PMI-ACP® Course Exam Preparation

D E L I V E R E D B Y:
W A F I M O H TA S E B
S O F T WA R E D E V E LO P M E N T M A N AG E R
P M P, P M I - A C P, P M I - S P, C E R T I F I E D S C R U M M A S T E R
Continuous Improvement

 Most traditional projects capture the majority of their lessons learned at the end of the project.
  The intent behind capturing these lessons is to allow the organization to apply them to future
  projects with a similar business or technical domain, or to projects that have similar team
  dynamics.
 This approach, frankly, is too little, too late. We need to apply the benefits of learning as we go—
  on our current project, and as soon as possible.
 Agile projects schedule continuous improvement activities into the plan as part of the
  methodology. The agile approach to lessons learned is deliberate and frequent, and it helps
  ensure that the team regularly considers adaptation and improvement to the point where it
  becomes habitual and part of their normal way of working.
 We will look at the T&T and K&S that are part of this “Learn” step:
   Retrospectives
   Knowledge Sharing
   Process Tailoring
   Principles of Systems Thinking (Complex, Adaptive, Chaos)
   Process Analysis
   Continuous Improvement Processes
   Self Assessment
Continuous Improvement - Retrospectives

 Retrospectives, which are common to all agile methods, are the primary learning, reflection, and
  readjustment events on agile projects.
 A retrospective is a special meeting that takes place after each iteration, in which the team
  members gather to inspect and improve their methods and teamwork.
 Retrospectives offer a number of benefits for teams, including the following types of
  improvements:
       Improved productivity: By applying lessons learned and reducing rework, the team can get more productive work done.
       Improved capability: Retrospectives provide a venue for spreading rare knowledge, and as the number of people who have
        the rare knowledge increases, so does the number of people who can perform tasks associated with the knowledge.
       Improved quality: We can improve quality on our projects by finding the circumstances that led to defects and removing the
        causes.
       Improved capacity: Retrospectives focus on finding process efficiency improvements, which can improve the team's capacity
        to do work.
Continuous Improvement - Retrospectives

   The retrospective process goes through the following five steps:
       The typical time is 2 hours


                                               Set Stage (5%)



                                           Gather Data (30-50%)



                                        Generate Insights (20-30%)



                                        Decide what to do (15-20%)



                                      Close the Retrospective (10-15%)
Continuous Improvement - Retrospectives

These steps operate
in an ongoing cycle                    1. Set Stage
                                                          3. Deliver completed user
that is synchronized                                         stories for evaluation
with the iterations
                                     2. Gather Data
                   Retrospective




                                                                                       Iteration
                                                          2. Build and test selected
                                   3. Generate Insights          user stories



                                   4. Decide what to do
                                                            1. Plan the iteration,
                                                                incorporating
                                                             improvements and
                                       5. Close the       experiments identified in
                                      Retrospective           the retrospective
Continuous Improvement - Retrospectives

   Step 1: Set the Stage:
     At the start of the retrospective, we need to set the stage to help people focus on the task at
       hand of reflecting on how things went.
     In setting the stage, we aim to create an atmosphere where people feel comfortable speaking
       about things that may not have gone so well on the project.
     Activities to help set the stage include:
          Check-in
          Focus on/ Focus off
          ESVP
          Working agreements
Continuous Improvement - Retrospectives

 Check-in: We use this exercise to help people put aside their concerns and focus on the
  retrospective. In a round-robin format, we ask people to summarize in one or two words what
  they hope to get from the retrospective, the main thing on their mind, or how they are feeling
  about the retrospective.
 Focus On / Focus Off: We use this activity to establish a mindset for productive communication.


                                FOCUS ON / FOCUS OFF
                          INQUIRY RATHER THAN ADVOCACY
                          DIALOGUE RATHER THAN DEBATE
                          CONVERSATION RATHER THAN ARGUMENT
                          UNDERSTANDING RATHER THAN DEFENDING

   In the focus on/focus off exercise, we refer participants to the whiteboard and ask them to
    discuss what the terms (i.e., inquiry, dialogue, conversation, understanding, advocacy, debate,
    argument, and defending) mean to them, inviting them to provide examples. Then we ask people
    if they are willing to stay in the left "Focus On" column. If there is disagreement, we should speak
    to the problems of moving into the right-hand column and try for consensus again.
Continuous Improvement - Retrospectives

   ESVP: This is a group exercise in which participants anonymously associate themselves with one
    of the following identities and record their choice on a slip of paper:
       Explorers: Explorers are eager to discover new ideas and insights, and they want to learn everything they can.
       Shoppers: Shoppers will look over all available information and will happily go home with one useful new idea.
       Vacationers: Vacationers aren't interested in the work of the retrospective, but they are happy to be away from their regular
        job.
       Prisoners: People who classify themselves as prisoners feel like they are being forced to attend the retrospective and would
        rather be doing something else.
   The anonymous results are collected and tallied for the group to see, after the results have been
    tallied, we should noticeably tear up and discard the slips of paper so no one worries about their
    answers being traced back to them via handwriting analysis. Then we ask the participants how
    they feel about the scores and what those scores mean for the retrospective.

   Working Agreements: For this activity, we have the participants form small groups and give them
    different topics to work on. We ask the small groups to define and explain the working
    agreements they would like to see in place for the retrospective. Then with the entire group, we
    spend time clarifying and refining ideas, building a single master list to work from.
Continuous Improvement - Retrospectives




   What are the goals of the “Set the Stage” step in the retrospective process?
Continuous Improvement - Retrospectives

   Step 2: Gather Data:
     In the gathering data phase, we create a shared picture of what happened during the
       iteration (or release or project, depending on the focus of the retrospective).
     Without a common vision for what occurred, the team will simply be speculating on what
       changes or improvements to make and may actually be addressing different issues or
       concerns without realizing it.
     There are several team-based activates that can be used to gather data:
           Timeline.
           Triple nickels.
           Color code dots.
           Mad, sad, glad.
           Locate strengths.
           Satisfaction histogram.
           Team radar.
           Like to like.
       When we are finished with this step in the process, we should have a comprehensive
        collection of observations, facts, and findings, all of which have a shared understanding by the
        team.
Continuous Improvement - Retrospectives

   Step 3: Generate Insights:
     This stage gives the team time to evaluate the data that was gathered in the previous step and
       derive meaningful insights from it.
     The goal of the generating insights stage is to help team members understand the implications
       of their findings and discussions.
     There are several team-based activates that can be used to gather data:
          Brainstorming.
          Five whys.
          Fishbone.
          Prioritize with dots.
          Identify themes.
Continuous Improvement - Retrospectives

   Step 4: Decide What to Do:
     The activities involved in the "decide what to do" step move the team from thinking about
       the iteration they just completed into thinking about the next iteration, including what they
       will change and how they will behave differently.
     In this step, the team identifies the highest-priority action items, creates detailed plans for
       experiments, and sets measurable goals to achieve the desired results.
     There are several activities that can be used to help the team decide on an action plan:
          Short subjects.
          SMART goals.
          Retrospective planning game.
          Circle of questions.
Continuous Improvement - Retrospectives

   Step 5: Close the Retrospective:
     The final step is closing the retrospective. We provide the team members opportunities to
       reflect on what happened during the retrospective and to express appreciation to each other
     Activities that summarize what the team decided to keep and what to change, what we are
       thankful for, and where we can make the best use of our time going forward, help round out
       the retrospective and reinforce its value to the project.
     There are several team-based activities that can be used in this final stage:
          Plus/Delta.
          Helped, Hindered, Hypothesis.
          Return on Time Invested (ROTI).
          Appreciations.


   So those are the five steps of the retrospective process. In summary, these important agile
    workshops enable the team to take the impediments and problems reported at daily stand-up
    meetings, along with items identified after reflection and observation, and do something to
    improve the situation while the lessons and actions are still relevant to the project.
Continuous Improvement – Knowledge Sharing

   Knowledge sharing happens at many levels, in both obvious and subtle ways. Product
    demonstrations are an example of an obvious method. The main purpose of such demonstrations
    is not to show off the product, since the team knows very well what works and does not work;
    instead, demos are done because they are high-ceremony ways to share knowledge through the
    following kind of dialogue:

       Team to customer: Here is what we think you asked for and what we have been able to build. Please tell us
        if we are on the right track.
       Customer to team: I like these bits, and this is okay, but you got this piece wrong. Oh, and that reminds
        me—we really need something over here to do X.


 An example of a less obvious way to share information is team co-location. This practice is not
  done to save space or ease management overhead; instead, it is done to leverage the sharing of
  tacit (unwritten) knowledge that occurs in face-to-face environments and through osmotic
  communication.
 Retrospectives are also knowledge transfer vehicles.
Continuous Improvement – Knowledge Sharing

   We understand that knowledge sharing is a good thing, why is it sometimes difficult to achieve
    and sustain?
       “Individuals are most commonly rewarded for what they know, not what they share." This reward system actually
        discourages knowledge sharing. To promote the idea of sharing knowledge, the organizational culture should instead
        encourage and reward the discovery, innovation, and transfer of information.
   Measuring Up to Encourage Desired Behavior:
       "You get what you measure, in fact you get only what you measure, nothing else. So you tend to lose the things that you can't
        measure, like knowledge sharing, insight, collaboration and creativity”
       How we can overcome this issue? We measure up .
 Measure up means, that we measuring something at one level above the normal span of control
  (The team level rather than the individual level) to encourage teamwork, collaboration, and
  global, rather than local optimization.
 Tracking velocity is an example of measuring up. We could quite easily trace velocity to individual
  team members and determine who is the most productive, but this approach would likely
  encourage negative behaviors and a lack of cooperation. So instead we measure velocity at a
  team level; as a result, team members are motivated to help each other.
Continuous Improvement – Process Tailoring

 When we tailor processes on agile projects, we amend the methodology to better fit the project
  environment we are using it in.
 Some methodologies are quite tailoring-friendly, some are not.
 There are benefits and risks with both extremes. When considering the question of whether
  process tailoring is appropriate, we should first recognize that all projects are different. They
  solve different problems, face different challenges, utilize different people, and operate in
  different organizations with different cultures and norms.
 We have two point of views here:
       Create process-per-project approach—in other words, creating processes that are situationally specific for the job at hand.
       Maintain an adherence to agile values and practices. Supports of this approach says that methodologies may transform the
        agile approach beyond recognition and then, when projects fail, those failures will be blamed on agile.
   Process tailoring can be effective and productive, but that we should be aware of the risks
    involved in this practice. The following are the key ways to mitigate these risks:
       Get used to normal, out-of-the-box agile before attempting to change it. The methods were created based on the collective
        wisdom of many experienced practitioners, so don't be too hasty to change them.
       Carefully examine the motivation to drop, amend, or append a practice. Is the change a lazy cop-out to avoid a more
        fundamental problem, or will it truly address a gap or be a value-add unique to the environment?
Continuous Improvement – Principles of System
                        Thinking

   Software projects are characterized by the level of complexity around requirements, as well as
    the complexity of the technology used on the projects.
                agreement
                Far from




                                                                     Chaos
                          Requirement




                                                                                     Agile works
                                             Low
                                                        Complex                       well here
                                          Complexity
                agreement




                                                          Low
                Close to




                                            Simple
                                                       Complexity


                                        Close to                         Far from
                                                        Technology
                                        certainty                        certainty
Continuous Improvement – Principles of System
                        Thinking

 We see projects range from simple (lower left) up to those categorized as anarchy or chaos
  (upper right).
 An agile approach works really well for projects in the middle ground. These projects are complex
  and have uncertainty around both requirements and the technical approach.

   Agile methods can of course be used for simple projects, too, in which the organization and the
    team will get the benefits of increased collaboration, communication, and visibility, but simple
    projects can be run just fine with traditional approaches as well. In contrast, complex projects
    begin to struggle when they are merged with traditional methods.

   If there is no clear agreement on what we are supposed to be building or what approach and
    tools we are using to build it, then our project is in a state of chaos. In this case, neither agile nor
    any other approach can assure success.

   We have to keep in mind this system-level understanding of the environment in which agile
    projects are operating when we think about modifying the methods.
Continuous Improvement – Process Analysis

 Process analysis is closely related to process tailoring and the principles of systems thinking.
  When we perform process analysis, we are reviewing and diagnosing issues with agile methods
  or, more likely, our home-grown add-ons and replacements to agile methods. This analysis may
  then lead to a decision to tailor the process.
 Anti-Patterns (bad things to watch out about methodologies):
       One size for all projects: it not possible to create the optimal methodology for all types of projects, al technologies, and all
        team sizes.
       Intolerant: A methodology is like a straightjacket in that it is a set of conventions and policies people agree to adhere to and
        use. The size and shape of the straightjacket should be chosen by the team and should not be made any tighter than
        necessary, so people have a little wiggle room in their actions.
       Heavy: There is a common but incorrect belief that the heavier a methodology is in artifacts and practices, the safer it is.
        However, adding weight to a methodology is not likely to improve the team's chance of delivering the project successfully.
        Instead, it diverts the team's time from the real goal of the project.
       Embellished: All methods tend to get embellished. We add in things that we think we "ought to" or "should" be doing, but we
        need to look out for these words as signals for potentially expensive, error-prone additions. Get the people directly affected
        by the process to review the methodology, and watch their faces closely for indications of what they know they won't do but
        are afraid to admit they won't do; these items are the embellishments.
Continuous Improvement – Process Analysis

   Anti-Patterns-Cont.
       Untried: Many methodologies are untried. They are proposals created from nothing and are full- blown "shoulds" in action.
        For example, how often have you heard statements like, "Well, this really looks like it should work"? Instead of creating
        complex theoretical methodologies, it is better to reuse, adjust, tune, and create just what is needed. See what actually
        works on projects and use that, not something untried that we believe "should work.“
       Used once: A methodology that is used once is a little better than one that is untried, but it is still no recipe for success. The
        reality is that different projects likely need different approaches, and just because an approach worked under one set of
        circumstances does not guarantee it will work under another.
   Process Success Criteria:
       The project got shipped: The product went out the door.
       The leadership remained intact: They didn't get fired for what they were doing (or not doing).
       The people on the project would work the same way again: They found the approach to be effective and enjoyable.
Continuous Improvement – Process Analysis

   Seven Principles that tells us if the methodology tend to success criteria:
     Interactive, face-to-face communication is the cheapest and fastest channel for exchanging
       information.
     Excess methodology weight is costly

     Larger teams need heavier methodologies

     Greater ceremony is appropriate for projects with greater criticality

     Increasing feedback and communication reduces the need for intermediate deliverables

     Discipline, skills, and understanding counter process, formality, and documentation

     Efficiency is expendable in non-bottleneck activities
Continuous Improvement – Continuous
                           Improvement Processes

 Continuous improvement is the ongoing process of enhancing the project approach and the
  product.
 This process is never completed; instead, it continues throughout the project in much the same
  way as stakeholder communications do.
 Continuous improvement is something we will always do.
 It is more like a journey than a destination, since it is always ongoing and is part of the iterative
  life cycle that drives agile methods.

   Continuous Improvement works on two levels:
     Continuous Process Improvement

     Continuous Product Improvement
Continuous Improvement – Continuous Improvement
                   Processes

   Continuous Process Improvement:
                                                                      Agile Cycle
       The agile cycle employs a continuous cycle of Plan,
        Develop, Evaluate, and Learn.
       This cycle is very similar to Deming’s “Plan, Do,
        Check, Act” cycle for problem solving and continuous
        improvement.
       The "Develop" phase in the agile life cycle is like
        Deming's "Do" phase. "Evaluate" is equivalent to the
        "Check" phase. In the "Learn" phase, we apply the
        lessons from the project, in much the same way as
        the "Act" phase in Deming's cycle. And the "Plan, Do,
        Check, Act" cycle is again mirrored in agile methods
        with demos, reviews, and retrospectives.
                                                                Plan, Do, Check, Act Cycle


                                                                            Plan



                                                                Act                    Do



                                                                           Check
Continuous Improvement – Continuous
                                 Improvement Processes

   Continuous Product Improvement:
       Just as the team practices and processes are being refined iteratively and continuously, so too is the evolving product.
       Iterative and incremental development is a form of continuous improvement, with customer feedback steering us toward the
        final solution.
       When the team builds small increments and get feedback, the product evolves toward the true business requirements. And
        sometimes the true business requirements may be quite different from the originally stated requirements, as the process of
        creation illuminates better options.
       By this cycle of developing in small increments, reviewing, discussing how to improve, and then doing some more
        development and maybe enhancing a few things, the product or service is incrementally built through a process of
        continuous improvement.
Continuous Improvement – Self Assessment

 Assessments of how to improve are not reserved just for the process and product; they are also
  done on the people side of the project, which is arguably the area that offers the greatest
  payback.
 “James Shore” offers a self-assessment quiz and scoring model that is focused on XP practices,
  teams can use this model to gauge their performance.
 The quiz and scoring graph measures how teams perform within the following categories:
       Thinking
       Collaborating
       Releasing
       Planning
       Developing
   The quiz is completed by answering questions within each category and scoring the answers on a
    0-100 scale.
Continuous Improvement – Self Assessment
 Once all the questions have been asked
  and scored, the results are plotted on a
  radar (spider) diagram.                                         Thinking
                                                                 100
 The team is then involved in analyzing the                      80
  chart to identify which areas could use                         60
                                                                  40
  improvement.                                 Developing
                                                                  20
                                                                                  Collaborating
                                                                   0



                                                      Planning               Releasing
Continuous Improvement – Self Assessment

   Another model for assessing high-performing teams is offered by “Jean Tabaka”, this model
    investigate the following areas:
       Self-organization: Is the team self-organizing, rather than functioning in a command-and-control, top-down
        organization?
       Empowered to make decisions: Is the team empowered to discuss, evaluate, and make decisions, rather than
        being dictated to by an outside authority?
       Belief in vision and success: Do team members understand the project vision and goals, and do they truly believe
        that, as a team, they can solve any problem to achieve those goals?
       Committed team: Are team members committed to succeed as a team, rather than being committed to individual
        success at any cost?
       Trust each other: Does the team have the confidence to continually work on improving their ability to act without
        fear, anger, or bullying?
       Participatory decision making: Is the team engaged in participatory decision making, rather than bending to
        authoritarian decision making or succumbing to decisions from others?
       Consensus-driven: Are team decisions consensus-driven, rather than leader-driven? Do team members share their
        opinions freely and participate in the final decision?
       Constructive disagreement: Is the team able to negotiate through a variety of alternatives and impacts surrounding
        a decision, and craft the one that provides the best outcome?
Practice Exam

1.   Your sponsor is asking about tailoring the company's newly adopted agile methodology. Your advice should be:
     A.   Tailoring it will be a good way to learn the methodology
     B.   Tailoring it will be a good way to ease into the initial adoption process
     C.   We should tailor it first, then consider adopting it
     D.   We should try it first, then consider tailoring it
2.   When conducting a retrospective, recognized "close the retrospective" activities include:
     A.   Plus/Delta; Helped, Hindered, Hypothesis; Return on Time Invested; Appreciations
     B.   Plus/Minus; Helped, Hindered, Hoped; Return on Time Invested; Applause
     C.   Plus/Delta; Helped, Hindered, Hoped; Return on Investment; Appreciations
     D.   Plus/Minus; Helped, Hindered, Hypothesis; Return on Time Delivered; Appreciations
3.   You have been asked to review a different project team's recently enhanced methodology to assess its effectiveness and desirable
     characteristics. 'The types of characteristics that you should be looking for include evidence of:
     A.   A preference for face-to-face communications, significant process weight, recommendations for larger teams to use lighter methods
     B.   A preference for face-to-face communications, not too much process weight, recommendations for larger teams to use lighter methods
     C.   A preference for face-to-face communications, significant process weight, recommendations for larger teams to use heavier methods
     D.   A preference for face-to-face communications, not too much process weight, recommendations for larger teams to use heavier methods
4.   The concept of knowledge sharing on an agile project is best characterized as:
     A.   Encouraged where possible and where the team shows an interest
     B.   Central to many of the practices undertaken
     C.   Undertaken if there is time left at the end of an iteration
     D.   Undertaken principally through stand-up meetings
Practice Exam

5. Continuous improvement is a core component of which of the following set of agile practices?
   A.  Pair programming; daily stand-up meetings; WIP limits
   B.  Story points; daily stand-up meetings; demos, reviews, and retrospectives
   C.  Pair programming; daily stand-up meetings; demos, reviews, and retrospectives
   D. Story points; daily stand-up meetings; WIP limits

6. When considering process tailoring, it is useful to keep in mind that the network of XP practices is:
   A.   Redundant
   B.   Duplicated
   C.   Optional
   D.   Balanced
7. The recommended stages of executing a retrospective, in sequence, are:
   A.   Decide what to do, set the stage, gather data, generate insights, close the retrospective
   B.   Decide what to do, gather data, set the stage, generate insights, close the retrospective
   C.   Set the stage, decide what to do, gather data, generate insights, close the retrospective
   D.   Set the stage, gather data, generate insights, decide what to do, close the retrospective
8. You are engaging in some process analysis and have been advised to watch out for the standard anti-patterns of poor methodology practice.
   The types of things you should be on the lookout for are processes that display signs of being:
   A.   One-of-a-kind, disciplined, heavy, embellished
   B.   One-size-fits-all, disciplined, heavy, embellished
   C.   One-size-fits-all, intolerant, heavy, embellished
   D.   One-of-a-kind, intolerant, embellished
Practice Exam

9.  Process tailoring is best undertaken on agile projects when:
    A.  There are difficulties in implementing agile practices
    B.  Experienced practitioners want to address an issue
    C.  The team needs new processes to keep them engaged
    D.  A boost in team velocity is needed to meet the schedule
10. Your project management office (PMO) has suggested your project could benefit from some self- assessment work at the next retrospective.
    Which of the following benefits would they most likely be looking to achieve from a self-assessment?
    A.  Improve personal and team practices
    B.  Gain insights for salary performance reviews
    C.  Identify personal traits for human resources counseling
    D.  Assess compatibilities for pair programming assignments
11. When undertaking process analysis, what are the success criteria that characterize a useful methodology?
    A.  The project got stopped, sponsorship remained intact, the team would work the same way again
    B.  The project got shipped, leadership remained intact, the team would work the same way again
    C.  The project got shipped, sponsorship remained intact, the team would work the same way again
    D.  The project got shipped, sponsorship remained intact, the team engaged in continuous improvement
12. When adopting a new agile practice, the general recommendations are to:
    A.  Develop the new approach yourself, try out the practice on local projects, inspect and review the findings early
    B.  Investigate the claims yourself, try out the practice on local projects, inspect and review the findings early
    C.  Investigate the claims yourself, try out the practice in small doses, inspect and review the findings early
    D.  Develop the new approach yourself, try out the practice in small doses, inspect and review the findings early
Practice Exam

13. As a manager of an agile team, when should you collect lessons learned?
    A.   At the end of the project
    B.   Throughout the project
    C.   When projects go well
    D.   When projects go poorly
14. Information exchanges in agile methods are designed to:
    A.   Facilitate knowledge sharing
    B.   Leverage electronic knowledge-sharing tools
    C.   Maximize resource utilization
    D.   Generate stable specifications

Más contenido relacionado

La actualidad más candente

Scrum guide presentation (Scrum Guide in easy to read PPT format)
Scrum guide presentation (Scrum Guide in easy to read PPT format)Scrum guide presentation (Scrum Guide in easy to read PPT format)
Scrum guide presentation (Scrum Guide in easy to read PPT format)Aloke Bhattacharya
 
Understanding Scrum in 30 Minutes
Understanding Scrum in 30 MinutesUnderstanding Scrum in 30 Minutes
Understanding Scrum in 30 MinutesAltaf Najvani
 
Agile estimating 12112013 - Agile KC Dec 2013
Agile estimating 12112013 - Agile KC Dec 2013Agile estimating 12112013 - Agile KC Dec 2013
Agile estimating 12112013 - Agile KC Dec 2013molsonkc
 
Scrum master competency
Scrum master competencyScrum master competency
Scrum master competencyJane Yip
 
Measuring the Performance of a Scrum Master
Measuring the Performance of a Scrum MasterMeasuring the Performance of a Scrum Master
Measuring the Performance of a Scrum MasterStephanie Gasche
 
Estimating with story points
Estimating with story pointsEstimating with story points
Estimating with story pointsWalid Farag
 
Agile Coaching Workshop
Agile Coaching WorkshopAgile Coaching Workshop
Agile Coaching WorkshopCraig Smith
 
story points v2
story points v2story points v2
story points v2Jane Yip
 
Introduction to scaled agile framework
Introduction to scaled agile frameworkIntroduction to scaled agile framework
Introduction to scaled agile frameworkITEM
 
The Scrum Master Role
The Scrum Master RoleThe Scrum Master Role
The Scrum Master RoleNigel Thurlow
 
A Day in the Life of a Scrum Master
A Day in the Life of a Scrum MasterA Day in the Life of a Scrum Master
A Day in the Life of a Scrum MasterLinda Podder
 
Agile for process improvement
Agile for process improvementAgile for process improvement
Agile for process improvementPeter Leeson
 
Scrum Meetings Infographic v12
Scrum Meetings Infographic v12Scrum Meetings Infographic v12
Scrum Meetings Infographic v12Nigel Thurlow
 
Foundations of the Scaled Agile Framework® (SAFe® ) 4.5
Foundations of the Scaled Agile Framework® (SAFe® ) 4.5Foundations of the Scaled Agile Framework® (SAFe® ) 4.5
Foundations of the Scaled Agile Framework® (SAFe® ) 4.5netmind
 
The Product Owner Role
The Product Owner RoleThe Product Owner Role
The Product Owner RoleRoman Pichler
 

La actualidad más candente (20)

Scrum Ceremonies
Scrum CeremoniesScrum Ceremonies
Scrum Ceremonies
 
Scrum guide presentation (Scrum Guide in easy to read PPT format)
Scrum guide presentation (Scrum Guide in easy to read PPT format)Scrum guide presentation (Scrum Guide in easy to read PPT format)
Scrum guide presentation (Scrum Guide in easy to read PPT format)
 
Understanding Scrum in 30 Minutes
Understanding Scrum in 30 MinutesUnderstanding Scrum in 30 Minutes
Understanding Scrum in 30 Minutes
 
Scrum at Scale
Scrum at ScaleScrum at Scale
Scrum at Scale
 
Agile estimating 12112013 - Agile KC Dec 2013
Agile estimating 12112013 - Agile KC Dec 2013Agile estimating 12112013 - Agile KC Dec 2013
Agile estimating 12112013 - Agile KC Dec 2013
 
Scrum master competency
Scrum master competencyScrum master competency
Scrum master competency
 
Measuring the Performance of a Scrum Master
Measuring the Performance of a Scrum MasterMeasuring the Performance of a Scrum Master
Measuring the Performance of a Scrum Master
 
An Overview of SAFe
An Overview of SAFeAn Overview of SAFe
An Overview of SAFe
 
Estimating with story points
Estimating with story pointsEstimating with story points
Estimating with story points
 
Agile Coaching Workshop
Agile Coaching WorkshopAgile Coaching Workshop
Agile Coaching Workshop
 
story points v2
story points v2story points v2
story points v2
 
Introduction to scaled agile framework
Introduction to scaled agile frameworkIntroduction to scaled agile framework
Introduction to scaled agile framework
 
The Scrum Master Role
The Scrum Master RoleThe Scrum Master Role
The Scrum Master Role
 
A Day in the Life of a Scrum Master
A Day in the Life of a Scrum MasterA Day in the Life of a Scrum Master
A Day in the Life of a Scrum Master
 
Agile for process improvement
Agile for process improvementAgile for process improvement
Agile for process improvement
 
Scrum values
Scrum valuesScrum values
Scrum values
 
Agile Planning and Estimation
Agile Planning and EstimationAgile Planning and Estimation
Agile Planning and Estimation
 
Scrum Meetings Infographic v12
Scrum Meetings Infographic v12Scrum Meetings Infographic v12
Scrum Meetings Infographic v12
 
Foundations of the Scaled Agile Framework® (SAFe® ) 4.5
Foundations of the Scaled Agile Framework® (SAFe® ) 4.5Foundations of the Scaled Agile Framework® (SAFe® ) 4.5
Foundations of the Scaled Agile Framework® (SAFe® ) 4.5
 
The Product Owner Role
The Product Owner RoleThe Product Owner Role
The Product Owner Role
 

Similar a Agile Continuous improvement

Facilitating online agile retrospectives
Facilitating online agile retrospectivesFacilitating online agile retrospectives
Facilitating online agile retrospectivesEnrico Teotti
 
Seda emdedding learning technologies evaluating and sustainability3
Seda emdedding learning technologies   evaluating and sustainability3Seda emdedding learning technologies   evaluating and sustainability3
Seda emdedding learning technologies evaluating and sustainability3BrianKilpatrick
 
Instructional Design: Demystified
Instructional Design: Demystified Instructional Design: Demystified
Instructional Design: Demystified Event Garde LLC
 
After Action Report: a structured support to the practice of continuous impro...
After Action Report: a structured support to the practice of continuous impro...After Action Report: a structured support to the practice of continuous impro...
After Action Report: a structured support to the practice of continuous impro...Learning Everywhere
 
Effectiveness of retrospective
Effectiveness of retrospectiveEffectiveness of retrospective
Effectiveness of retrospectiveSolomon Raja P.S
 
Innovators_Guidebook_workdifferently_gravitytank
Innovators_Guidebook_workdifferently_gravitytankInnovators_Guidebook_workdifferently_gravitytank
Innovators_Guidebook_workdifferently_gravitytankPooja Merai
 
A Guide For Retrospectives
A Guide For RetrospectivesA Guide For Retrospectives
A Guide For RetrospectivesJason Benton
 
Comp10 unit9 lecture_slides
Comp10 unit9 lecture_slidesComp10 unit9 lecture_slides
Comp10 unit9 lecture_slidesCMDLMS
 
Анна Мамаєва “Retrospective: Total Recall” - Lviv PMDay
Анна Мамаєва “Retrospective: Total Recall” - Lviv PMDayАнна Мамаєва “Retrospective: Total Recall” - Lviv PMDay
Анна Мамаєва “Retrospective: Total Recall” - Lviv PMDayLviv Startup Club
 
Course Level Revalidation workshop, School of Computing and Mathematics, 20/0...
Course Level Revalidation workshop, School of Computing and Mathematics, 20/0...Course Level Revalidation workshop, School of Computing and Mathematics, 20/0...
Course Level Revalidation workshop, School of Computing and Mathematics, 20/0...Viewpoints, University of Ulster
 
Coaching and coaches
Coaching and coachesCoaching and coaches
Coaching and coachesClara Novy
 
3. Armine - retrospective and grooming
3. Armine - retrospective and grooming3. Armine - retrospective and grooming
3. Armine - retrospective and groomingArevik Harutyunyan
 
Action Learning
Action Learning Action Learning
Action Learning carena
 
DraftEnergize Results ToolkitRefresh, Review, Reener.docx
DraftEnergize Results ToolkitRefresh, Review, Reener.docxDraftEnergize Results ToolkitRefresh, Review, Reener.docx
DraftEnergize Results ToolkitRefresh, Review, Reener.docxjacksnathalie
 
ITFT Strategic Management
ITFT Strategic ManagementITFT Strategic Management
ITFT Strategic Managementarchan26
 
EFFECTIVE BUSINESS DECISION MAKING CONCEPTS AND PROCESS
EFFECTIVE BUSINESS DECISION MAKING CONCEPTS AND PROCESSEFFECTIVE BUSINESS DECISION MAKING CONCEPTS AND PROCESS
EFFECTIVE BUSINESS DECISION MAKING CONCEPTS AND PROCESSVISHAL VERMA LAKHNAWI JI
 

Similar a Agile Continuous improvement (20)

Facilitating online agile retrospectives
Facilitating online agile retrospectivesFacilitating online agile retrospectives
Facilitating online agile retrospectives
 
Seda emdedding learning technologies evaluating and sustainability3
Seda emdedding learning technologies   evaluating and sustainability3Seda emdedding learning technologies   evaluating and sustainability3
Seda emdedding learning technologies evaluating and sustainability3
 
Instructional Design: Demystified
Instructional Design: Demystified Instructional Design: Demystified
Instructional Design: Demystified
 
Learn sprint
Learn sprintLearn sprint
Learn sprint
 
After Action Report: a structured support to the practice of continuous impro...
After Action Report: a structured support to the practice of continuous impro...After Action Report: a structured support to the practice of continuous impro...
After Action Report: a structured support to the practice of continuous impro...
 
Effectiveness of retrospective
Effectiveness of retrospectiveEffectiveness of retrospective
Effectiveness of retrospective
 
Innovators_Guidebook_workdifferently_gravitytank
Innovators_Guidebook_workdifferently_gravitytankInnovators_Guidebook_workdifferently_gravitytank
Innovators_Guidebook_workdifferently_gravitytank
 
A Guide For Retrospectives
A Guide For RetrospectivesA Guide For Retrospectives
A Guide For Retrospectives
 
Comp10 unit9 lecture_slides
Comp10 unit9 lecture_slidesComp10 unit9 lecture_slides
Comp10 unit9 lecture_slides
 
3 retro total recall
3 retro total recall3 retro total recall
3 retro total recall
 
Анна Мамаєва “Retrospective: Total Recall” - Lviv PMDay
Анна Мамаєва “Retrospective: Total Recall” - Lviv PMDayАнна Мамаєва “Retrospective: Total Recall” - Lviv PMDay
Анна Мамаєва “Retrospective: Total Recall” - Lviv PMDay
 
Course Level Revalidation workshop, School of Computing and Mathematics, 20/0...
Course Level Revalidation workshop, School of Computing and Mathematics, 20/0...Course Level Revalidation workshop, School of Computing and Mathematics, 20/0...
Course Level Revalidation workshop, School of Computing and Mathematics, 20/0...
 
Coaching and coaches
Coaching and coachesCoaching and coaches
Coaching and coaches
 
Agile overview
Agile overviewAgile overview
Agile overview
 
3. Armine - retrospective and grooming
3. Armine - retrospective and grooming3. Armine - retrospective and grooming
3. Armine - retrospective and grooming
 
Sad sprint retrospective
Sad sprint retrospectiveSad sprint retrospective
Sad sprint retrospective
 
Action Learning
Action Learning Action Learning
Action Learning
 
DraftEnergize Results ToolkitRefresh, Review, Reener.docx
DraftEnergize Results ToolkitRefresh, Review, Reener.docxDraftEnergize Results ToolkitRefresh, Review, Reener.docx
DraftEnergize Results ToolkitRefresh, Review, Reener.docx
 
ITFT Strategic Management
ITFT Strategic ManagementITFT Strategic Management
ITFT Strategic Management
 
EFFECTIVE BUSINESS DECISION MAKING CONCEPTS AND PROCESS
EFFECTIVE BUSINESS DECISION MAKING CONCEPTS AND PROCESSEFFECTIVE BUSINESS DECISION MAKING CONCEPTS AND PROCESS
EFFECTIVE BUSINESS DECISION MAKING CONCEPTS AND PROCESS
 

Último

Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEarley Information Science
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...gurkirankumar98700
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 

Último (20)

Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 

Agile Continuous improvement

  • 1. PMI-ACP® Course Exam Preparation D E L I V E R E D B Y: W A F I M O H TA S E B S O F T WA R E D E V E LO P M E N T M A N AG E R P M P, P M I - A C P, P M I - S P, C E R T I F I E D S C R U M M A S T E R
  • 2. Continuous Improvement  Most traditional projects capture the majority of their lessons learned at the end of the project. The intent behind capturing these lessons is to allow the organization to apply them to future projects with a similar business or technical domain, or to projects that have similar team dynamics.  This approach, frankly, is too little, too late. We need to apply the benefits of learning as we go— on our current project, and as soon as possible.  Agile projects schedule continuous improvement activities into the plan as part of the methodology. The agile approach to lessons learned is deliberate and frequent, and it helps ensure that the team regularly considers adaptation and improvement to the point where it becomes habitual and part of their normal way of working.  We will look at the T&T and K&S that are part of this “Learn” step:  Retrospectives  Knowledge Sharing  Process Tailoring  Principles of Systems Thinking (Complex, Adaptive, Chaos)  Process Analysis  Continuous Improvement Processes  Self Assessment
  • 3. Continuous Improvement - Retrospectives  Retrospectives, which are common to all agile methods, are the primary learning, reflection, and readjustment events on agile projects.  A retrospective is a special meeting that takes place after each iteration, in which the team members gather to inspect and improve their methods and teamwork.  Retrospectives offer a number of benefits for teams, including the following types of improvements:  Improved productivity: By applying lessons learned and reducing rework, the team can get more productive work done.  Improved capability: Retrospectives provide a venue for spreading rare knowledge, and as the number of people who have the rare knowledge increases, so does the number of people who can perform tasks associated with the knowledge.  Improved quality: We can improve quality on our projects by finding the circumstances that led to defects and removing the causes.  Improved capacity: Retrospectives focus on finding process efficiency improvements, which can improve the team's capacity to do work.
  • 4. Continuous Improvement - Retrospectives  The retrospective process goes through the following five steps:  The typical time is 2 hours Set Stage (5%) Gather Data (30-50%) Generate Insights (20-30%) Decide what to do (15-20%) Close the Retrospective (10-15%)
  • 5. Continuous Improvement - Retrospectives These steps operate in an ongoing cycle 1. Set Stage 3. Deliver completed user that is synchronized stories for evaluation with the iterations 2. Gather Data Retrospective Iteration 2. Build and test selected 3. Generate Insights user stories 4. Decide what to do 1. Plan the iteration, incorporating improvements and 5. Close the experiments identified in Retrospective the retrospective
  • 6. Continuous Improvement - Retrospectives  Step 1: Set the Stage:  At the start of the retrospective, we need to set the stage to help people focus on the task at hand of reflecting on how things went.  In setting the stage, we aim to create an atmosphere where people feel comfortable speaking about things that may not have gone so well on the project.  Activities to help set the stage include:  Check-in  Focus on/ Focus off  ESVP  Working agreements
  • 7. Continuous Improvement - Retrospectives  Check-in: We use this exercise to help people put aside their concerns and focus on the retrospective. In a round-robin format, we ask people to summarize in one or two words what they hope to get from the retrospective, the main thing on their mind, or how they are feeling about the retrospective.  Focus On / Focus Off: We use this activity to establish a mindset for productive communication. FOCUS ON / FOCUS OFF INQUIRY RATHER THAN ADVOCACY DIALOGUE RATHER THAN DEBATE CONVERSATION RATHER THAN ARGUMENT UNDERSTANDING RATHER THAN DEFENDING  In the focus on/focus off exercise, we refer participants to the whiteboard and ask them to discuss what the terms (i.e., inquiry, dialogue, conversation, understanding, advocacy, debate, argument, and defending) mean to them, inviting them to provide examples. Then we ask people if they are willing to stay in the left "Focus On" column. If there is disagreement, we should speak to the problems of moving into the right-hand column and try for consensus again.
  • 8. Continuous Improvement - Retrospectives  ESVP: This is a group exercise in which participants anonymously associate themselves with one of the following identities and record their choice on a slip of paper:  Explorers: Explorers are eager to discover new ideas and insights, and they want to learn everything they can.  Shoppers: Shoppers will look over all available information and will happily go home with one useful new idea.  Vacationers: Vacationers aren't interested in the work of the retrospective, but they are happy to be away from their regular job.  Prisoners: People who classify themselves as prisoners feel like they are being forced to attend the retrospective and would rather be doing something else.  The anonymous results are collected and tallied for the group to see, after the results have been tallied, we should noticeably tear up and discard the slips of paper so no one worries about their answers being traced back to them via handwriting analysis. Then we ask the participants how they feel about the scores and what those scores mean for the retrospective.  Working Agreements: For this activity, we have the participants form small groups and give them different topics to work on. We ask the small groups to define and explain the working agreements they would like to see in place for the retrospective. Then with the entire group, we spend time clarifying and refining ideas, building a single master list to work from.
  • 9. Continuous Improvement - Retrospectives  What are the goals of the “Set the Stage” step in the retrospective process?
  • 10. Continuous Improvement - Retrospectives  Step 2: Gather Data:  In the gathering data phase, we create a shared picture of what happened during the iteration (or release or project, depending on the focus of the retrospective).  Without a common vision for what occurred, the team will simply be speculating on what changes or improvements to make and may actually be addressing different issues or concerns without realizing it.  There are several team-based activates that can be used to gather data:  Timeline.  Triple nickels.  Color code dots.  Mad, sad, glad.  Locate strengths.  Satisfaction histogram.  Team radar.  Like to like.  When we are finished with this step in the process, we should have a comprehensive collection of observations, facts, and findings, all of which have a shared understanding by the team.
  • 11. Continuous Improvement - Retrospectives  Step 3: Generate Insights:  This stage gives the team time to evaluate the data that was gathered in the previous step and derive meaningful insights from it.  The goal of the generating insights stage is to help team members understand the implications of their findings and discussions.  There are several team-based activates that can be used to gather data:  Brainstorming.  Five whys.  Fishbone.  Prioritize with dots.  Identify themes.
  • 12. Continuous Improvement - Retrospectives  Step 4: Decide What to Do:  The activities involved in the "decide what to do" step move the team from thinking about the iteration they just completed into thinking about the next iteration, including what they will change and how they will behave differently.  In this step, the team identifies the highest-priority action items, creates detailed plans for experiments, and sets measurable goals to achieve the desired results.  There are several activities that can be used to help the team decide on an action plan:  Short subjects.  SMART goals.  Retrospective planning game.  Circle of questions.
  • 13. Continuous Improvement - Retrospectives  Step 5: Close the Retrospective:  The final step is closing the retrospective. We provide the team members opportunities to reflect on what happened during the retrospective and to express appreciation to each other  Activities that summarize what the team decided to keep and what to change, what we are thankful for, and where we can make the best use of our time going forward, help round out the retrospective and reinforce its value to the project.  There are several team-based activities that can be used in this final stage:  Plus/Delta.  Helped, Hindered, Hypothesis.  Return on Time Invested (ROTI).  Appreciations.  So those are the five steps of the retrospective process. In summary, these important agile workshops enable the team to take the impediments and problems reported at daily stand-up meetings, along with items identified after reflection and observation, and do something to improve the situation while the lessons and actions are still relevant to the project.
  • 14. Continuous Improvement – Knowledge Sharing  Knowledge sharing happens at many levels, in both obvious and subtle ways. Product demonstrations are an example of an obvious method. The main purpose of such demonstrations is not to show off the product, since the team knows very well what works and does not work; instead, demos are done because they are high-ceremony ways to share knowledge through the following kind of dialogue:  Team to customer: Here is what we think you asked for and what we have been able to build. Please tell us if we are on the right track.  Customer to team: I like these bits, and this is okay, but you got this piece wrong. Oh, and that reminds me—we really need something over here to do X.  An example of a less obvious way to share information is team co-location. This practice is not done to save space or ease management overhead; instead, it is done to leverage the sharing of tacit (unwritten) knowledge that occurs in face-to-face environments and through osmotic communication.  Retrospectives are also knowledge transfer vehicles.
  • 15. Continuous Improvement – Knowledge Sharing  We understand that knowledge sharing is a good thing, why is it sometimes difficult to achieve and sustain?  “Individuals are most commonly rewarded for what they know, not what they share." This reward system actually discourages knowledge sharing. To promote the idea of sharing knowledge, the organizational culture should instead encourage and reward the discovery, innovation, and transfer of information.  Measuring Up to Encourage Desired Behavior:  "You get what you measure, in fact you get only what you measure, nothing else. So you tend to lose the things that you can't measure, like knowledge sharing, insight, collaboration and creativity”  How we can overcome this issue? We measure up .  Measure up means, that we measuring something at one level above the normal span of control (The team level rather than the individual level) to encourage teamwork, collaboration, and global, rather than local optimization.  Tracking velocity is an example of measuring up. We could quite easily trace velocity to individual team members and determine who is the most productive, but this approach would likely encourage negative behaviors and a lack of cooperation. So instead we measure velocity at a team level; as a result, team members are motivated to help each other.
  • 16. Continuous Improvement – Process Tailoring  When we tailor processes on agile projects, we amend the methodology to better fit the project environment we are using it in.  Some methodologies are quite tailoring-friendly, some are not.  There are benefits and risks with both extremes. When considering the question of whether process tailoring is appropriate, we should first recognize that all projects are different. They solve different problems, face different challenges, utilize different people, and operate in different organizations with different cultures and norms.  We have two point of views here:  Create process-per-project approach—in other words, creating processes that are situationally specific for the job at hand.  Maintain an adherence to agile values and practices. Supports of this approach says that methodologies may transform the agile approach beyond recognition and then, when projects fail, those failures will be blamed on agile.  Process tailoring can be effective and productive, but that we should be aware of the risks involved in this practice. The following are the key ways to mitigate these risks:  Get used to normal, out-of-the-box agile before attempting to change it. The methods were created based on the collective wisdom of many experienced practitioners, so don't be too hasty to change them.  Carefully examine the motivation to drop, amend, or append a practice. Is the change a lazy cop-out to avoid a more fundamental problem, or will it truly address a gap or be a value-add unique to the environment?
  • 17. Continuous Improvement – Principles of System Thinking  Software projects are characterized by the level of complexity around requirements, as well as the complexity of the technology used on the projects. agreement Far from Chaos Requirement Agile works Low Complex well here Complexity agreement Low Close to Simple Complexity Close to Far from Technology certainty certainty
  • 18. Continuous Improvement – Principles of System Thinking  We see projects range from simple (lower left) up to those categorized as anarchy or chaos (upper right).  An agile approach works really well for projects in the middle ground. These projects are complex and have uncertainty around both requirements and the technical approach.  Agile methods can of course be used for simple projects, too, in which the organization and the team will get the benefits of increased collaboration, communication, and visibility, but simple projects can be run just fine with traditional approaches as well. In contrast, complex projects begin to struggle when they are merged with traditional methods.  If there is no clear agreement on what we are supposed to be building or what approach and tools we are using to build it, then our project is in a state of chaos. In this case, neither agile nor any other approach can assure success.  We have to keep in mind this system-level understanding of the environment in which agile projects are operating when we think about modifying the methods.
  • 19. Continuous Improvement – Process Analysis  Process analysis is closely related to process tailoring and the principles of systems thinking. When we perform process analysis, we are reviewing and diagnosing issues with agile methods or, more likely, our home-grown add-ons and replacements to agile methods. This analysis may then lead to a decision to tailor the process.  Anti-Patterns (bad things to watch out about methodologies):  One size for all projects: it not possible to create the optimal methodology for all types of projects, al technologies, and all team sizes.  Intolerant: A methodology is like a straightjacket in that it is a set of conventions and policies people agree to adhere to and use. The size and shape of the straightjacket should be chosen by the team and should not be made any tighter than necessary, so people have a little wiggle room in their actions.  Heavy: There is a common but incorrect belief that the heavier a methodology is in artifacts and practices, the safer it is. However, adding weight to a methodology is not likely to improve the team's chance of delivering the project successfully. Instead, it diverts the team's time from the real goal of the project.  Embellished: All methods tend to get embellished. We add in things that we think we "ought to" or "should" be doing, but we need to look out for these words as signals for potentially expensive, error-prone additions. Get the people directly affected by the process to review the methodology, and watch their faces closely for indications of what they know they won't do but are afraid to admit they won't do; these items are the embellishments.
  • 20. Continuous Improvement – Process Analysis  Anti-Patterns-Cont.  Untried: Many methodologies are untried. They are proposals created from nothing and are full- blown "shoulds" in action. For example, how often have you heard statements like, "Well, this really looks like it should work"? Instead of creating complex theoretical methodologies, it is better to reuse, adjust, tune, and create just what is needed. See what actually works on projects and use that, not something untried that we believe "should work.“  Used once: A methodology that is used once is a little better than one that is untried, but it is still no recipe for success. The reality is that different projects likely need different approaches, and just because an approach worked under one set of circumstances does not guarantee it will work under another.  Process Success Criteria:  The project got shipped: The product went out the door.  The leadership remained intact: They didn't get fired for what they were doing (or not doing).  The people on the project would work the same way again: They found the approach to be effective and enjoyable.
  • 21. Continuous Improvement – Process Analysis  Seven Principles that tells us if the methodology tend to success criteria:  Interactive, face-to-face communication is the cheapest and fastest channel for exchanging information.  Excess methodology weight is costly  Larger teams need heavier methodologies  Greater ceremony is appropriate for projects with greater criticality  Increasing feedback and communication reduces the need for intermediate deliverables  Discipline, skills, and understanding counter process, formality, and documentation  Efficiency is expendable in non-bottleneck activities
  • 22. Continuous Improvement – Continuous Improvement Processes  Continuous improvement is the ongoing process of enhancing the project approach and the product.  This process is never completed; instead, it continues throughout the project in much the same way as stakeholder communications do.  Continuous improvement is something we will always do.  It is more like a journey than a destination, since it is always ongoing and is part of the iterative life cycle that drives agile methods.  Continuous Improvement works on two levels:  Continuous Process Improvement  Continuous Product Improvement
  • 23. Continuous Improvement – Continuous Improvement Processes  Continuous Process Improvement: Agile Cycle  The agile cycle employs a continuous cycle of Plan, Develop, Evaluate, and Learn.  This cycle is very similar to Deming’s “Plan, Do, Check, Act” cycle for problem solving and continuous improvement.  The "Develop" phase in the agile life cycle is like Deming's "Do" phase. "Evaluate" is equivalent to the "Check" phase. In the "Learn" phase, we apply the lessons from the project, in much the same way as the "Act" phase in Deming's cycle. And the "Plan, Do, Check, Act" cycle is again mirrored in agile methods with demos, reviews, and retrospectives. Plan, Do, Check, Act Cycle Plan Act Do Check
  • 24. Continuous Improvement – Continuous Improvement Processes  Continuous Product Improvement:  Just as the team practices and processes are being refined iteratively and continuously, so too is the evolving product.  Iterative and incremental development is a form of continuous improvement, with customer feedback steering us toward the final solution.  When the team builds small increments and get feedback, the product evolves toward the true business requirements. And sometimes the true business requirements may be quite different from the originally stated requirements, as the process of creation illuminates better options.  By this cycle of developing in small increments, reviewing, discussing how to improve, and then doing some more development and maybe enhancing a few things, the product or service is incrementally built through a process of continuous improvement.
  • 25. Continuous Improvement – Self Assessment  Assessments of how to improve are not reserved just for the process and product; they are also done on the people side of the project, which is arguably the area that offers the greatest payback.  “James Shore” offers a self-assessment quiz and scoring model that is focused on XP practices, teams can use this model to gauge their performance.  The quiz and scoring graph measures how teams perform within the following categories:  Thinking  Collaborating  Releasing  Planning  Developing  The quiz is completed by answering questions within each category and scoring the answers on a 0-100 scale.
  • 26. Continuous Improvement – Self Assessment  Once all the questions have been asked and scored, the results are plotted on a radar (spider) diagram. Thinking 100  The team is then involved in analyzing the 80 chart to identify which areas could use 60 40 improvement. Developing 20 Collaborating 0 Planning Releasing
  • 27. Continuous Improvement – Self Assessment  Another model for assessing high-performing teams is offered by “Jean Tabaka”, this model investigate the following areas:  Self-organization: Is the team self-organizing, rather than functioning in a command-and-control, top-down organization?  Empowered to make decisions: Is the team empowered to discuss, evaluate, and make decisions, rather than being dictated to by an outside authority?  Belief in vision and success: Do team members understand the project vision and goals, and do they truly believe that, as a team, they can solve any problem to achieve those goals?  Committed team: Are team members committed to succeed as a team, rather than being committed to individual success at any cost?  Trust each other: Does the team have the confidence to continually work on improving their ability to act without fear, anger, or bullying?  Participatory decision making: Is the team engaged in participatory decision making, rather than bending to authoritarian decision making or succumbing to decisions from others?  Consensus-driven: Are team decisions consensus-driven, rather than leader-driven? Do team members share their opinions freely and participate in the final decision?  Constructive disagreement: Is the team able to negotiate through a variety of alternatives and impacts surrounding a decision, and craft the one that provides the best outcome?
  • 28. Practice Exam 1. Your sponsor is asking about tailoring the company's newly adopted agile methodology. Your advice should be: A. Tailoring it will be a good way to learn the methodology B. Tailoring it will be a good way to ease into the initial adoption process C. We should tailor it first, then consider adopting it D. We should try it first, then consider tailoring it 2. When conducting a retrospective, recognized "close the retrospective" activities include: A. Plus/Delta; Helped, Hindered, Hypothesis; Return on Time Invested; Appreciations B. Plus/Minus; Helped, Hindered, Hoped; Return on Time Invested; Applause C. Plus/Delta; Helped, Hindered, Hoped; Return on Investment; Appreciations D. Plus/Minus; Helped, Hindered, Hypothesis; Return on Time Delivered; Appreciations 3. You have been asked to review a different project team's recently enhanced methodology to assess its effectiveness and desirable characteristics. 'The types of characteristics that you should be looking for include evidence of: A. A preference for face-to-face communications, significant process weight, recommendations for larger teams to use lighter methods B. A preference for face-to-face communications, not too much process weight, recommendations for larger teams to use lighter methods C. A preference for face-to-face communications, significant process weight, recommendations for larger teams to use heavier methods D. A preference for face-to-face communications, not too much process weight, recommendations for larger teams to use heavier methods 4. The concept of knowledge sharing on an agile project is best characterized as: A. Encouraged where possible and where the team shows an interest B. Central to many of the practices undertaken C. Undertaken if there is time left at the end of an iteration D. Undertaken principally through stand-up meetings
  • 29. Practice Exam 5. Continuous improvement is a core component of which of the following set of agile practices? A. Pair programming; daily stand-up meetings; WIP limits B. Story points; daily stand-up meetings; demos, reviews, and retrospectives C. Pair programming; daily stand-up meetings; demos, reviews, and retrospectives D. Story points; daily stand-up meetings; WIP limits 6. When considering process tailoring, it is useful to keep in mind that the network of XP practices is: A. Redundant B. Duplicated C. Optional D. Balanced 7. The recommended stages of executing a retrospective, in sequence, are: A. Decide what to do, set the stage, gather data, generate insights, close the retrospective B. Decide what to do, gather data, set the stage, generate insights, close the retrospective C. Set the stage, decide what to do, gather data, generate insights, close the retrospective D. Set the stage, gather data, generate insights, decide what to do, close the retrospective 8. You are engaging in some process analysis and have been advised to watch out for the standard anti-patterns of poor methodology practice. The types of things you should be on the lookout for are processes that display signs of being: A. One-of-a-kind, disciplined, heavy, embellished B. One-size-fits-all, disciplined, heavy, embellished C. One-size-fits-all, intolerant, heavy, embellished D. One-of-a-kind, intolerant, embellished
  • 30. Practice Exam 9. Process tailoring is best undertaken on agile projects when: A. There are difficulties in implementing agile practices B. Experienced practitioners want to address an issue C. The team needs new processes to keep them engaged D. A boost in team velocity is needed to meet the schedule 10. Your project management office (PMO) has suggested your project could benefit from some self- assessment work at the next retrospective. Which of the following benefits would they most likely be looking to achieve from a self-assessment? A. Improve personal and team practices B. Gain insights for salary performance reviews C. Identify personal traits for human resources counseling D. Assess compatibilities for pair programming assignments 11. When undertaking process analysis, what are the success criteria that characterize a useful methodology? A. The project got stopped, sponsorship remained intact, the team would work the same way again B. The project got shipped, leadership remained intact, the team would work the same way again C. The project got shipped, sponsorship remained intact, the team would work the same way again D. The project got shipped, sponsorship remained intact, the team engaged in continuous improvement 12. When adopting a new agile practice, the general recommendations are to: A. Develop the new approach yourself, try out the practice on local projects, inspect and review the findings early B. Investigate the claims yourself, try out the practice on local projects, inspect and review the findings early C. Investigate the claims yourself, try out the practice in small doses, inspect and review the findings early D. Develop the new approach yourself, try out the practice in small doses, inspect and review the findings early
  • 31. Practice Exam 13. As a manager of an agile team, when should you collect lessons learned? A. At the end of the project B. Throughout the project C. When projects go well D. When projects go poorly 14. Information exchanges in agile methods are designed to: A. Facilitate knowledge sharing B. Leverage electronic knowledge-sharing tools C. Maximize resource utilization D. Generate stable specifications

Notas del editor

  1. The immediate application of lessons learned is especially critical for quickly changing projects and for projects with high degrees of uncertainty and risk, where staying the course could be fatal to the project if circumstances change.
  2.  Since retrospectives happen during the project, the lessons and improvements that result from them are applicable and relevant to upcoming work; after all, the upcoming work will have the same business domain, technical domain, and team dynamics as the iteration being assessed
  3. In setting the stage, we aim to:Explain why we are doing the retrospectiveGet people talking so they are comfortable contributing throughout the retrospectiveOutline the approach and topics of the retrospectiveEstablish ground rulesCheck safety levels; in other words, determine if people feel comfortable enough to contribute to the review
  4. Plus/Delta In this exercise, we capture and validate the team's ideas for what we should do more of (things that are going well) and what we should change (things that are not going well) on a whiteboard or flip chart.Helped, Hindered, Hypothesis This exercise helps generate feedback on the retrospective process itself and produces ideas for improvement. To run this session, we first prepare three flip charts, one titled "Helped," one titled "Hindered," and the last with the title of "Hypothesis:' We explain to the team that we are looking to improve the retrospective process and would like feedback on what they think helped, what was a hindrance, and any ideas for improvement (hypotheses) for retrospectives going forward. Participants then write ideas on sticky notes and post the notes on the appropriate flip chart.Return on Time Invested (ROTI) This is another exercise to generate feedback on the retrospective process. This exercise focuses on whether people believe their time was well spent.Appreciations During this exercise, team members have a chance to express appreciation to other team members for their help, contributions, problem-solving efforts, etc.
  5. KimizDalkir identifies that
  6. Talk about Multiple Layers of Continuous Improvement on Agile ProjectsContinuous improvement is also layered like an onion. In software development projects, for example, continuous improvement happens at the code level with pair programming. One person is writing code, and the other is reviewing, critiquing, and suggesting improvements. Daily stand-up meetings discuss work done and any issues or impediments on the project. These issues then become the "to-do" items for the Scrum_Master or project manager, who is responsible for removing impediments and improving the process. At a broader level, the iteration demo, review, and retrospective cycles that occur at a biweekly or monthly cadence purposely examine the process and look for improvements to make in the next iteration.