IT Integrated Project/
Solution Delivery And
Business Engagement Model

Alan McSweeney
Core Dimensions Of Projects

Every Project Has Two Core Dimensions:
IT And
Business
Functions/
Roles/
Activities

1.

Project Stages from Initial Concept to
Delivery

2.

Various Stakeholders Involved at
Various Project Stages and in Various
Roles Performing Various Activities

Project Stages/Timeline

March 2, 2014

2
Integrated Project Business Engagement Model
•

•

Projects are a continuum from initial concept to planning,
design, implementation and management and operation of the
implemented solution (and ultimate decommissioning) and
across IT and business functions
Therefore important to have an integrated project delivery
approach that crosses both these core dimensions

March 2, 2014

3
Components Of Integrated Project Delivery And
Business Engagement Model
Stages

S
Artefacts

A

A

Activities

G
Gates
March 2, 2014

4
Extended Dimensions Of Project Delivery
Project Review and Decision Gates

IT And
Business
Functions/
Roles/
Activities

Artefacts

Project Stages/Timeline
March 2, 2014

5
Extended Dimensions Of Project Delivery
•

Offers a common and consistent frame of reference for all
projects
Integrated Project Delivery Process And Business
Engagement Model
Time
Project Stages/ Timeline
Concept

Initiate

Plan

Design

Build

Test

Deploy

Manage
and
Operate

Project
Management

Project Activity/ Function

Business
Functions/
Roles

Business
Function
Business Analysis
Solution
Architecture
Implementation
and Delivery
Test and Quality
Organisation
Readiness
Service
Management
Infrastructure
and
Communications

March 2, 2014

7
Integrated Project Delivery Process And Business
Engagement Model
Take an artefacts- and results/deliverables-based
integrated approach with review gates where go/no-go
decisions are made
• Across all project phases and project delivery roles
• Focus on getting the project right at the start will yield
benefits
• Provides a complete view of what has to be achieved
• Allows project status to be assessed
• Allows effort to be quantified across all stages and
resources
• Designed to reduce risk of project failures
•

March 2, 2014

8
Integrated Project Delivery Process
•

Integrates project management into all other aspects and
activities of project and solution delivery
− Business
− Business Analysis
− Solution Architecture
− Implementation and Delivery
− Test and Quality
− Organisation Readiness
− Service Management
− Infrastructure

•

All relevant stakeholders are identified at an early stage
and involved throughout subsequently
March 2, 2014

9
Spectrum Of Project Failures
Performance and/or
Operational
Problems

Specified
Business Benefits
and Savings Not
Delivered
Functionality
Delivered Does not
Meet Business
Requirements

More Expensive
to Operate Than
Planned

Significant
Rework
Required

Project Late
and/or Over
Budget

Complete Project
Success:
On-time, On-budget
and Delivering
Specified Benefits

March 2, 2014

Solution Largely
Unused And/Or
Unusable

Increasing Frequency/
Probability of
Occurrence

Complete Project
Failure: Cancelled,
Unused, Rejected

10
Project Failures
•

Project Failures – late projects, over budget, project
functionality not delivered, anticipated business benefits
not achieved

•

Project Rework – involving additional cost

•

Deferred/Removed Scope – needed to meet project
schedule and either never implemented or implemented
later at additional cost

March 2, 2014

11
Reasons For Project Failures
•

Project foundations not correct before implementation starts
− Project failure is embedded in the process from the start

•
•
•

•
•
•

Requirements - not captured, documented, validated and agreed –
poor requirement management process and capability
Design - proposed solution designs not analysed and defined in
sufficient detail to understand
Implementation - started before scope and complexity understood,
documented and defined - there is no check ensure detail is
captured and documented before development starts
Scope - Project scope not defined and challenged and solution
complexity not understood and documented
Stakeholders – all stakeholders not accurately identified
Budget – project costs are not validated or challenged
March 2, 2014

12
Artefacts/Deliverables Define Across Project
Delivery Process
Time
Project Stages/ Timeline
Concept
Project
Management

Project Activity/ Function

Business
Functions/
Roles

Business
Function
Business Analysis
Solution
Architecture
Implementation
and Delivery
Test and Quality
Organisation
Readiness
Service
Management
Infrastructure
and
Communications

March 2, 2014

Initiate

Plan

Design

Build

Test

Deploy

Manage
and
Operate

Artefact
Artefact
Artefact
Artefact
Artefact
Artefact
Artefact
Artefact

13
Artefacts/Deliverables
•

Exist to demonstrate work done to a defined standard and
quality

•

Forces projects to gather information to validate their
activities

•

Provides an audit trail and proof of work done

•

Provides a library of project material that can be reused
for other projects

•

Artefacts structures are designed to be generic to apply
across all project types

March 2, 2014

14
Artefact View Of Integrated Project Delivery Process
Concept

Business
Function

Solution Concept/
Requirements
Document

Delivery

Project Plan
Project Resource Plan

Business Case

Rough Order of
Magnitude Estimate

Solution Architecture
High Level Design

March 2, 2014

Deploy

Operate

User Acceptance Test
Results

Benefits Realisation
Review
Lessons Learned

Non Functional
Requirements
Detailed Solution
Design/ Functional
Specification

User Acceptance Test
Design and Plan
Standard Operating
Procedures

Confirmed Estimates Data Migration Results
Data Audit
Data Design and Data
Build Documentation
Configuration
Migration Plan
Management Approach
Unit Test Results
and Plan
Technical/Build
Integration Test Results
Specification
Detailed Estimates

Documentation Library

Data Migration Test
System Test Plan
Results
UAT Changes and
Rework

Data Migration to Live
Results
Deploy to Production
Results
Support and Operations
Documentation

Go Live Support

Functional Test Design Functional Test Results Operational Readiness
and Plan
Review
Non-Functional Test
Non-Functional Test
Results
Design and Plan
Integration Test
Integration Test Design
Results
and Plan
System Test Results
System Test Design
and Plan

Management Team
Briefing
Communications
Strategy and Plan

Change Impact
Assessment
Detailed
Communications Plan
Training Needs Analysis

Service Impact
Assessment

Service Level
Requirements
Access and Security
Definition

Infrastructure Plan

Infrastructure

Test

Project Management – Planning, Resource, Scheduling
Risk, Actions, Issues and Dependencies Management
Reporting and Communications Management
Change Management

To Be Process
Definition

Test and Quality

Service
Management

Build

Benefits Schedule and
Benefits Realisation
Plan

Test Strategy

Organisation
Readiness

Design

Functional
Requirements
As Is Process Definition

Business
Analysis
Solution
Architecture

Plan

Project Charter
Project Initiation
Document

Project
Management

Initiate

Change Action Plan

Role Definition

Organisation Design
Develop Training
Material

Training Schedule

Operations Acceptance Operations Acceptance
Testing Design and Plan
Testing Results
Service Definition

Infrastructure Design Build Test Environment
Infrastructure Technical Build UAT Environment
Specification
Build OAT Environment
Build Development
Environment

Build Training
Environment

Organisation and
Staffing
Implementation
Training Delivery
Service and
Operational Level
Agreement(s)
Transfer to Production
Plan
Build Production
Environment

Decommission Unused
Environments

15
Artefact View Of Integrated Project Delivery Process
•

Takes a complete view of project delivery and
implementation from initial design to management and
operation

March 2, 2014

16
Artefact View Integrates Different Activity Lifecycles
Strategy, Business Planning and Business Analysis
Business Concept Initial Discovery

Requirements
Elicitation

Decision to
Proceed

Requirements Management and Change Management

Operations and
Use

Solution Architecture and Design
Solution
Architecture

Solution Design

Solution Specification and Change
Management

Project Management Cycle
Initiate

Execute and Control
Plan

Close

Solution Delivery - Implementation and Deployment Lifecycle
Setup and
Prepare

March 2, 2014

Implement
Manage
Develop

Test

Evolve

Deploy

17
Initial Focus Area – Business Engagement And
Solution Definition
Time
Getting This
Right …

Project Stages/ Timeline
Concept
Project
Management

Project Activity/ Function

Business
Functions/
Roles

Business
Function
Business Analysis
Solution
Architecture

Plan

Design

Build

Test

Deploy

Manage
and
Operate

Focus on these project stages
and project activities will
ensure that the project
foundations are sound

Implementation
and Delivery
Test and Quality
Organisation
Readiness
Service
Management
Infrastructure
and
Communications

March 2, 2014

Initiate

… Means Problems
Will Be Avoided At
Later Stages
18
Artefact View Of Initial Focus Area – Business
Engagement And Solution Definition

Business Function

Solution Concept/
Requirements
Document

Plan
Project Plan

Project Initiation
Document

Project Management

Initiate
Project Charter

Concept

Project Resource Plan

Business Case

Design

Benefits Schedule and
Benefits Realisation
Plan
Functional
Requirements
As Is Process
Definition

Business Analysis

Solution
Architecture

•

Rough Order of
Magnitude Estimate

To Be Process
Definition
Non Functional
Requirements

Solution Architecture
High Level Design

Detailed Solution
Design/ Functional
Specification

Establishes solid foundations on which to build solution
delivery and implementation
March 2, 2014

19
Initial Focus Area – Business Engagement And
Solution Definition

March 2, 2014

20
Initial Focus Area – Business Engagement And
Solution Definition And Validation
•

Have a defined solution to meet a defined and articulated
business need that will deliver a realisable and achievable
set of business benefits

•

Understand the complexity of what has to be delivered

March 2, 2014

21
Initial Focus Area – Business Engagement And
Solution Definition And Validation
•

Ensures there is a strong and solid foundation for solution
implementation, delivery and management and operation

March 2, 2014

22
Initial Focus Area – Business Engagement And
Solution Definition And Validation
Time

Getting
These Wrong
…

Project Stages/ Timeline
Concept
Project
Management

Project Activity/ Function

Business
Functions/
Roles

Initiate

Plan

Design

Build

Test

Deploy

Manage
and
Operate

Solution Concept/ Requirements
Business Case

Business
Function

Functional Requirements

Business Analysis

High Level Design

Solution
Architecture

Benefits Schedule and Benefits Realisation
Plan

Implementation
and Delivery
Test and Quality
Organisation
Readiness
Service
Management
Infrastructure
and
Communications

… Means Problems

Will Occur During
The Project

March 2, 2014

23
Initial Focus Area – Business Engagement And
Solution Definition And Validation
•

Where there are gaps in the foundation on which solution
implementation is being based, the project is at significant
risk of failure

March 2, 2014

24
Weaknesses In Business Analysis And Solution Design
Capabilities At The Root of Many Project Failures
Poor
Requirements
Poor Analysis
Practices

Business Requirements
Not Captured

Size/Capacity/
Complexity

Large Project,
Complex, Difficult
Changes and Processes

Poor Strategic
Alignment

Inadequate Business
Case, Undefined
Problem/Need

Large Project Team and
Multiple Stakeholders

Business Benefits
Not Measured

Business Needs
Not Met
Opportunities
Lost

Inadequate Resource
Allocation and
Prioritisation
Inadequate Business
Involvement

Dynamic, Changing
Environment

Poor Focus on
Business Needs
March 2, 2014

Inadequately Explored
Solution Options

Unproven Technology

Investment
Wasted

Solution Design Not
Aligned to Business Needs

Uncertainly/
Ambiguity

Poor Solution
Design
25
Analysis And Solution Design-Related Causes Of
Failures
Poor
Requirements
Poor Analysis
Practices

Business Requirements
Not Captured

Size/Capacity/
Complexity

Large Project,
Complex, Difficult
Changes and Processes

Poor Strategic
Alignment

Inadequate Business
Case, Undefined
Problem/Need

Large Project Team and
Multiple Stakeholders

Business Benefits
Not Measured

Business Needs
Not Met
Opportunities
Lost

Inadequate Resource
Allocation and
Prioritisation
Inadequate Business
Involvement

Dynamic, Changing
Environment

Poor Focus on
Business Needs
March 2, 2014

Inadequately Explored
Solution Options

Unproven Technology

Investment
Wasted

Solution Design Not
Aligned to Business Needs

Uncertainly/
Ambiguity

Poor Solution
Design
26
Project Gates
Time
Project Stages/ Timeline
Concept

Initiate

Plan

Design

Build

Test

Deploy

Manage
and
Operate

Project
Management

Business Analysis

Gate 7

Gate 6

Gate 5

Gate 4

Gate 3

Test and Quality

Gate 2

Implementation
and Delivery

Gate 1

Solution
Architecture

Gate 0

Project Activity/ Function

Business
Functions/
Roles

Business
Function

Organisation
Readiness
Service
Management
Infrastructure
and
Communications

March 2, 2014

27
Project Gates
•

Gates exist after each to ensure project is ready to move
to the next stage or to be stopped or whether rework is
required

•

Review and decision points

•

Artefacts must be ready for review on gate entry

•

Gate exit requires artefacts completed to the required
standard

•

Reduces cost, risk and rework

•

Puts controls around the delivery process

•

Ensures work remains on track
March 2, 2014

28
Gate Process

Gate Entry
Criteria

Gate
Successful Exit

Gate

Phase

Phase

Project
Stopped
Sent Back for
Rework

STOP

March 2, 2014

29
Project Process Gates
Gate 0
Concept

Gate 1
Initiate

Plan
Gate 2
Gate 3

Gate 4
Test

Build

Design

Gate 5
Gate 7

Gate 6
Deploy

March 2, 2014

Operate

30
Project Process Gates
Gate 0
Concept

Gate 1
Initiate

Plan

Validate Solution
Concept and Estimates
and Make Go/No Go
Decision

Gate 4

Gate 3

Test
Gate 5

Build
Build Review, Organisation
Design Review, Readiness to
Proceed to System Test and
UAT

March 2, 2014

Deploy

Design
Validate Detailed Design,
Readiness to Proceed to
Build and Make Go/No Go
Decision

Gate 7

Gate 6
Test Review,
Organisation
Change Review,
Training
Review, Service
Planning
Review

Gate 2

Validate Business Case
and Make Go/No Go
Decision

Validate Plan,
High-Level Design,
Benefits, Readiness
to Proceed to
Detailed Design
and Make Go/No
Go Decision

Operate
Go Live Readiness
Review, Staffing and
Training Review

Benefits Realisation
Validation, Lessons
Learned
31
Sample Gate Review for Gate 3 – Before Move To
Implementation/Development
•

Gate 3 Pre-requisites
−
−
−
−
−
−
−
−
−
−
−
−
−
−
−
−
−
−
−

•

Benefits Schedule
To Be Processes
Non-Functional Requirements
Detailed Solution Design/ Functional
Specification
Security Design
Data Design, Migration and Testing
Strategy
Design and Plan Functional Tests
Design and Plan Integration Tests
Design and Plan Non-Functional Tests
System Test Plan
Systems Inventory
Data Migration Plan
Change Impact Assessment
Detailed Communications Plan
Training Needs Analysis
Training Strategy
Service Design
Capacity Requirements Plan
Infrastructure Specification

March 2, 2014

•

32

Gate review ensures that the relevant
items have been created and are of
sufficient quality
Designed to ensure that solution
complexity has been captured so
there is confidence that what is being
developed is what is needed to be
developed

32
Artefact-Based Status View Of Project
Concept

Project Charter
Project Initiation
Document

Project
Management
Business
Function

Solution Concept/
Requirements
Document

Plan

Rough Order of
Magnitude Estimate

Business Case

Benefits Schedule and
Benefits Realisation
Plan
To Be Process
Definition

Solution Architecture
High Level Design

Configuration
Management Approach
and Plan`
Detailed Estimates

Test and Quality

Service
Management

Management Team
Briefing
Communications
Strategy and Plan
Service Impact
Assessment

Infrastructure Plan

Infrastructure

March 2, 2014

Test

Deploy

Operate

User Acceptance Test
Results

Benefits Realisation
Review
Lessons Learned

Non Functional
Requirements
Detailed Solution
Design/ Functional
Specification

Test Strategy

Organisation
Readiness

Build

Project Plan
Project Resource Plan

Data Audit

Delivery

Design

Functional
Requirements
As Is Process Definition

Business
Analysis
Solution
Architecture

Initiate

Confirmed Estimates
Data Design and Data
Migration Plan
Technical/Build
Specification

User Acceptance Test
Design and Plan
Standard Operating
Procedures

Data Migration Results
Build Documentation
Unit Test Results
Integration Test Results

Documentation Library

Data Migration Test
System Test Plan
Results
UAT Changes and
Rework

Data Migration to Live
Results
Deploy to Production
Results
Support and Operations
Documentation

Go Live Support

Functional Test Design Functional Test Results Operational Readiness
and Plan
Review
Non-Functional Test
Non-Functional Test
Results
Design and Plan
Integration Test
Integration Test Design
Results
and Plan
System Test Results
System Test Design
and Plan
Change Action Plan
Change Impact
Assessment
Organisation Design
Detailed
Develop Training
Communications Plan
Material
Training Needs Analysis
Service Level
Requirements
Access and Security
Definition

Role Definition
Training Schedule

Operations Acceptance Operations Acceptance
Testing Design and Plan
Testing Results
Service Definition

Infrastructure Design Build Test Environment
Infrastructure Technical Build UAT Environment
Specification
Build OAT Environment
Build Development
Environment

Build Training
Environment

Organisation and
Staffing
Implementation
Training Delivery
Service and
Operational Level
Agreement(s)
Transfer to Production
Plan
Build Production
Environment

Decommission Unused
Environments

33
Consistent View Of Projects

March 2, 2014

34
Artefact-Based Status View Of Project
•

Use the status of the artefacts at project stages to assess
and measure the status of the project

•

One element of project reporting

March 2, 2014

35
Summary
•

Provides a consistent and repeatable approach to projects

•

Independent of the specifics of a project

•

Artefact-based view

•

Enables gate review process where deliverables can be
evaluated for quality and substance

•

Enables status of the project to assessed

•

Ensures success by emphasising business engagement and
solution analysis and design at an early stage

•

Engages early with project complexity
March 2, 2014

36
More Information
Alan McSweeney
http://ie.linkedin.com/in/alanmcsweeney

March 2, 2014

37

Más contenido relacionado

La actualidad más candente

Solution Architecture Concept Workshop
Solution Architecture Concept WorkshopSolution Architecture Concept Workshop
Solution Architecture Concept WorkshopAlan McSweeney
 
Solution Architecture And (Robotic) Process Automation Solutions
Solution Architecture And (Robotic) Process Automation SolutionsSolution Architecture And (Robotic) Process Automation Solutions
Solution Architecture And (Robotic) Process Automation SolutionsAlan McSweeney
 
Incorporating A DesignOps Approach Into Solution Architecture
Incorporating A DesignOps Approach Into Solution ArchitectureIncorporating A DesignOps Approach Into Solution Architecture
Incorporating A DesignOps Approach Into Solution ArchitectureAlan McSweeney
 
Solution Architecture And Solution Security
Solution Architecture And Solution SecuritySolution Architecture And Solution Security
Solution Architecture And Solution SecurityAlan McSweeney
 
Solution Architecture Framework
Solution Architecture FrameworkSolution Architecture Framework
Solution Architecture FrameworkFirmansyahIrma1
 
Solution Security Architecture
Solution Security ArchitectureSolution Security Architecture
Solution Security ArchitectureAlan McSweeney
 
Review of Information Technology Function Critical Capability Models
Review of Information Technology Function Critical Capability ModelsReview of Information Technology Function Critical Capability Models
Review of Information Technology Function Critical Capability ModelsAlan McSweeney
 
Digital Transformation And Enterprise Architecture
Digital Transformation And Enterprise ArchitectureDigital Transformation And Enterprise Architecture
Digital Transformation And Enterprise ArchitectureAlan McSweeney
 
Introduction to Enterprise architecture and the steps to perform an Enterpris...
Introduction to Enterprise architecture and the steps to perform an Enterpris...Introduction to Enterprise architecture and the steps to perform an Enterpris...
Introduction to Enterprise architecture and the steps to perform an Enterpris...Prashanth Panduranga
 
Complexity and Solution Architecture
Complexity and Solution ArchitectureComplexity and Solution Architecture
Complexity and Solution ArchitectureAlan McSweeney
 
Introduction to Business Architecture - Part 2
Introduction to Business Architecture - Part 2Introduction to Business Architecture - Part 2
Introduction to Business Architecture - Part 2Alan McSweeney
 
Shadow IT And The Failure Of IT Architecture
Shadow IT And The Failure Of IT ArchitectureShadow IT And The Failure Of IT Architecture
Shadow IT And The Failure Of IT ArchitectureAlan McSweeney
 
Solution architecture
Solution architectureSolution architecture
Solution architectureiasaglobal
 
Solution Architecture and Solution Complexity
Solution Architecture and Solution ComplexitySolution Architecture and Solution Complexity
Solution Architecture and Solution ComplexityAlan McSweeney
 
Enterprise Architecture, Project Management & Digital Transformation
Enterprise Architecture, Project Management & Digital TransformationEnterprise Architecture, Project Management & Digital Transformation
Enterprise Architecture, Project Management & Digital TransformationRiaz A. Khan, OpenCA, TOGAF
 
Introduction to Enterprise Architecture and TOGAF 9.1
Introduction to Enterprise Architecture and TOGAF 9.1Introduction to Enterprise Architecture and TOGAF 9.1
Introduction to Enterprise Architecture and TOGAF 9.1iasaglobal
 
Approach To It Strategy And Architecture
Approach To It Strategy And ArchitectureApproach To It Strategy And Architecture
Approach To It Strategy And ArchitectureAlan McSweeney
 
Why Solutions Fail and the Business Value of Solution Architecture
Why Solutions Fail and the Business Value of Solution ArchitectureWhy Solutions Fail and the Business Value of Solution Architecture
Why Solutions Fail and the Business Value of Solution ArchitectureAlan McSweeney
 
Implementing Effective Enterprise Architecture
Implementing Effective Enterprise ArchitectureImplementing Effective Enterprise Architecture
Implementing Effective Enterprise ArchitectureLeo Shuster
 

La actualidad más candente (20)

Solution Architecture Concept Workshop
Solution Architecture Concept WorkshopSolution Architecture Concept Workshop
Solution Architecture Concept Workshop
 
Solution Architecture And (Robotic) Process Automation Solutions
Solution Architecture And (Robotic) Process Automation SolutionsSolution Architecture And (Robotic) Process Automation Solutions
Solution Architecture And (Robotic) Process Automation Solutions
 
Incorporating A DesignOps Approach Into Solution Architecture
Incorporating A DesignOps Approach Into Solution ArchitectureIncorporating A DesignOps Approach Into Solution Architecture
Incorporating A DesignOps Approach Into Solution Architecture
 
Solution Architecture And Solution Security
Solution Architecture And Solution SecuritySolution Architecture And Solution Security
Solution Architecture And Solution Security
 
Solution Architecture Framework
Solution Architecture FrameworkSolution Architecture Framework
Solution Architecture Framework
 
Solution Security Architecture
Solution Security ArchitectureSolution Security Architecture
Solution Security Architecture
 
Review of Information Technology Function Critical Capability Models
Review of Information Technology Function Critical Capability ModelsReview of Information Technology Function Critical Capability Models
Review of Information Technology Function Critical Capability Models
 
Digital Transformation And Enterprise Architecture
Digital Transformation And Enterprise ArchitectureDigital Transformation And Enterprise Architecture
Digital Transformation And Enterprise Architecture
 
Introduction to Enterprise architecture and the steps to perform an Enterpris...
Introduction to Enterprise architecture and the steps to perform an Enterpris...Introduction to Enterprise architecture and the steps to perform an Enterpris...
Introduction to Enterprise architecture and the steps to perform an Enterpris...
 
Complexity and Solution Architecture
Complexity and Solution ArchitectureComplexity and Solution Architecture
Complexity and Solution Architecture
 
Introduction to Business Architecture - Part 2
Introduction to Business Architecture - Part 2Introduction to Business Architecture - Part 2
Introduction to Business Architecture - Part 2
 
Solution Architecture
Solution ArchitectureSolution Architecture
Solution Architecture
 
Shadow IT And The Failure Of IT Architecture
Shadow IT And The Failure Of IT ArchitectureShadow IT And The Failure Of IT Architecture
Shadow IT And The Failure Of IT Architecture
 
Solution architecture
Solution architectureSolution architecture
Solution architecture
 
Solution Architecture and Solution Complexity
Solution Architecture and Solution ComplexitySolution Architecture and Solution Complexity
Solution Architecture and Solution Complexity
 
Enterprise Architecture, Project Management & Digital Transformation
Enterprise Architecture, Project Management & Digital TransformationEnterprise Architecture, Project Management & Digital Transformation
Enterprise Architecture, Project Management & Digital Transformation
 
Introduction to Enterprise Architecture and TOGAF 9.1
Introduction to Enterprise Architecture and TOGAF 9.1Introduction to Enterprise Architecture and TOGAF 9.1
Introduction to Enterprise Architecture and TOGAF 9.1
 
Approach To It Strategy And Architecture
Approach To It Strategy And ArchitectureApproach To It Strategy And Architecture
Approach To It Strategy And Architecture
 
Why Solutions Fail and the Business Value of Solution Architecture
Why Solutions Fail and the Business Value of Solution ArchitectureWhy Solutions Fail and the Business Value of Solution Architecture
Why Solutions Fail and the Business Value of Solution Architecture
 
Implementing Effective Enterprise Architecture
Implementing Effective Enterprise ArchitectureImplementing Effective Enterprise Architecture
Implementing Effective Enterprise Architecture
 

Similar a Integrated Project Delivery Model for IT and Business Alignment

eCIO PPT Roles for a SAP and Systems Integration Project
eCIO PPT Roles for a SAP and Systems Integration ProjecteCIO PPT Roles for a SAP and Systems Integration Project
eCIO PPT Roles for a SAP and Systems Integration ProjectDavid Niles
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMPSubodh Kumar
 
Integrating agile into sdlc presentation pmi v2
Integrating agile into sdlc presentation   pmi v2Integrating agile into sdlc presentation   pmi v2
Integrating agile into sdlc presentation pmi v2pmimkecomm
 
E success client-software-development
E success client-software-developmentE success client-software-development
E success client-software-developmentRiyaan Sharma
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagementDhamo daran
 
2014 sdlc project and gate process rollout published v6
2014 sdlc project and gate process rollout   published v62014 sdlc project and gate process rollout   published v6
2014 sdlc project and gate process rollout published v6Jayne Edwards
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
CAPM Exam preparation - series 1
CAPM Exam preparation - series 1CAPM Exam preparation - series 1
CAPM Exam preparation - series 1Toe Myint Naing
 
Project Managment Plan V1.0 related to business.pptx
Project Managment Plan V1.0 related to business.pptxProject Managment Plan V1.0 related to business.pptx
Project Managment Plan V1.0 related to business.pptxvenupk
 
Is your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on trackIs your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on trackProject Management Solutions
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration ManagementBhuWan Khadka
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system projectalpha1unity
 
Training on ASAP Methodology.ppt
Training on ASAP Methodology.pptTraining on ASAP Methodology.ppt
Training on ASAP Methodology.pptAshwaniKumar207236
 
Vamsi Krishna Gudiputi
Vamsi Krishna GudiputiVamsi Krishna Gudiputi
Vamsi Krishna GudiputiVamsi Gudiputi
 
Consultancy brochure_Europe (final)
Consultancy brochure_Europe (final)Consultancy brochure_Europe (final)
Consultancy brochure_Europe (final)Anthony Davies
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system projecta23ccb
 

Similar a Integrated Project Delivery Model for IT and Business Alignment (20)

PMP Prep Handout_Integration
PMP Prep Handout_IntegrationPMP Prep Handout_Integration
PMP Prep Handout_Integration
 
eCIO PPT Roles for a SAP and Systems Integration Project
eCIO PPT Roles for a SAP and Systems Integration ProjecteCIO PPT Roles for a SAP and Systems Integration Project
eCIO PPT Roles for a SAP and Systems Integration Project
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
 
Integrating agile into sdlc presentation pmi v2
Integrating agile into sdlc presentation   pmi v2Integrating agile into sdlc presentation   pmi v2
Integrating agile into sdlc presentation pmi v2
 
E success client-software-development
E success client-software-developmentE success client-software-development
E success client-software-development
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
2014 sdlc project and gate process rollout published v6
2014 sdlc project and gate process rollout   published v62014 sdlc project and gate process rollout   published v6
2014 sdlc project and gate process rollout published v6
 
3 project life cycle
3   project life cycle3   project life cycle
3 project life cycle
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
CAPM Exam preparation - series 1
CAPM Exam preparation - series 1CAPM Exam preparation - series 1
CAPM Exam preparation - series 1
 
Project Managment Plan V1.0 related to business.pptx
Project Managment Plan V1.0 related to business.pptxProject Managment Plan V1.0 related to business.pptx
Project Managment Plan V1.0 related to business.pptx
 
Is your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on trackIs your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on track
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration Management
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
 
Training on ASAP Methodology.ppt
Training on ASAP Methodology.pptTraining on ASAP Methodology.ppt
Training on ASAP Methodology.ppt
 
PROJECT MANAGEMENT
PROJECT MANAGEMENTPROJECT MANAGEMENT
PROJECT MANAGEMENT
 
Vamsi Krishna Gudiputi
Vamsi Krishna GudiputiVamsi Krishna Gudiputi
Vamsi Krishna Gudiputi
 
Consultancy brochure_Europe (final)
Consultancy brochure_Europe (final)Consultancy brochure_Europe (final)
Consultancy brochure_Europe (final)
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
 

Más de Alan McSweeney

Data Architecture for Solutions.pdf
Data Architecture for Solutions.pdfData Architecture for Solutions.pdf
Data Architecture for Solutions.pdfAlan McSweeney
 
Solution Architecture and Solution Estimation.pdf
Solution Architecture and Solution Estimation.pdfSolution Architecture and Solution Estimation.pdf
Solution Architecture and Solution Estimation.pdfAlan McSweeney
 
Validating COVID-19 Mortality Data and Deaths for Ireland March 2020 – March ...
Validating COVID-19 Mortality Data and Deaths for Ireland March 2020 – March ...Validating COVID-19 Mortality Data and Deaths for Ireland March 2020 – March ...
Validating COVID-19 Mortality Data and Deaths for Ireland March 2020 – March ...Alan McSweeney
 
Analysis of the Numbers of Catholic Clergy and Members of Religious in Irelan...
Analysis of the Numbers of Catholic Clergy and Members of Religious in Irelan...Analysis of the Numbers of Catholic Clergy and Members of Religious in Irelan...
Analysis of the Numbers of Catholic Clergy and Members of Religious in Irelan...Alan McSweeney
 
IT Architecture’s Role In Solving Technical Debt.pdf
IT Architecture’s Role In Solving Technical Debt.pdfIT Architecture’s Role In Solving Technical Debt.pdf
IT Architecture’s Role In Solving Technical Debt.pdfAlan McSweeney
 
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...Alan McSweeney
 
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...Alan McSweeney
 
Data Profiling, Data Catalogs and Metadata Harmonisation
Data Profiling, Data Catalogs and Metadata HarmonisationData Profiling, Data Catalogs and Metadata Harmonisation
Data Profiling, Data Catalogs and Metadata HarmonisationAlan McSweeney
 
Comparison of COVID-19 Mortality Data and Deaths for Ireland March 2020 – Mar...
Comparison of COVID-19 Mortality Data and Deaths for Ireland March 2020 – Mar...Comparison of COVID-19 Mortality Data and Deaths for Ireland March 2020 – Mar...
Comparison of COVID-19 Mortality Data and Deaths for Ireland March 2020 – Mar...Alan McSweeney
 
Analysis of Decentralised, Distributed Decision-Making For Optimising Domesti...
Analysis of Decentralised, Distributed Decision-Making For Optimising Domesti...Analysis of Decentralised, Distributed Decision-Making For Optimising Domesti...
Analysis of Decentralised, Distributed Decision-Making For Optimising Domesti...Alan McSweeney
 
Operational Risk Management Data Validation Architecture
Operational Risk Management Data Validation ArchitectureOperational Risk Management Data Validation Architecture
Operational Risk Management Data Validation ArchitectureAlan McSweeney
 
Data Integration, Access, Flow, Exchange, Transfer, Load And Extract Architec...
Data Integration, Access, Flow, Exchange, Transfer, Load And Extract Architec...Data Integration, Access, Flow, Exchange, Transfer, Load And Extract Architec...
Data Integration, Access, Flow, Exchange, Transfer, Load And Extract Architec...Alan McSweeney
 
Ireland 2019 and 2020 Compared - Individual Charts
Ireland   2019 and 2020 Compared - Individual ChartsIreland   2019 and 2020 Compared - Individual Charts
Ireland 2019 and 2020 Compared - Individual ChartsAlan McSweeney
 
Analysis of Irish Mortality Using Public Data Sources 2014-2020
Analysis of Irish Mortality Using Public Data Sources 2014-2020Analysis of Irish Mortality Using Public Data Sources 2014-2020
Analysis of Irish Mortality Using Public Data Sources 2014-2020Alan McSweeney
 
Ireland – 2019 And 2020 Compared In Data
Ireland – 2019 And 2020 Compared In DataIreland – 2019 And 2020 Compared In Data
Ireland – 2019 And 2020 Compared In DataAlan McSweeney
 
Critical Review of Open Group IT4IT Reference Architecture
Critical Review of Open Group IT4IT Reference ArchitectureCritical Review of Open Group IT4IT Reference Architecture
Critical Review of Open Group IT4IT Reference ArchitectureAlan McSweeney
 
Analysis of Possible Excess COVID-19 Deaths in Ireland From Jan 2020 to Jun 2020
Analysis of Possible Excess COVID-19 Deaths in Ireland From Jan 2020 to Jun 2020Analysis of Possible Excess COVID-19 Deaths in Ireland From Jan 2020 to Jun 2020
Analysis of Possible Excess COVID-19 Deaths in Ireland From Jan 2020 to Jun 2020Alan McSweeney
 
Creating A Business Focussed Information Technology Strategy
Creating A Business Focussed Information Technology StrategyCreating A Business Focussed Information Technology Strategy
Creating A Business Focussed Information Technology StrategyAlan McSweeney
 
Describing the Organisation Data Landscape
Describing the Organisation Data LandscapeDescribing the Organisation Data Landscape
Describing the Organisation Data LandscapeAlan McSweeney
 
Solution Architecture Centre Of Excellence
Solution Architecture Centre Of ExcellenceSolution Architecture Centre Of Excellence
Solution Architecture Centre Of ExcellenceAlan McSweeney
 

Más de Alan McSweeney (20)

Data Architecture for Solutions.pdf
Data Architecture for Solutions.pdfData Architecture for Solutions.pdf
Data Architecture for Solutions.pdf
 
Solution Architecture and Solution Estimation.pdf
Solution Architecture and Solution Estimation.pdfSolution Architecture and Solution Estimation.pdf
Solution Architecture and Solution Estimation.pdf
 
Validating COVID-19 Mortality Data and Deaths for Ireland March 2020 – March ...
Validating COVID-19 Mortality Data and Deaths for Ireland March 2020 – March ...Validating COVID-19 Mortality Data and Deaths for Ireland March 2020 – March ...
Validating COVID-19 Mortality Data and Deaths for Ireland March 2020 – March ...
 
Analysis of the Numbers of Catholic Clergy and Members of Religious in Irelan...
Analysis of the Numbers of Catholic Clergy and Members of Religious in Irelan...Analysis of the Numbers of Catholic Clergy and Members of Religious in Irelan...
Analysis of the Numbers of Catholic Clergy and Members of Religious in Irelan...
 
IT Architecture’s Role In Solving Technical Debt.pdf
IT Architecture’s Role In Solving Technical Debt.pdfIT Architecture’s Role In Solving Technical Debt.pdf
IT Architecture’s Role In Solving Technical Debt.pdf
 
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
 
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
 
Data Profiling, Data Catalogs and Metadata Harmonisation
Data Profiling, Data Catalogs and Metadata HarmonisationData Profiling, Data Catalogs and Metadata Harmonisation
Data Profiling, Data Catalogs and Metadata Harmonisation
 
Comparison of COVID-19 Mortality Data and Deaths for Ireland March 2020 – Mar...
Comparison of COVID-19 Mortality Data and Deaths for Ireland March 2020 – Mar...Comparison of COVID-19 Mortality Data and Deaths for Ireland March 2020 – Mar...
Comparison of COVID-19 Mortality Data and Deaths for Ireland March 2020 – Mar...
 
Analysis of Decentralised, Distributed Decision-Making For Optimising Domesti...
Analysis of Decentralised, Distributed Decision-Making For Optimising Domesti...Analysis of Decentralised, Distributed Decision-Making For Optimising Domesti...
Analysis of Decentralised, Distributed Decision-Making For Optimising Domesti...
 
Operational Risk Management Data Validation Architecture
Operational Risk Management Data Validation ArchitectureOperational Risk Management Data Validation Architecture
Operational Risk Management Data Validation Architecture
 
Data Integration, Access, Flow, Exchange, Transfer, Load And Extract Architec...
Data Integration, Access, Flow, Exchange, Transfer, Load And Extract Architec...Data Integration, Access, Flow, Exchange, Transfer, Load And Extract Architec...
Data Integration, Access, Flow, Exchange, Transfer, Load And Extract Architec...
 
Ireland 2019 and 2020 Compared - Individual Charts
Ireland   2019 and 2020 Compared - Individual ChartsIreland   2019 and 2020 Compared - Individual Charts
Ireland 2019 and 2020 Compared - Individual Charts
 
Analysis of Irish Mortality Using Public Data Sources 2014-2020
Analysis of Irish Mortality Using Public Data Sources 2014-2020Analysis of Irish Mortality Using Public Data Sources 2014-2020
Analysis of Irish Mortality Using Public Data Sources 2014-2020
 
Ireland – 2019 And 2020 Compared In Data
Ireland – 2019 And 2020 Compared In DataIreland – 2019 And 2020 Compared In Data
Ireland – 2019 And 2020 Compared In Data
 
Critical Review of Open Group IT4IT Reference Architecture
Critical Review of Open Group IT4IT Reference ArchitectureCritical Review of Open Group IT4IT Reference Architecture
Critical Review of Open Group IT4IT Reference Architecture
 
Analysis of Possible Excess COVID-19 Deaths in Ireland From Jan 2020 to Jun 2020
Analysis of Possible Excess COVID-19 Deaths in Ireland From Jan 2020 to Jun 2020Analysis of Possible Excess COVID-19 Deaths in Ireland From Jan 2020 to Jun 2020
Analysis of Possible Excess COVID-19 Deaths in Ireland From Jan 2020 to Jun 2020
 
Creating A Business Focussed Information Technology Strategy
Creating A Business Focussed Information Technology StrategyCreating A Business Focussed Information Technology Strategy
Creating A Business Focussed Information Technology Strategy
 
Describing the Organisation Data Landscape
Describing the Organisation Data LandscapeDescribing the Organisation Data Landscape
Describing the Organisation Data Landscape
 
Solution Architecture Centre Of Excellence
Solution Architecture Centre Of ExcellenceSolution Architecture Centre Of Excellence
Solution Architecture Centre Of Excellence
 

Último

Developing An App To Navigate The Roads of Brazil
Developing An App To Navigate The Roads of BrazilDeveloping An App To Navigate The Roads of Brazil
Developing An App To Navigate The Roads of BrazilV3cube
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 

Último (20)

Developing An App To Navigate The Roads of Brazil
Developing An App To Navigate The Roads of BrazilDeveloping An App To Navigate The Roads of Brazil
Developing An App To Navigate The Roads of Brazil
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 

Integrated Project Delivery Model for IT and Business Alignment

  • 1. IT Integrated Project/ Solution Delivery And Business Engagement Model Alan McSweeney
  • 2. Core Dimensions Of Projects Every Project Has Two Core Dimensions: IT And Business Functions/ Roles/ Activities 1. Project Stages from Initial Concept to Delivery 2. Various Stakeholders Involved at Various Project Stages and in Various Roles Performing Various Activities Project Stages/Timeline March 2, 2014 2
  • 3. Integrated Project Business Engagement Model • • Projects are a continuum from initial concept to planning, design, implementation and management and operation of the implemented solution (and ultimate decommissioning) and across IT and business functions Therefore important to have an integrated project delivery approach that crosses both these core dimensions March 2, 2014 3
  • 4. Components Of Integrated Project Delivery And Business Engagement Model Stages S Artefacts A A Activities G Gates March 2, 2014 4
  • 5. Extended Dimensions Of Project Delivery Project Review and Decision Gates IT And Business Functions/ Roles/ Activities Artefacts Project Stages/Timeline March 2, 2014 5
  • 6. Extended Dimensions Of Project Delivery • Offers a common and consistent frame of reference for all projects
  • 7. Integrated Project Delivery Process And Business Engagement Model Time Project Stages/ Timeline Concept Initiate Plan Design Build Test Deploy Manage and Operate Project Management Project Activity/ Function Business Functions/ Roles Business Function Business Analysis Solution Architecture Implementation and Delivery Test and Quality Organisation Readiness Service Management Infrastructure and Communications March 2, 2014 7
  • 8. Integrated Project Delivery Process And Business Engagement Model Take an artefacts- and results/deliverables-based integrated approach with review gates where go/no-go decisions are made • Across all project phases and project delivery roles • Focus on getting the project right at the start will yield benefits • Provides a complete view of what has to be achieved • Allows project status to be assessed • Allows effort to be quantified across all stages and resources • Designed to reduce risk of project failures • March 2, 2014 8
  • 9. Integrated Project Delivery Process • Integrates project management into all other aspects and activities of project and solution delivery − Business − Business Analysis − Solution Architecture − Implementation and Delivery − Test and Quality − Organisation Readiness − Service Management − Infrastructure • All relevant stakeholders are identified at an early stage and involved throughout subsequently March 2, 2014 9
  • 10. Spectrum Of Project Failures Performance and/or Operational Problems Specified Business Benefits and Savings Not Delivered Functionality Delivered Does not Meet Business Requirements More Expensive to Operate Than Planned Significant Rework Required Project Late and/or Over Budget Complete Project Success: On-time, On-budget and Delivering Specified Benefits March 2, 2014 Solution Largely Unused And/Or Unusable Increasing Frequency/ Probability of Occurrence Complete Project Failure: Cancelled, Unused, Rejected 10
  • 11. Project Failures • Project Failures – late projects, over budget, project functionality not delivered, anticipated business benefits not achieved • Project Rework – involving additional cost • Deferred/Removed Scope – needed to meet project schedule and either never implemented or implemented later at additional cost March 2, 2014 11
  • 12. Reasons For Project Failures • Project foundations not correct before implementation starts − Project failure is embedded in the process from the start • • • • • • Requirements - not captured, documented, validated and agreed – poor requirement management process and capability Design - proposed solution designs not analysed and defined in sufficient detail to understand Implementation - started before scope and complexity understood, documented and defined - there is no check ensure detail is captured and documented before development starts Scope - Project scope not defined and challenged and solution complexity not understood and documented Stakeholders – all stakeholders not accurately identified Budget – project costs are not validated or challenged March 2, 2014 12
  • 13. Artefacts/Deliverables Define Across Project Delivery Process Time Project Stages/ Timeline Concept Project Management Project Activity/ Function Business Functions/ Roles Business Function Business Analysis Solution Architecture Implementation and Delivery Test and Quality Organisation Readiness Service Management Infrastructure and Communications March 2, 2014 Initiate Plan Design Build Test Deploy Manage and Operate Artefact Artefact Artefact Artefact Artefact Artefact Artefact Artefact 13
  • 14. Artefacts/Deliverables • Exist to demonstrate work done to a defined standard and quality • Forces projects to gather information to validate their activities • Provides an audit trail and proof of work done • Provides a library of project material that can be reused for other projects • Artefacts structures are designed to be generic to apply across all project types March 2, 2014 14
  • 15. Artefact View Of Integrated Project Delivery Process Concept Business Function Solution Concept/ Requirements Document Delivery Project Plan Project Resource Plan Business Case Rough Order of Magnitude Estimate Solution Architecture High Level Design March 2, 2014 Deploy Operate User Acceptance Test Results Benefits Realisation Review Lessons Learned Non Functional Requirements Detailed Solution Design/ Functional Specification User Acceptance Test Design and Plan Standard Operating Procedures Confirmed Estimates Data Migration Results Data Audit Data Design and Data Build Documentation Configuration Migration Plan Management Approach Unit Test Results and Plan Technical/Build Integration Test Results Specification Detailed Estimates Documentation Library Data Migration Test System Test Plan Results UAT Changes and Rework Data Migration to Live Results Deploy to Production Results Support and Operations Documentation Go Live Support Functional Test Design Functional Test Results Operational Readiness and Plan Review Non-Functional Test Non-Functional Test Results Design and Plan Integration Test Integration Test Design Results and Plan System Test Results System Test Design and Plan Management Team Briefing Communications Strategy and Plan Change Impact Assessment Detailed Communications Plan Training Needs Analysis Service Impact Assessment Service Level Requirements Access and Security Definition Infrastructure Plan Infrastructure Test Project Management – Planning, Resource, Scheduling Risk, Actions, Issues and Dependencies Management Reporting and Communications Management Change Management To Be Process Definition Test and Quality Service Management Build Benefits Schedule and Benefits Realisation Plan Test Strategy Organisation Readiness Design Functional Requirements As Is Process Definition Business Analysis Solution Architecture Plan Project Charter Project Initiation Document Project Management Initiate Change Action Plan Role Definition Organisation Design Develop Training Material Training Schedule Operations Acceptance Operations Acceptance Testing Design and Plan Testing Results Service Definition Infrastructure Design Build Test Environment Infrastructure Technical Build UAT Environment Specification Build OAT Environment Build Development Environment Build Training Environment Organisation and Staffing Implementation Training Delivery Service and Operational Level Agreement(s) Transfer to Production Plan Build Production Environment Decommission Unused Environments 15
  • 16. Artefact View Of Integrated Project Delivery Process • Takes a complete view of project delivery and implementation from initial design to management and operation March 2, 2014 16
  • 17. Artefact View Integrates Different Activity Lifecycles Strategy, Business Planning and Business Analysis Business Concept Initial Discovery Requirements Elicitation Decision to Proceed Requirements Management and Change Management Operations and Use Solution Architecture and Design Solution Architecture Solution Design Solution Specification and Change Management Project Management Cycle Initiate Execute and Control Plan Close Solution Delivery - Implementation and Deployment Lifecycle Setup and Prepare March 2, 2014 Implement Manage Develop Test Evolve Deploy 17
  • 18. Initial Focus Area – Business Engagement And Solution Definition Time Getting This Right … Project Stages/ Timeline Concept Project Management Project Activity/ Function Business Functions/ Roles Business Function Business Analysis Solution Architecture Plan Design Build Test Deploy Manage and Operate Focus on these project stages and project activities will ensure that the project foundations are sound Implementation and Delivery Test and Quality Organisation Readiness Service Management Infrastructure and Communications March 2, 2014 Initiate … Means Problems Will Be Avoided At Later Stages 18
  • 19. Artefact View Of Initial Focus Area – Business Engagement And Solution Definition Business Function Solution Concept/ Requirements Document Plan Project Plan Project Initiation Document Project Management Initiate Project Charter Concept Project Resource Plan Business Case Design Benefits Schedule and Benefits Realisation Plan Functional Requirements As Is Process Definition Business Analysis Solution Architecture • Rough Order of Magnitude Estimate To Be Process Definition Non Functional Requirements Solution Architecture High Level Design Detailed Solution Design/ Functional Specification Establishes solid foundations on which to build solution delivery and implementation March 2, 2014 19
  • 20. Initial Focus Area – Business Engagement And Solution Definition March 2, 2014 20
  • 21. Initial Focus Area – Business Engagement And Solution Definition And Validation • Have a defined solution to meet a defined and articulated business need that will deliver a realisable and achievable set of business benefits • Understand the complexity of what has to be delivered March 2, 2014 21
  • 22. Initial Focus Area – Business Engagement And Solution Definition And Validation • Ensures there is a strong and solid foundation for solution implementation, delivery and management and operation March 2, 2014 22
  • 23. Initial Focus Area – Business Engagement And Solution Definition And Validation Time Getting These Wrong … Project Stages/ Timeline Concept Project Management Project Activity/ Function Business Functions/ Roles Initiate Plan Design Build Test Deploy Manage and Operate Solution Concept/ Requirements Business Case Business Function Functional Requirements Business Analysis High Level Design Solution Architecture Benefits Schedule and Benefits Realisation Plan Implementation and Delivery Test and Quality Organisation Readiness Service Management Infrastructure and Communications … Means Problems Will Occur During The Project March 2, 2014 23
  • 24. Initial Focus Area – Business Engagement And Solution Definition And Validation • Where there are gaps in the foundation on which solution implementation is being based, the project is at significant risk of failure March 2, 2014 24
  • 25. Weaknesses In Business Analysis And Solution Design Capabilities At The Root of Many Project Failures Poor Requirements Poor Analysis Practices Business Requirements Not Captured Size/Capacity/ Complexity Large Project, Complex, Difficult Changes and Processes Poor Strategic Alignment Inadequate Business Case, Undefined Problem/Need Large Project Team and Multiple Stakeholders Business Benefits Not Measured Business Needs Not Met Opportunities Lost Inadequate Resource Allocation and Prioritisation Inadequate Business Involvement Dynamic, Changing Environment Poor Focus on Business Needs March 2, 2014 Inadequately Explored Solution Options Unproven Technology Investment Wasted Solution Design Not Aligned to Business Needs Uncertainly/ Ambiguity Poor Solution Design 25
  • 26. Analysis And Solution Design-Related Causes Of Failures Poor Requirements Poor Analysis Practices Business Requirements Not Captured Size/Capacity/ Complexity Large Project, Complex, Difficult Changes and Processes Poor Strategic Alignment Inadequate Business Case, Undefined Problem/Need Large Project Team and Multiple Stakeholders Business Benefits Not Measured Business Needs Not Met Opportunities Lost Inadequate Resource Allocation and Prioritisation Inadequate Business Involvement Dynamic, Changing Environment Poor Focus on Business Needs March 2, 2014 Inadequately Explored Solution Options Unproven Technology Investment Wasted Solution Design Not Aligned to Business Needs Uncertainly/ Ambiguity Poor Solution Design 26
  • 27. Project Gates Time Project Stages/ Timeline Concept Initiate Plan Design Build Test Deploy Manage and Operate Project Management Business Analysis Gate 7 Gate 6 Gate 5 Gate 4 Gate 3 Test and Quality Gate 2 Implementation and Delivery Gate 1 Solution Architecture Gate 0 Project Activity/ Function Business Functions/ Roles Business Function Organisation Readiness Service Management Infrastructure and Communications March 2, 2014 27
  • 28. Project Gates • Gates exist after each to ensure project is ready to move to the next stage or to be stopped or whether rework is required • Review and decision points • Artefacts must be ready for review on gate entry • Gate exit requires artefacts completed to the required standard • Reduces cost, risk and rework • Puts controls around the delivery process • Ensures work remains on track March 2, 2014 28
  • 29. Gate Process Gate Entry Criteria Gate Successful Exit Gate Phase Phase Project Stopped Sent Back for Rework STOP March 2, 2014 29
  • 30. Project Process Gates Gate 0 Concept Gate 1 Initiate Plan Gate 2 Gate 3 Gate 4 Test Build Design Gate 5 Gate 7 Gate 6 Deploy March 2, 2014 Operate 30
  • 31. Project Process Gates Gate 0 Concept Gate 1 Initiate Plan Validate Solution Concept and Estimates and Make Go/No Go Decision Gate 4 Gate 3 Test Gate 5 Build Build Review, Organisation Design Review, Readiness to Proceed to System Test and UAT March 2, 2014 Deploy Design Validate Detailed Design, Readiness to Proceed to Build and Make Go/No Go Decision Gate 7 Gate 6 Test Review, Organisation Change Review, Training Review, Service Planning Review Gate 2 Validate Business Case and Make Go/No Go Decision Validate Plan, High-Level Design, Benefits, Readiness to Proceed to Detailed Design and Make Go/No Go Decision Operate Go Live Readiness Review, Staffing and Training Review Benefits Realisation Validation, Lessons Learned 31
  • 32. Sample Gate Review for Gate 3 – Before Move To Implementation/Development • Gate 3 Pre-requisites − − − − − − − − − − − − − − − − − − − • Benefits Schedule To Be Processes Non-Functional Requirements Detailed Solution Design/ Functional Specification Security Design Data Design, Migration and Testing Strategy Design and Plan Functional Tests Design and Plan Integration Tests Design and Plan Non-Functional Tests System Test Plan Systems Inventory Data Migration Plan Change Impact Assessment Detailed Communications Plan Training Needs Analysis Training Strategy Service Design Capacity Requirements Plan Infrastructure Specification March 2, 2014 • 32 Gate review ensures that the relevant items have been created and are of sufficient quality Designed to ensure that solution complexity has been captured so there is confidence that what is being developed is what is needed to be developed 32
  • 33. Artefact-Based Status View Of Project Concept Project Charter Project Initiation Document Project Management Business Function Solution Concept/ Requirements Document Plan Rough Order of Magnitude Estimate Business Case Benefits Schedule and Benefits Realisation Plan To Be Process Definition Solution Architecture High Level Design Configuration Management Approach and Plan` Detailed Estimates Test and Quality Service Management Management Team Briefing Communications Strategy and Plan Service Impact Assessment Infrastructure Plan Infrastructure March 2, 2014 Test Deploy Operate User Acceptance Test Results Benefits Realisation Review Lessons Learned Non Functional Requirements Detailed Solution Design/ Functional Specification Test Strategy Organisation Readiness Build Project Plan Project Resource Plan Data Audit Delivery Design Functional Requirements As Is Process Definition Business Analysis Solution Architecture Initiate Confirmed Estimates Data Design and Data Migration Plan Technical/Build Specification User Acceptance Test Design and Plan Standard Operating Procedures Data Migration Results Build Documentation Unit Test Results Integration Test Results Documentation Library Data Migration Test System Test Plan Results UAT Changes and Rework Data Migration to Live Results Deploy to Production Results Support and Operations Documentation Go Live Support Functional Test Design Functional Test Results Operational Readiness and Plan Review Non-Functional Test Non-Functional Test Results Design and Plan Integration Test Integration Test Design Results and Plan System Test Results System Test Design and Plan Change Action Plan Change Impact Assessment Organisation Design Detailed Develop Training Communications Plan Material Training Needs Analysis Service Level Requirements Access and Security Definition Role Definition Training Schedule Operations Acceptance Operations Acceptance Testing Design and Plan Testing Results Service Definition Infrastructure Design Build Test Environment Infrastructure Technical Build UAT Environment Specification Build OAT Environment Build Development Environment Build Training Environment Organisation and Staffing Implementation Training Delivery Service and Operational Level Agreement(s) Transfer to Production Plan Build Production Environment Decommission Unused Environments 33
  • 34. Consistent View Of Projects March 2, 2014 34
  • 35. Artefact-Based Status View Of Project • Use the status of the artefacts at project stages to assess and measure the status of the project • One element of project reporting March 2, 2014 35
  • 36. Summary • Provides a consistent and repeatable approach to projects • Independent of the specifics of a project • Artefact-based view • Enables gate review process where deliverables can be evaluated for quality and substance • Enables status of the project to assessed • Ensures success by emphasising business engagement and solution analysis and design at an early stage • Engages early with project complexity March 2, 2014 36