OPERATIONS
July, 2007
Writer: Bob Harvey
ROLLED PRODUCTS PRODUCTION
Rolled products under produced to budget by thirty-seven thousand cartons. The
greater driver of the result was impacted by an overspend on casual labour and
the ensuing additional negative financial recoveries impact of under producing to
budget.
Perini - Ran at 84.93% (increase of 11.12% on last month)
• Over the course of the month we incurred downtime for the following
main reasons: (see graph below also)
 48 hrs web breaks
 25 hrs scheduled maintenance
 23 hrs changeovers
 18 hrs Bundler cut seal problems
 16.5 hrs parent roll changes
• OEE ran at 33.41%. An increase of 3.57% on last month.
(56% Availability x 97% Quality Rate x 62% Performance rate).
The increase has come from small increases in availability and speed.
 Assigning the shift fitters to the Converting Technical Manager
to identify downtime issues. Further work needs to be done on
this item.
 The new line meetings is providing a good communication tool
and leading to more consistent setup of the line.
 The rollers for the Rewinder will be installed August 16. It is
expected this will give further improvements in speed.
• Engineering support (electrical) is still in need of dramatic escalation if
this is to improve. To date, Merino has been unsuccessful in this
venture. Additional downtime will be incurred from awaiting trained
electrical support until this problem has been rectified.
• Project V has unified the Senior Operators. They are working on a
cleaning regime sub-project and have identified the top five downtime
drivers.
 Paper quality
 Operator skills
 Parent roll changes
 Too many changeovers
 Set ups need to be optimised.
We should undervalue the feedback from the crews on this point. Their
viewpoints are backed up with facts and data. They know what the
problems are and are keen to be actively involved in the solutions.
June, 2007
• The majority of the negative financial result for this line is due to not
recovering to budget. This will continue until we have our workforce
trained and our line well supported by a well-informed engineering
team. We are currently working towards this goal as a “TEAM”. Perini
will arrive on August 20 to deliver advanced operating and
maintenance skills to our engineering and operating personnel. We
expect to see a lift in performance in the following weeks subsequent
this specialised training.
• Additionally a change in the rostering and scheduling of this line and
line 2 has allowed an above budget capacity opportunity. We expect
to fully utilise this increased capacity to deliver an above budget output
to the business. Line 2 is now operating 7 days / week and Jumbo is
operating Monday to Friday, 10hrs per day, plus Friday overtime.
DowntimebyReasonCode
0
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
32
34
36
38
40
42
44
46
48
50
52
Winder , Paper
tor n/ webbr eaks
Scheduled
maintenance
Changeover Changeover , f ine
tuning
Bundler poor cut
seal
ChangePaper
Reel
Other , f ur ther
descr iption
r equir ed
Wr apper ,
unknown
Shif t cleanup Bundler , unknown
Total
Months Jul Shif tRepDate (All) WCNoBPCS 1309
Sumof myTime
ReasonDesc
Drop More Series Fields Here
Refresh Date
D O WNT IME FO R J ULY 2007
T O P 10
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
110.00%
120.00%
Sum of Availability
Sum of QualityRate
Sum of Perf ormance
Sum of OEE
Linear (Sum of OEE)
WCNoBPCS 1309 Shif tRepItemNo (All) Shift RepShift (All) ShiftRepNo (All)
Shift RepDate
Dat a
Refres
h Data
O EE: J UNE 2 00 7
June, 2007
Jumbo Line – Ran at 54.98% efficiency
• The poor figures belie the result. This line was not scheduled to run
most of the month and was started up sporadically throughout the
month. With each start up comes a ramp up time of poor production.
No sooner had the line been settled, it was stopped so line 2 could run
out of stock products. This has been resolved with the introduction of
a new approach to scheduling the lines. In future this line will run Mon-
Fri 10hrs per day. The same operators will man it each day. This will
lead to consistent high efficiency runs.
Line 2 – Ran at 72.58% Efficiency.
• Efficiencies have dropped on this line during the month of July.
• In the first two weeks of the month, low sheet count products normally
scheduled on the Perini were moved to this line. It has been many
years since these products were run on this line and as such we
experienced set up and consistency issues throughout the weeks.
These issues will subside as more Perini products are moved onto
Line 2 and established settings can be determined.
• The changes to the roster did not deliver the expected lift in
performance. Key issues for this were the skills of operators were not
yet at the required level and each time the line was restarted we
incurred downtime issues relating to getting the line to operate
consistently. The change in roster in August allowing the line to run
24/7 with not stops to run the jumbo we expect will allow operators to
gain more experience in running the line due to the extended hours of
operational contact.
• Worn gearing on the Rewinder is limiting production by impeding line
speed. These parts arrived and are scheduled to be installed in the
first week of August. We will see and increase of 30% output on the
higher sheet count products such as 500, 850 & 1000 sheet rolls.
• The new roster allowing full time operation 7days per week with a
stable crew will allow us to focus our training more aptly. During July
the training and development focus was on the Jumbo as there were
skill deficiencies there.
Labour summary
• Two additional employees have been recruited to facilitate an above
budget increase in capacity for line 2 and Perini.
• The production lines will carry additional personnel to facilitate an
intensive training programme during July. The additional personnel will
be fazed out in early August and shift leaders will cover absent
employees whenever possible to reduce casual labour costs.
Quality
• There were 33 ncr’s submitted. The greatest impact came from electrical
failures in the mill which engineering are still attempting to resolve. The
other significant ncr reason and cost was due to poor quality paper from
the mill leading to two days of downtime on the Perini line alone. Costs
June, 2007
incurred include $5000 due to paper quality issues and $9,000 from
electrical failures on the mill.
Environmental
Resource Reduction Programme (R.R.P.)
Plastic: The implementation of a plastic recycling regime has not been
implemented. Alternative recyclers where interviewed during June with
the intention for a single company to manage all our waste streams. A
decision as to the successful tender is still outstanding with closure
expected this coming month.
Water Efficiency Team (W.E.T.)
Brad Storey is managing this project currently. See his report.
June, 2007

Más contenido relacionado

Destacado (9)

Assessment Criteria - Menegatti
Assessment Criteria - MenegattiAssessment Criteria - Menegatti
Assessment Criteria - Menegatti
 
NRFPRESENTATIONNEWSAIP1finallypresentation13july
NRFPRESENTATIONNEWSAIP1finallypresentation13julyNRFPRESENTATIONNEWSAIP1finallypresentation13july
NRFPRESENTATIONNEWSAIP1finallypresentation13july
 
Pp toddler temper tantrums
Pp toddler temper tantrumsPp toddler temper tantrums
Pp toddler temper tantrums
 
Eco by teeratorn
Eco by teeratornEco by teeratorn
Eco by teeratorn
 
Hydraulic accumulator
Hydraulic accumulatorHydraulic accumulator
Hydraulic accumulator
 
Fct
FctFct
Fct
 
SUPERCRITICAL FUEL INJECTION-A PROMISING TECHNOLOGY FOR IMPROVED FUEL EFFICIE...
SUPERCRITICAL FUEL INJECTION-A PROMISING TECHNOLOGY FOR IMPROVED FUEL EFFICIE...SUPERCRITICAL FUEL INJECTION-A PROMISING TECHNOLOGY FOR IMPROVED FUEL EFFICIE...
SUPERCRITICAL FUEL INJECTION-A PROMISING TECHNOLOGY FOR IMPROVED FUEL EFFICIE...
 
2 stroke cycle engines
2 stroke cycle engines2 stroke cycle engines
2 stroke cycle engines
 
Pressure die casting
Pressure die castingPressure die casting
Pressure die casting
 

Similar a Board report August 07

Rich_Elwell_Resume & successes_
Rich_Elwell_Resume & successes_Rich_Elwell_Resume & successes_
Rich_Elwell_Resume & successes_Richard Elwell
 
05262016 resume
05262016 resume05262016 resume
05262016 resumeDan Faust
 
Julian Kalac lean 6 sigma project list--2018
 Julian Kalac lean 6 sigma  project list--2018 Julian Kalac lean 6 sigma  project list--2018
Julian Kalac lean 6 sigma project list--2018Julian Kalac P.Eng
 
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.Raheem Arif
 
IRJET- Last Planner System
IRJET- Last Planner SystemIRJET- Last Planner System
IRJET- Last Planner SystemIRJET Journal
 
Invest NI Lean Conference 2016 | Case Study: AES | Our lean journey
Invest NI Lean Conference 2016 | Case Study: AES | Our lean journeyInvest NI Lean Conference 2016 | Case Study: AES | Our lean journey
Invest NI Lean Conference 2016 | Case Study: AES | Our lean journeyInvest Northern Ireland
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining CellIRJET Journal
 
MGMT 6103 - Control Phase- CMCC
MGMT 6103 - Control Phase- CMCCMGMT 6103 - Control Phase- CMCC
MGMT 6103 - Control Phase- CMCCLeonard Burch
 
Upstream optimization: How continuous improvement methods are having a positi...
Upstream optimization: How continuous improvement methods are having a positi...Upstream optimization: How continuous improvement methods are having a positi...
Upstream optimization: How continuous improvement methods are having a positi...Argo, Inc.
 
Upstream optimization: How continuous improvement methods are having a positi...
Upstream optimization: How continuous improvement methods are having a positi...Upstream optimization: How continuous improvement methods are having a positi...
Upstream optimization: How continuous improvement methods are having a positi...Tara Bilby
 
Executive Summarization (Maria Hu)
Executive Summarization (Maria Hu)Executive Summarization (Maria Hu)
Executive Summarization (Maria Hu)Marina Hu
 
My Resume 2008
My Resume 2008My Resume 2008
My Resume 2008SteveSpiva
 
Service Improvement Plans.pdf
Service Improvement Plans.pdfService Improvement Plans.pdf
Service Improvement Plans.pdfBoris Berovic
 
Discovering Lean at Hewlett Packard Laserjet Division
Discovering Lean at Hewlett Packard Laserjet DivisionDiscovering Lean at Hewlett Packard Laserjet Division
Discovering Lean at Hewlett Packard Laserjet DivisionIrina Dzhambazova
 
My CV Aug 2016 - v1
My CV Aug 2016 - v1My CV Aug 2016 - v1
My CV Aug 2016 - v1Mark Fulker
 
Audie Maxey Resume
Audie Maxey ResumeAudie Maxey Resume
Audie Maxey ResumeAudie Maxey
 
Business Plan Sample By Alan Ray
Business Plan Sample By Alan RayBusiness Plan Sample By Alan Ray
Business Plan Sample By Alan RayAlan Ray
 

Similar a Board report August 07 (20)

Rich_Elwell_Resume & successes_
Rich_Elwell_Resume & successes_Rich_Elwell_Resume & successes_
Rich_Elwell_Resume & successes_
 
05262016 resume
05262016 resume05262016 resume
05262016 resume
 
Julian Kalac lean 6 sigma project list--2018
 Julian Kalac lean 6 sigma  project list--2018 Julian Kalac lean 6 sigma  project list--2018
Julian Kalac lean 6 sigma project list--2018
 
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
 
IRJET- Last Planner System
IRJET- Last Planner SystemIRJET- Last Planner System
IRJET- Last Planner System
 
Invest NI Lean Conference 2016 | Case Study: AES | Our lean journey
Invest NI Lean Conference 2016 | Case Study: AES | Our lean journeyInvest NI Lean Conference 2016 | Case Study: AES | Our lean journey
Invest NI Lean Conference 2016 | Case Study: AES | Our lean journey
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining Cell
 
MGMT 6103 - Control Phase- CMCC
MGMT 6103 - Control Phase- CMCCMGMT 6103 - Control Phase- CMCC
MGMT 6103 - Control Phase- CMCC
 
Sachin_Deshpande
Sachin_DeshpandeSachin_Deshpande
Sachin_Deshpande
 
Sachin_Deshpande
Sachin_DeshpandeSachin_Deshpande
Sachin_Deshpande
 
Upstream optimization: How continuous improvement methods are having a positi...
Upstream optimization: How continuous improvement methods are having a positi...Upstream optimization: How continuous improvement methods are having a positi...
Upstream optimization: How continuous improvement methods are having a positi...
 
Upstream optimization: How continuous improvement methods are having a positi...
Upstream optimization: How continuous improvement methods are having a positi...Upstream optimization: How continuous improvement methods are having a positi...
Upstream optimization: How continuous improvement methods are having a positi...
 
JM Industries PVF
JM Industries PVFJM Industries PVF
JM Industries PVF
 
Executive Summarization (Maria Hu)
Executive Summarization (Maria Hu)Executive Summarization (Maria Hu)
Executive Summarization (Maria Hu)
 
My Resume 2008
My Resume 2008My Resume 2008
My Resume 2008
 
Service Improvement Plans.pdf
Service Improvement Plans.pdfService Improvement Plans.pdf
Service Improvement Plans.pdf
 
Discovering Lean at Hewlett Packard Laserjet Division
Discovering Lean at Hewlett Packard Laserjet DivisionDiscovering Lean at Hewlett Packard Laserjet Division
Discovering Lean at Hewlett Packard Laserjet Division
 
My CV Aug 2016 - v1
My CV Aug 2016 - v1My CV Aug 2016 - v1
My CV Aug 2016 - v1
 
Audie Maxey Resume
Audie Maxey ResumeAudie Maxey Resume
Audie Maxey Resume
 
Business Plan Sample By Alan Ray
Business Plan Sample By Alan RayBusiness Plan Sample By Alan Ray
Business Plan Sample By Alan Ray
 

Board report August 07

  • 1. OPERATIONS July, 2007 Writer: Bob Harvey ROLLED PRODUCTS PRODUCTION Rolled products under produced to budget by thirty-seven thousand cartons. The greater driver of the result was impacted by an overspend on casual labour and the ensuing additional negative financial recoveries impact of under producing to budget. Perini - Ran at 84.93% (increase of 11.12% on last month) • Over the course of the month we incurred downtime for the following main reasons: (see graph below also)  48 hrs web breaks  25 hrs scheduled maintenance  23 hrs changeovers  18 hrs Bundler cut seal problems  16.5 hrs parent roll changes • OEE ran at 33.41%. An increase of 3.57% on last month. (56% Availability x 97% Quality Rate x 62% Performance rate). The increase has come from small increases in availability and speed.  Assigning the shift fitters to the Converting Technical Manager to identify downtime issues. Further work needs to be done on this item.  The new line meetings is providing a good communication tool and leading to more consistent setup of the line.  The rollers for the Rewinder will be installed August 16. It is expected this will give further improvements in speed. • Engineering support (electrical) is still in need of dramatic escalation if this is to improve. To date, Merino has been unsuccessful in this venture. Additional downtime will be incurred from awaiting trained electrical support until this problem has been rectified. • Project V has unified the Senior Operators. They are working on a cleaning regime sub-project and have identified the top five downtime drivers.  Paper quality  Operator skills  Parent roll changes  Too many changeovers  Set ups need to be optimised. We should undervalue the feedback from the crews on this point. Their viewpoints are backed up with facts and data. They know what the problems are and are keen to be actively involved in the solutions. June, 2007
  • 2. • The majority of the negative financial result for this line is due to not recovering to budget. This will continue until we have our workforce trained and our line well supported by a well-informed engineering team. We are currently working towards this goal as a “TEAM”. Perini will arrive on August 20 to deliver advanced operating and maintenance skills to our engineering and operating personnel. We expect to see a lift in performance in the following weeks subsequent this specialised training. • Additionally a change in the rostering and scheduling of this line and line 2 has allowed an above budget capacity opportunity. We expect to fully utilise this increased capacity to deliver an above budget output to the business. Line 2 is now operating 7 days / week and Jumbo is operating Monday to Friday, 10hrs per day, plus Friday overtime. DowntimebyReasonCode 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 Winder , Paper tor n/ webbr eaks Scheduled maintenance Changeover Changeover , f ine tuning Bundler poor cut seal ChangePaper Reel Other , f ur ther descr iption r equir ed Wr apper , unknown Shif t cleanup Bundler , unknown Total Months Jul Shif tRepDate (All) WCNoBPCS 1309 Sumof myTime ReasonDesc Drop More Series Fields Here Refresh Date D O WNT IME FO R J ULY 2007 T O P 10 0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% 80.00% 90.00% 100.00% 110.00% 120.00% Sum of Availability Sum of QualityRate Sum of Perf ormance Sum of OEE Linear (Sum of OEE) WCNoBPCS 1309 Shif tRepItemNo (All) Shift RepShift (All) ShiftRepNo (All) Shift RepDate Dat a Refres h Data O EE: J UNE 2 00 7 June, 2007
  • 3. Jumbo Line – Ran at 54.98% efficiency • The poor figures belie the result. This line was not scheduled to run most of the month and was started up sporadically throughout the month. With each start up comes a ramp up time of poor production. No sooner had the line been settled, it was stopped so line 2 could run out of stock products. This has been resolved with the introduction of a new approach to scheduling the lines. In future this line will run Mon- Fri 10hrs per day. The same operators will man it each day. This will lead to consistent high efficiency runs. Line 2 – Ran at 72.58% Efficiency. • Efficiencies have dropped on this line during the month of July. • In the first two weeks of the month, low sheet count products normally scheduled on the Perini were moved to this line. It has been many years since these products were run on this line and as such we experienced set up and consistency issues throughout the weeks. These issues will subside as more Perini products are moved onto Line 2 and established settings can be determined. • The changes to the roster did not deliver the expected lift in performance. Key issues for this were the skills of operators were not yet at the required level and each time the line was restarted we incurred downtime issues relating to getting the line to operate consistently. The change in roster in August allowing the line to run 24/7 with not stops to run the jumbo we expect will allow operators to gain more experience in running the line due to the extended hours of operational contact. • Worn gearing on the Rewinder is limiting production by impeding line speed. These parts arrived and are scheduled to be installed in the first week of August. We will see and increase of 30% output on the higher sheet count products such as 500, 850 & 1000 sheet rolls. • The new roster allowing full time operation 7days per week with a stable crew will allow us to focus our training more aptly. During July the training and development focus was on the Jumbo as there were skill deficiencies there. Labour summary • Two additional employees have been recruited to facilitate an above budget increase in capacity for line 2 and Perini. • The production lines will carry additional personnel to facilitate an intensive training programme during July. The additional personnel will be fazed out in early August and shift leaders will cover absent employees whenever possible to reduce casual labour costs. Quality • There were 33 ncr’s submitted. The greatest impact came from electrical failures in the mill which engineering are still attempting to resolve. The other significant ncr reason and cost was due to poor quality paper from the mill leading to two days of downtime on the Perini line alone. Costs June, 2007
  • 4. incurred include $5000 due to paper quality issues and $9,000 from electrical failures on the mill. Environmental Resource Reduction Programme (R.R.P.) Plastic: The implementation of a plastic recycling regime has not been implemented. Alternative recyclers where interviewed during June with the intention for a single company to manage all our waste streams. A decision as to the successful tender is still outstanding with closure expected this coming month. Water Efficiency Team (W.E.T.) Brad Storey is managing this project currently. See his report. June, 2007