SlideShare una empresa de Scribd logo
1 de 33
Project Planning, Scheduling
and Resource allocation
Presented to:
Dr. Shakeel Iqbal

Presented by:
Jatin Mandhyan (06)
Kajal Kuki Patwari (07)
Krishna Mishra (08)
PM Process Summary
Define Project

State need, problem or opportunity
Define project objectives
Identify success criteria
List assumptions, risks and
obstacles
Define project scope and work
breakdown structure








We are here

Monitor & Control
Progress





Feedback




Establish progress reporting system
Set up change control process
Define problem escalation process
Monitor progress vs. plan
Revise project plan

Develop Detailed Plan






Identify project activities
Estimate activity duration
Determine resource requirements
Construct / analyze project network
Prepare project schedule

Close Out Project





Launch Plan






Recruit and organize project team
Establish team operating rules
Level project resources
Assign work




Obtain client acceptance
Install project deliverables
Complete project documentation
Complete post-implementation audit
Issue final project report

Adapted from Project Management, ©1987 Kepner-Tregoe, Inc.
and Effective Project Management by R.K. Wysocki, R. Beck Jr.
& D.B. Crane (Wiley, 1995)
2
3
4
“Failing to plan is planning to fail”
Planning:
 “what” is going to be done, “how”, “where”, by
“whom”, and “when”
 for effective monitoring and control of complex
projects

5
“Its about time”
Scheduling:
 “what” will be done, and “who” will be working
 relative timing of tasks & time frames
 a concise description of the plan

6
Three Basic Steps to a Project Schedule

7
Scheduling Techniques
Gantt or bar charts
Milestone charts
Line of balance
Networks
Program Evaluation and Review Technique (PERT)
Arrow Diagram Method (ADM) [Sometimes called the
Critical Path Method (CPM)]
Graphical Evaluation and Review Technique (GERT)
Precedence Diagram Method (PDM)

8
Types of Schedules
Gantt or Simple Bar Chart
• Graphical
representation
shows horizontal
bars against a
time scale
• At summary or
detailed levels

http://www.maxwideman.com/issacons/index.htm

9
Milestone Chart
• Graphical
representation
shows milestone
dates
• Identifies key
points in the
project's life span
• The bars are not
necessarily visible

http://www.maxwideman.com/issacons/index.htm

10
Progress Bar Chart
• Graphical
representation
shows progress
relative to plan
• In this case, behind
schedule
• No indication of
final completion

http://www.maxwideman.com/issacons/index.htm

11
Bar Chart Status Report
• Graphical
representation shows
original baseline
schedule (red bars)
and actual progress
relative to current
plan
• No indication of final
completion

http://www.maxwideman.com/issacons/index.htm

12
The Work Break Down Structure (WBS)
An organizational tool for complex projects
 A first step in creating a schedule
 Useful for defining the Scope of Work
 After decided how to do the work

Consists of:
 Goal statement for project
 Subdividing goal into smaller & smaller portions

13
Example WBS
W a re h o u s e W B S
T o c o n s t r u c t a 5 - u n it
w a r e h o u s e f o r lig h t in d u s t r y
C o m p le x

S it e P r e p a r a t io n

S urve y

S it e B o u n d a r ie s

E le v a t io n
D a t a P o in t s

S o ils A n a ly s is

B u ild in g
F o o t p r in t s

F o u n d a t io n

E x c a v a t e S o il

S tru c tu ra l

S y s te m s

F in is h in g

B a c k f ill & C o m p a c t

L o c a te
B u r ie d S e r v ic e s

Could be used to define scope of
work for surveyor sub-contract
14
15
Background
 Allahabad, about 600 km southeast of Delhi in Uttar
Pradesh (UP) State, is a major industrial city along National
Highway 2.
 The city is divided into the four districts of Allahabad, Naini,
Jhusi and Phaphamau.
 The adjacent Naini District across the River Yamuna is the
industrial center where communication, automobile,
fertilizer, textile and related industry companies are located.
The only traffic route connecting these two districts was the
existing bridge over the River Yamuna (Yamuna Bridge).
17
 The existing bridge (Yamuna Bridge) is a combined
highway-railway bridge constructed at the end of the 19th
century, and its narrow two lanes were straining to cope
with the increasing size and weight of the vehicles.
 Out of concern over the safety of the decaying bridge,
construction of a new substitute bridge was urgently
needed.

18
Objective
 Construct a four-lane bridge
 Replace the existing old two-lane bridge
 Alleviating chronic traffic congestion

19
Borrower/Executing Agency
 Borrower: The President of India
 Executing Agency: The Ministry of Surface
Transport (current Ministry of Shipping, Road
Transport and Highways)

20
Outline of Loan Agreement
Loan Amount / Loan Disbursed
Amount

10,037 million yen / 7,515 million yen

Exchange of Notes / Loan Agreement

December 1993 / January 1994

Terms and Conditions
-Interest Rate
-Repayment Period (Grace Period)
-Procurement

2.6%
30 years (10 years)
General untied

Final Disbursement Date

March 2005

Main Contractors

J/V of Hyundai Engineering Co. Ltd.
(Korea) and Hindustan Construction Co.
Ltd. (India)

Total Bridge Length:

1640 m

Width of superstructure

26 m

Main spans:

185 m – 260 m – 185 m
21
22
Output
The main scope of this
project include the
construction of a four-lane
cable-stayed bridge (Naini
Bridge; length, 1,640 m)
and approach roads (total
length: 3,806 m) was
implemented almost entirely
as planned.

23
In addition, based on recommendations suggested
in JBIC’s study the project scope was expanded
to include installation of toll booths and
monitoring equipment such as the weigh-in
motion system and the wind and structural health
monitoring system (WASHMS).

24
Project period
The project period was scheduled from January 1994 to July
2004 (ten years and seven months), which is four years and
four months longer than the planned period from January
1994 to March 2000 (six years three months) or 169% of the
planned period.
The main causes of delay:
(1)the delay in consultant tendering procedure
(2) the time required for the review and finalization of the
design of the first large-scale cable-stayed bridge in India.
(3)the delay in the tendering of contractors due to problems in
the course of the tendering procedure
(4)the change of the executing agency from the Ministry of
Surface Transport in 1997 in the midst of project
implementation
25
Project Cost
The project cost was 8,807 million yen 3,097 million
yen less than the planned 11,904 million yen or
74% of the planned project cost. In terms of
rupee, the actual cost was 3,145 million rupees
which is almost equal to the planned 3,217
rupees.
This difference is a resulted of the difference in the
rupee-yen exchange rate at time of planning and
ex-post evaluation.
26
Involvement of Maurer Söhne
Maurer Soehne manufactured 4 Swivel Joist
Expansion Joints with a length of 24,40 m each.
This cross-sectional width of the superstructure
considers 4 highway traffic lanes and two lateral
3m - tracks for “other” traffic and pedestrians.
Due to transport reasons, the joints were delivered
in two pieces to be connected on job site. The
joints can accommodate movements of 400 mm
(at both abutments) and 360 mm and 600 mm
respectively at the pylons.

27
Operation and maintenance status
On the Naini Bridge, weather observation devices,
which check conditions and measure the weight
and gradient of pylons, are set at seven positions
and are monitored 24 hours from the observation
equipment control room in the toll booth control
building.

28
Joint manufacture in the workshop

Joint installation

29
30
31
Effectiveness

Traffic volume

Time saving

Congestion length
decrease and time saving
32
bibliography
• Project planning, scheduling and control – James P. Lewis
• http://www.cowi.com/menu/service/BridgeTunnelandMarineStr
uctures/Bridges/Documents/BTM_Bridges_low.pdf
• http://www.cowi.dk/menu/service/Brotunnelogvandbygning/Do
cuments/021-1700-008e-07b_MajorBridges.pdf
• http://sine.ni.com/cs/app/doc/p/id/cs-12653
• http://en.wikipedia.org/wiki/File:New_Yamuna_Bridge_details.j
pg
• http://structurae.net/structures/data/index.cfm?id=s0011445

33

Más contenido relacionado

La actualidad más candente

Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)FahadHasan36
 
MODULE-III INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-III INFRASTRUCTURE ENGINEERING BTCVC702MODULE-III INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-III INFRASTRUCTURE ENGINEERING BTCVC702Dr. BASWESHWAR JIRWANKAR
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)Sandip Kumar Verma
 
“Construction Risk Management”
“Construction Risk Management”“Construction Risk Management”
“Construction Risk Management”Ary Jamil
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimatinghatim ahmed
 
Project management
Project managementProject management
Project managementTom Thand
 
human resource management for construction projects
 human resource management for construction projects human resource management for construction projects
human resource management for construction projectsSelf-employed
 
Lecture 8 monitoring & controlling (1)
Lecture 8  monitoring & controlling (1)Lecture 8  monitoring & controlling (1)
Lecture 8 monitoring & controlling (1)Nur Azwin
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Managementsrinivas2036
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project WorkshopEder Alves
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & managementManit Agarwal
 
Flyover Bridge construction project
Flyover Bridge construction projectFlyover Bridge construction project
Flyover Bridge construction projectAxay Sharma
 

La actualidad más candente (20)

Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)
 
MODULE-III INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-III INFRASTRUCTURE ENGINEERING BTCVC702MODULE-III INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-III INFRASTRUCTURE ENGINEERING BTCVC702
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)
 
Project Management
Project ManagementProject Management
Project Management
 
“Construction Risk Management”
“Construction Risk Management”“Construction Risk Management”
“Construction Risk Management”
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Project management
Project managementProject management
Project management
 
human resource management for construction projects
 human resource management for construction projects human resource management for construction projects
human resource management for construction projects
 
Lecture 8 monitoring & controlling (1)
Lecture 8  monitoring & controlling (1)Lecture 8  monitoring & controlling (1)
Lecture 8 monitoring & controlling (1)
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
Flyover Bridge construction project
Flyover Bridge construction projectFlyover Bridge construction project
Flyover Bridge construction project
 
Project Charter Guide
Project Charter GuideProject Charter Guide
Project Charter Guide
 
Construction project manager
Construction project managerConstruction project manager
Construction project manager
 

Destacado

Resource Scheduling
Resource SchedulingResource Scheduling
Resource SchedulingNicola2903
 
How To Build A PMO
How To Build A PMOHow To Build A PMO
How To Build A PMOTURKI , PMP
 
Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsMaria Erland, PMP
 
PMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_ManagementPMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_ManagementBob Zoller
 
Project Resource Management 3 Jon Lewis
Project Resource Management 3 Jon LewisProject Resource Management 3 Jon Lewis
Project Resource Management 3 Jon LewisBPUG Congress
 
Resource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingResource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingMashilo Kabedi
 
Resource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tipsResource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tipsian jones
 
Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Hussain Bandukwala
 
Strategy and Resource Allocation
Strategy and Resource Allocation Strategy and Resource Allocation
Strategy and Resource Allocation Riadh Mohammed Arif
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)Anand Subramaniam
 
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017Carol Smith
 

Destacado (15)

Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
How To Build A PMO
How To Build A PMOHow To Build A PMO
How To Build A PMO
 
Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And Benefits
 
PMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_ManagementPMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_Management
 
Project Resource Management 3 Jon Lewis
Project Resource Management 3 Jon LewisProject Resource Management 3 Jon Lewis
Project Resource Management 3 Jon Lewis
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
Resource management
Resource managementResource management
Resource management
 
PMO Frameworks
PMO FrameworksPMO Frameworks
PMO Frameworks
 
Resource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingResource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder Meeting
 
Resource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tipsResource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tips
 
Resource allocation
Resource allocationResource allocation
Resource allocation
 
Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)
 
Strategy and Resource Allocation
Strategy and Resource Allocation Strategy and Resource Allocation
Strategy and Resource Allocation
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
 
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
 

Similar a Planning, scheduling and resource allocation

3 planning and scheduling
3 planning and scheduling3 planning and scheduling
3 planning and schedulingDr.R. SELVAM
 
PPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaPPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaNarendra Vasudeva
 
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...IRJET Journal
 
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PROPLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PROIRJET Journal
 
06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultransConsultrans, S.A.
 
2010 10 14_bay_bridge_report_v5_d
2010 10 14_bay_bridge_report_v5_d2010 10 14_bay_bridge_report_v5_d
2010 10 14_bay_bridge_report_v5_dE'ville Eye
 
Tilos for linear project
Tilos for linear projectTilos for linear project
Tilos for linear projectThanh Hoang Lam
 
Training report on railway structure at tata aldesa
Training report on railway structure at tata aldesaTraining report on railway structure at tata aldesa
Training report on railway structure at tata aldesaUtsav Tripathy
 
Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...JumpingJaq
 
Expansion of state highway 1
Expansion of state highway 1Expansion of state highway 1
Expansion of state highway 1Sneha Kaira
 
PM Project group 4.pptx
PM Project group 4.pptxPM Project group 4.pptx
PM Project group 4.pptxKumarAnand99
 
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...IRJET Journal
 
Feasibility study on expansion of state highway
Feasibility study on expansion of state highwayFeasibility study on expansion of state highway
Feasibility study on expansion of state highwaysnehakaira
 

Similar a Planning, scheduling and resource allocation (20)

3 planning and scheduling
3 planning and scheduling3 planning and scheduling
3 planning and scheduling
 
PPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaPPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudeva
 
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
 
ToR
ToRToR
ToR
 
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PROPLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
 
06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans
 
2010 10 14_bay_bridge_report_v5_d
2010 10 14_bay_bridge_report_v5_d2010 10 14_bay_bridge_report_v5_d
2010 10 14_bay_bridge_report_v5_d
 
MERAJ UL HUDA CV
MERAJ UL HUDA CVMERAJ UL HUDA CV
MERAJ UL HUDA CV
 
Tilos for linear project
Tilos for linear projectTilos for linear project
Tilos for linear project
 
Training report on railway structure at tata aldesa
Training report on railway structure at tata aldesaTraining report on railway structure at tata aldesa
Training report on railway structure at tata aldesa
 
Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...
 
Expansion of state highway 1
Expansion of state highway 1Expansion of state highway 1
Expansion of state highway 1
 
cv Updated M.Anwar
cv Updated M.Anwarcv Updated M.Anwar
cv Updated M.Anwar
 
PM Project group 4.pptx
PM Project group 4.pptxPM Project group 4.pptx
PM Project group 4.pptx
 
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
 
Feasibility study on expansion of state highway
Feasibility study on expansion of state highwayFeasibility study on expansion of state highway
Feasibility study on expansion of state highway
 
20320130406022 2
20320130406022 220320130406022 2
20320130406022 2
 
20320130406022 2
20320130406022 220320130406022 2
20320130406022 2
 
Experience Record
Experience RecordExperience Record
Experience Record
 
RDP Chapter 19
RDP Chapter 19RDP Chapter 19
RDP Chapter 19
 

Último

办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一
办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一
办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一Fi L
 
Design and Managing Service in the field of tourism and hospitality industry
Design and Managing Service in the field of tourism and hospitality industryDesign and Managing Service in the field of tourism and hospitality industry
Design and Managing Service in the field of tourism and hospitality industryrioverosanniejoy
 
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一diploma 1
 
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一D SSS
 
西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造kbdhl05e
 
Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full NightCall Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...
Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...
Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...Yantram Animation Studio Corporation
 
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...katerynaivanenko1
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case StudySophia Viganò
 
group_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfgroup_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfneelspinoy
 
Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...
Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...
Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...mrchrns005
 
定制(CQU文凭证书)中央昆士兰大学毕业证成绩单原版一比一
定制(CQU文凭证书)中央昆士兰大学毕业证成绩单原版一比一定制(CQU文凭证书)中央昆士兰大学毕业证成绩单原版一比一
定制(CQU文凭证书)中央昆士兰大学毕业证成绩单原版一比一Fi ss
 
306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social MediaD SSS
 
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改yuu sss
 
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
PORTAFOLIO   2024_  ANASTASIYA  KUDINOVAPORTAFOLIO   2024_  ANASTASIYA  KUDINOVA
PORTAFOLIO 2024_ ANASTASIYA KUDINOVAAnastasiya Kudinova
 
shot list for my tv series two steps back
shot list for my tv series two steps backshot list for my tv series two steps back
shot list for my tv series two steps back17lcow074
 
Design principles on typography in design
Design principles on typography in designDesign principles on typography in design
Design principles on typography in designnooreen17
 
韩国SKKU学位证,成均馆大学毕业证书1:1制作
韩国SKKU学位证,成均馆大学毕业证书1:1制作韩国SKKU学位证,成均馆大学毕业证书1:1制作
韩国SKKU学位证,成均馆大学毕业证书1:1制作7tz4rjpd
 
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degreeyuu sss
 

Último (20)

Call Girls in Pratap Nagar, 9953056974 Escort Service
Call Girls in Pratap Nagar,  9953056974 Escort ServiceCall Girls in Pratap Nagar,  9953056974 Escort Service
Call Girls in Pratap Nagar, 9953056974 Escort Service
 
办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一
办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一
办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一
 
Design and Managing Service in the field of tourism and hospitality industry
Design and Managing Service in the field of tourism and hospitality industryDesign and Managing Service in the field of tourism and hospitality industry
Design and Managing Service in the field of tourism and hospitality industry
 
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
 
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
 
西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造
 
Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full NightCall Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
 
Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...
Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...
Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...
 
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case Study
 
group_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfgroup_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdf
 
Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...
Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...
Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...
 
定制(CQU文凭证书)中央昆士兰大学毕业证成绩单原版一比一
定制(CQU文凭证书)中央昆士兰大学毕业证成绩单原版一比一定制(CQU文凭证书)中央昆士兰大学毕业证成绩单原版一比一
定制(CQU文凭证书)中央昆士兰大学毕业证成绩单原版一比一
 
306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media
 
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
 
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
PORTAFOLIO   2024_  ANASTASIYA  KUDINOVAPORTAFOLIO   2024_  ANASTASIYA  KUDINOVA
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
 
shot list for my tv series two steps back
shot list for my tv series two steps backshot list for my tv series two steps back
shot list for my tv series two steps back
 
Design principles on typography in design
Design principles on typography in designDesign principles on typography in design
Design principles on typography in design
 
韩国SKKU学位证,成均馆大学毕业证书1:1制作
韩国SKKU学位证,成均馆大学毕业证书1:1制作韩国SKKU学位证,成均馆大学毕业证书1:1制作
韩国SKKU学位证,成均馆大学毕业证书1:1制作
 
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
 

Planning, scheduling and resource allocation

  • 1. Project Planning, Scheduling and Resource allocation Presented to: Dr. Shakeel Iqbal Presented by: Jatin Mandhyan (06) Kajal Kuki Patwari (07) Krishna Mishra (08)
  • 2. PM Process Summary Define Project State need, problem or opportunity Define project objectives Identify success criteria List assumptions, risks and obstacles Define project scope and work breakdown structure      We are here Monitor & Control Progress    Feedback   Establish progress reporting system Set up change control process Define problem escalation process Monitor progress vs. plan Revise project plan Develop Detailed Plan      Identify project activities Estimate activity duration Determine resource requirements Construct / analyze project network Prepare project schedule Close Out Project    Launch Plan     Recruit and organize project team Establish team operating rules Level project resources Assign work   Obtain client acceptance Install project deliverables Complete project documentation Complete post-implementation audit Issue final project report Adapted from Project Management, ©1987 Kepner-Tregoe, Inc. and Effective Project Management by R.K. Wysocki, R. Beck Jr. & D.B. Crane (Wiley, 1995) 2
  • 3. 3
  • 4. 4
  • 5. “Failing to plan is planning to fail” Planning:  “what” is going to be done, “how”, “where”, by “whom”, and “when”  for effective monitoring and control of complex projects 5
  • 6. “Its about time” Scheduling:  “what” will be done, and “who” will be working  relative timing of tasks & time frames  a concise description of the plan 6
  • 7. Three Basic Steps to a Project Schedule 7
  • 8. Scheduling Techniques Gantt or bar charts Milestone charts Line of balance Networks Program Evaluation and Review Technique (PERT) Arrow Diagram Method (ADM) [Sometimes called the Critical Path Method (CPM)] Graphical Evaluation and Review Technique (GERT) Precedence Diagram Method (PDM) 8
  • 9. Types of Schedules Gantt or Simple Bar Chart • Graphical representation shows horizontal bars against a time scale • At summary or detailed levels http://www.maxwideman.com/issacons/index.htm 9
  • 10. Milestone Chart • Graphical representation shows milestone dates • Identifies key points in the project's life span • The bars are not necessarily visible http://www.maxwideman.com/issacons/index.htm 10
  • 11. Progress Bar Chart • Graphical representation shows progress relative to plan • In this case, behind schedule • No indication of final completion http://www.maxwideman.com/issacons/index.htm 11
  • 12. Bar Chart Status Report • Graphical representation shows original baseline schedule (red bars) and actual progress relative to current plan • No indication of final completion http://www.maxwideman.com/issacons/index.htm 12
  • 13. The Work Break Down Structure (WBS) An organizational tool for complex projects  A first step in creating a schedule  Useful for defining the Scope of Work  After decided how to do the work Consists of:  Goal statement for project  Subdividing goal into smaller & smaller portions 13
  • 14. Example WBS W a re h o u s e W B S T o c o n s t r u c t a 5 - u n it w a r e h o u s e f o r lig h t in d u s t r y C o m p le x S it e P r e p a r a t io n S urve y S it e B o u n d a r ie s E le v a t io n D a t a P o in t s S o ils A n a ly s is B u ild in g F o o t p r in t s F o u n d a t io n E x c a v a t e S o il S tru c tu ra l S y s te m s F in is h in g B a c k f ill & C o m p a c t L o c a te B u r ie d S e r v ic e s Could be used to define scope of work for surveyor sub-contract 14
  • 15. 15
  • 16.
  • 17. Background  Allahabad, about 600 km southeast of Delhi in Uttar Pradesh (UP) State, is a major industrial city along National Highway 2.  The city is divided into the four districts of Allahabad, Naini, Jhusi and Phaphamau.  The adjacent Naini District across the River Yamuna is the industrial center where communication, automobile, fertilizer, textile and related industry companies are located. The only traffic route connecting these two districts was the existing bridge over the River Yamuna (Yamuna Bridge). 17
  • 18.  The existing bridge (Yamuna Bridge) is a combined highway-railway bridge constructed at the end of the 19th century, and its narrow two lanes were straining to cope with the increasing size and weight of the vehicles.  Out of concern over the safety of the decaying bridge, construction of a new substitute bridge was urgently needed. 18
  • 19. Objective  Construct a four-lane bridge  Replace the existing old two-lane bridge  Alleviating chronic traffic congestion 19
  • 20. Borrower/Executing Agency  Borrower: The President of India  Executing Agency: The Ministry of Surface Transport (current Ministry of Shipping, Road Transport and Highways) 20
  • 21. Outline of Loan Agreement Loan Amount / Loan Disbursed Amount 10,037 million yen / 7,515 million yen Exchange of Notes / Loan Agreement December 1993 / January 1994 Terms and Conditions -Interest Rate -Repayment Period (Grace Period) -Procurement 2.6% 30 years (10 years) General untied Final Disbursement Date March 2005 Main Contractors J/V of Hyundai Engineering Co. Ltd. (Korea) and Hindustan Construction Co. Ltd. (India) Total Bridge Length: 1640 m Width of superstructure 26 m Main spans: 185 m – 260 m – 185 m 21
  • 22. 22
  • 23. Output The main scope of this project include the construction of a four-lane cable-stayed bridge (Naini Bridge; length, 1,640 m) and approach roads (total length: 3,806 m) was implemented almost entirely as planned. 23
  • 24. In addition, based on recommendations suggested in JBIC’s study the project scope was expanded to include installation of toll booths and monitoring equipment such as the weigh-in motion system and the wind and structural health monitoring system (WASHMS). 24
  • 25. Project period The project period was scheduled from January 1994 to July 2004 (ten years and seven months), which is four years and four months longer than the planned period from January 1994 to March 2000 (six years three months) or 169% of the planned period. The main causes of delay: (1)the delay in consultant tendering procedure (2) the time required for the review and finalization of the design of the first large-scale cable-stayed bridge in India. (3)the delay in the tendering of contractors due to problems in the course of the tendering procedure (4)the change of the executing agency from the Ministry of Surface Transport in 1997 in the midst of project implementation 25
  • 26. Project Cost The project cost was 8,807 million yen 3,097 million yen less than the planned 11,904 million yen or 74% of the planned project cost. In terms of rupee, the actual cost was 3,145 million rupees which is almost equal to the planned 3,217 rupees. This difference is a resulted of the difference in the rupee-yen exchange rate at time of planning and ex-post evaluation. 26
  • 27. Involvement of Maurer Söhne Maurer Soehne manufactured 4 Swivel Joist Expansion Joints with a length of 24,40 m each. This cross-sectional width of the superstructure considers 4 highway traffic lanes and two lateral 3m - tracks for “other” traffic and pedestrians. Due to transport reasons, the joints were delivered in two pieces to be connected on job site. The joints can accommodate movements of 400 mm (at both abutments) and 360 mm and 600 mm respectively at the pylons. 27
  • 28. Operation and maintenance status On the Naini Bridge, weather observation devices, which check conditions and measure the weight and gradient of pylons, are set at seven positions and are monitored 24 hours from the observation equipment control room in the toll booth control building. 28
  • 29. Joint manufacture in the workshop Joint installation 29
  • 30. 30
  • 31. 31
  • 32. Effectiveness Traffic volume Time saving Congestion length decrease and time saving 32
  • 33. bibliography • Project planning, scheduling and control – James P. Lewis • http://www.cowi.com/menu/service/BridgeTunnelandMarineStr uctures/Bridges/Documents/BTM_Bridges_low.pdf • http://www.cowi.dk/menu/service/Brotunnelogvandbygning/Do cuments/021-1700-008e-07b_MajorBridges.pdf • http://sine.ni.com/cs/app/doc/p/id/cs-12653 • http://en.wikipedia.org/wiki/File:New_Yamuna_Bridge_details.j pg • http://structurae.net/structures/data/index.cfm?id=s0011445 33