SlideShare una empresa de Scribd logo
1 de 39
www.wizardea.com | contact@wizardea.com
B. M. Shahrier Majumder, PMP
PMP® Exam Preparation
Project Time Management
www.wizardea.com | contact@wizardea.com
Learning Objectives
Upon completion of this topic you will learn about
– The processes, activities and documentation items for Project
Time Management
– Elements (and deliverables) for Project Time Management
– Tools and techniques of the key activities of the Project Time
Management
3
www.wizardea.com | contact@wizardea.com
Time Management
Project Time Management includes the processes required
to accomplish timely completion of the project.
4
www.wizardea.com | contact@wizardea.com
Key Activities of Time Management
• Define Activities: The process of identifying the specific
actions to be performed to produce the project
deliverables.
• Sequence Activities: The process of identifying and
documenting relationships among the project activities.
• Estimate Activity Resource: The process of estimating the
type and qualities of material, people, equipment, or
supplies required to perform each activities.
5
www.wizardea.com | contact@wizardea.com
Key Activities of Time Management
• Estimate Activity Duration: The process of approximating
the number of work periods needed to complete individual
activities with specific resources.
• Develop Schedule: The process of analyzing activity
sequences, durations, resource requirements, and
schedule constrains to create the project schedule.
• Control Schedule: The process of monitoring the status of
the project to update project progress and managing
changes to the schedule baseline.
6
www.wizardea.com | contact@wizardea.com
Define Activities | Data Flow Diagram
7
7
Diagram Source | PMBOK 4th Edition
www.wizardea.com | contact@wizardea.com
Define Activities
Inputs Tools & Techniques Outputs
Scope baseline
Enterprise environmental
factors
Organizational process
assets
Decomposition
Rolling wave planning
Templates
Expert judgment
Activity list
Activity attributes
Milestone list
8
8
www.wizardea.com | contact@wizardea.com
Define Activities > Tools and Techniques
 Rolling Wave Planning
 Rolling wave planning is a form of progressive elaboration planning
where the work to be accomplished in the near term is planned in
detail at a low level of WBS, while work far in the future is planned for
the WBS components that are at relatively high level of the WBS.
 Templates
 A standard activity list or a portion of activity list from a
previous project is often usable as a template for new project.
9
www.wizardea.com | contact@wizardea.com
Define Activities > Outputs
 Activity List
 Activity list is a comprehensive list including all schedule activities required on the
project.
 Activity Attributes
 Activity attributes extend the description of the activity by identifying the multiple
components associated with each activity.
 The component of each activity evolve over time.
 During the initial stages of the project they include the Activity ID, WBS ID, and
activity name, and when completed may include activity codes, activity description,
predecessor activities, successor activities, logical relationships, leads and lags,
resource requirements, imposed dates, constrain and assumptions.
 Milestone List
 A milestone is a significant point or event in the project.
10
www.wizardea.com | contact@wizardea.com
Sequence Activities | Data Flow Diagram
11
11
Diagram Source | PMBOK 4th Edition
www.wizardea.com | contact@wizardea.com
Sequence Activities
Inputs Tools & Techniques Outputs
Activity list
Activity attributes
Milestone list
Project scope statement
Organization process
assets
Precedence diagramming
method (PDM)
Dependency determination
Appling leads and lags
Schedule network template
Project schedule network
diagram
Project document
(updates)
12
12
www.wizardea.com | contact@wizardea.com
Sequence Activities > Tools and Techniques
Activity
A
Activity
B
Finish to Start (FS) Relationship
Activity
A
Activity
B
Start to Start (SS) Relationship
Activity
A
Activity
B
Finish to Finish (FF) Relationship
Activity
A
Activity
B
Start to Finish (SF) Relationship
• Precedence diagramming method (PDM)
• PDM is a method used in Critical Path Methodology (CPM) for constructing a project
schedule network diagram that uses boxes or rectangular, referred to as nodes, to
represent activities and connect them with arrows that show the logical relationships
that exists between them.
13
www.wizardea.com | contact@wizardea.com
Sequence Activities > Tools and Techniques
 Dependency Determination
 Mandatory dependency
 Discretionary dependency
 External dependency
 Appling Leads and Lags
 A lead allows an acceleration of a successor activity
 A lag directs a delay in the successor activity
14
Activity
A
Activity
B
L=3
FS Relationship: The Start of B must lag (L)
the Finish of A by 3 days
Activity
A
Activity
B
L=4
SS Relationship: The Start of B must lag (L)
the Start of A by 4 days
Activity
A
Activity
B
L=5
FF Relationship: The Finish of B must lag (L)
the Finish of A by 5 days
Activity
A
Activity
B
L=6
SF Relationship: The Finish of B must lag (L)
the Start of A by 6 days
www.wizardea.com | contact@wizardea.com
Sequence Activities > Outputs
 Network Diagram
Any schematic display of the logical relationships of Project Activities.
Always drawn from left to right to reflect project chronology. Often
incorrectly referred to as a “PERT Chart”.
 Network Diagram Rules of Thumbs
There is a starting point
There is an ending point
There are predecessors for all activities
There are successors for all activities (no hangers!)
There are no loops
15
www.wizardea.com | contact@wizardea.com
Estimate Activity Resources | Data Flow Diagram
16
16
Diagram Source | PMBOK 4th Edition
www.wizardea.com | contact@wizardea.com
Estimate Activity Resource
Inputs Tools & Techniques Outputs
Activity lists
Activity attributes
Resource calendars
Enterprise environmental
factors
Organizational process
assets
Expert judgment
Alternative analysis
Published estimation data
Bottom-up estimating
Project management
software
Activity resource
requirements
Resource breakdown
structure
Project document updates
17
www.wizardea.com | contact@wizardea.com
Estimate Activity Resource > Inputs
• Resource Calendars
• A calendar that documents the working and nonworking days that
determine the dates that a resource is available or not.
18
www.wizardea.com | contact@wizardea.com
Estimate Activity Resource > Outputs
• Activity Resource Requirement
• An identification and description of the types of quantities of
resources required for each schedule activity in a work package
• Resource Breakdown Structure
• A hierarchical structure of identified resources by resource category
and type
19
www.wizardea.com | contact@wizardea.com
Estimate Activity Duration | Data Flow Diagram
20
Diagram Source | PMBOK 4th Edition
www.wizardea.com | contact@wizardea.com
Estimate Activity Durations
Inputs Tools & Techniques Outputs
Activity lists
Activity attributes
Activity resource
requirement
Resource calendar
Project scope statement
Enterprise environmental
factors
Organizational process
assets
Expert judgment
Analogous estimation
Parametric estimating
Three point estimates
Reserve analysis
Activity duration estimates
Project document updates
21
21
www.wizardea.com | contact@wizardea.com
Estimate Activity Durations
• Activity Effort and Duration
Total Time = Duration
Not working Time on Tasks
Actual Working on Tasks = Effort
22
22
www.wizardea.com | contact@wizardea.com
Estimate Activity Durations > Tools and
Techniques
 Analogous Estimating
 Top down estimating, uses actual duration of activities from previous projects
 Parametric Estimating
 Top down estimating, activity duration can be uses a mathematical model to
determine estimates
 Estimating the basis for activity duration can be quantitatively determine by multiply
the quantity of work to be performed by the productivity rate. e.g. Function Point
Estimation, Use Case Estimation.
 Three Point Estimating
 Estimating an average of the most likely, optimistic, pessimistic estimated duration.
23
www.wizardea.com | contact@wizardea.com
Estimate Activity Durations > Tools and
Techniques
 Multi Point Estimating (PERT)
Program Evaluation and Review Technique (PERT)
Calculation:
 Mean = (P + 4M + O)/6
 Standard Deviation = (P-O)/6
 Variance = ((P-O)/6)2
Here, P = Pessimistic Estimation, O = Optimistic Estimation and M = Most likely Estimation
 Reserve Analysis
Called time reserve, contingency, or buffer
Purpose – To add time to individual activities or the overall project
duration for schedule risks
Accumulated for the project and included in the project contingency
fund or management reserve
Note: Authors discourage adding time to individual activities since this is a form of padding
24
www.wizardea.com | contact@wizardea.com
• Complete the table using the formulas of PERT
25
Activity O M P Expected
Duration
Activity
Standard
deviation
Range of the
Estimates
A 14 27 47
B 41 60 89
C 39 44 48
D 29 37 42
www.wizardea.com | contact@wizardea.com
• What do you need before you try to develop a schedule
for your project?
26
www.wizardea.com | contact@wizardea.com
Develop Schedule | Data Flow Diagram
27
Diagram Source | PMBOK 4th Edition
www.wizardea.com | contact@wizardea.com
Develop Schedule
Inputs Tools & Techniques Outputs
Activity lists
Activity attributes
Project schedule network
diagrams
Activity resource
requirement
Resource calendar
Activity duration estimates
Project scope statement
Enterprise environmental
factors
Organizational process
assets
Schedule network analysis
Critical path method
Critical chain method
Resource leveling
What-if scenario analysis
Adjusting leads and lags
Schedule compression
Schedule model
Project schedule
Schedule baseline
Schedule data
Project document updates
28
28
www.wizardea.com | contact@wizardea.com
Develop Schedule > Tools and Techniques
• Critical Path Method (CPM)
• Critical Path Method (CPM), is a procedure for using network analysis
to identify those tasks which are on the critical path: ie where any delay
in the completion of these tasks will lengthen the project timescale,
unless action is taken.
• For all tasks off the critical path, a degree of tolerance is possible (eg.
late start, late completion, early start, etc.).
• Network charts and CPM analysis used to be carried out by hand.
• Software is now available which requires the user only to enter the
tasks, duration of each task and dependencies upon other tasks; a
network chart and CPM is then automatically created.
29
www.wizardea.com | contact@wizardea.com
Develop Schedule > Tools and Techniques
• Why Critical Path Method (CPM)
• The CPM formally identifies tasks which must be completed on time
for the whole project to be completed on time
• Identifies which tasks can be delayed for a while if resource needs to
be reallocated to catch up on missed tasks
• It helps you to identify the minimum length of time needed to
complete a project
• The CPM determines both the early start and the late start date for
each activity in the schedule.
30
www.wizardea.com | contact@wizardea.com
Develop Schedule > Tools and Techniques
• How to Use CPM
SAMPLE
Task ID Duration Dependency
A 7
B 3
C 6 A
D 3 B
E 3 D, F
F 2 B
G 3 C
H 2 E, G
31
31
www.wizardea.com | contact@wizardea.com
Develop Schedule > Tools and Techniques
• Calculating the Forward Pass
32
32
www.wizardea.com | contact@wizardea.com
Schedule Development >> Tools and
Techniques
• Calculating the Backward Pass
33
33
www.wizardea.com | contact@wizardea.com
Develop Schedule >> Tools and Techniques
• Calculating the Critical Path
34
34
www.wizardea.com | contact@wizardea.com
Develop Schedule > Tools and Techniques
• Critical Chain Method (CCM)
• Critical Chain Method (CCM), is a schedule network analysis
techniques that modifies the project schedule to account for limited
resources.
• Initially, the project schedule network diagram is built using duration
estimates with required dependencies and defined constrains as input.
The critical path is then calculated. After the critical path is designed,
resource availability is entered and the resource-limited schedule result
is determined. The resulting schedule often has an altered critical path.
35
www.wizardea.com | contact@wizardea.com
Control Schedule | Data Flow Diagram
36
Diagram Source | PMBOK 4th Edition
www.wizardea.com | contact@wizardea.com
Control Schedule
Inputs Tools & Techniques Outputs
Schedule management
plan
Project Schedule
Work performance
information
Organization process
assets
Performance reviews
Variance analysis
Project management
software
Resource leveling
What-if scenario analysis
Adjusting leads and lags
Progress reporting
Schedule compression
Scheduling tool
Work performance
measurements
Organizational process assets
updates
Change requests
Project management plan
updates
Project document updates
37
37
www.wizardea.com | contact@wizardea.com
Control Schedule > Tools and Techniques
• Progress reporting
• Actual Start and Finish Dates
• Remaining duration for unfinished tasks
• Percent completion (from Earned Value Analysis)
• Schedule Change Control System
• Part of Integrated Change Control
• Performance Measurements
• Schedule Variance (SV), Schedule Performance Index (SPI) (from
Earned Value Analysis)
• Schedule Comparison Bar Charts
• Tracking Gantt
38
GetFREETemplatesatwww.wizardea.com
www.wizardea.com | contact@wizardea.com
Questions
39
• [mail.shahrier@gmail.com]
• http://bd.linkedin.com/in/shahrier

Más contenido relacionado

La actualidad más candente

2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
Irefuser1
 

La actualidad más candente (20)

Project integration management
Project integration managementProject integration management
Project integration management
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
 
Pmi kenya starting a pmo
Pmi kenya starting a pmoPmi kenya starting a pmo
Pmi kenya starting a pmo
 
Project Management Course slide 1
Project Management Course slide 1Project Management Course slide 1
Project Management Course slide 1
 
Top 20 Best Project Management Software
Top 20 Best Project Management SoftwareTop 20 Best Project Management Software
Top 20 Best Project Management Software
 
Project Management slide 2
Project Management slide 2Project Management slide 2
Project Management slide 2
 
Project scope management
Project scope managementProject scope management
Project scope management
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
 
PMP Preparation 2 - Processes
PMP Preparation 2 - ProcessesPMP Preparation 2 - Processes
PMP Preparation 2 - Processes
 
Project integration management
Project integration managementProject integration management
Project integration management
 
PMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementPMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration Management
 
Planning process group
Planning process groupPlanning process group
Planning process group
 
10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
 
7.4 Control Costs
7.4 Control Costs7.4 Control Costs
7.4 Control Costs
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sample
 
Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...
 
Initiating a new project framework orientation: Innovate Vancouver
Initiating a new project framework orientation: Innovate VancouverInitiating a new project framework orientation: Innovate Vancouver
Initiating a new project framework orientation: Innovate Vancouver
 
NetCom Learning :The Ultimate Key to Project Managers Success - PMBOK Guide
NetCom Learning :The Ultimate Key to Project Managers Success - PMBOK GuideNetCom Learning :The Ultimate Key to Project Managers Success - PMBOK Guide
NetCom Learning :The Ultimate Key to Project Managers Success - PMBOK Guide
 

Destacado

Destacado (20)

04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
08 projectqualitymanagement
08 projectqualitymanagement08 projectqualitymanagement
08 projectqualitymanagement
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
09 projecthumanresourcemanagement
09 projecthumanresourcemanagement09 projecthumanresourcemanagement
09 projecthumanresourcemanagement
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
12 projectprocurementmanagement
12 projectprocurementmanagement12 projectprocurementmanagement
12 projectprocurementmanagement
 
PMP Preparation 1 - Framework
PMP Preparation 1 - FrameworkPMP Preparation 1 - Framework
PMP Preparation 1 - Framework
 
13 project control & closing management
13 project control & closing management13 project control & closing management
13 project control & closing management
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
10 projectcommunicationmanagement
10 projectcommunicationmanagement10 projectcommunicationmanagement
10 projectcommunicationmanagement
 
Project time management 1 final
Project time management 1 finalProject time management 1 final
Project time management 1 final
 
Chap013
Chap013Chap013
Chap013
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5
 
Project initiating and planning
Project initiating and planningProject initiating and planning
Project initiating and planning
 
Project Procurment Management
Project Procurment ManagementProject Procurment Management
Project Procurment Management
 
01 introductiontoframework
01 introductiontoframework01 introductiontoframework
01 introductiontoframework
 
Project communication management
Project communication managementProject communication management
Project communication management
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaOnline PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 

Similar a PMP Exam Preparation Course: 05 Project Time Management

Primavera6.0
Primavera6.0Primavera6.0
Primavera6.0
niict
 
L05 time management
L05 time managementL05 time management
L05 time management
Asa Chan
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptx
MohanadRabea1
 

Similar a PMP Exam Preparation Course: 05 Project Time Management (20)

Primavera6.0
Primavera6.0Primavera6.0
Primavera6.0
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
L05 time management
L05 time managementL05 time management
L05 time management
 
Time management
Time managementTime management
Time management
 
Pm short course
Pm short coursePm short course
Pm short course
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptx
 
3- Project Time Management.ppt
3- Project Time Management.ppt3- Project Time Management.ppt
3- Project Time Management.ppt
 
Session 5 4th edition PMP
Session 5 4th edition PMPSession 5 4th edition PMP
Session 5 4th edition PMP
 
Project Time Management ICTI.ppt
Project Time Management ICTI.pptProject Time Management ICTI.ppt
Project Time Management ICTI.ppt
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
tcc primavera
tcc primaveratcc primavera
tcc primavera
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
 
MIS Project management
MIS Project managementMIS Project management
MIS Project management
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Planning and Resourcing a Project
Planning and Resourcing a ProjectPlanning and Resourcing a Project
Planning and Resourcing a Project
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Management
 
PMP Training - Project Time Management Part 2
PMP Training - Project Time Management Part 2PMP Training - Project Time Management Part 2
PMP Training - Project Time Management Part 2
 
ASAP_Methodology.pptx
ASAP_Methodology.pptxASAP_Methodology.pptx
ASAP_Methodology.pptx
 
Chapter 4.pptx
Chapter 4.pptxChapter 4.pptx
Chapter 4.pptx
 
Chapter 3
Chapter 3Chapter 3
Chapter 3
 

Más de B M Shahrier Majumder, PMP, CSM (6)

PMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost ManagementPMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost Management
 
CMMI Appraisal Summary
CMMI Appraisal SummaryCMMI Appraisal Summary
CMMI Appraisal Summary
 
Southtech continues ISO 9001
Southtech continues ISO 9001Southtech continues ISO 9001
Southtech continues ISO 9001
 
Southtech Achieved CMMI L3
Southtech Achieved CMMI L3Southtech Achieved CMMI L3
Southtech Achieved CMMI L3
 
Software Quality Assurance
Software Quality AssuranceSoftware Quality Assurance
Software Quality Assurance
 
Information System Dashboard
Information System DashboardInformation System Dashboard
Information System Dashboard
 

Último

Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
KarakKing
 

Último (20)

On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 

PMP Exam Preparation Course: 05 Project Time Management

  • 1. www.wizardea.com | contact@wizardea.com B. M. Shahrier Majumder, PMP PMP® Exam Preparation
  • 3. www.wizardea.com | contact@wizardea.com Learning Objectives Upon completion of this topic you will learn about – The processes, activities and documentation items for Project Time Management – Elements (and deliverables) for Project Time Management – Tools and techniques of the key activities of the Project Time Management 3
  • 4. www.wizardea.com | contact@wizardea.com Time Management Project Time Management includes the processes required to accomplish timely completion of the project. 4
  • 5. www.wizardea.com | contact@wizardea.com Key Activities of Time Management • Define Activities: The process of identifying the specific actions to be performed to produce the project deliverables. • Sequence Activities: The process of identifying and documenting relationships among the project activities. • Estimate Activity Resource: The process of estimating the type and qualities of material, people, equipment, or supplies required to perform each activities. 5
  • 6. www.wizardea.com | contact@wizardea.com Key Activities of Time Management • Estimate Activity Duration: The process of approximating the number of work periods needed to complete individual activities with specific resources. • Develop Schedule: The process of analyzing activity sequences, durations, resource requirements, and schedule constrains to create the project schedule. • Control Schedule: The process of monitoring the status of the project to update project progress and managing changes to the schedule baseline. 6
  • 7. www.wizardea.com | contact@wizardea.com Define Activities | Data Flow Diagram 7 7 Diagram Source | PMBOK 4th Edition
  • 8. www.wizardea.com | contact@wizardea.com Define Activities Inputs Tools & Techniques Outputs Scope baseline Enterprise environmental factors Organizational process assets Decomposition Rolling wave planning Templates Expert judgment Activity list Activity attributes Milestone list 8 8
  • 9. www.wizardea.com | contact@wizardea.com Define Activities > Tools and Techniques  Rolling Wave Planning  Rolling wave planning is a form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail at a low level of WBS, while work far in the future is planned for the WBS components that are at relatively high level of the WBS.  Templates  A standard activity list or a portion of activity list from a previous project is often usable as a template for new project. 9
  • 10. www.wizardea.com | contact@wizardea.com Define Activities > Outputs  Activity List  Activity list is a comprehensive list including all schedule activities required on the project.  Activity Attributes  Activity attributes extend the description of the activity by identifying the multiple components associated with each activity.  The component of each activity evolve over time.  During the initial stages of the project they include the Activity ID, WBS ID, and activity name, and when completed may include activity codes, activity description, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constrain and assumptions.  Milestone List  A milestone is a significant point or event in the project. 10
  • 11. www.wizardea.com | contact@wizardea.com Sequence Activities | Data Flow Diagram 11 11 Diagram Source | PMBOK 4th Edition
  • 12. www.wizardea.com | contact@wizardea.com Sequence Activities Inputs Tools & Techniques Outputs Activity list Activity attributes Milestone list Project scope statement Organization process assets Precedence diagramming method (PDM) Dependency determination Appling leads and lags Schedule network template Project schedule network diagram Project document (updates) 12 12
  • 13. www.wizardea.com | contact@wizardea.com Sequence Activities > Tools and Techniques Activity A Activity B Finish to Start (FS) Relationship Activity A Activity B Start to Start (SS) Relationship Activity A Activity B Finish to Finish (FF) Relationship Activity A Activity B Start to Finish (SF) Relationship • Precedence diagramming method (PDM) • PDM is a method used in Critical Path Methodology (CPM) for constructing a project schedule network diagram that uses boxes or rectangular, referred to as nodes, to represent activities and connect them with arrows that show the logical relationships that exists between them. 13
  • 14. www.wizardea.com | contact@wizardea.com Sequence Activities > Tools and Techniques  Dependency Determination  Mandatory dependency  Discretionary dependency  External dependency  Appling Leads and Lags  A lead allows an acceleration of a successor activity  A lag directs a delay in the successor activity 14 Activity A Activity B L=3 FS Relationship: The Start of B must lag (L) the Finish of A by 3 days Activity A Activity B L=4 SS Relationship: The Start of B must lag (L) the Start of A by 4 days Activity A Activity B L=5 FF Relationship: The Finish of B must lag (L) the Finish of A by 5 days Activity A Activity B L=6 SF Relationship: The Finish of B must lag (L) the Start of A by 6 days
  • 15. www.wizardea.com | contact@wizardea.com Sequence Activities > Outputs  Network Diagram Any schematic display of the logical relationships of Project Activities. Always drawn from left to right to reflect project chronology. Often incorrectly referred to as a “PERT Chart”.  Network Diagram Rules of Thumbs There is a starting point There is an ending point There are predecessors for all activities There are successors for all activities (no hangers!) There are no loops 15
  • 16. www.wizardea.com | contact@wizardea.com Estimate Activity Resources | Data Flow Diagram 16 16 Diagram Source | PMBOK 4th Edition
  • 17. www.wizardea.com | contact@wizardea.com Estimate Activity Resource Inputs Tools & Techniques Outputs Activity lists Activity attributes Resource calendars Enterprise environmental factors Organizational process assets Expert judgment Alternative analysis Published estimation data Bottom-up estimating Project management software Activity resource requirements Resource breakdown structure Project document updates 17
  • 18. www.wizardea.com | contact@wizardea.com Estimate Activity Resource > Inputs • Resource Calendars • A calendar that documents the working and nonworking days that determine the dates that a resource is available or not. 18
  • 19. www.wizardea.com | contact@wizardea.com Estimate Activity Resource > Outputs • Activity Resource Requirement • An identification and description of the types of quantities of resources required for each schedule activity in a work package • Resource Breakdown Structure • A hierarchical structure of identified resources by resource category and type 19
  • 20. www.wizardea.com | contact@wizardea.com Estimate Activity Duration | Data Flow Diagram 20 Diagram Source | PMBOK 4th Edition
  • 21. www.wizardea.com | contact@wizardea.com Estimate Activity Durations Inputs Tools & Techniques Outputs Activity lists Activity attributes Activity resource requirement Resource calendar Project scope statement Enterprise environmental factors Organizational process assets Expert judgment Analogous estimation Parametric estimating Three point estimates Reserve analysis Activity duration estimates Project document updates 21 21
  • 22. www.wizardea.com | contact@wizardea.com Estimate Activity Durations • Activity Effort and Duration Total Time = Duration Not working Time on Tasks Actual Working on Tasks = Effort 22 22
  • 23. www.wizardea.com | contact@wizardea.com Estimate Activity Durations > Tools and Techniques  Analogous Estimating  Top down estimating, uses actual duration of activities from previous projects  Parametric Estimating  Top down estimating, activity duration can be uses a mathematical model to determine estimates  Estimating the basis for activity duration can be quantitatively determine by multiply the quantity of work to be performed by the productivity rate. e.g. Function Point Estimation, Use Case Estimation.  Three Point Estimating  Estimating an average of the most likely, optimistic, pessimistic estimated duration. 23
  • 24. www.wizardea.com | contact@wizardea.com Estimate Activity Durations > Tools and Techniques  Multi Point Estimating (PERT) Program Evaluation and Review Technique (PERT) Calculation:  Mean = (P + 4M + O)/6  Standard Deviation = (P-O)/6  Variance = ((P-O)/6)2 Here, P = Pessimistic Estimation, O = Optimistic Estimation and M = Most likely Estimation  Reserve Analysis Called time reserve, contingency, or buffer Purpose – To add time to individual activities or the overall project duration for schedule risks Accumulated for the project and included in the project contingency fund or management reserve Note: Authors discourage adding time to individual activities since this is a form of padding 24
  • 25. www.wizardea.com | contact@wizardea.com • Complete the table using the formulas of PERT 25 Activity O M P Expected Duration Activity Standard deviation Range of the Estimates A 14 27 47 B 41 60 89 C 39 44 48 D 29 37 42
  • 26. www.wizardea.com | contact@wizardea.com • What do you need before you try to develop a schedule for your project? 26
  • 27. www.wizardea.com | contact@wizardea.com Develop Schedule | Data Flow Diagram 27 Diagram Source | PMBOK 4th Edition
  • 28. www.wizardea.com | contact@wizardea.com Develop Schedule Inputs Tools & Techniques Outputs Activity lists Activity attributes Project schedule network diagrams Activity resource requirement Resource calendar Activity duration estimates Project scope statement Enterprise environmental factors Organizational process assets Schedule network analysis Critical path method Critical chain method Resource leveling What-if scenario analysis Adjusting leads and lags Schedule compression Schedule model Project schedule Schedule baseline Schedule data Project document updates 28 28
  • 29. www.wizardea.com | contact@wizardea.com Develop Schedule > Tools and Techniques • Critical Path Method (CPM) • Critical Path Method (CPM), is a procedure for using network analysis to identify those tasks which are on the critical path: ie where any delay in the completion of these tasks will lengthen the project timescale, unless action is taken. • For all tasks off the critical path, a degree of tolerance is possible (eg. late start, late completion, early start, etc.). • Network charts and CPM analysis used to be carried out by hand. • Software is now available which requires the user only to enter the tasks, duration of each task and dependencies upon other tasks; a network chart and CPM is then automatically created. 29
  • 30. www.wizardea.com | contact@wizardea.com Develop Schedule > Tools and Techniques • Why Critical Path Method (CPM) • The CPM formally identifies tasks which must be completed on time for the whole project to be completed on time • Identifies which tasks can be delayed for a while if resource needs to be reallocated to catch up on missed tasks • It helps you to identify the minimum length of time needed to complete a project • The CPM determines both the early start and the late start date for each activity in the schedule. 30
  • 31. www.wizardea.com | contact@wizardea.com Develop Schedule > Tools and Techniques • How to Use CPM SAMPLE Task ID Duration Dependency A 7 B 3 C 6 A D 3 B E 3 D, F F 2 B G 3 C H 2 E, G 31 31
  • 32. www.wizardea.com | contact@wizardea.com Develop Schedule > Tools and Techniques • Calculating the Forward Pass 32 32
  • 33. www.wizardea.com | contact@wizardea.com Schedule Development >> Tools and Techniques • Calculating the Backward Pass 33 33
  • 34. www.wizardea.com | contact@wizardea.com Develop Schedule >> Tools and Techniques • Calculating the Critical Path 34 34
  • 35. www.wizardea.com | contact@wizardea.com Develop Schedule > Tools and Techniques • Critical Chain Method (CCM) • Critical Chain Method (CCM), is a schedule network analysis techniques that modifies the project schedule to account for limited resources. • Initially, the project schedule network diagram is built using duration estimates with required dependencies and defined constrains as input. The critical path is then calculated. After the critical path is designed, resource availability is entered and the resource-limited schedule result is determined. The resulting schedule often has an altered critical path. 35
  • 36. www.wizardea.com | contact@wizardea.com Control Schedule | Data Flow Diagram 36 Diagram Source | PMBOK 4th Edition
  • 37. www.wizardea.com | contact@wizardea.com Control Schedule Inputs Tools & Techniques Outputs Schedule management plan Project Schedule Work performance information Organization process assets Performance reviews Variance analysis Project management software Resource leveling What-if scenario analysis Adjusting leads and lags Progress reporting Schedule compression Scheduling tool Work performance measurements Organizational process assets updates Change requests Project management plan updates Project document updates 37 37
  • 38. www.wizardea.com | contact@wizardea.com Control Schedule > Tools and Techniques • Progress reporting • Actual Start and Finish Dates • Remaining duration for unfinished tasks • Percent completion (from Earned Value Analysis) • Schedule Change Control System • Part of Integrated Change Control • Performance Measurements • Schedule Variance (SV), Schedule Performance Index (SPI) (from Earned Value Analysis) • Schedule Comparison Bar Charts • Tracking Gantt 38 GetFREETemplatesatwww.wizardea.com
  • 39. www.wizardea.com | contact@wizardea.com Questions 39 • [mail.shahrier@gmail.com] • http://bd.linkedin.com/in/shahrier