Sustainable Economic Development of the Sudurnes
                 region, Iceland

 OP Preparation: Programming Concepts & Tools


            JOSE MATEOS MORENO

            Ásbrú, 25 November 2011
Content

1. Principles of programming

2. The programming logic

3. Programming tools – SWOT &
   LFA




                     2
1. Programming Principles




            3
What is Programming ?

   Grouping a number of temporary, goal-oriented
   and unique activities, each contributing to reach
   objectives agreed upon beforehand

Questions:
   Where are we?
   Where do we want to go?
   How should we get there?
   How will we know when we are there?


                           4
The Programme Context

         Policy


        Programme


         Projects


                    5
What Does a Programme Look Like?
            (example OP Regional Development)

                                        OP Global
                                        Objective



                    Priority             Priority                 Priority
                    Axis 1                Axis 2                  Axis 3

 Group of      Group of      Group of    Group of     Group of       Group of     Group of

Operations    Operations   Operations   Operations   Operations     Operations   Operations




                                              6
The Structure of a Programme
                           Global
          Impacts         Objective   Programme



                          Specific    Priority Axes
          Results        Objectives



                       Operational    Group
          Outputs      Objectives     Operations



Inputs    Programme
          Operations



                          7
Who’s Responsible For What?


  Programme                  Projects

 Managing Authorities
  Certifying Authority
    Audit authority          Beneficiaries
 Intermediate Bodies
Monitoring Committees




                         8
Management Structure
                     European
                   Commission

  SCF       Accession
               Country     ?


          OP              Managing      Monitoring
                          Authority     Committee

        Priority         Intermediate
         Axis                  body
                           9
2. The Programming Logic




            10
Programming Logic
                   Analysis


                   Strategy
                                   Politics
                  Priority Axis

Bottom up
• Project ideas    Group of
  • Lobbying      Operations

                              11
Group of Operations (Measure)
Definition


• The basic unit of programme management,
  consisting of a set of similar projects
• The means by which a priority axis is implemented
  over several years which enable operations to be
  financed.




                          12
Embedding in Existing Policy

• IPA is meant to cofinance existing policy, not other
  way round
• Keep it simple: look at existing national structural
  policies
• Start programming process with this analysis of
  existing policy: this will be your cofinancing table




                             13
3. Programming Tools




          14
OP Policy Life Cycle

                          Detailed
                        programming
 Planning &
programming

                                      Programme
                                      implementation

  Monitoring,
  financial control, evaluation,
  corrective actions
                               15
Main Stages of OP Preparation
Organisation of OP process

            SWOT Analysis

             Strategic Goals and Priorities

                    Budget Allocation and Impacts

                             Implementing Arrangements


                                              Ex-ante Evaluation


                                                    Negotiations with EU


                             1 to 2 years
16
Programming Tools
  Analytical tools          Creative tools        Structuring tools
  Entity formulation        Brainstorming          Problem trees
Stakeholder analysis        Matching and           Objective trees
                             conversion
 Analysis of trends       Robust strategies           Clustering
                             approach
  SWOT analysis           Vision formulation           Scoping
Problem identification   Objective formulation     LFA approach
   Benchmarking                                    Synergy check
    Forecasting                                  Indicator formulation
 Scenario analysis
    Risk analysis


                                   17
Programming Tools
• Focus on two main tools:

   Analysing:
   – SWOT analyses

   Structuring:
   – Logical Framework Approach (LFA)




                        18
Main Stages of OP Preparation
Organisation of OP process

            SWOT Analysis

             Strategic Goals and Priorities

                    Budget Allocation and Impacts

                              Implementing Arrangements


                                              Ex-ante Evaluation


                                                    Negotiations with EU


                             1 to 2 years
                                      19
SWOT Analysis


              Strengths           Weaknesses
 Internal
 & static



External
& dynamic
             Opportunities         Threats



                             20
Main stages of OP-preparation
Organisation of OP process

             SWOT Analysis


             Strategic Goals and Priorities

                    Budget Allocation and Impacts

                              Implementing Arrangements


                                              Ex-ante Evaluation


                                                    Negotiations with EU


                             1 to 2 years
                                      21
LFA consist in...
… a matrix with four columns and four (or more) rows, which
 summarises the key elements of a project/programme:

• The project’s hierarchy of objectives (Project Description
  or Intervention Logic);
• The key external factors critical to the project’s success
  (Assumptions);
• How the project’s achievements will be monitored and
  evaluated (Indicators and Sources of Verification).



                             22
Typical structure of a Logframe




                 23
LFA Helps to Ensure That…
•    the purposes of the priorities and measures are
     consistent with the overall objective
•    indicators of achievement are quantified, verifiable and
     time bound
•    risks and assumptions are adequately defined;
•    any actions required to ensure programme impact are
     stated and time-bound (conditionality)
•    inputs and outputs needed to implement the project are
     sufficiently well-defined



                             24
The Logframe: Diagonal Logic




                25
Programme and Project Level

Intervention Logic        Intervention Logic
Overall objectives        NDP
Project purpose           Overall Objective
Results                   Priorities
Activities                Measures
                          Projects



    Project level          Programme level
                     26
Building a Logframe


        Analysis Phase                                              Planning Phase


Stakeholder analysis – identifying stakeholders        Developing Logframe matrix - project
                                                       structure, testing internal logic & risks,
Problem analysis - key problems, constraints &         formulating measurable indicators
opportunities; cause & effect relationships
                                                       Activity scheduling – determining
Objective analysis – developing solutions;             sequence and dependency of activities;
means to end relationships                             estimating duration, assigning responsibility
Strategy analysis – identifying strategies to          Resource scheduling – from activity
achieve solutions; selection                           schedule, developing input schedules and
                                                       budget



                                                  27
Example 2: Problem Tree
  Problem analysis: the problem tree helps to establish
  the cause/effect relation between problems
                                       Income of artisanal                                      EFFECTS
                                        fishers in decline




              Reduction of the                                 Low selling prices for
               fish resources                                     fishers in the
                                                                     villages



Destruction of the         Illegal fishing           Poor quality of        Limited access to
natural habitats              practices              the processed               market
                                                                                                CAUSES
                                                          catch

                                                        28
Problem Tree  Objective Tree

  • From problem tree to objective tree
  • Cause-Effect becomes Means-End
  • Goal hierarchy
  • Logic verified




                           29
Example 2: Objective Tree
Analysis of Objectives: convert the problems into positive
achievements through establishing means/ends relationships
                                                                                                    ENDS
                                         Income of artisinal
                                         fishers increased



             Depletion of the natural                                Selling price for
              fish stock reduced or                                       fishers
                     stopped                                           increased



 Natural habitats of           Illegal fishing           Processing of the          Access to       MEANS
  fish resources           practices significantly        catch improved         markets improved
     protected                     reduced

                                                               30
Strategy
                                     In the project
Out of the project
  These excluded                                          Income of the
                                                                                                                              OVERALL
 statements should                                       artisanalfishers
                                                          artisan fishers                                                     OBJECTIVE
                                                             increased
  be considered in
   the analysis of
 assumptions/risks
                         Depletion of the                                                Selling price for the
                        natural fish stock                                                fishers increased                   PURPOSE
                       reduced or stopped




        Natural habitats of              Illegal fishing
         fish resources              practices significantly
                                                                            Processing of the
                                                                             catch improved
                                                                                                            Access to the
                                                                                                           markets improved
                                                                                                                              RESULTS
            protected                        reduced

         Fish stock control strategy                                          Market orientation strategy

 Strategy based on policy priorities, cost-benefit, ongoing programmes, budget etc
                                                                            31
Logframe Matrix: Logical
Sequence of Completion




                       +
•Inputs
•Activities Schedule
                           32

Más contenido relacionado

La actualidad más candente

Logical Framework And Project Proposal
Logical Framework And Project ProposalLogical Framework And Project Proposal
Logical Framework And Project Proposalrexcris
 
Eu project managment
Eu project managmentEu project managment
Eu project managment000000000
 
Harrison.g.poole.k
Harrison.g.poole.kHarrison.g.poole.k
Harrison.g.poole.kNASAPMC
 
Logframework and swort thursday
Logframework and swort thursdayLogframework and swort thursday
Logframework and swort thursdayDavid mbwiga
 
Nichols.david
Nichols.davidNichols.david
Nichols.davidNASAPMC
 
Beginners Guide To Logical Framework Approach (BOND)
Beginners Guide To Logical Framework Approach (BOND)Beginners Guide To Logical Framework Approach (BOND)
Beginners Guide To Logical Framework Approach (BOND)rexcris
 
The logical framework matrix approach (LFMA)
The logical framework matrix approach (LFMA)The logical framework matrix approach (LFMA)
The logical framework matrix approach (LFMA)PhDSofiaUniversity
 
Result Base Project Management
Result Base Project ManagementResult Base Project Management
Result Base Project ManagementArifur Rahman
 
The Logical Framework Matrix Approach
The Logical Framework Matrix ApproachThe Logical Framework Matrix Approach
The Logical Framework Matrix ApproachPhDSofiaUniversity
 
Institutionalizing the Use of Evidence for Public Policy: A long path in Mexico
Institutionalizing the Use of Evidence for Public Policy: A long path in MexicoInstitutionalizing the Use of Evidence for Public Policy: A long path in Mexico
Institutionalizing the Use of Evidence for Public Policy: A long path in MexicoUnicefMaroc
 
Best Practices Frameworks 101
Best Practices Frameworks 101Best Practices Frameworks 101
Best Practices Frameworks 101shailsood
 
File 2 removed 4 slides 1
File 2 removed 4 slides 1File 2 removed 4 slides 1
File 2 removed 4 slides 1test prod1
 

La actualidad más candente (20)

Logical Framework And Project Proposal
Logical Framework And Project ProposalLogical Framework And Project Proposal
Logical Framework And Project Proposal
 
Eu project managment
Eu project managmentEu project managment
Eu project managment
 
Logical framework
Logical frameworkLogical framework
Logical framework
 
M&E of the Malaysian 10th Development plan at the Economic Planning Unit
M&E of the Malaysian 10th Development plan at the Economic Planning UnitM&E of the Malaysian 10th Development plan at the Economic Planning Unit
M&E of the Malaysian 10th Development plan at the Economic Planning Unit
 
Harrison.g.poole.k
Harrison.g.poole.kHarrison.g.poole.k
Harrison.g.poole.k
 
Logframework and swort thursday
Logframework and swort thursdayLogframework and swort thursday
Logframework and swort thursday
 
2. The Logical Framework
2. The Logical Framework2. The Logical Framework
2. The Logical Framework
 
Nichols.david
Nichols.davidNichols.david
Nichols.david
 
Logical framework
Logical frameworkLogical framework
Logical framework
 
Lfa
LfaLfa
Lfa
 
Beginners Guide To Logical Framework Approach (BOND)
Beginners Guide To Logical Framework Approach (BOND)Beginners Guide To Logical Framework Approach (BOND)
Beginners Guide To Logical Framework Approach (BOND)
 
The logical framework matrix approach (LFMA)
The logical framework matrix approach (LFMA)The logical framework matrix approach (LFMA)
The logical framework matrix approach (LFMA)
 
Result Base Project Management
Result Base Project ManagementResult Base Project Management
Result Base Project Management
 
The Logical Framework Matrix Approach
The Logical Framework Matrix ApproachThe Logical Framework Matrix Approach
The Logical Framework Matrix Approach
 
BNTF 7 RMF_MIS
BNTF 7 RMF_MISBNTF 7 RMF_MIS
BNTF 7 RMF_MIS
 
Ms4 lfa
Ms4 lfaMs4 lfa
Ms4 lfa
 
Institutionalizing the Use of Evidence for Public Policy: A long path in Mexico
Institutionalizing the Use of Evidence for Public Policy: A long path in MexicoInstitutionalizing the Use of Evidence for Public Policy: A long path in Mexico
Institutionalizing the Use of Evidence for Public Policy: A long path in Mexico
 
Best Practices Frameworks 101
Best Practices Frameworks 101Best Practices Frameworks 101
Best Practices Frameworks 101
 
File 2 removed 4 slides 1
File 2 removed 4 slides 1File 2 removed 4 slides 1
File 2 removed 4 slides 1
 
Symons
SymonsSymons
Symons
 

Similar a 3 programming and tools swot & lfa

5 The Logical Framework - a short course for NGOs
5 The Logical Framework - a short course for NGOs5 The Logical Framework - a short course for NGOs
5 The Logical Framework - a short course for NGOsTony
 
3 proj plan notes
3 proj plan notes3 proj plan notes
3 proj plan notesTony
 
Project Planning module 5 presenter notes
Project Planning module 5 presenter notesProject Planning module 5 presenter notes
Project Planning module 5 presenter notesTony
 
Project Planning module 5 Handout
Project Planning module 5 HandoutProject Planning module 5 Handout
Project Planning module 5 HandoutTony
 
3 proj plan handouts
3 proj plan handouts3 proj plan handouts
3 proj plan handoutsTony
 
Passion+Leadership=Thriving Manager.
Passion+Leadership=Thriving Manager.Passion+Leadership=Thriving Manager.
Passion+Leadership=Thriving Manager.Morné Schutte
 
Foundations of planning ppt @ bec doms bagalkot mba
Foundations of planning ppt @ bec doms bagalkot mbaFoundations of planning ppt @ bec doms bagalkot mba
Foundations of planning ppt @ bec doms bagalkot mbaBabasab Patil
 
2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adbngocjos
 
Elico Solutions' Odoo ERP Project Management Implementation Approach
Elico Solutions' Odoo ERP Project Management Implementation ApproachElico Solutions' Odoo ERP Project Management Implementation Approach
Elico Solutions' Odoo ERP Project Management Implementation ApproachElico Solutions Singapore
 
Borchardt.heidemarie
Borchardt.heidemarieBorchardt.heidemarie
Borchardt.heidemarieNASAPMC
 
Stefanini.trinh
Stefanini.trinhStefanini.trinh
Stefanini.trinhNASAPMC
 
Valuing organizational vision in the development of performance measurement f...
Valuing organizational vision in the development of performance measurement f...Valuing organizational vision in the development of performance measurement f...
Valuing organizational vision in the development of performance measurement f...Fbertrand
 
Enterprise Architecture Program Management Challenges
Enterprise Architecture Program Management ChallengesEnterprise Architecture Program Management Challenges
Enterprise Architecture Program Management ChallengesNashreen Hofmeester
 
Software project management introduction
Software project management introductionSoftware project management introduction
Software project management introductionKanchana Devi
 
2nd Partnership Inception Workshop_Presentation 3: Project planning tools
2nd Partnership Inception Workshop_Presentation 3: Project planning tools2nd Partnership Inception Workshop_Presentation 3: Project planning tools
2nd Partnership Inception Workshop_Presentation 3: Project planning toolsNawsheen Hosenally
 

Similar a 3 programming and tools swot & lfa (20)

5 The Logical Framework - a short course for NGOs
5 The Logical Framework - a short course for NGOs5 The Logical Framework - a short course for NGOs
5 The Logical Framework - a short course for NGOs
 
3 proj plan notes
3 proj plan notes3 proj plan notes
3 proj plan notes
 
Project Planning module 5 presenter notes
Project Planning module 5 presenter notesProject Planning module 5 presenter notes
Project Planning module 5 presenter notes
 
The Logical Framework Approach
The Logical Framework ApproachThe Logical Framework Approach
The Logical Framework Approach
 
Project formulation
Project formulationProject formulation
Project formulation
 
WRI Update: Governance of Forests Initiative (GFI)
WRI Update: Governance of Forests Initiative (GFI)WRI Update: Governance of Forests Initiative (GFI)
WRI Update: Governance of Forests Initiative (GFI)
 
Project Planning module 5 Handout
Project Planning module 5 HandoutProject Planning module 5 Handout
Project Planning module 5 Handout
 
3 proj plan handouts
3 proj plan handouts3 proj plan handouts
3 proj plan handouts
 
Passion+Leadership=Thriving Manager.
Passion+Leadership=Thriving Manager.Passion+Leadership=Thriving Manager.
Passion+Leadership=Thriving Manager.
 
Foundations of planning ppt @ bec doms bagalkot mba
Foundations of planning ppt @ bec doms bagalkot mbaFoundations of planning ppt @ bec doms bagalkot mba
Foundations of planning ppt @ bec doms bagalkot mba
 
2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb
 
Elico Solutions' Odoo ERP Project Management Implementation Approach
Elico Solutions' Odoo ERP Project Management Implementation ApproachElico Solutions' Odoo ERP Project Management Implementation Approach
Elico Solutions' Odoo ERP Project Management Implementation Approach
 
Borchardt.heidemarie
Borchardt.heidemarieBorchardt.heidemarie
Borchardt.heidemarie
 
UNIT - I - ppe.pptx
UNIT - I - ppe.pptxUNIT - I - ppe.pptx
UNIT - I - ppe.pptx
 
Disaster Risk Management
Disaster Risk ManagementDisaster Risk Management
Disaster Risk Management
 
Stefanini.trinh
Stefanini.trinhStefanini.trinh
Stefanini.trinh
 
Valuing organizational vision in the development of performance measurement f...
Valuing organizational vision in the development of performance measurement f...Valuing organizational vision in the development of performance measurement f...
Valuing organizational vision in the development of performance measurement f...
 
Enterprise Architecture Program Management Challenges
Enterprise Architecture Program Management ChallengesEnterprise Architecture Program Management Challenges
Enterprise Architecture Program Management Challenges
 
Software project management introduction
Software project management introductionSoftware project management introduction
Software project management introduction
 
2nd Partnership Inception Workshop_Presentation 3: Project planning tools
2nd Partnership Inception Workshop_Presentation 3: Project planning tools2nd Partnership Inception Workshop_Presentation 3: Project planning tools
2nd Partnership Inception Workshop_Presentation 3: Project planning tools
 

Más de Dagný Gísladóttir (15)

3.4 project level lfa and quality
3.4 project level lfa and quality3.4 project level lfa and quality
3.4 project level lfa and quality
 
3.3 project fiche
3.3 project fiche3.3 project fiche
3.3 project fiche
 
3.1 procurement and prag rules
3.1 procurement and prag rules3.1 procurement and prag rules
3.1 procurement and prag rules
 
2.1 pcm
2.1 pcm2.1 pcm
2.1 pcm
 
1.4 swot and needs assessment
1.4 swot and needs assessment1.4 swot and needs assessment
1.4 swot and needs assessment
 
1.3 contents and processes
1.3 contents and processes1.3 contents and processes
1.3 contents and processes
 
1.2 ipa overview
1.2 ipa overview1.2 ipa overview
1.2 ipa overview
 
Presentation workshop111208 ssg
Presentation workshop111208 ssgPresentation workshop111208 ssg
Presentation workshop111208 ssg
 
3 aspects of the eu methodology 19 october 2011
3   aspects of the eu methodology 19 october 20113   aspects of the eu methodology 19 october 2011
3 aspects of the eu methodology 19 october 2011
 
1 the national and regional perspectives seminar workshop 19 october-2011
1   the national and regional perspectives seminar workshop 19 october-20111   the national and regional perspectives seminar workshop 19 october-2011
1 the national and regional perspectives seminar workshop 19 october-2011
 
6 sept project fiche
6 sept project fiche6 sept project fiche
6 sept project fiche
 
5 project prioritization
5 project prioritization5 project prioritization
5 project prioritization
 
4 sept pcm
4 sept pcm4 sept pcm
4 sept pcm
 
2 ipa overview
2 ipa overview2 ipa overview
2 ipa overview
 
1 content working group iii
1 content working group iii1 content working group iii
1 content working group iii
 

Último

DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningLars Bell
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfPrecisely
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenHervé Boutemy
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024Lorenzo Miniero
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
unit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxunit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxBkGupta21
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxLoriGlavin3
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxLoriGlavin3
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESSALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESmohitsingh558521
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 

Último (20)

DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine Tuning
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache Maven
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
unit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxunit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptx
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptx
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESSALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 

3 programming and tools swot & lfa

  • 1. Sustainable Economic Development of the Sudurnes region, Iceland OP Preparation: Programming Concepts & Tools JOSE MATEOS MORENO Ásbrú, 25 November 2011
  • 2. Content 1. Principles of programming 2. The programming logic 3. Programming tools – SWOT & LFA 2
  • 4. What is Programming ? Grouping a number of temporary, goal-oriented and unique activities, each contributing to reach objectives agreed upon beforehand Questions: Where are we? Where do we want to go? How should we get there? How will we know when we are there? 4
  • 5. The Programme Context Policy Programme Projects 5
  • 6. What Does a Programme Look Like? (example OP Regional Development) OP Global Objective Priority Priority Priority Axis 1 Axis 2 Axis 3 Group of Group of Group of Group of Group of Group of Group of Operations Operations Operations Operations Operations Operations Operations 6
  • 7. The Structure of a Programme Global Impacts Objective Programme Specific Priority Axes Results Objectives Operational Group Outputs Objectives Operations Inputs Programme Operations 7
  • 8. Who’s Responsible For What? Programme Projects Managing Authorities Certifying Authority Audit authority Beneficiaries Intermediate Bodies Monitoring Committees 8
  • 9. Management Structure European Commission SCF Accession Country ? OP Managing Monitoring Authority Committee Priority Intermediate Axis body 9
  • 10. 2. The Programming Logic 10
  • 11. Programming Logic Analysis Strategy Politics Priority Axis Bottom up • Project ideas Group of • Lobbying Operations 11
  • 12. Group of Operations (Measure) Definition • The basic unit of programme management, consisting of a set of similar projects • The means by which a priority axis is implemented over several years which enable operations to be financed. 12
  • 13. Embedding in Existing Policy • IPA is meant to cofinance existing policy, not other way round • Keep it simple: look at existing national structural policies • Start programming process with this analysis of existing policy: this will be your cofinancing table 13
  • 15. OP Policy Life Cycle Detailed programming Planning & programming Programme implementation Monitoring, financial control, evaluation, corrective actions 15
  • 16. Main Stages of OP Preparation Organisation of OP process SWOT Analysis Strategic Goals and Priorities Budget Allocation and Impacts Implementing Arrangements Ex-ante Evaluation Negotiations with EU 1 to 2 years 16
  • 17. Programming Tools Analytical tools Creative tools Structuring tools Entity formulation Brainstorming Problem trees Stakeholder analysis Matching and Objective trees conversion Analysis of trends Robust strategies Clustering approach SWOT analysis Vision formulation Scoping Problem identification Objective formulation LFA approach Benchmarking Synergy check Forecasting Indicator formulation Scenario analysis Risk analysis 17
  • 18. Programming Tools • Focus on two main tools: Analysing: – SWOT analyses Structuring: – Logical Framework Approach (LFA) 18
  • 19. Main Stages of OP Preparation Organisation of OP process SWOT Analysis Strategic Goals and Priorities Budget Allocation and Impacts Implementing Arrangements Ex-ante Evaluation Negotiations with EU 1 to 2 years 19
  • 20. SWOT Analysis Strengths Weaknesses Internal & static External & dynamic Opportunities Threats 20
  • 21. Main stages of OP-preparation Organisation of OP process SWOT Analysis Strategic Goals and Priorities Budget Allocation and Impacts Implementing Arrangements Ex-ante Evaluation Negotiations with EU 1 to 2 years 21
  • 22. LFA consist in... … a matrix with four columns and four (or more) rows, which summarises the key elements of a project/programme: • The project’s hierarchy of objectives (Project Description or Intervention Logic); • The key external factors critical to the project’s success (Assumptions); • How the project’s achievements will be monitored and evaluated (Indicators and Sources of Verification). 22
  • 23. Typical structure of a Logframe 23
  • 24. LFA Helps to Ensure That… • the purposes of the priorities and measures are consistent with the overall objective • indicators of achievement are quantified, verifiable and time bound • risks and assumptions are adequately defined; • any actions required to ensure programme impact are stated and time-bound (conditionality) • inputs and outputs needed to implement the project are sufficiently well-defined 24
  • 26. Programme and Project Level Intervention Logic Intervention Logic Overall objectives NDP Project purpose Overall Objective Results Priorities Activities Measures Projects Project level Programme level 26
  • 27. Building a Logframe Analysis Phase Planning Phase Stakeholder analysis – identifying stakeholders Developing Logframe matrix - project structure, testing internal logic & risks, Problem analysis - key problems, constraints & formulating measurable indicators opportunities; cause & effect relationships Activity scheduling – determining Objective analysis – developing solutions; sequence and dependency of activities; means to end relationships estimating duration, assigning responsibility Strategy analysis – identifying strategies to Resource scheduling – from activity achieve solutions; selection schedule, developing input schedules and budget 27
  • 28. Example 2: Problem Tree Problem analysis: the problem tree helps to establish the cause/effect relation between problems Income of artisanal EFFECTS fishers in decline Reduction of the Low selling prices for fish resources fishers in the villages Destruction of the Illegal fishing Poor quality of Limited access to natural habitats practices the processed market CAUSES catch 28
  • 29. Problem Tree  Objective Tree • From problem tree to objective tree • Cause-Effect becomes Means-End • Goal hierarchy • Logic verified 29
  • 30. Example 2: Objective Tree Analysis of Objectives: convert the problems into positive achievements through establishing means/ends relationships ENDS Income of artisinal fishers increased Depletion of the natural Selling price for fish stock reduced or fishers stopped increased Natural habitats of Illegal fishing Processing of the Access to MEANS fish resources practices significantly catch improved markets improved protected reduced 30
  • 31. Strategy In the project Out of the project These excluded Income of the OVERALL statements should artisanalfishers artisan fishers OBJECTIVE increased be considered in the analysis of assumptions/risks Depletion of the Selling price for the natural fish stock fishers increased PURPOSE reduced or stopped Natural habitats of Illegal fishing fish resources practices significantly Processing of the catch improved Access to the markets improved RESULTS protected reduced Fish stock control strategy Market orientation strategy Strategy based on policy priorities, cost-benefit, ongoing programmes, budget etc 31
  • 32. Logframe Matrix: Logical Sequence of Completion + •Inputs •Activities Schedule 32