IFMA Presentation: BIM Making the Facility Manager's Life Easier
1. BIM Making the Facility
Manager’s Life Easier:
Techniques to Reduce Risk on Your Next
Project and Protect Your Investment
Eric Peabody Suj Mishra
eric@dpsf.com suj@dpsf.com
415 777-3737 415 777-3737
2. Agenda
Quick Overview
What is BIM, how does it work
Reduce Risk
Use the Risk=Cost equation to benefit
everyone
Prove it!
Experimental data on three identical
projects
Use BIM in FM today
Free tools to implement BIM now
The Design Partnership LLP
Architects + Planners
3. Quick Overview of BIM
The Design Partnership LLP
Architects + Planners
4. Project Delivery Improvement
Automatic Document Coordination
3D Systems Coordination
Virtual Building Simulation
Direct Fabrication
The Design Partnership LLP
Architects + Planners
5. BIM is a 3D Database
The Design Partnership LLP
Architects + Planners
20. Increase in Architect’s
Exposure
Unknown Consequences Of Sharing BIM
Information
Design Only Information In BIM Model
Extensive Pre-coordination
Fabrication From Design Models
Increased Exposure to Risk
The Design Partnership LLP
Architects + Planners
22. Decrease in Owner’s Risk
Reduced Bids Due To Reduced
Contractor Risks
Reduced Risk Of
– Change Orders From Unknown Conditions
– Coordination Changes
– Fighting Among AEC Entities
Reduced User Changes Due To Better
Pre-visualization And Planning
Design Partnership LLPRisk
The
Reduced
Architects + Planners
23. Architect’s Exposure
However
Architect’s Risk
Reduced Risk for All = Reduced
Cost
The Design Partnership LLP
Architects + Planners
26. Experimental Controls
Experimental Variables
BIM Use Area* Start** Architect
Cath Lab 7 CAD 720 SF 2006
Cath Lab 9 2” 1,173 SF 2009
Standard
Cath Lab Everything 1,060 SF 2010
10
*Results expressed per SF to normalize this variable
**Cost values escalated to 2010 relative value to normalize this variable
27. Cath Lab 7
CAD Only
The Design Partnership LLP
Architects + Planners
30. (E) CAD V.I.F. (N) CAD Construction
The Design Partnership LLP
Architects + Planners
31. (E) CAD V.I.F. (N) CAD Construction
The Design Partnership LLP
Architects + Planners
32. (E) CAD V.I.F. (N) CAD Construction
The Design Partnership LLP
Architects + Planners
33. (E) CAD V.I.F. (N) CAD Construction
The Design Partnership LLP
Architects + Planners
34. The delay was caused…by the
over-head structural and M/E/P/FP
not being coordinated. The
majority of the overhead had to be
re-designed. DPR
Construction
The Design Partnership LLP
Architects + Planners
35. Cath Lab 9
BIM to 2”
The Design Partnership LLP
Architects + Planners
50. Construction Cost
BIM Use % from
CAD
Cath Lab 7 CAD
Cath Lab 9 2” Standard -15.0%
Cath Lab Everything
*All figures in 2010 Relative Value -4.1%
10
Change Order
BIM Use % of Total
Cost 7 CAD
Cath Lab 12.4%
Cath Lab 9 2” Standard 8.1%
Cath Lab Everything <0.1%
10
*All figures in 2010 Relative Value
The Design Partnership LLP
Architects + Planners
51. Construction BIM Use Construction Days/SF % from
Schedule
Cath Lab 7 CAD 8.40 mo 0.23 D/SF
CAD
Cath Lab 9 2” Standard 8.50 mo 0.15 D/SF -34.8%
Cath Lab Everything 8.45 mo 0.16 D/SF -30.4%
10
All Costs
Survey All Construction Margin** Total
Services* $
Cath Lab 7 18.5% 18.5%
Cath Lab 9 1.6% 27.3% (15.0%) (22.0%) (23.3%)
Cath Lab 10 1.6% 18.5%
*All design professional fees, including non-BIM fees
(4.1%) (18.6%) (17.9%)
**Cath lab contribution margin of ~$8,000 per day
The Design Partnership LLP
Architects + Planners
52. Conclusions
Save up to 23% on project costs
Complete project 35% faster
Drop change order rate to <0.1%
44% fewer RFIs
The Design Partnership LLP
Architects + Planners
53. Federated Model
REVIT
3D CADD REVIT
NAVISWORKS
ABS CADD/REVIT
The Design Partnership LLP
Architects + Planners
54. Use BIM in FM Today
BIM model from construction
phase
Navisworks Freedom
Smart Tags linked to (E) systems
QR codes linked to (E) systems
The Design Partnership LLP
Architects + Planners
55. Free Tools
Navisworks Freedom: Model
Navigation
QR reader: QR Droid or Adobe AIR
QR Code Generator: Kaywa.com
The Design Partnership LLP
Architects + Planners
56. Thanks. Questions?
Find the slides from this presentation on SlideShare.
Search for us by name: TheDesignPartnership
Or by our public profile: http://www.slideshare.net/TheDesignPartnership
Eric Peabody Suj Mishra
eric@dpsf.com suj@dpsf.com
415 777-3737 415 777-3737
Notas del editor
Quarter million $ saved on Cath 9
Go to Revit demo after this slide. Focus on 3D views, and explain that the drawings are views of a model, not drafted abstractions.
Go to Revit demo after this slide. Focus on 3D views, and explain that the drawings are views of a model, not drafted abstractions.