Topics of Discussion

l   Contracting Methods
l   Advantages and Disadvantages
l   Design/Build Subcontractors
l   Terminology
Types of Contracting Methods

l   Design/Build


l   Traditional (Design – Bid – Build)


l   Construction Manager (CM)
Contractual Relationships

 Design/Build



                 Owner



            Design/Builder



                          Contractors /
           A/E
                         Subcontractors
Design/Build Definition

l   Design/Build
     Method  where design and construction are a
      single source of responsibility for one entity.
     Design/Builder  may or may not self perform
      some or all of the design and construction work.
     Design/Builder  accountable from the earliest
      stages of the project.
     Thisform of construction services has become
      more popular in the last 5-10 years; however,
      Duke has been doing this for 25 years.
Design/Build Process
l   Owner conceives Project.
l   Owner receives price/budget for design and
    construction from single entity, up front, prior to full
    design.
l   Owner contracts directly with the Design/Builder.
l   Design/Builder has full responsibility for design and
    construction.
l   Design/Builder contracts with all A/E Firms and
    subcontractors.
l   Design/Builder then works with Owner to design
    project and create construction documents.
l   Design/Builder hires subcontractors, manages
    construction.
Contractual Relationships

l   Traditional
     Design   – Bid – Build

                        Owner




                  A/E             General
                                 Contractor



                                Subcontractors
Traditional Definition

l   Design – Bid – Build
     Architect   is responsible for design.
     General Contractor is responsible for
      construction.
     General Contractor is obligated to perform
      exactly what is indicated or inferred by contract
      drawings and specifications.
     Method  is oldest way to buy construction
      services.
     Normally General Contractor is not involved in
      the design or preconstruction phase - builds
      only.
Traditional Process

l   Traditional
     Design     – Bid – Build
        –   Owner conceives project
        –   Owner hires architect
        –   Architect provides budget / feasibility
        –   Architect designs project
        –   General Contractor bids project
        –   Owner hires General Contractor
        –   General Contractor hires subcontractors,
            manages construction
Contractual Relationships

l   Construction Manager


                     Owner




       A/E           Construction
                                    Contractors
                       Manager
Construction Manager Definition
l   The Construction Manager (CM) is a professional
    management team with focus on construction.
    Many CM firms are also GC’s or used to be a GC.
l   Specialize in organizing and buying the various
    components of the Project and administer the work
    on behalf of the Owner.
l   Preconstruction phase likely to involve interface
    with Architect, but no control of Architect.
l   Architect control is left up to the Owner
l   This term did not exist 25 years ago.
l   In purest form does not hold contracts.
l   Usually used on larger projects.
Construction Manager Process

l   Owner conceives project
l   Owner hires an Architect
l   Owner hires Construction Manager, fee based
l   Architect designs, Construction Manager monitors
    design
l   Construction Manager manages bidding process
l   Construction Manager administers contracts
l   Contractors (subcontractors) contract with Owner
l   Prime Contractors manage construction day to day
l   Construction Manager oversees construction

Más contenido relacionado

La actualidad más candente

CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
Pundlik Rathod
 
Build,Operate,Own,Transfer (BOOT)
Build,Operate,Own,Transfer (BOOT)Build,Operate,Own,Transfer (BOOT)
Build,Operate,Own,Transfer (BOOT)
Mohd. Ikhwan
 
Residential Land Development Process
Residential Land Development ProcessResidential Land Development Process
Residential Land Development Process
Duncan Smith
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
ALI HYDER GADHI
 

La actualidad más candente (20)

CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Contracts
ContractsContracts
Contracts
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 
Build,Operate,Own,Transfer (BOOT)
Build,Operate,Own,Transfer (BOOT)Build,Operate,Own,Transfer (BOOT)
Build,Operate,Own,Transfer (BOOT)
 
Contracts - Estimation, Costing and Valuation Engineering
Contracts - Estimation, Costing and Valuation EngineeringContracts - Estimation, Costing and Valuation Engineering
Contracts - Estimation, Costing and Valuation Engineering
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
Bot(build operate transfer)
Bot(build operate transfer)Bot(build operate transfer)
Bot(build operate transfer)
 
Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
 
Residential Land Development Process
Residential Land Development ProcessResidential Land Development Process
Residential Land Development Process
 
EPC Contracts
EPC Contracts EPC Contracts
EPC Contracts
 
Valuation
ValuationValuation
Valuation
 
Construction equipment
Construction equipmentConstruction equipment
Construction equipment
 
Rate analysis
Rate analysisRate analysis
Rate analysis
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 
Valuation 08.04.2020
Valuation 08.04.2020Valuation 08.04.2020
Valuation 08.04.2020
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and Arbitration
 

Similar a Contracting Methods

Similar a Contracting Methods (20)

ACH 231 Lecture 06 (Project Delivery)
ACH 231 Lecture 06 (Project Delivery)ACH 231 Lecture 06 (Project Delivery)
ACH 231 Lecture 06 (Project Delivery)
 
ACH 231 Lecture 06 (Project Delivery)
ACH 231 Lecture 06 (Project Delivery)ACH 231 Lecture 06 (Project Delivery)
ACH 231 Lecture 06 (Project Delivery)
 
Mit1 040s09 lec18
Mit1 040s09 lec18Mit1 040s09 lec18
Mit1 040s09 lec18
 
Defining and documenting a project
Defining and documenting a projectDefining and documenting a project
Defining and documenting a project
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1
 
ACE Team 2 - WK6 - IPD Presentation
ACE Team 2 - WK6 - IPD PresentationACE Team 2 - WK6 - IPD Presentation
ACE Team 2 - WK6 - IPD Presentation
 
ACH 121 Lecture 02 (Arch. Basic Services )
ACH 121 Lecture 02 (Arch. Basic Services )ACH 121 Lecture 02 (Arch. Basic Services )
ACH 121 Lecture 02 (Arch. Basic Services )
 
Bridging Gt Apr09
Bridging Gt Apr09Bridging Gt Apr09
Bridging Gt Apr09
 
Lecture 1.pptx
Lecture 1.pptxLecture 1.pptx
Lecture 1.pptx
 
Architect-Led Design-Build: a PRACTICAL business plan
Architect-Led Design-Build:  a PRACTICAL business planArchitect-Led Design-Build:  a PRACTICAL business plan
Architect-Led Design-Build: a PRACTICAL business plan
 
R&M Property Group Ltd brochure - 2018
R&M Property Group Ltd  brochure - 2018R&M Property Group Ltd  brochure - 2018
R&M Property Group Ltd brochure - 2018
 
Construction management cm
Construction management cmConstruction management cm
Construction management cm
 
Adnan.S_CV
Adnan.S_CVAdnan.S_CV
Adnan.S_CV
 
Nuclear Supply Chain Symposium - Canadian Contracting Models
Nuclear Supply Chain Symposium - Canadian Contracting ModelsNuclear Supply Chain Symposium - Canadian Contracting Models
Nuclear Supply Chain Symposium - Canadian Contracting Models
 
Professional_practice_coa
Professional_practice_coaProfessional_practice_coa
Professional_practice_coa
 
Professional_practice_I.pptx
Professional_practice_I.pptxProfessional_practice_I.pptx
Professional_practice_I.pptx
 
Architecture Professional practice
Architecture Professional  practice Architecture Professional  practice
Architecture Professional practice
 
ARTSCAPE_Introduction
ARTSCAPE_IntroductionARTSCAPE_Introduction
ARTSCAPE_Introduction
 
CONS6817_S03'16
CONS6817_S03'16CONS6817_S03'16
CONS6817_S03'16
 
Matrix207
Matrix207Matrix207
Matrix207
 

Contracting Methods

  • 1. Topics of Discussion l Contracting Methods l Advantages and Disadvantages l Design/Build Subcontractors l Terminology
  • 2. Types of Contracting Methods l Design/Build l Traditional (Design – Bid – Build) l Construction Manager (CM)
  • 3. Contractual Relationships  Design/Build Owner Design/Builder Contractors / A/E Subcontractors
  • 4. Design/Build Definition l Design/Build  Method where design and construction are a single source of responsibility for one entity.  Design/Builder may or may not self perform some or all of the design and construction work.  Design/Builder accountable from the earliest stages of the project.  Thisform of construction services has become more popular in the last 5-10 years; however, Duke has been doing this for 25 years.
  • 5. Design/Build Process l Owner conceives Project. l Owner receives price/budget for design and construction from single entity, up front, prior to full design. l Owner contracts directly with the Design/Builder. l Design/Builder has full responsibility for design and construction. l Design/Builder contracts with all A/E Firms and subcontractors. l Design/Builder then works with Owner to design project and create construction documents. l Design/Builder hires subcontractors, manages construction.
  • 6. Contractual Relationships l Traditional  Design – Bid – Build Owner A/E General Contractor Subcontractors
  • 7. Traditional Definition l Design – Bid – Build  Architect is responsible for design.  General Contractor is responsible for construction.  General Contractor is obligated to perform exactly what is indicated or inferred by contract drawings and specifications.  Method is oldest way to buy construction services.  Normally General Contractor is not involved in the design or preconstruction phase - builds only.
  • 8. Traditional Process l Traditional  Design – Bid – Build – Owner conceives project – Owner hires architect – Architect provides budget / feasibility – Architect designs project – General Contractor bids project – Owner hires General Contractor – General Contractor hires subcontractors, manages construction
  • 9. Contractual Relationships l Construction Manager Owner A/E Construction Contractors Manager
  • 10. Construction Manager Definition l The Construction Manager (CM) is a professional management team with focus on construction. Many CM firms are also GC’s or used to be a GC. l Specialize in organizing and buying the various components of the Project and administer the work on behalf of the Owner. l Preconstruction phase likely to involve interface with Architect, but no control of Architect. l Architect control is left up to the Owner l This term did not exist 25 years ago. l In purest form does not hold contracts. l Usually used on larger projects.
  • 11. Construction Manager Process l Owner conceives project l Owner hires an Architect l Owner hires Construction Manager, fee based l Architect designs, Construction Manager monitors design l Construction Manager manages bidding process l Construction Manager administers contracts l Contractors (subcontractors) contract with Owner l Prime Contractors manage construction day to day l Construction Manager oversees construction