SlideShare a Scribd company logo
1 of 4
Download to read offline
PTI JOURNAL
August 2013 • V. 9 • No. 1
JOURNAL OF THE POST-TENSIONING INSTITUTE
Effective Use of
Post-Tensioning in Buildings
15 Corner Post-Tensioned Slab-
Column Connections
49 PT Design Alternative Yields Benefits
PTI JOURNAL | August 2013 49
CASE STUDIES
One Museum Park West: Converting a
High-Rise Tower’s Structural Design to
Unbonded Post-Tensioning
By Rattan L. Khosa
One Museum Park West is a prime example of the
benefits of converting conventionally reinforced slabs into
unbonded post-tensioned slabs. The 55-story high-rise
condominium tower (Fig. 1) was originally designed with
an 8 in. (203 mm) thick concrete flat plate using reinforcing
bar. A multitude of very deep transfer girders on the sixth
floor were also designed without post-tensioning (PT).
Because the project was over budget, the concrete and
forming contractor requested that the PT supplier conduct
a Value Engineering Analysis (VEA) to reduce the cost of
the structure, though there were some concerns by a few
members of the construction team about using PT in a
floor system with a complex, irregular shape (Fig. 2).
Two value-engineered options were presented to the
construction team:
1. Option A:
	 (a) Retain all the interior columns.
	 (b)Use a 6 in. (152 mm) thick flat plate slab
with PT.
	 (c) Use PT in the transfer girders.
2. Option B:
	 (a) Retain the 8 in. (203 mm) slab thickness but
with an unbonded PT system.
	 (b) Delete some transfer girders.
	 (c) Delete some interior columns.
	 (d) Use PT in the transfer girders.
	 (e) Reduce the depth of the transfer girders.
In Option A, the transfer girder depths would decrease
due to the reduction in dead load resulting from the use
of thinner slabs. The main disadvantage in this option
was that a 7.5 in. (191 mm) slab would still be required
for plumbing in the bathrooms per code requirements of
the city of Chicago. Accordingly, this would have increased
the forming costs. Ultimately, the Owner chose Option B,
based on the enhanced value (described in the following)
and the reduction in the overall cost. Even though it
used more concrete and had a taller building height than
Option A, Option B had less concrete and building height
than the original design.
Initially, the decision was to use PT in all floors; but in
the end, PT was only used in the sixth floor (transfer floor)
to roof level due to the construction schedule of the first
five floors. To meet the construction schedule deadlines,
a consulting structural engineering company was hired to
design the structural floor system in partnership with the
PT supplier. Together, they ensured that the quantities of
the PT and reinforcing bar materials were in compliance
with the initial VEA. This alternate structural design was
incorporated into the Structural Engineer of Record’s
design documents.
The 8 in. (203 mm) thick flat plate floor had banded
tendons in the east-west direction and the uniform
Fig. 1—One Museum Park West, Chicago, IL.
50 August 2013 | PTI JOURNAL
CASE STUDIES
tendons in the north-south direction (Fig. 3). Approxi-
mately one-third of the columns were eliminated on all
levels above Level  6. Stud rails were introduced in four
columns to deal with punching shear. The post-tensioned
transfer girder depths varied from 6 ft 6 in. (2.0 m) to 8 ft
(2.4 m), which was a 25% reduction in depth compared to
the conventionally reinforced transfer girders. The transfer
girders had between 46 and 142 PT tendons. To balance
the dead load, the transfer girder tendons were stressed in
five stages at the completion of the sixth, 18th, 30th, 42nd,
and 53rd floors.
Thestructuraldesignwasbasedon5000psi(34.5 MPa)
concrete. However, the concrete contractor decided to
provide8750psi(60.3MPa)concrete.Althoughthehigher
strength concrete cost more, it allowed for stressing the
tendons the day after concrete was poured. This resulted
in a short 3-day cycle per a typical floor and reduced the
construction schedule by several weeks.
At some locations, the tendon lengths were very
short due to building plan geometry. Initially, 10% more
tendons were added to compensate for potential seating
losses and meet the required effective forces. These
“stand-by” tendons would be stressed only when there
were under-elongations. Since this “insurance” would
cost an additional $75,000, the owner deleted them and
asked for a plan to prevent elongation problems. The PT
supplier developed procedures for the PT installer to keep
the anchor cavity, the jack grippers, and the stressing tails
extremely clean. Furthermore, at the recommendation of
the PT supplier, the Structural Engineer of Record allowed
for 5% overstress when there were under-elongations in
the short-length tendons. Consequently, the actual field
elongations were exceptionally satisfactory.
Because many interior columns were deleted, more
space was opened up for residential use to the delight
of the Architect. This revision helped in the marketing
of the column-free condominiums to the delight of the
Owner. The quantity of PT in the building increased from
35,000 ft (10,688 m) in a few cantilevered balconies (orig-
inal design) to 1.6 million ft (487,680 m) in 49 floors (final
design). The concrete contractor indicated that the value
engineering resulted in a savings of $4 million due to the
items listed as follows:
•	 Reduction in the number of columns, which
reduced the concrete, reinforcing bar, and
forming costs.
•	 Deletion of several transfer girders.
•	 Reduction of the depth of remaining
transfer girders.
•	 Reduction of the reinforcing bar in slabs.
•	 Reduction of the number of caissons, though the
size of the remaining caissons did increase.
•	 Reduction of building height due to the reduc-
tion of transfer girder depths. As a result, there
were cost savings in the shear walls, curtain walls,
elevator, and vertical mechanical/electrical/
plumbing and piping/conduit.
Credits
Project: One Museum Park West, Chicago, IL
Owner: Enterprise Companies
Fig. 2—Irregular floor plan.
ConcreteandFormingContractor: Adjustable Forms, Inc.
Consulting Structural Engineering Company: Larson
Engineering
PT Supplier: AMSYSCO, Inc.
PTI Fellow Rattan L. Khosa is President/Owner of
AMSYSCO, Inc., a post-tensioning system supplier in
Romeoville, IL. Khosa earned his MS degree in structural
engineering from the University of Maryland, College
Park, MD, and his MBA from the University of Chicago,
Chicago, IL. He is a member of the PTI Board of Direc-
tors, Chair of PTI Committee DC-70, Special Topics, and
member of PTI Committee M10, Unbonded Tendon. He is
also a Past President of PTI. He is a licensed professional
engineer in multiple states with over 40 years of experience
in design and construction of post-tensioned structures.
PTI JOURNAL | August 2013 51
CASE STUDIES
Fig.3—Representativetendonplacementplan.

More Related Content

What's hot

Cost effective construction tech PPT
Cost effective construction tech PPT Cost effective construction tech PPT
Cost effective construction tech PPT Nischay N Gowda
 
PRECAST CONCRETE STAIRS
  PRECAST CONCRETE STAIRS  PRECAST CONCRETE STAIRS
PRECAST CONCRETE STAIRSAbhishek Mewada
 
Prefabrication - building construction
Prefabrication - building constructionPrefabrication - building construction
Prefabrication - building constructionMoksha Bhatia
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systemsAkshay Revekar
 
Charles correa - housing projects
Charles correa - housing projectsCharles correa - housing projects
Charles correa - housing projectsAarti Rani
 
Long span structures
Long span structures  Long span structures
Long span structures Aroh Thombre
 
PORTAL FRAME- Structural systems
PORTAL FRAME- Structural systemsPORTAL FRAME- Structural systems
PORTAL FRAME- Structural systemsGrace Henry
 
Long span structures case study (LINK IN DESCRIPTION FOR DOWNLOAD)
Long span structures case study (LINK IN DESCRIPTION FOR DOWNLOAD)Long span structures case study (LINK IN DESCRIPTION FOR DOWNLOAD)
Long span structures case study (LINK IN DESCRIPTION FOR DOWNLOAD)Dimple Poddar
 
modular coordination
modular coordinationmodular coordination
modular coordinationShailja km
 
Folded plate structure
Folded plate structureFolded plate structure
Folded plate structureVikas Mehta
 
steel roof truss
steel roof trusssteel roof truss
steel roof trussRohit Dutta
 
Folded plates and space truss structures
Folded plates and space truss  structuresFolded plates and space truss  structures
Folded plates and space truss structuresRajesh Kolli
 

What's hot (20)

Precast-concrete Details
Precast-concrete DetailsPrecast-concrete Details
Precast-concrete Details
 
Waffle slab
Waffle slabWaffle slab
Waffle slab
 
Cost effective construction tech PPT
Cost effective construction tech PPT Cost effective construction tech PPT
Cost effective construction tech PPT
 
PRECAST CONCRETE STAIRS
  PRECAST CONCRETE STAIRS  PRECAST CONCRETE STAIRS
PRECAST CONCRETE STAIRS
 
Prefabrication - building construction
Prefabrication - building constructionPrefabrication - building construction
Prefabrication - building construction
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
 
Charles correa - housing projects
Charles correa - housing projectsCharles correa - housing projects
Charles correa - housing projects
 
Cladding
CladdingCladding
Cladding
 
Highrise structure
Highrise structureHighrise structure
Highrise structure
 
Long span structures
Long span structures  Long span structures
Long span structures
 
PORTAL FRAME- Structural systems
PORTAL FRAME- Structural systemsPORTAL FRAME- Structural systems
PORTAL FRAME- Structural systems
 
Long span structures case study (LINK IN DESCRIPTION FOR DOWNLOAD)
Long span structures case study (LINK IN DESCRIPTION FOR DOWNLOAD)Long span structures case study (LINK IN DESCRIPTION FOR DOWNLOAD)
Long span structures case study (LINK IN DESCRIPTION FOR DOWNLOAD)
 
modular coordination
modular coordinationmodular coordination
modular coordination
 
Mudarchitecture,
Mudarchitecture,Mudarchitecture,
Mudarchitecture,
 
Folded plate structure
Folded plate structureFolded plate structure
Folded plate structure
 
steel roof truss
steel roof trusssteel roof truss
steel roof truss
 
Type of high rise building
Type of high rise buildingType of high rise building
Type of high rise building
 
FOLDED PLATES TYPES
FOLDED PLATES TYPES FOLDED PLATES TYPES
FOLDED PLATES TYPES
 
Filler slab
Filler slabFiller slab
Filler slab
 
Folded plates and space truss structures
Folded plates and space truss  structuresFolded plates and space truss  structures
Folded plates and space truss structures
 

Similar to One Museum Park West (Post-Tensioning case study)

Design Appraisal report
Design Appraisal reportDesign Appraisal report
Design Appraisal reportConor Meaney
 
Post tensioning in building structures
Post tensioning in building structuresPost tensioning in building structures
Post tensioning in building structuresLuan Truong Van
 
Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Ramin Vaghei
 
Case Study - One Eleven Tower
Case Study - One Eleven TowerCase Study - One Eleven Tower
Case Study - One Eleven TowerAMSYSCO Inc.
 
Post tensioned (PT) slabs
Post tensioned (PT) slabsPost tensioned (PT) slabs
Post tensioned (PT) slabsFOYSOLMAHMUD1
 
Lincoln arc welding article183
Lincoln arc welding article183Lincoln arc welding article183
Lincoln arc welding article183Miklos Peller, Sr.
 
Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wallHarsh Bothra
 
Precast Concrete is the most prominent structure
Precast Concrete is the most prominent structurePrecast Concrete is the most prominent structure
Precast Concrete is the most prominent structureNisshantSinghSaud
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesSayedaAmrin
 
Composite construction or Composite Structure/Frame
Composite construction or Composite Structure/FrameComposite construction or Composite Structure/Frame
Composite construction or Composite Structure/FrameAbdul Rahman
 
Ceb 706 design of reinforeced and presressed concrete updated!
Ceb 706 design of reinforeced and presressed concrete updated!Ceb 706 design of reinforeced and presressed concrete updated!
Ceb 706 design of reinforeced and presressed concrete updated!vishwaleenram
 
Comparison of Pre-Engineered Building and Conventional Steel Truss Building
Comparison of Pre-Engineered Building and Conventional Steel Truss BuildingComparison of Pre-Engineered Building and Conventional Steel Truss Building
Comparison of Pre-Engineered Building and Conventional Steel Truss BuildingRoshni Ramakrishnan
 
A long span structure in Romania Full paper balint karoly
A long span structure in Romania Full paper balint karolyA long span structure in Romania Full paper balint karoly
A long span structure in Romania Full paper balint karolyAnupama Krishnan
 
Low cost houisng and alternate building materials
Low cost houisng and alternate building materialsLow cost houisng and alternate building materials
Low cost houisng and alternate building materialsNaresh Yadav
 
TWIN WALL CONSTRUCTION.pptx
TWIN WALL CONSTRUCTION.pptxTWIN WALL CONSTRUCTION.pptx
TWIN WALL CONSTRUCTION.pptxSomeshMathad
 
IRJET- Analysis on Performance of Reinforced Concrete and Prestressed Slabs u...
IRJET- Analysis on Performance of Reinforced Concrete and Prestressed Slabs u...IRJET- Analysis on Performance of Reinforced Concrete and Prestressed Slabs u...
IRJET- Analysis on Performance of Reinforced Concrete and Prestressed Slabs u...IRJET Journal
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
Gen geot cs_sscanada_16.1
Gen geot cs_sscanada_16.1Gen geot cs_sscanada_16.1
Gen geot cs_sscanada_16.1Tensar
 
Whitemud Drive Retaining Wall
Whitemud Drive Retaining WallWhitemud Drive Retaining Wall
Whitemud Drive Retaining WallJim McMullan
 

Similar to One Museum Park West (Post-Tensioning case study) (20)

Design Appraisal report
Design Appraisal reportDesign Appraisal report
Design Appraisal report
 
Post tensioning in building structures
Post tensioning in building structuresPost tensioning in building structures
Post tensioning in building structures
 
Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...
 
Case Study - One Eleven Tower
Case Study - One Eleven TowerCase Study - One Eleven Tower
Case Study - One Eleven Tower
 
Post tensioned (PT) slabs
Post tensioned (PT) slabsPost tensioned (PT) slabs
Post tensioned (PT) slabs
 
Special-concretes
Special-concretesSpecial-concretes
Special-concretes
 
Lincoln arc welding article183
Lincoln arc welding article183Lincoln arc welding article183
Lincoln arc welding article183
 
Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wall
 
Precast Concrete is the most prominent structure
Precast Concrete is the most prominent structurePrecast Concrete is the most prominent structure
Precast Concrete is the most prominent structure
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examples
 
Composite construction or Composite Structure/Frame
Composite construction or Composite Structure/FrameComposite construction or Composite Structure/Frame
Composite construction or Composite Structure/Frame
 
Ceb 706 design of reinforeced and presressed concrete updated!
Ceb 706 design of reinforeced and presressed concrete updated!Ceb 706 design of reinforeced and presressed concrete updated!
Ceb 706 design of reinforeced and presressed concrete updated!
 
Comparison of Pre-Engineered Building and Conventional Steel Truss Building
Comparison of Pre-Engineered Building and Conventional Steel Truss BuildingComparison of Pre-Engineered Building and Conventional Steel Truss Building
Comparison of Pre-Engineered Building and Conventional Steel Truss Building
 
A long span structure in Romania Full paper balint karoly
A long span structure in Romania Full paper balint karolyA long span structure in Romania Full paper balint karoly
A long span structure in Romania Full paper balint karoly
 
Low cost houisng and alternate building materials
Low cost houisng and alternate building materialsLow cost houisng and alternate building materials
Low cost houisng and alternate building materials
 
TWIN WALL CONSTRUCTION.pptx
TWIN WALL CONSTRUCTION.pptxTWIN WALL CONSTRUCTION.pptx
TWIN WALL CONSTRUCTION.pptx
 
IRJET- Analysis on Performance of Reinforced Concrete and Prestressed Slabs u...
IRJET- Analysis on Performance of Reinforced Concrete and Prestressed Slabs u...IRJET- Analysis on Performance of Reinforced Concrete and Prestressed Slabs u...
IRJET- Analysis on Performance of Reinforced Concrete and Prestressed Slabs u...
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
Gen geot cs_sscanada_16.1
Gen geot cs_sscanada_16.1Gen geot cs_sscanada_16.1
Gen geot cs_sscanada_16.1
 
Whitemud Drive Retaining Wall
Whitemud Drive Retaining WallWhitemud Drive Retaining Wall
Whitemud Drive Retaining Wall
 

More from AMSYSCO Inc.

CTBUH Innovation Award Nominee - Vertical Unbonded Post-Tensioning
CTBUH Innovation Award Nominee - Vertical Unbonded Post-TensioningCTBUH Innovation Award Nominee - Vertical Unbonded Post-Tensioning
CTBUH Innovation Award Nominee - Vertical Unbonded Post-TensioningAMSYSCO Inc.
 
Case Study - University of Colorado Parking Garage and Field
Case Study - University of Colorado Parking Garage and FieldCase Study - University of Colorado Parking Garage and Field
Case Study - University of Colorado Parking Garage and FieldAMSYSCO Inc.
 
OneEleven Tower - post tensioned transfer deck
OneEleven Tower - post tensioned transfer deckOneEleven Tower - post tensioned transfer deck
OneEleven Tower - post tensioned transfer deckAMSYSCO Inc.
 
Concrete International - Wayzata Bay Infrastructure
Concrete International - Wayzata Bay InfrastructureConcrete International - Wayzata Bay Infrastructure
Concrete International - Wayzata Bay InfrastructureAMSYSCO Inc.
 
What Could You Buy For $263 Trillion
What Could You Buy For $263 TrillionWhat Could You Buy For $263 Trillion
What Could You Buy For $263 TrillionAMSYSCO Inc.
 
AMSYSCO's resume of Tall Buildings
AMSYSCO's resume of Tall BuildingsAMSYSCO's resume of Tall Buildings
AMSYSCO's resume of Tall BuildingsAMSYSCO Inc.
 
PTI Journal : Buford Ave post-tensioned pavement
PTI Journal : Buford Ave post-tensioned pavementPTI Journal : Buford Ave post-tensioned pavement
PTI Journal : Buford Ave post-tensioned pavementAMSYSCO Inc.
 
Post Tensioning Review Session for Installers
Post Tensioning Review Session for InstallersPost Tensioning Review Session for Installers
Post Tensioning Review Session for InstallersAMSYSCO Inc.
 
Infrastructure and Unbonded Post Tensioning
Infrastructure and Unbonded Post TensioningInfrastructure and Unbonded Post Tensioning
Infrastructure and Unbonded Post TensioningAMSYSCO Inc.
 
The Importance of Unbonded Field Certification
The Importance of Unbonded Field CertificationThe Importance of Unbonded Field Certification
The Importance of Unbonded Field CertificationAMSYSCO Inc.
 
Minnesota Twins Target Field & Post Tensioning
Minnesota Twins Target Field & Post TensioningMinnesota Twins Target Field & Post Tensioning
Minnesota Twins Target Field & Post TensioningAMSYSCO Inc.
 
Case Study – Social Media Small Business
Case Study – Social Media Small BusinessCase Study – Social Media Small Business
Case Study – Social Media Small BusinessAMSYSCO Inc.
 
2009 PTI Legends & Fellow Awards
2009 PTI Legends & Fellow Awards2009 PTI Legends & Fellow Awards
2009 PTI Legends & Fellow AwardsAMSYSCO Inc.
 
2008 PTI Awards Booklet
2008 PTI Awards Booklet2008 PTI Awards Booklet
2008 PTI Awards BookletAMSYSCO Inc.
 
Post-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsPost-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsAMSYSCO Inc.
 
White paper - Encapsulated Post Tensioned Concrete
White paper -  Encapsulated Post Tensioned ConcreteWhite paper -  Encapsulated Post Tensioned Concrete
White paper - Encapsulated Post Tensioned ConcreteAMSYSCO Inc.
 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post TensioningAMSYSCO Inc.
 
Parking Today article: Louisville Arena
Parking Today article: Louisville ArenaParking Today article: Louisville Arena
Parking Today article: Louisville ArenaAMSYSCO Inc.
 
ENR Article: 1620 S. Michigan Condos
ENR Article: 1620 S. Michigan CondosENR Article: 1620 S. Michigan Condos
ENR Article: 1620 S. Michigan CondosAMSYSCO Inc.
 

More from AMSYSCO Inc. (20)

CTBUH Innovation Award Nominee - Vertical Unbonded Post-Tensioning
CTBUH Innovation Award Nominee - Vertical Unbonded Post-TensioningCTBUH Innovation Award Nominee - Vertical Unbonded Post-Tensioning
CTBUH Innovation Award Nominee - Vertical Unbonded Post-Tensioning
 
Case Study - University of Colorado Parking Garage and Field
Case Study - University of Colorado Parking Garage and FieldCase Study - University of Colorado Parking Garage and Field
Case Study - University of Colorado Parking Garage and Field
 
OneEleven Tower - post tensioned transfer deck
OneEleven Tower - post tensioned transfer deckOneEleven Tower - post tensioned transfer deck
OneEleven Tower - post tensioned transfer deck
 
Concrete International - Wayzata Bay Infrastructure
Concrete International - Wayzata Bay InfrastructureConcrete International - Wayzata Bay Infrastructure
Concrete International - Wayzata Bay Infrastructure
 
What Could You Buy For $263 Trillion
What Could You Buy For $263 TrillionWhat Could You Buy For $263 Trillion
What Could You Buy For $263 Trillion
 
AMSYSCO's resume of Tall Buildings
AMSYSCO's resume of Tall BuildingsAMSYSCO's resume of Tall Buildings
AMSYSCO's resume of Tall Buildings
 
PTI Journal : Buford Ave post-tensioned pavement
PTI Journal : Buford Ave post-tensioned pavementPTI Journal : Buford Ave post-tensioned pavement
PTI Journal : Buford Ave post-tensioned pavement
 
Post Tensioning Review Session for Installers
Post Tensioning Review Session for InstallersPost Tensioning Review Session for Installers
Post Tensioning Review Session for Installers
 
Infrastructure and Unbonded Post Tensioning
Infrastructure and Unbonded Post TensioningInfrastructure and Unbonded Post Tensioning
Infrastructure and Unbonded Post Tensioning
 
The Importance of Unbonded Field Certification
The Importance of Unbonded Field CertificationThe Importance of Unbonded Field Certification
The Importance of Unbonded Field Certification
 
Minnesota Twins Target Field & Post Tensioning
Minnesota Twins Target Field & Post TensioningMinnesota Twins Target Field & Post Tensioning
Minnesota Twins Target Field & Post Tensioning
 
Case Study – Social Media Small Business
Case Study – Social Media Small BusinessCase Study – Social Media Small Business
Case Study – Social Media Small Business
 
2009 PTI Legends & Fellow Awards
2009 PTI Legends & Fellow Awards2009 PTI Legends & Fellow Awards
2009 PTI Legends & Fellow Awards
 
2008 PTI Awards Booklet
2008 PTI Awards Booklet2008 PTI Awards Booklet
2008 PTI Awards Booklet
 
Build for You
Build for YouBuild for You
Build for You
 
Post-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsPost-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for Contractors
 
White paper - Encapsulated Post Tensioned Concrete
White paper -  Encapsulated Post Tensioned ConcreteWhite paper -  Encapsulated Post Tensioned Concrete
White paper - Encapsulated Post Tensioned Concrete
 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post Tensioning
 
Parking Today article: Louisville Arena
Parking Today article: Louisville ArenaParking Today article: Louisville Arena
Parking Today article: Louisville Arena
 
ENR Article: 1620 S. Michigan Condos
ENR Article: 1620 S. Michigan CondosENR Article: 1620 S. Michigan Condos
ENR Article: 1620 S. Michigan Condos
 

Recently uploaded

怎么办理英国Newcastle毕业证纽卡斯尔大学学位证书一手渠道
怎么办理英国Newcastle毕业证纽卡斯尔大学学位证书一手渠道怎么办理英国Newcastle毕业证纽卡斯尔大学学位证书一手渠道
怎么办理英国Newcastle毕业证纽卡斯尔大学学位证书一手渠道yrolcks
 
Pearl Disrtrict urban analyusis study pptx
Pearl Disrtrict urban analyusis study pptxPearl Disrtrict urban analyusis study pptx
Pearl Disrtrict urban analyusis study pptxDanielTamiru4
 
Unit1_Syllbwbnwnwneneneneneneentation_Sem2.pptx
Unit1_Syllbwbnwnwneneneneneneentation_Sem2.pptxUnit1_Syllbwbnwnwneneneneneneentation_Sem2.pptx
Unit1_Syllbwbnwnwneneneneneneentation_Sem2.pptxNitish292041
 
Pharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdfPharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdfAayushChavan5
 
10 Best WordPress Plugins to make the website effective in 2024
10 Best WordPress Plugins to make the website effective in 202410 Best WordPress Plugins to make the website effective in 2024
10 Best WordPress Plugins to make the website effective in 2024digital learning point
 
The spirit of digital place - game worlds and architectural phenomenology
The spirit of digital place - game worlds and architectural phenomenologyThe spirit of digital place - game worlds and architectural phenomenology
The spirit of digital place - game worlds and architectural phenomenologyChristopher Totten
 
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书zdzoqco
 
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.pptMaking and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.pptJIT KUMAR GUPTA
 
10 must-have Chrome extensions for designers
10 must-have Chrome extensions for designers10 must-have Chrome extensions for designers
10 must-have Chrome extensions for designersPixeldarts
 
cda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis pptcda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis pptMaryamAfzal41
 
group_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfgroup_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfneelspinoy
 
AI and Design Vol. 2: Navigating the New Frontier - Morgenbooster
AI and Design Vol. 2: Navigating the New Frontier - MorgenboosterAI and Design Vol. 2: Navigating the New Frontier - Morgenbooster
AI and Design Vol. 2: Navigating the New Frontier - Morgenbooster1508 A/S
 
Piece by Piece Magazine
Piece by Piece Magazine                      Piece by Piece Magazine
Piece by Piece Magazine CharlottePulte
 
world health day 2024.pptxgbbvggvbhjjjbbbb
world health day 2024.pptxgbbvggvbhjjjbbbbworld health day 2024.pptxgbbvggvbhjjjbbbb
world health day 2024.pptxgbbvggvbhjjjbbbbpreetirao780
 
simpson-lee_house_dt20ajshsjsjsjsjj15.pdf
simpson-lee_house_dt20ajshsjsjsjsjj15.pdfsimpson-lee_house_dt20ajshsjsjsjsjj15.pdf
simpson-lee_house_dt20ajshsjsjsjsjj15.pdfLucyBonelli
 
How to Empower the future of UX Design with Gen AI
How to Empower the future of UX Design with Gen AIHow to Empower the future of UX Design with Gen AI
How to Empower the future of UX Design with Gen AIyuj
 
Map of St. Louis Parks
Map of St. Louis Parks                              Map of St. Louis Parks
Map of St. Louis Parks CharlottePulte
 
Karim apartment ideas 01 ppppppppppppppp
Karim apartment ideas 01 pppppppppppppppKarim apartment ideas 01 ppppppppppppppp
Karim apartment ideas 01 pppppppppppppppNadaMohammed714321
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Rndexperts
 
General Knowledge Quiz Game C++ CODE.pptx
General Knowledge Quiz Game C++ CODE.pptxGeneral Knowledge Quiz Game C++ CODE.pptx
General Knowledge Quiz Game C++ CODE.pptxmarckustrevion
 

Recently uploaded (20)

怎么办理英国Newcastle毕业证纽卡斯尔大学学位证书一手渠道
怎么办理英国Newcastle毕业证纽卡斯尔大学学位证书一手渠道怎么办理英国Newcastle毕业证纽卡斯尔大学学位证书一手渠道
怎么办理英国Newcastle毕业证纽卡斯尔大学学位证书一手渠道
 
Pearl Disrtrict urban analyusis study pptx
Pearl Disrtrict urban analyusis study pptxPearl Disrtrict urban analyusis study pptx
Pearl Disrtrict urban analyusis study pptx
 
Unit1_Syllbwbnwnwneneneneneneentation_Sem2.pptx
Unit1_Syllbwbnwnwneneneneneneentation_Sem2.pptxUnit1_Syllbwbnwnwneneneneneneentation_Sem2.pptx
Unit1_Syllbwbnwnwneneneneneneentation_Sem2.pptx
 
Pharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdfPharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdf
 
10 Best WordPress Plugins to make the website effective in 2024
10 Best WordPress Plugins to make the website effective in 202410 Best WordPress Plugins to make the website effective in 2024
10 Best WordPress Plugins to make the website effective in 2024
 
The spirit of digital place - game worlds and architectural phenomenology
The spirit of digital place - game worlds and architectural phenomenologyThe spirit of digital place - game worlds and architectural phenomenology
The spirit of digital place - game worlds and architectural phenomenology
 
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
 
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.pptMaking and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
 
10 must-have Chrome extensions for designers
10 must-have Chrome extensions for designers10 must-have Chrome extensions for designers
10 must-have Chrome extensions for designers
 
cda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis pptcda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis ppt
 
group_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfgroup_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdf
 
AI and Design Vol. 2: Navigating the New Frontier - Morgenbooster
AI and Design Vol. 2: Navigating the New Frontier - MorgenboosterAI and Design Vol. 2: Navigating the New Frontier - Morgenbooster
AI and Design Vol. 2: Navigating the New Frontier - Morgenbooster
 
Piece by Piece Magazine
Piece by Piece Magazine                      Piece by Piece Magazine
Piece by Piece Magazine
 
world health day 2024.pptxgbbvggvbhjjjbbbb
world health day 2024.pptxgbbvggvbhjjjbbbbworld health day 2024.pptxgbbvggvbhjjjbbbb
world health day 2024.pptxgbbvggvbhjjjbbbb
 
simpson-lee_house_dt20ajshsjsjsjsjj15.pdf
simpson-lee_house_dt20ajshsjsjsjsjj15.pdfsimpson-lee_house_dt20ajshsjsjsjsjj15.pdf
simpson-lee_house_dt20ajshsjsjsjsjj15.pdf
 
How to Empower the future of UX Design with Gen AI
How to Empower the future of UX Design with Gen AIHow to Empower the future of UX Design with Gen AI
How to Empower the future of UX Design with Gen AI
 
Map of St. Louis Parks
Map of St. Louis Parks                              Map of St. Louis Parks
Map of St. Louis Parks
 
Karim apartment ideas 01 ppppppppppppppp
Karim apartment ideas 01 pppppppppppppppKarim apartment ideas 01 ppppppppppppppp
Karim apartment ideas 01 ppppppppppppppp
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025
 
General Knowledge Quiz Game C++ CODE.pptx
General Knowledge Quiz Game C++ CODE.pptxGeneral Knowledge Quiz Game C++ CODE.pptx
General Knowledge Quiz Game C++ CODE.pptx
 

One Museum Park West (Post-Tensioning case study)

  • 1. PTI JOURNAL August 2013 • V. 9 • No. 1 JOURNAL OF THE POST-TENSIONING INSTITUTE Effective Use of Post-Tensioning in Buildings 15 Corner Post-Tensioned Slab- Column Connections 49 PT Design Alternative Yields Benefits
  • 2. PTI JOURNAL | August 2013 49 CASE STUDIES One Museum Park West: Converting a High-Rise Tower’s Structural Design to Unbonded Post-Tensioning By Rattan L. Khosa One Museum Park West is a prime example of the benefits of converting conventionally reinforced slabs into unbonded post-tensioned slabs. The 55-story high-rise condominium tower (Fig. 1) was originally designed with an 8 in. (203 mm) thick concrete flat plate using reinforcing bar. A multitude of very deep transfer girders on the sixth floor were also designed without post-tensioning (PT). Because the project was over budget, the concrete and forming contractor requested that the PT supplier conduct a Value Engineering Analysis (VEA) to reduce the cost of the structure, though there were some concerns by a few members of the construction team about using PT in a floor system with a complex, irregular shape (Fig. 2). Two value-engineered options were presented to the construction team: 1. Option A: (a) Retain all the interior columns. (b)Use a 6 in. (152 mm) thick flat plate slab with PT. (c) Use PT in the transfer girders. 2. Option B: (a) Retain the 8 in. (203 mm) slab thickness but with an unbonded PT system. (b) Delete some transfer girders. (c) Delete some interior columns. (d) Use PT in the transfer girders. (e) Reduce the depth of the transfer girders. In Option A, the transfer girder depths would decrease due to the reduction in dead load resulting from the use of thinner slabs. The main disadvantage in this option was that a 7.5 in. (191 mm) slab would still be required for plumbing in the bathrooms per code requirements of the city of Chicago. Accordingly, this would have increased the forming costs. Ultimately, the Owner chose Option B, based on the enhanced value (described in the following) and the reduction in the overall cost. Even though it used more concrete and had a taller building height than Option A, Option B had less concrete and building height than the original design. Initially, the decision was to use PT in all floors; but in the end, PT was only used in the sixth floor (transfer floor) to roof level due to the construction schedule of the first five floors. To meet the construction schedule deadlines, a consulting structural engineering company was hired to design the structural floor system in partnership with the PT supplier. Together, they ensured that the quantities of the PT and reinforcing bar materials were in compliance with the initial VEA. This alternate structural design was incorporated into the Structural Engineer of Record’s design documents. The 8 in. (203 mm) thick flat plate floor had banded tendons in the east-west direction and the uniform Fig. 1—One Museum Park West, Chicago, IL.
  • 3. 50 August 2013 | PTI JOURNAL CASE STUDIES tendons in the north-south direction (Fig. 3). Approxi- mately one-third of the columns were eliminated on all levels above Level  6. Stud rails were introduced in four columns to deal with punching shear. The post-tensioned transfer girder depths varied from 6 ft 6 in. (2.0 m) to 8 ft (2.4 m), which was a 25% reduction in depth compared to the conventionally reinforced transfer girders. The transfer girders had between 46 and 142 PT tendons. To balance the dead load, the transfer girder tendons were stressed in five stages at the completion of the sixth, 18th, 30th, 42nd, and 53rd floors. Thestructuraldesignwasbasedon5000psi(34.5 MPa) concrete. However, the concrete contractor decided to provide8750psi(60.3MPa)concrete.Althoughthehigher strength concrete cost more, it allowed for stressing the tendons the day after concrete was poured. This resulted in a short 3-day cycle per a typical floor and reduced the construction schedule by several weeks. At some locations, the tendon lengths were very short due to building plan geometry. Initially, 10% more tendons were added to compensate for potential seating losses and meet the required effective forces. These “stand-by” tendons would be stressed only when there were under-elongations. Since this “insurance” would cost an additional $75,000, the owner deleted them and asked for a plan to prevent elongation problems. The PT supplier developed procedures for the PT installer to keep the anchor cavity, the jack grippers, and the stressing tails extremely clean. Furthermore, at the recommendation of the PT supplier, the Structural Engineer of Record allowed for 5% overstress when there were under-elongations in the short-length tendons. Consequently, the actual field elongations were exceptionally satisfactory. Because many interior columns were deleted, more space was opened up for residential use to the delight of the Architect. This revision helped in the marketing of the column-free condominiums to the delight of the Owner. The quantity of PT in the building increased from 35,000 ft (10,688 m) in a few cantilevered balconies (orig- inal design) to 1.6 million ft (487,680 m) in 49 floors (final design). The concrete contractor indicated that the value engineering resulted in a savings of $4 million due to the items listed as follows: • Reduction in the number of columns, which reduced the concrete, reinforcing bar, and forming costs. • Deletion of several transfer girders. • Reduction of the depth of remaining transfer girders. • Reduction of the reinforcing bar in slabs. • Reduction of the number of caissons, though the size of the remaining caissons did increase. • Reduction of building height due to the reduc- tion of transfer girder depths. As a result, there were cost savings in the shear walls, curtain walls, elevator, and vertical mechanical/electrical/ plumbing and piping/conduit. Credits Project: One Museum Park West, Chicago, IL Owner: Enterprise Companies Fig. 2—Irregular floor plan. ConcreteandFormingContractor: Adjustable Forms, Inc. Consulting Structural Engineering Company: Larson Engineering PT Supplier: AMSYSCO, Inc. PTI Fellow Rattan L. Khosa is President/Owner of AMSYSCO, Inc., a post-tensioning system supplier in Romeoville, IL. Khosa earned his MS degree in structural engineering from the University of Maryland, College Park, MD, and his MBA from the University of Chicago, Chicago, IL. He is a member of the PTI Board of Direc- tors, Chair of PTI Committee DC-70, Special Topics, and member of PTI Committee M10, Unbonded Tendon. He is also a Past President of PTI. He is a licensed professional engineer in multiple states with over 40 years of experience in design and construction of post-tensioned structures.
  • 4. PTI JOURNAL | August 2013 51 CASE STUDIES Fig.3—Representativetendonplacementplan.