London 2012 Olympics
Managing and controlling contingency
18th
April 2013
What we wanted to achieve
• Control of change – limit the
amount of change that affected
the programme and no surprises
• Greater understanding and clarity
– make decisions based on the
best data possible
• Promotion of activity – actively
look at what could be done to
limit change
• Release of contingency – the
great prize is not to spend
Risk management overview
•Ensure sufficient contingency
available to complete the job
•Limit the amount of free funds at
project level – Milton Friedman?
•Strictly control the use of
contingency
•Low levels of delegation but
processes for emergencies
•Re-calculate requirement regularly
and measure performance
•Clear guidance on the expectation
for the return of contingency
•Make it a programme objective to
review contingency levels
Principles
The three lines of defence
• Detailed project level identification
and management of individual
risks
• ODA Programme Assurance –
oversight of the process and
compliance with it and the quality
check of the data
• ODA Risk and Audit – Setting of
policy, audit of outputs and
process and reporting to the Audit
Committee
The three lines of defence model
Control of contingency
Contingency is controlled through a series of regular governance meetings
• Funders – Held by the Government funding
departments
•QRA calculated quarterly & contingency adjusted
•Available quarterly by application to the Funders
• Programme - Held by the ODA
•QRA calculated quarterly & contingency adjusted
•Accessible with approval to Funders
• Project – held within the project budgets
•QRA calculated quarterly but trended each month
•Available with approval of change board, also
delegation
• Risk management is part of the change control process
• Governance rules that required authorisation for all changes
• Senior management reviews at various stages of the change lifecycle
• Risks migrate through the process until they become certain and are
requests for change with budget authority or milestone change
Risk management context
• Two parts
1. Assessment
1. Identification
2. Analysis
3. Evaluation
2. Treatment – Formulation of mitigation
plans and actions
• Repeat regularly based on need
Risk management activities
• Hold risks centrally and monitor through assurance
• Ensure risk are recorded consistently with clear accountability
• Report key risks and overall risk status at project and programme level
• Escalate key decisions to higher authority levels for resolution
• Monitor risk management process for compliance and report
• Periodic review process for improvement
• Risk management must be part of the project or progress process
• Risk management carried out within the project or function
• Assured by the central team for review, update and compliance
• Risks reported by the project team as part of the process
• Consolidation of programme risks by the central team
Risk management implementation and assurance
Risk management integrated with core programme
• Risk management integrated with core programme activities
• Reported as part of monthly cycle for implementation reviews etc.
• Part of commercial reporting
• QRA was used to calculate the contingency required for the budgets as part of
the Baseline Report published in November 2007 – Yellow Book
• QRA was part of the ongoing calculation of Anticipated Final Cost - the basis
for programme performance
• QRA was also used to calculate programme risk contingency
• Schedule QRA was used to determine schedule risk on the complex projects
and against interfaces
Quantification of risk - QRA
Review of risks
• Risks, trends and issues reviewed
monthly with the project team and at
implementation reviews with
Programme Executive
• Key programme risks reviewed
monthly with SROs
• Programme risks reviewed by ODA
assurance group monthly
• Programme QRA and key programme
risks review at the Funders Quarterly
Risk Working Group
• Key programme risks reviewed by the
Audit Committee of the ODA Board
Reporting of risks
• Project risks, trends and issues reported
as part of Project Status Report
• Project QRA results included in calculation
of AFC (Anticipated Final Cost) and
reported on Project Cost Report
• Key programme risks reported as part of
the Monthly Progress Report
• Programme QRA reported to the
Government Olympic Executive and
Funders as part of the Quarterly Report
• Key risks reported to the Audit Committee
of the ODA Board
• Programme risk assurance report to
monitor performance of and compliance
with risk process
Contingency reporting
• Dashboard showed the current status of contingency each period
• Contingency remaining, forecast requirement and variances
• Changes from last period, key risks
• Headroom and potential savings identified for re-cycling
Key messages for success
• Ensure sufficient contingency is
available
• Limit the amount of free funds
available – un-let scope?
• Ensure strict controls to manage
contingency are in place
• Assure the process, have regular
audits for compliance and report at
the highest level
• Have clear open reporting that
shows how the values have been
derived
• Have lots of opportunity for
executive investigation, challenge
and engagement
• Use contingency as a performance
measure – cost to go, drawdown,
profiling
Benefits of the approach
• Sufficient resources are available to
complete the project to its timescale –
time is always the quiet victim
• Scope creep is minimised as contingency
is only used for those things that
• It is clear how much contingency has
been used and how much is required to
complete
• Un-needed funds can be re-cycled for
further investment
• Performance is easier to monitor as it is
not clouded by the inappropriate use of
hidden funds
• It doesn’t matter how much contingency
you start out with but how much you
spend along the way.
•Developer deals intended to
fund the IBC/MPC and
Athletes Village
•Deal might be difficult to
finalise
•Private funding would come
with additional requirements
that might not be acceptable
In the event the credit crunch
made the deals unattractive
and they collapsed
•What happened?
•Re-design to reduce cost
•Funded from contingency
and savings
Risk: Credit Crunch and funding of IBC/MPC and Village
•High number of interfaces and
complexity
•New bridges, roads, sewers,
utilities connecting to Venues
•Venues and infrastructure are in
areas of changing topography
What did we do?
•Try to minimise the interfaces
•Understand and manage the
interfaces
•Procure in larger packages and
transfer the integration risk to the
supply chain
Risk: Programme interfaces and integration
•Currently about 6,500 employees on the park and a
further 5,000 on the Village
•3 major unions represented
•The Olympic Programme is high profile and is a
target increasing as the games approached
•Some demonstrations but no real industrial
disputes to date
Key risk: Industrial relations
What do we do?
•Agreed with the unions key principles of employment including:
•All labour directly employed and local where possible
•Pay to Working Rule Agreement rates
•Union representation on site
•High standard of welfare, training and employee facilities
•Active and regular discussion with all the key unions
•Enforcement of agreements
Risk: Security, considerations, changes and authority
•Security is key during games and
construction
•Security includes perimeter guarding,
CCTV, Fencing etc.
•Changes in security scope are always
liable and to some extent unknowable
•Change in threat can mean a scope
change such as:
•Building resilience
•Hostile Vehicle Mitigation
Mitigation
•Close relationship with the security community and identification of possible
measures required
•Developed scope to be flexible and signed of by security stakeholders
•Transferred cost of risk to Funders
•Village comprises approximately
16,000 bed spaces during Games
•And 2,500 flats in Legacy
•11 Plots of which 5 were CM and 6
tier 1
•Large number of flats in one go in
the UK to a strict deadline
•Supply chain risks for component
manufacture and deliverysuch as:
•Bathroom pods
•Cladding panels
What we did
•Negotiated with constructors to
accelerate and buy off delay and
disruption claims
Delay to completion of the Athletes Village
Risk: Health and Safety
•Up to 10,000 workers on site during peak
•Complex, constrained site involving:
•Working at height
•Hot working
•Heavy machinery
•Tunnelling and underground works
•Temporary works
•Demolition
•Railway working
What we did
•High focus on safety culture with ‘Safe Start’ and toolbox talks etc…
•Made senior managers responsible for safety performance
•Stopped work when safety was compromised
•World beating safety performance
•So far the only Olympics without a fatality
Questions?

Más contenido relacionado

La actualidad más candente

Strategic Analysis Report FINAL
Strategic Analysis Report FINALStrategic Analysis Report FINAL
Strategic Analysis Report FINAL
Rafael Martinez
 
A case study on ikea
A case study on ikeaA case study on ikea
A case study on ikea
philmayo
 
International Marketing Plan- Laneige
International Marketing Plan- LaneigeInternational Marketing Plan- Laneige
International Marketing Plan- Laneige
Lysette Guambo
 
Executive summary brand Management: Virgin
Executive summary brand Management: VirginExecutive summary brand Management: Virgin
Executive summary brand Management: Virgin
Subhi Pradhan
 

La actualidad más candente (20)

Strategic Analysis Report FINAL
Strategic Analysis Report FINALStrategic Analysis Report FINAL
Strategic Analysis Report FINAL
 
Risk Management for Airlines – Financial Risks
Risk Management for Airlines – Financial RisksRisk Management for Airlines – Financial Risks
Risk Management for Airlines – Financial Risks
 
Edita final project - mba - s3 - group f
Edita   final project - mba - s3 - group fEdita   final project - mba - s3 - group f
Edita final project - mba - s3 - group f
 
Carnival Cruise Lines
Carnival Cruise LinesCarnival Cruise Lines
Carnival Cruise Lines
 
Case Study on Mavi Jeans: Jeans That Fit
Case Study on Mavi Jeans: Jeans That FitCase Study on Mavi Jeans: Jeans That Fit
Case Study on Mavi Jeans: Jeans That Fit
 
Glossier Marketing Plan
Glossier Marketing PlanGlossier Marketing Plan
Glossier Marketing Plan
 
Restaurants Industry: Social Media Benchmarks & Impact Report
Restaurants Industry: Social Media Benchmarks & Impact ReportRestaurants Industry: Social Media Benchmarks & Impact Report
Restaurants Industry: Social Media Benchmarks & Impact Report
 
Mc Donald's Operations Strategy
Mc Donald's Operations StrategyMc Donald's Operations Strategy
Mc Donald's Operations Strategy
 
A case study on ikea
A case study on ikeaA case study on ikea
A case study on ikea
 
Creating Digital Strategies for International Markets
Creating Digital Strategies  for International MarketsCreating Digital Strategies  for International Markets
Creating Digital Strategies for International Markets
 
International Marketing Plan- Laneige
International Marketing Plan- LaneigeInternational Marketing Plan- Laneige
International Marketing Plan- Laneige
 
Airline Innovation Trends
Airline Innovation TrendsAirline Innovation Trends
Airline Innovation Trends
 
6th GHANA CEO SUMMIT BROCHURE.pdf
6th GHANA CEO SUMMIT BROCHURE.pdf6th GHANA CEO SUMMIT BROCHURE.pdf
6th GHANA CEO SUMMIT BROCHURE.pdf
 
Digital Transformation Toolkit - Overview and Approach
Digital Transformation Toolkit - Overview and ApproachDigital Transformation Toolkit - Overview and Approach
Digital Transformation Toolkit - Overview and Approach
 
Digital Platform Economy
Digital Platform EconomyDigital Platform Economy
Digital Platform Economy
 
Strategy Evaluation of Carnival corporation-plc
Strategy Evaluation of Carnival corporation-plc Strategy Evaluation of Carnival corporation-plc
Strategy Evaluation of Carnival corporation-plc
 
IKEA’s- Global Marketing Strategy
IKEA’s- Global Marketing StrategyIKEA’s- Global Marketing Strategy
IKEA’s- Global Marketing Strategy
 
Virgin Atlantic Brand Strategy
Virgin Atlantic Brand Strategy Virgin Atlantic Brand Strategy
Virgin Atlantic Brand Strategy
 
Executive summary brand Management: Virgin
Executive summary brand Management: VirginExecutive summary brand Management: Virgin
Executive summary brand Management: Virgin
 
Advertising and IMC Principles and Practice 11th Edition Moriarty Test Bank
Advertising and IMC Principles and Practice 11th Edition Moriarty Test BankAdvertising and IMC Principles and Practice 11th Edition Moriarty Test Bank
Advertising and IMC Principles and Practice 11th Edition Moriarty Test Bank
 

Destacado

Legal Management Process: A paradignm shift as a business enabler
Legal Management Process: A paradignm shift as a business enablerLegal Management Process: A paradignm shift as a business enabler
Legal Management Process: A paradignm shift as a business enabler
ambergupt78
 
Collaboration, sharing knowledge and improving delivery within local government
Collaboration, sharing knowledge and improving delivery within local governmentCollaboration, sharing knowledge and improving delivery within local government
Collaboration, sharing knowledge and improving delivery within local government
Association for Project Management
 

Destacado (20)

Contingency and management reserve
Contingency and management reserveContingency and management reserve
Contingency and management reserve
 
Risk contingency survey
Risk contingency surveyRisk contingency survey
Risk contingency survey
 
Fujitsu’s management of contingency
Fujitsu’s management of contingencyFujitsu’s management of contingency
Fujitsu’s management of contingency
 
Calculating contingency for management reserve
Calculating contingency for management reserveCalculating contingency for management reserve
Calculating contingency for management reserve
 
Risk contingency and management reserve
Risk contingency and management reserveRisk contingency and management reserve
Risk contingency and management reserve
 
The construction programme - assurance and controls
The construction programme - assurance and controlsThe construction programme - assurance and controls
The construction programme - assurance and controls
 
2012 financial plan for FFGA
2012 financial plan for FFGA2012 financial plan for FFGA
2012 financial plan for FFGA
 
President Barack Obama - Honolulu Authoirty for Rapid Transit (HART) - SOS - ...
President Barack Obama - Honolulu Authoirty for Rapid Transit (HART) - SOS - ...President Barack Obama - Honolulu Authoirty for Rapid Transit (HART) - SOS - ...
President Barack Obama - Honolulu Authoirty for Rapid Transit (HART) - SOS - ...
 
Contingency drawdown curve
Contingency drawdown curveContingency drawdown curve
Contingency drawdown curve
 
Legal Management Process: A paradignm shift as a business enabler
Legal Management Process: A paradignm shift as a business enablerLegal Management Process: A paradignm shift as a business enabler
Legal Management Process: A paradignm shift as a business enabler
 
A simple approach to contingency drawdown, presented by Ben Fry, 10th Oct 201...
A simple approach to contingency drawdown, presented by Ben Fry, 10th Oct 201...A simple approach to contingency drawdown, presented by Ben Fry, 10th Oct 201...
A simple approach to contingency drawdown, presented by Ben Fry, 10th Oct 201...
 
Workshop project risk management (29 june 2012)
Workshop   project risk management (29 june 2012)Workshop   project risk management (29 june 2012)
Workshop project risk management (29 june 2012)
 
Project risk management workshops
Project risk management workshopsProject risk management workshops
Project risk management workshops
 
Creativity - Does this involve thinking?
Creativity - Does this involve thinking?Creativity - Does this involve thinking?
Creativity - Does this involve thinking?
 
Project management driven by the top ten critical improvements qu…
Project management driven by the top ten critical improvements qu…Project management driven by the top ten critical improvements qu…
Project management driven by the top ten critical improvements qu…
 
Collaboration, sharing knowledge and improving delivery within local government
Collaboration, sharing knowledge and improving delivery within local governmentCollaboration, sharing knowledge and improving delivery within local government
Collaboration, sharing knowledge and improving delivery within local government
 
Knowledge management and lessons learned
Knowledge management and lessons learnedKnowledge management and lessons learned
Knowledge management and lessons learned
 
UK submarine dismantling: A case study in programme management
UK submarine dismantling: A case study in programme managementUK submarine dismantling: A case study in programme management
UK submarine dismantling: A case study in programme management
 
Delivering escapes: from idea to reality by Nena Chaletzos, 11th May 2016
Delivering escapes: from idea to reality by Nena Chaletzos, 11th May 2016Delivering escapes: from idea to reality by Nena Chaletzos, 11th May 2016
Delivering escapes: from idea to reality by Nena Chaletzos, 11th May 2016
 
NorthConnect - delivering Scotland’s sustainable future
NorthConnect - delivering Scotland’s sustainable futureNorthConnect - delivering Scotland’s sustainable future
NorthConnect - delivering Scotland’s sustainable future
 

Similar a London 2012 Olympics, Managing and controlling contingency

Balancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBalancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction Projects
Brown Smith Wallace
 
PROJECT RISK MANAGEMENT
PROJECT  RISK  MANAGEMENTPROJECT  RISK  MANAGEMENT
PROJECT RISK MANAGEMENT
Neenu Babu
 
Managing the Consulting Engagement
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting Engagement
Saumya Ganguly
 
Day 1 1620 - 1705 - pearl 1 - deep kamal singh
Day 1   1620 - 1705 - pearl 1 - deep kamal singhDay 1   1620 - 1705 - pearl 1 - deep kamal singh
Day 1 1620 - 1705 - pearl 1 - deep kamal singh
PMI2011
 
Day 201-20-201620-20-201705-20-20pearl-201-20-20deep-20kamal-20singh-13100801...
Day 201-20-201620-20-201705-20-20pearl-201-20-20deep-20kamal-20singh-13100801...Day 201-20-201620-20-201705-20-20pearl-201-20-20deep-20kamal-20singh-13100801...
Day 201-20-201620-20-201705-20-20pearl-201-20-20deep-20kamal-20singh-13100801...
PMI_IREP_TP
 

Similar a London 2012 Olympics, Managing and controlling contingency (20)

Heartbeats & Bloodstreams.pptx
Heartbeats & Bloodstreams.pptxHeartbeats & Bloodstreams.pptx
Heartbeats & Bloodstreams.pptx
 
Development of Universal Credit with Agile
Development of Universal Credit with AgileDevelopment of Universal Credit with Agile
Development of Universal Credit with Agile
 
Balancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBalancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction Projects
 
PROJECT RISK MANAGEMENT
PROJECT  RISK  MANAGEMENTPROJECT  RISK  MANAGEMENT
PROJECT RISK MANAGEMENT
 
Delivering urgent projects - management and system engineering challenges
Delivering urgent projects - management and system engineering challengesDelivering urgent projects - management and system engineering challenges
Delivering urgent projects - management and system engineering challenges
 
Advanced project risk reporting webinar, 21 September 2022
Advanced project risk reporting webinar, 21 September 2022Advanced project risk reporting webinar, 21 September 2022
Advanced project risk reporting webinar, 21 September 2022
 
Managing the Consulting Engagement
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting Engagement
 
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
 
Risk Management System
Risk Management System Risk Management System
Risk Management System
 
Enterprise risk management presentation to APM SWWE branch
Enterprise risk management presentation to APM SWWE branchEnterprise risk management presentation to APM SWWE branch
Enterprise risk management presentation to APM SWWE branch
 
Risk Factors
Risk FactorsRisk Factors
Risk Factors
 
Project management
Project managementProject management
Project management
 
Day 1 1620 - 1705 - pearl 1 - deep kamal singh
Day 1   1620 - 1705 - pearl 1 - deep kamal singhDay 1   1620 - 1705 - pearl 1 - deep kamal singh
Day 1 1620 - 1705 - pearl 1 - deep kamal singh
 
Day 201-20-201620-20-201705-20-20pearl-201-20-20deep-20kamal-20singh-13100801...
Day 201-20-201620-20-201705-20-20pearl-201-20-20deep-20kamal-20singh-13100801...Day 201-20-201620-20-201705-20-20pearl-201-20-20deep-20kamal-20singh-13100801...
Day 201-20-201620-20-201705-20-20pearl-201-20-20deep-20kamal-20singh-13100801...
 
Project lifecycle
Project lifecycleProject lifecycle
Project lifecycle
 
LN I - PPT.pptx
LN I - PPT.pptxLN I - PPT.pptx
LN I - PPT.pptx
 
Project Costs, Budgeting and Appraisal
Project Costs, Budgeting and AppraisalProject Costs, Budgeting and Appraisal
Project Costs, Budgeting and Appraisal
 
project introduction.pdf
project introduction.pdfproject introduction.pdf
project introduction.pdf
 
Business Case _ PM.pptx
Business Case _ PM.pptxBusiness Case _ PM.pptx
Business Case _ PM.pptx
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project delivery
 

Más de Association for Project Management

Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Association for Project Management
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
Association for Project Management
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Association for Project Management
 

Más de Association for Project Management (20)

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
 

Último

Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
amitlee9823
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
dollysharma2066
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
Matteo Carbone
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 

Último (20)

Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture concept
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 

London 2012 Olympics, Managing and controlling contingency

  • 1. London 2012 Olympics Managing and controlling contingency 18th April 2013
  • 2. What we wanted to achieve • Control of change – limit the amount of change that affected the programme and no surprises • Greater understanding and clarity – make decisions based on the best data possible • Promotion of activity – actively look at what could be done to limit change • Release of contingency – the great prize is not to spend Risk management overview
  • 3. •Ensure sufficient contingency available to complete the job •Limit the amount of free funds at project level – Milton Friedman? •Strictly control the use of contingency •Low levels of delegation but processes for emergencies •Re-calculate requirement regularly and measure performance •Clear guidance on the expectation for the return of contingency •Make it a programme objective to review contingency levels Principles
  • 4. The three lines of defence • Detailed project level identification and management of individual risks • ODA Programme Assurance – oversight of the process and compliance with it and the quality check of the data • ODA Risk and Audit – Setting of policy, audit of outputs and process and reporting to the Audit Committee The three lines of defence model
  • 5. Control of contingency Contingency is controlled through a series of regular governance meetings • Funders – Held by the Government funding departments •QRA calculated quarterly & contingency adjusted •Available quarterly by application to the Funders • Programme - Held by the ODA •QRA calculated quarterly & contingency adjusted •Accessible with approval to Funders • Project – held within the project budgets •QRA calculated quarterly but trended each month •Available with approval of change board, also delegation
  • 6. • Risk management is part of the change control process • Governance rules that required authorisation for all changes • Senior management reviews at various stages of the change lifecycle • Risks migrate through the process until they become certain and are requests for change with budget authority or milestone change Risk management context
  • 7. • Two parts 1. Assessment 1. Identification 2. Analysis 3. Evaluation 2. Treatment – Formulation of mitigation plans and actions • Repeat regularly based on need Risk management activities • Hold risks centrally and monitor through assurance • Ensure risk are recorded consistently with clear accountability • Report key risks and overall risk status at project and programme level • Escalate key decisions to higher authority levels for resolution • Monitor risk management process for compliance and report • Periodic review process for improvement
  • 8. • Risk management must be part of the project or progress process • Risk management carried out within the project or function • Assured by the central team for review, update and compliance • Risks reported by the project team as part of the process • Consolidation of programme risks by the central team Risk management implementation and assurance
  • 9. Risk management integrated with core programme • Risk management integrated with core programme activities • Reported as part of monthly cycle for implementation reviews etc. • Part of commercial reporting
  • 10. • QRA was used to calculate the contingency required for the budgets as part of the Baseline Report published in November 2007 – Yellow Book • QRA was part of the ongoing calculation of Anticipated Final Cost - the basis for programme performance • QRA was also used to calculate programme risk contingency • Schedule QRA was used to determine schedule risk on the complex projects and against interfaces Quantification of risk - QRA
  • 11. Review of risks • Risks, trends and issues reviewed monthly with the project team and at implementation reviews with Programme Executive • Key programme risks reviewed monthly with SROs • Programme risks reviewed by ODA assurance group monthly • Programme QRA and key programme risks review at the Funders Quarterly Risk Working Group • Key programme risks reviewed by the Audit Committee of the ODA Board
  • 12. Reporting of risks • Project risks, trends and issues reported as part of Project Status Report • Project QRA results included in calculation of AFC (Anticipated Final Cost) and reported on Project Cost Report • Key programme risks reported as part of the Monthly Progress Report • Programme QRA reported to the Government Olympic Executive and Funders as part of the Quarterly Report • Key risks reported to the Audit Committee of the ODA Board • Programme risk assurance report to monitor performance of and compliance with risk process
  • 13. Contingency reporting • Dashboard showed the current status of contingency each period • Contingency remaining, forecast requirement and variances • Changes from last period, key risks • Headroom and potential savings identified for re-cycling
  • 14. Key messages for success • Ensure sufficient contingency is available • Limit the amount of free funds available – un-let scope? • Ensure strict controls to manage contingency are in place • Assure the process, have regular audits for compliance and report at the highest level • Have clear open reporting that shows how the values have been derived • Have lots of opportunity for executive investigation, challenge and engagement • Use contingency as a performance measure – cost to go, drawdown, profiling
  • 15. Benefits of the approach • Sufficient resources are available to complete the project to its timescale – time is always the quiet victim • Scope creep is minimised as contingency is only used for those things that • It is clear how much contingency has been used and how much is required to complete • Un-needed funds can be re-cycled for further investment • Performance is easier to monitor as it is not clouded by the inappropriate use of hidden funds • It doesn’t matter how much contingency you start out with but how much you spend along the way.
  • 16. •Developer deals intended to fund the IBC/MPC and Athletes Village •Deal might be difficult to finalise •Private funding would come with additional requirements that might not be acceptable In the event the credit crunch made the deals unattractive and they collapsed •What happened? •Re-design to reduce cost •Funded from contingency and savings Risk: Credit Crunch and funding of IBC/MPC and Village
  • 17. •High number of interfaces and complexity •New bridges, roads, sewers, utilities connecting to Venues •Venues and infrastructure are in areas of changing topography What did we do? •Try to minimise the interfaces •Understand and manage the interfaces •Procure in larger packages and transfer the integration risk to the supply chain Risk: Programme interfaces and integration
  • 18. •Currently about 6,500 employees on the park and a further 5,000 on the Village •3 major unions represented •The Olympic Programme is high profile and is a target increasing as the games approached •Some demonstrations but no real industrial disputes to date Key risk: Industrial relations What do we do? •Agreed with the unions key principles of employment including: •All labour directly employed and local where possible •Pay to Working Rule Agreement rates •Union representation on site •High standard of welfare, training and employee facilities •Active and regular discussion with all the key unions •Enforcement of agreements
  • 19. Risk: Security, considerations, changes and authority •Security is key during games and construction •Security includes perimeter guarding, CCTV, Fencing etc. •Changes in security scope are always liable and to some extent unknowable •Change in threat can mean a scope change such as: •Building resilience •Hostile Vehicle Mitigation Mitigation •Close relationship with the security community and identification of possible measures required •Developed scope to be flexible and signed of by security stakeholders •Transferred cost of risk to Funders
  • 20. •Village comprises approximately 16,000 bed spaces during Games •And 2,500 flats in Legacy •11 Plots of which 5 were CM and 6 tier 1 •Large number of flats in one go in the UK to a strict deadline •Supply chain risks for component manufacture and deliverysuch as: •Bathroom pods •Cladding panels What we did •Negotiated with constructors to accelerate and buy off delay and disruption claims Delay to completion of the Athletes Village
  • 21. Risk: Health and Safety •Up to 10,000 workers on site during peak •Complex, constrained site involving: •Working at height •Hot working •Heavy machinery •Tunnelling and underground works •Temporary works •Demolition •Railway working What we did •High focus on safety culture with ‘Safe Start’ and toolbox talks etc… •Made senior managers responsible for safety performance •Stopped work when safety was compromised •World beating safety performance •So far the only Olympics without a fatality