SlideShare a Scribd company logo
1 of 19
BY ABHISEK PANDA
REGD NO.-110301CER058
1
KEY PLAN OF THE PROJECT
2
DETAILS OF THE PROJECT
 Client Municipal Corporation,
Jalandhar
 Construction agency M/S Gammon India Ltd.
 Type of contract Item rate
 Total length of ROB 1.65 Km
 Cost of the project Rs 20 crores
 Contract period 15 months
 Starting date 28-06-2004
3
COMPANY PROFILE
 Gammon India Limited is one of the leading
construction companies in India today.
 The company was established by late Mr. J. C.
Gammon in 1919 as a firm of Civil Engineers &
Contractor.
 Gammon's capabilities cover the entire spectrum
of technological advances in bridge engineering.
 Besides designing and building bridges, Gammon
has achieved perfection in the techniques of
launching, underwater concreting development of
supporting equipment.
4
EQUIPMENTS USED AT SITE
Needle type vibrator (60 mm dia) Concrete pump (56 m³/hr)
Gantry girder ( 60 ton) Transit mixer (7 m³ capacity)
5
EQUIPMENTS USED AT SITE
6
7
FOUNDATION : PILES
 Piles are long slender members that carry and
transfer the load of the structure to the ground
located at some depth below the ground and the earth
surrounding the piles.
 Bored cast in-situ friction RCC piles of diameter 1000
mm.
 M35 grade of concrete was used at our site.
 Average depth of the piles was 20 m. 8
PIER CAP
9
CONCRETE MIX PROPORTION FOR PILE CAP
 Different grades of concrete were used for the
bridge construction.
 M35 was used for the pile cap.
 Steel used : Fe 415.
 Cement used : Vikram cement (OPC 53 grade)
 Aggregates used : 10 mm, 20 mm and sand.
 Admixture used : FORSOC CONPLAST SP
430.
Cement : Sand : Coarse Aggregate = 1 : 1.36 : 3.24
Cement W/C
Ratio
Water Sand 20 mm 10 mm Admixture
400
kg/m³
0.37 148
kg/m³
684
kg/m³
592.5
kg/m³
592.5
kg/m³
0.4
1 0.37 1.36 1.94 1.3 0.001
10
PROJECT NO. 2
SUPERVISION OF THE
SUPERSTRUCTURE
11
Pretensioned I-Girder
12
Methodology for the construction of I-Girder:
1. Preparing the shuttering:
Bearing plates Dowel bars
Groove made for bearings
Bearing
plate
dowels
grease
Dowel bars
200 mm length
Outer dia 50 mm
Inner dia 22 mm
13
2. Lowering of the reinforcement cage:
Gantry girder : 60 ton and 35 ton
3. Cable threading:
14
Reinforcement
cage
cables
Wedges
and
barrels
4. Stressing:
Least count of the pump : 5 kg/cm².
5. Closing of the side shutters
6. Concreting:
Automatic batching plant
Needle type vibrator : 60 mm dia
Concrete pump : 56 m³/hr
7. Deshuttering:
After 24 hrs
Cement W/C
Ratio
Water Sand 20 mm 10 mm Admixture
435
kg/m³
0.30 130.5
kg/m³
652
kg/m³
741
kg/m³
494
kg/m³
0.8%
15
Concrete coming out of
the pipe line
Deshuttered beam
8. Destressing
Using the grinder.
9. Lifting of the girders
10. Curing
For next 25 days at least.
16
Hessian
cloth
Cables
after
cutting at
top
Cables after
cutting at bottom
BOX GIRDER
I-girders can be used only for the spans smaller than 20-25 m or which
are
not curved. For curved spans and spans which are greater than 20-25
m, box
girders are used.
17
SAFETY REQUIREMENTS
1. Training the workers.
2. Providing the first aid.
3. List of nearby hospitals.
4. Safety manual.
5. Banners.
6. Using the safety equipments.
7. Providing the vehicle.
18
19

More Related Content

What's hot

Bridge Design Presentation, Mechanics Statics
Bridge Design Presentation, Mechanics StaticsBridge Design Presentation, Mechanics Statics
Bridge Design Presentation, Mechanics StaticsAdibah Hanusi
 
Concrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slabConcrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slabDivineGraceFernando
 
Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)varun km
 
Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)SSudhaVelan
 
Design and construction of concrete roads
Design and construction of concrete roadsDesign and construction of concrete roads
Design and construction of concrete roadsOlukayode Alao
 
Tw Rcc Dams Display
Tw Rcc Dams DisplayTw Rcc Dams Display
Tw Rcc Dams DisplayTed Warren
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentationPravin Gaurav
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing TechniqueSeminar Links
 
Precast structure
Precast structurePrecast structure
Precast structurepiyush9392
 
One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)AMSYSCO Inc.
 
Prefabricated wall panel
Prefabricated wall panelPrefabricated wall panel
Prefabricated wall panelSAHIL KUMAR
 
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...R C Patil Patil
 
Signature bridge presentation
Signature bridge presentationSignature bridge presentation
Signature bridge presentationBhismo Dev
 
Literature work study of precast concrete connections in seismic
Literature work study of precast concrete connections in seismicLiterature work study of precast concrete connections in seismic
Literature work study of precast concrete connections in seismicIAEME Publication
 
IRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET Journal
 

What's hot (20)

Bridge Design Presentation, Mechanics Statics
Bridge Design Presentation, Mechanics StaticsBridge Design Presentation, Mechanics Statics
Bridge Design Presentation, Mechanics Statics
 
Concrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slabConcrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slab
 
Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)
 
Signature bridge
Signature bridgeSignature bridge
Signature bridge
 
Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)
 
Design and construction of concrete roads
Design and construction of concrete roadsDesign and construction of concrete roads
Design and construction of concrete roads
 
Precast
PrecastPrecast
Precast
 
Tw Rcc Dams Display
Tw Rcc Dams DisplayTw Rcc Dams Display
Tw Rcc Dams Display
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentation
 
Chimney one go
Chimney one goChimney one go
Chimney one go
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
Precast structure
Precast structurePrecast structure
Precast structure
 
One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)
 
Prefabricated wall panel
Prefabricated wall panelPrefabricated wall panel
Prefabricated wall panel
 
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
 
Signature bridge presentation
Signature bridge presentationSignature bridge presentation
Signature bridge presentation
 
Literature work study of precast concrete connections in seismic
Literature work study of precast concrete connections in seismicLiterature work study of precast concrete connections in seismic
Literature work study of precast concrete connections in seismic
 
8课
8课8课
8课
 
IRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing Technique
 
PreCast Construction
PreCast ConstructionPreCast Construction
PreCast Construction
 

Viewers also liked

PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge ConstructionRobin Nirwal
 
Railway Bridges History & Construction
Railway Bridges History & ConstructionRailway Bridges History & Construction
Railway Bridges History & ConstructionZakaria Yahya
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineeringHalcrow
 
Barbendingscheduleby shamshair ali
Barbendingscheduleby shamshair aliBarbendingscheduleby shamshair ali
Barbendingscheduleby shamshair aliShamshair Ali
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project managementKabilan Kabi
 
Basics of bridge construction
Basics of bridge constructionBasics of bridge construction
Basics of bridge constructionsymphonyjo
 
indian railways Presentation .
 indian railways Presentation . indian railways Presentation .
indian railways Presentation .Akash Gupta
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction managementAditi Shah
 
Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...Rajesh Prasad
 
Bar bending schedule(by akhil)
Bar bending schedule(by akhil)Bar bending schedule(by akhil)
Bar bending schedule(by akhil)Lamdade Akhil
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Final ppt of project
Final ppt of projectFinal ppt of project
Final ppt of projectRuchi Gulati
 
Project Management PPT
Project Management PPTProject Management PPT
Project Management PPTbletindia
 
Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD Alok Mishra
 

Viewers also liked (19)

presentation
presentationpresentation
presentation
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge Construction
 
Railway Bridges History & Construction
Railway Bridges History & ConstructionRailway Bridges History & Construction
Railway Bridges History & Construction
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Diabetes
DiabetesDiabetes
Diabetes
 
Barbendingscheduleby shamshair ali
Barbendingscheduleby shamshair aliBarbendingscheduleby shamshair ali
Barbendingscheduleby shamshair ali
 
PERT CPM Intro
PERT CPM IntroPERT CPM Intro
PERT CPM Intro
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Basics of bridge construction
Basics of bridge constructionBasics of bridge construction
Basics of bridge construction
 
indian railways Presentation .
 indian railways Presentation . indian railways Presentation .
indian railways Presentation .
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Bar bending schedule(by akhil)
Bar bending schedule(by akhil)Bar bending schedule(by akhil)
Bar bending schedule(by akhil)
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Final ppt of project
Final ppt of projectFinal ppt of project
Final ppt of project
 
Project Management PPT
Project Management PPTProject Management PPT
Project Management PPT
 
Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD
 
Project management
Project managementProject management
Project management
 

Similar to Cep construction of railway overbridge by abhisek panda

Polavaram internship
Polavaram internshipPolavaram internship
Polavaram internshipsaibabu48
 
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...IEI GSC
 
flyover internship 2
flyover internship 2flyover internship 2
flyover internship 2Ravi Mehta
 
Amit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAmit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAman Jain
 
Dmrctrainingpresentation 161115165907
Dmrctrainingpresentation 161115165907Dmrctrainingpresentation 161115165907
Dmrctrainingpresentation 161115165907yogesh pal
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveyingAnchit Agrawal
 
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Rabindra Shrestha
 
Dismantling of existing ROB, CSB Nagpur, AFCONS
Dismantling of existing ROB, CSB Nagpur, AFCONSDismantling of existing ROB, CSB Nagpur, AFCONS
Dismantling of existing ROB, CSB Nagpur, AFCONSSaritaJoshi5
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover projectKriShna Sharma
 
IRJET- Experimental Investigation of Paver Blocks using High Early Strenght C...
IRJET- Experimental Investigation of Paver Blocks using High Early Strenght C...IRJET- Experimental Investigation of Paver Blocks using High Early Strenght C...
IRJET- Experimental Investigation of Paver Blocks using High Early Strenght C...IRJET Journal
 
Precast Wings segment casting NHAI Spine
Precast Wings segment casting NHAI Spine Precast Wings segment casting NHAI Spine
Precast Wings segment casting NHAI Spine Roshan Sharma
 

Similar to Cep construction of railway overbridge by abhisek panda (20)

Hanging bridge kota
Hanging bridge kotaHanging bridge kota
Hanging bridge kota
 
Summer training report
Summer training reportSummer training report
Summer training report
 
DMC piling
DMC pilingDMC piling
DMC piling
 
Polavaram internship
Polavaram internshipPolavaram internship
Polavaram internship
 
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
 
flyover internship 2
flyover internship 2flyover internship 2
flyover internship 2
 
DMC Piling
DMC PilingDMC Piling
DMC Piling
 
Amit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAmit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha university
 
Dmrctrainingpresentation 161115165907
Dmrctrainingpresentation 161115165907Dmrctrainingpresentation 161115165907
Dmrctrainingpresentation 161115165907
 
PDash,NMDCEDL6.pptx
PDash,NMDCEDL6.pptxPDash,NMDCEDL6.pptx
PDash,NMDCEDL6.pptx
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)
 
SANDEEP PPT
SANDEEP PPTSANDEEP PPT
SANDEEP PPT
 
Major Project ppt
Major Project ppt Major Project ppt
Major Project ppt
 
Dismantling of existing ROB, CSB Nagpur, AFCONS
Dismantling of existing ROB, CSB Nagpur, AFCONSDismantling of existing ROB, CSB Nagpur, AFCONS
Dismantling of existing ROB, CSB Nagpur, AFCONS
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
 
IRJET- Experimental Investigation of Paver Blocks using High Early Strenght C...
IRJET- Experimental Investigation of Paver Blocks using High Early Strenght C...IRJET- Experimental Investigation of Paver Blocks using High Early Strenght C...
IRJET- Experimental Investigation of Paver Blocks using High Early Strenght C...
 
Precast Wings segment casting NHAI Spine
Precast Wings segment casting NHAI Spine Precast Wings segment casting NHAI Spine
Precast Wings segment casting NHAI Spine
 
Delhi metro presention
Delhi   metro presentionDelhi   metro presention
Delhi metro presention
 

Recently uploaded

Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 

Recently uploaded (20)

Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 

Cep construction of railway overbridge by abhisek panda

  • 1. BY ABHISEK PANDA REGD NO.-110301CER058 1
  • 2. KEY PLAN OF THE PROJECT 2
  • 3. DETAILS OF THE PROJECT  Client Municipal Corporation, Jalandhar  Construction agency M/S Gammon India Ltd.  Type of contract Item rate  Total length of ROB 1.65 Km  Cost of the project Rs 20 crores  Contract period 15 months  Starting date 28-06-2004 3
  • 4. COMPANY PROFILE  Gammon India Limited is one of the leading construction companies in India today.  The company was established by late Mr. J. C. Gammon in 1919 as a firm of Civil Engineers & Contractor.  Gammon's capabilities cover the entire spectrum of technological advances in bridge engineering.  Besides designing and building bridges, Gammon has achieved perfection in the techniques of launching, underwater concreting development of supporting equipment. 4
  • 5. EQUIPMENTS USED AT SITE Needle type vibrator (60 mm dia) Concrete pump (56 m³/hr) Gantry girder ( 60 ton) Transit mixer (7 m³ capacity) 5
  • 7. 7
  • 8. FOUNDATION : PILES  Piles are long slender members that carry and transfer the load of the structure to the ground located at some depth below the ground and the earth surrounding the piles.  Bored cast in-situ friction RCC piles of diameter 1000 mm.  M35 grade of concrete was used at our site.  Average depth of the piles was 20 m. 8
  • 10. CONCRETE MIX PROPORTION FOR PILE CAP  Different grades of concrete were used for the bridge construction.  M35 was used for the pile cap.  Steel used : Fe 415.  Cement used : Vikram cement (OPC 53 grade)  Aggregates used : 10 mm, 20 mm and sand.  Admixture used : FORSOC CONPLAST SP 430. Cement : Sand : Coarse Aggregate = 1 : 1.36 : 3.24 Cement W/C Ratio Water Sand 20 mm 10 mm Admixture 400 kg/m³ 0.37 148 kg/m³ 684 kg/m³ 592.5 kg/m³ 592.5 kg/m³ 0.4 1 0.37 1.36 1.94 1.3 0.001 10
  • 11. PROJECT NO. 2 SUPERVISION OF THE SUPERSTRUCTURE 11
  • 13. Methodology for the construction of I-Girder: 1. Preparing the shuttering: Bearing plates Dowel bars Groove made for bearings Bearing plate dowels grease Dowel bars 200 mm length Outer dia 50 mm Inner dia 22 mm 13
  • 14. 2. Lowering of the reinforcement cage: Gantry girder : 60 ton and 35 ton 3. Cable threading: 14 Reinforcement cage cables Wedges and barrels
  • 15. 4. Stressing: Least count of the pump : 5 kg/cm². 5. Closing of the side shutters 6. Concreting: Automatic batching plant Needle type vibrator : 60 mm dia Concrete pump : 56 m³/hr 7. Deshuttering: After 24 hrs Cement W/C Ratio Water Sand 20 mm 10 mm Admixture 435 kg/m³ 0.30 130.5 kg/m³ 652 kg/m³ 741 kg/m³ 494 kg/m³ 0.8% 15 Concrete coming out of the pipe line Deshuttered beam
  • 16. 8. Destressing Using the grinder. 9. Lifting of the girders 10. Curing For next 25 days at least. 16 Hessian cloth Cables after cutting at top Cables after cutting at bottom
  • 17. BOX GIRDER I-girders can be used only for the spans smaller than 20-25 m or which are not curved. For curved spans and spans which are greater than 20-25 m, box girders are used. 17
  • 18. SAFETY REQUIREMENTS 1. Training the workers. 2. Providing the first aid. 3. List of nearby hospitals. 4. Safety manual. 5. Banners. 6. Using the safety equipments. 7. Providing the vehicle. 18
  • 19. 19