • Recently adopted legislation requires the merging of strategic planning of public policies with the budget process within the government and the parliament. This will include mandatory three-year budget planning and the introduction of programme budgeting by 2015. • It is planned that MTEFs for sectors will be developed alongside programme budgeting. For this to be feasible it will be necessary to ensure correspondence between the budget programmes and the NAD sectors. Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 45. Strategic Planning and Coordination of Public Policies • The guidelines for drafting the strategic documents were provided in the form of recommendations, and the uniform information system was introduced for the collection of data required for the government work program. • Draft Methodology for Integrated Strategic Planning was prepared, and this draft is to be adopted. • Still, upgrading of strategic planning and coordination of public policies within the Government should be considered the priority task in the forthcoming public administration reform process. Project funded by The European Union Government of the Republic of Serbia European Integration Office
  • 46. Project funded by The European Union Government of the Republic of Serbia European Integration Office Thank you for your attention All presentations are available on the PPF5 website: www.ppf5.rs

Editor's Notes

  1. Services Studies - identification and preparation of projects, feasibility studies, economic and marketing studies, technical studies, evaluations and audits (Global price) Technical assistance - the service provider has an advisory role, directs or supervises a project, or providing expert services defined in the contract (fee-based) The combination - defined as resources and productSupplies Purchase, lease or rental of assets (equipment). During the delivery of the equipment may be required installation and maintenance productsWorks Performance, or design and construction that result in the building or work of civil engineers who themselves are sufficient to meet the economic or technical function.Twinning (Twinning: 1-2 MEUR and Twinning light: up to 200.000 EUR)Cooperation tool between a Public Administration in a Partner/ Beneficiary country and the equivalent institution in an EU Member StateIt consists of sending to Serbia at least one resident adviser (12- 24 months)- RTA- and a number of medium and short-term missions, all to be carried out by public officials of the EU Member State institutionKey features is the concept of mandatory results: both the Serbian and the EU partner commit themselves to work towards a commonly agreed result, which should be measurable and precise. Includes at least some elements of approximation to the EU acquisGrantsDirect payments of non-commercial nature Grants contract is used for the grant scheme as direct donation for local and regional authorities and civil society organizations Direct Agreements For particular tasks with specific organizations like UNHCR etc.