SlideShare una empresa de Scribd logo
1 de 37



I wish to express my sincere gratitude to Shri- S.K.Banjara(C.E.)
PGTI ,CSPGCL for providing me an opportunity to do my vocational
training and project work in (D.S.P.M,TPS) korba, east.
I sincerely thank Mr . joshi sir (H.O.D of electrical engg.
department) Govt. polytechnic college for their guidance and
encouragement in carrying out this project work. I also wish to
express my gratitude to the officials and other staff members of
DSPM,TPS korba ,east who rendered there help during the period
of my project work.
Finally I express my thanks to my parents for supporting me while
I was able to complete this work successfully.
Submitted by:-
Ayushi
introduction
to thermal power plant
 Nowadays, Thermal power plant constitute
about 60 % of the total installed capacity in
the country. A Thermal power plant uses coal
and water to produce high pressure and high
temperature steam. The energy of this
steam is converted in to mechanical energy
due to rotation of turbine. Now mechanical
energy of turbine is converted into electrical
form with the help of alternators.
 The functioning of every thermal power plant
is based on the following processes
 Coal to steam
 Steam to mechanical power
 Power generation, transmission and
distribution.
Layout of thermal power plant
Working of thermal power plant
Coal handling plant
Coal handling plant---:
Peat Lignite Bitum. Anth
Carbon % 50-55 65-75 76-90 >93
Hydrogen % # 6.2 # 5.5 5.5-6.0 <2.8
Oxygen % # 35 #20 8-18 <3
Water treatment section
Water treatment plant
 The system which is used to remove the impurities
present in raw water is known as Water Treatment. Water
treatment is done to protect the boiler tubes from
corrosion and thus from damage.The final product of WT
plant is de-mineralized water (DM water). The water
treatment is sub-divided as:-
 Pre-treatment
 Post treatment
 Pre-treatment- In the pre-treatment almost all visible
matters are separated from water. In practice, alum and
lime are used for quick sedimentation . The treatment
removes 90% of organic impurities and thus clarified
water is obtained.
 Post treatment- This is about dissolved impurities which
are mostly salts of sodium, calcium and magnesium and
other elements.
 After this process DM water is obtained which is stored
in DM water tanks and then supplied to boiler.
Boiler structure
 The heat of combustion of coal in the boiler is utilized
to convert water in to steam at high temperature and
pressure .The flue gases from boiler make their
journey through super heater, economizer, air-pre
heater .The boiler in the thermal power station
consists of the following equipments:-
 Super heater:-super heater is used to remove the moisture
content from the steam. Super heater raises the
temperature of steam above 540 degree celcius .
Advantages of super heater-
1. Increases efficiency
2. Reduces corrosion of turbine blades
 Economizer:-An economizer is essentially a feed water
heater and derives heat from the flue gases for this
purpose. The feed water is fed to the economizer
before supplying it to the boiler. The economizer
extracts a part of heat of flue gases to increase the
feed water temperature. Thus, saving on fuel
consumption to a large extent.
 Air pre-heater:-An air pre-heater increases the temperature
of the air supplied for coal burning by deriving heat
from flue gases. The heat is transferred to the air fed
into the boiler for combustion and increases
efficiency.
 They are used to separate the
ash particles from flue gases. In
this the flue gas is allowed into
the ESP, where there are several
metallic plates. when these gases
enter , a very high potential
difference is applied, which
causes gas particles to ionize
and stick to the plates, whereas
the ash particles fall down and
are collected in a hopper . The
flue gases is allowed to cool
down and is the released to the
chimney.
 Turbine is the prime mover converting the energy of steam to the
rotation of turbine shaft which in turns rotates the rotor of generator.
 In small generation unit (below 100MW) only single stage turbine is
used. But in large generation unit three stage turbine is used.
a. High pressure or (HP) turbine
b. Intermediate pressure or (IP) turbine
c. Low pressure or (LP) turbine

Electrical equipments in power plant
 Power plant consists of variety of
electrical equipment.
 Major electrical equipments are
Alternator, exciters, synchronizing
equipment, Circuit Breakers, current
and potential transformers, relays and
protection equipments, isolator,
lightening arresters, earthing
equipment, station transformer, battery
and motor for driving auxiliaries.
 Transformer is the main equipment
used in the power station.
Transformer
 Transformer is a static device which
transfers AC electrical power from one
circuit to another without changing the
frequency but the voltage level is
changed.
Cooling OFB OB ON
MVA 130 90 65
KV no-load 230 H.V.
13.8 L.V.
Current (HV) 326.3 A 226 A 163 A
(LV) 5438.5 A 3765 A 2719 A
Phase 3
Frequency 50 Hz
Impedance voltage 12.56%
Vector symbol Yd11
Temperature rise Oil – 40 °C
Winding – 56 °C
The rating of 130 MVA Generator
Transformer
 In electricity generation, an
electric generator or alternator
is a device that converts
mechanical energy into to
electrical energy.
Maximum KVA rating : 294100
KVA
Maximum KW rating
:250000KW
RPM (revolution/minute) : 3000 rpm
Rated stator voltage : 16.5 KV
Rated stator current : 10291
Amp
Rated power factor : 0.85 Lag
Excitation current :
Specification of Turbo generator
(2x250 MW unit)
switch yard
 A switching substation, or switchyard, is a substation without
transformers that operates only at a single voltage level.
Switchyards, used mainly for connections and
interconnections, are essential for transmission, distribution,
collection, and controlling the flow of electricity.
 The switchyard delivers power generated at the power plant to
the electrical grid.
 Switchyards are generally classified by voltage level, circuit
breaker and bus arrangements. Switchyards are often located
directly adjacent to or near a power station.
220 kv switch yard
Lightening arrestor
 These are used to discharge
lightening over voltages and
switching over voltages to earth.
Circuit breaker
 A circuit breaker is a mechanical device
used to open and close contact under
loading and un-loading conditions.
Relay
 Relay is electro-mechanical device
which sense the excessive flow of
current and send signal to the circuit
breaker.
 These are used to disconnect transmission
line under no load condition for safety,
isolation and maintenance.
 Current transformer:- It is an instrument transformer
which is used to measure the current from high
voltage line with the use of normal ampere meter.
Potential transformer
 Potential transformer:- It is an instrument
transformer which is used to measure the
high voltage from an ordinary low voltage
instrument.
 The porcelain insulators
are used to support the bus-bar
from pole to ground. Current
rating of porcelain is above
2000Amp.
 Bus-bar is a main bar or
conductor carrying an electric
current to which many
connections are to be made.
 Material used for bus bar is
aluminium because it is high
corrosion resistance than
copper and lower cost. Bus-bar
are of 5 to 6 meter in length.
Control room
 A control room is a room serving as a centre
where a large power equipment facilities or
services can be monitored and controlled.
Safety equipments used in power
plants
Thermal power plant ppt

Más contenido relacionado

La actualidad más candente

Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
Dr. Ramesh B
 
Thermal Power Generation Report
Thermal Power Generation ReportThermal Power Generation Report
Thermal Power Generation Report
Manish Kumar
 
Classification of nuclear power plant 2171910 , power plant engineering.
Classification of nuclear power plant 2171910  , power plant  engineering.Classification of nuclear power plant 2171910  , power plant  engineering.
Classification of nuclear power plant 2171910 , power plant engineering.
Hitarth Shah
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
foxycrow
 

La actualidad más candente (20)

Thermal power station
Thermal power stationThermal power station
Thermal power station
 
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
 
Thermal Power Plant Basic to Knowledge
Thermal Power Plant Basic to KnowledgeThermal Power Plant Basic to Knowledge
Thermal Power Plant Basic to Knowledge
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Power Plant Familiarization
Power Plant FamiliarizationPower Plant Familiarization
Power Plant Familiarization
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
report on thermal power plant
report on thermal power plantreport on thermal power plant
report on thermal power plant
 
Thermal Power Generation Report
Thermal Power Generation ReportThermal Power Generation Report
Thermal Power Generation Report
 
Ppt for power plant
Ppt for power plantPpt for power plant
Ppt for power plant
 
training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...
 
Thermal Power Generation
Thermal Power GenerationThermal Power Generation
Thermal Power Generation
 
Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)
 
Classification of nuclear power plant 2171910 , power plant engineering.
Classification of nuclear power plant 2171910  , power plant  engineering.Classification of nuclear power plant 2171910  , power plant  engineering.
Classification of nuclear power plant 2171910 , power plant engineering.
 
Thermal Power plant visit Report by Amit Hinge
Thermal Power plant visit Report by Amit HingeThermal Power plant visit Report by Amit Hinge
Thermal Power plant visit Report by Amit Hinge
 
Ntpc report harsh
Ntpc report  harshNtpc report  harsh
Ntpc report harsh
 
Gas Turbine Power Plant
Gas Turbine Power PlantGas Turbine Power Plant
Gas Turbine Power Plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermal power plant
 Thermal power plant  Thermal power plant
Thermal power plant
 

Destacado

Kalisindh Super Thermal Power Plant,Jhalawar,Rajasthan ,Report
 Kalisindh Super  Thermal Power Plant,Jhalawar,Rajasthan ,Report Kalisindh Super  Thermal Power Plant,Jhalawar,Rajasthan ,Report
Kalisindh Super Thermal Power Plant,Jhalawar,Rajasthan ,Report
MAHENDRA MEENA
 
Bearing design for Turbo Generator- Internship at BHEL
Bearing design for Turbo Generator- Internship at BHELBearing design for Turbo Generator- Internship at BHEL
Bearing design for Turbo Generator- Internship at BHEL
Siva Pradeep Bolisetti
 
A presentation on turbogenerator and excitor
A presentation on turbogenerator and excitorA presentation on turbogenerator and excitor
A presentation on turbogenerator and excitor
PRAKHAR MEHROTRA
 

Destacado (20)

Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)
 
THERMAL POWER STATION PPT.
THERMAL POWER STATION PPT.THERMAL POWER STATION PPT.
THERMAL POWER STATION PPT.
 
Best ppt on thermal power station working
Best ppt on thermal power station workingBest ppt on thermal power station working
Best ppt on thermal power station working
 
kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training ppt
 
Thermal power plant ppt
Thermal power plant pptThermal power plant ppt
Thermal power plant ppt
 
Thermal power-plant
Thermal power-plantThermal power-plant
Thermal power-plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Apresentationonturbogeneratorandexcitor 1312012333
Apresentationonturbogeneratorandexcitor 1312012333Apresentationonturbogeneratorandexcitor 1312012333
Apresentationonturbogeneratorandexcitor 1312012333
 
Thermal Power Plant
Thermal Power PlantThermal Power Plant
Thermal Power Plant
 
Life is a Game ppt
Life is a Game pptLife is a Game ppt
Life is a Game ppt
 
Kalisindh Super Thermal Power Plant,Jhalawar,Rajasthan ,Report
 Kalisindh Super  Thermal Power Plant,Jhalawar,Rajasthan ,Report Kalisindh Super  Thermal Power Plant,Jhalawar,Rajasthan ,Report
Kalisindh Super Thermal Power Plant,Jhalawar,Rajasthan ,Report
 
Bhel HaridwarTraing Report
Bhel HaridwarTraing ReportBhel HaridwarTraing Report
Bhel HaridwarTraing Report
 
coal handling plant
coal handling plantcoal handling plant
coal handling plant
 
Bearing design for Turbo Generator- Internship at BHEL
Bearing design for Turbo Generator- Internship at BHELBearing design for Turbo Generator- Internship at BHEL
Bearing design for Turbo Generator- Internship at BHEL
 
Chpppt 100617141038-phpapp01
Chpppt 100617141038-phpapp01Chpppt 100617141038-phpapp01
Chpppt 100617141038-phpapp01
 
660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliaries660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliaries
 
NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')
NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')
NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')
 
Panipat thermal power station training ppt
Panipat thermal power station training pptPanipat thermal power station training ppt
Panipat thermal power station training ppt
 
A presentation on turbogenerator and excitor
A presentation on turbogenerator and excitorA presentation on turbogenerator and excitor
A presentation on turbogenerator and excitor
 

Similar a Thermal power plant ppt

Presentation 1 (2).pptx
Presentation 1 (2).pptxPresentation 1 (2).pptx
Presentation 1 (2).pptx
NaveenJarwal1
 
presentation_thermal_power_plant_1447503788_165600.pptx
presentation_thermal_power_plant_1447503788_165600.pptxpresentation_thermal_power_plant_1447503788_165600.pptx
presentation_thermal_power_plant_1447503788_165600.pptx
rajam575648
 
Vocational training at mejia thermal power plant
Vocational training at mejia thermal power plantVocational training at mejia thermal power plant
Vocational training at mejia thermal power plant
Nipak Banerjee
 
NTPC faridabad nd badarpur
NTPC faridabad nd badarpurNTPC faridabad nd badarpur
NTPC faridabad nd badarpur
Shrey Dhasmana
 

Similar a Thermal power plant ppt (20)

Kota super thermal power station, kota
Kota super thermal power station, kotaKota super thermal power station, kota
Kota super thermal power station, kota
 
Industrial training at NTPC
Industrial training at NTPCIndustrial training at NTPC
Industrial training at NTPC
 
Ppt on power generation(thermal), transmission &amp; distribution
Ppt on power generation(thermal), transmission &amp; distributionPpt on power generation(thermal), transmission &amp; distribution
Ppt on power generation(thermal), transmission &amp; distribution
 
Presentation 1 (2).pptx
Presentation 1 (2).pptxPresentation 1 (2).pptx
Presentation 1 (2).pptx
 
V.T ppt
V.T pptV.T ppt
V.T ppt
 
presentation_thermal_power.pptx
presentation_thermal_power.pptxpresentation_thermal_power.pptx
presentation_thermal_power.pptx
 
presentation_thermal_power_plant_1447503788_165600.pptx
presentation_thermal_power_plant_1447503788_165600.pptxpresentation_thermal_power_plant_1447503788_165600.pptx
presentation_thermal_power_plant_1447503788_165600.pptx
 
tps 180150109049 180150109078.pptx
tps 180150109049 180150109078.pptxtps 180150109049 180150109078.pptx
tps 180150109049 180150109078.pptx
 
Kstps ppt
Kstps pptKstps ppt
Kstps ppt
 
Ntpc barh (bstpp)
Ntpc barh (bstpp)Ntpc barh (bstpp)
Ntpc barh (bstpp)
 
ntpc
ntpcntpc
ntpc
 
Vocational training at mejia thermal power plant
Vocational training at mejia thermal power plantVocational training at mejia thermal power plant
Vocational training at mejia thermal power plant
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
 
KTPS
KTPSKTPS
KTPS
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docx
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docx
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docx
 
NTPC faridabad nd badarpur
NTPC faridabad nd badarpurNTPC faridabad nd badarpur
NTPC faridabad nd badarpur
 
MTPS Bappa main
MTPS Bappa mainMTPS Bappa main
MTPS Bappa main
 
RPS.pptx
RPS.pptxRPS.pptx
RPS.pptx
 

Último

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 

Último (20)

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 

Thermal power plant ppt

  • 1.
  • 2.
  • 3.    I wish to express my sincere gratitude to Shri- S.K.Banjara(C.E.) PGTI ,CSPGCL for providing me an opportunity to do my vocational training and project work in (D.S.P.M,TPS) korba, east. I sincerely thank Mr . joshi sir (H.O.D of electrical engg. department) Govt. polytechnic college for their guidance and encouragement in carrying out this project work. I also wish to express my gratitude to the officials and other staff members of DSPM,TPS korba ,east who rendered there help during the period of my project work. Finally I express my thanks to my parents for supporting me while I was able to complete this work successfully. Submitted by:- Ayushi
  • 4.
  • 5.
  • 6.
  • 7. introduction to thermal power plant  Nowadays, Thermal power plant constitute about 60 % of the total installed capacity in the country. A Thermal power plant uses coal and water to produce high pressure and high temperature steam. The energy of this steam is converted in to mechanical energy due to rotation of turbine. Now mechanical energy of turbine is converted into electrical form with the help of alternators.  The functioning of every thermal power plant is based on the following processes  Coal to steam  Steam to mechanical power  Power generation, transmission and distribution.
  • 8. Layout of thermal power plant
  • 9. Working of thermal power plant
  • 11.
  • 12. Coal handling plant---: Peat Lignite Bitum. Anth Carbon % 50-55 65-75 76-90 >93 Hydrogen % # 6.2 # 5.5 5.5-6.0 <2.8 Oxygen % # 35 #20 8-18 <3
  • 15.  The system which is used to remove the impurities present in raw water is known as Water Treatment. Water treatment is done to protect the boiler tubes from corrosion and thus from damage.The final product of WT plant is de-mineralized water (DM water). The water treatment is sub-divided as:-  Pre-treatment  Post treatment  Pre-treatment- In the pre-treatment almost all visible matters are separated from water. In practice, alum and lime are used for quick sedimentation . The treatment removes 90% of organic impurities and thus clarified water is obtained.  Post treatment- This is about dissolved impurities which are mostly salts of sodium, calcium and magnesium and other elements.  After this process DM water is obtained which is stored in DM water tanks and then supplied to boiler.
  • 17.  The heat of combustion of coal in the boiler is utilized to convert water in to steam at high temperature and pressure .The flue gases from boiler make their journey through super heater, economizer, air-pre heater .The boiler in the thermal power station consists of the following equipments:-  Super heater:-super heater is used to remove the moisture content from the steam. Super heater raises the temperature of steam above 540 degree celcius . Advantages of super heater- 1. Increases efficiency 2. Reduces corrosion of turbine blades
  • 18.  Economizer:-An economizer is essentially a feed water heater and derives heat from the flue gases for this purpose. The feed water is fed to the economizer before supplying it to the boiler. The economizer extracts a part of heat of flue gases to increase the feed water temperature. Thus, saving on fuel consumption to a large extent.  Air pre-heater:-An air pre-heater increases the temperature of the air supplied for coal burning by deriving heat from flue gases. The heat is transferred to the air fed into the boiler for combustion and increases efficiency.
  • 19.  They are used to separate the ash particles from flue gases. In this the flue gas is allowed into the ESP, where there are several metallic plates. when these gases enter , a very high potential difference is applied, which causes gas particles to ionize and stick to the plates, whereas the ash particles fall down and are collected in a hopper . The flue gases is allowed to cool down and is the released to the chimney.
  • 20.  Turbine is the prime mover converting the energy of steam to the rotation of turbine shaft which in turns rotates the rotor of generator.  In small generation unit (below 100MW) only single stage turbine is used. But in large generation unit three stage turbine is used. a. High pressure or (HP) turbine b. Intermediate pressure or (IP) turbine c. Low pressure or (LP) turbine
  • 21.
  • 22. Electrical equipments in power plant  Power plant consists of variety of electrical equipment.  Major electrical equipments are Alternator, exciters, synchronizing equipment, Circuit Breakers, current and potential transformers, relays and protection equipments, isolator, lightening arresters, earthing equipment, station transformer, battery and motor for driving auxiliaries.  Transformer is the main equipment used in the power station.
  • 24.  Transformer is a static device which transfers AC electrical power from one circuit to another without changing the frequency but the voltage level is changed. Cooling OFB OB ON MVA 130 90 65 KV no-load 230 H.V. 13.8 L.V. Current (HV) 326.3 A 226 A 163 A (LV) 5438.5 A 3765 A 2719 A Phase 3 Frequency 50 Hz Impedance voltage 12.56% Vector symbol Yd11 Temperature rise Oil – 40 °C Winding – 56 °C The rating of 130 MVA Generator Transformer
  • 25.  In electricity generation, an electric generator or alternator is a device that converts mechanical energy into to electrical energy. Maximum KVA rating : 294100 KVA Maximum KW rating :250000KW RPM (revolution/minute) : 3000 rpm Rated stator voltage : 16.5 KV Rated stator current : 10291 Amp Rated power factor : 0.85 Lag Excitation current : Specification of Turbo generator (2x250 MW unit)
  • 26. switch yard  A switching substation, or switchyard, is a substation without transformers that operates only at a single voltage level. Switchyards, used mainly for connections and interconnections, are essential for transmission, distribution, collection, and controlling the flow of electricity.  The switchyard delivers power generated at the power plant to the electrical grid.  Switchyards are generally classified by voltage level, circuit breaker and bus arrangements. Switchyards are often located directly adjacent to or near a power station.
  • 28. Lightening arrestor  These are used to discharge lightening over voltages and switching over voltages to earth.
  • 29. Circuit breaker  A circuit breaker is a mechanical device used to open and close contact under loading and un-loading conditions.
  • 30. Relay  Relay is electro-mechanical device which sense the excessive flow of current and send signal to the circuit breaker.
  • 31.  These are used to disconnect transmission line under no load condition for safety, isolation and maintenance.
  • 32.  Current transformer:- It is an instrument transformer which is used to measure the current from high voltage line with the use of normal ampere meter.
  • 33. Potential transformer  Potential transformer:- It is an instrument transformer which is used to measure the high voltage from an ordinary low voltage instrument.
  • 34.  The porcelain insulators are used to support the bus-bar from pole to ground. Current rating of porcelain is above 2000Amp.  Bus-bar is a main bar or conductor carrying an electric current to which many connections are to be made.  Material used for bus bar is aluminium because it is high corrosion resistance than copper and lower cost. Bus-bar are of 5 to 6 meter in length.
  • 35. Control room  A control room is a room serving as a centre where a large power equipment facilities or services can be monitored and controlled.
  • 36. Safety equipments used in power plants