The Effect of Scope Changes on Project Duration Extensions
Extended Abstract of a PhD Dissertation1
Moshe Ayal
Faculty of Management, Tel Aviv University, Tel Aviv 69978
Abstract
The objective of this research is twofold: first to construct and validate an explanatory model for
project duration extensions, and second to analyze the effect of scope changes and other related
drivers on project delivery times. The research is based on a field study, which draws data from an
engineering service environment, and uses means of structural equation modeling for analysis. The
model contributes to a better understanding of the effect of various scope changes on project
duration, and enables the construction of a practical tool for estimating project duration.
Introduction
Projects frequently finish late and over budget, thus causing organizations heavy penalties and
damage their prestige. Moreover, as projects are hardly ever completed without introducing changes
to their original baseline plan, a major challenge is to accurately estimate the project delivery time,
while understanding the effects of other factors that create the discrepancy between estimated and
actual project completion times. Thus, the intention in this work is to quantify the factors affecting
duration extensions, an issue that has barely been addressed in the literature. One way to quantify
these factors is by generating a descriptive empirical model that includes the major behavioral and
quantitative measures of performance.
Literature
The section reviews the following themes: (1) duration estimation, the basis of duration extension
measures, (2) possible generators of duration extensions, and (3) scope changes, and their effect on
project performance.
Duration Estimation. The tools most commonly used are based upon mathematical models in
which task duration is explained by technical parameters of the task and the experience of the
executing entity. Well known examples of these tools are SLIM (Putnam, 1978), and COCOMO
Softwares (Boehm, 1981; Boehm et al., 2000). Burt and Kemp (1991) proposed predicting task
duration from knowledge about durations of categories of tasks. However, here a potential bias
exists, known in the psychology literature as the planning fallacy, due to the tendency of individuals
to underestimate the amount of time needed to complete a given project. In the words of Buehler,
Griffin and Ross (1994), they tend to focus on the future, ignoring past experience.
Duration Extensions Generators. Several generators are discussed in the literature. Levy and
Globerson (1997) implemented concepts from queuing theory for reducing the impact of waiting
periods of critical work packages on the delivery times of projects executed in parallel. Goldratt
(1997) claimed that task splitting, whether planned or results from preemptive processing might
lead to severe duration extensions. Shenhar (2001) classified technological uncertainty into four
levels, correlating them with overall project duration. Shenhar et al. (2002) also claimed that
1 Thesis Supervisor: Prof. Shlomo Globerson
EFFECT OF SCOPE CHANGES ON PROJECT DURATION EXTENSIONS - MOSHE AYAL
2
projects high in uncertainty must be managed differently, employing means to reduce the
uncertainty. Low experience with technology often results in what we term low structured projects
(Applegate, Austin, and McFarlan, 2003) where risk mitigation is of great need. Based on surveys,
Chan and Kumaraswamy (2002) mentioned: (1) impractical design, (2) labor shortages, (3) poor
performance, (5) unforeseen conditions, and (6) poor communication. Still, literature lacks
empirical quantifications of the effects of the above-mentioned generators on project duration.
Scope Changes. Modification to the agreed upon scope (PMBOK, 2000) are considered as
inherent in the nature of projects because of their complexity and the inevitable appearance of
unforeseen problems (Ertel, 2000). The evidence shows that scope changes have a significant
impact on the cost of projects. Chick (1999) showed that the later a change occurs in a project the
more effect it will have on the project’s cost, and also mentioned a possible effect on project
schedule. Kauffmann et al. (2002) used the earned value method in quantifying scope change
‘magnitude’ for cost adjustments. Barry et al. (2002) showed a correlation between software project
duration and effort. However, a thorough investigation of the effect of scope changes on project
duration has not yet been conducted.
Research Design
Figure 1 illustrates the hypothesized work package duration extensions model. The model
includes three exogenous variables: (1) Technological Uncertainty, (2) Project Priority, and (3)
Unforeseen Stoppages. It also has six endogenous variables: (1) Additional Materials, which refers
to inventory orders, and (2) Additional Labor, both resulting from scope changes, and marked
inside a dashed box; (3) Waiting in Line; (4) Preemptive Processing; (5) Stoppage Period, and (6)
the main dependent variable: Duration Extension, which refers to a work package.
Figure 1. Hypothesized Work Package Duration Extensions Model
Unforeseen
Stoppages
Project
Priority
Preemptive
Processing
Waiting
in Line
Duration
Extension
Stoppage
Period
Technological
Uncertainty
H1 H2
H3
(H7)
(H6)
H5
H4
Additional
Materials
Additional
Labor
Table 1 summarizes the proposed model variables and the rationale for their selection.
EFFECT OF SCOPE CHANGES ON PROJECT DURATION EXTENSIONS - MOSHE AYAL
3
Table 1. Proposed Model Variables
Variable Description Rationale
Technological
Uncertainty
Level of technological uncertainty associated
with a certain work package
Technological uncertainty is correlated with
duration (Shenhar, 2001)
Project Priority
Priorities assigned to projects by top
management team
May decrease duration extensions by
reducing waiting periods
Unforeseen
Stoppages
Number of unforeseen operational stoppages
caused by internal or external sources
A greater number of operational stoppages
may increase in-process duration
Stoppage
Period
Total time periods of operational stoppages
caused by internal or external sources
Longer periods of operational stoppages may
increase in-process duration
Additional
Materials
Number of material orders resulting from
scope changes
Waiting until materials arrival, if filing for an
external supply, may increase the duration
Additional
Labor
Additional labor resulting from scope changes
Scope changes could affect duration (Chick,
1999)
Waiting in Line
Time from the arrival of a work package to the
beginning of its processing
Waiting periods may extend delivery times
(Levy and Globerson, 1997)
Preemptive
Processing
Number of breaks during processing a work
package
Task splitting increases in-process duration
(Goldratt, 1997)
Duration
Extension
Work package in-process duration extension
relative to planned duration
The main dependent variable of the research
Table 2 provides five hypotheses that are derived directly from the duration extensions model,
based on its flow. The sixth hypothesis involves two exogenous variables, not included in the model
for reasons of parsimony: (1) Internal Scope Changes, and (2) External Scope Changes. The seventh
hypothesis is indicated by a correlation in the duration extensions model, and is tested separately
within the projects’ framework.
Table 2. Hypotheses
Variable Effect on Variable Rationale
H1 Additional Labor +
Duration
Extension
Additional labor calls for resources, which in many cases are not
currently available
H2
Additional
Materials
+
Duration
Extension
In-process duration extensions may result from having to wait until
materials arrive
H3
Preemptive
Processing
+
Duration
Extension
Goldratt's (1997) claim that splitting a task results in extending its in-
process duration
H4 Additional Labor +
Preemptive
Processing
Work package manager needs to wait for available resources and/or
materials to arrive
H5 Waiting in Line -
Preemptive
Processing
The negative effect of waiting periods can be decreased by working
intensively and continuously
External Scope
Changes
++
Internal Scope
Changes
+
H7
Technological
Uncertainty
+ Project Priority
Allocating priority to a project may help in rapidly mitigating the
uncertainties in its work packages
Work package managers who introduce scope changes try to avoid
material orders and use in stock materials, so as not to wait for the
materials to arrive. Thus, external scope changes are expected to
have a greater effect on material orders than Internal scope changes
Additional
Materials
H6
EFFECT OF SCOPE CHANGES ON PROJECT DURATION EXTENSIONS - MOSHE AYAL
4
Analysis. We analyze the model using means of structural equation modeling (SEM) in order to
elicit the partial correlations amongst the variables, and to establish the causal relations. Two of the
variables are dummy ones: (1) Project Priority, which takes the value of ‘1’ for prioritized project,
and ‘0’ otherwise, and (2) Technological Uncertainty, which takes the value of ‘1’ for work
package with technological uncertainty, and ‘0’ otherwise. We conduct linear multiple regression in
examining Hypothesis 6, and use means of binomial regression to test Hypothesis 7, on the effect of
technological uncertainty on project priority. We use the EQS software package (Byrne, 1994) for
conducting the SEM analysis. In order to bring all data to the same reference point, the model’s
variables, except for the dummies, are divided by the planned duration of the work package.
Data collection. The study draws data from 714 work packages comprising the 56 systems
engineering projects being performed at the time by a leading engineering services corporation. The
projects ranged in value from several thousand dollars to one hundred thousand dollars, while the
work packages comprising these projects ranged in duration from several days to a month. The
projects had a sequential PERT/CPM structure, thus above 90% of the work packages where
critical. Top management team, department managers, project managers and professional section
managers were involved in data gathering. They used an interactive data collection interface, which
was part of the project control system of the corporation.
Results
Table 3 shows the means, standard deviations, variables ranges and bivariate correlations for the
variables of the proposed model. Note that in some cases total labor hours invested in a work
package were decreased as a result of scope changes. However, in our data it was the rare case, as
most of the time scope changes resulted in additional labor, which sometimes accumulated to as
high as several hundreds of percents of the allocated labor hours!
Table 3. Descriptive Statistics and Pearson Correlation Matrix
Variables Mean s.d. Min Max 1 2 3 4 5 6 7 8
1 Tech. Uncertainty 0.29 0.46 0 1
2 Project Priority 0.37 0.48 0 1 .22**
3 Unforeseen Stoppages 0.04 0.10 0 0.5 -.08* -.02
4 Stoppage Period 0.10 0.36 0 6.5 -.05 -.05 .53**
5 Additional Materials 0.02 0.06 0 0.5 .18** .04 .01 -.01
6 Additional Labor 0.23 0.63 -0.47 7 .29** .06 -.03 -.05 .54**
7 Waiting in Line 0.30 0.29 0 1.5 -.08* -.21** -.003 .002 .03 .12**
8 Preemptive Processing 0.15 0.14 0 1 .09* .01 .28** .08* .11** .27** -.05
9 Duration Extension 0.31 0.68 -0.66 7 .11** -.08* .31** .60** .41** .48** .28** .25**
Note . n=714 (work packages)
* p < .05
** p < .01
EFFECT OF SCOPE CHANGES ON PROJECT DURATION EXTENSIONS - MOSHE AYAL
5
Model Fit. Using structural equation modeling means of analysis, the hypothesized model of
work package duration extensions is found significant: 6.322
=χ , with 18 degrees of freedom,
which rejects the null model hypothesis. In addition, the goodness of fit indices: NFI=0.98;
NNFI=0.98; CFI=0.99; and RMSEA=0.034 (for n=714 work packages), indicating a good fit of the
model to the data (Bagozzi & Yi, 1988; Bagozzi & Yi, 1989).
Hypotheses 1 to 5. From the partial correlations given in Table 4, Hypotheses 1 to 5 are seen to
have statistical significance. Note that two of the hypothesized relations are proved not to be
significant: (1) additional material orders affect preemptive processing, but only indirectly, via the
resulted additional labor; and (2) project priority affects duration extension only indirectly, via
shorter waiting in line periods. In addition, out of the three correlations tested, only the one between
project priority and technological uncertainty is found significant (r =0.22).
Table 4. Direct Relations in the Work Packages Duration Extensions Model
Hyp. From To
Standardized
coefficients
t-values
H1 Additional Labor Duration Extension .34 13.49
H2 Additional Materials Duration Extension .21 8.80
Waiting in Line Duration Extension .23 10.92
H3 Preemptive Processing Duration Extension .10 4.81
Stoppage Period Duration Extension .61 29.83
Project Priority Duration Extension -.03 -1.62(*)
Technological Uncertainty Additional Labor .20 6.38
Additional Materials Additional Labor .51 16.36
Technological Uncertainty Additional Materials .18 4.82
Project Priority Waiting in Line -.21 -5.74
Unforeseen Stoppages Preemptive Processing .23 8.44
H4 Additional Labor Preemptive Processing .32 7.76
Additional Materials Preemptive Processing -.06 -1.46(*)
H5 Waiting in Line Preemptive Processing -.08 -2.31
Unforeseen Stoppages Stoppage Period .53 16.62
Note. n=714; NFI=0.98; NNFI=0.98; CFI=0.99; RMSEA=0.034.
(*) path not significant
Duration Prediction. Using means of linear multiple regression, we derive a mathematical
model for the prediction of work package duration based on its predetermined variables,
performance variables, and disruptions like forced stoppages and scope changes (R2
=0.71). Table 5
shows the predictors of the best-fitting model. Note that if we ignore the two scope changes
variables – additional material orders, and additional labor - we explain only 51% of the variance in
the duration extension. Conducting a partial F-test we again confirm the hypothesis that the two
variables representing scope changes are significant in the model.
EFFECT OF SCOPE CHANGES ON PROJECT DURATION EXTENSIONS - MOSHE AYAL
6
Table 5. Predictors of Work Package Duration Extentions
Models:
Predictor Estimate St. Error Estimate St. Error
Project Priority -0.039 0.039
Technological Uncertainty 0.218 0.041
Unforeseen Stoppages -0.470* 0.214
Stoppage Period 1.159** 0.039 1.188** 0.059
Additional Materials 2.466** 0.282
Additional Labor 0.363** 0.027
Waiting in Line 0.552** 0.049 0.686** 0.063
Preemptive Processing 0.519** 0.107 1.133** 0.139
Intercept -0.171** 0.026 -0.212** 0.038
R^2 0.707 0.513
Adj. R^2 0.705 0.509
Note . n=714. Partial F test for Model(2) = 328, p<0.001
* p < .05
** p < .01
(1) Best Fitting (2) without Scope Changes
Hypothesis 6. To test Hypothesis 6, on the effects of internal and external scope changes on
additional material orders, we regressed the additional material orders against the number of
external and internal scope changes, dividing both by the planned duration, as with all the variables.
The results showed in Table 6 indicate that external scope changes result in a significantly higher
amount of material orders than do internal scope changes. Note, however, that the number of
internal and external scope changes is almost the same.
Table 6. Additional Material Orders by Number of External and Internal Scope Changes
Predictor Number Estimate St. Error
Internal Scope Changes 113 0.065** 0.02
External Scope Changes 120 0.267** 0.021
Intercept 0.003 0.002
R^2 0.19
Adj. R^2 0.187
Note . n=714 (work packages)
** p < .01
Hypothesis 7. Figure 2 shows the number of prioritized and non-prioritized projects by the
number of work packages with technological uncertainty. The data shows that the majority of the
projects of five or more work packages with technological uncertainty are prioritized. To formally
corroborate Hypothesis 7, we regressed project priority against the number of work packages with
technological uncertainty in the project, using means of binomial regression.
EFFECT OF SCOPE CHANGES ON PROJECT DURATION EXTENSIONS - MOSHE AYAL
7
Figure 2. Prioritized and Non-Prioritized Projects by Work Packages with Technological Uncertainty
0
5
10
15
20
0-1 2-3 4 5 6-11
Work Packages with Technological Uncertainty
Projects
Regular Projects
Prioritized Projects
Table 7 presents the results of the binomial regression, which indicate that a project consists of
five or more work packages with technological uncertainties is likely to get priority by top
management. This might shed some new light on the way top management reduces technological
uncertainties in projects.
Table 7. Project Priority by Number of Work Packages with Technological Uncertainties
Predictor Estimate St. Error Significance
Technological Uncertainty 0.88 0.26 0.001
Intercept -4.19 1.13 0.001
-2LL 45.88
Note . n=56 (projects).
Implications and Conclusions
Functional Level. Functional managers usually do not have a picture of the entire projects.
Rather they see various work packages arriving from different project managers that must be
processed according to certain priority rules. The model developed here can help them to better
assess the effects of the various disruptions that occur while the work packages are being processed.
They can also use the model to compensate for duration extensions, thus enabling better
performance of overall workload.
EFFECT OF SCOPE CHANGES ON PROJECT DURATION EXTENSIONS - MOSHE AYAL
8
Project / Multi-Project Level. At the project level, we should distinguish between critical work
packages that need to be tightly controlled, and non-critical work packages. At the multi-project
level, top management has to differentiate between prioritized and non-prioritized projects, giving
top priority to critical work packages belonging to prioritized projects. This will assure that the
projects with the highest priority will be delivered on time. The proposed model assesses the effect
of unforeseen disruptions on critical work packages of high-priority projects, and provides better
tools for estimating final duration and compensating for delays.
Summary
The study contributes to an improved understanding of duration extensions and their causes, by
quantifying scope changes, differentiating amongst the various types of scope changes, and
constructing an integrated model of work package duration extensions. The study pointed to the
greater effect of external scope changes, compared with internal ones, on material orders, and thus
on the total duration extensions. Generally, the model can be implemented for forecasting work
package duration extensions, and estimating the effect on the project’s duration. Finally, several
implications at the functional, the project, and the multi-project levels are suggested.
Acknowledgments
This work is based on my PhD dissertation, supervised by Prof S. Globerson. I wish to expresses
my gratitude to him, and to all whose insights have contributed to this thesis.
References
Applegate, L.M., Austin, R.D., & McFarlan, F.W. 2003 Corporate Information Strategy and
Management: Text and Cases. NY: McGraw-Hill Irwin.
Bagozzi, R.P., & Yi, Y. 1988. On the evaluation of structural equation models. Journal of Academy
of Marketing Science, 16(1): 74–94.
Bagozzi, R.P., & Yi, Y. 1989. On the use of structural equation models in experimental designs.
Journal of Marketing Research, 26(3): 271–284.
Barry, E.J., Mukhopadhyay, T., & Slaughter. S.A. 2002. Software Project Duration and Effort: An
Empirical Study. Information Technology and Management, 3(1-2): 113-136.
Boehm, B.W. 1981. Software engineering economics. Advances in computing science and
technology. NJ: Prentice-Hall.
Boehm, B.W., Horowitz, E., Madachy, R., Reifer, D., Clark, B.K., Steece, B., Brown, A.W.,
Chulani, S., & Abts, C. 2000. Software Cost Estimation with COCOMO II. NJ: Prentice Hall.
Buehler, R., Griffin, D., & Ross, M. 1994. Exploring the "planning fallacy": Why people
underestimate their task completion times. Journal of Personality and Social Psychology, 67:
366-381.
Burt, C.D.B., & Kemp, S. 1991. Retrospective duration estimation of public events. Memory &
Cognition, 19: 252-262.
EFFECT OF SCOPE CHANGES ON PROJECT DURATION EXTENSIONS - MOSHE AYAL
9
Byrne B.M. 1994 Structural Equation Modeling with EQS and EQS/Windows. Newbury Park, CA:
Sage Publications.
Chan, D.W.M., & Kumaraswamy, M.M. 2002. Compressing construction durations: Lessons
learned from Hong Kong building projects. International Journal of Project Management,
20(1): 23-35.
Chick, D. 1999. The time value of project change. Cost Engineering, 41(6): 27-31.
Ertel, D., & Rudner, S. 2000. Scope change negotiations: Are write-off inevitable? Consulting to
Management, 11 (2): 3-8.
Goldratt, E.M. 1997. Critical Chain. NY: North River Press.
Kauffmann, P., Keating, C., & Considine, C. 2002. Using earned value methods to substantiate
change-of-scope claims. Engineering Management Journal, 14(1): 13-20.
Levy, N., & Globerson, S. 1997. Improving multi-project management by using queuing theory
approach. Project Management Journal, 28(4): 40-46.
Project Management Institute, 2000. A Guide to the Project Management Body of Knowledge
(PMBOK Guide). Project Management Institute, Upper Darby, PA.
Putnam, L.H. 1978. A general empirical solution to the macro software sizing and estimating
problem. IEEE Transactions on Software Engineering, 4(4): 345-361.
Shenhar, A.J. 2001. One size does not fit all projects - exploring classical contingency domains.
Management Science, 47(3): 394-414.
Shenhar, A.J., Tishler, A., Dvir, D., Lipovetsky, S., & Lechler. T. 2002. Refining the search for
project success factors: A multivariate, typological approach. R & D Management, 32(2): 111-
126.

Más contenido relacionado

La actualidad más candente

Optimizing Time and Effort Parameters of COCOMO II Using Fuzzy Multi-objectiv...
Optimizing Time and Effort Parameters of COCOMO II Using Fuzzy Multi-objectiv...Optimizing Time and Effort Parameters of COCOMO II Using Fuzzy Multi-objectiv...
Optimizing Time and Effort Parameters of COCOMO II Using Fuzzy Multi-objectiv...TELKOMNIKA JOURNAL
 
Application of Genetic Algorithm in Software Engineering: A Review
Application of Genetic Algorithm in Software Engineering: A ReviewApplication of Genetic Algorithm in Software Engineering: A Review
Application of Genetic Algorithm in Software Engineering: A ReviewIRJESJOURNAL
 
A Study: The Analysis of Test Driven Development And Design Driven Test
A Study: The Analysis of Test Driven Development And Design Driven TestA Study: The Analysis of Test Driven Development And Design Driven Test
A Study: The Analysis of Test Driven Development And Design Driven TestEditor IJMTER
 
Chapter 8 software testing
Chapter 8 software testingChapter 8 software testing
Chapter 8 software testingdespicable me
 
Determination of Software Release Instant of Three-Tier Client Server Softwar...
Determination of Software Release Instant of Three-Tier Client Server Softwar...Determination of Software Release Instant of Three-Tier Client Server Softwar...
Determination of Software Release Instant of Three-Tier Client Server Softwar...Waqas Tariq
 
Final Exam Solutions Fall02
Final Exam Solutions Fall02Final Exam Solutions Fall02
Final Exam Solutions Fall02Radu_Negulescu
 
Comparison between Test-Driven Development and Conventional Development: A Ca...
Comparison between Test-Driven Development and Conventional Development: A Ca...Comparison between Test-Driven Development and Conventional Development: A Ca...
Comparison between Test-Driven Development and Conventional Development: A Ca...IJERA Editor
 
Testability measurement model for object oriented design (tmmood)
Testability measurement model for object oriented design (tmmood)Testability measurement model for object oriented design (tmmood)
Testability measurement model for object oriented design (tmmood)ijcsit
 
COMPARATIVE STUDY OF SOFTWARE ESTIMATION TECHNIQUES
COMPARATIVE STUDY OF SOFTWARE ESTIMATION TECHNIQUES COMPARATIVE STUDY OF SOFTWARE ESTIMATION TECHNIQUES
COMPARATIVE STUDY OF SOFTWARE ESTIMATION TECHNIQUES ijseajournal
 
Marshall Esc Lille Defense R2
Marshall Esc Lille Defense R2Marshall Esc Lille Defense R2
Marshall Esc Lille Defense R2Drmarshallpmp
 

La actualidad más candente (13)

Defect Age
Defect  AgeDefect  Age
Defect Age
 
Optimizing Time and Effort Parameters of COCOMO II Using Fuzzy Multi-objectiv...
Optimizing Time and Effort Parameters of COCOMO II Using Fuzzy Multi-objectiv...Optimizing Time and Effort Parameters of COCOMO II Using Fuzzy Multi-objectiv...
Optimizing Time and Effort Parameters of COCOMO II Using Fuzzy Multi-objectiv...
 
Application of Genetic Algorithm in Software Engineering: A Review
Application of Genetic Algorithm in Software Engineering: A ReviewApplication of Genetic Algorithm in Software Engineering: A Review
Application of Genetic Algorithm in Software Engineering: A Review
 
A Study: The Analysis of Test Driven Development And Design Driven Test
A Study: The Analysis of Test Driven Development And Design Driven TestA Study: The Analysis of Test Driven Development And Design Driven Test
A Study: The Analysis of Test Driven Development And Design Driven Test
 
Chapter 8 software testing
Chapter 8 software testingChapter 8 software testing
Chapter 8 software testing
 
Determination of Software Release Instant of Three-Tier Client Server Softwar...
Determination of Software Release Instant of Three-Tier Client Server Softwar...Determination of Software Release Instant of Three-Tier Client Server Softwar...
Determination of Software Release Instant of Three-Tier Client Server Softwar...
 
Final Exam Solutions Fall02
Final Exam Solutions Fall02Final Exam Solutions Fall02
Final Exam Solutions Fall02
 
MCP2
MCP2MCP2
MCP2
 
Comparison between Test-Driven Development and Conventional Development: A Ca...
Comparison between Test-Driven Development and Conventional Development: A Ca...Comparison between Test-Driven Development and Conventional Development: A Ca...
Comparison between Test-Driven Development and Conventional Development: A Ca...
 
Testability measurement model for object oriented design (tmmood)
Testability measurement model for object oriented design (tmmood)Testability measurement model for object oriented design (tmmood)
Testability measurement model for object oriented design (tmmood)
 
Bj33356362
Bj33356362Bj33356362
Bj33356362
 
COMPARATIVE STUDY OF SOFTWARE ESTIMATION TECHNIQUES
COMPARATIVE STUDY OF SOFTWARE ESTIMATION TECHNIQUES COMPARATIVE STUDY OF SOFTWARE ESTIMATION TECHNIQUES
COMPARATIVE STUDY OF SOFTWARE ESTIMATION TECHNIQUES
 
Marshall Esc Lille Defense R2
Marshall Esc Lille Defense R2Marshall Esc Lille Defense R2
Marshall Esc Lille Defense R2
 

Destacado

MICRO TEACHING IDIK4013-Memanfaatkan Pustaka dalam Penulisan Karya Ilmiah
MICRO TEACHING IDIK4013-Memanfaatkan Pustaka dalam Penulisan Karya IlmiahMICRO TEACHING IDIK4013-Memanfaatkan Pustaka dalam Penulisan Karya Ilmiah
MICRO TEACHING IDIK4013-Memanfaatkan Pustaka dalam Penulisan Karya IlmiahRatzman III
 
Format laporan Tutor Universitas Terbuka 2014
Format laporan Tutor Universitas Terbuka 2014Format laporan Tutor Universitas Terbuka 2014
Format laporan Tutor Universitas Terbuka 2014Ratzman III
 
Arduino Ch3 : Tilt Sensing Servo Motor Controller
Arduino Ch3 : Tilt Sensing Servo Motor Controller Arduino Ch3 : Tilt Sensing Servo Motor Controller
Arduino Ch3 : Tilt Sensing Servo Motor Controller Ratzman III
 
Tugas Tutorial EKSI4202 Hukum Pajak
Tugas Tutorial EKSI4202 Hukum PajakTugas Tutorial EKSI4202 Hukum Pajak
Tugas Tutorial EKSI4202 Hukum PajakRatzman III
 
Tugas Wajib Tutorial I - EKSI4202 - Hukum Pajak
Tugas Wajib Tutorial I  -  EKSI4202 - Hukum PajakTugas Wajib Tutorial I  -  EKSI4202 - Hukum Pajak
Tugas Wajib Tutorial I - EKSI4202 - Hukum PajakRatzman III
 
Benefits of drinking water
Benefits of drinking waterBenefits of drinking water
Benefits of drinking waterEason Chan
 
10 Tips for WeChat
10 Tips for WeChat10 Tips for WeChat
10 Tips for WeChatChris Baker
 

Destacado (8)

MICRO TEACHING IDIK4013-Memanfaatkan Pustaka dalam Penulisan Karya Ilmiah
MICRO TEACHING IDIK4013-Memanfaatkan Pustaka dalam Penulisan Karya IlmiahMICRO TEACHING IDIK4013-Memanfaatkan Pustaka dalam Penulisan Karya Ilmiah
MICRO TEACHING IDIK4013-Memanfaatkan Pustaka dalam Penulisan Karya Ilmiah
 
Format laporan Tutor Universitas Terbuka 2014
Format laporan Tutor Universitas Terbuka 2014Format laporan Tutor Universitas Terbuka 2014
Format laporan Tutor Universitas Terbuka 2014
 
Arduino Ch3 : Tilt Sensing Servo Motor Controller
Arduino Ch3 : Tilt Sensing Servo Motor Controller Arduino Ch3 : Tilt Sensing Servo Motor Controller
Arduino Ch3 : Tilt Sensing Servo Motor Controller
 
Tugas Tutorial EKSI4202 Hukum Pajak
Tugas Tutorial EKSI4202 Hukum PajakTugas Tutorial EKSI4202 Hukum Pajak
Tugas Tutorial EKSI4202 Hukum Pajak
 
Tugas Wajib Tutorial I - EKSI4202 - Hukum Pajak
Tugas Wajib Tutorial I  -  EKSI4202 - Hukum PajakTugas Wajib Tutorial I  -  EKSI4202 - Hukum Pajak
Tugas Wajib Tutorial I - EKSI4202 - Hukum Pajak
 
Benefits of drinking water
Benefits of drinking waterBenefits of drinking water
Benefits of drinking water
 
Stay Up To Date on the Latest Happenings in the Boardroom: Recommended Summer...
Stay Up To Date on the Latest Happenings in the Boardroom: Recommended Summer...Stay Up To Date on the Latest Happenings in the Boardroom: Recommended Summer...
Stay Up To Date on the Latest Happenings in the Boardroom: Recommended Summer...
 
10 Tips for WeChat
10 Tips for WeChat10 Tips for WeChat
10 Tips for WeChat
 

Similar a 10.1.1.194.6071

Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...IOSR Journals
 
A Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To ConcreteA Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To ConcreteDawn Cook
 
Project Performance Analysis And Delivery Methods - Quantitative Analysis
Project Performance Analysis And Delivery Methods - Quantitative AnalysisProject Performance Analysis And Delivery Methods - Quantitative Analysis
Project Performance Analysis And Delivery Methods - Quantitative AnalysisSeta Ohanesian, PMP, LEED AP
 
Proceedings of the 2013 Industrial and Systems Engineering Res.docx
Proceedings of the 2013 Industrial and Systems Engineering Res.docxProceedings of the 2013 Industrial and Systems Engineering Res.docx
Proceedings of the 2013 Industrial and Systems Engineering Res.docxstilliegeorgiana
 
ANALYSIS OF PROJECT SCOPE CHANGE MANAGEMENT AS A TOOL FOR PROJECT SUCCESS CA...
ANALYSIS OF PROJECT SCOPE CHANGE MANAGEMENT AS A TOOL FOR PROJECT SUCCESS  CA...ANALYSIS OF PROJECT SCOPE CHANGE MANAGEMENT AS A TOOL FOR PROJECT SUCCESS  CA...
ANALYSIS OF PROJECT SCOPE CHANGE MANAGEMENT AS A TOOL FOR PROJECT SUCCESS CA...Karla Adamson
 
Improvement of the model of minimization of the costs in a time overrun conte...
Improvement of the model of minimization of the costs in a time overrun conte...Improvement of the model of minimization of the costs in a time overrun conte...
Improvement of the model of minimization of the costs in a time overrun conte...IAEME Publication
 
Simulasi lean contractor
Simulasi lean contractorSimulasi lean contractor
Simulasi lean contractorRifki Rizal
 
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxRUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxtoltonkendal
 
Rapid Improvements with No Commercial Production: How do the Improvements Occ...
Rapid Improvements with No Commercial Production: How do the Improvements Occ...Rapid Improvements with No Commercial Production: How do the Improvements Occ...
Rapid Improvements with No Commercial Production: How do the Improvements Occ...Jeffrey Funk
 
Project management chapter 11
Project management chapter 11Project management chapter 11
Project management chapter 11VancityInstitute
 
Applicability of heuristic approach in planning and scheduling project
Applicability of heuristic approach in planning and scheduling projectApplicability of heuristic approach in planning and scheduling project
Applicability of heuristic approach in planning and scheduling projectAlexander Decker
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis IOSR Journals
 
Logistic improvement using scor
Logistic improvement using scorLogistic improvement using scor
Logistic improvement using scorShashank Kapoor
 
Project management synopsis [www.writekraft.com]
Project management synopsis  [www.writekraft.com]Project management synopsis  [www.writekraft.com]
Project management synopsis [www.writekraft.com]WriteKraft Dissertations
 
A Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project ManagementA Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project ManagementJoe Osborn
 
Causes and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitCauses and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitIJERA Editor
 
BEST PRACTICES OF PM EFFECT ON PROJECT SUCCESS
BEST PRACTICES OF PM EFFECT ON  PROJECT SUCCESSBEST PRACTICES OF PM EFFECT ON  PROJECT SUCCESS
BEST PRACTICES OF PM EFFECT ON PROJECT SUCCESSMuhammad Awais
 

Similar a 10.1.1.194.6071 (20)

Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
 
A Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To ConcreteA Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To Concrete
 
A9 r30d0
A9 r30d0A9 r30d0
A9 r30d0
 
Project Performance Analysis And Delivery Methods - Quantitative Analysis
Project Performance Analysis And Delivery Methods - Quantitative AnalysisProject Performance Analysis And Delivery Methods - Quantitative Analysis
Project Performance Analysis And Delivery Methods - Quantitative Analysis
 
Proceedings of the 2013 Industrial and Systems Engineering Res.docx
Proceedings of the 2013 Industrial and Systems Engineering Res.docxProceedings of the 2013 Industrial and Systems Engineering Res.docx
Proceedings of the 2013 Industrial and Systems Engineering Res.docx
 
CIA_application award paper
CIA_application award paperCIA_application award paper
CIA_application award paper
 
ANALYSIS OF PROJECT SCOPE CHANGE MANAGEMENT AS A TOOL FOR PROJECT SUCCESS CA...
ANALYSIS OF PROJECT SCOPE CHANGE MANAGEMENT AS A TOOL FOR PROJECT SUCCESS  CA...ANALYSIS OF PROJECT SCOPE CHANGE MANAGEMENT AS A TOOL FOR PROJECT SUCCESS  CA...
ANALYSIS OF PROJECT SCOPE CHANGE MANAGEMENT AS A TOOL FOR PROJECT SUCCESS CA...
 
Improvement of the model of minimization of the costs in a time overrun conte...
Improvement of the model of minimization of the costs in a time overrun conte...Improvement of the model of minimization of the costs in a time overrun conte...
Improvement of the model of minimization of the costs in a time overrun conte...
 
Simulasi lean contractor
Simulasi lean contractorSimulasi lean contractor
Simulasi lean contractor
 
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxRUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
 
Rapid Improvements with No Commercial Production: How do the Improvements Occ...
Rapid Improvements with No Commercial Production: How do the Improvements Occ...Rapid Improvements with No Commercial Production: How do the Improvements Occ...
Rapid Improvements with No Commercial Production: How do the Improvements Occ...
 
Project management chapter 11
Project management chapter 11Project management chapter 11
Project management chapter 11
 
Applicability of heuristic approach in planning and scheduling project
Applicability of heuristic approach in planning and scheduling projectApplicability of heuristic approach in planning and scheduling project
Applicability of heuristic approach in planning and scheduling project
 
D012522433
D012522433D012522433
D012522433
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis
 
Logistic improvement using scor
Logistic improvement using scorLogistic improvement using scor
Logistic improvement using scor
 
Project management synopsis [www.writekraft.com]
Project management synopsis  [www.writekraft.com]Project management synopsis  [www.writekraft.com]
Project management synopsis [www.writekraft.com]
 
A Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project ManagementA Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project Management
 
Causes and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitCauses and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in Kuwait
 
BEST PRACTICES OF PM EFFECT ON PROJECT SUCCESS
BEST PRACTICES OF PM EFFECT ON  PROJECT SUCCESSBEST PRACTICES OF PM EFFECT ON  PROJECT SUCCESS
BEST PRACTICES OF PM EFFECT ON PROJECT SUCCESS
 

Más de Ratzman III

Review Artikel Tinjauan Pustaka
Review Artikel Tinjauan PustakaReview Artikel Tinjauan Pustaka
Review Artikel Tinjauan PustakaRatzman III
 
Arduino - Ch 2: Sunrise-Sunset Light Switch
Arduino - Ch 2: Sunrise-Sunset Light SwitchArduino - Ch 2: Sunrise-Sunset Light Switch
Arduino - Ch 2: Sunrise-Sunset Light SwitchRatzman III
 
Arduino - CH 1: The Trick Switch
Arduino - CH 1: The Trick SwitchArduino - CH 1: The Trick Switch
Arduino - CH 1: The Trick SwitchRatzman III
 
Bab 3 - Kalkulus Relasional
Bab 3 -  Kalkulus RelasionalBab 3 -  Kalkulus Relasional
Bab 3 - Kalkulus RelasionalRatzman III
 
Bab 2 Aljabar Relasional
Bab 2   Aljabar RelasionalBab 2   Aljabar Relasional
Bab 2 Aljabar RelasionalRatzman III
 
Bab 1 RDBMS Review
Bab 1   RDBMS ReviewBab 1   RDBMS Review
Bab 1 RDBMS ReviewRatzman III
 
Kisi kisi basis data uts
Kisi kisi basis data utsKisi kisi basis data uts
Kisi kisi basis data utsRatzman III
 
Kisi kisi basis data uts
Kisi kisi basis data utsKisi kisi basis data uts
Kisi kisi basis data utsRatzman III
 
Modul my sql tutorial part 6
Modul my sql tutorial part 6Modul my sql tutorial part 6
Modul my sql tutorial part 6Ratzman III
 
Modul my sql tutorial part 5
Modul my sql tutorial part 5Modul my sql tutorial part 5
Modul my sql tutorial part 5Ratzman III
 
Format Pengabdian Masyarakat
Format Pengabdian MasyarakatFormat Pengabdian Masyarakat
Format Pengabdian MasyarakatRatzman III
 
Format makalah knsi 2013
Format makalah knsi 2013Format makalah knsi 2013
Format makalah knsi 2013Ratzman III
 
Basis Data, Ch 4 - Relasonal Aljabar & Calculus
Basis Data, Ch 4 - Relasonal Aljabar & CalculusBasis Data, Ch 4 - Relasonal Aljabar & Calculus
Basis Data, Ch 4 - Relasonal Aljabar & CalculusRatzman III
 
Basis Data, Ch. 3 - Relational Model
Basis Data, Ch. 3 - Relational ModelBasis Data, Ch. 3 - Relational Model
Basis Data, Ch. 3 - Relational ModelRatzman III
 

Más de Ratzman III (20)

Review Artikel Tinjauan Pustaka
Review Artikel Tinjauan PustakaReview Artikel Tinjauan Pustaka
Review Artikel Tinjauan Pustaka
 
Arduino - Ch 2: Sunrise-Sunset Light Switch
Arduino - Ch 2: Sunrise-Sunset Light SwitchArduino - Ch 2: Sunrise-Sunset Light Switch
Arduino - Ch 2: Sunrise-Sunset Light Switch
 
Arduino - CH 1: The Trick Switch
Arduino - CH 1: The Trick SwitchArduino - CH 1: The Trick Switch
Arduino - CH 1: The Trick Switch
 
Bab 3 - Kalkulus Relasional
Bab 3 -  Kalkulus RelasionalBab 3 -  Kalkulus Relasional
Bab 3 - Kalkulus Relasional
 
Bab 2 Aljabar Relasional
Bab 2   Aljabar RelasionalBab 2   Aljabar Relasional
Bab 2 Aljabar Relasional
 
Bab 1 RDBMS Review
Bab 1   RDBMS ReviewBab 1   RDBMS Review
Bab 1 RDBMS Review
 
Kisi kisi basis data uts
Kisi kisi basis data utsKisi kisi basis data uts
Kisi kisi basis data uts
 
Kisi kisi basis data uts
Kisi kisi basis data utsKisi kisi basis data uts
Kisi kisi basis data uts
 
Modul my sql tutorial part 6
Modul my sql tutorial part 6Modul my sql tutorial part 6
Modul my sql tutorial part 6
 
Nilai lab 01pt3
Nilai lab 01pt3Nilai lab 01pt3
Nilai lab 01pt3
 
Format sap
Format sapFormat sap
Format sap
 
Tugas i
Tugas iTugas i
Tugas i
 
Modul my sql tutorial part 5
Modul my sql tutorial part 5Modul my sql tutorial part 5
Modul my sql tutorial part 5
 
1088
10881088
1088
 
1152
11521152
1152
 
Pengabdian 2
Pengabdian 2Pengabdian 2
Pengabdian 2
 
Format Pengabdian Masyarakat
Format Pengabdian MasyarakatFormat Pengabdian Masyarakat
Format Pengabdian Masyarakat
 
Format makalah knsi 2013
Format makalah knsi 2013Format makalah knsi 2013
Format makalah knsi 2013
 
Basis Data, Ch 4 - Relasonal Aljabar & Calculus
Basis Data, Ch 4 - Relasonal Aljabar & CalculusBasis Data, Ch 4 - Relasonal Aljabar & Calculus
Basis Data, Ch 4 - Relasonal Aljabar & Calculus
 
Basis Data, Ch. 3 - Relational Model
Basis Data, Ch. 3 - Relational ModelBasis Data, Ch. 3 - Relational Model
Basis Data, Ch. 3 - Relational Model
 

Último

ICS 2208 Lecture Slide Notes for Topic 6
ICS 2208 Lecture Slide Notes for Topic 6ICS 2208 Lecture Slide Notes for Topic 6
ICS 2208 Lecture Slide Notes for Topic 6Vanessa Camilleri
 
Using Grammatical Signals Suitable to Patterns of Idea Development
Using Grammatical Signals Suitable to Patterns of Idea DevelopmentUsing Grammatical Signals Suitable to Patterns of Idea Development
Using Grammatical Signals Suitable to Patterns of Idea Developmentchesterberbo7
 
4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptxmary850239
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmStan Meyer
 
How to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 DatabaseHow to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 DatabaseCeline George
 
31 ĐỀ THI THỬ VÀO LỚP 10 - TIẾNG ANH - FORM MỚI 2025 - 40 CÂU HỎI - BÙI VĂN V...
31 ĐỀ THI THỬ VÀO LỚP 10 - TIẾNG ANH - FORM MỚI 2025 - 40 CÂU HỎI - BÙI VĂN V...31 ĐỀ THI THỬ VÀO LỚP 10 - TIẾNG ANH - FORM MỚI 2025 - 40 CÂU HỎI - BÙI VĂN V...
31 ĐỀ THI THỬ VÀO LỚP 10 - TIẾNG ANH - FORM MỚI 2025 - 40 CÂU HỎI - BÙI VĂN V...Nguyen Thanh Tu Collection
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfVanessa Camilleri
 
Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17Celine George
 
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptx
Unraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptxUnraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptx
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptxDhatriParmar
 
Congestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentationCongestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentationdeepaannamalai16
 
Indexing Structures in Database Management system.pdf
Indexing Structures in Database Management system.pdfIndexing Structures in Database Management system.pdf
Indexing Structures in Database Management system.pdfChristalin Nelson
 
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDecoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDhatriParmar
 
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnvESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnvRicaMaeCastro1
 
Narcotic and Non Narcotic Analgesic..pdf
Narcotic and Non Narcotic Analgesic..pdfNarcotic and Non Narcotic Analgesic..pdf
Narcotic and Non Narcotic Analgesic..pdfPrerana Jadhav
 
Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operationalssuser3e220a
 
Scientific Writing :Research Discourse
Scientific  Writing :Research  DiscourseScientific  Writing :Research  Discourse
Scientific Writing :Research DiscourseAnita GoswamiGiri
 
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...DhatriParmar
 
Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1GloryAnnCastre1
 

Último (20)

ICS 2208 Lecture Slide Notes for Topic 6
ICS 2208 Lecture Slide Notes for Topic 6ICS 2208 Lecture Slide Notes for Topic 6
ICS 2208 Lecture Slide Notes for Topic 6
 
Using Grammatical Signals Suitable to Patterns of Idea Development
Using Grammatical Signals Suitable to Patterns of Idea DevelopmentUsing Grammatical Signals Suitable to Patterns of Idea Development
Using Grammatical Signals Suitable to Patterns of Idea Development
 
4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx
 
prashanth updated resume 2024 for Teaching Profession
prashanth updated resume 2024 for Teaching Professionprashanth updated resume 2024 for Teaching Profession
prashanth updated resume 2024 for Teaching Profession
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and Film
 
How to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 DatabaseHow to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 Database
 
31 ĐỀ THI THỬ VÀO LỚP 10 - TIẾNG ANH - FORM MỚI 2025 - 40 CÂU HỎI - BÙI VĂN V...
31 ĐỀ THI THỬ VÀO LỚP 10 - TIẾNG ANH - FORM MỚI 2025 - 40 CÂU HỎI - BÙI VĂN V...31 ĐỀ THI THỬ VÀO LỚP 10 - TIẾNG ANH - FORM MỚI 2025 - 40 CÂU HỎI - BÙI VĂN V...
31 ĐỀ THI THỬ VÀO LỚP 10 - TIẾNG ANH - FORM MỚI 2025 - 40 CÂU HỎI - BÙI VĂN V...
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdf
 
Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17
 
Faculty Profile prashantha K EEE dept Sri Sairam college of Engineering
Faculty Profile prashantha K EEE dept Sri Sairam college of EngineeringFaculty Profile prashantha K EEE dept Sri Sairam college of Engineering
Faculty Profile prashantha K EEE dept Sri Sairam college of Engineering
 
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptx
Unraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptxUnraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptx
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptx
 
Congestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentationCongestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentation
 
Indexing Structures in Database Management system.pdf
Indexing Structures in Database Management system.pdfIndexing Structures in Database Management system.pdf
Indexing Structures in Database Management system.pdf
 
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDecoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
 
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnvESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
 
Narcotic and Non Narcotic Analgesic..pdf
Narcotic and Non Narcotic Analgesic..pdfNarcotic and Non Narcotic Analgesic..pdf
Narcotic and Non Narcotic Analgesic..pdf
 
Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operational
 
Scientific Writing :Research Discourse
Scientific  Writing :Research  DiscourseScientific  Writing :Research  Discourse
Scientific Writing :Research Discourse
 
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
 
Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1
 

10.1.1.194.6071

  • 1. The Effect of Scope Changes on Project Duration Extensions Extended Abstract of a PhD Dissertation1 Moshe Ayal Faculty of Management, Tel Aviv University, Tel Aviv 69978 Abstract The objective of this research is twofold: first to construct and validate an explanatory model for project duration extensions, and second to analyze the effect of scope changes and other related drivers on project delivery times. The research is based on a field study, which draws data from an engineering service environment, and uses means of structural equation modeling for analysis. The model contributes to a better understanding of the effect of various scope changes on project duration, and enables the construction of a practical tool for estimating project duration. Introduction Projects frequently finish late and over budget, thus causing organizations heavy penalties and damage their prestige. Moreover, as projects are hardly ever completed without introducing changes to their original baseline plan, a major challenge is to accurately estimate the project delivery time, while understanding the effects of other factors that create the discrepancy between estimated and actual project completion times. Thus, the intention in this work is to quantify the factors affecting duration extensions, an issue that has barely been addressed in the literature. One way to quantify these factors is by generating a descriptive empirical model that includes the major behavioral and quantitative measures of performance. Literature The section reviews the following themes: (1) duration estimation, the basis of duration extension measures, (2) possible generators of duration extensions, and (3) scope changes, and their effect on project performance. Duration Estimation. The tools most commonly used are based upon mathematical models in which task duration is explained by technical parameters of the task and the experience of the executing entity. Well known examples of these tools are SLIM (Putnam, 1978), and COCOMO Softwares (Boehm, 1981; Boehm et al., 2000). Burt and Kemp (1991) proposed predicting task duration from knowledge about durations of categories of tasks. However, here a potential bias exists, known in the psychology literature as the planning fallacy, due to the tendency of individuals to underestimate the amount of time needed to complete a given project. In the words of Buehler, Griffin and Ross (1994), they tend to focus on the future, ignoring past experience. Duration Extensions Generators. Several generators are discussed in the literature. Levy and Globerson (1997) implemented concepts from queuing theory for reducing the impact of waiting periods of critical work packages on the delivery times of projects executed in parallel. Goldratt (1997) claimed that task splitting, whether planned or results from preemptive processing might lead to severe duration extensions. Shenhar (2001) classified technological uncertainty into four levels, correlating them with overall project duration. Shenhar et al. (2002) also claimed that 1 Thesis Supervisor: Prof. Shlomo Globerson
  • 2. EFFECT OF SCOPE CHANGES ON PROJECT DURATION EXTENSIONS - MOSHE AYAL 2 projects high in uncertainty must be managed differently, employing means to reduce the uncertainty. Low experience with technology often results in what we term low structured projects (Applegate, Austin, and McFarlan, 2003) where risk mitigation is of great need. Based on surveys, Chan and Kumaraswamy (2002) mentioned: (1) impractical design, (2) labor shortages, (3) poor performance, (5) unforeseen conditions, and (6) poor communication. Still, literature lacks empirical quantifications of the effects of the above-mentioned generators on project duration. Scope Changes. Modification to the agreed upon scope (PMBOK, 2000) are considered as inherent in the nature of projects because of their complexity and the inevitable appearance of unforeseen problems (Ertel, 2000). The evidence shows that scope changes have a significant impact on the cost of projects. Chick (1999) showed that the later a change occurs in a project the more effect it will have on the project’s cost, and also mentioned a possible effect on project schedule. Kauffmann et al. (2002) used the earned value method in quantifying scope change ‘magnitude’ for cost adjustments. Barry et al. (2002) showed a correlation between software project duration and effort. However, a thorough investigation of the effect of scope changes on project duration has not yet been conducted. Research Design Figure 1 illustrates the hypothesized work package duration extensions model. The model includes three exogenous variables: (1) Technological Uncertainty, (2) Project Priority, and (3) Unforeseen Stoppages. It also has six endogenous variables: (1) Additional Materials, which refers to inventory orders, and (2) Additional Labor, both resulting from scope changes, and marked inside a dashed box; (3) Waiting in Line; (4) Preemptive Processing; (5) Stoppage Period, and (6) the main dependent variable: Duration Extension, which refers to a work package. Figure 1. Hypothesized Work Package Duration Extensions Model Unforeseen Stoppages Project Priority Preemptive Processing Waiting in Line Duration Extension Stoppage Period Technological Uncertainty H1 H2 H3 (H7) (H6) H5 H4 Additional Materials Additional Labor Table 1 summarizes the proposed model variables and the rationale for their selection.
  • 3. EFFECT OF SCOPE CHANGES ON PROJECT DURATION EXTENSIONS - MOSHE AYAL 3 Table 1. Proposed Model Variables Variable Description Rationale Technological Uncertainty Level of technological uncertainty associated with a certain work package Technological uncertainty is correlated with duration (Shenhar, 2001) Project Priority Priorities assigned to projects by top management team May decrease duration extensions by reducing waiting periods Unforeseen Stoppages Number of unforeseen operational stoppages caused by internal or external sources A greater number of operational stoppages may increase in-process duration Stoppage Period Total time periods of operational stoppages caused by internal or external sources Longer periods of operational stoppages may increase in-process duration Additional Materials Number of material orders resulting from scope changes Waiting until materials arrival, if filing for an external supply, may increase the duration Additional Labor Additional labor resulting from scope changes Scope changes could affect duration (Chick, 1999) Waiting in Line Time from the arrival of a work package to the beginning of its processing Waiting periods may extend delivery times (Levy and Globerson, 1997) Preemptive Processing Number of breaks during processing a work package Task splitting increases in-process duration (Goldratt, 1997) Duration Extension Work package in-process duration extension relative to planned duration The main dependent variable of the research Table 2 provides five hypotheses that are derived directly from the duration extensions model, based on its flow. The sixth hypothesis involves two exogenous variables, not included in the model for reasons of parsimony: (1) Internal Scope Changes, and (2) External Scope Changes. The seventh hypothesis is indicated by a correlation in the duration extensions model, and is tested separately within the projects’ framework. Table 2. Hypotheses Variable Effect on Variable Rationale H1 Additional Labor + Duration Extension Additional labor calls for resources, which in many cases are not currently available H2 Additional Materials + Duration Extension In-process duration extensions may result from having to wait until materials arrive H3 Preemptive Processing + Duration Extension Goldratt's (1997) claim that splitting a task results in extending its in- process duration H4 Additional Labor + Preemptive Processing Work package manager needs to wait for available resources and/or materials to arrive H5 Waiting in Line - Preemptive Processing The negative effect of waiting periods can be decreased by working intensively and continuously External Scope Changes ++ Internal Scope Changes + H7 Technological Uncertainty + Project Priority Allocating priority to a project may help in rapidly mitigating the uncertainties in its work packages Work package managers who introduce scope changes try to avoid material orders and use in stock materials, so as not to wait for the materials to arrive. Thus, external scope changes are expected to have a greater effect on material orders than Internal scope changes Additional Materials H6
  • 4. EFFECT OF SCOPE CHANGES ON PROJECT DURATION EXTENSIONS - MOSHE AYAL 4 Analysis. We analyze the model using means of structural equation modeling (SEM) in order to elicit the partial correlations amongst the variables, and to establish the causal relations. Two of the variables are dummy ones: (1) Project Priority, which takes the value of ‘1’ for prioritized project, and ‘0’ otherwise, and (2) Technological Uncertainty, which takes the value of ‘1’ for work package with technological uncertainty, and ‘0’ otherwise. We conduct linear multiple regression in examining Hypothesis 6, and use means of binomial regression to test Hypothesis 7, on the effect of technological uncertainty on project priority. We use the EQS software package (Byrne, 1994) for conducting the SEM analysis. In order to bring all data to the same reference point, the model’s variables, except for the dummies, are divided by the planned duration of the work package. Data collection. The study draws data from 714 work packages comprising the 56 systems engineering projects being performed at the time by a leading engineering services corporation. The projects ranged in value from several thousand dollars to one hundred thousand dollars, while the work packages comprising these projects ranged in duration from several days to a month. The projects had a sequential PERT/CPM structure, thus above 90% of the work packages where critical. Top management team, department managers, project managers and professional section managers were involved in data gathering. They used an interactive data collection interface, which was part of the project control system of the corporation. Results Table 3 shows the means, standard deviations, variables ranges and bivariate correlations for the variables of the proposed model. Note that in some cases total labor hours invested in a work package were decreased as a result of scope changes. However, in our data it was the rare case, as most of the time scope changes resulted in additional labor, which sometimes accumulated to as high as several hundreds of percents of the allocated labor hours! Table 3. Descriptive Statistics and Pearson Correlation Matrix Variables Mean s.d. Min Max 1 2 3 4 5 6 7 8 1 Tech. Uncertainty 0.29 0.46 0 1 2 Project Priority 0.37 0.48 0 1 .22** 3 Unforeseen Stoppages 0.04 0.10 0 0.5 -.08* -.02 4 Stoppage Period 0.10 0.36 0 6.5 -.05 -.05 .53** 5 Additional Materials 0.02 0.06 0 0.5 .18** .04 .01 -.01 6 Additional Labor 0.23 0.63 -0.47 7 .29** .06 -.03 -.05 .54** 7 Waiting in Line 0.30 0.29 0 1.5 -.08* -.21** -.003 .002 .03 .12** 8 Preemptive Processing 0.15 0.14 0 1 .09* .01 .28** .08* .11** .27** -.05 9 Duration Extension 0.31 0.68 -0.66 7 .11** -.08* .31** .60** .41** .48** .28** .25** Note . n=714 (work packages) * p < .05 ** p < .01
  • 5. EFFECT OF SCOPE CHANGES ON PROJECT DURATION EXTENSIONS - MOSHE AYAL 5 Model Fit. Using structural equation modeling means of analysis, the hypothesized model of work package duration extensions is found significant: 6.322 =χ , with 18 degrees of freedom, which rejects the null model hypothesis. In addition, the goodness of fit indices: NFI=0.98; NNFI=0.98; CFI=0.99; and RMSEA=0.034 (for n=714 work packages), indicating a good fit of the model to the data (Bagozzi & Yi, 1988; Bagozzi & Yi, 1989). Hypotheses 1 to 5. From the partial correlations given in Table 4, Hypotheses 1 to 5 are seen to have statistical significance. Note that two of the hypothesized relations are proved not to be significant: (1) additional material orders affect preemptive processing, but only indirectly, via the resulted additional labor; and (2) project priority affects duration extension only indirectly, via shorter waiting in line periods. In addition, out of the three correlations tested, only the one between project priority and technological uncertainty is found significant (r =0.22). Table 4. Direct Relations in the Work Packages Duration Extensions Model Hyp. From To Standardized coefficients t-values H1 Additional Labor Duration Extension .34 13.49 H2 Additional Materials Duration Extension .21 8.80 Waiting in Line Duration Extension .23 10.92 H3 Preemptive Processing Duration Extension .10 4.81 Stoppage Period Duration Extension .61 29.83 Project Priority Duration Extension -.03 -1.62(*) Technological Uncertainty Additional Labor .20 6.38 Additional Materials Additional Labor .51 16.36 Technological Uncertainty Additional Materials .18 4.82 Project Priority Waiting in Line -.21 -5.74 Unforeseen Stoppages Preemptive Processing .23 8.44 H4 Additional Labor Preemptive Processing .32 7.76 Additional Materials Preemptive Processing -.06 -1.46(*) H5 Waiting in Line Preemptive Processing -.08 -2.31 Unforeseen Stoppages Stoppage Period .53 16.62 Note. n=714; NFI=0.98; NNFI=0.98; CFI=0.99; RMSEA=0.034. (*) path not significant Duration Prediction. Using means of linear multiple regression, we derive a mathematical model for the prediction of work package duration based on its predetermined variables, performance variables, and disruptions like forced stoppages and scope changes (R2 =0.71). Table 5 shows the predictors of the best-fitting model. Note that if we ignore the two scope changes variables – additional material orders, and additional labor - we explain only 51% of the variance in the duration extension. Conducting a partial F-test we again confirm the hypothesis that the two variables representing scope changes are significant in the model.
  • 6. EFFECT OF SCOPE CHANGES ON PROJECT DURATION EXTENSIONS - MOSHE AYAL 6 Table 5. Predictors of Work Package Duration Extentions Models: Predictor Estimate St. Error Estimate St. Error Project Priority -0.039 0.039 Technological Uncertainty 0.218 0.041 Unforeseen Stoppages -0.470* 0.214 Stoppage Period 1.159** 0.039 1.188** 0.059 Additional Materials 2.466** 0.282 Additional Labor 0.363** 0.027 Waiting in Line 0.552** 0.049 0.686** 0.063 Preemptive Processing 0.519** 0.107 1.133** 0.139 Intercept -0.171** 0.026 -0.212** 0.038 R^2 0.707 0.513 Adj. R^2 0.705 0.509 Note . n=714. Partial F test for Model(2) = 328, p<0.001 * p < .05 ** p < .01 (1) Best Fitting (2) without Scope Changes Hypothesis 6. To test Hypothesis 6, on the effects of internal and external scope changes on additional material orders, we regressed the additional material orders against the number of external and internal scope changes, dividing both by the planned duration, as with all the variables. The results showed in Table 6 indicate that external scope changes result in a significantly higher amount of material orders than do internal scope changes. Note, however, that the number of internal and external scope changes is almost the same. Table 6. Additional Material Orders by Number of External and Internal Scope Changes Predictor Number Estimate St. Error Internal Scope Changes 113 0.065** 0.02 External Scope Changes 120 0.267** 0.021 Intercept 0.003 0.002 R^2 0.19 Adj. R^2 0.187 Note . n=714 (work packages) ** p < .01 Hypothesis 7. Figure 2 shows the number of prioritized and non-prioritized projects by the number of work packages with technological uncertainty. The data shows that the majority of the projects of five or more work packages with technological uncertainty are prioritized. To formally corroborate Hypothesis 7, we regressed project priority against the number of work packages with technological uncertainty in the project, using means of binomial regression.
  • 7. EFFECT OF SCOPE CHANGES ON PROJECT DURATION EXTENSIONS - MOSHE AYAL 7 Figure 2. Prioritized and Non-Prioritized Projects by Work Packages with Technological Uncertainty 0 5 10 15 20 0-1 2-3 4 5 6-11 Work Packages with Technological Uncertainty Projects Regular Projects Prioritized Projects Table 7 presents the results of the binomial regression, which indicate that a project consists of five or more work packages with technological uncertainties is likely to get priority by top management. This might shed some new light on the way top management reduces technological uncertainties in projects. Table 7. Project Priority by Number of Work Packages with Technological Uncertainties Predictor Estimate St. Error Significance Technological Uncertainty 0.88 0.26 0.001 Intercept -4.19 1.13 0.001 -2LL 45.88 Note . n=56 (projects). Implications and Conclusions Functional Level. Functional managers usually do not have a picture of the entire projects. Rather they see various work packages arriving from different project managers that must be processed according to certain priority rules. The model developed here can help them to better assess the effects of the various disruptions that occur while the work packages are being processed. They can also use the model to compensate for duration extensions, thus enabling better performance of overall workload.
  • 8. EFFECT OF SCOPE CHANGES ON PROJECT DURATION EXTENSIONS - MOSHE AYAL 8 Project / Multi-Project Level. At the project level, we should distinguish between critical work packages that need to be tightly controlled, and non-critical work packages. At the multi-project level, top management has to differentiate between prioritized and non-prioritized projects, giving top priority to critical work packages belonging to prioritized projects. This will assure that the projects with the highest priority will be delivered on time. The proposed model assesses the effect of unforeseen disruptions on critical work packages of high-priority projects, and provides better tools for estimating final duration and compensating for delays. Summary The study contributes to an improved understanding of duration extensions and their causes, by quantifying scope changes, differentiating amongst the various types of scope changes, and constructing an integrated model of work package duration extensions. The study pointed to the greater effect of external scope changes, compared with internal ones, on material orders, and thus on the total duration extensions. Generally, the model can be implemented for forecasting work package duration extensions, and estimating the effect on the project’s duration. Finally, several implications at the functional, the project, and the multi-project levels are suggested. Acknowledgments This work is based on my PhD dissertation, supervised by Prof S. Globerson. I wish to expresses my gratitude to him, and to all whose insights have contributed to this thesis. References Applegate, L.M., Austin, R.D., & McFarlan, F.W. 2003 Corporate Information Strategy and Management: Text and Cases. NY: McGraw-Hill Irwin. Bagozzi, R.P., & Yi, Y. 1988. On the evaluation of structural equation models. Journal of Academy of Marketing Science, 16(1): 74–94. Bagozzi, R.P., & Yi, Y. 1989. On the use of structural equation models in experimental designs. Journal of Marketing Research, 26(3): 271–284. Barry, E.J., Mukhopadhyay, T., & Slaughter. S.A. 2002. Software Project Duration and Effort: An Empirical Study. Information Technology and Management, 3(1-2): 113-136. Boehm, B.W. 1981. Software engineering economics. Advances in computing science and technology. NJ: Prentice-Hall. Boehm, B.W., Horowitz, E., Madachy, R., Reifer, D., Clark, B.K., Steece, B., Brown, A.W., Chulani, S., & Abts, C. 2000. Software Cost Estimation with COCOMO II. NJ: Prentice Hall. Buehler, R., Griffin, D., & Ross, M. 1994. Exploring the "planning fallacy": Why people underestimate their task completion times. Journal of Personality and Social Psychology, 67: 366-381. Burt, C.D.B., & Kemp, S. 1991. Retrospective duration estimation of public events. Memory & Cognition, 19: 252-262.
  • 9. EFFECT OF SCOPE CHANGES ON PROJECT DURATION EXTENSIONS - MOSHE AYAL 9 Byrne B.M. 1994 Structural Equation Modeling with EQS and EQS/Windows. Newbury Park, CA: Sage Publications. Chan, D.W.M., & Kumaraswamy, M.M. 2002. Compressing construction durations: Lessons learned from Hong Kong building projects. International Journal of Project Management, 20(1): 23-35. Chick, D. 1999. The time value of project change. Cost Engineering, 41(6): 27-31. Ertel, D., & Rudner, S. 2000. Scope change negotiations: Are write-off inevitable? Consulting to Management, 11 (2): 3-8. Goldratt, E.M. 1997. Critical Chain. NY: North River Press. Kauffmann, P., Keating, C., & Considine, C. 2002. Using earned value methods to substantiate change-of-scope claims. Engineering Management Journal, 14(1): 13-20. Levy, N., & Globerson, S. 1997. Improving multi-project management by using queuing theory approach. Project Management Journal, 28(4): 40-46. Project Management Institute, 2000. A Guide to the Project Management Body of Knowledge (PMBOK Guide). Project Management Institute, Upper Darby, PA. Putnam, L.H. 1978. A general empirical solution to the macro software sizing and estimating problem. IEEE Transactions on Software Engineering, 4(4): 345-361. Shenhar, A.J. 2001. One size does not fit all projects - exploring classical contingency domains. Management Science, 47(3): 394-414. Shenhar, A.J., Tishler, A., Dvir, D., Lipovetsky, S., & Lechler. T. 2002. Refining the search for project success factors: A multivariate, typological approach. R & D Management, 32(2): 111- 126.