4. Euclid Creek Tunnel:
By the Numbers
• Tunnel • Shafts: 5 total
– 24’ diameter – 24’ to 60’ diameter
– 9,500/17,750’ – 185-225’ deep
– 60,100,000 gallons • 2,465 linear feet of
• ~30 near surface open cut pipe placed
structures • 2,110 linear feet of
– 11 complete microtunnel complete
– 12under construction – 240 more to go
euclidcreek.blogspot.com
5. Shaft #1: Construction Staging Site
• “Mackenzie” tunneled and lined 9,450’
• Operating 24/7 with regularly-scheduled
maintenance periods
• Lake Erie tunneling completed
euclidcreek.blogspot.com
8. Shaft #2: Easterly WWTP
• Shaft 2: 95 feet excavated
– Blasting last 100 feet; will begin this year
• Structure 2-2: installing final lining
• Structure 2-8: installing support of excavation
euclidcreek.blogspot.com
11. Shaft #3: Beulah Park
• East 156th Street
– West side sidewalk still closed
– Currently reduced to single lane for dewatering
well installation; flaggers are present
– Commenced soft ground excavation
euclidcreek.blogspot.com
17. Shaft #3: Beulah Park
• Structure Monitoring
– Letters distributed April 10, 2013
• DMP installed April 22, 2013
euclidcreek.blogspot.com
18. Site #4: Triangle Park
• Excavation work is complete at this site
• Currently installing baffle drop structures
• Fencing will remain throughout 2014
• Completed structure in Nottingham
euclidcreek.blogspot.com
20. Site #4: Lakeshore Blvd. Relief Sewer
• 66” trenchless sewer pipe, microtunneled
from Euclid Creek Pump Station to Shaft 4
euclidcreek.blogspot.com
21.
22. Site #5: Nottingham & St. Clair
• Excavation complete of Shaft 5:
225 feet excavated
• Commenced excavation of Structure 5-4
• 500 cy concrete pour April 8th
euclidcreek.blogspot.com
25. Stay Informed
• Blog
– EuclidCreek.blogspot.com
• Collinwood Observer
– Ads and articles
• Semi-Monthly Newsletter
– E-mail distribution
– eltingj@neorsd.org to be added to the list
euclidcreek.blogspot.com
26. How to Reach Us
Social Media
facebook.com/yoursewerdistrict
@neorsd | @wallywaterdrop
Customer Service
(216) 881-8247
Emergencies: NEORSD ECT Field Office
(216) 268-5469
Ryan Sullivan, sullivanr@neorsd.org
Jenn Elting, eltingj@neorsd.org
euclidcreek.blogspot.com
27. Next Meeting
Tuesday, May 21, 2013
6:00 p.m.
Cleveland Public Library,
Memorial-Nottingham Branch
Save the Date!
June 18
July 16
August 20
euclidcreek.blogspot.com