24. Construction Estimate 2009: Concept Plan & $6 million NYS Grant 2010: Detailed needs assessment and design to meet the Town’s current and modest future expansion Current Cost: $7,655,248 5% contingency No standby generator Standard insulation No Labor / Material Escalation through early 2012 Recommended Additions: 10% contingency $414,930 Standby generator $248,958 Premium insulation $129,114 Labor / Material Escalation $99,693 $892,695