The document summarizes container terminal projects at Cai Mep area including details about draft, operation timelines, and capacities. It lists 14 proposed terminals, their expected draft depths, and planned operation times. It also provides distances from Cai Mep to major industrial zones and details on the two phases of the I Container Terminal Project including area, berth length, equipment, vessel capacity, annual throughput, and operation models.
2. LONG AN PROVINCE DONG NAI PROVINCE BINH DUONG PROVINCE BA RIA – VUNG TAU PROVINCE - CaiMep HO CHI MINH CITY
3. I CONTAINER TERMINAL PROJECT AT CAI MEP AREA -14m -14m -12 m G Loc Name Draft Time Operation N SITV (HPH) 12 m 7/2010 I SP-PSA (PSA) 12 m 6/2009 G TCCT (SNP) 14 m 6/2009 G TCIT (SNP & WHL,HJS,MOL) 14 m 01/2011 E CMIT (APMT) 14 m 04/2011 D ODA-CAIMEP (Vietnam GOV) 14 m 12/2012 C SSIT (SSA) 14 m 10/2011 B Germalink (CGM-CMA) 14 m 2015 A Cai Mep Downstream 14 m postponed
4.
5. T CC T Nhon Trach CatLai Bien Hoa Binh Duong Ho Chi Minh city DISTANCE FROM HO CHI MINH MAJOR INDUSTRY ZONE TO CAIMEP CaiMep Hiep Phuoc IP 50 km 77 km 65 km 48 km
6. PHASE 1 PHASE 2 Total area 200,000sqm 400,000sqm Berth length 300m 590m Equipment 03 Post-pana QMGCs; 10 RTGs 6+1, 15 trailers, 04 reach-stakers 06 Post-pana QMGCs; 20 RTGs 6+1, 30 trailers, 01 reach-staker Vessel capacity 110,000-DWT (or 10,000-TEU) 110,000-DWT (or 10,000-TEU) Annual capacity 600,000 TEUs 1,200,00 TEUs Operation model Managed by TCCT Joint Stock Company Managed by the JV Company (TCIT) Construction time January 2006 Late 2008 Operation time June 2009 January 15, 2011