SlideShare una empresa de Scribd logo
1 de 21
Casting Yard
Introduction
A casting yard is a confined place where all the concrete structures like
segments, parapets, I- girders/beams, boundary wall panels, cable troughs
etc. Re-casted/manufactured, shifted to their stack yard, cured for the
specific period/days and then shifted to the working site/viaduct after
they gain their required strength.
Layout of Casting Yard
Requirements of a Casting Yard
• Site for any Casting Yard should be easily accessible from all site locations.
• Land should be available from 25 Acres to 40 Acres for establishing a
casting yard.
• Approach Road leading to Casting Yard should be easily identified.
• Good Environmental conditions.
• It should not more than 3 to 4 kms from working site.
• Proper Drinking Water facilities for Engineers, Supervisors & Labours.
• Canteen facilities for the staff & Labours.
• Medical treatment Centre in case of emergency.
Casting methods
• Long-Line Method
• Short Line Method
Long Line Method
•

All segments of a span are manufactured on a fixed bed with the
formwork moving along the bed for successive casting operation.
• Shows profile of real structure at one time.
• Pier segment is cast first between the fixed bulkhead and the removable
formwork, then the segments.
Short Line Method
• It is a match casting process.
• Stationary forms are used next to the previously cast segment in order to
get a homogeneous perfect fitting match-cast joint.
Match-cast segment
To the stock yard
Match-casting for a vertical curve
• Match cast segment first translated from its original position and then give
a small rotation in the vertical plane w.r.t. the horizontal axis.
Match-casting for a horizontal curve
• Match-cast segment is first moved to its position by pure translation and
then the segment is rotated in plan w.r.t. the vertical axis.
Geometry Control
• Establishment stations to the north and south side of the segment before
the casting is must.
• Tolerances are in the order of a fraction of a millimeter.

Geometry control Program
•
•
•
•
•

Calculate the theoretical casting coordinates of segment n.
Measure the actual casting coordinates
Calculate error in casting
Calculate correction to be made in casting n+1 match-casting with n
Adjust match-casting of n to compensate for error while
casting n+1
Batching & mixing of concrete







Raw material
Cement (OPC grade 53)
Fly Ash (Maximum 30% of cement)
Water (between 0.1 & 0.4)
Admixture (SP-430, SP-432)
Fine aggregate
Coarse aggregates of 10mm & 20mm size
Batching procedure
• Batching plant may be of manually operated type or may be operated with
the help of computer aided software.
• The quantities are filled in the computer and start key is pressed, the
sensors provided near the gates get into action and according to the load
scale value, that much quantity of sand, 10mm aggregates, & 20mm
aggregates are filled in a bucket.
• When the required quantity of the aggregates is filled the gates get closed
automatically and the bucket is pulled up.
For fine & coarse aggregate

For cement & fly ash
• As the bucket reaches the top, its contents are put into a mixing
pan, where it gets mixed with the cement, water & admixtures from their
separate hoppers.

Mixing tank
Quality Control
Survey Procedures
• Initial Set Up Survey - required for formwork setting and getting the match
cast segment in “rough” position
• Final Set Up Survey - required for final adjustments of the match cast
segment and small adjustments to the formwork once the forms have
been closed up to final position
• As Cast Survey - required to obtain “as cast” data on the segment used to
determine the positioning of the segment in the “match cast” position
• Inputting Data – required for geometry control for the
for the next segment to be cast
Test of concrete
For Ordinary Concrete
• Slump test
• Setting time test
Initial setting time
Final setting time
• Compressive strength test
For self compacting Concrete
• Flow test
• V-funnel test
• L box test
Result : 120 mm
Test cubes for compression test
Precast vs Cast in Place Concrete
Precast
High Quality Control

Cast in place
Less Quality Control

Casting cannot be delayed due to weather It may be delayed.
conditions
Controlled pour conditions, strict quality
control measures and factory strength
testing ensure pre-cast concrete strength
and durability specifications.

Uncontrolled factors can decrease the
strength and durability of freshly poured
concrete.

Flexibility to make changes to structure
right up until the minute the concrete is
poured in the form

Last minute changes are difficult to make
and cost money
THANK YOU!

Más contenido relacionado

La actualidad más candente

Well Foundation
Well FoundationWell Foundation
Well Foundationakjain_mkt
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentationRahul bhatnagar
 
Bridge inspection,maintenance and repair
Bridge inspection,maintenance and repairBridge inspection,maintenance and repair
Bridge inspection,maintenance and repairKartikSuryawanshi2
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...Arman Hashmi
 
Metro ppt-180628112005
Metro ppt-180628112005Metro ppt-180628112005
Metro ppt-180628112005PRATAP MISHRA
 
Precast segmental construction of bridges
Precast segmental construction of bridgesPrecast segmental construction of bridges
Precast segmental construction of bridgesmukul srivastava
 
Ppt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasadPpt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasadLachhmikant. Prasad
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge ConstructionMAHAVIR MEENA
 
Design of rcc structures
Design of rcc structuresDesign of rcc structures
Design of rcc structuresR VIJAYAKUMAR
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)RAMPRASAD KUMAWAT
 
Metro Construction
Metro ConstructionMetro Construction
Metro ConstructionMayur Soni
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road constructionAnitha Jacob
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavementpradip dangar
 

La actualidad más candente (20)

Well Foundation
Well FoundationWell Foundation
Well Foundation
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentation
 
Bridge inspection,maintenance and repair
Bridge inspection,maintenance and repairBridge inspection,maintenance and repair
Bridge inspection,maintenance and repair
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
 
Metro ppt-180628112005
Metro ppt-180628112005Metro ppt-180628112005
Metro ppt-180628112005
 
Precast segmental construction of bridges
Precast segmental construction of bridgesPrecast segmental construction of bridges
Precast segmental construction of bridges
 
UNDERPASS DESIGN
UNDERPASS DESIGNUNDERPASS DESIGN
UNDERPASS DESIGN
 
Ppt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasadPpt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasad
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge Construction
 
Viaduct segment
Viaduct segmentViaduct segment
Viaduct segment
 
Design of rcc structures
Design of rcc structuresDesign of rcc structures
Design of rcc structures
 
Design of barrages
Design of barragesDesign of barrages
Design of barrages
 
Tunnel engineering
  Tunnel engineering  Tunnel engineering
Tunnel engineering
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
1.1 box jacking
1.1 box jacking1.1 box jacking
1.1 box jacking
 
Pile foundation
Pile  foundation Pile  foundation
Pile foundation
 
Metro Construction
Metro ConstructionMetro Construction
Metro Construction
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road construction
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
Deck slab bridge
Deck slab bridgeDeck slab bridge
Deck slab bridge
 

Destacado

Hyderabad metro rail L&T | Construction sequence and procedure
Hyderabad metro rail L&T | Construction sequence and procedureHyderabad metro rail L&T | Construction sequence and procedure
Hyderabad metro rail L&T | Construction sequence and procedureAravind Samala
 
NATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in TunnelingNATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in TunnelingHamed Zarei
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 
Top down construction
Top down constructionTop down construction
Top down constructionAmulya Kansal
 
Shield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and LessonsShield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and Lessonscoen_van_der_vliet
 
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)Hamed Zarei
 
New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)Austrian Standards
 
World Tunnel Conference 2014
World Tunnel Conference 2014World Tunnel Conference 2014
World Tunnel Conference 2014richardbieniawski
 
Tunneling Construction - NATM
Tunneling Construction - NATMTunneling Construction - NATM
Tunneling Construction - NATMluisaam
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt1971995
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete constructionMadan Mohan Jana
 
Basics of bridge construction
Basics of bridge constructionBasics of bridge construction
Basics of bridge constructionsymphonyjo
 

Destacado (20)

PPT OF LG
PPT OF LGPPT OF LG
PPT OF LG
 
Hyderabad metro rail L&T | Construction sequence and procedure
Hyderabad metro rail L&T | Construction sequence and procedureHyderabad metro rail L&T | Construction sequence and procedure
Hyderabad metro rail L&T | Construction sequence and procedure
 
NATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in TunnelingNATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in Tunneling
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
Top down construction
Top down constructionTop down construction
Top down construction
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Shield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and LessonsShield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and Lessons
 
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
 
New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)
 
World Tunnel Conference 2014
World Tunnel Conference 2014World Tunnel Conference 2014
World Tunnel Conference 2014
 
Tunnels concepts
Tunnels conceptsTunnels concepts
Tunnels concepts
 
Bridge 91 Design
Bridge 91 DesignBridge 91 Design
Bridge 91 Design
 
Tunneling
Tunneling Tunneling
Tunneling
 
Directional Drilling
Directional DrillingDirectional Drilling
Directional Drilling
 
Tunneling Construction - NATM
Tunneling Construction - NATMTunneling Construction - NATM
Tunneling Construction - NATM
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
 
Dam PPT
Dam PPTDam PPT
Dam PPT
 
PreCast Construction
PreCast ConstructionPreCast Construction
PreCast Construction
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Basics of bridge construction
Basics of bridge constructionBasics of bridge construction
Basics of bridge construction
 

Similar a Casting yard

Construction of well foundation
Construction of well foundation Construction of well foundation
Construction of well foundation dilip patidar
 
deep foundation for hidth buliding (7).ppt
deep foundation  for hidth buliding (7).pptdeep foundation  for hidth buliding (7).ppt
deep foundation for hidth buliding (7).pptAbdulwalimusemohamed
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing TechniqueSeminar Links
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete Sreekutty S
 
Operation and Well Setting GTI SEG-SUSC 08-10-2016
Operation and Well Setting GTI SEG-SUSC 08-10-2016Operation and Well Setting GTI SEG-SUSC 08-10-2016
Operation and Well Setting GTI SEG-SUSC 08-10-2016Mohamed _el_shora
 
Non Destructive Test
Non Destructive TestNon Destructive Test
Non Destructive TestParth Desani
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptxRaviUraiya1
 
Non destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptxNon destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptxReigerRoyal
 
8. Road Construction Technology.pdf
8. Road Construction Technology.pdf8. Road Construction Technology.pdf
8. Road Construction Technology.pdfEr. Bam Bhandari
 
Construction practices and quality control
Construction practices and quality controlConstruction practices and quality control
Construction practices and quality controlSIBENDU SURAJEET JENA
 
1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptx1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptxJanak82
 
Construction Survey
Construction SurveyConstruction Survey
Construction Surveyhalmifaizol
 

Similar a Casting yard (20)

Construction of well foundation
Construction of well foundation Construction of well foundation
Construction of well foundation
 
Lining in tunnels
Lining in tunnelsLining in tunnels
Lining in tunnels
 
2022-07-13.pptx
2022-07-13.pptx2022-07-13.pptx
2022-07-13.pptx
 
Mahi ppt suez (2)
Mahi ppt suez (2)Mahi ppt suez (2)
Mahi ppt suez (2)
 
Concreting work
Concreting workConcreting work
Concreting work
 
Summer training report
Summer training reportSummer training report
Summer training report
 
deep foundation for hidth buliding (7).ppt
deep foundation  for hidth buliding (7).pptdeep foundation  for hidth buliding (7).ppt
deep foundation for hidth buliding (7).ppt
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
Concrete
ConcreteConcrete
Concrete
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete
 
Operation and Well Setting GTI SEG-SUSC 08-10-2016
Operation and Well Setting GTI SEG-SUSC 08-10-2016Operation and Well Setting GTI SEG-SUSC 08-10-2016
Operation and Well Setting GTI SEG-SUSC 08-10-2016
 
Board pile method
Board pile methodBoard pile method
Board pile method
 
Non Destructive Test
Non Destructive TestNon Destructive Test
Non Destructive Test
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptx
 
Non destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptxNon destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptx
 
8. Road Construction Technology.pdf
8. Road Construction Technology.pdf8. Road Construction Technology.pdf
8. Road Construction Technology.pdf
 
Construction practices and quality control
Construction practices and quality controlConstruction practices and quality control
Construction practices and quality control
 
1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptx1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptx
 
Construction Survey
Construction SurveyConstruction Survey
Construction Survey
 
2022 Spring Educational Workshop presentation on QA for CIR and CCPR
2022 Spring Educational Workshop presentation on QA for CIR and CCPR2022 Spring Educational Workshop presentation on QA for CIR and CCPR
2022 Spring Educational Workshop presentation on QA for CIR and CCPR
 

Último

ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxVanesaIglesias10
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)cama23
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4JOYLYNSAMANIEGO
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4MiaBumagat1
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYKayeClaireEstoconing
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Seán Kennedy
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfErwinPantujan2
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...Postal Advocate Inc.
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 

Último (20)

ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptx
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
 
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptxYOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 

Casting yard

  • 2. Introduction A casting yard is a confined place where all the concrete structures like segments, parapets, I- girders/beams, boundary wall panels, cable troughs etc. Re-casted/manufactured, shifted to their stack yard, cured for the specific period/days and then shifted to the working site/viaduct after they gain their required strength.
  • 4. Requirements of a Casting Yard • Site for any Casting Yard should be easily accessible from all site locations. • Land should be available from 25 Acres to 40 Acres for establishing a casting yard. • Approach Road leading to Casting Yard should be easily identified. • Good Environmental conditions. • It should not more than 3 to 4 kms from working site. • Proper Drinking Water facilities for Engineers, Supervisors & Labours. • Canteen facilities for the staff & Labours. • Medical treatment Centre in case of emergency.
  • 5. Casting methods • Long-Line Method • Short Line Method
  • 6. Long Line Method • All segments of a span are manufactured on a fixed bed with the formwork moving along the bed for successive casting operation. • Shows profile of real structure at one time. • Pier segment is cast first between the fixed bulkhead and the removable formwork, then the segments.
  • 7. Short Line Method • It is a match casting process. • Stationary forms are used next to the previously cast segment in order to get a homogeneous perfect fitting match-cast joint.
  • 9. Match-casting for a vertical curve • Match cast segment first translated from its original position and then give a small rotation in the vertical plane w.r.t. the horizontal axis.
  • 10. Match-casting for a horizontal curve • Match-cast segment is first moved to its position by pure translation and then the segment is rotated in plan w.r.t. the vertical axis.
  • 11. Geometry Control • Establishment stations to the north and south side of the segment before the casting is must. • Tolerances are in the order of a fraction of a millimeter. Geometry control Program • • • • • Calculate the theoretical casting coordinates of segment n. Measure the actual casting coordinates Calculate error in casting Calculate correction to be made in casting n+1 match-casting with n Adjust match-casting of n to compensate for error while casting n+1
  • 12. Batching & mixing of concrete       Raw material Cement (OPC grade 53) Fly Ash (Maximum 30% of cement) Water (between 0.1 & 0.4) Admixture (SP-430, SP-432) Fine aggregate Coarse aggregates of 10mm & 20mm size
  • 13. Batching procedure • Batching plant may be of manually operated type or may be operated with the help of computer aided software. • The quantities are filled in the computer and start key is pressed, the sensors provided near the gates get into action and according to the load scale value, that much quantity of sand, 10mm aggregates, & 20mm aggregates are filled in a bucket. • When the required quantity of the aggregates is filled the gates get closed automatically and the bucket is pulled up.
  • 14. For fine & coarse aggregate For cement & fly ash
  • 15. • As the bucket reaches the top, its contents are put into a mixing pan, where it gets mixed with the cement, water & admixtures from their separate hoppers. Mixing tank
  • 16. Quality Control Survey Procedures • Initial Set Up Survey - required for formwork setting and getting the match cast segment in “rough” position • Final Set Up Survey - required for final adjustments of the match cast segment and small adjustments to the formwork once the forms have been closed up to final position • As Cast Survey - required to obtain “as cast” data on the segment used to determine the positioning of the segment in the “match cast” position • Inputting Data – required for geometry control for the for the next segment to be cast
  • 17. Test of concrete For Ordinary Concrete • Slump test • Setting time test Initial setting time Final setting time • Compressive strength test For self compacting Concrete • Flow test • V-funnel test • L box test
  • 19. Test cubes for compression test
  • 20. Precast vs Cast in Place Concrete Precast High Quality Control Cast in place Less Quality Control Casting cannot be delayed due to weather It may be delayed. conditions Controlled pour conditions, strict quality control measures and factory strength testing ensure pre-cast concrete strength and durability specifications. Uncontrolled factors can decrease the strength and durability of freshly poured concrete. Flexibility to make changes to structure right up until the minute the concrete is poured in the form Last minute changes are difficult to make and cost money