3. MS Project Perspective on Duration Duration: How long it will take to complete a task/activity and thereby contribute to building a deliverable Given: The productive work required and the units of production capacity available Expressed as time (minutes; hours; days)
4. MS Project Perspective on Duration Productive Work: How long it will take to complete a task/activity and thereby contribute to building a deliverable Given: The productive work required and the units of production capacity available Expressed as time (minutes; hours; days)
5. MS Project Perspective on Duration Unit of Capacity Available for Work The availability of productive capacity to conduct work Given The Calendar configuration in MS Project Expressed as availability (100 = full availability)
6. 16 8/.5 Duration = Work/Units 8 16 *.5 Work = duration *Units .5 8/16 units = Work/duration