CONTENTS
Introduction
U/G & O/C Comparison
Deepening And Widening Of Shaft
Special Methods Of Shaft Sinking
1. Wood/Steel Piling
2. Open Caisson
3. Cementation Process
4. Freezing Process
Advanced Techniques In Shaft Sinking
1. VSM – Vertical Shaft Sinking Machine
2. Shaft Boring System
3. Shaft Boring
Conclusions
Reference
INTRODUCTION
In India, “MINING” industry is the backbone of India’s economy and
energy. After agriculture mining is the second most important industry on
which India’s economy is depend. Which helps in growth of any country
in every aspects, because all existing industries are depend on mining.
There is none of the industry which will replace to mining industry.
Mining remains the most important player in the Indian industry, as well
as Indian economy, Mining industry plays an important role in the
development of nation.
For underground mining working access should be very
precious and reliable. There are many other access but most reliable
option one access to excavate deep seated mineral body, that term is
called as SHAFT. There is no other access existing which can replace
shaft. So we will have to go through shaft. And for better shaft reliability
we have to sink in better ways, that’s why SHINKING is very important.
But there are many things would be considered. Then we can make
better shaft.
Speedy and economical shaft sinking operation depends upon
not only on actual sinking speeds but to a great extent also on the
planning of the number and the size of the shaft of the hoisting
equipment. the shaft sinking with permanent winding equipment offers
some advantages due to the fact that in this case the transition from
shaft sinking to tunneling requires less time and that in case the
transition from shaft sinking to tunneling requires less time and that it is
possible to dispense with the expenditures on the installation and
dismantling of temporary equipment.
Mechanical excavation methods are a step change in
excavation performance and labour safety compared to drill and blast
operations. In hard rock conditions, road headers cannot be used
effectively, so disc cutting is the first
For excavation of declines, tunnel boring machines (TBM) can
be used in many cases. These provide, in certain rock conditions,
considerably higher production rates compared to drill and blast
excavation. Vertical shaft sinking machine (VSM) that allows
excavating shallow shafts in soil a medium soft rock.
OPENCAST AND UNDERGROUND
PRODUCTION COMPARISION
DEEPENING AND WIDENING
OF SHAFT
DEEPENING
OF
EXISTAING
SHAFAT
DEEPENING OF EXISTAING SHAFAT
• A regular coal winding shaft 6.0 m in
diameter has to be deepened to touch the
bottom seam 100 m below without affecting
normal winding operations.
Major equipment:
• 1. Electric winding engines 2
• 2. Hoisting sheaves 2
• 3. Sinking buckets 3
• 4. Single tub cage 1
DEEPENING OF EXISTAING SHAFAT
• 5. Tubs
• 6. Jack hammer 6
• 7. Pneumatic picks 4
• 8. Pneumatic face pumps 2
• 9. Electric pump
• 10. Platform with folding doors for shaft top
• 11. Shuttering for concreting
• 12. Pipes, cables, ropes etc.
Deepening operations
• Small shaft “A” is sunk near the coal winding pit on the side, away
from main haulage level. Head room is made for installation of
winding sheaves of the hoist “E”. The depth should be enough to
reach beyond the sump of old shaft, cross the safety rock plug “p” and
allow sufficient head room for the installation of the sheaves of
second hoist is driven.
• Level road way “L” to the position on shaft deepening. The place is
widened and heightened for installation of winding engine “H” its
sheaves and other equipment. Additional hoists are installed for
carrying the suspended sinking equipment.
• The shaft center is marked accurately by correlation through the shaft
“A”. The perimeter to be excavated is marked on the rock surface.
• After deepening the shaft to some depths the platform with folding
doors is installed at its mouth.
• Sinking proceeds in the normal manner. The rock from sinking
buckets is dumped into mine tubs and hauled up through shaft A. The
debris can be packed into underground galleries or hoisted to surface
through the main winding shaft for disposal.
• On completion of sinking plug P is removed in sections.
WIDENING A SHAFT
• WIDENING A SHAFT USED FOR COAL WINDING:
In this case entirely different procedure must be
adopted, one of the essential items of equipment being a
strong cylindrical steel shield which fits inside the old shaft and
does not interfere with the travel of the cages.
• PRELIMINARY WORK
Sufficient ground at the surface must first be excavated
behind the old shaft walling down to the depth of say 30 m to
enable a concrete wall 1m thick and 6m internal diameter to be
erected all around the shaft. This wall should be founded on
steel girders and provided with pockets with receives other
girders for the support of existing pit-top frame, receiving
guides etc.
• The next step is to erect a strong platform on
girders at the depth of 3.6m and to widen the
shaft to this depth, the debris being raise to the
crab engine and kibble. The platform then
removed and re-erected at the depth of 6m., the
shaft being widened to this depth in similar way.
The widened shaft should be supported
temporarily by steel ring and backing deals, the
first ring being hung from the girders at the base
of the concrete walling is built up and the platform
removed all together.
• All this preliminary work is necessary to enable
the protecting shield walling platform to be
installed in the shaft.
SPECIAL METHODS OF SHAFT
SINKING
1. Wood/Steel Piling
2. Open Caisson
3. Cementation Process
4. Freezing Process
SHAFT SINKING METHODS
a) Wood/Steel Piling
This method is known as simply PILLING or SHEET
PILLING and is suited sinking through loose deposit of sand
, mud,or alluvium near the surface upto a depth of 20 m.
Interlocking steel pile, 6m to 10m long,are used and they
are practically water-tight. Additional length may be
available by welding or riveting2 or 3 lengths of pile.
The surface, the piles are setup to from a ring and then they
are hammered down in rotation, each member being driven
a few meter at a time by adirect acting state piling hammer.
As the pile descent in the lose ground, the latter,enclosed
by the piles is excavated and cleared up, but it should be
remembered that the bottom ends of the piles are kept
sufficiently ahead of the excavation to prevent.
Inrush of water are loose sand. When the excavation
reaches strong rock, permanent lining is constructed and
the sinking then proceeds in the manner describe for normal
condition.
a) Wood/Steel Piling
b) Open Caisson
In this method the
shaft is started by
digging shallow
excavation and placing
a cutting shoe on the
bottom of the pit. The
ground inside and just
under the shoe is
excavated and the
lining is built up as the
shoe sinks.
c) Cementation Process
Cavities and fissures
are filled with quick-
setting cement under
high pressure then
allowed to set. Cement
pumps are designed
for pressure as high as
6kgf to 300kgf.
This method is use in
sudamdih and
monidoh collieries.
d) Freezing Process
This method was first used in 1883. The wet round is artificially frozen
and then blasted and excavated as though it were solid rock. From 20 to
50 holes are drilled on the circumference of a circle. Circulating pipes are
placed in the holes and a calcium or magnesium chloride solution is
pumped through the pipes to freeze the ground.
ADVANCED TECHNIQUES
IN SHAFT SINKING
RECENT/NEW METHODS OF SHAFT
SINKING
There are different methods of shaft sinking/construction. Actually three
possible methods allowing a shaft to me sunk through highly weathered
over burden on the basis of Excavation and Wall support.
These are;
1. VSM – Vertical Shaft sinking Machine
2. SHAFT BORING SYSTEM
3. SHAFT BORING
VSM – Vertical Shaft
sinking Machine
 Shaft installation in difficult
ground conditions – especially
under ground water – requires
special equipment.
 Till today, with the help of
several Vertical Shaft Boring
Machines (VSM) dozens of
shafts have been sunken in a
variety of ground conditions.
 They have a drill diameter of
5 to 10 meters and built shafts
with a maximum depth of 65
meters.
 VSM Technique is an
application for Offshore Mining
Purposes.
COMPONENTS SHAFT
SINKING
MACHINE
 Shaft Sinking Machine
consists of two main
components
1.shaft boring machine
2.the lowering units
 The shaft boring machine is
lowered into the launch shaft
structure and attached firmly
to the shaft with its three
machine arms.
 A rotating cutting drum
equipped with chisel tools is
attached to a telescopic
boom.
 This road header excavates
ADVANTAGES
 All operational processes are controlled and monitored from the
surface. In addition to the separation plant, lowering units and
recovery winches, the jobsite equipment includes a control
container and power supply units.
 All information available about the excavation is collected and
visualized in the control container.
 There, the operator has a full overview of the situation at hand
and can respond accordingly at all times.
After completing excavation or when changing excavation tools,
the shaft boring machine is retrieved using the recovery winches.
The advantages of the modular design of the overall system
become particularly apparent in inner-city projects.
The equipment can be arranged as needed. For example, the
separation plant can be installed in a street next to the jobsite if
there is not enough space for it next to the shaft.
SHAFT BORING SYSTEM
 The SBS is a development for the mechanized
excavation of deep vertical blind shafts in hard
rock conditions.
 The semi full-face sequential excavation
process is based on the use of a rotating cutting
wheel excavating the full shaft diameter in a two
stage process for one complete stroke.
The excavation process is divided into two steps:
 trench excavation to a depth of one stroke with
the cutting wheel rotating around its horizontal
axis and being pushed downward in the shaft
direction.
 excavation of the entire bench (face) area by
slewing the rotating cutting wheel 180° around
the shaft vertical axis.
The SBS machinery consists of three
major areas of equipment and
operation which are (starting from the
bottom):
excavation chamber with cutting wheel, cutting
wheel drive assembly, mechanical machine
support structure, shotcrete and probe drilling
equipment
(Figure (1))
 adjustable front support with slew
bearing/drive assembly cutting wheel support
and dust shield (Figure (2))
 regular rock support area for rock bolts
(Figure (3))
 SBS mainframe with gripper carrier, gripper
system and thrust cylinders (Figure (4))
 rear alignment system (secondary gripper)
muck handling system (Figure 3(5)).
ADVANTAGES
 High sinking rates.
High level of safety.
Integrated system for excavation, mucking and rock
support.
Fully accessible bench.
Dedicated drill rigs for probing and pre-excavation grouting.
Semi-partial face excavation system with industry standard
disc cutters.
SHAFT BORING
CONVENTIONAL PILOT DRILLING
A tri-cone pilot bit is normally used varying from 9
inches (229mm) to 15 inches (381mm). The 15 inches
(381mm) bit is normally used on long holes with a 12 7/8
inches (327mm) integral drill steel string with a 10 1/8-inch
DI 42 tool joints. During drilling a fluid is pumped through
the center of the drill string to the cutting face, where the
rock cuttings are flushed and raised from the bottom of the
hole through the annulus around the drill string to the collar
of the hole. The drilling fluid is settled in a closed loop via a
series of settling dams so that the drilling water can be re-
used. See figure.
CONVENTIONAL UP-REAMING OF PILOT HOLES:
On completion of pilot drilling and at such time that the
pilot hole breaks through into the lower excavation, a reaming
head is fitted to the end of the drillstring. The size of the
reaming heads range between 1, 2 meters and 6, 1 meters in
diameter. The head is rotated by the machine and is pulled
back against the rock face at the same time. Tungsten
Carbide insert cutters are fitted to the head and these cut
grooves in the rock in a rotary crushing mode. The ‘kerfs’ of
rock in between the grooves ‘spall’ out and rock failure occurs
in a tensile mode. The rock cuttings fall to the bottom of the
hole where it is mucked out by a mechanical loader.
It is a safe, efficient and cost-effective method of
making holes through different geological formations with the
use of powerful machines, high strength drill string and
reliable heads. The maximum loading capacity of the drill
string limits the diameter as well as the length of the shaft.
The loading is dynamic and only approximately calculable
because tensile, torsional and bending stresses are
overlapping. See figure.
DOWN BORING WITH A PRE-DRILLED
PILOT HOLE
In this case an oversize pilot hole is drilled.
The cutting head is installed at the top of
the pilot hole and drilling takes place in the
downward mode. Rock cuttings are
flushed down the oversize pilot hole to the
bottom of the hole where it is removed. In
the case of smaller holes, the machine
provides cutter thrust and in the case of
large diameter shafts the cutter head is
weighted through the addition of steel
collars. The down boring method is not
used often as the risk of blocking the pilot
hole and creating mud rushes at the
CONCLUSIONS
In day to day life, demands of mineral is increasing and for fulfillment
of this we would extracted more minerals by increasing production
and productivity of Indian mines working. The production of opencast
mining is greater than underground mines but shallow depth reserves
are being depleted, for what mineral have to extracted from
underground by underground method. . But most of the mineral
reserves are situated at great depth. For minerals extraction from
underground drives access through shaft. And to drives shaft, sinking
is most important aspect. So we have to adopt best sinking methods
so that cost of sinking will be reduce and sinking work will be done at
faster rate to achieve the targeted production.
For better sinking methods we studied the various Shaft
Sinking methods. After studying, found that, the advanced
mechanical excavations systems can have significant advantages
over conventional drill and blast methods for sinking of shafts in many
different aspects. Advanced mechanical excavation systems allow
for a significantly enhanced level of productivity and safety due to the
high degree of mechanization and industrialization. Due to high
production performance.
After studying case studies of two mines i.e Mansar and
Balaghat mine in India where the shaft sinking was carried out
recently by conventional shaft sinking methods techniques for the
purpose of shaft sinking . The shaft of Mansar and Balaghat mines
have made by Conventional Shaft sinking method but if this shaft
would have been sunk with the advanced technologies like VSM and
Shaft borer the production rate would have been raised to 30 %
(Marks, 2002) with the sophisticated usage of manpower, increasing
safety and reducing cost of capital on shaft sinking with less time
required for sinking same length of shaft.
Most reliable we can call that the advance sinking methods
eliminates the usage of tedious method of Drilling and Blasting which
is most critical to accidents with respect to safetyin mines. This
mechanized method can also be applied for widening and deepening
of existing shafts.
But there are some natural and technical problems, of using
advanced techniques in India, regarding with natural and technical
condition in India such as geology, ground condition, required capital
cost, operating cost, environment, suitability of techniques with
Indian mining atmosphere, lack of knowledge about techniques, lack
of worker’s experience, other training arrangement.
So we will have to make several modification in
technique’s construction and its working parameters
according to suitability of techniques with Indian mining
working and geological aspects. So that, it will work as
better as possible and as per mentioned above, it will help
to enhance production, productivity and safety measures
of Indian mining industry. Really it will help to achieve
India’s mineral target production.
In this thesis an attempt has been made to study
the advanced shaft sinking techniques which are not
practiced in Indian condition but in future those may be
practiced in our condition and it will help to improve the
production, productivity and safety measures. By
application of the advanced techniques India can achieve
their goals in production and economy.
REFERENCE
1. Dinesh Baliga, B-mechanised Shaft Sinking – JI. Of Mine, Metal
And Fuels And Special Number 1972.
2. Chatterjee, S K Et Al- The Development Of Base Metal Mine –
Techniques Employed At Zawar Mines – Ji. Of Mine, Metal And
Fuels And Special Number 1972.
3. Karwande, V L And Paranjpe D V – Mechanised Shaft Sinking At
Singareni Collieries Ltd – Indian Mining And Engg. Journal,
Special Number 1968.
4. Nath P D – Sinking Through Running Sand - Indian Mining And
Engg. Journal, Special Number 1968.
5. Heinrich R. Gierke, Dulmen – Design Of Shaft ,Shaft Sinking –
Symposium In Ranchi, Coal Expansion In India, 21-23 November
1983.
6. Walter Von Der Linden –N Shaft Sinking In Theory And Actual
Performance - Ji. Of Mine, Metal And Fuels And Special Number
1962.
7. Mankovsky G I – Development Of Shaft Sinking Techniques In
The Ussr - Ji. Of Mine, Metal And Fuels And Special Number
1962.
8. Horizon Mining By C.H. Fritzsche And E.L.J. Potts.
9. Mining By B.Boky.
Shaft  sinking 2

Más contenido relacionado

La actualidad más candente

Mining Machinery Learning Material
Mining Machinery Learning MaterialMining Machinery Learning Material
Mining Machinery Learning MaterialBhaskar Naidu
 
Conventional shaft sinking by manual means
Conventional shaft sinking by manual meansConventional shaft sinking by manual means
Conventional shaft sinking by manual meansSafdar Ali
 
Haulage system in Mines
Haulage system in MinesHaulage system in Mines
Haulage system in Minesajeetkm
 
Lectures on metal mining
Lectures on metal miningLectures on metal mining
Lectures on metal miningRanjeet Kumar
 
Thin seam mining
Thin seam miningThin seam mining
Thin seam miningSafdar Ali
 
Development and depillaring with continuous miner
Development and depillaring with continuous minerDevelopment and depillaring with continuous miner
Development and depillaring with continuous minerSafdar Ali
 
Mine machinery - Wire ropes
Mine machinery - Wire ropesMine machinery - Wire ropes
Mine machinery - Wire ropesajeetkm
 
Longwall Mining
Longwall MiningLongwall Mining
Longwall MiningVR M
 

La actualidad más candente (20)

Caving Underground Mining Methods (longwall, Sublevel caving, & Block caving)
Caving Underground Mining Methods (longwall, Sublevel caving, &  Block caving)Caving Underground Mining Methods (longwall, Sublevel caving, &  Block caving)
Caving Underground Mining Methods (longwall, Sublevel caving, & Block caving)
 
Mining Machinery Learning Material
Mining Machinery Learning MaterialMining Machinery Learning Material
Mining Machinery Learning Material
 
depllaring in coal mines
depllaring in coal minesdepllaring in coal mines
depllaring in coal mines
 
Conventional shaft sinking by manual means
Conventional shaft sinking by manual meansConventional shaft sinking by manual means
Conventional shaft sinking by manual means
 
Underground mine
Underground mineUnderground mine
Underground mine
 
Drilling and blasting
Drilling and blastingDrilling and blasting
Drilling and blasting
 
Room and Pillar Mining Method
Room and Pillar Mining MethodRoom and Pillar Mining Method
Room and Pillar Mining Method
 
Haulage system in Mines
Haulage system in MinesHaulage system in Mines
Haulage system in Mines
 
Shrinkage and Vertical Crater Retreat Stoping
Shrinkage and Vertical Crater Retreat StopingShrinkage and Vertical Crater Retreat Stoping
Shrinkage and Vertical Crater Retreat Stoping
 
Pillar design in coal mines
Pillar design in coal minesPillar design in coal mines
Pillar design in coal mines
 
Underground Mining System Question Pattern and Answer
Underground Mining System Question Pattern and AnswerUnderground Mining System Question Pattern and Answer
Underground Mining System Question Pattern and Answer
 
Lectures on metal mining
Lectures on metal miningLectures on metal mining
Lectures on metal mining
 
Thin seam mining
Thin seam miningThin seam mining
Thin seam mining
 
Roof supports in coal mines
Roof supports in coal minesRoof supports in coal mines
Roof supports in coal mines
 
Development and depillaring with continuous miner
Development and depillaring with continuous minerDevelopment and depillaring with continuous miner
Development and depillaring with continuous miner
 
Mine machinery - Wire ropes
Mine machinery - Wire ropesMine machinery - Wire ropes
Mine machinery - Wire ropes
 
Shaft
Shaft Shaft
Shaft
 
Damps & Mine Dust
Damps & Mine DustDamps & Mine Dust
Damps & Mine Dust
 
Longwall Mining
Longwall MiningLongwall Mining
Longwall Mining
 
Pillar design
Pillar designPillar design
Pillar design
 

Similar a Shaft sinking 2

shaftab-170524171214.pdf
shaftab-170524171214.pdfshaftab-170524171214.pdf
shaftab-170524171214.pdfSaimHaq
 
Presentation on surface investigation techniques for foundation
Presentation on surface investigation techniques  for foundationPresentation on surface investigation techniques  for foundation
Presentation on surface investigation techniques for foundationashishcivil098
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling explorationjamali husain
 
Support Systems In Cut And Fill Method Of Stoping
Support Systems In Cut And Fill Method Of StopingSupport Systems In Cut And Fill Method Of Stoping
Support Systems In Cut And Fill Method Of Stopingem_vishal
 
Rock Drilling and Types of Rock Drilling
Rock Drilling and Types of Rock DrillingRock Drilling and Types of Rock Drilling
Rock Drilling and Types of Rock DrillingMOHAMMED SOHEL AHMED
 
Underground mining method
Underground mining methodUnderground mining method
Underground mining methodSafdar Ali
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sectionsjuwes
 
Sublevel open stopping assignment
Sublevel open stopping assignmentSublevel open stopping assignment
Sublevel open stopping assignmentvirendrasuryawanshi
 
Transmission tower
Transmission towerTransmission tower
Transmission towerKiran Hadiya
 
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILLDesign and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILLDr. Malek Smadi
 
Wel Planing
Wel PlaningWel Planing
Wel Planingsaqib129
 
Underground Coal Mining Study
Underground Coal Mining StudyUnderground Coal Mining Study
Underground Coal Mining StudyOnur Tuncay
 
Advance Construction equipment's reports
Advance Construction equipment's reports Advance Construction equipment's reports
Advance Construction equipment's reports ssuser061280
 
Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Mayur Rahangdale
 

Similar a Shaft sinking 2 (20)

shaftab-170524171214.pdf
shaftab-170524171214.pdfshaftab-170524171214.pdf
shaftab-170524171214.pdf
 
Presentation on surface investigation techniques for foundation
Presentation on surface investigation techniques  for foundationPresentation on surface investigation techniques  for foundation
Presentation on surface investigation techniques for foundation
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling exploration
 
Support Systems In Cut And Fill Method Of Stoping
Support Systems In Cut And Fill Method Of StopingSupport Systems In Cut And Fill Method Of Stoping
Support Systems In Cut And Fill Method Of Stoping
 
UNIT 1a.pdf
UNIT 1a.pdfUNIT 1a.pdf
UNIT 1a.pdf
 
Rock Drilling and Types of Rock Drilling
Rock Drilling and Types of Rock DrillingRock Drilling and Types of Rock Drilling
Rock Drilling and Types of Rock Drilling
 
Underground mining method
Underground mining methodUnderground mining method
Underground mining method
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sections
 
Sublevel open stopping assignment
Sublevel open stopping assignmentSublevel open stopping assignment
Sublevel open stopping assignment
 
Open pit mining
Open pit miningOpen pit mining
Open pit mining
 
Transmission tower
Transmission towerTransmission tower
Transmission tower
 
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILLDesign and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
 
Wel Planing
Wel PlaningWel Planing
Wel Planing
 
Continuous miner
Continuous minerContinuous miner
Continuous miner
 
Shaft boring methods
Shaft boring methodsShaft boring methods
Shaft boring methods
 
Underground Coal Mining Study
Underground Coal Mining StudyUnderground Coal Mining Study
Underground Coal Mining Study
 
Advance Construction equipment's reports
Advance Construction equipment's reports Advance Construction equipment's reports
Advance Construction equipment's reports
 
Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)
 
Chapter 09
Chapter 09Chapter 09
Chapter 09
 

Último

Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesRAJNEESHKUMAR341697
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxNadaHaitham1
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEselvakumar948
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxchumtiyababu
 

Último (20)

Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 

Shaft sinking 2

  • 1. SHAFT SINKING Rajiv Gandhi College Of Engineering, Research & Technology PRESENTED BY : SUNIL D. WASADE Guided By Prof. B.K. KHADE H.O.D. Dr. M.D. Uttarwar Mining Engineering 2015-2016
  • 2. CONTENTS Introduction U/G & O/C Comparison Deepening And Widening Of Shaft Special Methods Of Shaft Sinking 1. Wood/Steel Piling 2. Open Caisson 3. Cementation Process 4. Freezing Process Advanced Techniques In Shaft Sinking 1. VSM – Vertical Shaft Sinking Machine 2. Shaft Boring System 3. Shaft Boring Conclusions Reference
  • 3. INTRODUCTION In India, “MINING” industry is the backbone of India’s economy and energy. After agriculture mining is the second most important industry on which India’s economy is depend. Which helps in growth of any country in every aspects, because all existing industries are depend on mining. There is none of the industry which will replace to mining industry. Mining remains the most important player in the Indian industry, as well as Indian economy, Mining industry plays an important role in the development of nation. For underground mining working access should be very precious and reliable. There are many other access but most reliable option one access to excavate deep seated mineral body, that term is called as SHAFT. There is no other access existing which can replace shaft. So we will have to go through shaft. And for better shaft reliability we have to sink in better ways, that’s why SHINKING is very important. But there are many things would be considered. Then we can make better shaft.
  • 4. Speedy and economical shaft sinking operation depends upon not only on actual sinking speeds but to a great extent also on the planning of the number and the size of the shaft of the hoisting equipment. the shaft sinking with permanent winding equipment offers some advantages due to the fact that in this case the transition from shaft sinking to tunneling requires less time and that in case the transition from shaft sinking to tunneling requires less time and that it is possible to dispense with the expenditures on the installation and dismantling of temporary equipment. Mechanical excavation methods are a step change in excavation performance and labour safety compared to drill and blast operations. In hard rock conditions, road headers cannot be used effectively, so disc cutting is the first For excavation of declines, tunnel boring machines (TBM) can be used in many cases. These provide, in certain rock conditions, considerably higher production rates compared to drill and blast excavation. Vertical shaft sinking machine (VSM) that allows excavating shallow shafts in soil a medium soft rock.
  • 8. DEEPENING OF EXISTAING SHAFAT • A regular coal winding shaft 6.0 m in diameter has to be deepened to touch the bottom seam 100 m below without affecting normal winding operations. Major equipment: • 1. Electric winding engines 2 • 2. Hoisting sheaves 2 • 3. Sinking buckets 3 • 4. Single tub cage 1
  • 9. DEEPENING OF EXISTAING SHAFAT • 5. Tubs • 6. Jack hammer 6 • 7. Pneumatic picks 4 • 8. Pneumatic face pumps 2 • 9. Electric pump • 10. Platform with folding doors for shaft top • 11. Shuttering for concreting • 12. Pipes, cables, ropes etc.
  • 10. Deepening operations • Small shaft “A” is sunk near the coal winding pit on the side, away from main haulage level. Head room is made for installation of winding sheaves of the hoist “E”. The depth should be enough to reach beyond the sump of old shaft, cross the safety rock plug “p” and allow sufficient head room for the installation of the sheaves of second hoist is driven. • Level road way “L” to the position on shaft deepening. The place is widened and heightened for installation of winding engine “H” its sheaves and other equipment. Additional hoists are installed for carrying the suspended sinking equipment. • The shaft center is marked accurately by correlation through the shaft “A”. The perimeter to be excavated is marked on the rock surface. • After deepening the shaft to some depths the platform with folding doors is installed at its mouth. • Sinking proceeds in the normal manner. The rock from sinking buckets is dumped into mine tubs and hauled up through shaft A. The debris can be packed into underground galleries or hoisted to surface through the main winding shaft for disposal. • On completion of sinking plug P is removed in sections.
  • 11. WIDENING A SHAFT • WIDENING A SHAFT USED FOR COAL WINDING: In this case entirely different procedure must be adopted, one of the essential items of equipment being a strong cylindrical steel shield which fits inside the old shaft and does not interfere with the travel of the cages. • PRELIMINARY WORK Sufficient ground at the surface must first be excavated behind the old shaft walling down to the depth of say 30 m to enable a concrete wall 1m thick and 6m internal diameter to be erected all around the shaft. This wall should be founded on steel girders and provided with pockets with receives other girders for the support of existing pit-top frame, receiving guides etc.
  • 12. • The next step is to erect a strong platform on girders at the depth of 3.6m and to widen the shaft to this depth, the debris being raise to the crab engine and kibble. The platform then removed and re-erected at the depth of 6m., the shaft being widened to this depth in similar way. The widened shaft should be supported temporarily by steel ring and backing deals, the first ring being hung from the girders at the base of the concrete walling is built up and the platform removed all together. • All this preliminary work is necessary to enable the protecting shield walling platform to be installed in the shaft.
  • 13. SPECIAL METHODS OF SHAFT SINKING 1. Wood/Steel Piling 2. Open Caisson 3. Cementation Process 4. Freezing Process
  • 14. SHAFT SINKING METHODS a) Wood/Steel Piling
  • 15. This method is known as simply PILLING or SHEET PILLING and is suited sinking through loose deposit of sand , mud,or alluvium near the surface upto a depth of 20 m. Interlocking steel pile, 6m to 10m long,are used and they are practically water-tight. Additional length may be available by welding or riveting2 or 3 lengths of pile. The surface, the piles are setup to from a ring and then they are hammered down in rotation, each member being driven a few meter at a time by adirect acting state piling hammer. As the pile descent in the lose ground, the latter,enclosed by the piles is excavated and cleared up, but it should be remembered that the bottom ends of the piles are kept sufficiently ahead of the excavation to prevent. Inrush of water are loose sand. When the excavation reaches strong rock, permanent lining is constructed and the sinking then proceeds in the manner describe for normal condition. a) Wood/Steel Piling
  • 16. b) Open Caisson In this method the shaft is started by digging shallow excavation and placing a cutting shoe on the bottom of the pit. The ground inside and just under the shoe is excavated and the lining is built up as the shoe sinks.
  • 17. c) Cementation Process Cavities and fissures are filled with quick- setting cement under high pressure then allowed to set. Cement pumps are designed for pressure as high as 6kgf to 300kgf. This method is use in sudamdih and monidoh collieries.
  • 18. d) Freezing Process This method was first used in 1883. The wet round is artificially frozen and then blasted and excavated as though it were solid rock. From 20 to 50 holes are drilled on the circumference of a circle. Circulating pipes are placed in the holes and a calcium or magnesium chloride solution is pumped through the pipes to freeze the ground.
  • 20. RECENT/NEW METHODS OF SHAFT SINKING There are different methods of shaft sinking/construction. Actually three possible methods allowing a shaft to me sunk through highly weathered over burden on the basis of Excavation and Wall support. These are; 1. VSM – Vertical Shaft sinking Machine 2. SHAFT BORING SYSTEM 3. SHAFT BORING
  • 21. VSM – Vertical Shaft sinking Machine  Shaft installation in difficult ground conditions – especially under ground water – requires special equipment.  Till today, with the help of several Vertical Shaft Boring Machines (VSM) dozens of shafts have been sunken in a variety of ground conditions.  They have a drill diameter of 5 to 10 meters and built shafts with a maximum depth of 65 meters.  VSM Technique is an application for Offshore Mining Purposes.
  • 22. COMPONENTS SHAFT SINKING MACHINE  Shaft Sinking Machine consists of two main components 1.shaft boring machine 2.the lowering units  The shaft boring machine is lowered into the launch shaft structure and attached firmly to the shaft with its three machine arms.  A rotating cutting drum equipped with chisel tools is attached to a telescopic boom.  This road header excavates
  • 23. ADVANTAGES  All operational processes are controlled and monitored from the surface. In addition to the separation plant, lowering units and recovery winches, the jobsite equipment includes a control container and power supply units.  All information available about the excavation is collected and visualized in the control container.  There, the operator has a full overview of the situation at hand and can respond accordingly at all times. After completing excavation or when changing excavation tools, the shaft boring machine is retrieved using the recovery winches. The advantages of the modular design of the overall system become particularly apparent in inner-city projects. The equipment can be arranged as needed. For example, the separation plant can be installed in a street next to the jobsite if there is not enough space for it next to the shaft.
  • 24. SHAFT BORING SYSTEM  The SBS is a development for the mechanized excavation of deep vertical blind shafts in hard rock conditions.  The semi full-face sequential excavation process is based on the use of a rotating cutting wheel excavating the full shaft diameter in a two stage process for one complete stroke. The excavation process is divided into two steps:  trench excavation to a depth of one stroke with the cutting wheel rotating around its horizontal axis and being pushed downward in the shaft direction.  excavation of the entire bench (face) area by slewing the rotating cutting wheel 180° around the shaft vertical axis.
  • 25. The SBS machinery consists of three major areas of equipment and operation which are (starting from the bottom): excavation chamber with cutting wheel, cutting wheel drive assembly, mechanical machine support structure, shotcrete and probe drilling equipment (Figure (1))  adjustable front support with slew bearing/drive assembly cutting wheel support and dust shield (Figure (2))  regular rock support area for rock bolts (Figure (3))  SBS mainframe with gripper carrier, gripper system and thrust cylinders (Figure (4))  rear alignment system (secondary gripper) muck handling system (Figure 3(5)).
  • 26. ADVANTAGES  High sinking rates. High level of safety. Integrated system for excavation, mucking and rock support. Fully accessible bench. Dedicated drill rigs for probing and pre-excavation grouting. Semi-partial face excavation system with industry standard disc cutters.
  • 28. CONVENTIONAL PILOT DRILLING A tri-cone pilot bit is normally used varying from 9 inches (229mm) to 15 inches (381mm). The 15 inches (381mm) bit is normally used on long holes with a 12 7/8 inches (327mm) integral drill steel string with a 10 1/8-inch DI 42 tool joints. During drilling a fluid is pumped through the center of the drill string to the cutting face, where the rock cuttings are flushed and raised from the bottom of the hole through the annulus around the drill string to the collar of the hole. The drilling fluid is settled in a closed loop via a series of settling dams so that the drilling water can be re- used. See figure.
  • 29. CONVENTIONAL UP-REAMING OF PILOT HOLES: On completion of pilot drilling and at such time that the pilot hole breaks through into the lower excavation, a reaming head is fitted to the end of the drillstring. The size of the reaming heads range between 1, 2 meters and 6, 1 meters in diameter. The head is rotated by the machine and is pulled back against the rock face at the same time. Tungsten Carbide insert cutters are fitted to the head and these cut grooves in the rock in a rotary crushing mode. The ‘kerfs’ of rock in between the grooves ‘spall’ out and rock failure occurs in a tensile mode. The rock cuttings fall to the bottom of the hole where it is mucked out by a mechanical loader. It is a safe, efficient and cost-effective method of making holes through different geological formations with the use of powerful machines, high strength drill string and reliable heads. The maximum loading capacity of the drill string limits the diameter as well as the length of the shaft. The loading is dynamic and only approximately calculable because tensile, torsional and bending stresses are overlapping. See figure.
  • 30. DOWN BORING WITH A PRE-DRILLED PILOT HOLE
  • 31. In this case an oversize pilot hole is drilled. The cutting head is installed at the top of the pilot hole and drilling takes place in the downward mode. Rock cuttings are flushed down the oversize pilot hole to the bottom of the hole where it is removed. In the case of smaller holes, the machine provides cutter thrust and in the case of large diameter shafts the cutter head is weighted through the addition of steel collars. The down boring method is not used often as the risk of blocking the pilot hole and creating mud rushes at the
  • 32. CONCLUSIONS In day to day life, demands of mineral is increasing and for fulfillment of this we would extracted more minerals by increasing production and productivity of Indian mines working. The production of opencast mining is greater than underground mines but shallow depth reserves are being depleted, for what mineral have to extracted from underground by underground method. . But most of the mineral reserves are situated at great depth. For minerals extraction from underground drives access through shaft. And to drives shaft, sinking is most important aspect. So we have to adopt best sinking methods so that cost of sinking will be reduce and sinking work will be done at faster rate to achieve the targeted production. For better sinking methods we studied the various Shaft Sinking methods. After studying, found that, the advanced mechanical excavations systems can have significant advantages over conventional drill and blast methods for sinking of shafts in many different aspects. Advanced mechanical excavation systems allow for a significantly enhanced level of productivity and safety due to the high degree of mechanization and industrialization. Due to high production performance.
  • 33. After studying case studies of two mines i.e Mansar and Balaghat mine in India where the shaft sinking was carried out recently by conventional shaft sinking methods techniques for the purpose of shaft sinking . The shaft of Mansar and Balaghat mines have made by Conventional Shaft sinking method but if this shaft would have been sunk with the advanced technologies like VSM and Shaft borer the production rate would have been raised to 30 % (Marks, 2002) with the sophisticated usage of manpower, increasing safety and reducing cost of capital on shaft sinking with less time required for sinking same length of shaft. Most reliable we can call that the advance sinking methods eliminates the usage of tedious method of Drilling and Blasting which is most critical to accidents with respect to safetyin mines. This mechanized method can also be applied for widening and deepening of existing shafts. But there are some natural and technical problems, of using advanced techniques in India, regarding with natural and technical condition in India such as geology, ground condition, required capital cost, operating cost, environment, suitability of techniques with Indian mining atmosphere, lack of knowledge about techniques, lack of worker’s experience, other training arrangement.
  • 34. So we will have to make several modification in technique’s construction and its working parameters according to suitability of techniques with Indian mining working and geological aspects. So that, it will work as better as possible and as per mentioned above, it will help to enhance production, productivity and safety measures of Indian mining industry. Really it will help to achieve India’s mineral target production. In this thesis an attempt has been made to study the advanced shaft sinking techniques which are not practiced in Indian condition but in future those may be practiced in our condition and it will help to improve the production, productivity and safety measures. By application of the advanced techniques India can achieve their goals in production and economy.
  • 35. REFERENCE 1. Dinesh Baliga, B-mechanised Shaft Sinking – JI. Of Mine, Metal And Fuels And Special Number 1972. 2. Chatterjee, S K Et Al- The Development Of Base Metal Mine – Techniques Employed At Zawar Mines – Ji. Of Mine, Metal And Fuels And Special Number 1972. 3. Karwande, V L And Paranjpe D V – Mechanised Shaft Sinking At Singareni Collieries Ltd – Indian Mining And Engg. Journal, Special Number 1968. 4. Nath P D – Sinking Through Running Sand - Indian Mining And Engg. Journal, Special Number 1968. 5. Heinrich R. Gierke, Dulmen – Design Of Shaft ,Shaft Sinking – Symposium In Ranchi, Coal Expansion In India, 21-23 November 1983. 6. Walter Von Der Linden –N Shaft Sinking In Theory And Actual Performance - Ji. Of Mine, Metal And Fuels And Special Number 1962. 7. Mankovsky G I – Development Of Shaft Sinking Techniques In The Ussr - Ji. Of Mine, Metal And Fuels And Special Number 1962. 8. Horizon Mining By C.H. Fritzsche And E.L.J. Potts. 9. Mining By B.Boky.