Improvements for
           Chowgule & Co. Ltd. – Shipbuilding
                       Division

Ambattuparambil Gopi Nikhil – 09NA1008
• Located on River
  Zuari at Loutulim
• Builders, owners &
  repairers of river       – Iron Ore Barges
  fleets since 1951        – Deep Sea Refrigerated
                             Fishing Trawlers
• Developing               – Grab & Cutter Section
  waterways economy          Dredgers
                           – Tugs
• Built over 100 vessels
                           – Twin-Hull Catamarans
  including                – Floating Restaurants
GOA




      River Zuari
• Construction Bays on either side of Slipway
• Main yard near Outfitting Jetty
• Ample amount of Skids for module assembly
  but scattered
• Distance between Stockyard & Main yard
• Space between Gate & Main Yard unutilized
  (trees?)
Production                Grit Blasting/
Design Room   Department   Scheduling
                                          painting
Assembly
           CNC                   Modular
Lofting                of
          Cutting              Construction
                    Modules
Survey   Movement   Launching   Sea Trials
• Slipway – 220m x 20m
• 2 Construction bays – either side of slipway
  – 90m x 30m open space
  – 90m x 40m open space
• Outfitting Jetty 7m x 10m x 15m
• Sufficient skids for pre-fabrication of
  modules/panels
• Well equipped workshop
• Shipyard specializes in smaller vessels especially those
  used in waterways and for fishing
• Capacity is limited
• Delivery time is of utmost importance
   – Being a private yard (no Govt support)
   – To get more orders
   – Maintain credibility
• Will need more facilities if it wants to extend its
  product catalogue
• Best way to improve layout maybe to induct a
  production flow line model that allows easy flow of
  materials without bottlenecks
• Set up Stockyard near Checkpoint to reduce travel
  time of plates coming in and to be nearer to Main
  yard. Shift Sand blasting unit accordingly
• Use the unutilized area to set up Grit
  blasting/painting & CNC Cutting units – Reduces
  travel time of modules/plates
• Add more (or shift existing) skids nearer to Main yard
  to reduce travel time of modules
• Shift Main office building to give direct access of main
  yard to construction bays
• May shift store to north of Main yard if space permits
•   Faster production line
•   Lesser delivery time  more orders
•   Lower man-time requirement
•   Use of lifting equipment freed for better
    purposes (due to lower amount of shifting of
    modules & panels)
• Cannot increase production too much due to
  space constraints
• Lack of dry dock reduces capability for
  advanced outfitting
09NA1008
              Presentation on Improvement of
             Shipyard Layout in Chowgule & Co.
                 Ltd. – Shipbuilding Division


Ambattuparambil Gopi Nikhil – 09NA1008

Más contenido relacionado

La actualidad más candente

SeniorDesignProjectReport
SeniorDesignProjectReportSeniorDesignProjectReport
SeniorDesignProjectReport
Daniel Place
 
DESIGN OF A 17 METRE FAST PATROL BOAT WITH AN INSIGHT INTO AN INNOVATIVE BOW ...
DESIGN OF A 17 METRE FAST PATROL BOAT WITH AN INSIGHT INTO AN INNOVATIVE BOW ...DESIGN OF A 17 METRE FAST PATROL BOAT WITH AN INSIGHT INTO AN INNOVATIVE BOW ...
DESIGN OF A 17 METRE FAST PATROL BOAT WITH AN INSIGHT INTO AN INNOVATIVE BOW ...
Alec Maclean
 
Personal Survival and Social Responsibilities(PSSR)
Personal Survival and Social Responsibilities(PSSR)Personal Survival and Social Responsibilities(PSSR)
Personal Survival and Social Responsibilities(PSSR)
nmahi96
 
propulsion engineering-02-resistance of ships
propulsion engineering-02-resistance of shipspropulsion engineering-02-resistance of ships
propulsion engineering-02-resistance of ships
fahrenheit
 

La actualidad más candente (20)

Hydrostatics 1 n 2
Hydrostatics 1 n 2 Hydrostatics 1 n 2
Hydrostatics 1 n 2
 
Ship Motion and Stresses
Ship Motion and StressesShip Motion and Stresses
Ship Motion and Stresses
 
Motion Response Project pdf
Motion Response Project pdfMotion Response Project pdf
Motion Response Project pdf
 
Ship Construction- Ship Dimensions
Ship Construction- Ship DimensionsShip Construction- Ship Dimensions
Ship Construction- Ship Dimensions
 
Preliminary ship-design
Preliminary ship-designPreliminary ship-design
Preliminary ship-design
 
Inclining Experiment and Angle of Loll 23 Sept 2019.pptx
Inclining Experiment and Angle of Loll 23 Sept 2019.pptxInclining Experiment and Angle of Loll 23 Sept 2019.pptx
Inclining Experiment and Angle of Loll 23 Sept 2019.pptx
 
Ship terms
Ship termsShip terms
Ship terms
 
SeniorDesignProjectReport
SeniorDesignProjectReportSeniorDesignProjectReport
SeniorDesignProjectReport
 
Basics of-ship-resistance
Basics of-ship-resistanceBasics of-ship-resistance
Basics of-ship-resistance
 
Ship Loads and stresses
Ship Loads and stressesShip Loads and stresses
Ship Loads and stresses
 
DESIGN OF A 17 METRE FAST PATROL BOAT WITH AN INSIGHT INTO AN INNOVATIVE BOW ...
DESIGN OF A 17 METRE FAST PATROL BOAT WITH AN INSIGHT INTO AN INNOVATIVE BOW ...DESIGN OF A 17 METRE FAST PATROL BOAT WITH AN INSIGHT INTO AN INNOVATIVE BOW ...
DESIGN OF A 17 METRE FAST PATROL BOAT WITH AN INSIGHT INTO AN INNOVATIVE BOW ...
 
Hydrostatics and stability
Hydrostatics and stabilityHydrostatics and stability
Hydrostatics and stability
 
Personal Survival and Social Responsibilities(PSSR)
Personal Survival and Social Responsibilities(PSSR)Personal Survival and Social Responsibilities(PSSR)
Personal Survival and Social Responsibilities(PSSR)
 
Ship Building (parts of ship)
Ship Building (parts of ship)Ship Building (parts of ship)
Ship Building (parts of ship)
 
OFFSHORE PLATFORM_1.ppt (1).pdf
OFFSHORE PLATFORM_1.ppt (1).pdfOFFSHORE PLATFORM_1.ppt (1).pdf
OFFSHORE PLATFORM_1.ppt (1).pdf
 
Ship dry docking
Ship dry dockingShip dry docking
Ship dry docking
 
propulsion engineering-02-resistance of ships
propulsion engineering-02-resistance of shipspropulsion engineering-02-resistance of ships
propulsion engineering-02-resistance of ships
 
ISM Code
ISM CodeISM Code
ISM Code
 
Displacemnt
DisplacemntDisplacemnt
Displacemnt
 
Small angle stability longitudinal
Small angle stability longitudinal Small angle stability longitudinal
Small angle stability longitudinal
 

Destacado

Life and Work of a Naval Architect
Life and Work of a Naval ArchitectLife and Work of a Naval Architect
Life and Work of a Naval Architect
Callum Campbell
 
Osx project update inglês_setembro_final
Osx project update inglês_setembro_finalOsx project update inglês_setembro_final
Osx project update inglês_setembro_final
osxri
 
Presentation2
Presentation2Presentation2
Presentation2
rizalris
 
shipyard hazards rev 01 2009 01
 shipyard hazards rev 01 2009 01 shipyard hazards rev 01 2009 01
shipyard hazards rev 01 2009 01
Ainnz Abiggaill
 
Empowering Seafarer Manpower Solution of Shipping Industry
Empowering Seafarer Manpower Solution of Shipping IndustryEmpowering Seafarer Manpower Solution of Shipping Industry
Empowering Seafarer Manpower Solution of Shipping Industry
Inderveer Solanki
 

Destacado (20)

Shipyard Management - Design, Planning & Operations
Shipyard Management - Design, Planning & OperationsShipyard Management - Design, Planning & Operations
Shipyard Management - Design, Planning & Operations
 
Loksa Shipyard presentation
Loksa Shipyard presentationLoksa Shipyard presentation
Loksa Shipyard presentation
 
Project management standards for shipyard projects
Project management standards for shipyard projectsProject management standards for shipyard projects
Project management standards for shipyard projects
 
Dept NA-ME
Dept NA-MEDept NA-ME
Dept NA-ME
 
Life and Work of a Naval Architect
Life and Work of a Naval ArchitectLife and Work of a Naval Architect
Life and Work of a Naval Architect
 
Want To Pursue A Career In Naval Architecture?
Want To Pursue A Career In Naval Architecture?Want To Pursue A Career In Naval Architecture?
Want To Pursue A Career In Naval Architecture?
 
INTRODUCTION TO TERM USED IN NAVAL ARCHITECT
INTRODUCTION TO TERM USED IN NAVAL ARCHITECTINTRODUCTION TO TERM USED IN NAVAL ARCHITECT
INTRODUCTION TO TERM USED IN NAVAL ARCHITECT
 
SHIP THEORY : Basics Of Ship Geometry : Lines Plan__by jishnu saji
SHIP THEORY : Basics Of Ship Geometry : Lines Plan__by jishnu sajiSHIP THEORY : Basics Of Ship Geometry : Lines Plan__by jishnu saji
SHIP THEORY : Basics Of Ship Geometry : Lines Plan__by jishnu saji
 
Hydrostatics
HydrostaticsHydrostatics
Hydrostatics
 
PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop
PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - WorkshopPROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop
PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop
 
Osx project update inglês_setembro_final
Osx project update inglês_setembro_finalOsx project update inglês_setembro_final
Osx project update inglês_setembro_final
 
present abm
present abmpresent abm
present abm
 
Painting in confined spaces
Painting in confined spacesPainting in confined spaces
Painting in confined spaces
 
Presentation2
Presentation2Presentation2
Presentation2
 
shipyard hazards rev 01 2009 01
 shipyard hazards rev 01 2009 01 shipyard hazards rev 01 2009 01
shipyard hazards rev 01 2009 01
 
Empowering Seafarer Manpower Solution of Shipping Industry
Empowering Seafarer Manpower Solution of Shipping IndustryEmpowering Seafarer Manpower Solution of Shipping Industry
Empowering Seafarer Manpower Solution of Shipping Industry
 
프레젠테이션1
프레젠테이션1프레젠테이션1
프레젠테이션1
 
프레젠테이션
프레젠테이션프레젠테이션
프레젠테이션
 
In class exercise #1.ppt
In class exercise #1.pptIn class exercise #1.ppt
In class exercise #1.ppt
 
D. David Andrews London College
D. David Andrews London CollegeD. David Andrews London College
D. David Andrews London College
 

Similar a Shipyard layout improvement

Design and Manufacturing Development of Thick
Design and Manufacturing Development of ThickDesign and Manufacturing Development of Thick
Design and Manufacturing Development of Thick
Bill Cleary
 
GTL Oil & Gas Supplement
GTL Oil & Gas SupplementGTL Oil & Gas Supplement
GTL Oil & Gas Supplement
gavinrixon
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012
Richard Turnbull
 
Seatrains for Marine Highway
Seatrains for Marine HighwaySeatrains for Marine Highway
Seatrains for Marine Highway
Stephanie Camay
 
Capabilities and resources
Capabilities and resourcesCapabilities and resources
Capabilities and resources
Martin de Beer
 
Innovation Presentation
Innovation PresentationInnovation Presentation
Innovation Presentation
Ivan Kablar
 

Similar a Shipyard layout improvement (20)

Marine-Shipbuilding-and-Onboard-Systems.ppt
Marine-Shipbuilding-and-Onboard-Systems.pptMarine-Shipbuilding-and-Onboard-Systems.ppt
Marine-Shipbuilding-and-Onboard-Systems.ppt
 
Re - Entry Drilling Project
Re - Entry Drilling ProjectRe - Entry Drilling Project
Re - Entry Drilling Project
 
PFS.pptx
PFS.pptxPFS.pptx
PFS.pptx
 
Design and Manufacturing Development of Thick
Design and Manufacturing Development of ThickDesign and Manufacturing Development of Thick
Design and Manufacturing Development of Thick
 
120625 0814 Tops
120625 0814 Tops120625 0814 Tops
120625 0814 Tops
 
rapid walls- modular construction technology
rapid walls- modular construction technologyrapid walls- modular construction technology
rapid walls- modular construction technology
 
Blastechnik blastrooms presentation
Blastechnik blastrooms presentationBlastechnik blastrooms presentation
Blastechnik blastrooms presentation
 
GTL Oil & Gas Supplement
GTL Oil & Gas SupplementGTL Oil & Gas Supplement
GTL Oil & Gas Supplement
 
Offshore structure design, Sigve Hamilton Aspelund
Offshore structure design, Sigve Hamilton AspelundOffshore structure design, Sigve Hamilton Aspelund
Offshore structure design, Sigve Hamilton Aspelund
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012
 
Seatrains for Marine Highway
Seatrains for Marine HighwaySeatrains for Marine Highway
Seatrains for Marine Highway
 
Vedam Designs: Solutions for Shallow Water maintenance Dredging
Vedam Designs: Solutions for Shallow Water maintenance DredgingVedam Designs: Solutions for Shallow Water maintenance Dredging
Vedam Designs: Solutions for Shallow Water maintenance Dredging
 
Propel ppt
Propel pptPropel ppt
Propel ppt
 
Propel ppt
Propel pptPropel ppt
Propel ppt
 
Capabilities and resources
Capabilities and resourcesCapabilities and resources
Capabilities and resources
 
Royal IHC corporate presentation
Royal IHC corporate presentationRoyal IHC corporate presentation
Royal IHC corporate presentation
 
HydroWorks innovation
HydroWorks innovationHydroWorks innovation
HydroWorks innovation
 
Hydroworks innovation
Hydroworks innovationHydroworks innovation
Hydroworks innovation
 
Innovation Presentation
Innovation PresentationInnovation Presentation
Innovation Presentation
 
Cosworth process
Cosworth processCosworth process
Cosworth process
 

Último

Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
KarakKing
 

Último (20)

Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
OSCM Unit 2_Operations Processes & Systems
OSCM Unit 2_Operations Processes & SystemsOSCM Unit 2_Operations Processes & Systems
OSCM Unit 2_Operations Processes & Systems
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
latest AZ-104 Exam Questions and Answers
latest AZ-104 Exam Questions and Answerslatest AZ-104 Exam Questions and Answers
latest AZ-104 Exam Questions and Answers
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Plant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxPlant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptx
 

Shipyard layout improvement

  • 1. Improvements for Chowgule & Co. Ltd. – Shipbuilding Division Ambattuparambil Gopi Nikhil – 09NA1008
  • 2. • Located on River Zuari at Loutulim • Builders, owners & repairers of river – Iron Ore Barges fleets since 1951 – Deep Sea Refrigerated Fishing Trawlers • Developing – Grab & Cutter Section waterways economy Dredgers – Tugs • Built over 100 vessels – Twin-Hull Catamarans including – Floating Restaurants
  • 3. GOA River Zuari
  • 4.
  • 5. • Construction Bays on either side of Slipway • Main yard near Outfitting Jetty • Ample amount of Skids for module assembly but scattered • Distance between Stockyard & Main yard • Space between Gate & Main Yard unutilized (trees?)
  • 6.
  • 7. Production Grit Blasting/ Design Room Department Scheduling painting
  • 8. Assembly CNC Modular Lofting of Cutting Construction Modules
  • 9. Survey Movement Launching Sea Trials
  • 10. • Slipway – 220m x 20m • 2 Construction bays – either side of slipway – 90m x 30m open space – 90m x 40m open space • Outfitting Jetty 7m x 10m x 15m • Sufficient skids for pre-fabrication of modules/panels • Well equipped workshop
  • 11. • Shipyard specializes in smaller vessels especially those used in waterways and for fishing • Capacity is limited • Delivery time is of utmost importance – Being a private yard (no Govt support) – To get more orders – Maintain credibility • Will need more facilities if it wants to extend its product catalogue • Best way to improve layout maybe to induct a production flow line model that allows easy flow of materials without bottlenecks
  • 12.
  • 13. • Set up Stockyard near Checkpoint to reduce travel time of plates coming in and to be nearer to Main yard. Shift Sand blasting unit accordingly • Use the unutilized area to set up Grit blasting/painting & CNC Cutting units – Reduces travel time of modules/plates • Add more (or shift existing) skids nearer to Main yard to reduce travel time of modules • Shift Main office building to give direct access of main yard to construction bays • May shift store to north of Main yard if space permits
  • 14. Faster production line • Lesser delivery time  more orders • Lower man-time requirement • Use of lifting equipment freed for better purposes (due to lower amount of shifting of modules & panels)
  • 15. • Cannot increase production too much due to space constraints • Lack of dry dock reduces capability for advanced outfitting
  • 16. 09NA1008 Presentation on Improvement of Shipyard Layout in Chowgule & Co. Ltd. – Shipbuilding Division Ambattuparambil Gopi Nikhil – 09NA1008