SlideShare una empresa de Scribd logo
1 de 32
Presenters:
   Glen Boswall, Partner, Clark Wilson LLP
Oliver C. Hanson, Associate, Clark Wilson LLP
   Samantha Ip, Partner, Clark Wilson LLP
Anna Sekunova, Associate, Clark Wilson LLP
 Satinder Sidhu, Associate, Clark Wilson LLP
Construction Defect Claims

      The Ins & Outs, The Do’s & Don’ts




                                 BUILDEX Vancouver
         Presented by Samantha Ip & Oliver C. Hanson
                                  February 14, 2013
Construction Defect Claims

• Dealing with construction deficiency claims
• A party’s responsibilities at law both in contract and in
  tort
• Damages
• Limitation periods
   – How long does a party have to commence a claim?
• Risk management




                                                              3
1. Breach of Contract

• A civil cause of action arising from the failure of one or
  more parties to the contract to perform his or her
  obligations under the contract
• In most contracts between the original building owner
  and the developer, there are express and implied
  warranties as to the quality of construction




                                                               4
1. Breach of Contract (cont’d)

• Express warranties
   – Written terms of the contract, which state the
     quality of construction
• Implied warranties
   – Implied terms of the contract that the construction
     work was performed in a good and workmanlike
     manner, and is free of defects




                                                           5
2. Negligence

• A failure to exercise the care that a reasonably prudent
  person would exercise in like circumstances
• Members of a construction team, including the
  developer and general contractor, may be found liable
  to an owner of a building for faulty construction where
  they have failed to meet a reasonable standard of care
  in performing their duties




                                                             6
2. Negligence (cont’d)

• A claim for negligence can be advanced by an original
  or subsequent owner of the building
• The leading Canadian case on liability to subsequent
  owners is Winnipeg Condominium Corporation No. 36 v.
  Bird Construction Co., which involved a 15 story
  apartment built in 1972, but where construction
  defects were not discovered until 1989




                                                          7
2. Negligence (cont’d)

• The Supreme Court of Canada held:
“[W]here a contractor (or any other person) is negligent
  in planning or constructing a building, and where that
  building is found to contain defects resulting from
  that negligence which pose a real and substantial
  danger to the occupants of the building, the
  reasonable costs of repairing the defects and putting
  the building back in a non-dangerous state are
  recoverable in tort by the occupants.” (emphasis
  added)



                                                           8
2. Negligence (cont’d)

• In terms of the standard that a contractor must
  conduct itself, the Court said:
“the duty in tort with respect to materials and
   workmanship flows from the contractor’s duty to
   ensure that the building meets a reasonable and safe
   standard of construction…”




                                                          9
2. Negligence (cont’d)

• The requirement of a “Dangerous Defect”
   – An owner cannot succeed in a claim against the
     developer or contractor in negligence to recover
     “pure economic loss”, i.e. costs to repair the alleged
     defects
   – UNLESS the alleged defects pose a real and
     substantial danger to the health and safety of the
     occupants of the building (the “Dangerous Defect”)




                                                              10
2. Negligence (cont’d)

• The requirement of a “Dangerous Defect”
   – It is not necessary that the alleged defects create an
     imminent risk of harm
   – In Roy v. Thiessen, the Saskatchewan Court of
     Queen’s Bench held that inadequate ventilation
     would eventually lead to rotting of trusses and
     beams, and that this was sufficient to constitute a
     dangerous defect




                                                              11
2. Negligence (cont’d)

• The requirement of a “Dangerous Defect”
   – In Carleton Condominium Corp. No. 21 v. Minto
     Construction Ltd., the court held that seismic
     deficiencies are “dangerous defects”
   – The judge acknowledged that minor deviations from
     a building code are normal and would not
     necessarily constitute a dangerous defect
   – Also raised the possibility of recovery based on
     policy reasons where no dangerous defect was
     found


                                                         12
3. Duty to Warn

• As part of a contractor’s duty to adhere to a standard of
  reasonable care in performing the construction work,
  the contractor also has a duty to warn of known
  dangers or deficiencies
• The usual situation in which the duty to warn will arise
  is where the issue relates to the safety or suitability of
  what the contractor was himself being asked to
  undertake




                                                               13
3. Duty to Warn (cont’d)

• In order to discharge a contractor’s duty to warn, the
  warning ought to meet the following requirements:
  a) The warning must be clear and complete;
  b) It must provide all current information regarding the risks
     and dangers;
  c) The warning must be explicit enough to give a full
     indication of the dangers;
  d) The explicitness of the warnings must be proportional to
     the severity of the danger; and
  e) The warning must be reasonably communicated and
     clearly presented.

                                                                   14
4. Negligent Misrepresentation

• A claim for negligent misrepresentation is based on an
  alleged promise by a developer that a building will be
  free of defects, comply with the applicable building
  code and bylaws, and otherwise be safe for the
  occupants of the building




                                                           15
4. Negligent Misrepresentation (cont’d)

• An owner of a building must establish five elements to be
  successful in a claim for negligent misrepresentation:
   –   There must be a duty of care based on a "special
       relationship" between the representor and the representee;
   –   The representation in question must be untrue, inaccurate
       or misleading;
   –   The representor must have acted negligently in making the
       misrepresentation;
   –   The representee must have relied, in a reasonable manner,
       on the negligent misrepresentation; and
   –   The reliance must have been detrimental to the representee
       in the sense that damages resulted.
                                                                   16
5. Damages

• Damages for breach of contract
   – The Plaintiff is to be put in the same position as it
     would have been had the contract been performed
     as agreed
   – Where a contractor is in breach of its contractual
     obligations, the owner is entitled to damages
     measured by the cost of making good the
     construction defects and omissions




                                                             17
5. Damages (cont’d)

• Damages for negligence
   – In Winnipeg Condominium, supra, the extent of the
     liability of contractors was described as follows:
   “Where negligence is established and such defects
    manifest themselves before any damage to persons
    or property occurs, they should, in my view, be
    liable for the reasonable cost of repairing the
    defects and putting the building back into a non-
    dangerous state”



                                                          18
5. Damages (cont’d)

• A developer or contractor will not be exposed to
  damages for breach of contract AND damages for
  negligence
• In addition to damages for direct losses, a developer or
  contractor may also be subject to an award of
  consequential damages, i.e. loss of profits, delay costs,
  etc.




                                                              19
5. Damages (cont’d)

• Method of assessing damages
   – The court may use one of two methods to assess
     damages:
      a) The diminution of market value, which measures
         the extent to which the deficiency has reduced the
         value of the building; or
      b) Cost of repairs.




                                                              20
5. Damages (cont’d)

• Method of assessing damages
   – The court will generally award damages on the basis
     of the cost of repairs if two conditions are met:
      a) The new owner has undertaken, or has satisfied the
         court that it will undertake the repairs; and
      b) The cost of repairs is reasonable in the
         circumstances.




                                                              21
5. Damages (cont’d)
• Method of assessing damages
   – Where an owner has not undertaken the repairs, a court may
     look at a number of factors when considering which method of
     calculating damages is more suitable, including:
      a) Is the proposed repair work necessary?
      b) Does the homeowner intend to perform the repairs?
      c) Is there sufficient evidence of the cost of the repairs on
         which to base a damage award?
      d) What is the diminution in value of the home as
         constructed?
      e) Is the cost of repair reasonable in relation to the
         diminution in value and the cost of the project?
                                                                  22
6. Limitation Periods

• The B.C. Limitation Act, RSBC 1996, c. 266 sets out the
  time period that an individual has to file a civil claim for
  construction defects
   – Claims for pure economic loss are 6 years
• Falling in line with reform that has already taken place
  throughout Canada, a new limitations statute, the
  Limitation Act, SBC 2012, c. 13, will come into force on
  June 1, 2013




                                                                 23
6. Limitation Periods (cont’d)

• The new Act sets a single limitation period of two years
  for most claims
• The two-year period begins to run when a claim is
  discovered
• A claim is discovered when a person knew, or
  reasonably ought to have known: (a) that the loss had
  occurred; (b) that the loss was caused by an act or
  omission; (c) the identity of the person responsible for
  the act or omission; and (d) that a court proceeding
  would be the appropriate course of action to remedy
  the loss

                                                             24
7. Risk Management

• Written agreement
  – Describes the rights and obligations of each party
     • Pricing
     • Schedule and timing
     • Quality standards
     • Payment and changes
     • Termination
     • Limitation of liability
     • Dispute resolution


                                                         25
7. Risk Management (cont’d)

• Read your agreement
• Know your agreement
• Follow your agreement




                              26
7. Risk Management (cont’d)

• Understand your legal rights outside of the agreement
   – Common law duties
   – Professional obligations
   – Statutory duties and obligations
   – Generally accepted construction standards




                                                          27
7. Risk Management (cont’d)

• Insurance
   – Insurance is intended to provide you with coverage
     when an unexpected incident occurs
   – Types of construction insurance: commercial general
     liability, professional liability and/or wrap-up liability
     insurance
   – Utilize an insurance broker




                                                                  28
7. Risk Management (cont’d)

• Insurance – Notice of a “Claim”
   – Always ensure that you give notice to your insurer
     (via your broker) of a claim or potential claim
   – What is a “claim”?
      • For a “claim” to be made there must be some form of
        communication of a demand for compensation or
        other form of reparation by a third party upon the
        insured, or at least communication by the third party
        to the insured of a clear intention to hold the insured
        responsible for the damages in question…



                                                                  29
7. Risk Management (cont’d)

• Construction team
   – The lowest bid may not be the best bid
   – You can avoid future cost and complications if you
     work with parties who have a good reputation in the
     industry, even if the party is not the least expensive




                                                              30
7. Risk Management (cont’d)

• Early resolution
   – The costs associated with construction deficiency
     and delay claims escalate over time
   – Attempt to resolve disputes early on by utilizing the
     alternative dispute resolution mechanisms in the
     contract, i.e. negotiation, mediation and/or
     arbitration




                                                             31
Please direct inquiries or comments to:
Samantha Ip, Partner, Clark Wilson LLP
ssi@cwilson.com | 604.643.3172
Oliver C. Hanson, Associate, Clark Wilson LLP
och@cwilson.com | 604.643.3120
www.cwilson.com




THANK YOU

Más contenido relacionado

La actualidad más candente

"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"Abhishek Shah
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreementabdmuhaiminyunus
 
Day-01_1025 Engineer's Roles and Risks - Adrias Tan
Day-01_1025 Engineer's Roles and Risks - Adrias TanDay-01_1025 Engineer's Roles and Risks - Adrias Tan
Day-01_1025 Engineer's Roles and Risks - Adrias TanAdrias TAN
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFrancis Ho
 
Contracts Management
Contracts Management Contracts Management
Contracts Management Mohib Ullah
 
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...HIMADRI BANERJI
 
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEotمحاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEotKhaled M. Al Kolfat MS.Eng,MoP,P3O,PMOC,PMP,M.ASCE
 
Building a New Home?
Building a New Home?Building a New Home?
Building a New Home?daholmes210
 
Rims Energy Session 2008
Rims Energy Session 2008Rims Energy Session 2008
Rims Energy Session 2008gabelugo
 
Dispute resolution technique
Dispute resolution techniqueDispute resolution technique
Dispute resolution techniqueSaad Ullah
 
Presentation Teush
Presentation TeushPresentation Teush
Presentation Teushsveki
 
Fidic contract administration
Fidic contract administrationFidic contract administration
Fidic contract administrationZabeel Institute
 
Fidic contract
Fidic contract Fidic contract
Fidic contract Yash Patel
 

La actualidad más candente (20)

"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreement
 
Day-01_1025 Engineer's Roles and Risks - Adrias Tan
Day-01_1025 Engineer's Roles and Risks - Adrias TanDay-01_1025 Engineer's Roles and Risks - Adrias Tan
Day-01_1025 Engineer's Roles and Risks - Adrias Tan
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
Eot
EotEot
Eot
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
 
Fidic
FidicFidic
Fidic
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
 
Contracts Management
Contracts Management Contracts Management
Contracts Management
 
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
 
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEotمحاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
 
Building a New Home?
Building a New Home?Building a New Home?
Building a New Home?
 
Rims Energy Session 2008
Rims Energy Session 2008Rims Energy Session 2008
Rims Energy Session 2008
 
Chapter 5 [compatibility mode]
Chapter 5 [compatibility mode]Chapter 5 [compatibility mode]
Chapter 5 [compatibility mode]
 
Dispute resolution technique
Dispute resolution techniqueDispute resolution technique
Dispute resolution technique
 
Presentation Teush
Presentation TeushPresentation Teush
Presentation Teush
 
Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]
 
Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]
 
Fidic contract administration
Fidic contract administrationFidic contract administration
Fidic contract administration
 
Fidic contract
Fidic contract Fidic contract
Fidic contract
 

Destacado

Plumbing system for training, 22.01.2017
Plumbing system for training, 22.01.2017Plumbing system for training, 22.01.2017
Plumbing system for training, 22.01.2017Krishnandu Barma
 
Construction site safety
Construction site safetyConstruction site safety
Construction site safetyDebajit Roy
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systemsAkshay Revekar
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADGLA University
 
Structural systems in high rise buildings
Structural systems in high rise buildingsStructural systems in high rise buildings
Structural systems in high rise buildingsKarthik Suresh
 

Destacado (6)

Plumbing system for training, 22.01.2017
Plumbing system for training, 22.01.2017Plumbing system for training, 22.01.2017
Plumbing system for training, 22.01.2017
 
Plumbing training
Plumbing training Plumbing training
Plumbing training
 
Construction site safety
Construction site safetyConstruction site safety
Construction site safety
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
 
Structural systems in high rise buildings
Structural systems in high rise buildingsStructural systems in high rise buildings
Structural systems in high rise buildings
 

Similar a Construction Defect Claims: The Ins & The Outs, The Do's & The Don'ts

Disputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptDisputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptNesrElhandasa1
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsFrancis Ho
 
Construction law lecture 10
Construction law lecture 10Construction law lecture 10
Construction law lecture 10Jessyca Than
 
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...Francis Ho
 
Utahcondolaw -- Construction Defects in Utah
Utahcondolaw -- Construction Defects in UtahUtahcondolaw -- Construction Defects in Utah
Utahcondolaw -- Construction Defects in Utahlwhobbs
 
Drafting Construction Contracts
Drafting Construction ContractsDrafting Construction Contracts
Drafting Construction ContractsMelissa Brumback
 
Chapter 20 – Product Liability
Chapter 20 – Product LiabilityChapter 20 – Product Liability
Chapter 20 – Product LiabilityUAF_BA330
 
The Masquerade Of Low Bids_Phillips
The Masquerade Of Low Bids_PhillipsThe Masquerade Of Low Bids_Phillips
The Masquerade Of Low Bids_PhillipsContract Cities
 
Collateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsCollateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsFrancis Ho
 
Understanding The role of The Consultant
Understanding The role of The ConsultantUnderstanding The role of The Consultant
Understanding The role of The ConsultantHarry Gusti Nugroho
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITIONByishimoBTCChef
 
Building Act, Code, Consenting and Failed Repairs - Dr Duncan Webb Lane Neave
Building Act, Code, Consenting and Failed Repairs - Dr Duncan Webb Lane NeaveBuilding Act, Code, Consenting and Failed Repairs - Dr Duncan Webb Lane Neave
Building Act, Code, Consenting and Failed Repairs - Dr Duncan Webb Lane NeaveEQCfix New Zealand
 
Remedies for Breach of Contract
Remedies for Breach of ContractRemedies for Breach of Contract
Remedies for Breach of ContractArissa Loh
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Melvin Lim
 
Recent Case Law Developments - 2014 Olswang Construction Law Conference
Recent Case Law Developments - 2014 Olswang Construction Law ConferenceRecent Case Law Developments - 2014 Olswang Construction Law Conference
Recent Case Law Developments - 2014 Olswang Construction Law ConferenceFrancis Ho
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011Maatla Moadi
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014SHKLaw
 

Similar a Construction Defect Claims: The Ins & The Outs, The Do's & The Don'ts (20)

Design liability
Design liabilityDesign liability
Design liability
 
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptDisputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction Projects
 
Construction law lecture 10
Construction law lecture 10Construction law lecture 10
Construction law lecture 10
 
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
 
Utahcondolaw -- Construction Defects in Utah
Utahcondolaw -- Construction Defects in UtahUtahcondolaw -- Construction Defects in Utah
Utahcondolaw -- Construction Defects in Utah
 
Drafting Construction Contracts
Drafting Construction ContractsDrafting Construction Contracts
Drafting Construction Contracts
 
Chapter 20 – Product Liability
Chapter 20 – Product LiabilityChapter 20 – Product Liability
Chapter 20 – Product Liability
 
The Masquerade Of Low Bids_Phillips
The Masquerade Of Low Bids_PhillipsThe Masquerade Of Low Bids_Phillips
The Masquerade Of Low Bids_Phillips
 
Collateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsCollateral Warranties and Third Party Rights
Collateral Warranties and Third Party Rights
 
Understanding The role of The Consultant
Understanding The role of The ConsultantUnderstanding The role of The Consultant
Understanding The role of The Consultant
 
Construction law cl3 (completed)
Construction law cl3 (completed)Construction law cl3 (completed)
Construction law cl3 (completed)
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Building Act, Code, Consenting and Failed Repairs - Dr Duncan Webb Lane Neave
Building Act, Code, Consenting and Failed Repairs - Dr Duncan Webb Lane NeaveBuilding Act, Code, Consenting and Failed Repairs - Dr Duncan Webb Lane Neave
Building Act, Code, Consenting and Failed Repairs - Dr Duncan Webb Lane Neave
 
Kandil_Sameh_AR50123
Kandil_Sameh_AR50123Kandil_Sameh_AR50123
Kandil_Sameh_AR50123
 
Remedies for Breach of Contract
Remedies for Breach of ContractRemedies for Breach of Contract
Remedies for Breach of Contract
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
 
Recent Case Law Developments - 2014 Olswang Construction Law Conference
Recent Case Law Developments - 2014 Olswang Construction Law ConferenceRecent Case Law Developments - 2014 Olswang Construction Law Conference
Recent Case Law Developments - 2014 Olswang Construction Law Conference
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 

Más de Samantha Ip

Pollution Exclusion
Pollution ExclusionPollution Exclusion
Pollution ExclusionSamantha Ip
 
Consultant Agreements and the Role of the Consultant
Consultant Agreements and the Role of the ConsultantConsultant Agreements and the Role of the Consultant
Consultant Agreements and the Role of the ConsultantSamantha Ip
 
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...Samantha Ip
 
Errors & Omissions Insurance Update: Brokers' E&O Exposure
Errors & Omissions Insurance Update: Brokers' E&O ExposureErrors & Omissions Insurance Update: Brokers' E&O Exposure
Errors & Omissions Insurance Update: Brokers' E&O ExposureSamantha Ip
 
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...Samantha Ip
 
Limitation Act Reform: The Canadian Perspective
Limitation Act Reform: The Canadian PerspectiveLimitation Act Reform: The Canadian Perspective
Limitation Act Reform: The Canadian PerspectiveSamantha Ip
 
When It Comes To Defence Costs, First Layer Is Usually The Payer
When It Comes To Defence Costs, First Layer Is Usually The PayerWhen It Comes To Defence Costs, First Layer Is Usually The Payer
When It Comes To Defence Costs, First Layer Is Usually The PayerSamantha Ip
 
CCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesCCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesSamantha Ip
 
Bad Faith Litigation in Canada: Much Ado About Nothing?
Bad Faith Litigation in Canada: Much Ado About Nothing?Bad Faith Litigation in Canada: Much Ado About Nothing?
Bad Faith Litigation in Canada: Much Ado About Nothing?Samantha Ip
 
E&O Insurance - An Update on Legal Issues
E&O Insurance - An Update on Legal IssuesE&O Insurance - An Update on Legal Issues
E&O Insurance - An Update on Legal IssuesSamantha Ip
 
Limitation Act Reform - The Canadian Perspective
Limitation Act Reform - The Canadian PerspectiveLimitation Act Reform - The Canadian Perspective
Limitation Act Reform - The Canadian PerspectiveSamantha Ip
 

Más de Samantha Ip (12)

Sports & Events
Sports & EventsSports & Events
Sports & Events
 
Pollution Exclusion
Pollution ExclusionPollution Exclusion
Pollution Exclusion
 
Consultant Agreements and the Role of the Consultant
Consultant Agreements and the Role of the ConsultantConsultant Agreements and the Role of the Consultant
Consultant Agreements and the Role of the Consultant
 
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...
 
Errors & Omissions Insurance Update: Brokers' E&O Exposure
Errors & Omissions Insurance Update: Brokers' E&O ExposureErrors & Omissions Insurance Update: Brokers' E&O Exposure
Errors & Omissions Insurance Update: Brokers' E&O Exposure
 
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...
 
Limitation Act Reform: The Canadian Perspective
Limitation Act Reform: The Canadian PerspectiveLimitation Act Reform: The Canadian Perspective
Limitation Act Reform: The Canadian Perspective
 
When It Comes To Defence Costs, First Layer Is Usually The Payer
When It Comes To Defence Costs, First Layer Is Usually The PayerWhen It Comes To Defence Costs, First Layer Is Usually The Payer
When It Comes To Defence Costs, First Layer Is Usually The Payer
 
CCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesCCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case Studies
 
Bad Faith Litigation in Canada: Much Ado About Nothing?
Bad Faith Litigation in Canada: Much Ado About Nothing?Bad Faith Litigation in Canada: Much Ado About Nothing?
Bad Faith Litigation in Canada: Much Ado About Nothing?
 
E&O Insurance - An Update on Legal Issues
E&O Insurance - An Update on Legal IssuesE&O Insurance - An Update on Legal Issues
E&O Insurance - An Update on Legal Issues
 
Limitation Act Reform - The Canadian Perspective
Limitation Act Reform - The Canadian PerspectiveLimitation Act Reform - The Canadian Perspective
Limitation Act Reform - The Canadian Perspective
 

Construction Defect Claims: The Ins & The Outs, The Do's & The Don'ts

  • 1. Presenters: Glen Boswall, Partner, Clark Wilson LLP Oliver C. Hanson, Associate, Clark Wilson LLP Samantha Ip, Partner, Clark Wilson LLP Anna Sekunova, Associate, Clark Wilson LLP Satinder Sidhu, Associate, Clark Wilson LLP
  • 2. Construction Defect Claims The Ins & Outs, The Do’s & Don’ts BUILDEX Vancouver Presented by Samantha Ip & Oliver C. Hanson February 14, 2013
  • 3. Construction Defect Claims • Dealing with construction deficiency claims • A party’s responsibilities at law both in contract and in tort • Damages • Limitation periods – How long does a party have to commence a claim? • Risk management 3
  • 4. 1. Breach of Contract • A civil cause of action arising from the failure of one or more parties to the contract to perform his or her obligations under the contract • In most contracts between the original building owner and the developer, there are express and implied warranties as to the quality of construction 4
  • 5. 1. Breach of Contract (cont’d) • Express warranties – Written terms of the contract, which state the quality of construction • Implied warranties – Implied terms of the contract that the construction work was performed in a good and workmanlike manner, and is free of defects 5
  • 6. 2. Negligence • A failure to exercise the care that a reasonably prudent person would exercise in like circumstances • Members of a construction team, including the developer and general contractor, may be found liable to an owner of a building for faulty construction where they have failed to meet a reasonable standard of care in performing their duties 6
  • 7. 2. Negligence (cont’d) • A claim for negligence can be advanced by an original or subsequent owner of the building • The leading Canadian case on liability to subsequent owners is Winnipeg Condominium Corporation No. 36 v. Bird Construction Co., which involved a 15 story apartment built in 1972, but where construction defects were not discovered until 1989 7
  • 8. 2. Negligence (cont’d) • The Supreme Court of Canada held: “[W]here a contractor (or any other person) is negligent in planning or constructing a building, and where that building is found to contain defects resulting from that negligence which pose a real and substantial danger to the occupants of the building, the reasonable costs of repairing the defects and putting the building back in a non-dangerous state are recoverable in tort by the occupants.” (emphasis added) 8
  • 9. 2. Negligence (cont’d) • In terms of the standard that a contractor must conduct itself, the Court said: “the duty in tort with respect to materials and workmanship flows from the contractor’s duty to ensure that the building meets a reasonable and safe standard of construction…” 9
  • 10. 2. Negligence (cont’d) • The requirement of a “Dangerous Defect” – An owner cannot succeed in a claim against the developer or contractor in negligence to recover “pure economic loss”, i.e. costs to repair the alleged defects – UNLESS the alleged defects pose a real and substantial danger to the health and safety of the occupants of the building (the “Dangerous Defect”) 10
  • 11. 2. Negligence (cont’d) • The requirement of a “Dangerous Defect” – It is not necessary that the alleged defects create an imminent risk of harm – In Roy v. Thiessen, the Saskatchewan Court of Queen’s Bench held that inadequate ventilation would eventually lead to rotting of trusses and beams, and that this was sufficient to constitute a dangerous defect 11
  • 12. 2. Negligence (cont’d) • The requirement of a “Dangerous Defect” – In Carleton Condominium Corp. No. 21 v. Minto Construction Ltd., the court held that seismic deficiencies are “dangerous defects” – The judge acknowledged that minor deviations from a building code are normal and would not necessarily constitute a dangerous defect – Also raised the possibility of recovery based on policy reasons where no dangerous defect was found 12
  • 13. 3. Duty to Warn • As part of a contractor’s duty to adhere to a standard of reasonable care in performing the construction work, the contractor also has a duty to warn of known dangers or deficiencies • The usual situation in which the duty to warn will arise is where the issue relates to the safety or suitability of what the contractor was himself being asked to undertake 13
  • 14. 3. Duty to Warn (cont’d) • In order to discharge a contractor’s duty to warn, the warning ought to meet the following requirements: a) The warning must be clear and complete; b) It must provide all current information regarding the risks and dangers; c) The warning must be explicit enough to give a full indication of the dangers; d) The explicitness of the warnings must be proportional to the severity of the danger; and e) The warning must be reasonably communicated and clearly presented. 14
  • 15. 4. Negligent Misrepresentation • A claim for negligent misrepresentation is based on an alleged promise by a developer that a building will be free of defects, comply with the applicable building code and bylaws, and otherwise be safe for the occupants of the building 15
  • 16. 4. Negligent Misrepresentation (cont’d) • An owner of a building must establish five elements to be successful in a claim for negligent misrepresentation: – There must be a duty of care based on a "special relationship" between the representor and the representee; – The representation in question must be untrue, inaccurate or misleading; – The representor must have acted negligently in making the misrepresentation; – The representee must have relied, in a reasonable manner, on the negligent misrepresentation; and – The reliance must have been detrimental to the representee in the sense that damages resulted. 16
  • 17. 5. Damages • Damages for breach of contract – The Plaintiff is to be put in the same position as it would have been had the contract been performed as agreed – Where a contractor is in breach of its contractual obligations, the owner is entitled to damages measured by the cost of making good the construction defects and omissions 17
  • 18. 5. Damages (cont’d) • Damages for negligence – In Winnipeg Condominium, supra, the extent of the liability of contractors was described as follows: “Where negligence is established and such defects manifest themselves before any damage to persons or property occurs, they should, in my view, be liable for the reasonable cost of repairing the defects and putting the building back into a non- dangerous state” 18
  • 19. 5. Damages (cont’d) • A developer or contractor will not be exposed to damages for breach of contract AND damages for negligence • In addition to damages for direct losses, a developer or contractor may also be subject to an award of consequential damages, i.e. loss of profits, delay costs, etc. 19
  • 20. 5. Damages (cont’d) • Method of assessing damages – The court may use one of two methods to assess damages: a) The diminution of market value, which measures the extent to which the deficiency has reduced the value of the building; or b) Cost of repairs. 20
  • 21. 5. Damages (cont’d) • Method of assessing damages – The court will generally award damages on the basis of the cost of repairs if two conditions are met: a) The new owner has undertaken, or has satisfied the court that it will undertake the repairs; and b) The cost of repairs is reasonable in the circumstances. 21
  • 22. 5. Damages (cont’d) • Method of assessing damages – Where an owner has not undertaken the repairs, a court may look at a number of factors when considering which method of calculating damages is more suitable, including: a) Is the proposed repair work necessary? b) Does the homeowner intend to perform the repairs? c) Is there sufficient evidence of the cost of the repairs on which to base a damage award? d) What is the diminution in value of the home as constructed? e) Is the cost of repair reasonable in relation to the diminution in value and the cost of the project? 22
  • 23. 6. Limitation Periods • The B.C. Limitation Act, RSBC 1996, c. 266 sets out the time period that an individual has to file a civil claim for construction defects – Claims for pure economic loss are 6 years • Falling in line with reform that has already taken place throughout Canada, a new limitations statute, the Limitation Act, SBC 2012, c. 13, will come into force on June 1, 2013 23
  • 24. 6. Limitation Periods (cont’d) • The new Act sets a single limitation period of two years for most claims • The two-year period begins to run when a claim is discovered • A claim is discovered when a person knew, or reasonably ought to have known: (a) that the loss had occurred; (b) that the loss was caused by an act or omission; (c) the identity of the person responsible for the act or omission; and (d) that a court proceeding would be the appropriate course of action to remedy the loss 24
  • 25. 7. Risk Management • Written agreement – Describes the rights and obligations of each party • Pricing • Schedule and timing • Quality standards • Payment and changes • Termination • Limitation of liability • Dispute resolution 25
  • 26. 7. Risk Management (cont’d) • Read your agreement • Know your agreement • Follow your agreement 26
  • 27. 7. Risk Management (cont’d) • Understand your legal rights outside of the agreement – Common law duties – Professional obligations – Statutory duties and obligations – Generally accepted construction standards 27
  • 28. 7. Risk Management (cont’d) • Insurance – Insurance is intended to provide you with coverage when an unexpected incident occurs – Types of construction insurance: commercial general liability, professional liability and/or wrap-up liability insurance – Utilize an insurance broker 28
  • 29. 7. Risk Management (cont’d) • Insurance – Notice of a “Claim” – Always ensure that you give notice to your insurer (via your broker) of a claim or potential claim – What is a “claim”? • For a “claim” to be made there must be some form of communication of a demand for compensation or other form of reparation by a third party upon the insured, or at least communication by the third party to the insured of a clear intention to hold the insured responsible for the damages in question… 29
  • 30. 7. Risk Management (cont’d) • Construction team – The lowest bid may not be the best bid – You can avoid future cost and complications if you work with parties who have a good reputation in the industry, even if the party is not the least expensive 30
  • 31. 7. Risk Management (cont’d) • Early resolution – The costs associated with construction deficiency and delay claims escalate over time – Attempt to resolve disputes early on by utilizing the alternative dispute resolution mechanisms in the contract, i.e. negotiation, mediation and/or arbitration 31
  • 32. Please direct inquiries or comments to: Samantha Ip, Partner, Clark Wilson LLP ssi@cwilson.com | 604.643.3172 Oliver C. Hanson, Associate, Clark Wilson LLP och@cwilson.com | 604.643.3120 www.cwilson.com THANK YOU