Hydro-Electric Power Plant
Introduction:
One of the most widely used renewable source of energy for generating
electricity on large scale basis is hydropower

The power obtained from river or ocean water is called as hydropower.

Hydropower is the renewable source of energy since water is available
in large quantities from rain, rivers, and oceans and this is will be
available for unlimited time to come.

30% of total power of the world is met by hydro-electric power.

Total hydro-potential of the world id 5000 GW.
Essential features of Hydro-Electric Power
  Plant:
The essential features of a water power plant are as below:
1. Catchment area.
2. Reservoir.
3. Dam and intake house.
4. water way.
5. Power house.
6. Tail race or outlet water way.

 1.Catchment Area.
 The catchment area of a hydro plant is the whole area behind the
 dam, draining into a stream or river across which the dam has
 been built at a suitable place.
2-       Water reservoir:
 In a reservoir the water collected
  from the catchment area is stored
  behind a dam.
 Catchment area gets its water from
  rain and streams.
 The level of water surface in the
  reservoir is called Head water level.
  Note : Continuous availability of
  water is a basic necessity for a
  hydro-electric power plant.
3-       Dam :
 The purpose of the dam is to store
  the water and to regulate the out
  going flow of water.
 The dam helps to store all the
  incoming water. It also helps to
  increase the head of the water. In
  order to generate a required quantity
  of power it is necessary that a
  sufficient head is available.           5
• Dam are classified based on following factors:
a) Function
b) Shape
c) Construction material
d) Design
a)       Based on function the dam may be called as storage dam,
diversion dam or detention dam.
b) Based on the shape the dam may of trapezoidal section &
     arch type.
c)      The materials used for constructing dams are earth, rock
pieces, stone masonry.
d) According to structural design the dam maybe classified as:
i. Gravity dam
ii. Arch dam
iii. Buttress dam
Types of Dam:
1. Masonry Dams.
2. Earth Dams.
The masonry dams are of three major classes:
a) Gravity dam.
b) Buttress dam.
c) Arched dam.
d) Gravity dam:
Resist the pressure of water by its weight.
Construction of material used for his dam, is solid masonry or
concrete.
b) Arch dam:
It resist the pressure of water partly due to its
weight and partly due to arch action.
c) Buttress dam:
• Buttress supporting a flat slab.
• When cost of reinforced concrete is high such
   type of dam is selected.
Spillway:
 Excess accumulation of water endangers
  the stability of dam construction. Also in
  order to avoid the over flow of water out
  of the dam especially during rainy
  seasons spillways are provided. This
  prevents the rise of water level in the
  dam.
 Spillways are passages which allows the
  excess water to flow to a storage area
  away from the dam.

Gate:
 A gate is used to regulate or control the
  flow of water from the dam.

Pressure tunnel:
   It is a passage that carries water from the
    reservoir to the surge tank.



7 May 2012                                        9
Surge tank:
 A Surge tank is a small reservoir or tank in which the water level rises or
  falls due to sudden changes in pressure.
Purpose of surge tank:
 To serve as a supply tank to the turbine when the water in the pipe is
  accelerated during increased load conditions and as a storage tank when the
  water is decelerating during reduced load conditions.
 To reduce the distance between the free water surface in the dam and the
  turbine, thereby reducing the water-hammer effect on penstock and also
  protect the upstream tunnel from high pressure rise.
Water-hammer effect :
o The water hammer is defined as the change in pressure rapidly above or below normal
  pressure caused by sudden change in the rate of water flow through the pipe, according
  to the demand of prime mover i.e. turbine




                                                                                    10
4-        Water Ways.
Water ways are the passages, through which the water is
conveyed to the turbines from the dam. These may include
tunnels, canals, flumes, forebays and penstocks and also
surge tanks.
A forebay is an enlarged passage for drawing the water
from the reservoir or the river and giving it to the pipe lines
or canals.




 7 May 2012                                                       11
Penstock thickness:
Number of penstock
A hydro Power Plant uses a number of turbine which are to be
supplied water through penstock.
• To use a single penstock for the whole a plant.
• To use on penstock for each turbine separately.
• To provide multiple penstock but each penstock supplying water
   to at least two turbine.


Factors for Selecting number of penstocks:
• Economy.
• Operational safety.
• Transportation facilities.
5-     Power House.
The power house is a building in which the turbines, alternators
and the auxiliary plant are housed. Some important items of
equipment provided in the power house are as follows:
i. Turbines
ii. Generators
iii. Governors
iv. Relief valve for penstock setting
v. Gate valve
vi. Transformer
vii. Switch board equipment and instruments
viii. Oil circuit breaker
ix. Storage batteries
x. Outgoing connections
xi. Cranes
xii. Shops & offices
The surface power house has been broadly divided into three
subdivisions which is separated
from the intake as mentioned below :
(a) Substructure ;
(b) Intermediate structure ;
(c) Super-structure.
Draft tube:
 It is connected to the outlet of the turbine.
 It allows the turbine to be placed above the tail water level.
6-     Tail water level or Tail race:
o Tail water level is the water level after the discharge from the
   turbine. The discharged water is sent to the river, thus the level of
   the river is the tail water level.
Electric generator, Step-up transformer and Pylon :
 As the water rushes through the turbine, it spins the turbine shaft,
   which is coupled to the electric generator. The generator has a
   rotating electromagnet called a rotor and a stationary part called a
   stator. The rotor creates a magnetic field that produces an electric
   charge in the stator. The charge is transmitted as electricity. The
   step-up transformer increases the voltage of the current coming
   from the stator. The electricity is distributed through power lines
   also called as pylon.
Classification of hydro-Electric power plant
The classification of hydro electric power plant depend on the following
factors:
1) Quantity of water:
It is following types.
i. Run of river plant.
ii. Storage plant.
iii. Pumped storage.

2)   Availability of Head of Water:
a)   Low head plant.                  Operating head < 15m.
b)   Medium head plant.               Operating head 15 to 50m.
c)   High head plants                 Operating head > 50m.
a)       Low head plant
     • Operating head is less than 15m.
     • Vertical shaft Francis turbine or Kaplan turbine.
     • Small dam is required.
a)       Medium head plant
     • Operating head is less than 15 to 50m.
     • Francis turbines.
     • Forebay is provided at the beginning of the penstock.
a)        High head plant
     •   Operating head exceed 50m.
     •   Pelton turbines.
     •   surge tank is attached to the penstock to reduce water hammer effect on the
         penstock.
Advantages of hydel power plant :

 Water is a renewable energy source.
 Maintenance and operation charges are very low.
 The efficiency of the plant does not change with age.
 In addition to power generation, hydro-electric power
  plants are also useful for flood control, irrigation
  purposes, fishery and recreation.
 Have a longer life(100 to 125 years) as they operate at
  atmospheric temperature.
 Water stored in the hydro-electric power plants can also
  be used for domestic water supply.
 Since hydro-electric power plants run at low speeds(300
  to 400 rpm) there is no requirement of special alloy steel
  construction materials or specialised mechanical
  maintenance.
Disadvantages of hydel power plant :

 The initial cost of the plant is very high.
 Since they are located far away from the load centre, cost of
  transmission lines and transmission losses will be more.
 During drought season the power production may be reduced
  or even stopped due to insufficient water in the reservoir.
 Water in the reservoir is lost by evaporation.
Draft Tube:
Reaction turbines must be completely enclosed because a
pressure difference exists between the working fluid (water) in
the turbine and atmosphere. Therefore, it is necessary to
connect the turbine outlet by means of a pipe known as draft
tube upto tailrace level.
Types of Draft Tubes
(1) Conical Draft Tube.
This is known as tapered draft tube and used in all reaction
turbines where conditions permit. It is preferred for low specific
speed and vertical shaft Francis turbine. The maximum cone
angle of this draft tube is limited to 8° (a = 4°). The hydraulic
efficiency of such type of draft tube is 90%.
2-     Elbow Type Draft Tube.
The elbow type draft tube is often preferred in most of the power
plants, where the setting of vertical draft tube does not permit
enough room without excessive cost of excavation.
3-     Moody Draft Tube.
This draft tube has an advantage that its conical portion at the
center reduces the whirl action of water moving with high velocity
centre reduces.
Hydraulic Turbines
Advantages:
Simple in construction.
Easily controllable.
Efficient.
Ability to work at peak load.
Work on load variation.
Start from cold conditions & pick up load at short time.
Types of turbines:
a) Impulse
b) Reaction
Impulse Turbine:
The passages are not completely filled, water acting on a wheel
buckets is at atmospheric pressure and is supplied at few points at the
periphery of wheel & kinetic energy is supplied to the wheel.
Casing
Penstock
Nozzle
Runner
Buckets
Needle Valve
shaft
Reaction Turbine:
Water passages are completely filled with water, water acting on
wheel vanes is under pressure greater than atmospheric, water enter
all around the periphery of wheel and energy is in the form of both
pressure & kinetic energy is utilized by the wheel.
Essential parts:
Spiral casing
Guide wheel
Runner
Draft tube

• Horizontal shaft type or vertical shaft type turbine
• Low & medium head turbines
Direction of flow of water:
I.     Tangential flow turbine
II.    Radial flow turbine.
III.   Axial flow turbine.
IV.    Mixed flow turbine.


         Types of turbine Flow direction
         Kaplan turbine          Axial flow

         Franics Turbine         Radial inward or mixed flow

         Pelton wheel            Tangential flow
Position of shaft:
I.    Vertical shaft turbine.
II.   Horizontal shaft turbine.

Head of water:
I. High head turbines.
II. Medium head turbines.
III. Low head turbines.

Impulse turbines                  high head.
Reaction turbines                 low & medium heads.
Performance of water turbine:
Important parameter for any particular turbine are:
• Discharge
• Head
• Efficiency
• Speed
• Power

The turbine characteristic like unit power, unit speed & unit discharge
help in studying the performance of turbines.
Specific Speed:
The specific speed of a turbine is defined as the speed at which the
turbine runs developing one B.H.P. under a head of one meter.
The equation for the specific speed of a turbine can be obtained by
using the principle of similarity.


where D and N are diameter and speed of a turbine and H is the head
acting on the turbine.

where B is the height of the blade and Vf is the velocity of flow.
Substituting the value of D in the above equation.




   where P is the power developed.
Substituting the value of Q in the above equation, we get




where C is constant depending upon the type of the turbine.
If the turbine develops 1 B.H.P. under one meter head then
                  C = N = N.
where Ns is the specific speed as per the definition.
Substituting the value of C in the above equation, we get
SELECTION OF SITE FOR A HYDRO-ELECTRIC
  POWER PLANT
The following factors should be given careful consideration
while selecting a site for a hydro-electric power plant:
1. Water Available.
The recorded observation should be taken over a number of years to
know within reasonable, limits the maximum and minimum
variations from the average discharge. the river flow data should be
based on daily, weekly, monthly and yearly flow ever a number of
years. Then the curves or graphs can be plotted between tile river
flow and time. These are known as hygrographs and flow
duration curves.
2. Water-Storage.
The output of a hydropower plant is not uniform due to wide
variations of rain fall. To have a uniform power output, a water
storage is needed so that excess flow at certain times may be stored
to make it available at the times of low flow. To select the site of the
Dam, careful study should be made of the geology and topography of
the catchment area to see if the natural foundations could be found
and put to the best use.
3. Head of Water.
The level of water in the reservoir for a proposed plant should always
be within limits throughout the year.
4. Distance from Load Center.
Most of the time the electric power generated in a hydro-electric
power plant has to be used some considerable distance from the
site of plant. For this reason, to be economical on transmission of
electric power, the routes and the distances should be carefully
considered since the cost of erection of transmission lines and
their maintenance will depend upon the route
selected.
5. Access to Site.
It is always a desirable factor to have a good access to the site of
the plant. This factor is very important if the electric power
generated is to be utilized at or near the plant site. The transport
facilities must also be given due consideration.
Hydrology
• It is natural science that deal with the distribution of water on land
  beneath the surface of earth.
• It deal with the solid, liquid & vapour forms of water.
Hydrologic cycle:
The various processes involved in the transfer of moisture from the sea
to the land and back to the sea again constitute which is called
hydrologic cycle.
Hydrologic eq. is expressed as follows:
P=R+E
Where,
P = perspiration
R = Run-off
E = Evaporation.
Perspiration:
It includes all the water that falls from atm. To the earth
surface. Mostly perspiration is of two types.
Liquid perspiration (rainfall)
Solid perspiration (Snow, Hail storm)
Run-off:
It is that portion of the perspiration which makes its way
towards stream, lakes or ocean.
Run-off occur only if the rate of perspiration exceed the rate
at which water infiltrate into the soil & after depression
small and large on the soil surface get filled in the water.
Evaporation:
Transfer of water from liquid to vapour state
Transpiration:
Process by which water is released to the atmosphere by the
plant.
Assignment
• Topics: 6.37 & 6.38(6.38.1, 6.38.2, 6.38.3,
  6.38.4)
• Examples:
• 6.1 to 6.13, 6.15 to 6.20.
Questions?

Más contenido relacionado

La actualidad más candente

PUMPED STORAGE PLANT
PUMPED STORAGE PLANTPUMPED STORAGE PLANT
PUMPED STORAGE PLANTNilanjana Sen
 
Ppt for power plant
Ppt for power plantPpt for power plant
Ppt for power plantra m
 
Component of Hydro Power Plant
Component of Hydro Power PlantComponent of Hydro Power Plant
Component of Hydro Power PlantSatish Taji
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plantNishkam Dhiman
 
Elements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTSElements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTSRaju D
 
Types of turbine & thier application
Types of turbine & thier applicationTypes of turbine & thier application
Types of turbine & thier applicationdaudsangeenkhan
 
Unit_IV-HYDRO ELECTRIC POWER PLANTS
Unit_IV-HYDRO ELECTRIC POWER PLANTSUnit_IV-HYDRO ELECTRIC POWER PLANTS
Unit_IV-HYDRO ELECTRIC POWER PLANTSS.Vijaya Bhaskar
 
Pumped storage hydro power plant
Pumped storage hydro power plantPumped storage hydro power plant
Pumped storage hydro power plantCraZzy Shubh
 
Selection of Turbine | Fluid Mechanics
Selection of Turbine | Fluid MechanicsSelection of Turbine | Fluid Mechanics
Selection of Turbine | Fluid MechanicsSatish Taji
 
Chapter one-Introduction to Hydroelectric power plant
Chapter one-Introduction to Hydroelectric power plantChapter one-Introduction to Hydroelectric power plant
Chapter one-Introduction to Hydroelectric power plantYimam Alemu
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plantsnelkoli
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plantShaik Afzal
 
Hydropower - power house
Hydropower - power houseHydropower - power house
Hydropower - power housearullawrance90
 
Braking methods of induction motor
Braking methods of induction motorBraking methods of induction motor
Braking methods of induction motorraviarmugam
 

La actualidad más candente (20)

PUMPED STORAGE PLANT
PUMPED STORAGE PLANTPUMPED STORAGE PLANT
PUMPED STORAGE PLANT
 
Ppt for power plant
Ppt for power plantPpt for power plant
Ppt for power plant
 
Power plant technology
Power plant technologyPower plant technology
Power plant technology
 
Component of Hydro Power Plant
Component of Hydro Power PlantComponent of Hydro Power Plant
Component of Hydro Power Plant
 
Hydro Power Plants
Hydro Power PlantsHydro Power Plants
Hydro Power Plants
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Elements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTSElements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTS
 
Types of turbine & thier application
Types of turbine & thier applicationTypes of turbine & thier application
Types of turbine & thier application
 
Unit_IV-HYDRO ELECTRIC POWER PLANTS
Unit_IV-HYDRO ELECTRIC POWER PLANTSUnit_IV-HYDRO ELECTRIC POWER PLANTS
Unit_IV-HYDRO ELECTRIC POWER PLANTS
 
Pumped storage hydro power plant
Pumped storage hydro power plantPumped storage hydro power plant
Pumped storage hydro power plant
 
Selection of Turbine | Fluid Mechanics
Selection of Turbine | Fluid MechanicsSelection of Turbine | Fluid Mechanics
Selection of Turbine | Fluid Mechanics
 
Chapter one-Introduction to Hydroelectric power plant
Chapter one-Introduction to Hydroelectric power plantChapter one-Introduction to Hydroelectric power plant
Chapter one-Introduction to Hydroelectric power plant
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Power plant economics
Power plant economicsPower plant economics
Power plant economics
 
Hydraulic turbines
Hydraulic turbinesHydraulic turbines
Hydraulic turbines
 
Hydropower - power house
Hydropower - power houseHydropower - power house
Hydropower - power house
 
Braking methods of induction motor
Braking methods of induction motorBraking methods of induction motor
Braking methods of induction motor
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 

Similar a Hydro electric power plant lecture

Malay nces ppt
Malay nces pptMalay nces ppt
Malay nces ppt9888437802
 
hydro-electricpowerplant_NPS.pdf
hydro-electricpowerplant_NPS.pdfhydro-electricpowerplant_NPS.pdf
hydro-electricpowerplant_NPS.pdfNAVEENM849290
 
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptxWajidMalik27
 
Lecture 20 hydro electric power plant
Lecture 20 hydro electric power plantLecture 20 hydro electric power plant
Lecture 20 hydro electric power plantSwapnil Gadgune
 
Calculation Efficiency of 2GW Hydropower Plant.
Calculation Efficiency of 2GW Hydropower Plant.Calculation Efficiency of 2GW Hydropower Plant.
Calculation Efficiency of 2GW Hydropower Plant.Salman Jailani
 
Calculation Efficiency of 5GW Hydropower Plant.
Calculation Efficiency of 5GW Hydropower Plant.Calculation Efficiency of 5GW Hydropower Plant.
Calculation Efficiency of 5GW Hydropower Plant.Salman Jailani
 
Hydro Electric Power plant
Hydro Electric Power plantHydro Electric Power plant
Hydro Electric Power plantRatan Debnath
 
RES Lecture 18 Hydro.pptx
RES Lecture 18 Hydro.pptxRES Lecture 18 Hydro.pptx
RES Lecture 18 Hydro.pptxEngr umar
 
Introduction to power plant
Introduction to power plantIntroduction to power plant
Introduction to power plantRahul Rathod
 
Hydroelectric powerplant
Hydroelectric powerplantHydroelectric powerplant
Hydroelectric powerplantGurkirat Singh
 
Hydal power plant
Hydal power plantHydal power plant
Hydal power plantJUNAID SK
 
HYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in India
HYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in IndiaHYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in India
HYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in IndiaMayurjyotiNeog
 
Hydropower engineering -Hydraulics
Hydropower engineering -HydraulicsHydropower engineering -Hydraulics
Hydropower engineering -HydraulicsCivil Zone
 

Similar a Hydro electric power plant lecture (20)

Malay nces ppt
Malay nces pptMalay nces ppt
Malay nces ppt
 
hydro-electricpowerplant_NPS.pdf
hydro-electricpowerplant_NPS.pdfhydro-electricpowerplant_NPS.pdf
hydro-electricpowerplant_NPS.pdf
 
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
 
Lecture 20 hydro electric power plant
Lecture 20 hydro electric power plantLecture 20 hydro electric power plant
Lecture 20 hydro electric power plant
 
Hydel Generation and Types Of Turbines
Hydel Generation and Types Of TurbinesHydel Generation and Types Of Turbines
Hydel Generation and Types Of Turbines
 
Calculation Efficiency of 2GW Hydropower Plant.
Calculation Efficiency of 2GW Hydropower Plant.Calculation Efficiency of 2GW Hydropower Plant.
Calculation Efficiency of 2GW Hydropower Plant.
 
Calculation Efficiency of 5GW Hydropower Plant.
Calculation Efficiency of 5GW Hydropower Plant.Calculation Efficiency of 5GW Hydropower Plant.
Calculation Efficiency of 5GW Hydropower Plant.
 
UNIT 4.pptx
UNIT 4.pptxUNIT 4.pptx
UNIT 4.pptx
 
Hydro Electric Power plant
Hydro Electric Power plantHydro Electric Power plant
Hydro Electric Power plant
 
RES Lecture 18 Hydro.pptx
RES Lecture 18 Hydro.pptxRES Lecture 18 Hydro.pptx
RES Lecture 18 Hydro.pptx
 
Introduction to power plant
Introduction to power plantIntroduction to power plant
Introduction to power plant
 
Hydroelectric powerplant
Hydroelectric powerplantHydroelectric powerplant
Hydroelectric powerplant
 
Hydal power plant
Hydal power plantHydal power plant
Hydal power plant
 
HYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in India
HYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in IndiaHYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in India
HYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in India
 
HYDROELECTRIC POWER
HYDROELECTRIC POWERHYDROELECTRIC POWER
HYDROELECTRIC POWER
 
Hydro power plant
Hydro power plant Hydro power plant
Hydro power plant
 
Hydropower engineering -Hydraulics
Hydropower engineering -HydraulicsHydropower engineering -Hydraulics
Hydropower engineering -Hydraulics
 
904787
904787904787
904787
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
UNIT 4.pptx
UNIT 4.pptxUNIT 4.pptx
UNIT 4.pptx
 

Último

Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024The Digital Insurer
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
Ransomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfRansomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfOverkill Security
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businesspanagenda
 
AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024The Digital Insurer
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...apidays
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsNanddeep Nachan
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoffsammart93
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWERMadyBayot
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FMESafe Software
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...apidays
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxRustici Software
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MIND CTI
 

Último (20)

Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Ransomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfRansomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdf
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectors
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 

Hydro electric power plant lecture

  • 2. Introduction: One of the most widely used renewable source of energy for generating electricity on large scale basis is hydropower The power obtained from river or ocean water is called as hydropower. Hydropower is the renewable source of energy since water is available in large quantities from rain, rivers, and oceans and this is will be available for unlimited time to come. 30% of total power of the world is met by hydro-electric power. Total hydro-potential of the world id 5000 GW.
  • 3.
  • 4. Essential features of Hydro-Electric Power Plant: The essential features of a water power plant are as below: 1. Catchment area. 2. Reservoir. 3. Dam and intake house. 4. water way. 5. Power house. 6. Tail race or outlet water way. 1.Catchment Area. The catchment area of a hydro plant is the whole area behind the dam, draining into a stream or river across which the dam has been built at a suitable place.
  • 5. 2- Water reservoir:  In a reservoir the water collected from the catchment area is stored behind a dam.  Catchment area gets its water from rain and streams.  The level of water surface in the reservoir is called Head water level. Note : Continuous availability of water is a basic necessity for a hydro-electric power plant. 3- Dam :  The purpose of the dam is to store the water and to regulate the out going flow of water.  The dam helps to store all the incoming water. It also helps to increase the head of the water. In order to generate a required quantity of power it is necessary that a sufficient head is available. 5
  • 6. • Dam are classified based on following factors: a) Function b) Shape c) Construction material d) Design a) Based on function the dam may be called as storage dam, diversion dam or detention dam. b) Based on the shape the dam may of trapezoidal section & arch type. c) The materials used for constructing dams are earth, rock pieces, stone masonry. d) According to structural design the dam maybe classified as: i. Gravity dam ii. Arch dam iii. Buttress dam
  • 7. Types of Dam: 1. Masonry Dams. 2. Earth Dams. The masonry dams are of three major classes: a) Gravity dam. b) Buttress dam. c) Arched dam. d) Gravity dam: Resist the pressure of water by its weight. Construction of material used for his dam, is solid masonry or concrete.
  • 8. b) Arch dam: It resist the pressure of water partly due to its weight and partly due to arch action. c) Buttress dam: • Buttress supporting a flat slab. • When cost of reinforced concrete is high such type of dam is selected.
  • 9. Spillway:  Excess accumulation of water endangers the stability of dam construction. Also in order to avoid the over flow of water out of the dam especially during rainy seasons spillways are provided. This prevents the rise of water level in the dam.  Spillways are passages which allows the excess water to flow to a storage area away from the dam. Gate:  A gate is used to regulate or control the flow of water from the dam. Pressure tunnel:  It is a passage that carries water from the reservoir to the surge tank. 7 May 2012 9
  • 10. Surge tank:  A Surge tank is a small reservoir or tank in which the water level rises or falls due to sudden changes in pressure. Purpose of surge tank:  To serve as a supply tank to the turbine when the water in the pipe is accelerated during increased load conditions and as a storage tank when the water is decelerating during reduced load conditions.  To reduce the distance between the free water surface in the dam and the turbine, thereby reducing the water-hammer effect on penstock and also protect the upstream tunnel from high pressure rise. Water-hammer effect : o The water hammer is defined as the change in pressure rapidly above or below normal pressure caused by sudden change in the rate of water flow through the pipe, according to the demand of prime mover i.e. turbine 10
  • 11. 4- Water Ways. Water ways are the passages, through which the water is conveyed to the turbines from the dam. These may include tunnels, canals, flumes, forebays and penstocks and also surge tanks. A forebay is an enlarged passage for drawing the water from the reservoir or the river and giving it to the pipe lines or canals. 7 May 2012 11
  • 13. Number of penstock A hydro Power Plant uses a number of turbine which are to be supplied water through penstock. • To use a single penstock for the whole a plant. • To use on penstock for each turbine separately. • To provide multiple penstock but each penstock supplying water to at least two turbine. Factors for Selecting number of penstocks: • Economy. • Operational safety. • Transportation facilities.
  • 14. 5- Power House. The power house is a building in which the turbines, alternators and the auxiliary plant are housed. Some important items of equipment provided in the power house are as follows: i. Turbines ii. Generators iii. Governors iv. Relief valve for penstock setting v. Gate valve vi. Transformer vii. Switch board equipment and instruments viii. Oil circuit breaker ix. Storage batteries x. Outgoing connections xi. Cranes xii. Shops & offices
  • 15. The surface power house has been broadly divided into three subdivisions which is separated from the intake as mentioned below : (a) Substructure ; (b) Intermediate structure ; (c) Super-structure.
  • 16. Draft tube:  It is connected to the outlet of the turbine.  It allows the turbine to be placed above the tail water level. 6- Tail water level or Tail race: o Tail water level is the water level after the discharge from the turbine. The discharged water is sent to the river, thus the level of the river is the tail water level. Electric generator, Step-up transformer and Pylon :  As the water rushes through the turbine, it spins the turbine shaft, which is coupled to the electric generator. The generator has a rotating electromagnet called a rotor and a stationary part called a stator. The rotor creates a magnetic field that produces an electric charge in the stator. The charge is transmitted as electricity. The step-up transformer increases the voltage of the current coming from the stator. The electricity is distributed through power lines also called as pylon.
  • 17. Classification of hydro-Electric power plant The classification of hydro electric power plant depend on the following factors: 1) Quantity of water: It is following types. i. Run of river plant. ii. Storage plant. iii. Pumped storage. 2) Availability of Head of Water: a) Low head plant. Operating head < 15m. b) Medium head plant. Operating head 15 to 50m. c) High head plants Operating head > 50m.
  • 18. a) Low head plant • Operating head is less than 15m. • Vertical shaft Francis turbine or Kaplan turbine. • Small dam is required.
  • 19. a) Medium head plant • Operating head is less than 15 to 50m. • Francis turbines. • Forebay is provided at the beginning of the penstock.
  • 20. a) High head plant • Operating head exceed 50m. • Pelton turbines. • surge tank is attached to the penstock to reduce water hammer effect on the penstock.
  • 21. Advantages of hydel power plant :  Water is a renewable energy source.  Maintenance and operation charges are very low.  The efficiency of the plant does not change with age.  In addition to power generation, hydro-electric power plants are also useful for flood control, irrigation purposes, fishery and recreation.  Have a longer life(100 to 125 years) as they operate at atmospheric temperature.  Water stored in the hydro-electric power plants can also be used for domestic water supply.  Since hydro-electric power plants run at low speeds(300 to 400 rpm) there is no requirement of special alloy steel construction materials or specialised mechanical maintenance.
  • 22. Disadvantages of hydel power plant :  The initial cost of the plant is very high.  Since they are located far away from the load centre, cost of transmission lines and transmission losses will be more.  During drought season the power production may be reduced or even stopped due to insufficient water in the reservoir.  Water in the reservoir is lost by evaporation.
  • 23. Draft Tube: Reaction turbines must be completely enclosed because a pressure difference exists between the working fluid (water) in the turbine and atmosphere. Therefore, it is necessary to connect the turbine outlet by means of a pipe known as draft tube upto tailrace level. Types of Draft Tubes (1) Conical Draft Tube. This is known as tapered draft tube and used in all reaction turbines where conditions permit. It is preferred for low specific speed and vertical shaft Francis turbine. The maximum cone angle of this draft tube is limited to 8° (a = 4°). The hydraulic efficiency of such type of draft tube is 90%.
  • 24. 2- Elbow Type Draft Tube. The elbow type draft tube is often preferred in most of the power plants, where the setting of vertical draft tube does not permit enough room without excessive cost of excavation. 3- Moody Draft Tube. This draft tube has an advantage that its conical portion at the center reduces the whirl action of water moving with high velocity centre reduces.
  • 25. Hydraulic Turbines Advantages: Simple in construction. Easily controllable. Efficient. Ability to work at peak load. Work on load variation. Start from cold conditions & pick up load at short time. Types of turbines: a) Impulse b) Reaction
  • 26. Impulse Turbine: The passages are not completely filled, water acting on a wheel buckets is at atmospheric pressure and is supplied at few points at the periphery of wheel & kinetic energy is supplied to the wheel. Casing Penstock Nozzle Runner Buckets Needle Valve shaft
  • 27. Reaction Turbine: Water passages are completely filled with water, water acting on wheel vanes is under pressure greater than atmospheric, water enter all around the periphery of wheel and energy is in the form of both pressure & kinetic energy is utilized by the wheel. Essential parts: Spiral casing Guide wheel Runner Draft tube • Horizontal shaft type or vertical shaft type turbine • Low & medium head turbines
  • 28. Direction of flow of water: I. Tangential flow turbine II. Radial flow turbine. III. Axial flow turbine. IV. Mixed flow turbine. Types of turbine Flow direction Kaplan turbine Axial flow Franics Turbine Radial inward or mixed flow Pelton wheel Tangential flow
  • 29. Position of shaft: I. Vertical shaft turbine. II. Horizontal shaft turbine. Head of water: I. High head turbines. II. Medium head turbines. III. Low head turbines. Impulse turbines high head. Reaction turbines low & medium heads.
  • 30.
  • 31. Performance of water turbine: Important parameter for any particular turbine are: • Discharge • Head • Efficiency • Speed • Power The turbine characteristic like unit power, unit speed & unit discharge help in studying the performance of turbines.
  • 32.
  • 33.
  • 34.
  • 35. Specific Speed: The specific speed of a turbine is defined as the speed at which the turbine runs developing one B.H.P. under a head of one meter. The equation for the specific speed of a turbine can be obtained by using the principle of similarity. where D and N are diameter and speed of a turbine and H is the head acting on the turbine. where B is the height of the blade and Vf is the velocity of flow. Substituting the value of D in the above equation. where P is the power developed.
  • 36. Substituting the value of Q in the above equation, we get where C is constant depending upon the type of the turbine. If the turbine develops 1 B.H.P. under one meter head then C = N = N. where Ns is the specific speed as per the definition. Substituting the value of C in the above equation, we get
  • 37.
  • 38.
  • 39.
  • 40. SELECTION OF SITE FOR A HYDRO-ELECTRIC POWER PLANT The following factors should be given careful consideration while selecting a site for a hydro-electric power plant: 1. Water Available. The recorded observation should be taken over a number of years to know within reasonable, limits the maximum and minimum variations from the average discharge. the river flow data should be based on daily, weekly, monthly and yearly flow ever a number of years. Then the curves or graphs can be plotted between tile river flow and time. These are known as hygrographs and flow duration curves.
  • 41. 2. Water-Storage. The output of a hydropower plant is not uniform due to wide variations of rain fall. To have a uniform power output, a water storage is needed so that excess flow at certain times may be stored to make it available at the times of low flow. To select the site of the Dam, careful study should be made of the geology and topography of the catchment area to see if the natural foundations could be found and put to the best use. 3. Head of Water. The level of water in the reservoir for a proposed plant should always be within limits throughout the year.
  • 42. 4. Distance from Load Center. Most of the time the electric power generated in a hydro-electric power plant has to be used some considerable distance from the site of plant. For this reason, to be economical on transmission of electric power, the routes and the distances should be carefully considered since the cost of erection of transmission lines and their maintenance will depend upon the route selected. 5. Access to Site. It is always a desirable factor to have a good access to the site of the plant. This factor is very important if the electric power generated is to be utilized at or near the plant site. The transport facilities must also be given due consideration.
  • 43. Hydrology • It is natural science that deal with the distribution of water on land beneath the surface of earth. • It deal with the solid, liquid & vapour forms of water. Hydrologic cycle: The various processes involved in the transfer of moisture from the sea to the land and back to the sea again constitute which is called hydrologic cycle. Hydrologic eq. is expressed as follows: P=R+E Where, P = perspiration R = Run-off E = Evaporation.
  • 44. Perspiration: It includes all the water that falls from atm. To the earth surface. Mostly perspiration is of two types. Liquid perspiration (rainfall) Solid perspiration (Snow, Hail storm) Run-off: It is that portion of the perspiration which makes its way towards stream, lakes or ocean. Run-off occur only if the rate of perspiration exceed the rate at which water infiltrate into the soil & after depression small and large on the soil surface get filled in the water. Evaporation: Transfer of water from liquid to vapour state Transpiration: Process by which water is released to the atmosphere by the plant.
  • 45. Assignment • Topics: 6.37 & 6.38(6.38.1, 6.38.2, 6.38.3, 6.38.4) • Examples: • 6.1 to 6.13, 6.15 to 6.20.