SlideShare una empresa de Scribd logo
1 de 36
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
Topic:
Process Safety
Management in
Design, Construction
& Commissioning
By:
Lalit K. Vijh
ED- Technical
Engineers India Limited
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
MAJOR HAZARDS IN OIL INDUSTRY
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
SAN JUANICO DISASTER PEMEX, MEXICO, 1984
BEFORE AFTER
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
SAN JUANICO DISASTER, PEMEX, MEXICO, 1984
8” Pipe rupture occurred near the sphere
The Control Room operator tried to identify the cause of pressure fall but without success.
The release of LPG occurred for more than 5-10 minute
The gas cloud grew to cover a large area and ignited from a ignition by ground flare.
The VCE severely damaged the tank farm and resulted in LPG leak from other damaged tanks
Just 4 minutes later first tank underwent BLEVE.
Over the next hour, 12 separate BLEVE explosions were recorded.
The two largest BLEVE’s(from 2400 m3 spherical tanks) registered 5.0 seismic reading on R.S
The explosions destroyed the local town of San Juan Ixhuatepec.
Approximately 500-600 people killed and 5000-7000 others suffering severe burns.
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
LESSONS LEARNED - SAN JUANICO DISASTER
Sitting of Major Hazard Installation
• The high death toll occurred because the housing was too near to the plant. At the time the plant was constructed the area
was underdeveloped, but over the years the built-up area had gradually crept up to the site.
Layout and Protection of large LPG Storages
• The total destruction of the facility occurred because there was a failure of the overall system of protection, which includes
layout, emergency isolation and water spray systems.
Gas Detection and Emergency Isolation
• One feature which might have averted the disaster is more effective gas detection and emergency isolation. The plant had
no gas detector system and probably as a consequence, emergency isolation was too late.
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
LPG FIRE AT VALERO, MCKEE REFINERY, 2007
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
LPG FIRE AT VALERO, MCKEE REFINERY
The propane release was likely caused by the freeze-related failure of high-pressure piping at a
control station that had not been in service for approximately 15 years.
The lack of remote isolation significantly increased the duration and size of the fire, resulting in
extensive damage to the Propane Deasphalting Unit, the main pipe rack, and an adjacent process
unit.
Flame impingement on a non-fireproofed structural support caused a pipe rack to
collapse, significantly increasing the size and duration of the fire, and led to the evacuation and
extended shutdown of the refinery.
The exposure of three one-ton chlorine containers to radiant heating from the fire led to the release
of approximately 2.5 tons of highly toxic chlorine.
A butane storage sphere was exposed to radiant heating that blistered its paint. The manual firewater
deluge valve for the butane sphere was located too close to the PDA unit and could not be opened
during the fire.
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
JAIPUR FIRE ACCIDENT 2009
• 11 Dead
• Loss of ~ Rs.280 Crores
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
EXPLOSION IN VENEZUELA'S LARGEST OIL REFINERY ON 25-08-2012
• 48 Dead (official figure)
• Initial Report indicate poor maintenance
as chief cause
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
Source : Harry J. Toups LSU Department of Chemical Engineering ,SACHE 2003 Workshop
Mechanical
Operator Error
Unknown
Process Upsets
Natural Hazards
Design
Sabotage & Arson
0 10 20 30 40 50
44 %
22 %
12 %
11 %
5 %
5 %
1 %
CAUSE OF ACCIDENTS IN OIL INDUSTRY
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
APPROACH FOR SAFETY IN PLANT DESIGN?
Eliminate or minimize hazards rather than control hazards
Don’t wait for a major accident to identify need to improve major hazard management.
Need to learn lessons from accidents but don’t rely on this approach
Manage risks via Foresight rather than Hindsight i.e. be proactive rather than reactive.
More a philosophy and way of thinking than a specific set of tools and methods applicable at all levels of design and
operation from conceptual design to plant operations
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
INHERENT PASSIVE
ACTIVE PROCEDURAL
PROCESS SAFETY STRATEGIES
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
• Eliminate or reduce the hazard by changing to a process or
materials which are non-hazardous or less hazardousINHERENT
• Minimize hazard using process or equipment design features
which reduce frequency or consequence without the active
functioning of any device
PASSIVE
PROCESS SAFETY STRATEGIES
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
• Controls, safety interlocks, automatic shut down systems
• Multiple active elements : Sensors, Logic device, Control
element
ACTIVE
• Standard operating procedures, safety rules, emergency
response procedures, trainingPROCEDURAL
PROCESS SAFETY STRATEGIES
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
HSE during Project Execution
• Environment Impact Assessment
• Environmental Baseline Survey
• Process Hazard Review
• Hazard Identification (HAZID)
Project Conceptualization Stage
• P&ID Review For Operational Safety
• HSE Plan & HSE Philosophy
• HAZOP & SIL Studies
• Fire, Explosion & Dispersion Analysis/ Consequence Analysis
• HSE Action Tracking Register & PHSER
Process Design Stage
• Plot Plan Review
• Plot Plan Review Through Plot Plan Risk Review Committee
• Quantitative Risk Assessment
• Detailed HAZOP & HAZOP Close Out Report
• Fire & Gas Safety System Review
• Cause & Effects/Safety Charts Review
• Preparation of HSE Dossier & PHSER
• Safety Manual & Operating Manual Preparation
Engineering Stage
• Safety Guidelines to Contractors
• Safety Monitoring through Dedicated Safety Engineers
• Safety Meetings
• Safety Performance Evaluation
Construction Stage
• Punch List Preparation
• Startup Formats
• Pre Startup Safety Audit
Commissioning Stage
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
CONCEPTUAL DESIGN (Coarse HAZOP, What-if, Ranking)
SITE SELECTION (Rapid Risk Analysis, Environmental Impact Assessment)
PROCESS DESIGN (HAZOP, Safety Review, SIL)
ENGINEERING (Qualitative Risk Analysis, Plot Plan Review)
START-UP (Safety Audit, Emergency Plan)
RISK CONTROL DURING PROJECT STAGES
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
SAFETY AT PLANNING STAGE
Prevention of accidents should be the goal
Design options (use of chemicals, technology etc)
Layout review (various locations and configurations)
Hazard Identification (HAZID)
Environment Impact Assessment
Environmental Baseline Survey
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
HSE DURING ENGINEERING
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
SAFETY AT DESIGN STAGE
Adequate Design suitable for operations:
HAZID (Hazard Identification)
HAZOP (Hazard and Operability Study)
HSEIA (Health Safety Environment Impact Assessment)
• COMAH (Control of Major Accidental Hazard), OHRA (Occupational Health Risk Assessment), EIA (Environment
Impact Assessment)
• HSECES (HSE Critical Equipment System), SCE/PS (Safety Critical Elements / Performance Standards)
• Fire Safety Assessment and Dispersion Analysis, QRA (Quantitative Risk Assessment)
• Noise Study, EERA (Escape, Evacuation and Rescue Analysis), Waste Management Plan
SIL (Safety Integrity Level)
ALARP Study (As Low As Reasonably Practicable)
Active and Passive Fire Protection System
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
TYPICAL PROCESS SAFETY CODES & STANDARDS USED IN DESIGN
Some of the standards widely used by designers and operating companies are:
• American Petroleum Institute (API)
• American Society of Mechanical Engineers (ASME)
• National Fire Protection Association (NFPA)
• Oil Industry Safety Directorate (OISD) / Local Standards
• British Standard Institution (BSI)
• International Standard Organization (ISO)
• Static & Mobile Pressure Vessel (SMPV) Rules
• Petroleum Rules
• IBR regulation
Process Design and Hydrocarbon Services are complying to various OISD Standards
• OISD-STD-106 (Pressure Relief & Disposal System)
• OISD-STD-108 (Recommended Practices on Oil Storage and Handling)
• OISD-STD-116/117 (for Fire Protection)
• OISD-STD-118 (Layouts for Oil and Gas Installations)
• OISD-STD-144 (LPG Installations)
• OISD-STD-150 (for LPG Mounded Storage Facility)
• OISD-STD-152 (Safety instrumentation for process system in HC industry)
• OISD-STD-163 (Process Control Room Safety)
• OISD-STD-164 (Fire Proofing in Oil & Gas Industry)
• OISD-STD-194 (Standard for Storage And Handling of LNG)
• OISD-STD-197 (Guidelines for EIA)
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
PROCESS DESIGN PHILOSOPHY
Selection of proper Material of Construction (MOC)
Selection of proper piping class, rating.
Selection of proper design conditions (Pressure, Temperature)
Selection of hold up volume
Conformity to various codes/ standards
Adherence to good design practice
Feed Back from previous jobs, Client, Engineering, Commissioning.
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
PROCESS SAFETY PHILOSOPHY - LOPA
PROCESS
MITIGATION SYSTEM
OFFSITEEMERGENCY RESPONSE
ONSITE EMERGENCY RESPONSE
PREVENTION SYSTEM
CONTROL & MONITORING
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
PROCESS SAFETY PHILOSOPHY
Pressure Venting provisions shall be in accordance with API RP 520 (Part 1 &2), API RP 521 Standards
Flare system is provided to safely dispose of the materials released from PSV in case of any malfunction of system
• Controlling case for refinery or petrochemical complexes are usually cooling water or power failure. Whenever there is
one cooling water system, cooling water failure loads for various units are added to calculate total flare load of the
complex.
• For a large complex with very high flare load for cooling water failure case, complex may be segregated in to two or
more cooling water systems and then flare load of one (controlling ) cooling water system may be considered for
further design
• Temperature profile of flare header (ISBL & OSBL) is essential in having optimum provision of expansion loops in
flare headers
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
PROCESS SAFETY PHILOSOPHY : LAYOUT
Key considerations/ safety features for layout
• Separation of hazardous areas from non-hazardous areas
• Safe separation distances
• Adequate escape routes, safe access for operation and maintenance of equipment
• Main ignition sources should be grouped and located upstream prevailing wind.
• Emergency response teams to have clear access to all fire fighting equipment.
• Cable trays, pipe racks and escape routes shall be positioned such that risk of damage by pool fire or explosions is
minimized.
• Optimize availability of emergency services and main safety equipment under all foreseeable events.
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
Process Safety PhilosophyHazardous Area Classification
• The hazardous area classification shall be performed in accordance with IP Model Code of Safe Practice Part 15.
• Based on the above code various areas shall be classified into zones and Electrical appliances shall be selected suitably.
The Emergency Shutdown system
• The Emergency Shutdown system shall be designed to fail-safe so that, in the event of loss of any of the controls to the
system, the shutdown valves shall fail closed and the blowdown valves fail open.
• The Emergency Shutdown system shall be reviewed in accordance with IEC 61508.
PRPROCESS SAFETY PHILOSOPHY
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
Redundancy
Voting systems
Philosophy of alarms and trips
Emergency depressurization
Emergency shut down (ESD)
Safety valve
HIPPS – High Integrity Pressure Protection System
PROCESS SAFETY PHILOSOPHY - Instrumentation
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
FIRE CONTROL AND MITIGATION– F&G Detection System
• The required functions/actions on fire and/or gas detection shall be developed during detail design
phase.
• The Fire and Gas Detection systems shall be designed and installed in accordance with NFPA and OISD
Standards.
• Detector locations shall be determined by means of case by case examination of the facilities layout and
may be placed either peripherally around the facilities, at suitable intervals or placed to cover areas with
a leak potential, or both.
The fire and gas (F&G) detection system is to provide an early
warning to personnel of the existence of a potentially dangerous
situation and to enable automatic initiation of remedial actions
• Gas detectors – H2, HC, H2S, Cl
• Fire detectors –Flame, Heat, Smoke
F&G Field Devices
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
• The main objective of active fire protection is to:
• Provide cooling (Deluge System, Sprinkling System)
• Control the fire (ie., prevent it from spreading)
• Extinguishment of the fire incident (Fire Extinguishers, Foam System)
Active Fire Protection : A “dormant” system that needs to be activated in
order to perform its function.
• Fire Proofing/ Passive fire protection is a barrier or safeguard which provides protection against the
heat from a fire without additional intervention i.e. it performs its function without relying on
activation.
Passive Fire Protection : A system that performs its function without
relying on the requirement of activation
FIRE CONTROL AND MITIGATION – ACTIVE AND PASSIVE FIRE PROTECTION
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
HSE DURING CONSTRUCTION
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
SAFETY AT CONSTRUCTION STAGE
Setting of Project specific HSE objective and targets
Implementation of Project specific HSE Plan
Preparation and Implementation of ERP
Project HSE Review (PHSER for Construction)
Dedicated Warehouse /Procedures for storage of Materials and Hazardous substances
HSE Training, Inspection & audit
HIRA & Legal register and ensuring its compliance
Pre- Deployment Inspection and Certification for Mobilization of suitable and safe equipment
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
Tools for Monitoring/Implementation of HSE at Sites
• HSE Specification
• HSE Plan
• HSE Procedures
• HSE Induction
• Hazard Identification & Risk Analysis (HIRA)/ Job
Safety Analysis (JSA)
• Tool Box Talks
• Mock Drills (Fire, Electrocution , Fall from height )
• HSE Inspection/ Walk-through
• HSE Meetings
• Road Safety & Movement of vehicles
• Fitness certificates for all Lifting tools & Tackles, Cranes
• HSE Permits Viz. Scaffolds, Confined space, Height
work, Excavation
• HSE Awareness/ Motivational Programs
• HSE Reporting including LTIFR, FAR
• Reporting of Near Miss Accidents & Corrective Actions
• Accident Investigations & Recommendations
• Analysis of Leading &Trailing Indicators
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
• Legal compliance
• HSE Management System & Competence
• HSE Performance
Pre qualification &Selection
• General Terms & Condition
• Code of Conduct
Contractor Preparation
• HSE Plan & Organization
• Competence of Personnel
• Signing of code of conduct
Contract Award
• Kick of Meeting
• Medical Check up
Pre commencement & Mobilization
• HSE Training as per approved HSE Training MatrixContractors Orientation & Training
• Periodic evaluation
• HSE Review meeting
Managing the Contractors
• HSE Performance Records
Post Contract Evaluation
CONTRACTOR’s SAFETY MANAGEMENT PROCESS
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
HSE DURING COMMISSIONING
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
SAFETY AT PRECOMMISSIONING & COMMISSIONING AND HANDOVER
SIMOPS - Simultaneous Operation study for Planning and coordination
Multilayer Safety checks to meet Aggressive Schedule
Multi disciplinary trained manpower
Manuals, SOP & Checklists
Authorization & documentation for Changes, Bypass etc
Pre Start up Safety Review
HSE Action Tracking Register/ Formal HSE Close out Report
Project HSE Review (PHSER for Pre- Commissioning)
Lesson Learnt
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
SUMMARY
Safety in design is of paramount importance for process safety management
Goal should be to prevent rather than control & mitigate hazards
Select inherently safe processes and Incorporate adequate active & passive safety features in design minimizing
dependence on human intervention
Select Process specifications/ design conditions, Materials to reflect normal as well as start up/ transient conditions
Ensure strict adherence to safety & design standard & codes during design/engineering/construction & commissioning
Carryout Safety Studies like RRA/ QRA, HAZID, HAZOP, SIL etc to ensure adequate safety features including control &
mitigation are built in design & to finalize location/ layout of facilities
Technical Session # 3A
Topic : Process Safety Management in Design , Construction & Commissioning
THANK YOU

Más contenido relacionado

La actualidad más candente

Introduction to PSM Online Interactive Training
Introduction to PSM Online Interactive TrainingIntroduction to PSM Online Interactive Training
Introduction to PSM Online Interactive TrainingJohn Kingsley
 
Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)TheSafetyGuru
 
SPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT SlidesSPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT Slidesidell bryan
 
Seminar- Process Safety Management_.pptx
Seminar- Process Safety Management_.pptxSeminar- Process Safety Management_.pptx
Seminar- Process Safety Management_.pptxMoonJ3
 
_Process_Safety_Management
_Process_Safety_Management_Process_Safety_Management
_Process_Safety_ManagementEssam Osmaan
 
Quantative-Risk assessment-Hazop-Study
Quantative-Risk assessment-Hazop-StudyQuantative-Risk assessment-Hazop-Study
Quantative-Risk assessment-Hazop-StudyMassimo Talia
 
MIQA, An Ultimate Element of PSM Implementation
MIQA, An Ultimate Element of PSM ImplementationMIQA, An Ultimate Element of PSM Implementation
MIQA, An Ultimate Element of PSM ImplementationMAHENDRA KUMAR RASTOGI
 
PSM Process Safety Management.pdf
PSM Process Safety Management.pdfPSM Process Safety Management.pdf
PSM Process Safety Management.pdfssuser2fc67e
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputGaurav Singh Rajput
 
The business case for process safety final ppt
The business case for process safety final pptThe business case for process safety final ppt
The business case for process safety final pptorosghe
 
Bow Tie methodology for Operational Safety & Risk Management
Bow Tie methodology for Operational Safety & Risk ManagementBow Tie methodology for Operational Safety & Risk Management
Bow Tie methodology for Operational Safety & Risk ManagementArthurGroot
 
Process Hazard Analysis
Process Hazard AnalysisProcess Hazard Analysis
Process Hazard AnalysisNGE
 

La actualidad más candente (20)

Introduction to PSM Online Interactive Training
Introduction to PSM Online Interactive TrainingIntroduction to PSM Online Interactive Training
Introduction to PSM Online Interactive Training
 
Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)
 
SPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT SlidesSPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT Slides
 
14 Tips for Process Safety Management
14 Tips for Process Safety Management14 Tips for Process Safety Management
14 Tips for Process Safety Management
 
HAZOP and QRA.pptx
HAZOP and QRA.pptxHAZOP and QRA.pptx
HAZOP and QRA.pptx
 
Seminar- Process Safety Management_.pptx
Seminar- Process Safety Management_.pptxSeminar- Process Safety Management_.pptx
Seminar- Process Safety Management_.pptx
 
_Process_Safety_Management
_Process_Safety_Management_Process_Safety_Management
_Process_Safety_Management
 
Quantative-Risk assessment-Hazop-Study
Quantative-Risk assessment-Hazop-StudyQuantative-Risk assessment-Hazop-Study
Quantative-Risk assessment-Hazop-Study
 
MIQA, An Ultimate Element of PSM Implementation
MIQA, An Ultimate Element of PSM ImplementationMIQA, An Ultimate Element of PSM Implementation
MIQA, An Ultimate Element of PSM Implementation
 
Hazop analysis
Hazop analysisHazop analysis
Hazop analysis
 
PSM Process Safety Management.pdf
PSM Process Safety Management.pdfPSM Process Safety Management.pdf
PSM Process Safety Management.pdf
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
 
HAZOP.PPT
HAZOP.PPTHAZOP.PPT
HAZOP.PPT
 
The business case for process safety final ppt
The business case for process safety final pptThe business case for process safety final ppt
The business case for process safety final ppt
 
Hazop analysis complete report
Hazop analysis complete reportHazop analysis complete report
Hazop analysis complete report
 
management of change
management of changemanagement of change
management of change
 
Bow Tie methodology for Operational Safety & Risk Management
Bow Tie methodology for Operational Safety & Risk ManagementBow Tie methodology for Operational Safety & Risk Management
Bow Tie methodology for Operational Safety & Risk Management
 
Vda process auditing
Vda process auditingVda process auditing
Vda process auditing
 
Pressure Relief Systems
Pressure Relief Systems Pressure Relief Systems
Pressure Relief Systems
 
Process Hazard Analysis
Process Hazard AnalysisProcess Hazard Analysis
Process Hazard Analysis
 

Similar a Process Safety Management in Design, Construction & Commissioning | Lalit K. Vijh ED- Technical Engineers India Limited

GW Presentation for Horn Mountain.pdf
GW Presentation for Horn Mountain.pdfGW Presentation for Horn Mountain.pdf
GW Presentation for Horn Mountain.pdfCanadianHegemony
 
Evan Gritman Lewis
Evan Gritman LewisEvan Gritman Lewis
Evan Gritman LewisEvan Lewis
 
Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016
Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016
Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016John Newquist
 
Mes presentation subsea reliability
Mes presentation  subsea reliability  Mes presentation  subsea reliability
Mes presentation subsea reliability Changiz Rezvani
 
Mes presentation subsea reliability
Mes presentation subsea reliability  Mes presentation subsea reliability
Mes presentation subsea reliability Changiz Rezvani
 
Mes presentation subsea reliability changiz
Mes presentation  subsea reliability changizMes presentation  subsea reliability changiz
Mes presentation subsea reliability changizChangiz Rezvani
 
Introduction to Process Flares
Introduction to Process FlaresIntroduction to Process Flares
Introduction to Process FlaresKarl Kolmetz
 
Design basis - PROCESS DESIGN FUNDAMENTALS
Design basis  - PROCESS DESIGN FUNDAMENTALSDesign basis  - PROCESS DESIGN FUNDAMENTALS
Design basis - PROCESS DESIGN FUNDAMENTALSiFluids Engineering
 
Design basis - PROCESS DESIGN FUNDAMENTALS
Design basis  - PROCESS DESIGN FUNDAMENTALSDesign basis  - PROCESS DESIGN FUNDAMENTALS
Design basis - PROCESS DESIGN FUNDAMENTALSiFluids Engineering
 
Jurg hauptli resume
Jurg hauptli resumeJurg hauptli resume
Jurg hauptli resumeJurg Hauptli
 
FDC Catalog (English)
FDC Catalog (English)FDC Catalog (English)
FDC Catalog (English)jehsan
 

Similar a Process Safety Management in Design, Construction & Commissioning | Lalit K. Vijh ED- Technical Engineers India Limited (20)

GW Presentation for Horn Mountain.pdf
GW Presentation for Horn Mountain.pdfGW Presentation for Horn Mountain.pdf
GW Presentation for Horn Mountain.pdf
 
Presentation_HealthWay
Presentation_HealthWayPresentation_HealthWay
Presentation_HealthWay
 
COMPL OF WORKS1
COMPL OF WORKS1COMPL OF WORKS1
COMPL OF WORKS1
 
Evan Gritman Lewis
Evan Gritman LewisEvan Gritman Lewis
Evan Gritman Lewis
 
Safety Concepts of Plant Design
Safety Concepts of Plant DesignSafety Concepts of Plant Design
Safety Concepts of Plant Design
 
Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016
Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016
Discussing osha 1910 106 nfpa 30 and recent fire incidents of 2015 2016
 
lecture 0.pdf
lecture 0.pdflecture 0.pdf
lecture 0.pdf
 
2009 Face Conference Energy Le Moine
2009 Face Conference Energy Le Moine2009 Face Conference Energy Le Moine
2009 Face Conference Energy Le Moine
 
Mes presentation subsea reliability
Mes presentation  subsea reliability  Mes presentation  subsea reliability
Mes presentation subsea reliability
 
Mes presentation subsea reliability
Mes presentation subsea reliability  Mes presentation subsea reliability
Mes presentation subsea reliability
 
Mes presentation subsea reliability changiz
Mes presentation  subsea reliability changizMes presentation  subsea reliability changiz
Mes presentation subsea reliability changiz
 
Introduction to Process Flares
Introduction to Process FlaresIntroduction to Process Flares
Introduction to Process Flares
 
BK2014
BK2014BK2014
BK2014
 
Training program for_urea_engineers_july_by ukh
Training program for_urea_engineers_july_by ukhTraining program for_urea_engineers_july_by ukh
Training program for_urea_engineers_july_by ukh
 
Dermarkar
DermarkarDermarkar
Dermarkar
 
Design basis - PROCESS DESIGN FUNDAMENTALS
Design basis  - PROCESS DESIGN FUNDAMENTALSDesign basis  - PROCESS DESIGN FUNDAMENTALS
Design basis - PROCESS DESIGN FUNDAMENTALS
 
Design basis - PROCESS DESIGN FUNDAMENTALS
Design basis  - PROCESS DESIGN FUNDAMENTALSDesign basis  - PROCESS DESIGN FUNDAMENTALS
Design basis - PROCESS DESIGN FUNDAMENTALS
 
Jurg hauptli resume
Jurg hauptli resumeJurg hauptli resume
Jurg hauptli resume
 
Compact Spring Supports Webinar
Compact Spring Supports WebinarCompact Spring Supports Webinar
Compact Spring Supports Webinar
 
FDC Catalog (English)
FDC Catalog (English)FDC Catalog (English)
FDC Catalog (English)
 

Más de Cairn India Limited

Cairn India | News Article: Upstream - Mr Elango P
Cairn India | News Article: Upstream -  Mr Elango P  Cairn India | News Article: Upstream -  Mr Elango P
Cairn India | News Article: Upstream - Mr Elango P Cairn India Limited
 
Cairn India | Sustainability Report 2013
Cairn India | Sustainability Report 2013Cairn India | Sustainability Report 2013
Cairn India | Sustainability Report 2013Cairn India Limited
 
Cairn India | Q2 Results | FY 2013-14
Cairn India | Q2 Results | FY 2013-14 Cairn India | Q2 Results | FY 2013-14
Cairn India | Q2 Results | FY 2013-14 Cairn India Limited
 
Cairn India - Corporate Presentation - September 2013
Cairn India - Corporate Presentation - September 2013Cairn India - Corporate Presentation - September 2013
Cairn India - Corporate Presentation - September 2013Cairn India Limited
 
Occupational health Strategy & Planning: Dr. Ramnik Parekh
Occupational health Strategy & Planning: Dr. Ramnik ParekhOccupational health Strategy & Planning: Dr. Ramnik Parekh
Occupational health Strategy & Planning: Dr. Ramnik ParekhCairn India Limited
 
Occupational Health & Safety in India - Framework and Challenges | Mr. Anup C...
Occupational Health & Safety in India - Framework and Challenges | Mr. Anup C...Occupational Health & Safety in India - Framework and Challenges | Mr. Anup C...
Occupational Health & Safety in India - Framework and Challenges | Mr. Anup C...Cairn India Limited
 
HEAT STRESS PREVENTION – A CASE STUDY | Dr. Divyang Shah, – Occupational Heal...
HEAT STRESS PREVENTION – A CASE STUDY | Dr. Divyang Shah, – Occupational Heal...HEAT STRESS PREVENTION – A CASE STUDY | Dr. Divyang Shah, – Occupational Heal...
HEAT STRESS PREVENTION – A CASE STUDY | Dr. Divyang Shah, – Occupational Heal...Cairn India Limited
 
North Sea Emergency Response Preparedness 25 Years On | Ms. Claire Forbes, Re...
North Sea Emergency Response Preparedness 25 Years On | Ms. Claire Forbes, Re...North Sea Emergency Response Preparedness 25 Years On | Ms. Claire Forbes, Re...
North Sea Emergency Response Preparedness 25 Years On | Ms. Claire Forbes, Re...Cairn India Limited
 
Organisational Resilience following a Major Disaster | Mr. David G. Broadbent...
Organisational Resilience following a Major Disaster | Mr. David G. Broadbent...Organisational Resilience following a Major Disaster | Mr. David G. Broadbent...
Organisational Resilience following a Major Disaster | Mr. David G. Broadbent...Cairn India Limited
 
Importance of Data Driven Decision Making in Enterprise Energy Management | D...
Importance of Data Driven Decision Making in Enterprise Energy Management | D...Importance of Data Driven Decision Making in Enterprise Energy Management | D...
Importance of Data Driven Decision Making in Enterprise Energy Management | D...Cairn India Limited
 
Co-processing in cement kiln Concepts and in Oil and Gas Sector | John Jones,...
Co-processing in cement kiln Concepts and in Oil and Gas Sector | John Jones,...Co-processing in cement kiln Concepts and in Oil and Gas Sector | John Jones,...
Co-processing in cement kiln Concepts and in Oil and Gas Sector | John Jones,...Cairn India Limited
 
Water Usage Optimization & Management for Hydraulic Fracturing | Dr. Chris Fr...
Water Usage Optimization & Management for Hydraulic Fracturing | Dr. Chris Fr...Water Usage Optimization & Management for Hydraulic Fracturing | Dr. Chris Fr...
Water Usage Optimization & Management for Hydraulic Fracturing | Dr. Chris Fr...Cairn India Limited
 
Health, Safety and Environment Aspects of Carbon dioxide Sequestration | By: ...
Health, Safety and Environment Aspects of Carbon dioxide Sequestration | By: ...Health, Safety and Environment Aspects of Carbon dioxide Sequestration | By: ...
Health, Safety and Environment Aspects of Carbon dioxide Sequestration | By: ...Cairn India Limited
 
Lessons from Texas City | Michael P. Broadribb, Baker Engineering & Risk Cons...
Lessons from Texas City | Michael P. Broadribb, Baker Engineering & Risk Cons...Lessons from Texas City | Michael P. Broadribb, Baker Engineering & Risk Cons...
Lessons from Texas City | Michael P. Broadribb, Baker Engineering & Risk Cons...Cairn India Limited
 
Improving Health, Safety and Environment Performance Analysis | Mark Weitner,...
Improving Health, Safety and Environment Performance Analysis | Mark Weitner,...Improving Health, Safety and Environment Performance Analysis | Mark Weitner,...
Improving Health, Safety and Environment Performance Analysis | Mark Weitner,...Cairn India Limited
 
The Continuing Challenges of Balancing Process Safety Management and Personal...
The Continuing Challenges of Balancing Process Safety Management and Personal...The Continuing Challenges of Balancing Process Safety Management and Personal...
The Continuing Challenges of Balancing Process Safety Management and Personal...Cairn India Limited
 
Competency Development – a paradigm shift | Alastair Shakeshaft, Director, B...
Competency Development  – a paradigm shift | Alastair Shakeshaft, Director, B...Competency Development  – a paradigm shift | Alastair Shakeshaft, Director, B...
Competency Development – a paradigm shift | Alastair Shakeshaft, Director, B...Cairn India Limited
 
Building the competence of your workforce | Teresa Budworth, Chief Executive,...
Building the competence of your workforce | Teresa Budworth, Chief Executive,...Building the competence of your workforce | Teresa Budworth, Chief Executive,...
Building the competence of your workforce | Teresa Budworth, Chief Executive,...Cairn India Limited
 
Sustainability in Cement Industry | Rakesh Bhargava, Chief Climate & Sustaina...
Sustainability in Cement Industry | Rakesh Bhargava, Chief Climate & Sustaina...Sustainability in Cement Industry | Rakesh Bhargava, Chief Climate & Sustaina...
Sustainability in Cement Industry | Rakesh Bhargava, Chief Climate & Sustaina...Cairn India Limited
 
Inclusive Growth – Is Sustainability the Answer ? | Dr. Yogendra Saxena, Tata...
Inclusive Growth – Is Sustainability the Answer ? | Dr. Yogendra Saxena, Tata...Inclusive Growth – Is Sustainability the Answer ? | Dr. Yogendra Saxena, Tata...
Inclusive Growth – Is Sustainability the Answer ? | Dr. Yogendra Saxena, Tata...Cairn India Limited
 

Más de Cairn India Limited (20)

Cairn India | News Article: Upstream - Mr Elango P
Cairn India | News Article: Upstream -  Mr Elango P  Cairn India | News Article: Upstream -  Mr Elango P
Cairn India | News Article: Upstream - Mr Elango P
 
Cairn India | Sustainability Report 2013
Cairn India | Sustainability Report 2013Cairn India | Sustainability Report 2013
Cairn India | Sustainability Report 2013
 
Cairn India | Q2 Results | FY 2013-14
Cairn India | Q2 Results | FY 2013-14 Cairn India | Q2 Results | FY 2013-14
Cairn India | Q2 Results | FY 2013-14
 
Cairn India - Corporate Presentation - September 2013
Cairn India - Corporate Presentation - September 2013Cairn India - Corporate Presentation - September 2013
Cairn India - Corporate Presentation - September 2013
 
Occupational health Strategy & Planning: Dr. Ramnik Parekh
Occupational health Strategy & Planning: Dr. Ramnik ParekhOccupational health Strategy & Planning: Dr. Ramnik Parekh
Occupational health Strategy & Planning: Dr. Ramnik Parekh
 
Occupational Health & Safety in India - Framework and Challenges | Mr. Anup C...
Occupational Health & Safety in India - Framework and Challenges | Mr. Anup C...Occupational Health & Safety in India - Framework and Challenges | Mr. Anup C...
Occupational Health & Safety in India - Framework and Challenges | Mr. Anup C...
 
HEAT STRESS PREVENTION – A CASE STUDY | Dr. Divyang Shah, – Occupational Heal...
HEAT STRESS PREVENTION – A CASE STUDY | Dr. Divyang Shah, – Occupational Heal...HEAT STRESS PREVENTION – A CASE STUDY | Dr. Divyang Shah, – Occupational Heal...
HEAT STRESS PREVENTION – A CASE STUDY | Dr. Divyang Shah, – Occupational Heal...
 
North Sea Emergency Response Preparedness 25 Years On | Ms. Claire Forbes, Re...
North Sea Emergency Response Preparedness 25 Years On | Ms. Claire Forbes, Re...North Sea Emergency Response Preparedness 25 Years On | Ms. Claire Forbes, Re...
North Sea Emergency Response Preparedness 25 Years On | Ms. Claire Forbes, Re...
 
Organisational Resilience following a Major Disaster | Mr. David G. Broadbent...
Organisational Resilience following a Major Disaster | Mr. David G. Broadbent...Organisational Resilience following a Major Disaster | Mr. David G. Broadbent...
Organisational Resilience following a Major Disaster | Mr. David G. Broadbent...
 
Importance of Data Driven Decision Making in Enterprise Energy Management | D...
Importance of Data Driven Decision Making in Enterprise Energy Management | D...Importance of Data Driven Decision Making in Enterprise Energy Management | D...
Importance of Data Driven Decision Making in Enterprise Energy Management | D...
 
Co-processing in cement kiln Concepts and in Oil and Gas Sector | John Jones,...
Co-processing in cement kiln Concepts and in Oil and Gas Sector | John Jones,...Co-processing in cement kiln Concepts and in Oil and Gas Sector | John Jones,...
Co-processing in cement kiln Concepts and in Oil and Gas Sector | John Jones,...
 
Water Usage Optimization & Management for Hydraulic Fracturing | Dr. Chris Fr...
Water Usage Optimization & Management for Hydraulic Fracturing | Dr. Chris Fr...Water Usage Optimization & Management for Hydraulic Fracturing | Dr. Chris Fr...
Water Usage Optimization & Management for Hydraulic Fracturing | Dr. Chris Fr...
 
Health, Safety and Environment Aspects of Carbon dioxide Sequestration | By: ...
Health, Safety and Environment Aspects of Carbon dioxide Sequestration | By: ...Health, Safety and Environment Aspects of Carbon dioxide Sequestration | By: ...
Health, Safety and Environment Aspects of Carbon dioxide Sequestration | By: ...
 
Lessons from Texas City | Michael P. Broadribb, Baker Engineering & Risk Cons...
Lessons from Texas City | Michael P. Broadribb, Baker Engineering & Risk Cons...Lessons from Texas City | Michael P. Broadribb, Baker Engineering & Risk Cons...
Lessons from Texas City | Michael P. Broadribb, Baker Engineering & Risk Cons...
 
Improving Health, Safety and Environment Performance Analysis | Mark Weitner,...
Improving Health, Safety and Environment Performance Analysis | Mark Weitner,...Improving Health, Safety and Environment Performance Analysis | Mark Weitner,...
Improving Health, Safety and Environment Performance Analysis | Mark Weitner,...
 
The Continuing Challenges of Balancing Process Safety Management and Personal...
The Continuing Challenges of Balancing Process Safety Management and Personal...The Continuing Challenges of Balancing Process Safety Management and Personal...
The Continuing Challenges of Balancing Process Safety Management and Personal...
 
Competency Development – a paradigm shift | Alastair Shakeshaft, Director, B...
Competency Development  – a paradigm shift | Alastair Shakeshaft, Director, B...Competency Development  – a paradigm shift | Alastair Shakeshaft, Director, B...
Competency Development – a paradigm shift | Alastair Shakeshaft, Director, B...
 
Building the competence of your workforce | Teresa Budworth, Chief Executive,...
Building the competence of your workforce | Teresa Budworth, Chief Executive,...Building the competence of your workforce | Teresa Budworth, Chief Executive,...
Building the competence of your workforce | Teresa Budworth, Chief Executive,...
 
Sustainability in Cement Industry | Rakesh Bhargava, Chief Climate & Sustaina...
Sustainability in Cement Industry | Rakesh Bhargava, Chief Climate & Sustaina...Sustainability in Cement Industry | Rakesh Bhargava, Chief Climate & Sustaina...
Sustainability in Cement Industry | Rakesh Bhargava, Chief Climate & Sustaina...
 
Inclusive Growth – Is Sustainability the Answer ? | Dr. Yogendra Saxena, Tata...
Inclusive Growth – Is Sustainability the Answer ? | Dr. Yogendra Saxena, Tata...Inclusive Growth – Is Sustainability the Answer ? | Dr. Yogendra Saxena, Tata...
Inclusive Growth – Is Sustainability the Answer ? | Dr. Yogendra Saxena, Tata...
 

Último

digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingrajputmeenakshi733
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...Hector Del Castillo, CPM, CPMM
 
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...SOFTTECHHUB
 
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxGo for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxRakhi Bazaar
 
20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdf20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdfChris Skinner
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersPeter Horsten
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsKnowledgeSeed
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreNZSG
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterJamesConcepcion7
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsIndiaMART InterMESH Limited
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesDoe Paoro
 
NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryEffective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryWhittensFineJewelry1
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 

Último (20)

digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketing
 
WAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdfWAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdf
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
 
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
 
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxGo for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
 
20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdf20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdf
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exporters
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applications
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource Centre
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare Newsletter
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan Dynamics
 
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptxThe Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic Experiences
 
NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors Data
 
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryEffective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 

Process Safety Management in Design, Construction & Commissioning | Lalit K. Vijh ED- Technical Engineers India Limited

  • 1. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning Topic: Process Safety Management in Design, Construction & Commissioning By: Lalit K. Vijh ED- Technical Engineers India Limited
  • 2. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning MAJOR HAZARDS IN OIL INDUSTRY
  • 3. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning SAN JUANICO DISASTER PEMEX, MEXICO, 1984 BEFORE AFTER
  • 4. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning SAN JUANICO DISASTER, PEMEX, MEXICO, 1984 8” Pipe rupture occurred near the sphere The Control Room operator tried to identify the cause of pressure fall but without success. The release of LPG occurred for more than 5-10 minute The gas cloud grew to cover a large area and ignited from a ignition by ground flare. The VCE severely damaged the tank farm and resulted in LPG leak from other damaged tanks Just 4 minutes later first tank underwent BLEVE. Over the next hour, 12 separate BLEVE explosions were recorded. The two largest BLEVE’s(from 2400 m3 spherical tanks) registered 5.0 seismic reading on R.S The explosions destroyed the local town of San Juan Ixhuatepec. Approximately 500-600 people killed and 5000-7000 others suffering severe burns.
  • 5. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning LESSONS LEARNED - SAN JUANICO DISASTER Sitting of Major Hazard Installation • The high death toll occurred because the housing was too near to the plant. At the time the plant was constructed the area was underdeveloped, but over the years the built-up area had gradually crept up to the site. Layout and Protection of large LPG Storages • The total destruction of the facility occurred because there was a failure of the overall system of protection, which includes layout, emergency isolation and water spray systems. Gas Detection and Emergency Isolation • One feature which might have averted the disaster is more effective gas detection and emergency isolation. The plant had no gas detector system and probably as a consequence, emergency isolation was too late.
  • 6. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning LPG FIRE AT VALERO, MCKEE REFINERY, 2007
  • 7. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning LPG FIRE AT VALERO, MCKEE REFINERY The propane release was likely caused by the freeze-related failure of high-pressure piping at a control station that had not been in service for approximately 15 years. The lack of remote isolation significantly increased the duration and size of the fire, resulting in extensive damage to the Propane Deasphalting Unit, the main pipe rack, and an adjacent process unit. Flame impingement on a non-fireproofed structural support caused a pipe rack to collapse, significantly increasing the size and duration of the fire, and led to the evacuation and extended shutdown of the refinery. The exposure of three one-ton chlorine containers to radiant heating from the fire led to the release of approximately 2.5 tons of highly toxic chlorine. A butane storage sphere was exposed to radiant heating that blistered its paint. The manual firewater deluge valve for the butane sphere was located too close to the PDA unit and could not be opened during the fire.
  • 8. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning JAIPUR FIRE ACCIDENT 2009 • 11 Dead • Loss of ~ Rs.280 Crores
  • 9. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning EXPLOSION IN VENEZUELA'S LARGEST OIL REFINERY ON 25-08-2012 • 48 Dead (official figure) • Initial Report indicate poor maintenance as chief cause
  • 10. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning Source : Harry J. Toups LSU Department of Chemical Engineering ,SACHE 2003 Workshop Mechanical Operator Error Unknown Process Upsets Natural Hazards Design Sabotage & Arson 0 10 20 30 40 50 44 % 22 % 12 % 11 % 5 % 5 % 1 % CAUSE OF ACCIDENTS IN OIL INDUSTRY
  • 11. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning APPROACH FOR SAFETY IN PLANT DESIGN? Eliminate or minimize hazards rather than control hazards Don’t wait for a major accident to identify need to improve major hazard management. Need to learn lessons from accidents but don’t rely on this approach Manage risks via Foresight rather than Hindsight i.e. be proactive rather than reactive. More a philosophy and way of thinking than a specific set of tools and methods applicable at all levels of design and operation from conceptual design to plant operations
  • 12. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning INHERENT PASSIVE ACTIVE PROCEDURAL PROCESS SAFETY STRATEGIES
  • 13. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning • Eliminate or reduce the hazard by changing to a process or materials which are non-hazardous or less hazardousINHERENT • Minimize hazard using process or equipment design features which reduce frequency or consequence without the active functioning of any device PASSIVE PROCESS SAFETY STRATEGIES
  • 14. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning • Controls, safety interlocks, automatic shut down systems • Multiple active elements : Sensors, Logic device, Control element ACTIVE • Standard operating procedures, safety rules, emergency response procedures, trainingPROCEDURAL PROCESS SAFETY STRATEGIES
  • 15. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning HSE during Project Execution • Environment Impact Assessment • Environmental Baseline Survey • Process Hazard Review • Hazard Identification (HAZID) Project Conceptualization Stage • P&ID Review For Operational Safety • HSE Plan & HSE Philosophy • HAZOP & SIL Studies • Fire, Explosion & Dispersion Analysis/ Consequence Analysis • HSE Action Tracking Register & PHSER Process Design Stage • Plot Plan Review • Plot Plan Review Through Plot Plan Risk Review Committee • Quantitative Risk Assessment • Detailed HAZOP & HAZOP Close Out Report • Fire & Gas Safety System Review • Cause & Effects/Safety Charts Review • Preparation of HSE Dossier & PHSER • Safety Manual & Operating Manual Preparation Engineering Stage • Safety Guidelines to Contractors • Safety Monitoring through Dedicated Safety Engineers • Safety Meetings • Safety Performance Evaluation Construction Stage • Punch List Preparation • Startup Formats • Pre Startup Safety Audit Commissioning Stage
  • 16. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning CONCEPTUAL DESIGN (Coarse HAZOP, What-if, Ranking) SITE SELECTION (Rapid Risk Analysis, Environmental Impact Assessment) PROCESS DESIGN (HAZOP, Safety Review, SIL) ENGINEERING (Qualitative Risk Analysis, Plot Plan Review) START-UP (Safety Audit, Emergency Plan) RISK CONTROL DURING PROJECT STAGES
  • 17. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning SAFETY AT PLANNING STAGE Prevention of accidents should be the goal Design options (use of chemicals, technology etc) Layout review (various locations and configurations) Hazard Identification (HAZID) Environment Impact Assessment Environmental Baseline Survey
  • 18. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning HSE DURING ENGINEERING
  • 19. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning SAFETY AT DESIGN STAGE Adequate Design suitable for operations: HAZID (Hazard Identification) HAZOP (Hazard and Operability Study) HSEIA (Health Safety Environment Impact Assessment) • COMAH (Control of Major Accidental Hazard), OHRA (Occupational Health Risk Assessment), EIA (Environment Impact Assessment) • HSECES (HSE Critical Equipment System), SCE/PS (Safety Critical Elements / Performance Standards) • Fire Safety Assessment and Dispersion Analysis, QRA (Quantitative Risk Assessment) • Noise Study, EERA (Escape, Evacuation and Rescue Analysis), Waste Management Plan SIL (Safety Integrity Level) ALARP Study (As Low As Reasonably Practicable) Active and Passive Fire Protection System
  • 20. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning TYPICAL PROCESS SAFETY CODES & STANDARDS USED IN DESIGN Some of the standards widely used by designers and operating companies are: • American Petroleum Institute (API) • American Society of Mechanical Engineers (ASME) • National Fire Protection Association (NFPA) • Oil Industry Safety Directorate (OISD) / Local Standards • British Standard Institution (BSI) • International Standard Organization (ISO) • Static & Mobile Pressure Vessel (SMPV) Rules • Petroleum Rules • IBR regulation Process Design and Hydrocarbon Services are complying to various OISD Standards • OISD-STD-106 (Pressure Relief & Disposal System) • OISD-STD-108 (Recommended Practices on Oil Storage and Handling) • OISD-STD-116/117 (for Fire Protection) • OISD-STD-118 (Layouts for Oil and Gas Installations) • OISD-STD-144 (LPG Installations) • OISD-STD-150 (for LPG Mounded Storage Facility) • OISD-STD-152 (Safety instrumentation for process system in HC industry) • OISD-STD-163 (Process Control Room Safety) • OISD-STD-164 (Fire Proofing in Oil & Gas Industry) • OISD-STD-194 (Standard for Storage And Handling of LNG) • OISD-STD-197 (Guidelines for EIA)
  • 21. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning PROCESS DESIGN PHILOSOPHY Selection of proper Material of Construction (MOC) Selection of proper piping class, rating. Selection of proper design conditions (Pressure, Temperature) Selection of hold up volume Conformity to various codes/ standards Adherence to good design practice Feed Back from previous jobs, Client, Engineering, Commissioning.
  • 22. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning PROCESS SAFETY PHILOSOPHY - LOPA PROCESS MITIGATION SYSTEM OFFSITEEMERGENCY RESPONSE ONSITE EMERGENCY RESPONSE PREVENTION SYSTEM CONTROL & MONITORING
  • 23. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning PROCESS SAFETY PHILOSOPHY Pressure Venting provisions shall be in accordance with API RP 520 (Part 1 &2), API RP 521 Standards Flare system is provided to safely dispose of the materials released from PSV in case of any malfunction of system • Controlling case for refinery or petrochemical complexes are usually cooling water or power failure. Whenever there is one cooling water system, cooling water failure loads for various units are added to calculate total flare load of the complex. • For a large complex with very high flare load for cooling water failure case, complex may be segregated in to two or more cooling water systems and then flare load of one (controlling ) cooling water system may be considered for further design • Temperature profile of flare header (ISBL & OSBL) is essential in having optimum provision of expansion loops in flare headers
  • 24. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning PROCESS SAFETY PHILOSOPHY : LAYOUT Key considerations/ safety features for layout • Separation of hazardous areas from non-hazardous areas • Safe separation distances • Adequate escape routes, safe access for operation and maintenance of equipment • Main ignition sources should be grouped and located upstream prevailing wind. • Emergency response teams to have clear access to all fire fighting equipment. • Cable trays, pipe racks and escape routes shall be positioned such that risk of damage by pool fire or explosions is minimized. • Optimize availability of emergency services and main safety equipment under all foreseeable events.
  • 25. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning Process Safety PhilosophyHazardous Area Classification • The hazardous area classification shall be performed in accordance with IP Model Code of Safe Practice Part 15. • Based on the above code various areas shall be classified into zones and Electrical appliances shall be selected suitably. The Emergency Shutdown system • The Emergency Shutdown system shall be designed to fail-safe so that, in the event of loss of any of the controls to the system, the shutdown valves shall fail closed and the blowdown valves fail open. • The Emergency Shutdown system shall be reviewed in accordance with IEC 61508. PRPROCESS SAFETY PHILOSOPHY
  • 26. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning Redundancy Voting systems Philosophy of alarms and trips Emergency depressurization Emergency shut down (ESD) Safety valve HIPPS – High Integrity Pressure Protection System PROCESS SAFETY PHILOSOPHY - Instrumentation
  • 27. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning FIRE CONTROL AND MITIGATION– F&G Detection System • The required functions/actions on fire and/or gas detection shall be developed during detail design phase. • The Fire and Gas Detection systems shall be designed and installed in accordance with NFPA and OISD Standards. • Detector locations shall be determined by means of case by case examination of the facilities layout and may be placed either peripherally around the facilities, at suitable intervals or placed to cover areas with a leak potential, or both. The fire and gas (F&G) detection system is to provide an early warning to personnel of the existence of a potentially dangerous situation and to enable automatic initiation of remedial actions • Gas detectors – H2, HC, H2S, Cl • Fire detectors –Flame, Heat, Smoke F&G Field Devices
  • 28. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning • The main objective of active fire protection is to: • Provide cooling (Deluge System, Sprinkling System) • Control the fire (ie., prevent it from spreading) • Extinguishment of the fire incident (Fire Extinguishers, Foam System) Active Fire Protection : A “dormant” system that needs to be activated in order to perform its function. • Fire Proofing/ Passive fire protection is a barrier or safeguard which provides protection against the heat from a fire without additional intervention i.e. it performs its function without relying on activation. Passive Fire Protection : A system that performs its function without relying on the requirement of activation FIRE CONTROL AND MITIGATION – ACTIVE AND PASSIVE FIRE PROTECTION
  • 29. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning HSE DURING CONSTRUCTION
  • 30. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning SAFETY AT CONSTRUCTION STAGE Setting of Project specific HSE objective and targets Implementation of Project specific HSE Plan Preparation and Implementation of ERP Project HSE Review (PHSER for Construction) Dedicated Warehouse /Procedures for storage of Materials and Hazardous substances HSE Training, Inspection & audit HIRA & Legal register and ensuring its compliance Pre- Deployment Inspection and Certification for Mobilization of suitable and safe equipment
  • 31. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning Tools for Monitoring/Implementation of HSE at Sites • HSE Specification • HSE Plan • HSE Procedures • HSE Induction • Hazard Identification & Risk Analysis (HIRA)/ Job Safety Analysis (JSA) • Tool Box Talks • Mock Drills (Fire, Electrocution , Fall from height ) • HSE Inspection/ Walk-through • HSE Meetings • Road Safety & Movement of vehicles • Fitness certificates for all Lifting tools & Tackles, Cranes • HSE Permits Viz. Scaffolds, Confined space, Height work, Excavation • HSE Awareness/ Motivational Programs • HSE Reporting including LTIFR, FAR • Reporting of Near Miss Accidents & Corrective Actions • Accident Investigations & Recommendations • Analysis of Leading &Trailing Indicators
  • 32. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning • Legal compliance • HSE Management System & Competence • HSE Performance Pre qualification &Selection • General Terms & Condition • Code of Conduct Contractor Preparation • HSE Plan & Organization • Competence of Personnel • Signing of code of conduct Contract Award • Kick of Meeting • Medical Check up Pre commencement & Mobilization • HSE Training as per approved HSE Training MatrixContractors Orientation & Training • Periodic evaluation • HSE Review meeting Managing the Contractors • HSE Performance Records Post Contract Evaluation CONTRACTOR’s SAFETY MANAGEMENT PROCESS
  • 33. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning HSE DURING COMMISSIONING
  • 34. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning SAFETY AT PRECOMMISSIONING & COMMISSIONING AND HANDOVER SIMOPS - Simultaneous Operation study for Planning and coordination Multilayer Safety checks to meet Aggressive Schedule Multi disciplinary trained manpower Manuals, SOP & Checklists Authorization & documentation for Changes, Bypass etc Pre Start up Safety Review HSE Action Tracking Register/ Formal HSE Close out Report Project HSE Review (PHSER for Pre- Commissioning) Lesson Learnt
  • 35. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning SUMMARY Safety in design is of paramount importance for process safety management Goal should be to prevent rather than control & mitigate hazards Select inherently safe processes and Incorporate adequate active & passive safety features in design minimizing dependence on human intervention Select Process specifications/ design conditions, Materials to reflect normal as well as start up/ transient conditions Ensure strict adherence to safety & design standard & codes during design/engineering/construction & commissioning Carryout Safety Studies like RRA/ QRA, HAZID, HAZOP, SIL etc to ensure adequate safety features including control & mitigation are built in design & to finalize location/ layout of facilities
  • 36. Technical Session # 3A Topic : Process Safety Management in Design , Construction & Commissioning THANK YOU