SlideShare una empresa de Scribd logo
1 de 28
How to build external single-leaf
walls in HOTBLOK System -
heat transfer coefficient
U=0.15 W/m²K
www.Thermibau.com
Before bricklaying, check all corner levels of the building under
construction, and take care of a proper insulation against dampness – in
accordance with good building practices. The substrate below the first
row of blocks must be clean and even (it will minimize the consumption
of thermal insulating mortar).
HOTBLOK System
All partition elements of the blocks are 3 cm thick, apart from one,
which is 5 cm thick, and which should always be laid to the inside of the
wall – the inner part of the building.
HOTBLOK System
We recommend using a pre-mix for thermal insulating mortar. It can be
prepared either in a concrete mixer or by a manual slow-speed stirrer.
The first layer of mortar, the so-called smoothing underlayment, aims to
cover possible imperfections - level differences between designated
control points, and can be slightly thicker, but the thickness of
successive mortar layers should not exceed 8-10mm. The mortar
should be evenly distributed across the full width of a HOTBLOK
block. It is incorrect to apply mortar in the form of the so-called
„patches”.
HOTBLOK System
Start external walls bricklaying
by adjusting corner blocks,
ensuring proper positioning in
the corners /external, internal/,
and checking their location in
relation to the points (levels) set
previously. The arrangement of
first blocks is especially
important because of the
consequences at a later
construction stage. Blocks in the
corners need to be stacked
alternately.
HOTBLOK System
Elements of HOTBLOK System lock together by means of a „tongue and
groove” design, therefore, after laying at the destination place in a wall, it
is necessary to control each element using special tools /spirit level/,
vertically and horizontally. Neglecting this important principle may result
in difficulties with fitting the successive blocks in the other wall courses.
HOTBLOK System
It is necessary to make sure that
successive block courses in all
corners are on the same level. The
string line laid across the surface
will allow to control if blocks are
arranged horizontally between
corners. The construction of
consecutive courses of the wall is
always preceded by setting up
corners.
The header surfaces of all elements of the System are desiged to ensure
adequate tightness and strength of the wall after combining them, so that
heat transfer coefficient parameters, declared by the System
manufacturer, is preserved, eliminating possible thermal bridges. To avoid
rolls on the mortal surface, blocks must be inserted from above into the
„locks” of already fixed elements, only then pressed down to the mortar
layer.
HOTBLOK System
HOTBLOK System elements can be adjusted or cut - depending on needs – using
commonly available cutting tools (eg. circular saw), and polyurethane foam can be
applied in the joints. Cut elements of the System should be arranged so that they
do not align in two successive block courses, in accordance with good bricklaying
practices. If possible, it is recommended to shift by one-half block length in two
successive rows of blocks. Trimmed blocks should be placed in the middle part of
the wall, not its edges.
HOTBLOK System
Combining internal load-
bearing walls with external
walls built in HOTBLOK
System, can be achieved by
implementation of „ties” -
metal connectors/anchor
bolts available on the
market, or by placing a
special fiberglass
components in a weld.
HOTBLOK System
Jamb blocks usage eliminates thermal bridges around window and door
openings. Their internal design - the shape of insulating chambers -
allows to maintain a consistent coefficient of thermal insulation. The
design of jamb blocks as well as other HOTBLOK System elements
ensures that the outer parts of window and door frames reach insulating
layer from each side, which eliminates thermal bridges. Correct and
precise construction of openings in external walls enables easy and fast
installation of windows and doors.
HOTBLOK System
Using lintels, which consist of two elements /reinforced load-bearing
lintel and insulation lintel/, window or door openings can be finished
without the necessity of making breaks imposed by technological
properties of materials. Lintels shold be longer at least 30 cm on each
side of opening edge.
HOTBLOK System
After being set up on the
wall, mounted lintels have
load bearing function and
in a simple way ensure the
continuity of a wall course.
The height of a lintel and
a basic block should be
equal, and their thickness
carefully matched to
create a uniform, smooth
base for plaster. After
filling with concrete you
can proceed with
bricklaying, without breaks
imposed by technological
properties of materials.
HOTBLOK System
Window opening ready to install
the window. If there are two
windows side by side - should be
at least 60 cm in between (one
block).
HOTBLOK System
Building in HOTBLOK System proceeds much faster than in other technologies
due to considerable size of the blocks as well as their precise tongue and groove
joints. For every 1 m² of a wall only 6.9 blocks are needed. Wall construction is
accelerated also by, relatively small for this size, weight of a single element, and by
grips placed in both sides of the blocks, thanks to which they are easy to carry
around on the building site.
HOTBLOK System
On the wall constructed from HOTBLOK System each kind of upper-
storey floor structure can be used, in accordance with good bricklaying
practices and building instructions.
HOTBLOK System
The complete construction is tied with a knee wall reinforcement. First,
reinforcement insulation is mounted on the external side of the constructed knee
wall. Then, on the internal side, L-shaped knee wall element is installed. The L-
shaped elements, which run around the entire building, tie up the whole
construction, similar to a stable frame /ring/, stiffening it. L-shaped blocks will also
function as a supportive element for the wall plate, on which structural elements of
the roof truss will be based. In the places where rafters cross reinforcement
insulation, birdsmouth joints should be made and sealed with polyurethane foam.
HOTBLOK System
Making grooves and drilling holes
in a building constructed in
HOTBLOK System is performed
in exactly the same way as in
facilities built using other
technologies. The elements of the
System are made of expanded
clay aggregate, which is made of
high quality clay, fire-hardened in
high temperature – above
1.100˚C, so its treatment can be
compared to working with other
materials made of ceramic.
HOTBLOK System
External walls built in HOTBLOK System can be finished with aesthetic
solutions which do not affect negatively its excellent properties. The best
alternative is to make a layer reinforced with fiberglass mesh, the application
of standard lime-cement plaster and exterior silicate or silicone paint in one of
the variety of colours available on the market.
HOTBLOK System
A house built in HOTBLOK System is energy
efficient. Wall insulation parameters, not
exceeding 0,15 W/m2K, enable to build
the energy saving/passive house. This
guarantees low heating costs in winter and
ensures comfort during hot weather. In case
of single-leaf walls many costs connected
with additional insulation are eliminated and
construction time considerably reduced.
ADVANTAGES - SAVINGS and COMFORT
Expanded clay aggregate, of which HOTBLOK elements are made, is fire-
hardened, specially selected clay, healthy and natural material used in
construction for years. HOTBLOK blocks have a very good diffusion coefficient
(water vapor permeability), mi=5 (ideal diffusion coefficient is 1, brick wall is 7,
wood is 12, polystyrene is 50). This allows to maintain the „microclimate” as in
the old brick building (not thermally insulated) while maintaining stringent
thermal standards. The condition of breathability is, however, the use of
breathable plaster and paint!! Expanded clay has also bactericidal and fungicidal
properties, which also results in a favourable microclimate.
ADVANTAGES – HEALTHY MICROCLIMATE
In May 2011 HOTBLOK System received a
certificate from Passivhaus Institut Darmstadt
– a comprehensive system-based solution for
passive and energy efficient construction.
Family house – Wroclaw.
SELECTED PROJECTS
Family house – Lublin vicinity.
SELECTED PROJECTS
Family house construction in Cork, Ireland.
SELECTED PROJECTS
Family house – Wrocaw vicinity.
SELECTED PROJECTS
Passive office building –Torun vicinity
SELECTED PROJECTS
Exemplary Energy
Performance Certificate
of a building made in
HOTBLOK System
Distribution in Europe:
ThermiBau.com

Más contenido relacionado

La actualidad más candente

Visual Dictionary - Archess
Visual Dictionary - ArchessVisual Dictionary - Archess
Visual Dictionary - ArchessArchess
 
BTECH 1 PROJECT 2 FINAL REPORT
BTECH 1 PROJECT 2 FINAL REPORT BTECH 1 PROJECT 2 FINAL REPORT
BTECH 1 PROJECT 2 FINAL REPORT Darshiini Vig
 
Visual Dictionary
Visual DictionaryVisual Dictionary
Visual Dictionaryconduit1
 
SEC01_BRYAN,BIETSCH_A310-WALLSECTION4
SEC01_BRYAN,BIETSCH_A310-WALLSECTION4SEC01_BRYAN,BIETSCH_A310-WALLSECTION4
SEC01_BRYAN,BIETSCH_A310-WALLSECTION4Bryan Bietsch
 
Visual dictionary Sp10stain
Visual dictionary  Sp10stainVisual dictionary  Sp10stain
Visual dictionary Sp10stainSp10stain
 
1515-T_Drawings
1515-T_Drawings1515-T_Drawings
1515-T_DrawingsMark Daly
 
visual dictionary- cornerbead
visual dictionary- cornerbeadvisual dictionary- cornerbead
visual dictionary- cornerbeadcornerbead
 
Visual Dictionary
Visual DictionaryVisual Dictionary
Visual Dictionarymasonry
 
Chapter 4 (e) cavity walls
Chapter 4 (e) cavity wallsChapter 4 (e) cavity walls
Chapter 4 (e) cavity wallsKHUSHBU SHAH
 
(Power Shrink) Visual Dictionary Done
(Power Shrink)   Visual Dictionary Done(Power Shrink)   Visual Dictionary Done
(Power Shrink) Visual Dictionary DoneAuburn University
 
Codename Astm1
Codename Astm1Codename Astm1
Codename Astm1ASTM1
 

La actualidad más candente (15)

Bcon report
Bcon reportBcon report
Bcon report
 
Visual Dictionary - Archess
Visual Dictionary - ArchessVisual Dictionary - Archess
Visual Dictionary - Archess
 
BTECH 1 PROJECT 2 FINAL REPORT
BTECH 1 PROJECT 2 FINAL REPORT BTECH 1 PROJECT 2 FINAL REPORT
BTECH 1 PROJECT 2 FINAL REPORT
 
Visual Dictionary
Visual DictionaryVisual Dictionary
Visual Dictionary
 
Air bricks
Air bricksAir bricks
Air bricks
 
SEC01_BRYAN,BIETSCH_A310-WALLSECTION4
SEC01_BRYAN,BIETSCH_A310-WALLSECTION4SEC01_BRYAN,BIETSCH_A310-WALLSECTION4
SEC01_BRYAN,BIETSCH_A310-WALLSECTION4
 
Visual dictionary Sp10stain
Visual dictionary  Sp10stainVisual dictionary  Sp10stain
Visual dictionary Sp10stain
 
1515-T_Drawings
1515-T_Drawings1515-T_Drawings
1515-T_Drawings
 
visual dictionary- cornerbead
visual dictionary- cornerbeadvisual dictionary- cornerbead
visual dictionary- cornerbead
 
Visual Dictionary
Visual DictionaryVisual Dictionary
Visual Dictionary
 
Chapter 4 (e) cavity walls
Chapter 4 (e) cavity wallsChapter 4 (e) cavity walls
Chapter 4 (e) cavity walls
 
(Power Shrink) Visual Dictionary Done
(Power Shrink)   Visual Dictionary Done(Power Shrink)   Visual Dictionary Done
(Power Shrink) Visual Dictionary Done
 
Final bsci ppt
Final bsci pptFinal bsci ppt
Final bsci ppt
 
Sp10Lumber
Sp10LumberSp10Lumber
Sp10Lumber
 
Codename Astm1
Codename Astm1Codename Astm1
Codename Astm1
 

Similar a Prezentacja hotblok jak budować eng

Building Industry catalague 2015
Building Industry catalague 2015Building Industry catalague 2015
Building Industry catalague 2015Lesley Lloyd
 
AAC Installation Guidelines
AAC Installation GuidelinesAAC Installation Guidelines
AAC Installation GuidelinesBENAY MUNDA
 
BituTherm Extruded Polystyrene Thermal Insulation Board Presentation
BituTherm Extruded Polystyrene Thermal Insulation Board PresentationBituTherm Extruded Polystyrene Thermal Insulation Board Presentation
BituTherm Extruded Polystyrene Thermal Insulation Board PresentationMohammed Asif
 
Tutor l1 blockwork
Tutor l1 blockworkTutor l1 blockwork
Tutor l1 blockworkLuke D'Arcy
 
about_Simprolit_material
about_Simprolit_materialabout_Simprolit_material
about_Simprolit_materialIvan Stijovic
 
Bolster2-Code Requirements to Mortar
Bolster2-Code Requirements to MortarBolster2-Code Requirements to Mortar
Bolster2-Code Requirements to Mortarbolster2
 
Visual dictionary
Visual dictionaryVisual dictionary
Visual dictionarysp10pex
 
Tutor l1 blockwork
Tutor l1 blockworkTutor l1 blockwork
Tutor l1 blockworkLuke D'Arcy
 
Tutor l1 blockwork
Tutor l1 blockworkTutor l1 blockwork
Tutor l1 blockworkLuke D'Arcy
 
Visual Dictionary- Sp10Crawlspace
Visual Dictionary- Sp10CrawlspaceVisual Dictionary- Sp10Crawlspace
Visual Dictionary- Sp10CrawlspaceSp10Crawlspace
 
Visual dictionary - Sp10Window
Visual dictionary - Sp10WindowVisual dictionary - Sp10Window
Visual dictionary - Sp10WindowSp10window
 
REINFORCED CONCRETE PRECAST TWIN WALLS
REINFORCED CONCRETE PRECAST TWIN WALLSREINFORCED CONCRETE PRECAST TWIN WALLS
REINFORCED CONCRETE PRECAST TWIN WALLSGuy Pomphrey
 
Curtain wall introduction & requirements
Curtain wall introduction & requirementsCurtain wall introduction & requirements
Curtain wall introduction & requirementsArshad khan
 
Acp and glazing
Acp and glazingAcp and glazing
Acp and glazingaduiti
 
مرسل sphrical building.pdf
مرسل sphrical building.pdfمرسل sphrical building.pdf
مرسل sphrical building.pdfHebatalrahman1
 
Simprolit system - min eng
Simprolit system - min engSimprolit system - min eng
Simprolit system - min engIvan Stijovic
 

Similar a Prezentacja hotblok jak budować eng (20)

Building Industry catalague 2015
Building Industry catalague 2015Building Industry catalague 2015
Building Industry catalague 2015
 
AAC Installation Guidelines
AAC Installation GuidelinesAAC Installation Guidelines
AAC Installation Guidelines
 
BituTherm Extruded Polystyrene Thermal Insulation Board Presentation
BituTherm Extruded Polystyrene Thermal Insulation Board PresentationBituTherm Extruded Polystyrene Thermal Insulation Board Presentation
BituTherm Extruded Polystyrene Thermal Insulation Board Presentation
 
Tutor l1 blockwork
Tutor l1 blockworkTutor l1 blockwork
Tutor l1 blockwork
 
about_Simprolit_material
about_Simprolit_materialabout_Simprolit_material
about_Simprolit_material
 
Panel system
Panel systemPanel system
Panel system
 
Bolster2-Code Requirements to Mortar
Bolster2-Code Requirements to MortarBolster2-Code Requirements to Mortar
Bolster2-Code Requirements to Mortar
 
Curtain walls
Curtain wallsCurtain walls
Curtain walls
 
Visual dictionary
Visual dictionaryVisual dictionary
Visual dictionary
 
Tutor l1 blockwork
Tutor l1 blockworkTutor l1 blockwork
Tutor l1 blockwork
 
Tutor l1 blockwork
Tutor l1 blockworkTutor l1 blockwork
Tutor l1 blockwork
 
blockwork
 blockwork blockwork
blockwork
 
Sp10Crawlspace
Sp10CrawlspaceSp10Crawlspace
Sp10Crawlspace
 
Visual Dictionary- Sp10Crawlspace
Visual Dictionary- Sp10CrawlspaceVisual Dictionary- Sp10Crawlspace
Visual Dictionary- Sp10Crawlspace
 
Visual dictionary - Sp10Window
Visual dictionary - Sp10WindowVisual dictionary - Sp10Window
Visual dictionary - Sp10Window
 
REINFORCED CONCRETE PRECAST TWIN WALLS
REINFORCED CONCRETE PRECAST TWIN WALLSREINFORCED CONCRETE PRECAST TWIN WALLS
REINFORCED CONCRETE PRECAST TWIN WALLS
 
Curtain wall introduction & requirements
Curtain wall introduction & requirementsCurtain wall introduction & requirements
Curtain wall introduction & requirements
 
Acp and glazing
Acp and glazingAcp and glazing
Acp and glazing
 
مرسل sphrical building.pdf
مرسل sphrical building.pdfمرسل sphrical building.pdf
مرسل sphrical building.pdf
 
Simprolit system - min eng
Simprolit system - min engSimprolit system - min eng
Simprolit system - min eng
 

Último

Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
An introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxAn introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxPurva Nikam
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniquesugginaramesh
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 

Último (20)

Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
An introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxAn introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptx
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniques
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 

Prezentacja hotblok jak budować eng

  • 1. How to build external single-leaf walls in HOTBLOK System - heat transfer coefficient U=0.15 W/m²K www.Thermibau.com
  • 2. Before bricklaying, check all corner levels of the building under construction, and take care of a proper insulation against dampness – in accordance with good building practices. The substrate below the first row of blocks must be clean and even (it will minimize the consumption of thermal insulating mortar). HOTBLOK System
  • 3. All partition elements of the blocks are 3 cm thick, apart from one, which is 5 cm thick, and which should always be laid to the inside of the wall – the inner part of the building. HOTBLOK System
  • 4. We recommend using a pre-mix for thermal insulating mortar. It can be prepared either in a concrete mixer or by a manual slow-speed stirrer. The first layer of mortar, the so-called smoothing underlayment, aims to cover possible imperfections - level differences between designated control points, and can be slightly thicker, but the thickness of successive mortar layers should not exceed 8-10mm. The mortar should be evenly distributed across the full width of a HOTBLOK block. It is incorrect to apply mortar in the form of the so-called „patches”. HOTBLOK System
  • 5. Start external walls bricklaying by adjusting corner blocks, ensuring proper positioning in the corners /external, internal/, and checking their location in relation to the points (levels) set previously. The arrangement of first blocks is especially important because of the consequences at a later construction stage. Blocks in the corners need to be stacked alternately. HOTBLOK System
  • 6. Elements of HOTBLOK System lock together by means of a „tongue and groove” design, therefore, after laying at the destination place in a wall, it is necessary to control each element using special tools /spirit level/, vertically and horizontally. Neglecting this important principle may result in difficulties with fitting the successive blocks in the other wall courses. HOTBLOK System It is necessary to make sure that successive block courses in all corners are on the same level. The string line laid across the surface will allow to control if blocks are arranged horizontally between corners. The construction of consecutive courses of the wall is always preceded by setting up corners.
  • 7. The header surfaces of all elements of the System are desiged to ensure adequate tightness and strength of the wall after combining them, so that heat transfer coefficient parameters, declared by the System manufacturer, is preserved, eliminating possible thermal bridges. To avoid rolls on the mortal surface, blocks must be inserted from above into the „locks” of already fixed elements, only then pressed down to the mortar layer. HOTBLOK System
  • 8. HOTBLOK System elements can be adjusted or cut - depending on needs – using commonly available cutting tools (eg. circular saw), and polyurethane foam can be applied in the joints. Cut elements of the System should be arranged so that they do not align in two successive block courses, in accordance with good bricklaying practices. If possible, it is recommended to shift by one-half block length in two successive rows of blocks. Trimmed blocks should be placed in the middle part of the wall, not its edges. HOTBLOK System
  • 9. Combining internal load- bearing walls with external walls built in HOTBLOK System, can be achieved by implementation of „ties” - metal connectors/anchor bolts available on the market, or by placing a special fiberglass components in a weld. HOTBLOK System
  • 10. Jamb blocks usage eliminates thermal bridges around window and door openings. Their internal design - the shape of insulating chambers - allows to maintain a consistent coefficient of thermal insulation. The design of jamb blocks as well as other HOTBLOK System elements ensures that the outer parts of window and door frames reach insulating layer from each side, which eliminates thermal bridges. Correct and precise construction of openings in external walls enables easy and fast installation of windows and doors. HOTBLOK System
  • 11. Using lintels, which consist of two elements /reinforced load-bearing lintel and insulation lintel/, window or door openings can be finished without the necessity of making breaks imposed by technological properties of materials. Lintels shold be longer at least 30 cm on each side of opening edge. HOTBLOK System
  • 12. After being set up on the wall, mounted lintels have load bearing function and in a simple way ensure the continuity of a wall course. The height of a lintel and a basic block should be equal, and their thickness carefully matched to create a uniform, smooth base for plaster. After filling with concrete you can proceed with bricklaying, without breaks imposed by technological properties of materials. HOTBLOK System
  • 13. Window opening ready to install the window. If there are two windows side by side - should be at least 60 cm in between (one block). HOTBLOK System
  • 14. Building in HOTBLOK System proceeds much faster than in other technologies due to considerable size of the blocks as well as their precise tongue and groove joints. For every 1 m² of a wall only 6.9 blocks are needed. Wall construction is accelerated also by, relatively small for this size, weight of a single element, and by grips placed in both sides of the blocks, thanks to which they are easy to carry around on the building site. HOTBLOK System
  • 15. On the wall constructed from HOTBLOK System each kind of upper- storey floor structure can be used, in accordance with good bricklaying practices and building instructions. HOTBLOK System
  • 16. The complete construction is tied with a knee wall reinforcement. First, reinforcement insulation is mounted on the external side of the constructed knee wall. Then, on the internal side, L-shaped knee wall element is installed. The L- shaped elements, which run around the entire building, tie up the whole construction, similar to a stable frame /ring/, stiffening it. L-shaped blocks will also function as a supportive element for the wall plate, on which structural elements of the roof truss will be based. In the places where rafters cross reinforcement insulation, birdsmouth joints should be made and sealed with polyurethane foam. HOTBLOK System
  • 17. Making grooves and drilling holes in a building constructed in HOTBLOK System is performed in exactly the same way as in facilities built using other technologies. The elements of the System are made of expanded clay aggregate, which is made of high quality clay, fire-hardened in high temperature – above 1.100˚C, so its treatment can be compared to working with other materials made of ceramic. HOTBLOK System
  • 18. External walls built in HOTBLOK System can be finished with aesthetic solutions which do not affect negatively its excellent properties. The best alternative is to make a layer reinforced with fiberglass mesh, the application of standard lime-cement plaster and exterior silicate or silicone paint in one of the variety of colours available on the market. HOTBLOK System
  • 19. A house built in HOTBLOK System is energy efficient. Wall insulation parameters, not exceeding 0,15 W/m2K, enable to build the energy saving/passive house. This guarantees low heating costs in winter and ensures comfort during hot weather. In case of single-leaf walls many costs connected with additional insulation are eliminated and construction time considerably reduced. ADVANTAGES - SAVINGS and COMFORT
  • 20. Expanded clay aggregate, of which HOTBLOK elements are made, is fire- hardened, specially selected clay, healthy and natural material used in construction for years. HOTBLOK blocks have a very good diffusion coefficient (water vapor permeability), mi=5 (ideal diffusion coefficient is 1, brick wall is 7, wood is 12, polystyrene is 50). This allows to maintain the „microclimate” as in the old brick building (not thermally insulated) while maintaining stringent thermal standards. The condition of breathability is, however, the use of breathable plaster and paint!! Expanded clay has also bactericidal and fungicidal properties, which also results in a favourable microclimate. ADVANTAGES – HEALTHY MICROCLIMATE
  • 21. In May 2011 HOTBLOK System received a certificate from Passivhaus Institut Darmstadt – a comprehensive system-based solution for passive and energy efficient construction.
  • 22. Family house – Wroclaw. SELECTED PROJECTS
  • 23. Family house – Lublin vicinity. SELECTED PROJECTS
  • 24. Family house construction in Cork, Ireland. SELECTED PROJECTS
  • 25. Family house – Wrocaw vicinity. SELECTED PROJECTS
  • 26. Passive office building –Torun vicinity SELECTED PROJECTS
  • 27. Exemplary Energy Performance Certificate of a building made in HOTBLOK System