SlideShare una empresa de Scribd logo
1 de 11
Davis Landings
Affordable Housing Project




                  August 3, 2012

  Community Land Trust of Palm Beach County, Inc.
Project Update
• Construction started 11/1/2011
   • Estimated Completion 8/30/2012
   • 90%+ Complete
• Interior build out nearing completion
• Landscaping being installed
• Cabinets and A/C being installed
Budget Update  7/31/2012
                                                                                 Invoiced to        Projected
                                                          11/1/2011 Budget          Date            Balance
Hard Costs
 Construction                                                   4,155,000    $ 3,315,848.12     $    839,151.88
 Contingency                                                      415,500    $     125,281.28   $    290,218.72
Total Hard Costs                                                4,570,500                       $ 4,570,500.00
Financing Costs
 Title and Recording-Construction                                  21,880    $      20,332.05   $      1,547.95
 Soft Cost Revolving Credit                                        15,000    $       3,258.00   $     11,742.00
Total Financing Cost                                               36,880                       $     36,880.00
Soft Costs
 Architectural and Engineering Design plus CO # 1 & 2             292,300    $     321,616.00   $    (29,316.00)
 A-E CO#3                                                          54,756
 Structural Soil Study                                              4,740                       $      4,740.00
 Construction Materials Testing                                          -                      $           -
 Legal                                                             20,000    $       4,460.00   $     15,540.00
 Accounting                                                         8,000                       $      8,000.00
 Marketing                                                         10,000    $       2,898.00   $      7,102.00
 Permit Fees                                                       96,500    $     111,840.00   $    (15,340.00)
 Impact Fees                                                      138,500    $     138,460.00   $         40.00
 Utility Connection Fees                                          118,000    $     117,743.07   $        256.93
 Inspection / Thresh. Insp.                                                                     $           -
 Property Upkeep                                                    7,244                       $      7,244.00
 Soft Cost Contingency                                             60,753    $      48,909.00   $     11,844.00
Total Soft Costs                                                  810,793                       $    810,793.00
Project Management / Overhead and Administration
 Project Management / Overhead and Administration                 220,000    $     161,821.00   $     58,179.00
Transformer Cost
 Lake Worth Power Transformer                                      25,000    $      24,710.57   $        289.43
Reserves
 Operating Reserve                                                 59,833                       $     59,833.00
Total Reserves                                                     59,833                       $     59,833.00
Total Budget                                             $      5,723,006    $ 4,397,177.09     $ 1,325,828.91
Construction Contract/CO Update
Davis Landings Change Log
                                                                                      Fixed Base Bid                                    $4,155,000
                                                                      Fixed Add Alteratives Approved                                     $144,098
                                                                                   Total                                                $4,299,098
Actual/Potential Change Log             7/30/2012

                                         Submitted                  new contract
CO      Description                         Date        Value         amount        Date Approved                           Notes
001     LWDD - canal work                   12/09/11     $15,265       $4,170,265          01/03/12    Permit requirement
002     Security thru Dec 2011              12/09/11     $11,635       $4,181,899          01/03/12    Unforeseen site condition
003     Rubber base for playground          12/09/11     $20,160       $4,202,059          01/04/12    Add alternative accepted
004     Quartz countertops                  12/09/11     $50,846       $4,252,905          01/04/12    Add alternative accepted
005     Security cameras                    12/09/11     $24,000       $4,276,905          01/04/12    Add alternative accepted
006     Playground equipment                12/09/11      $8,160       $4,285,065          01/04/12    Add alternative accepted
007     Washers and Dryers                  12/09/11     $31,782       $4,316,847          01/04/12    Add alternative accepted
008     Window treatments                   12/09/11      $9,150       $4,325,997          01/04/12    Add alternative accepted
009     Security Jan-Feb 2012               01/15/12     $29,500       $4,355,497          01/20/12    Job site security
010     Stored materials storage            01/15/12     $37,100       $4,392,597          01/20/12    Job site management
011     Bathroom hi hat lights              02/17/12      $5,060       $4,397,657          03/02/12    Code review requirement
012     Gable ends - structural             02/17/12     $14,692       $4,412,349          03/05/12    Code review requirement
013     Elevator air conditioning           03/05/12      $8,033       $4,420,382          03/08/12    Code review requirement
014     Heat Detectors                      03/05/12      $2,232       $4,422,614          03/08/12    Building Inspector requirement
015     Electrical disconnect               03/20/12      $2,651       $4,425,265          05/31/12    Building dept comment
016     Sink upgrade                        03/12/12      $2,657       $4,427,922          03/15/12    plan coordination
017     Drywall modifications               04/15/12      $7,192       $4,435,114          07/01/12    plan coordination
018     Security Mar - May                  05/23/12     $22,200       $4,457,313          07/01/12    Job site security
019     Shelving Credit                     06/06/12     ($8,455)      $4,448,858          07/01/12    Owner selection
020     504 changes                         06/14/12      $2,750       $4,451,608          07/01/12    DES HUD
021     Time for site lighting permit       07/11/12          $0       $4,451,608          07/11/12    Permitting
022     Misc. 502, tile, ect.               07/11/12      $7,153       $4,458,762                      Misc.
023     Balcony mud, tile credit            07/11/12      $6,401       $4,465,163                      Appearance
024     Security Jun - Sep                 estimated     $30,000       $4,495,163                      Job site security
025     Stored material handling           estimated     $10,000       $4,505,163                      Job site management
026
027
Void    Air Conditioning cages       -                         $0                                      Void
        Total                                            $350,163
        Current/Estimated Contract Value               $4,505,163
        Percentage CO's                                      4.8%                                      Includes add/alternatives

        Impact on Project Contingency
        Initial Budget Construction Contingency         $415,500
        CO 1 - 8                                       ($170,997)
        CO 9 - 25                                      ($179,165)
        Current Budget Contingency                       $65,337
        Current Contingency %                               1.6%
Davis Landings Project Spending
6000



5000



4000



                                                                            Projected
3000
                                                                            Actual


2000



1000



  0
       Nov   Dec   Jan   Feb   Mar   April   May   Jun   July   Aug   Sep
Davis Landings Site Plans
Site Nov. 2011 – Feb. 2012
March 2012 – June 2012
July 2012
Questions & Follow-Up

Más contenido relacionado

La actualidad más candente

Customer contractor defined requirements plan
Customer   contractor defined requirements planCustomer   contractor defined requirements plan
Customer contractor defined requirements planTony Burnett
 
City Council July 19, 2011 Finance Presentation
City Council July 19, 2011 Finance PresentationCity Council July 19, 2011 Finance Presentation
City Council July 19, 2011 Finance PresentationCity of San Angelo Texas
 
2011 Q2 MD&A & Interim Financial Statements
2011 Q2 MD&A & Interim Financial Statements2011 Q2 MD&A & Interim Financial Statements
2011 Q2 MD&A & Interim Financial StatementsProphecy Corp
 
Modeling Presentation
Modeling PresentationModeling Presentation
Modeling Presentationdverm
 
2011 Fhrboc Presentation T&T
2011 Fhrboc Presentation T&T2011 Fhrboc Presentation T&T
2011 Fhrboc Presentation T&Tnperrine
 
Swifton CFOs - McCarter English - Fin Proj 100511
Swifton CFOs - McCarter English - Fin Proj 100511Swifton CFOs - McCarter English - Fin Proj 100511
Swifton CFOs - McCarter English - Fin Proj 100511David Fogel
 
Swifton - The Capital Network - Financial Projections
Swifton - The Capital Network - Financial ProjectionsSwifton - The Capital Network - Financial Projections
Swifton - The Capital Network - Financial ProjectionsDavid Fogel
 
Sgs Sfp 2012 15 C
Sgs Sfp 2012 15 CSgs Sfp 2012 15 C
Sgs Sfp 2012 15 Cmarsfs
 
occidental petroleum 2007 Consolidated Condensed Balance Sheets
occidental petroleum 2007 Consolidated Condensed Balance Sheetsoccidental petroleum 2007 Consolidated Condensed Balance Sheets
occidental petroleum 2007 Consolidated Condensed Balance Sheetsfinance13
 
Finance Budgeting Powerpoint Presentation Slides
Finance Budgeting Powerpoint Presentation SlidesFinance Budgeting Powerpoint Presentation Slides
Finance Budgeting Powerpoint Presentation SlidesSlideTeam
 
Forecast Vs Actual Budget PowerPoint Presentation Slides
Forecast Vs Actual Budget PowerPoint Presentation Slides Forecast Vs Actual Budget PowerPoint Presentation Slides
Forecast Vs Actual Budget PowerPoint Presentation Slides SlideTeam
 
CIV214702 Sulphur Mountain/Gaggero v Redmonds Relevant Case Record 3
CIV214702 Sulphur Mountain/Gaggero v Redmonds Relevant Case Record 3CIV214702 Sulphur Mountain/Gaggero v Redmonds Relevant Case Record 3
CIV214702 Sulphur Mountain/Gaggero v Redmonds Relevant Case Record 3jamesmaredmond
 

La actualidad más candente (16)

Customer contractor defined requirements plan
Customer   contractor defined requirements planCustomer   contractor defined requirements plan
Customer contractor defined requirements plan
 
Marketing Solar for Agricultural Users
Marketing Solar for Agricultural UsersMarketing Solar for Agricultural Users
Marketing Solar for Agricultural Users
 
City Council July 19, 2011 Finance Presentation
City Council July 19, 2011 Finance PresentationCity Council July 19, 2011 Finance Presentation
City Council July 19, 2011 Finance Presentation
 
Top Ten Drgs By Doctor
Top Ten Drgs By DoctorTop Ten Drgs By Doctor
Top Ten Drgs By Doctor
 
2011 Q2 MD&A & Interim Financial Statements
2011 Q2 MD&A & Interim Financial Statements2011 Q2 MD&A & Interim Financial Statements
2011 Q2 MD&A & Interim Financial Statements
 
Modeling Presentation
Modeling PresentationModeling Presentation
Modeling Presentation
 
2011 Fhrboc Presentation T&T
2011 Fhrboc Presentation T&T2011 Fhrboc Presentation T&T
2011 Fhrboc Presentation T&T
 
Section 6 revision
Section 6 revisionSection 6 revision
Section 6 revision
 
MA AMTA 52st Annual Meeting
MA AMTA 52st Annual MeetingMA AMTA 52st Annual Meeting
MA AMTA 52st Annual Meeting
 
Swifton CFOs - McCarter English - Fin Proj 100511
Swifton CFOs - McCarter English - Fin Proj 100511Swifton CFOs - McCarter English - Fin Proj 100511
Swifton CFOs - McCarter English - Fin Proj 100511
 
Swifton - The Capital Network - Financial Projections
Swifton - The Capital Network - Financial ProjectionsSwifton - The Capital Network - Financial Projections
Swifton - The Capital Network - Financial Projections
 
Sgs Sfp 2012 15 C
Sgs Sfp 2012 15 CSgs Sfp 2012 15 C
Sgs Sfp 2012 15 C
 
occidental petroleum 2007 Consolidated Condensed Balance Sheets
occidental petroleum 2007 Consolidated Condensed Balance Sheetsoccidental petroleum 2007 Consolidated Condensed Balance Sheets
occidental petroleum 2007 Consolidated Condensed Balance Sheets
 
Finance Budgeting Powerpoint Presentation Slides
Finance Budgeting Powerpoint Presentation SlidesFinance Budgeting Powerpoint Presentation Slides
Finance Budgeting Powerpoint Presentation Slides
 
Forecast Vs Actual Budget PowerPoint Presentation Slides
Forecast Vs Actual Budget PowerPoint Presentation Slides Forecast Vs Actual Budget PowerPoint Presentation Slides
Forecast Vs Actual Budget PowerPoint Presentation Slides
 
CIV214702 Sulphur Mountain/Gaggero v Redmonds Relevant Case Record 3
CIV214702 Sulphur Mountain/Gaggero v Redmonds Relevant Case Record 3CIV214702 Sulphur Mountain/Gaggero v Redmonds Relevant Case Record 3
CIV214702 Sulphur Mountain/Gaggero v Redmonds Relevant Case Record 3
 

Destacado

Destacado (20)

83 muster2014 jill bestic
83 muster2014 jill bestic83 muster2014 jill bestic
83 muster2014 jill bestic
 
CEN PRI realiza Toma de Protesta a Candidatos a Diputados por Eleccion Popula...
CEN PRI realiza Toma de Protesta a Candidatos a Diputados por Eleccion Popula...CEN PRI realiza Toma de Protesta a Candidatos a Diputados por Eleccion Popula...
CEN PRI realiza Toma de Protesta a Candidatos a Diputados por Eleccion Popula...
 
84 begudes i entrepans
84 begudes i entrepans84 begudes i entrepans
84 begudes i entrepans
 
863 alzheimer
863 alzheimer863 alzheimer
863 alzheimer
 
8360_toc
8360_toc8360_toc
8360_toc
 
фер ферр(в 87 120)
фер ферр(в 87 120)фер ферр(в 87 120)
фер ферр(в 87 120)
 
Genaral Configuration 8600 Nortel
Genaral Configuration 8600 NortelGenaral Configuration 8600 Nortel
Genaral Configuration 8600 Nortel
 
84 adoração
84   adoração84   adoração
84 adoração
 
84825772 metodos-de-ensino
84825772 metodos-de-ensino84825772 metodos-de-ensino
84825772 metodos-de-ensino
 
85 0063-a rev 6-eco-2 operation_web
85 0063-a rev 6-eco-2 operation_web85 0063-a rev 6-eco-2 operation_web
85 0063-a rev 6-eco-2 operation_web
 
864 inc. a
864 inc. a864 inc. a
864 inc. a
 
86akademeia what's the laugh
86akademeia what's the laugh86akademeia what's the laugh
86akademeia what's the laugh
 
8287494393@ flat sale in dwarka sector-8
8287494393@ flat sale in dwarka sector-88287494393@ flat sale in dwarka sector-8
8287494393@ flat sale in dwarka sector-8
 
BRE-CASE Seminarium 79 - Is the Polish Banking Sector Innovative?
 BRE-CASE Seminarium 79  -  Is the Polish Banking Sector Innovative? BRE-CASE Seminarium 79  -  Is the Polish Banking Sector Innovative?
BRE-CASE Seminarium 79 - Is the Polish Banking Sector Innovative?
 
850m Manual Web
850m Manual Web850m Manual Web
850m Manual Web
 
PEDIDO DE PROVIDÊNCIA 835
PEDIDO DE PROVIDÊNCIA 835PEDIDO DE PROVIDÊNCIA 835
PEDIDO DE PROVIDÊNCIA 835
 
86 anni4
86 anni486 anni4
86 anni4
 
שיחת הגאולה פר' כי תישא - 836
שיחת הגאולה פר' כי תישא - 836 שיחת הגאולה פר' כי תישא - 836
שיחת הגאולה פר' כי תישא - 836
 
87157401
8715740187157401
87157401
 
83 good karma
83 good karma83 good karma
83 good karma
 

Similar a Affordable Housing Project Near Completion with Budget Update

C Miller Wk5 Project1
C Miller Wk5 Project1C Miller Wk5 Project1
C Miller Wk5 Project1treavor96
 
City Council March 20, 2012 City Hall Complex 2012
City Council March 20, 2012 City Hall Complex 2012City Council March 20, 2012 City Hall Complex 2012
City Council March 20, 2012 City Hall Complex 2012City of San Angelo Texas
 
Three Rivers TIFA Update Ex Sum 12.4.12
Three Rivers TIFA Update Ex Sum  12.4.12Three Rivers TIFA Update Ex Sum  12.4.12
Three Rivers TIFA Update Ex Sum 12.4.12Chuck Eckenstahler
 
Ahs provisional-31 st dec 2011 (6)
Ahs provisional-31 st dec 2011 (6)Ahs provisional-31 st dec 2011 (6)
Ahs provisional-31 st dec 2011 (6)kiransagam
 
Ahs provisional-31 st dec 2011 (6)
Ahs provisional-31 st dec 2011 (6)Ahs provisional-31 st dec 2011 (6)
Ahs provisional-31 st dec 2011 (6)kiransagam
 
Ahs provisional-31 st dec 2011 (6)
Ahs provisional-31 st dec 2011 (6)Ahs provisional-31 st dec 2011 (6)
Ahs provisional-31 st dec 2011 (6)kiransagam
 
Midterm solutions
Midterm solutionsMidterm solutions
Midterm solutionsemahacct
 
Forecast Vs Actual Budget Powerpoint Presentation Slides
Forecast Vs Actual Budget Powerpoint Presentation SlidesForecast Vs Actual Budget Powerpoint Presentation Slides
Forecast Vs Actual Budget Powerpoint Presentation SlidesSlideTeam
 
Villa Alhambra Financials May 2012
Villa Alhambra Financials May 2012Villa Alhambra Financials May 2012
Villa Alhambra Financials May 2012VillaAlhambra
 
2008 annual audited financial statements
2008 annual audited financial statements2008 annual audited financial statements
2008 annual audited financial statementsProphecy Corp
 
Actual Cost Vs Plan Projection Powerpoint Presentation Slides
Actual Cost Vs Plan Projection Powerpoint Presentation SlidesActual Cost Vs Plan Projection Powerpoint Presentation Slides
Actual Cost Vs Plan Projection Powerpoint Presentation SlidesSlideTeam
 
Actual Cost Vs Budget Powerpoint Presentation Slides
Actual Cost Vs Budget Powerpoint Presentation SlidesActual Cost Vs Budget Powerpoint Presentation Slides
Actual Cost Vs Budget Powerpoint Presentation SlidesSlideTeam
 
2010 04 14 Proserv Mms Pocsr Rotac Presentation
2010 04 14 Proserv Mms Pocsr Rotac Presentation2010 04 14 Proserv Mms Pocsr Rotac Presentation
2010 04 14 Proserv Mms Pocsr Rotac PresentationRobert Byrd
 
Dri expansion cost breakdown pdf-1
Dri expansion cost breakdown   pdf-1Dri expansion cost breakdown   pdf-1
Dri expansion cost breakdown pdf-1Tumehfamily
 

Similar a Affordable Housing Project Near Completion with Budget Update (20)

C Miller Wk5 Project1
C Miller Wk5 Project1C Miller Wk5 Project1
C Miller Wk5 Project1
 
City Council March 20, 2012 City Hall Complex 2012
City Council March 20, 2012 City Hall Complex 2012City Council March 20, 2012 City Hall Complex 2012
City Council March 20, 2012 City Hall Complex 2012
 
2011 Budget
2011 Budget2011 Budget
2011 Budget
 
Pre Budget Meeting December 5, 2012
Pre Budget Meeting December 5, 2012 Pre Budget Meeting December 5, 2012
Pre Budget Meeting December 5, 2012
 
Raquel Guglielmetti Excel Handout
Raquel Guglielmetti Excel HandoutRaquel Guglielmetti Excel Handout
Raquel Guglielmetti Excel Handout
 
Three Rivers TIFA Update Ex Sum 12.4.12
Three Rivers TIFA Update Ex Sum  12.4.12Three Rivers TIFA Update Ex Sum  12.4.12
Three Rivers TIFA Update Ex Sum 12.4.12
 
Seymour Johnson AFB
Seymour Johnson AFBSeymour Johnson AFB
Seymour Johnson AFB
 
Ahs provisional-31 st dec 2011 (6)
Ahs provisional-31 st dec 2011 (6)Ahs provisional-31 st dec 2011 (6)
Ahs provisional-31 st dec 2011 (6)
 
Ahs provisional-31 st dec 2011 (6)
Ahs provisional-31 st dec 2011 (6)Ahs provisional-31 st dec 2011 (6)
Ahs provisional-31 st dec 2011 (6)
 
Ahs provisional-31 st dec 2011 (6)
Ahs provisional-31 st dec 2011 (6)Ahs provisional-31 st dec 2011 (6)
Ahs provisional-31 st dec 2011 (6)
 
Midterm solutions
Midterm solutionsMidterm solutions
Midterm solutions
 
Forecast Vs Actual Budget Powerpoint Presentation Slides
Forecast Vs Actual Budget Powerpoint Presentation SlidesForecast Vs Actual Budget Powerpoint Presentation Slides
Forecast Vs Actual Budget Powerpoint Presentation Slides
 
Pre budget meeting website slides
Pre budget meeting  website slidesPre budget meeting  website slides
Pre budget meeting website slides
 
Villa Alhambra Financials May 2012
Villa Alhambra Financials May 2012Villa Alhambra Financials May 2012
Villa Alhambra Financials May 2012
 
2008 annual audited financial statements
2008 annual audited financial statements2008 annual audited financial statements
2008 annual audited financial statements
 
Solution ACC180 Jan 2012
Solution ACC180 Jan 2012Solution ACC180 Jan 2012
Solution ACC180 Jan 2012
 
Actual Cost Vs Plan Projection Powerpoint Presentation Slides
Actual Cost Vs Plan Projection Powerpoint Presentation SlidesActual Cost Vs Plan Projection Powerpoint Presentation Slides
Actual Cost Vs Plan Projection Powerpoint Presentation Slides
 
Actual Cost Vs Budget Powerpoint Presentation Slides
Actual Cost Vs Budget Powerpoint Presentation SlidesActual Cost Vs Budget Powerpoint Presentation Slides
Actual Cost Vs Budget Powerpoint Presentation Slides
 
2010 04 14 Proserv Mms Pocsr Rotac Presentation
2010 04 14 Proserv Mms Pocsr Rotac Presentation2010 04 14 Proserv Mms Pocsr Rotac Presentation
2010 04 14 Proserv Mms Pocsr Rotac Presentation
 
Dri expansion cost breakdown pdf-1
Dri expansion cost breakdown   pdf-1Dri expansion cost breakdown   pdf-1
Dri expansion cost breakdown pdf-1
 

Último

Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsKnowledgeSeed
 
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryEffective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryWhittensFineJewelry1
 
WSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdfWSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdfJamesConcepcion7
 
business environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxbusiness environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxShruti Mittal
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdfChris Skinner
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...ssuserf63bd7
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreNZSG
 
Technical Leaders - Working with the Management Team
Technical Leaders - Working with the Management TeamTechnical Leaders - Working with the Management Team
Technical Leaders - Working with the Management TeamArik Fletcher
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckHajeJanKamps
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in PhilippinesDavidSamuel525586
 
20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdf20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdfChris Skinner
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...Associazione Digital Days
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesDoe Paoro
 
digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingrajputmeenakshi733
 

Último (20)

Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applications
 
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryEffective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
 
WSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdfWSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdf
 
business environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxbusiness environment micro environment macro environment.pptx
business environment micro environment macro environment.pptx
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource Centre
 
Technical Leaders - Working with the Management Team
Technical Leaders - Working with the Management TeamTechnical Leaders - Working with the Management Team
Technical Leaders - Working with the Management Team
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deck
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in Philippines
 
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptxThe Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
 
20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdf20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdf
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic Experiences
 
digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketing
 

Affordable Housing Project Near Completion with Budget Update

  • 1. Davis Landings Affordable Housing Project August 3, 2012 Community Land Trust of Palm Beach County, Inc.
  • 2. Project Update • Construction started 11/1/2011 • Estimated Completion 8/30/2012 • 90%+ Complete • Interior build out nearing completion • Landscaping being installed • Cabinets and A/C being installed
  • 3.
  • 4. Budget Update 7/31/2012 Invoiced to Projected 11/1/2011 Budget Date Balance Hard Costs Construction 4,155,000 $ 3,315,848.12 $ 839,151.88 Contingency 415,500 $ 125,281.28 $ 290,218.72 Total Hard Costs 4,570,500 $ 4,570,500.00 Financing Costs Title and Recording-Construction 21,880 $ 20,332.05 $ 1,547.95 Soft Cost Revolving Credit 15,000 $ 3,258.00 $ 11,742.00 Total Financing Cost 36,880 $ 36,880.00 Soft Costs Architectural and Engineering Design plus CO # 1 & 2 292,300 $ 321,616.00 $ (29,316.00) A-E CO#3 54,756 Structural Soil Study 4,740 $ 4,740.00 Construction Materials Testing - $ - Legal 20,000 $ 4,460.00 $ 15,540.00 Accounting 8,000 $ 8,000.00 Marketing 10,000 $ 2,898.00 $ 7,102.00 Permit Fees 96,500 $ 111,840.00 $ (15,340.00) Impact Fees 138,500 $ 138,460.00 $ 40.00 Utility Connection Fees 118,000 $ 117,743.07 $ 256.93 Inspection / Thresh. Insp. $ - Property Upkeep 7,244 $ 7,244.00 Soft Cost Contingency 60,753 $ 48,909.00 $ 11,844.00 Total Soft Costs 810,793 $ 810,793.00 Project Management / Overhead and Administration Project Management / Overhead and Administration 220,000 $ 161,821.00 $ 58,179.00 Transformer Cost Lake Worth Power Transformer 25,000 $ 24,710.57 $ 289.43 Reserves Operating Reserve 59,833 $ 59,833.00 Total Reserves 59,833 $ 59,833.00 Total Budget $ 5,723,006 $ 4,397,177.09 $ 1,325,828.91
  • 5. Construction Contract/CO Update Davis Landings Change Log Fixed Base Bid $4,155,000 Fixed Add Alteratives Approved $144,098 Total $4,299,098 Actual/Potential Change Log 7/30/2012 Submitted new contract CO Description Date Value amount Date Approved Notes 001 LWDD - canal work 12/09/11 $15,265 $4,170,265 01/03/12 Permit requirement 002 Security thru Dec 2011 12/09/11 $11,635 $4,181,899 01/03/12 Unforeseen site condition 003 Rubber base for playground 12/09/11 $20,160 $4,202,059 01/04/12 Add alternative accepted 004 Quartz countertops 12/09/11 $50,846 $4,252,905 01/04/12 Add alternative accepted 005 Security cameras 12/09/11 $24,000 $4,276,905 01/04/12 Add alternative accepted 006 Playground equipment 12/09/11 $8,160 $4,285,065 01/04/12 Add alternative accepted 007 Washers and Dryers 12/09/11 $31,782 $4,316,847 01/04/12 Add alternative accepted 008 Window treatments 12/09/11 $9,150 $4,325,997 01/04/12 Add alternative accepted 009 Security Jan-Feb 2012 01/15/12 $29,500 $4,355,497 01/20/12 Job site security 010 Stored materials storage 01/15/12 $37,100 $4,392,597 01/20/12 Job site management 011 Bathroom hi hat lights 02/17/12 $5,060 $4,397,657 03/02/12 Code review requirement 012 Gable ends - structural 02/17/12 $14,692 $4,412,349 03/05/12 Code review requirement 013 Elevator air conditioning 03/05/12 $8,033 $4,420,382 03/08/12 Code review requirement 014 Heat Detectors 03/05/12 $2,232 $4,422,614 03/08/12 Building Inspector requirement 015 Electrical disconnect 03/20/12 $2,651 $4,425,265 05/31/12 Building dept comment 016 Sink upgrade 03/12/12 $2,657 $4,427,922 03/15/12 plan coordination 017 Drywall modifications 04/15/12 $7,192 $4,435,114 07/01/12 plan coordination 018 Security Mar - May 05/23/12 $22,200 $4,457,313 07/01/12 Job site security 019 Shelving Credit 06/06/12 ($8,455) $4,448,858 07/01/12 Owner selection 020 504 changes 06/14/12 $2,750 $4,451,608 07/01/12 DES HUD 021 Time for site lighting permit 07/11/12 $0 $4,451,608 07/11/12 Permitting 022 Misc. 502, tile, ect. 07/11/12 $7,153 $4,458,762 Misc. 023 Balcony mud, tile credit 07/11/12 $6,401 $4,465,163 Appearance 024 Security Jun - Sep estimated $30,000 $4,495,163 Job site security 025 Stored material handling estimated $10,000 $4,505,163 Job site management 026 027 Void Air Conditioning cages - $0 Void Total $350,163 Current/Estimated Contract Value $4,505,163 Percentage CO's 4.8% Includes add/alternatives Impact on Project Contingency Initial Budget Construction Contingency $415,500 CO 1 - 8 ($170,997) CO 9 - 25 ($179,165) Current Budget Contingency $65,337 Current Contingency % 1.6%
  • 6. Davis Landings Project Spending 6000 5000 4000 Projected 3000 Actual 2000 1000 0 Nov Dec Jan Feb Mar April May Jun July Aug Sep
  • 8. Site Nov. 2011 – Feb. 2012
  • 9. March 2012 – June 2012