SlideShare una empresa de Scribd logo
1 de 8
<PROJECT NAME>
RISK MANAGEMENT PLAN
Version <1.0>
04/08/2013
Risk Management Plan
<Project Name> Version: 1.0
TABLE OF CONTENTS
1 INTRODUCTION......................................................................................................................1
1.1 Purpose Of The Risk Management Plan............................................................................1
2 RISK MANAGEMENT PROCEDURE...................................................................................2
2.1 Process................................................................................................................................2
2.2 Risk Identification..............................................................................................................3
2.3 Risk Analysis......................................................................................................................3
2.3.1 Qualitative Risk Analysis........................................................................................3
2.3.2 Quantitative Risk Analysis......................................................................................4
2.4 Risk Response Planning.....................................................................................................5
2.5 Risk Mitigation and Avoidance..........................................................................................5
3 RISK REGISTER.......................................................................................................................6
6
Risk Management Plan
<Project Name> Version: 1.0
1 INTRODUCTION
1.1 PURPOSE OF THE RISK MANAGEMENT PLAN
Any kind of project is susceptible to risks of various natures that can have different degrees
of effect in the normal project. It may or may not have positive or negative effects on a
project’s objectives. Risk Management assists in the prevention and minimization of
unfavorable events. The objective of a risk management is to secure the project from risks
by identifying, assessing, responding to, monitoring, and reporting risks.
The purpose of the risk management plan is to establish the framework in which the
project team will identify risks and develop strategies to mitigate or avoid those risks.
However, before risks can be identified and managed, there are preliminary project
elements which must be completed. These elements are outlined in the risk management
approach.
This project is considered a medium risk project as it has an overall risk score of 24 on a
scale from 0 to 100. The project risk score is the average of the risk scores of the most
significant risks to this project. A risk score below 16 is low risk project, a score between
16 and 45 is a medium risk project and a score above 45 is a high-risk project.
Before risk management begins it is imperative that a foundation is established for
providing structured project information, thus, the following project elements were
completed and defined prior to developing this Risk Management Plan:
• Define work scope, schedule, resources, and cost elements
o Develop project WBS/WBS dictionary
o Develop master schedule and detailed schedules
o Estimate project cost and finalize budget
o Identify required and available resources
o Establish performance measurement metrics
• Define minimum and maximum baseline thresholds
o Schedule
o Resources
o Cost
• Baseline reporting requirements
o Format
o Frequency of distribution
o Distribution list
• Define Risk Management Roles and Responsibilities
o Project Manager chairs the risk assessment meetings
Page 1
Risk Management Plan
<Project Name> Version: 1.0
o Project team participates in risk assessment meetings and members serve as
meeting recorder and timekeeper
o Key stakeholders participate in risk assessment meetings
o Project Sponsor may participate in risk assessment meetings
The Risk Management Plan for the Construction of Scrap Tire Recycling Plant gives an
outline of the risk associated with the project by identifying, analyzing and managing the
risks involved.
2 RISK MANAGEMENT PROCEDURE
2.1 PROCESS
The approach we have taken to manage risks for Construction of Scrap Tire recycling Plant
included a methodical process by which the project team identified, scored, and ranked the
various risks. The most likely and highest impact risks were added to the project schedule
to ensure that the assigned risk managers take the necessary steps to implement the
mitigation response at the appropriate time during the schedule. Risk managers will
provide status updates on their assigned risks in the bi-weekly project team meetings, but
only when the meetings include their risk’s planned timeframe. Upon the completion of
the project, during the closing process, the project manager will analyze each risk as well
as the risk management process. Based on this analysis, the project manager will identify
any improvements that can be made to the risk management process for future projects.
These improvements will be captured as part of the lessons learned knowledge base.
The risk management process gives an outline to Project Manager and all the project
personnel of the future risk and gives an ample amount of time to come up with the
solutions beforehand. A well articulated Risk Management Plan helps in utmost resource
utilization, meet scheduling on time and prevent unwanted risks associated.
The risk management process comprises of some steps, but is not limited to, and if
followed properly helps in mitigating the risk or minimizing the effects. Some of the steps
are identifying the risk, identifying the source of the risk, measuring, evaluating, mitigating
and monitoring the risk.
The diagram below depicts the various steps involved in the risk management process.
Page 2
Risk Management Plan
<Project Name> Version: 1.0
2.2 RISK IDENTIFICATION
The task of the Risk Management Manager would be to identify all the risks associated
with the Construction of Scrap Tire Recycling Plant and submit it during the risk
identification process. After acquiring all the details about the risks the project team,
appropriate stakeholders would work on handling the risks. This process would also
include an evaluation of environmental factor, organizational culture and the project
management plan including the project scope.
Some of the important factors, which will be included in the identification process, are
project deliverables, assumptions, constraints, WBS, cost/effort estimates, resource plan,
and other key project documents.
A Risk Management Log will then be created and updated as and when needed. The log
will be stored electronically which can be used for future reference.
2.3 RISK ANALYSIS
In order to determine the severity of the risks identified by the team, a probability and
impact factor was assigned to each risk. This process allowed the project manager to
prioritize risks based upon the effect they may have on the project. The project manager
utilized a probability-impact matrix to facilitate the team in moving each risk to the
appropriate place on the chart.
Once the risks were assigned a probability and impact and placed in the appropriate
position on the chart, the recorder captured the finished product and the project manager
moved the process on to the next step: risk mitigation/avoidance planning
2.3.1 Qualitative Risk Analysis
The Project Manager will assess each identified risk based on the probability and impact of
occurrence for each risk, with input from the project team using the following approach:
Page 3
Risk Management Plan
<Project Name> Version: 1.0
Probability
• High – Greater than <70%> probability of occurrence
• Medium – Between <30%> and <70%> probability of occurrence
• Low – Below <30%> probability of occurrence
Impact
• High – Risk that has the potential to greatly impact project cost, project schedule or
performance
• Medium – Risk that has the potential to slightly impact project cost, project schedule or
performance
• Low – Risk that has relatively little impact on cost, schedule or performance
Risks that fall within the RED and YELLOW zones will have risk response planning which
may include both a risk mitigation and a risk contingency plan.
2.3.2 Quantitative Risk Analysis
The most likely and greatest impact risks have been added to the project plan to ensure that
they are monitored during the time the project is exposed to each risk. At the appropriate
time in the project schedule a Risk Manager is assigned to each risk. During the bi-weekly
project team meeting the Risk Manager for each risk will discuss the status of that risk;
however, only risks, which fall in the current time period, will be discussed. Risk
monitoring will be a continuous process throughout the life of this project. As risks
approach on the project schedule the project manager will ensure that the appropriate risk
Page 4
Risk Management Plan
Impact
H
M
L
L M H
Probability
<Project Name> Version: 1.0
manager provides the necessary status updates which include the risk status, identification
of trigger conditions, and the documentation of the results of the risk response.
The qualitative analysis will prioritize the risks based on the probability and the impact
criteria. The effect of the risks on the project activities will then be estimated, a numerical
rating will be applied to each risk, and then documentation will be done based on the
following steps:
• Identifying and valuing assets
• Determining the Single Loss Expectancy (SLE)
• Determining Annual Rate of Occurrence
• Determining Annual Loss Expectancy
• Determining the cost of controls
• Risk On Security Investment (ROSI)
• Results of the Quantitative Risk Analysis
2.4 RISK RESPONSE PLANNING
Each major risk (those falling in the Red & Yellow zones) will be assigned to a project
team member for monitoring purposes to ensure that the risk will not “fall through the
cracks”.
For each major risk, one of the following approaches will be selected to address it:
• Avoid – eliminate the threat by eliminating the cause
• Mitigate – Identify ways to reduce the probability or the impact of the risk
• Accept – Nothing will be done
• Transfer – Make another party responsible for the risk (buy insurance, outsourcing, etc.)
For each risk that will be mitigated, the project team will identify ways to prevent the risk
from occurring or reduce its impact or probability of occurring. This may include
prototyping, adding tasks to the project schedule, adding resources, etc.
For each major risk that is to be mitigated or that is accepted, a course of action will be
outlined for the event that the risk does materialize in order to minimize its impact.
2.5 RISK MITIGATION AND AVOIDANCE
The project manager has led the project team in developing responses to each identified
risk. As more risks are identified, they will be qualified and the team will develop
avoidance and mitigation strategies. These risks will also be added to the Risk Register
and the project plan to ensure they are monitored at the appropriate times and are
responded to accordingly.
The risks for this project will be managed and controlled within the constraints of time,
scope, and cost. All identified risks will be evaluated in order to determine how they affect
Page 5
Risk Management Plan
<Project Name> Version: 1.0
this triple constraint. The project manager, with the assistance of the project team, will
determine the best way to respond to each risk to ensure compliance with these constraints.
In extreme cases it may be necessary to allow flexibility to one of the project’s constraints.
Only one of the constraints for this project allows for flexibility as a last resort. If
necessary, funding may be added to the project to allow for more resources in order to
meet the time (schedule) and scope constraints. Time and scope are firm constraints and
allow for no flexibility. Again, the cost constraint is flexible only in extreme cases where
no other risk avoidance or mitigation strategy will work.
3 RISK REGISTER
The Risk Register for this project is a log of all identified risks, their probability and impact
to the project, the category they belong to, mitigation strategy, and when the risk will
occur. The register was created through the initial project risk management meeting led by
the project manager. During this meeting, the project team identified and categorized each
risk. Additionally, the team assigned each risk a score based on the probability of it
occurring and the impact it could potentially have. The Risk Register also contains the
mitigation strategy for each risk as well as when the risk is likely to occur.
Based on the identified risks and timeframes in the risk register, each risk has been added
to the project plan. At the appropriate time in the plan—prior to when the risk is most
likely to occur—the project manager will assign a risk manager to ensure adherence to the
agreed upon mitigation strategy. The each risk manager will provide the status of their
assigned risk at the bi-weekly project team meeting for their risk’s planned timeframe.
The Risk Register will be maintained as an appendix to this Risk Management Plan.
Page 6
Risk Management Plan

Más contenido relacionado

La actualidad más candente

Construction project risk management
Construction project risk managementConstruction project risk management
Construction project risk managementIQPC
 
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...Ahmed Fouad, MCIArb, PMP, SP, RMP
 
Risk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.pptRisk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.pptTouqeer1
 
project management fundamentals Chapter 1
project management fundamentals Chapter 1project management fundamentals Chapter 1
project management fundamentals Chapter 1Mazhar Poohlah
 
Risk and issue management
Risk and issue managementRisk and issue management
Risk and issue managementThomas Petite
 
Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdfAditi Garg
 
05. Project And Organizational Structure
05. Project And Organizational Structure05. Project And Organizational Structure
05. Project And Organizational StructureBhuWan Khadka
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: BudgetMinhas Kamal
 
Types of resources in civil engineering field
Types of resources in civil engineering fieldTypes of resources in civil engineering field
Types of resources in civil engineering fieldswetha110
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessAlberto Sanchez
 
11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk AnalysisDavidMcLachlan1
 
Chapter 1 An Overview Of Project Management
Chapter 1  An Overview Of Project ManagementChapter 1  An Overview Of Project Management
Chapter 1 An Overview Of Project ManagementMahesh Bendigeri
 
Earned value management (EVM)
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)Joshua Render
 
Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5pankajsh10
 
Traditional Management System.ppt
Traditional Management System.pptTraditional Management System.ppt
Traditional Management System.pptUtkarshDwivedi74
 

La actualidad más candente (20)

Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Construction project risk management
Construction project risk managementConstruction project risk management
Construction project risk management
 
Different project management methodologies
Different project management methodologiesDifferent project management methodologies
Different project management methodologies
 
Risk management
Risk management Risk management
Risk management
 
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
 
Risk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.pptRisk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.ppt
 
project management fundamentals Chapter 1
project management fundamentals Chapter 1project management fundamentals Chapter 1
project management fundamentals Chapter 1
 
Risk and issue management
Risk and issue managementRisk and issue management
Risk and issue management
 
Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdf
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
 
Project Teamwork
Project TeamworkProject Teamwork
Project Teamwork
 
05. Project And Organizational Structure
05. Project And Organizational Structure05. Project And Organizational Structure
05. Project And Organizational Structure
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: Budget
 
Types of resources in civil engineering field
Types of resources in civil engineering fieldTypes of resources in civil engineering field
Types of resources in civil engineering field
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
 
11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis
 
Chapter 1 An Overview Of Project Management
Chapter 1  An Overview Of Project ManagementChapter 1  An Overview Of Project Management
Chapter 1 An Overview Of Project Management
 
Earned value management (EVM)
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)
 
Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5
 
Traditional Management System.ppt
Traditional Management System.pptTraditional Management System.ppt
Traditional Management System.ppt
 

Destacado

Destacado (10)

HC Data Pro Risk Management Plan
HC Data Pro Risk Management PlanHC Data Pro Risk Management Plan
HC Data Pro Risk Management Plan
 
Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4
 
Project Management Plan - Group Presentation
Project Management Plan - Group PresentationProject Management Plan - Group Presentation
Project Management Plan - Group Presentation
 
Risk Management Plan Example
Risk Management Plan ExampleRisk Management Plan Example
Risk Management Plan Example
 
Pm study project risk management test
Pm study project  risk management testPm study project  risk management test
Pm study project risk management test
 
Kaizen bcic
Kaizen bcicKaizen bcic
Kaizen bcic
 
PMP - Risk Management plan & template
PMP - Risk Management plan & templatePMP - Risk Management plan & template
PMP - Risk Management plan & template
 
4 m's of production
4 m's of production 4 m's of production
4 m's of production
 
5 m’s of management
5 m’s of management5 m’s of management
5 m’s of management
 
Sample project plan
Sample project planSample project plan
Sample project plan
 

Similar a Risk management plan tyre recycling plant

Risk management-plan template
Risk management-plan templateRisk management-plan template
Risk management-plan templateVivek Srivastava
 
Templates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docx
Templates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docxTemplates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docx
Templates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docxmattinsonjanel
 
Project Name Risk Management PlanVersion 1.0 Error! Unkno.docx
Project Name Risk Management PlanVersion 1.0 Error! Unkno.docxProject Name Risk Management PlanVersion 1.0 Error! Unkno.docx
Project Name Risk Management PlanVersion 1.0 Error! Unkno.docxwkyra78
 
Risk management plan for Human Resource Software
Risk management plan for Human Resource SoftwareRisk management plan for Human Resource Software
Risk management plan for Human Resource SoftwareDavid Bustin
 
Risk management and assessment
Risk management and assessmentRisk management and assessment
Risk management and assessmentabassociates
 
Project risk management
Project risk managementProject risk management
Project risk managementBarnatuCoffee
 
Construction project management &amp; risk mitigation
Construction project management &amp; risk mitigationConstruction project management &amp; risk mitigation
Construction project management &amp; risk mitigationrajlaxmipardeshi
 
2.11 risk management 1
2.11 risk management 12.11 risk management 1
2.11 risk management 1reddvise
 
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaOnline PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaGlobalSkillup
 
Eplc risk management_template
Eplc risk management_templateEplc risk management_template
Eplc risk management_templategguinle
 
RM_audit_overview_w_voice.pptx (2).mp4 Interoperability.docx
RM_audit_overview_w_voice.pptx (2).mp4  Interoperability.docxRM_audit_overview_w_voice.pptx (2).mp4  Interoperability.docx
RM_audit_overview_w_voice.pptx (2).mp4 Interoperability.docxSUBHI7
 
Risk management
Risk managementRisk management
Risk managementbipulpwc
 
Critical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_enCritical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_enVyacheslav Guzovsky
 
10.9 STORE-DRIVEN FORECASTS. The Home Depot is a lead.docx
10.9  STORE-DRIVEN FORECASTS. The Home Depot is a lead.docx10.9  STORE-DRIVEN FORECASTS. The Home Depot is a lead.docx
10.9 STORE-DRIVEN FORECASTS. The Home Depot is a lead.docxhyacinthshackley2629
 
Risk management plan
Risk management planRisk management plan
Risk management planKashif Mastan
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk ManagementSAJJAD KHUDHUR ABBAS
 

Similar a Risk management plan tyre recycling plant (20)

Risk management-plan template
Risk management-plan templateRisk management-plan template
Risk management-plan template
 
Templates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docx
Templates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docxTemplates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docx
Templates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docx
 
Project Name Risk Management PlanVersion 1.0 Error! Unkno.docx
Project Name Risk Management PlanVersion 1.0 Error! Unkno.docxProject Name Risk Management PlanVersion 1.0 Error! Unkno.docx
Project Name Risk Management PlanVersion 1.0 Error! Unkno.docx
 
Risk management plan for Human Resource Software
Risk management plan for Human Resource SoftwareRisk management plan for Human Resource Software
Risk management plan for Human Resource Software
 
Risk management and assessment
Risk management and assessmentRisk management and assessment
Risk management and assessment
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Construction project management &amp; risk mitigation
Construction project management &amp; risk mitigationConstruction project management &amp; risk mitigation
Construction project management &amp; risk mitigation
 
2.11 risk management 1
2.11 risk management 12.11 risk management 1
2.11 risk management 1
 
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaOnline PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
 
Eplc risk management_template
Eplc risk management_templateEplc risk management_template
Eplc risk management_template
 
11 project risk management
11 project risk management11 project risk management
11 project risk management
 
RM_audit_overview_w_voice.pptx (2).mp4 Interoperability.docx
RM_audit_overview_w_voice.pptx (2).mp4  Interoperability.docxRM_audit_overview_w_voice.pptx (2).mp4  Interoperability.docx
RM_audit_overview_w_voice.pptx (2).mp4 Interoperability.docx
 
TOPIC5.pdf
TOPIC5.pdfTOPIC5.pdf
TOPIC5.pdf
 
Risk management
Risk managementRisk management
Risk management
 
Project risk analysis
Project risk analysisProject risk analysis
Project risk analysis
 
Critical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_enCritical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_en
 
10.9 STORE-DRIVEN FORECASTS. The Home Depot is a lead.docx
10.9  STORE-DRIVEN FORECASTS. The Home Depot is a lead.docx10.9  STORE-DRIVEN FORECASTS. The Home Depot is a lead.docx
10.9 STORE-DRIVEN FORECASTS. The Home Depot is a lead.docx
 
Risk management plan
Risk management planRisk management plan
Risk management plan
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 

Más de abhishekthakur309

Seminar on diffusion welding
Seminar on diffusion weldingSeminar on diffusion welding
Seminar on diffusion weldingabhishekthakur309
 
Project plan tyre recycling plant
Project plan   tyre recycling plantProject plan   tyre recycling plant
Project plan tyre recycling plantabhishekthakur309
 
Presentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plantPresentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plantabhishekthakur309
 
Presentation on failure of nokia
Presentation on failure of nokiaPresentation on failure of nokia
Presentation on failure of nokiaabhishekthakur309
 
Mrketing plan recharging technology abhishek thakur,sourabh kulkarni
Mrketing plan recharging technology  abhishek thakur,sourabh kulkarniMrketing plan recharging technology  abhishek thakur,sourabh kulkarni
Mrketing plan recharging technology abhishek thakur,sourabh kulkarniabhishekthakur309
 
Failure of nokia research paper
Failure of nokia research paperFailure of nokia research paper
Failure of nokia research paperabhishekthakur309
 

Más de abhishekthakur309 (8)

Smart cycle presentation
Smart cycle presentationSmart cycle presentation
Smart cycle presentation
 
Seminar on diffusion welding
Seminar on diffusion weldingSeminar on diffusion welding
Seminar on diffusion welding
 
Project plan tyre recycling plant
Project plan   tyre recycling plantProject plan   tyre recycling plant
Project plan tyre recycling plant
 
Presentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plantPresentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plant
 
Presentation on failure of nokia
Presentation on failure of nokiaPresentation on failure of nokia
Presentation on failure of nokia
 
Mrketing plan recharging technology abhishek thakur,sourabh kulkarni
Mrketing plan recharging technology  abhishek thakur,sourabh kulkarniMrketing plan recharging technology  abhishek thakur,sourabh kulkarni
Mrketing plan recharging technology abhishek thakur,sourabh kulkarni
 
Failure of nokia research paper
Failure of nokia research paperFailure of nokia research paper
Failure of nokia research paper
 
Smart cycle proposal
Smart cycle proposalSmart cycle proposal
Smart cycle proposal
 

Último

Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Alex Marques
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementTulsiDhidhi1
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningCIToolkit
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Smisbafathima9940
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...Pooja Nehwal
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 

Último (20)

Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing management
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for Learning
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima S
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 

Risk management plan tyre recycling plant

  • 1. <PROJECT NAME> RISK MANAGEMENT PLAN Version <1.0> 04/08/2013 Risk Management Plan
  • 2. <Project Name> Version: 1.0 TABLE OF CONTENTS 1 INTRODUCTION......................................................................................................................1 1.1 Purpose Of The Risk Management Plan............................................................................1 2 RISK MANAGEMENT PROCEDURE...................................................................................2 2.1 Process................................................................................................................................2 2.2 Risk Identification..............................................................................................................3 2.3 Risk Analysis......................................................................................................................3 2.3.1 Qualitative Risk Analysis........................................................................................3 2.3.2 Quantitative Risk Analysis......................................................................................4 2.4 Risk Response Planning.....................................................................................................5 2.5 Risk Mitigation and Avoidance..........................................................................................5 3 RISK REGISTER.......................................................................................................................6 6 Risk Management Plan
  • 3. <Project Name> Version: 1.0 1 INTRODUCTION 1.1 PURPOSE OF THE RISK MANAGEMENT PLAN Any kind of project is susceptible to risks of various natures that can have different degrees of effect in the normal project. It may or may not have positive or negative effects on a project’s objectives. Risk Management assists in the prevention and minimization of unfavorable events. The objective of a risk management is to secure the project from risks by identifying, assessing, responding to, monitoring, and reporting risks. The purpose of the risk management plan is to establish the framework in which the project team will identify risks and develop strategies to mitigate or avoid those risks. However, before risks can be identified and managed, there are preliminary project elements which must be completed. These elements are outlined in the risk management approach. This project is considered a medium risk project as it has an overall risk score of 24 on a scale from 0 to 100. The project risk score is the average of the risk scores of the most significant risks to this project. A risk score below 16 is low risk project, a score between 16 and 45 is a medium risk project and a score above 45 is a high-risk project. Before risk management begins it is imperative that a foundation is established for providing structured project information, thus, the following project elements were completed and defined prior to developing this Risk Management Plan: • Define work scope, schedule, resources, and cost elements o Develop project WBS/WBS dictionary o Develop master schedule and detailed schedules o Estimate project cost and finalize budget o Identify required and available resources o Establish performance measurement metrics • Define minimum and maximum baseline thresholds o Schedule o Resources o Cost • Baseline reporting requirements o Format o Frequency of distribution o Distribution list • Define Risk Management Roles and Responsibilities o Project Manager chairs the risk assessment meetings Page 1 Risk Management Plan
  • 4. <Project Name> Version: 1.0 o Project team participates in risk assessment meetings and members serve as meeting recorder and timekeeper o Key stakeholders participate in risk assessment meetings o Project Sponsor may participate in risk assessment meetings The Risk Management Plan for the Construction of Scrap Tire Recycling Plant gives an outline of the risk associated with the project by identifying, analyzing and managing the risks involved. 2 RISK MANAGEMENT PROCEDURE 2.1 PROCESS The approach we have taken to manage risks for Construction of Scrap Tire recycling Plant included a methodical process by which the project team identified, scored, and ranked the various risks. The most likely and highest impact risks were added to the project schedule to ensure that the assigned risk managers take the necessary steps to implement the mitigation response at the appropriate time during the schedule. Risk managers will provide status updates on their assigned risks in the bi-weekly project team meetings, but only when the meetings include their risk’s planned timeframe. Upon the completion of the project, during the closing process, the project manager will analyze each risk as well as the risk management process. Based on this analysis, the project manager will identify any improvements that can be made to the risk management process for future projects. These improvements will be captured as part of the lessons learned knowledge base. The risk management process gives an outline to Project Manager and all the project personnel of the future risk and gives an ample amount of time to come up with the solutions beforehand. A well articulated Risk Management Plan helps in utmost resource utilization, meet scheduling on time and prevent unwanted risks associated. The risk management process comprises of some steps, but is not limited to, and if followed properly helps in mitigating the risk or minimizing the effects. Some of the steps are identifying the risk, identifying the source of the risk, measuring, evaluating, mitigating and monitoring the risk. The diagram below depicts the various steps involved in the risk management process. Page 2 Risk Management Plan
  • 5. <Project Name> Version: 1.0 2.2 RISK IDENTIFICATION The task of the Risk Management Manager would be to identify all the risks associated with the Construction of Scrap Tire Recycling Plant and submit it during the risk identification process. After acquiring all the details about the risks the project team, appropriate stakeholders would work on handling the risks. This process would also include an evaluation of environmental factor, organizational culture and the project management plan including the project scope. Some of the important factors, which will be included in the identification process, are project deliverables, assumptions, constraints, WBS, cost/effort estimates, resource plan, and other key project documents. A Risk Management Log will then be created and updated as and when needed. The log will be stored electronically which can be used for future reference. 2.3 RISK ANALYSIS In order to determine the severity of the risks identified by the team, a probability and impact factor was assigned to each risk. This process allowed the project manager to prioritize risks based upon the effect they may have on the project. The project manager utilized a probability-impact matrix to facilitate the team in moving each risk to the appropriate place on the chart. Once the risks were assigned a probability and impact and placed in the appropriate position on the chart, the recorder captured the finished product and the project manager moved the process on to the next step: risk mitigation/avoidance planning 2.3.1 Qualitative Risk Analysis The Project Manager will assess each identified risk based on the probability and impact of occurrence for each risk, with input from the project team using the following approach: Page 3 Risk Management Plan
  • 6. <Project Name> Version: 1.0 Probability • High – Greater than <70%> probability of occurrence • Medium – Between <30%> and <70%> probability of occurrence • Low – Below <30%> probability of occurrence Impact • High – Risk that has the potential to greatly impact project cost, project schedule or performance • Medium – Risk that has the potential to slightly impact project cost, project schedule or performance • Low – Risk that has relatively little impact on cost, schedule or performance Risks that fall within the RED and YELLOW zones will have risk response planning which may include both a risk mitigation and a risk contingency plan. 2.3.2 Quantitative Risk Analysis The most likely and greatest impact risks have been added to the project plan to ensure that they are monitored during the time the project is exposed to each risk. At the appropriate time in the project schedule a Risk Manager is assigned to each risk. During the bi-weekly project team meeting the Risk Manager for each risk will discuss the status of that risk; however, only risks, which fall in the current time period, will be discussed. Risk monitoring will be a continuous process throughout the life of this project. As risks approach on the project schedule the project manager will ensure that the appropriate risk Page 4 Risk Management Plan Impact H M L L M H Probability
  • 7. <Project Name> Version: 1.0 manager provides the necessary status updates which include the risk status, identification of trigger conditions, and the documentation of the results of the risk response. The qualitative analysis will prioritize the risks based on the probability and the impact criteria. The effect of the risks on the project activities will then be estimated, a numerical rating will be applied to each risk, and then documentation will be done based on the following steps: • Identifying and valuing assets • Determining the Single Loss Expectancy (SLE) • Determining Annual Rate of Occurrence • Determining Annual Loss Expectancy • Determining the cost of controls • Risk On Security Investment (ROSI) • Results of the Quantitative Risk Analysis 2.4 RISK RESPONSE PLANNING Each major risk (those falling in the Red & Yellow zones) will be assigned to a project team member for monitoring purposes to ensure that the risk will not “fall through the cracks”. For each major risk, one of the following approaches will be selected to address it: • Avoid – eliminate the threat by eliminating the cause • Mitigate – Identify ways to reduce the probability or the impact of the risk • Accept – Nothing will be done • Transfer – Make another party responsible for the risk (buy insurance, outsourcing, etc.) For each risk that will be mitigated, the project team will identify ways to prevent the risk from occurring or reduce its impact or probability of occurring. This may include prototyping, adding tasks to the project schedule, adding resources, etc. For each major risk that is to be mitigated or that is accepted, a course of action will be outlined for the event that the risk does materialize in order to minimize its impact. 2.5 RISK MITIGATION AND AVOIDANCE The project manager has led the project team in developing responses to each identified risk. As more risks are identified, they will be qualified and the team will develop avoidance and mitigation strategies. These risks will also be added to the Risk Register and the project plan to ensure they are monitored at the appropriate times and are responded to accordingly. The risks for this project will be managed and controlled within the constraints of time, scope, and cost. All identified risks will be evaluated in order to determine how they affect Page 5 Risk Management Plan
  • 8. <Project Name> Version: 1.0 this triple constraint. The project manager, with the assistance of the project team, will determine the best way to respond to each risk to ensure compliance with these constraints. In extreme cases it may be necessary to allow flexibility to one of the project’s constraints. Only one of the constraints for this project allows for flexibility as a last resort. If necessary, funding may be added to the project to allow for more resources in order to meet the time (schedule) and scope constraints. Time and scope are firm constraints and allow for no flexibility. Again, the cost constraint is flexible only in extreme cases where no other risk avoidance or mitigation strategy will work. 3 RISK REGISTER The Risk Register for this project is a log of all identified risks, their probability and impact to the project, the category they belong to, mitigation strategy, and when the risk will occur. The register was created through the initial project risk management meeting led by the project manager. During this meeting, the project team identified and categorized each risk. Additionally, the team assigned each risk a score based on the probability of it occurring and the impact it could potentially have. The Risk Register also contains the mitigation strategy for each risk as well as when the risk is likely to occur. Based on the identified risks and timeframes in the risk register, each risk has been added to the project plan. At the appropriate time in the plan—prior to when the risk is most likely to occur—the project manager will assign a risk manager to ensure adherence to the agreed upon mitigation strategy. The each risk manager will provide the status of their assigned risk at the bi-weekly project team meeting for their risk’s planned timeframe. The Risk Register will be maintained as an appendix to this Risk Management Plan. Page 6 Risk Management Plan