SlideShare a Scribd company logo
1 of 12
Technician Training: Startup Basics
Startup Basics
o Pre-Power – Instructions & Checklist
o Power Checks
o Pumps & Rotation Checks
o Actuated Valves
o Sensors & Instrumentation
o Control Panel PLC Input-Output
o Alarm Log Accuracy
o Data Communications
o Before activating power to the control panel network, it is important to have a
complete pre-check
 Energizing the panels with wiring incomplete or incorrect can be a safety
issue and can damage equipment
o Fuel System controls are a network of panels and devices with multiple
interconnecting wires
 It is important that all of the elements of the network be complete and
correct prior to energizing any panel within the network
 Check every device & every panel for correct wire terminations
 Check for any loose wires in terminal blocks
 Check for damage wire insulation
 Check for frayed wires at terminations
 Check for open panels or junction boxes
 Check that all wire is stranded copper conductors
Pre-Power
o Power wiring is usually performed under a separate contract
 After a complete pre-power check - Observer power connections & work
with the electrical contractor to activate and verify circuits
o When the power circuit is activated – Check at the control panel for the correct
voltage and phases where applicable
o With the proper checks, the control panels can be energized by the internal
circuit breakers, fuses, or disconnects
 The PLCs should power up and display a green power-on indicator
Power Check
o Single Phase & Three Phase pumps can rotate in either direction
 Rotation can be checked by observing the fan on the motor, while the pump motor
starter is momentarily bumped
 DO NOT run the dry pump for more than a few seconds
 Submersible pumps usually only operate in one direction and a check is not required
o Pumps should be marked with the direction of rotation, or refer to the sketch for the
common Viking Pump orientation
 Moving fluid along the long arc of the pump cavity
Pumps & Rotation Check
o The method to change directions is noted on the motor
 Single Phase – Usually interchange wires 5 & 8
 Three Phase – Interchange any two power leads
o When fluid is available to operate the pumps under load, the amp load on the
pump power wire should be checked to assure that it is in normal range
 The overload trip setting should be checked to match the full load amp
(FLA) noted on the motor nameplate
Pumps & Rotation Check (cont.)
o When the control panel is energized, all actuated valves should move to the closed
position, unless specifically programmed otherwise
 Confirm the closed valve position for all actuators by the actuator indication dial
 Check the valve stem to confirm that the valve itself is in fact closed & that the
closed position is indicated on the control panel screen
o Use the control panel to move the actuated valves – one by one – to the open position
 Confirm that the correct valve moves to the open position & that the control panel
screen indicates open
o Common errors in wiring actuators
 Open/Closed command signals are switched, Open/Closed limit switch signals are
switched, wiring not secured
Actuated Valves
o When the control panel is energized – All sensors should be in their normal
position
 Control Panel screen should be checked to confirm sensor position
o Where possible the sensor state should be changed by manipulating the sensor,
and confirm that the control panel indication changes to the proper condition
o Common Errors
 Loose wire connections at the sensor or the panel termination
Sensors & Instrumentation
o Control panel schematic – relates the sensor or valve wire termination # to an
input or output # on the PLC
o PLC has indicators for inputs/outputs for the on/off state
 Review wiring schematic and manipulate the sensor to generate a PLC
input
 Confirm that the correct PLC input is generated
o If problems are identified with valves and sensor indications on the PLC screen,
check that associated input or output on the PLC to see if it is in fact activated
Check Control Panel PLC Input/Output
o If the PLC input is not activated, check that the sensor wire is landed on the
correct terminal block & the wire termination is good
 Then check that the power wire going out to the sensor is terminated
correctly in the panel
 Recheck the wiring terminations at the sensor and confirm that there is
power on the sensor COM wire
 For an on/off sensor, disconnect the sensor and use a continuity test
with a Fluke to confirm that the sensor is good and changes state
properly
Check Control Panel PLC Input/Output (cont.)
o Alarm Log – Records date, time, and location of the alarms for the operator
o As the sensors are tested, confirm that the alarm log is generated accurately
o If the log is not accurate and the PLC input check correctly, then it is likely a
programming issue
Check Alarm Log Accuracy
o The master control panel likely has a BMS interface
 When the fuel system startup is complete the integration of the system should be checked
o BMS interface is dry contacts only
 Conditions such as a leak/general alarm should be generated and confirmed to be received by
the BMS system
o Typically the BMS has a data connection with the fuel system and up to hundreds of points of
monitoring
 The first step is to make sure that the BMS is communicating properly
 Can it see the fuel system panel on its network and can it read some obvious values like
Pump Manual Mode/Tank Volume
o Once communications to the BMS valid – Check individual points
 Operate the fuel system or manipulate sensors to generate the required points
 If the inputs are correct at the PLC, then any BMS discrepancy is a pogromming issue,
either within the PLC or at the BMS
Check Data Communications

More Related Content

What's hot

Ford OBD1 Code List (PDF)
Ford OBD1 Code List (PDF)Ford OBD1 Code List (PDF)
Ford OBD1 Code List (PDF)Tim Miller
 
OBD2 Powertrain Code List (P2A00- P2FXX)
OBD2 Powertrain Code List (P2A00- P2FXX)OBD2 Powertrain Code List (P2A00- P2FXX)
OBD2 Powertrain Code List (P2A00- P2FXX)Tim Miller
 
GM OBD1 Code List (PDF)
GM OBD1 Code List (PDF)GM OBD1 Code List (PDF)
GM OBD1 Code List (PDF)Tim Miller
 
GM OBD1 Code List (PDF)
GM OBD1 Code List (PDF)GM OBD1 Code List (PDF)
GM OBD1 Code List (PDF)Tim Miller
 
Ford OBD2 Codes
Ford OBD2 CodesFord OBD2 Codes
Ford OBD2 CodesTim Miller
 
Crp680 new common rail pump tester
Crp680 new common rail pump testerCrp680 new common rail pump tester
Crp680 new common rail pump testerWendy Diesel
 
Chevrolet OBD2 Codes
Chevrolet OBD2 CodesChevrolet OBD2 Codes
Chevrolet OBD2 CodesTim Miller
 
Honda/ Acura OBD2 Code List (PDF)
Honda/ Acura OBD2 Code List (PDF)Honda/ Acura OBD2 Code List (PDF)
Honda/ Acura OBD2 Code List (PDF)Tim Miller
 
OBD2 Powertrain Code List (P2700- P2799)
OBD2 Powertrain Code List (P2700- P2799)OBD2 Powertrain Code List (P2700- P2799)
OBD2 Powertrain Code List (P2700- P2799)Tim Miller
 
Variable speed fire pump controllers
Variable speed fire pump controllersVariable speed fire pump controllers
Variable speed fire pump controllersmichaeljmack
 
Nissan OBD2 Codes
Nissan OBD2 CodesNissan OBD2 Codes
Nissan OBD2 CodesTim Miller
 
GM OBD2 Code List (PDF)
GM OBD2 Code List (PDF)GM OBD2 Code List (PDF)
GM OBD2 Code List (PDF)Tim Miller
 
OBD2 Powertrain Code List (P2100- P2199)
OBD2 Powertrain Code List (P2100- P2199)OBD2 Powertrain Code List (P2100- P2199)
OBD2 Powertrain Code List (P2100- P2199)Tim Miller
 
Hyundai OBD2 Codes
Hyundai OBD2 CodesHyundai OBD2 Codes
Hyundai OBD2 CodesTim Miller
 
OBD2 Powertrain Code List (P2600- P2699)
OBD2 Powertrain Code List (P2600- P2699)OBD2 Powertrain Code List (P2600- P2699)
OBD2 Powertrain Code List (P2600- P2699)Tim Miller
 
Land Rover OBD2 Codes
Land Rover OBD2 CodesLand Rover OBD2 Codes
Land Rover OBD2 CodesTim Miller
 
Dodge/Chrysler/Jeep OBD2 Codes
Dodge/Chrysler/Jeep OBD2 CodesDodge/Chrysler/Jeep OBD2 Codes
Dodge/Chrysler/Jeep OBD2 CodesTim Miller
 
Advanced motion controls b25a40
Advanced motion controls b25a40Advanced motion controls b25a40
Advanced motion controls b25a40Electromate
 

What's hot (20)

Ford OBD1 Code List (PDF)
Ford OBD1 Code List (PDF)Ford OBD1 Code List (PDF)
Ford OBD1 Code List (PDF)
 
OBD2 Powertrain Code List (P2A00- P2FXX)
OBD2 Powertrain Code List (P2A00- P2FXX)OBD2 Powertrain Code List (P2A00- P2FXX)
OBD2 Powertrain Code List (P2A00- P2FXX)
 
GM OBD1 Code List (PDF)
GM OBD1 Code List (PDF)GM OBD1 Code List (PDF)
GM OBD1 Code List (PDF)
 
Codes
CodesCodes
Codes
 
GM OBD1 Code List (PDF)
GM OBD1 Code List (PDF)GM OBD1 Code List (PDF)
GM OBD1 Code List (PDF)
 
Ford OBD2 Codes
Ford OBD2 CodesFord OBD2 Codes
Ford OBD2 Codes
 
Crp680 new common rail pump tester
Crp680 new common rail pump testerCrp680 new common rail pump tester
Crp680 new common rail pump tester
 
Chevrolet OBD2 Codes
Chevrolet OBD2 CodesChevrolet OBD2 Codes
Chevrolet OBD2 Codes
 
Powertrain Codes DTC list
Powertrain Codes DTC listPowertrain Codes DTC list
Powertrain Codes DTC list
 
Honda/ Acura OBD2 Code List (PDF)
Honda/ Acura OBD2 Code List (PDF)Honda/ Acura OBD2 Code List (PDF)
Honda/ Acura OBD2 Code List (PDF)
 
OBD2 Powertrain Code List (P2700- P2799)
OBD2 Powertrain Code List (P2700- P2799)OBD2 Powertrain Code List (P2700- P2799)
OBD2 Powertrain Code List (P2700- P2799)
 
Variable speed fire pump controllers
Variable speed fire pump controllersVariable speed fire pump controllers
Variable speed fire pump controllers
 
Nissan OBD2 Codes
Nissan OBD2 CodesNissan OBD2 Codes
Nissan OBD2 Codes
 
GM OBD2 Code List (PDF)
GM OBD2 Code List (PDF)GM OBD2 Code List (PDF)
GM OBD2 Code List (PDF)
 
OBD2 Powertrain Code List (P2100- P2199)
OBD2 Powertrain Code List (P2100- P2199)OBD2 Powertrain Code List (P2100- P2199)
OBD2 Powertrain Code List (P2100- P2199)
 
Hyundai OBD2 Codes
Hyundai OBD2 CodesHyundai OBD2 Codes
Hyundai OBD2 Codes
 
OBD2 Powertrain Code List (P2600- P2699)
OBD2 Powertrain Code List (P2600- P2699)OBD2 Powertrain Code List (P2600- P2699)
OBD2 Powertrain Code List (P2600- P2699)
 
Land Rover OBD2 Codes
Land Rover OBD2 CodesLand Rover OBD2 Codes
Land Rover OBD2 Codes
 
Dodge/Chrysler/Jeep OBD2 Codes
Dodge/Chrysler/Jeep OBD2 CodesDodge/Chrysler/Jeep OBD2 Codes
Dodge/Chrysler/Jeep OBD2 Codes
 
Advanced motion controls b25a40
Advanced motion controls b25a40Advanced motion controls b25a40
Advanced motion controls b25a40
 

Viewers also liked

สมาช กกล _มเลยช_มแพ
สมาช กกล _มเลยช_มแพสมาช กกล _มเลยช_มแพ
สมาช กกล _มเลยช_มแพgilratika
 
Curriculum_vitae_Rahul_for_QC
Curriculum_vitae_Rahul_for_QCCurriculum_vitae_Rahul_for_QC
Curriculum_vitae_Rahul_for_QCrahul atpadkar
 
Earthsafe Pump Controllers for Mission Critical Fuel Systems
Earthsafe Pump Controllers for Mission Critical Fuel SystemsEarthsafe Pump Controllers for Mission Critical Fuel Systems
Earthsafe Pump Controllers for Mission Critical Fuel SystemsEarthsafe Systems, Inc.
 
Project_casia_alchemist
Project_casia_alchemistProject_casia_alchemist
Project_casia_alchemistmitesh gajjar
 
สมาช กกล _มเลยช_มแพ
สมาช กกล _มเลยช_มแพสมาช กกล _มเลยช_มแพ
สมาช กกล _มเลยช_มแพgilratika
 
สมาช กกล _มเลยช_มแพ
สมาช กกล _มเลยช_มแพสมาช กกล _มเลยช_มแพ
สมาช กกล _มเลยช_มแพgilratika
 
Math teachers guide_1 (1)
Math teachers guide_1 (1)Math teachers guide_1 (1)
Math teachers guide_1 (1)Brandanlee
 
Etude E-marketing : Email mobile - maelle urban
Etude E-marketing : Email mobile - maelle urbanEtude E-marketing : Email mobile - maelle urban
Etude E-marketing : Email mobile - maelle urbanmaelleurban
 
#Bornsocial Usages des médias sociaux par les moins de 13 ans
#Bornsocial Usages des médias sociaux par les moins de 13 ans#Bornsocial Usages des médias sociaux par les moins de 13 ans
#Bornsocial Usages des médias sociaux par les moins de 13 ansheaven
 
Présentation Métier / Responsable Webdesign
Présentation Métier / Responsable WebdesignPrésentation Métier / Responsable Webdesign
Présentation Métier / Responsable Webdesigntakaclike
 
Votre presence mobile : du centre de cout au profit
Votre presence mobile : du centre de cout au profitVotre presence mobile : du centre de cout au profit
Votre presence mobile : du centre de cout au profitacti
 

Viewers also liked (20)

สมาช กกล _มเลยช_มแพ
สมาช กกล _มเลยช_มแพสมาช กกล _มเลยช_มแพ
สมาช กกล _มเลยช_มแพ
 
Curriculum_vitae_Rahul_for_QC
Curriculum_vitae_Rahul_for_QCCurriculum_vitae_Rahul_for_QC
Curriculum_vitae_Rahul_for_QC
 
Earthsafe Critical Fuel Systems 01
Earthsafe Critical Fuel Systems 01Earthsafe Critical Fuel Systems 01
Earthsafe Critical Fuel Systems 01
 
Sale download123.vn
Sale download123.vnSale download123.vn
Sale download123.vn
 
Technician Training: Safety basics
Technician Training: Safety basicsTechnician Training: Safety basics
Technician Training: Safety basics
 
Chapter1
Chapter1Chapter1
Chapter1
 
Earthsafe Pump Controllers for Mission Critical Fuel Systems
Earthsafe Pump Controllers for Mission Critical Fuel SystemsEarthsafe Pump Controllers for Mission Critical Fuel Systems
Earthsafe Pump Controllers for Mission Critical Fuel Systems
 
Project_casia_alchemist
Project_casia_alchemistProject_casia_alchemist
Project_casia_alchemist
 
1
11
1
 
สมาช กกล _มเลยช_มแพ
สมาช กกล _มเลยช_มแพสมาช กกล _มเลยช_มแพ
สมาช กกล _มเลยช_มแพ
 
สมาช กกล _มเลยช_มแพ
สมาช กกล _มเลยช_มแพสมาช กกล _มเลยช_มแพ
สมาช กกล _มเลยช_มแพ
 
Technician Training: Wiring Basics
Technician Training: Wiring BasicsTechnician Training: Wiring Basics
Technician Training: Wiring Basics
 
Math teachers guide_1 (1)
Math teachers guide_1 (1)Math teachers guide_1 (1)
Math teachers guide_1 (1)
 
Royal resort
Royal resortRoyal resort
Royal resort
 
Etude E-marketing : Email mobile - maelle urban
Etude E-marketing : Email mobile - maelle urbanEtude E-marketing : Email mobile - maelle urban
Etude E-marketing : Email mobile - maelle urban
 
Guide bonnes pratiques energies renouvelables
Guide bonnes pratiques energies renouvelablesGuide bonnes pratiques energies renouvelables
Guide bonnes pratiques energies renouvelables
 
#Bornsocial Usages des médias sociaux par les moins de 13 ans
#Bornsocial Usages des médias sociaux par les moins de 13 ans#Bornsocial Usages des médias sociaux par les moins de 13 ans
#Bornsocial Usages des médias sociaux par les moins de 13 ans
 
Présentation Métier / Responsable Webdesign
Présentation Métier / Responsable WebdesignPrésentation Métier / Responsable Webdesign
Présentation Métier / Responsable Webdesign
 
Agccpfpaca
AgccpfpacaAgccpfpaca
Agccpfpaca
 
Votre presence mobile : du centre de cout au profit
Votre presence mobile : du centre de cout au profitVotre presence mobile : du centre de cout au profit
Votre presence mobile : du centre de cout au profit
 

Similar to Technician Training: Startup Basics

Power transformer testing and commissioning guidelines r
Power transformer testing and commissioning guidelines rPower transformer testing and commissioning guidelines r
Power transformer testing and commissioning guidelines rAshish Patel
 
PLC INPUT&OUTPUT DEVICES.pptx
PLC INPUT&OUTPUT DEVICES.pptxPLC INPUT&OUTPUT DEVICES.pptx
PLC INPUT&OUTPUT DEVICES.pptxJannaRicaBeason
 
How to trouble shoot frac pump transmission problems
How to trouble shoot frac pump transmission problemsHow to trouble shoot frac pump transmission problems
How to trouble shoot frac pump transmission problemsDavid Aakre
 
Submersible Pumps Trouble Shooting
Submersible Pumps Trouble ShootingSubmersible Pumps Trouble Shooting
Submersible Pumps Trouble Shootingcontrolspecialties1
 
Lecture control 1.pptx
Lecture control 1.pptxLecture control 1.pptx
Lecture control 1.pptxAsmaCh17
 
Water Temperature
Water TemperatureWater Temperature
Water TemperatureTheju Paul
 
Motor testing procedure by javid iqbal sodagar
Motor testing procedure by javid iqbal sodagarMotor testing procedure by javid iqbal sodagar
Motor testing procedure by javid iqbal sodagarjavid iqbal sodagar
 
SubstationCommissioning.pdf
SubstationCommissioning.pdfSubstationCommissioning.pdf
SubstationCommissioning.pdfAnithaSyam
 
Angel Vacaro Jr. RESUME (Autosaved)
Angel Vacaro Jr. RESUME (Autosaved)Angel Vacaro Jr. RESUME (Autosaved)
Angel Vacaro Jr. RESUME (Autosaved)Angel Jr. Vacaro
 
Maintenance schedule of Substation.
Maintenance schedule of Substation.Maintenance schedule of Substation.
Maintenance schedule of Substation.Sheikh Nazmul Islam
 
Vacuum loader user manual
Vacuum loader user manualVacuum loader user manual
Vacuum loader user manualssuser660147
 
How to identify and solve the problem that piezoelectric products unable to a...
How to identify and solve the problem that piezoelectric products unable to a...How to identify and solve the problem that piezoelectric products unable to a...
How to identify and solve the problem that piezoelectric products unable to a...wangwang49
 
Instrumentation positioner presentation
Instrumentation positioner presentationInstrumentation positioner presentation
Instrumentation positioner presentationSANGRAM PATNAIK
 
Chapter 5 mukesh gurjar
Chapter 5 mukesh gurjarChapter 5 mukesh gurjar
Chapter 5 mukesh gurjarMukesh gurjar
 

Similar to Technician Training: Startup Basics (20)

Power transformer testing and commissioning guidelines r
Power transformer testing and commissioning guidelines rPower transformer testing and commissioning guidelines r
Power transformer testing and commissioning guidelines r
 
PLC INPUT&OUTPUT DEVICES.pptx
PLC INPUT&OUTPUT DEVICES.pptxPLC INPUT&OUTPUT DEVICES.pptx
PLC INPUT&OUTPUT DEVICES.pptx
 
How to trouble shoot frac pump transmission problems
How to trouble shoot frac pump transmission problemsHow to trouble shoot frac pump transmission problems
How to trouble shoot frac pump transmission problems
 
Submersible Pumps Trouble Shooting
Submersible Pumps Trouble ShootingSubmersible Pumps Trouble Shooting
Submersible Pumps Trouble Shooting
 
egr automotriz
egr automotrizegr automotriz
egr automotriz
 
PLC Troubleshooting & Maintenance
PLC Troubleshooting & MaintenancePLC Troubleshooting & Maintenance
PLC Troubleshooting & Maintenance
 
ABC of BMS.pdf
ABC of BMS.pdfABC of BMS.pdf
ABC of BMS.pdf
 
Lecture control 1.pptx
Lecture control 1.pptxLecture control 1.pptx
Lecture control 1.pptx
 
On off controller
On off controllerOn off controller
On off controller
 
Diesel Fire Pump Controllers
Diesel Fire Pump ControllersDiesel Fire Pump Controllers
Diesel Fire Pump Controllers
 
Water Temperature
Water TemperatureWater Temperature
Water Temperature
 
Motor testing procedure by javid iqbal sodagar
Motor testing procedure by javid iqbal sodagarMotor testing procedure by javid iqbal sodagar
Motor testing procedure by javid iqbal sodagar
 
SubstationCommissioning.pdf
SubstationCommissioning.pdfSubstationCommissioning.pdf
SubstationCommissioning.pdf
 
Angel Vacaro Jr. RESUME (Autosaved)
Angel Vacaro Jr. RESUME (Autosaved)Angel Vacaro Jr. RESUME (Autosaved)
Angel Vacaro Jr. RESUME (Autosaved)
 
Maintenance schedule of Substation.
Maintenance schedule of Substation.Maintenance schedule of Substation.
Maintenance schedule of Substation.
 
Vacuum loader user manual
Vacuum loader user manualVacuum loader user manual
Vacuum loader user manual
 
How to identify and solve the problem that piezoelectric products unable to a...
How to identify and solve the problem that piezoelectric products unable to a...How to identify and solve the problem that piezoelectric products unable to a...
How to identify and solve the problem that piezoelectric products unable to a...
 
Instrumentation positioner presentation
Instrumentation positioner presentationInstrumentation positioner presentation
Instrumentation positioner presentation
 
Chapter 5 mukesh gurjar
Chapter 5 mukesh gurjarChapter 5 mukesh gurjar
Chapter 5 mukesh gurjar
 
Pcb automatic vaccum loader user guidance | SunzonTech
Pcb automatic vaccum loader user guidance | SunzonTechPcb automatic vaccum loader user guidance | SunzonTech
Pcb automatic vaccum loader user guidance | SunzonTech
 

Recently uploaded

Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxsaniyaimamuddin
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxappkodes
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 

Recently uploaded (20)

Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptx
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 

Technician Training: Startup Basics

  • 2. Startup Basics o Pre-Power – Instructions & Checklist o Power Checks o Pumps & Rotation Checks o Actuated Valves o Sensors & Instrumentation o Control Panel PLC Input-Output o Alarm Log Accuracy o Data Communications
  • 3. o Before activating power to the control panel network, it is important to have a complete pre-check  Energizing the panels with wiring incomplete or incorrect can be a safety issue and can damage equipment o Fuel System controls are a network of panels and devices with multiple interconnecting wires  It is important that all of the elements of the network be complete and correct prior to energizing any panel within the network  Check every device & every panel for correct wire terminations  Check for any loose wires in terminal blocks  Check for damage wire insulation  Check for frayed wires at terminations  Check for open panels or junction boxes  Check that all wire is stranded copper conductors Pre-Power
  • 4. o Power wiring is usually performed under a separate contract  After a complete pre-power check - Observer power connections & work with the electrical contractor to activate and verify circuits o When the power circuit is activated – Check at the control panel for the correct voltage and phases where applicable o With the proper checks, the control panels can be energized by the internal circuit breakers, fuses, or disconnects  The PLCs should power up and display a green power-on indicator Power Check
  • 5. o Single Phase & Three Phase pumps can rotate in either direction  Rotation can be checked by observing the fan on the motor, while the pump motor starter is momentarily bumped  DO NOT run the dry pump for more than a few seconds  Submersible pumps usually only operate in one direction and a check is not required o Pumps should be marked with the direction of rotation, or refer to the sketch for the common Viking Pump orientation  Moving fluid along the long arc of the pump cavity Pumps & Rotation Check
  • 6. o The method to change directions is noted on the motor  Single Phase – Usually interchange wires 5 & 8  Three Phase – Interchange any two power leads o When fluid is available to operate the pumps under load, the amp load on the pump power wire should be checked to assure that it is in normal range  The overload trip setting should be checked to match the full load amp (FLA) noted on the motor nameplate Pumps & Rotation Check (cont.)
  • 7. o When the control panel is energized, all actuated valves should move to the closed position, unless specifically programmed otherwise  Confirm the closed valve position for all actuators by the actuator indication dial  Check the valve stem to confirm that the valve itself is in fact closed & that the closed position is indicated on the control panel screen o Use the control panel to move the actuated valves – one by one – to the open position  Confirm that the correct valve moves to the open position & that the control panel screen indicates open o Common errors in wiring actuators  Open/Closed command signals are switched, Open/Closed limit switch signals are switched, wiring not secured Actuated Valves
  • 8. o When the control panel is energized – All sensors should be in their normal position  Control Panel screen should be checked to confirm sensor position o Where possible the sensor state should be changed by manipulating the sensor, and confirm that the control panel indication changes to the proper condition o Common Errors  Loose wire connections at the sensor or the panel termination Sensors & Instrumentation
  • 9. o Control panel schematic – relates the sensor or valve wire termination # to an input or output # on the PLC o PLC has indicators for inputs/outputs for the on/off state  Review wiring schematic and manipulate the sensor to generate a PLC input  Confirm that the correct PLC input is generated o If problems are identified with valves and sensor indications on the PLC screen, check that associated input or output on the PLC to see if it is in fact activated Check Control Panel PLC Input/Output
  • 10. o If the PLC input is not activated, check that the sensor wire is landed on the correct terminal block & the wire termination is good  Then check that the power wire going out to the sensor is terminated correctly in the panel  Recheck the wiring terminations at the sensor and confirm that there is power on the sensor COM wire  For an on/off sensor, disconnect the sensor and use a continuity test with a Fluke to confirm that the sensor is good and changes state properly Check Control Panel PLC Input/Output (cont.)
  • 11. o Alarm Log – Records date, time, and location of the alarms for the operator o As the sensors are tested, confirm that the alarm log is generated accurately o If the log is not accurate and the PLC input check correctly, then it is likely a programming issue Check Alarm Log Accuracy
  • 12. o The master control panel likely has a BMS interface  When the fuel system startup is complete the integration of the system should be checked o BMS interface is dry contacts only  Conditions such as a leak/general alarm should be generated and confirmed to be received by the BMS system o Typically the BMS has a data connection with the fuel system and up to hundreds of points of monitoring  The first step is to make sure that the BMS is communicating properly  Can it see the fuel system panel on its network and can it read some obvious values like Pump Manual Mode/Tank Volume o Once communications to the BMS valid – Check individual points  Operate the fuel system or manipulate sensors to generate the required points  If the inputs are correct at the PLC, then any BMS discrepancy is a pogromming issue, either within the PLC or at the BMS Check Data Communications