SlideShare una empresa de Scribd logo
1 de 37
A SEMINAR PRESENTATION
ON
Kota Super thermal power
station

ELECTRICAL ENGINEERING
SKIT, JAIPUR

Presented By :Rohit Pareta







Kota Super Thermal Power Station is
coal based steam plant.
It Is Located on the left bank of
Chambal river in Kota (Rajasthan).
Total generation capacity is
1240MW.
Required 250 hectares land.
The project was proposed By the
Central Electricity Authority and
production start in 1983.
Good transportation Network.
Abundant amount of water.
Nearest to load center.
Good geographical features to built
a plant.
Availability of land to build new
units .
Availability of both skilled person
and labor.
Synchronising Date of units
Stage

Unit No.

Capacity(MW)

Synchronising
Date

Cost(Rs. Crore)

I

1

110

17.1.1983

143

2

110

13.7.1983

3

210

25.9.1988

4

210

1.5.1989

III

5

210

26.3.1994

480

IV

6

195

31.7.2003

635

V

7

195

30.5.2009

880

II

480
Basic Plant Layout
FUELS
(A) Coal.
(i) Type :
Stack Coal
(ii) Calorific Value:
4450 K.Cal./Kg.
(iii) Quantity Used.:
3074 tonnes per day.
(iv) Ash contents.:
40%
(v) Type of Handling.
Belt Conveyor.
(vii) Type of disposal of Ash.
a) Fly Ash.
b) Bottom Ash. Wet.
(B) OIL
(i) Type:
Furnace Oil.
(ii) Qty. used:
As per requirement &
conditions.
Main Equipments
•
•
•
•
•
•
•
•
•

Coal Handling Plant
Boiler
Turbine, Generator
Super Heater & Re- Heater
Cooling System
Water Treating Plant
Ash Handling Plant
Control Room
Advantages & Disadvantages
OVERVIEW OF COAL HANDLING PLANT
Row coal from Bharat
coal ltd. Dhanbad &
bilaspur(MP)

To KSTPS from Gurla via a
single railway track

Wagon trippler

Coal size reduced by 20 mm

Bunkers

Crusher
house

Hoppers

Raw coal
feeders
CONVEYING
SYSTEM
Coal mills
(pulverization)

BOILER FURNACE
COAL HANDLING PLANT
• The Coal Received from BHARAT COKING COAL LTD. DHANBAD
& SOUTH EASTERN COAL FIELD LTD. BILASPUR(M.P.) by train.

• Everyday 3- 4 trains of coal are unloaded, each train
consists 58 wagons.

•Specification of conveying system:
oBelt width : 1400mm
oSpeed : 2.2m/sec
oTotal install power : 360kw
oCapacity : 1350/750 ton/hr
oNo. of conveyor: 38
Boiler

• It is a closed vessel in which water under
pressure is converted into steam.
• Hot water or steam used to transfer heat to a
process.
• A boiler is always designed to absorb
maximum amount of heat released in process
of combustion.
• Furnace:- It is primary part of boiler where the
fuel is burnt to liberate the heat energy.
Overview of Boiler

DM water

Boiler water tubes
& various stages

Super
heated
steam

Flue gases
Air from
environment via
draft fans

Pulverized coal

Boiler furnace

Ash handling
plant
Types of Boilers

• Fire tube boiler

• Water tube Boiler
Boiler at KSTPS
Super heater
• Super heater consists
group of tubes.
• The tubes are heated by
the heat of combustion
gases during their passage
from furnace to chimney,
so the temperature
increased.
• Super heater remove the
moisture from the steam
leaving from the boiler
tubes.

Economizer
• Economizer is a device
which recover the heat
from the flue gases on
their way to chimney.
• It increases the 10-12%
efficiency of the plant.
Super Heater and Economiser
Air Pre-heater
• Function- To raise the
tempreatur of air.
• Benefits- Increase the
efficiency of plant.
• Type- Plate, Tubular,
Regenrative.
• KSTPS uses
Regenerative type.
STEAM TURBINE
BOILER & SUPERHEATER
STEAM AT
545 C

STEAM AT
535 C
H P TURBINE

REHEATER

M P TURBINE
STEAM AT
545 C

STEAM AT
535 C
L P TURBINE
TECHNICAL DATA OF 110 MW TURBINE
•
•
•
•

1.
2.
3.
4.

Rated output
: 110 MW.
Economic output
: 95 MW.
Rated speed
: 3000 rpm
Direction of rotation viewing from : Clockwise
the front bearing pedestal.
• 5. Rated temperature of steam before :
535oC
the stop valve.
• 6. Maximum temperature of steam before : 545oC
the stop valve.
TECHNICAL DATA OF 210 MW
TURBINE
•

Rated Output

:

210 MW.

•

Rated Speed.

:

3000 rpm.

• Main steam pressure.

:

150 Kg./Cm2

• Main steam temperature.

:

535oC.

• Reheat steam temperature.

:

• Weight of turbine.

:

• Overall length.

:

535oC.
475 T approx.
16.975 Mtrs. approx.
Cooling System
• In KSTPS hydrogen cooling
system is employed for generator
cooling.
• Hydrogen is used because of its
superior cooling properties & low
density.
• Thermal conductivity of H2 7.3
times of air.
• Seal oil system are used in turbine
for less friction in bearing.
• Water cooling also used for any
kind of fire.
WATER TREATMENT PLANT
The principle problem in high pressure boiler are
corrosion and steam impurities. These impurities
form deposite over turbine blades and nozzeles.
Corrosion costs power station crores rupees in
repair.
Process flow sheet of pretreatment
plant
Chlorine Lime Alum
Raw
Water

Clarifier
CWST

Raw Water
from
Reservoir

Storage
Tank

Pressure
Filter

DMST
Water Treatment Plant
 Pressure filter removes
undisclosed impurities from
raw water.
 Carbon filter removes excess
chlorine from clarified
water.
 D.M. plant removes dissolved
impurities from clarified
water.
 Conductivity ,pH & silica
content of this water must be
checked time to time.
Water Flow

B
O
I
L
E
R

B.F.P
Treatment
plant

Raw Water

ECONOMIZER

STEAM

C
O
N
D
E
N
S
E
R

COOLING
HOT WATER
ASH HANDLING PLANT
This plant can be divided into three sub plants as follows :-

1)Fuel and Ash Plant:It is specially designed for bottom ash and fly ash in
electro static precipitator economizer and air preheaters hoppers.
2)Air and Gas Plant:The flue gases after passing through the ElectroStatic Precipitator is exhausted through chimney.
3) Ash Disposal and & Dust Collection
Plant:Dry free fly ash is
collected in two
number of 31 fly ash
hopper which are
handled by two
independent fly
ash system.
ASH HANDLING
ID Fan

Boiler
ESP

Dry Ash

water

Fly Ash
To coal mill
To furnace

wet ash

A
P
H

PA Fan
FD Fan
Fly ash utilization
1). FLY ASH:
• Fly ash is used for making Cement and Bricks.
2). BOTTOM ASH:
• Used for increase the fertility of soil.
• Construction of Roads
Steam pressure &
control desk

Turbine desk

Fan control
desk

Fuel control
desk

Generator
control
desk
KSTPS supplies power to…..
•
•
•
•
•
•

220 KV GSS Sakatura
JAIPUR (Hirapura & Sanganer GSS)
BYAWAR
Power Grid Corporation of India
JHALAWAR(Modak)
10% use in auxiliary supply.
Advantages
• The fuel used is quite cheap.
• Less initial cost as compared to other generating
plants.
• It can be installed at any place irrespective of the
existence of coal. The coal can be transported to the
site of the plant by rail or road.
• It require less space as compared to Hydro power
plants.
• Cost of generation is less than that of diesel power
plants.
Disadvantages
• It pollutes the atmosphere due to production
of large amount of smoke and fumes.
• It is costlier in running cost as compared to
Hydro electric plants.
• The overall efficiency of thermal power plant
is less then 40 %.
• Disposal of ash is major problem.
Thank You !!!
Queries….???

Más contenido relacionado

La actualidad más candente

kstps summer training 36 slides
 kstps summer training 36 slides kstps summer training 36 slides
kstps summer training 36 slidesDanveer Singh
 
Overview of mejia thermal power station, DVC
Overview of mejia thermal power station, DVCOverview of mejia thermal power station, DVC
Overview of mejia thermal power station, DVCNITISHKHALKHO
 
Kota Super Thermal Power Station Training report
Kota Super Thermal Power Station Training reportKota Super Thermal Power Station Training report
Kota Super Thermal Power Station Training reportDeepak Solanki
 
ppt on kota super thermal power plant
ppt on kota super thermal power plantppt on kota super thermal power plant
ppt on kota super thermal power plantArpit Budania
 
Thermal Power Plant training Report
Thermal Power Plant training ReportThermal Power Plant training Report
Thermal Power Plant training ReportShani Kumar Singh
 
kota super thermal Power station training report
kota super thermal Power station training reportkota super thermal Power station training report
kota super thermal Power station training reportEr. Aman Agrawal
 
kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptEr. Aman Agrawal
 
kota thermal power plant
kota thermal power plantkota thermal power plant
kota thermal power plantravi kant
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...haxxo24
 
GSECL Electrical branch Training Report
GSECL Electrical branch Training ReportGSECL Electrical branch Training Report
GSECL Electrical branch Training ReportUtsav Yagnik
 
Supercritical boiler ntpc sipat
Supercritical boiler ntpc sipatSupercritical boiler ntpc sipat
Supercritical boiler ntpc sipatpratikguptateddy
 
VOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBAVOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBAVIKASH BAGHEL
 
GANDHINAGAR THERMAL POWERPLANT
GANDHINAGAR THERMAL POWERPLANTGANDHINAGAR THERMAL POWERPLANT
GANDHINAGAR THERMAL POWERPLANTNiravDesai66
 
Presentation on thermal power plant
Presentation on thermal power plantPresentation on thermal power plant
Presentation on thermal power plantRashmi Nimje
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plantRahul Jalan
 

La actualidad más candente (20)

kstps summer training 36 slides
 kstps summer training 36 slides kstps summer training 36 slides
kstps summer training 36 slides
 
Overview of mejia thermal power station, DVC
Overview of mejia thermal power station, DVCOverview of mejia thermal power station, DVC
Overview of mejia thermal power station, DVC
 
Kota Super Thermal Power Station Training report
Kota Super Thermal Power Station Training reportKota Super Thermal Power Station Training report
Kota Super Thermal Power Station Training report
 
ppt on kota super thermal power plant
ppt on kota super thermal power plantppt on kota super thermal power plant
ppt on kota super thermal power plant
 
Thermal Power Plant training Report
Thermal Power Plant training ReportThermal Power Plant training Report
Thermal Power Plant training Report
 
kota super thermal Power station training report
kota super thermal Power station training reportkota super thermal Power station training report
kota super thermal Power station training report
 
Kstps ppt
Kstps pptKstps ppt
Kstps ppt
 
kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training ppt
 
kota thermal power plant
kota thermal power plantkota thermal power plant
kota thermal power plant
 
GSECL TPS SIKKA
GSECL TPS SIKKAGSECL TPS SIKKA
GSECL TPS SIKKA
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
GSECL Electrical branch Training Report
GSECL Electrical branch Training ReportGSECL Electrical branch Training Report
GSECL Electrical branch Training Report
 
Supercritical boiler ntpc sipat
Supercritical boiler ntpc sipatSupercritical boiler ntpc sipat
Supercritical boiler ntpc sipat
 
Thermal power plant ppt
Thermal power plant pptThermal power plant ppt
Thermal power plant ppt
 
DAMODAR VALLEY CORPORATION(THERMAL POWER STATION),DURGAPUR seminar
DAMODAR VALLEY CORPORATION(THERMAL POWER STATION),DURGAPUR seminarDAMODAR VALLEY CORPORATION(THERMAL POWER STATION),DURGAPUR seminar
DAMODAR VALLEY CORPORATION(THERMAL POWER STATION),DURGAPUR seminar
 
VOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBAVOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBA
 
GANDHINAGAR THERMAL POWERPLANT
GANDHINAGAR THERMAL POWERPLANTGANDHINAGAR THERMAL POWERPLANT
GANDHINAGAR THERMAL POWERPLANT
 
Presentation on thermal power plant
Presentation on thermal power plantPresentation on thermal power plant
Presentation on thermal power plant
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 

Similar a Kstps ppt

KSTPS presentation.pptx
KSTPS presentation.pptxKSTPS presentation.pptx
KSTPS presentation.pptxParulChandna6
 
Thermal power plant
 Thermal power plant  Thermal power plant
Thermal power plant sagar20jain
 
Summer Training Presentation Kota Super Thermal Power Station
Summer Training Presentation Kota Super Thermal Power StationSummer Training Presentation Kota Super Thermal Power Station
Summer Training Presentation Kota Super Thermal Power StationFellowBuddy.com
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant pptPrakash Jarotia
 
Ntpc dadri ppt by pc sharma
Ntpc dadri ppt by pc sharmaNtpc dadri ppt by pc sharma
Ntpc dadri ppt by pc sharmaPrakash Sharma
 
KSTPS PPT Astha.pptx
KSTPS PPT Astha.pptxKSTPS PPT Astha.pptx
KSTPS PPT Astha.pptxssuser4c2635
 
Presentation on Kota super Thermal Power Station
Presentation on Kota super Thermal Power StationPresentation on Kota super Thermal Power Station
Presentation on Kota super Thermal Power Stationpukhraj palariya
 
Kota super thermal power plant
Kota super thermal power plantKota super thermal power plant
Kota super thermal power plantR G Sanjay Prakash
 
Thermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E JaipurThermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E JaipurChandra veer singh
 
Coal based power plant
Coal based power plantCoal based power plant
Coal based power plantGaurav Kaushik
 
Kota super thermal power plant seminar
Kota super thermal power plant seminarKota super thermal power plant seminar
Kota super thermal power plant seminarCentury Rayon
 
OVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTS
OVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTSOVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTS
OVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTSharshavardhan sivadi
 
Ppt on btps bokaro industrial training
Ppt on btps bokaro industrial trainingPpt on btps bokaro industrial training
Ppt on btps bokaro industrial trainingRadhe Shyam
 
Ppt of internship at dccpp
Ppt of internship at dccppPpt of internship at dccpp
Ppt of internship at dccppDurgSingh
 

Similar a Kstps ppt (20)

KSTPS presentation.pptx
KSTPS presentation.pptxKSTPS presentation.pptx
KSTPS presentation.pptx
 
Thermal power plant
 Thermal power plant  Thermal power plant
Thermal power plant
 
kota super thermal poer plant
kota super thermal poer plantkota super thermal poer plant
kota super thermal poer plant
 
Ntpc dadri ppt
Ntpc dadri pptNtpc dadri ppt
Ntpc dadri ppt
 
power plant ppt
power plant pptpower plant ppt
power plant ppt
 
Summer Training Presentation Kota Super Thermal Power Station
Summer Training Presentation Kota Super Thermal Power StationSummer Training Presentation Kota Super Thermal Power Station
Summer Training Presentation Kota Super Thermal Power Station
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
 
Ntpc dadri ppt by pc sharma
Ntpc dadri ppt by pc sharmaNtpc dadri ppt by pc sharma
Ntpc dadri ppt by pc sharma
 
KSTPS PPT Astha.pptx
KSTPS PPT Astha.pptxKSTPS PPT Astha.pptx
KSTPS PPT Astha.pptx
 
Presentation on Kota super Thermal Power Station
Presentation on Kota super Thermal Power StationPresentation on Kota super Thermal Power Station
Presentation on Kota super Thermal Power Station
 
Kota super thermal power plant
Kota super thermal power plantKota super thermal power plant
Kota super thermal power plant
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
 
Thermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E JaipurThermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E Jaipur
 
Coal based power plant
Coal based power plantCoal based power plant
Coal based power plant
 
Kota super thermal power plant seminar
Kota super thermal power plant seminarKota super thermal power plant seminar
Kota super thermal power plant seminar
 
OVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTS
OVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTSOVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTS
OVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTS
 
ntpc dadri
ntpc dadri ntpc dadri
ntpc dadri
 
Ppt on btps bokaro industrial training
Ppt on btps bokaro industrial trainingPpt on btps bokaro industrial training
Ppt on btps bokaro industrial training
 
Ntpc2 111125042448-phpapp02
Ntpc2 111125042448-phpapp02Ntpc2 111125042448-phpapp02
Ntpc2 111125042448-phpapp02
 
Ppt of internship at dccpp
Ppt of internship at dccppPpt of internship at dccpp
Ppt of internship at dccpp
 

Último

8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditNhtLNguyn9
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 

Último (20)

8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal audit
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 

Kstps ppt

  • 1. A SEMINAR PRESENTATION ON Kota Super thermal power station ELECTRICAL ENGINEERING SKIT, JAIPUR Presented By :Rohit Pareta
  • 2.
  • 3.      Kota Super Thermal Power Station is coal based steam plant. It Is Located on the left bank of Chambal river in Kota (Rajasthan). Total generation capacity is 1240MW. Required 250 hectares land. The project was proposed By the Central Electricity Authority and production start in 1983.
  • 4. Good transportation Network. Abundant amount of water. Nearest to load center. Good geographical features to built a plant. Availability of land to build new units . Availability of both skilled person and labor.
  • 5. Synchronising Date of units Stage Unit No. Capacity(MW) Synchronising Date Cost(Rs. Crore) I 1 110 17.1.1983 143 2 110 13.7.1983 3 210 25.9.1988 4 210 1.5.1989 III 5 210 26.3.1994 480 IV 6 195 31.7.2003 635 V 7 195 30.5.2009 880 II 480
  • 7. FUELS (A) Coal. (i) Type : Stack Coal (ii) Calorific Value: 4450 K.Cal./Kg. (iii) Quantity Used.: 3074 tonnes per day. (iv) Ash contents.: 40% (v) Type of Handling. Belt Conveyor. (vii) Type of disposal of Ash. a) Fly Ash. b) Bottom Ash. Wet. (B) OIL (i) Type: Furnace Oil. (ii) Qty. used: As per requirement & conditions.
  • 8. Main Equipments • • • • • • • • • Coal Handling Plant Boiler Turbine, Generator Super Heater & Re- Heater Cooling System Water Treating Plant Ash Handling Plant Control Room Advantages & Disadvantages
  • 9. OVERVIEW OF COAL HANDLING PLANT Row coal from Bharat coal ltd. Dhanbad & bilaspur(MP) To KSTPS from Gurla via a single railway track Wagon trippler Coal size reduced by 20 mm Bunkers Crusher house Hoppers Raw coal feeders CONVEYING SYSTEM Coal mills (pulverization) BOILER FURNACE
  • 10. COAL HANDLING PLANT • The Coal Received from BHARAT COKING COAL LTD. DHANBAD & SOUTH EASTERN COAL FIELD LTD. BILASPUR(M.P.) by train. • Everyday 3- 4 trains of coal are unloaded, each train consists 58 wagons. •Specification of conveying system: oBelt width : 1400mm oSpeed : 2.2m/sec oTotal install power : 360kw oCapacity : 1350/750 ton/hr oNo. of conveyor: 38
  • 11. Boiler • It is a closed vessel in which water under pressure is converted into steam. • Hot water or steam used to transfer heat to a process. • A boiler is always designed to absorb maximum amount of heat released in process of combustion. • Furnace:- It is primary part of boiler where the fuel is burnt to liberate the heat energy.
  • 12. Overview of Boiler DM water Boiler water tubes & various stages Super heated steam Flue gases Air from environment via draft fans Pulverized coal Boiler furnace Ash handling plant
  • 13. Types of Boilers • Fire tube boiler • Water tube Boiler
  • 15. Super heater • Super heater consists group of tubes. • The tubes are heated by the heat of combustion gases during their passage from furnace to chimney, so the temperature increased. • Super heater remove the moisture from the steam leaving from the boiler tubes. Economizer • Economizer is a device which recover the heat from the flue gases on their way to chimney. • It increases the 10-12% efficiency of the plant.
  • 16. Super Heater and Economiser
  • 17. Air Pre-heater • Function- To raise the tempreatur of air. • Benefits- Increase the efficiency of plant. • Type- Plate, Tubular, Regenrative. • KSTPS uses Regenerative type.
  • 18. STEAM TURBINE BOILER & SUPERHEATER STEAM AT 545 C STEAM AT 535 C H P TURBINE REHEATER M P TURBINE STEAM AT 545 C STEAM AT 535 C L P TURBINE
  • 19.
  • 20. TECHNICAL DATA OF 110 MW TURBINE • • • • 1. 2. 3. 4. Rated output : 110 MW. Economic output : 95 MW. Rated speed : 3000 rpm Direction of rotation viewing from : Clockwise the front bearing pedestal. • 5. Rated temperature of steam before : 535oC the stop valve. • 6. Maximum temperature of steam before : 545oC the stop valve.
  • 21. TECHNICAL DATA OF 210 MW TURBINE • Rated Output : 210 MW. • Rated Speed. : 3000 rpm. • Main steam pressure. : 150 Kg./Cm2 • Main steam temperature. : 535oC. • Reheat steam temperature. : • Weight of turbine. : • Overall length. : 535oC. 475 T approx. 16.975 Mtrs. approx.
  • 22. Cooling System • In KSTPS hydrogen cooling system is employed for generator cooling. • Hydrogen is used because of its superior cooling properties & low density. • Thermal conductivity of H2 7.3 times of air. • Seal oil system are used in turbine for less friction in bearing. • Water cooling also used for any kind of fire.
  • 23. WATER TREATMENT PLANT The principle problem in high pressure boiler are corrosion and steam impurities. These impurities form deposite over turbine blades and nozzeles. Corrosion costs power station crores rupees in repair.
  • 24. Process flow sheet of pretreatment plant Chlorine Lime Alum Raw Water Clarifier CWST Raw Water from Reservoir Storage Tank Pressure Filter DMST
  • 25. Water Treatment Plant  Pressure filter removes undisclosed impurities from raw water.  Carbon filter removes excess chlorine from clarified water.  D.M. plant removes dissolved impurities from clarified water.  Conductivity ,pH & silica content of this water must be checked time to time.
  • 27. ASH HANDLING PLANT This plant can be divided into three sub plants as follows :- 1)Fuel and Ash Plant:It is specially designed for bottom ash and fly ash in electro static precipitator economizer and air preheaters hoppers. 2)Air and Gas Plant:The flue gases after passing through the ElectroStatic Precipitator is exhausted through chimney.
  • 28. 3) Ash Disposal and & Dust Collection Plant:Dry free fly ash is collected in two number of 31 fly ash hopper which are handled by two independent fly ash system.
  • 29. ASH HANDLING ID Fan Boiler ESP Dry Ash water Fly Ash To coal mill To furnace wet ash A P H PA Fan FD Fan
  • 30. Fly ash utilization 1). FLY ASH: • Fly ash is used for making Cement and Bricks. 2). BOTTOM ASH: • Used for increase the fertility of soil. • Construction of Roads
  • 31. Steam pressure & control desk Turbine desk Fan control desk Fuel control desk Generator control desk
  • 32.
  • 33. KSTPS supplies power to….. • • • • • • 220 KV GSS Sakatura JAIPUR (Hirapura & Sanganer GSS) BYAWAR Power Grid Corporation of India JHALAWAR(Modak) 10% use in auxiliary supply.
  • 34. Advantages • The fuel used is quite cheap. • Less initial cost as compared to other generating plants. • It can be installed at any place irrespective of the existence of coal. The coal can be transported to the site of the plant by rail or road. • It require less space as compared to Hydro power plants. • Cost of generation is less than that of diesel power plants.
  • 35. Disadvantages • It pollutes the atmosphere due to production of large amount of smoke and fumes. • It is costlier in running cost as compared to Hydro electric plants. • The overall efficiency of thermal power plant is less then 40 %. • Disposal of ash is major problem.